Professional Documents
Culture Documents
four jobs and only three pledges. The table below gives the expected time for each pledge to do each job.
Job 1 Alice 4 Job 2 9 8 4 Job 3 3 2 5 Job 4 8 6 7
Barbara 7 Jennifer 3
If she wishes to minimize the time taken, to whom should she assign which job?
Compare the effect of the scheduling methods (A) FCFS (first come, first served), (B) EDD (earliest due date), and (C) SPT (shortest processing time).
Develop the appropriate sequencing for these jobs using the Critical Ratio criteria.
Job 1 Alice 4
Job 2 9 8 4 0
Job 3 3 2 5 0
Job 4 8 6 7 0
Note: The dummy must be added because we have four jobs and only three people. Solve this table for the set of assignments giving the minimum total job time. Your final table should look like:
Job 1 Alice 0
Job 2 4 4 0 0
Job 3 0 0 3 2
Job 4 3 2 3 0
The set of optimal assignments would then be: Alice - Job 1 Barbara - Job 3 Jennifer - Job 2 Dummy - Job 4 Note that Job 4 does not get done since it is assigned to the Dummy. Problem 2: (A)
FCFS Sequence Process Flow Due Lateness Time Time Date 2 8 6 4 1 21 2 10 16 20 21 69 5 8 12 10 4 0 2 4 10 17 33
A B C D E TOTALS
Average completion time = 69 / 5 = 13.8 days Average number of jobs in the system = 69 / 21 = 3.28 jobs Average lateness = 33 / 5 = 6.6 days Utilization = 21 / 69 = 30.4%
(B)
EDD Sequence Process Flow Due Lateness Time Time Date 1 2 8 4 6 21 1 3 11 15 21 51 4 5 8 10 12 0 0 3 5 9 17
E A B D C TOTALS
Average completion time = 45 / 5 = 9 days Average number of jobs in the system = 45 / 21 = 2.14 jobs Average lateness = 14 / 5 = 2.8 days Utilization = 21 / 45 = 46.7% Problem 3:
Job Hours to Time Process Due 2 8 4 10 5 12 7 16 4 17 15 18 Computed Critical Ratio 7/2 = 3.5 16/8 = 2.0 4/4 = 1.0 17/10 = 1.7 15/5 = 3.0 18/12 = 1.5
Critical Critical Ratio Ratio Sequence #306 #998 #429 #281 #038 #407 1.0 1.5 1.7 2.0 3.0 3.5
Problem 4: