Professional Documents
Culture Documents
Thermal insulation refurbishment projects carried out at two major BP sites in past 15 years have cost ~ $450MM
25/02/2013 1
25/02/2013
25/02/2013
25/02/2013
25/02/2013
GPB - History
25/02/2013
25/02/2013
25/02/2013
GPB - Outcome
Failure Rate and Forecast
Actual failure rate increasing Forecast trend to continue
25/02/2013
For operating temperatures below ambient the differential vapour pressure across the insulation draws water towards steel substrate
Corrosion rate at sub zero temperatures low, but Severe corrosion can occur at locations where transition to ambient temperature or at protrusions through insulation
All thermally insulated surfaces operating between 5oC and 200oC and service life > 10 years should receive adequate corrosion protection before application of thermal insulation
25/02/2013 11
It is prudent to require corrosion protection on process equipment operating above the following threshold temperatures
Austenitic and low Mo-duplex stainless steels >25oC Duplex, super duplex and super austenitic stainless steels >80oC
25/02/2013 12
Rainwater
Fog
Concentrated Water
25/02/2013
13
25/02/2013
14
CUI has been reported under the entire range of commonly used thermal insulating materials
25/02/2013 15
Where rate of water ingress is slow, absorbent materials may draw a significant amount of water away from steel surface, but ! Prevailing weather conditions and general physical conditions of insulation are most significant factors
25/02/2013 16
25/02/2013
17
Non-metallic weather barriers have greater potential for limiting water ingress as more flexible and accommodating of complex geometries etc. but
If water ingress occurs there is less likelihood of draining away of evaporating off Success of application highly dependent on skills and experience of work force Insulation contractors are reluctant to use them
25/02/2013 18
Aluminised steel
Typically contains ~10% Si which is detrimental to corrosion performance
Rust breakthrough can occur within 1 year of exposure to aggressive environment unsightly but does not cause rapid perforation
Aluminium
Extremely good resistance to environmental corrosion
thicker gauge to galvanised or aluminised steel for improved mechanical properties
25/02/2013
19
Flexibility and ease of repair mean they are good for complex geometries etc Success dependent on skill of applicator; but exhibit poor impact resistance and are susceptible to environmental degradation
Elastomeric sheet
Typically 1mm sheet cut to size and sealed with both adhesive and sealant Not such a big departure from metal sheeting more acceptable to contractors Optimum performance dependent on skill of applicator; sensitive to environmental degradation under extreme weather conditions
25/02/2013
20
It is comparatively easy to achieve a completely water tight system initially. However, if the barrier is breached and water gains access it is most like to collect and stay within the insulation no loss due evaporation or natural drainage.
25/02/2013 21
25/02/2013
22
Aluminium and stainless steel overlapping spiral wrap foils are alternatives to liquid applied coating systems for protecting stainless steels from pitting and/or SCC
25/02/2013
24
Slurry blasting, which uses small amounts of entrained water in abrasive stream, is capable of producing similar degree of surface cleanliness to dry blasting
Minor rust staining considered to have minimal effect when surface tolerant primers are applied as the first coat
25/02/2013
25
Maintenance painting:
The need to maximise plant availability means much of the insulation maintenance and CUI mitigation activities are carried out while the plant is operating Applying protective coating to live plant is fraught with difficulties due to the influence of substrate temperature, eg:
Substrate Temperature (oC) Lifespan (years)
12 6 3
26
Responsibilities for the integrity of the thermal insulation system need to be clearly assigned
A full risk assessment should drive the CUI inspection and maintenance schedule Routine inspections of insulated plant and equipment should be carried out to identify displaced, missing or damaged sections of the weather barrier, and potential points of water entry A strict quality control regime should be enforced during all insulation maintenance activities
25/02/2013 28
CUI Inspection
25/02/2013
29
Isolated strip and search visual inspection alone is uneconomic and carries a low probability of finding all CUI affected areas
However, practical experience would dictate that for high risk areas complete removal of insulation plus visual inspection is the most reliable method of determining the extent of the problem
30
25/02/2013
Screening .. provide evidence that corrosion is taking place, but unable to measure unequivocally
Long Range Ultrasonics; Local and Long Range Electromagnetics
25/02/2013
31
Advantages
Quick to set up and use No hazards to equipment operator Insulated plant and equipment inspected remotely
Disadvantages
Only detects deficiencies in insulation For optimum results need ~30oC gradient across insulation Need to exercise care where insulation subject to wet/dry cycles Vicinity of very hot bare objects or reflective metal cladding can obscure defects Interpretation of results requires a skilled and experienced operator
25/02/2013
32
Heat loss from a section of insulated pipe at the bottom of a vertical run due to wet insulation
25/02/2013
33
Use involves
Positioning a small probe close insulation for ~20 secs while the backscattered neutrons are counted
25/02/2013
25/02/2013
35
The current preference amongst plant operators is for Real-Time Radiography (RTR). This utilises a visual display unit to show a real time view of the silhouette of the outside surface of the pipe.
25/02/2013
36
Uses low energy radiation source Radiation signals converted into linear equivalent wall thickness Cannot distinguish between internal and external wall loss Handle wall thickness of between 1 and 1.5 C-arm lengths currently available are 8, 13 and 18
25/02/2013
37
Under favourable circumstances, including good weather, it may be possible to inspect 1000 m per day In current form best viewed as screening tool for focusing more detailed (visual) examination CHIME - Creeping Head-Wave Method
Similar in principle to Teletest uses surface-skimming waves which become out of phase if a defect is detected Claims to provide more detailed information but inspection distance ~ metres
25/02/2013 39
PULSED EDDY CURRENT Can measure pipe wall thickness through insulation of thickness ~ 200 mm max. Only applicable to carbon & low alloy steels Typical smallest defect detected is 50% of stand-off distance Thickness readings require calibration against measured defects If steel is not electro-magnetically homogeneous the tool will give spurious results A minimum clearance of 2 between measurement point and any adjacent detail eg. welds, supports Electrical distortions and mechanical vibrations affect the tools performance Performance is significantly reduced by galvanised or aluminised weather-proofing Individual readings take typically 2 to 5 secs but the method can not be regarded as scanning Measurements can be made at remote locations from stairways and ladders by mounting probe on a pole
25/02/2013 41
Tendency to provide a high frequency of false indications, but rarely fails to locate external corrosion Unable to quantify degree of severity of damage, with typically only C and D corresponding to actual CUI Should be limited to interrogating straight pipe max. length ~150m Min. pipe OD is 4.5, with max. ~60 Insulation removal is minimal compared to Long Range Ultrasonics resulting typically ~50% cost savings Typical tolerance for positioning of anomalies is 1.5m Unable to determine the specific orientation on pipe of an anomaly
25/02/2013 42
Probability of failure
Normally apply a scoring type assessment based on list of key factors
Consequence of failure
The impact upon safety of personnel Effect on the environment of a product leak Cost of lost production and/or repairs to damaged equipment
25/02/2013 43
CUI RBI
PROBABILITY
25/02/2013
44
CUI RBI
RISK RATING
25/02/2013
45
CUI - RBI
CUI Risk Pyramid
2 Yes
1
No
Yes
No
No
Gas Service
Yes
Insulation Removal
No
No
Yes
No
No
Hydrocarbon Service
Yes
Out
25/02/2013
No
Avoidance requires proactive management throughout the life of a plant, equipment, etc starting with informed design and installation practice
eg. Application of a sound coating system to the insulated steel substrate, where possible, can really pay dividends
Cost effective management throughout operational life requires a risk based assessment approach and clear line of responsibility
Rigorously applied and regularly reviewed
There is a growing range of inspection techniques, of increasing sophistication, available to support an RBI approach, but .
No single technique practically and/or economically holds all the answers
25/02/2013
47