ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
Processes
Sand Shell Plaster Ceramic Investment Lost foam Pressure Vacuum Die Centrifugal Squeeze Semi-solid Single crystal Directional solidification Slush Continuous
4
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
Breakdown of Castings
Ingots for bulk deformation processing 85% Cast to near net shape - 15%
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
Ingots
Iron or steel molds Water-cooled molds Continuous casting
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
Shapes
Permanent mold (cavity)
die casting hot chamber cold chamber
Expendable Molds
sand shell slurry investment
lost wax lost foam
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
Shapes
Centrifugal
pipes spinning
Capabilities
Dimensions
sand casting - as large as you like small - 1 mm or so
Tolerances
0.005 in to 0.1 in
Surface finish
die casting 8-16 micro-inches (1-3 mm)
Casting Steps
quick route from raw material to finished product
Melt metals Pour / force liquid into hollow cavity (mold) Cool / Solidify Remove Finish
Melting
Raw material (charge)
scrap, alloying materials
Heat
Furnace Atmosphere
Atmosphere Heating
Raw materials
Air (oxygen), vacuum, inert gas (argon) External - electric, gas, oil Internal - induction, mix fuel with charge
steel making in blast furnace -mix coke with iron
Furnace material
refractory ceramics
Furnaces
Blast furnace
Furnaces
Furnaces
Induction Furnace
Electric Furnace
Sand Casting
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
16
Sand Casting
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
17
Sand Casting
S
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
18
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
19
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011 1
20
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
2 21
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
22
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
23
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
24
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
25
Die Casting
n
Cold chamber
Hot chamber
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
26
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
27
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
28
Continuous Casting
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
29
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
30
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011 1
31
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
32
Investment Casting
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
33
Vacuum Casting
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
34
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
35
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
36
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
37
Centrifugal Casting
s
horizontal
vertical
38
Centrifugal Casting
Directional Solidification
Casting Characteristics
Table 5.6 Typical materials cast
All All
Weig ht (kg)
Process
Sand Shell Expendab le mold pattern
Minimum Maximum
0.05 0.05 No limi t 100+
Section thickness (mm ) Shape complexity Di mensional Minimum Maximum * accuracy* Porosity*
4 4 1-2 2-3 3 2 3 2 No limi t --
All Nonferrou s (Al, Mg, Plaster Zn, Cu) mold All (High melting pt.) Investment Permanen t mold All Nonferrou s (Al, Mg, Zn, Cu) Die Centrifuga l All
0.05
No limi t
5-20
No limi t
0.05
50+
1-2
1-2
--
0.005 0.5
100+ 300
1-3 2-3
3 2-3
1 3-4
1 1
1 2
75 50
<0.05 50 1-2 1-2 3-4 1 -5000+ 2-10 1-2 3-4 3 *Relative rating: 1 best, 5 worst. Note : These ratings are only gene ral; significant variations can occ ur, depend ing on the method s use d d.
0.5 2
12 100
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
42
Microstructure
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
43
Microstructure - Dendrites
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
45
Microstructure - Dendrites
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
46
Fluidity
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
47
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
48
Casting Defects
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
49
Shrinkage
TABLE 5.1 Volumetric solidification contraction (%) 6.6 6.3 3.8 2.53 4 4.9 Volumetric solidification contraction (%) 4.5 4 Expansion to 2.5 4.2 45.5 6.5
Metal or alloy Aluminum Al4.5%Cu Al12%Si Carbon steel 1% carbon steel Copper Source: After R. A. Flinn.
Metal or alloy 70%Cu30%Zn 90%Cu10%Al Gray iron Magnesium White iron Zinc
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
50
Differential Cooling
Transition between thicker and thinner sections can lead to porosity
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
5 51
Pipe Defect
Due to shrinkage giving rise to a funnel-like cavity Solutions
insulate top (glass wool) heat top (exothermic mixture thermit)
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
52
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
53
Chills
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
54
Car Rims
Stamped
Cast
55
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
56
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
58
Casting costs
TABLE 5.10 Cost* Process Die Equipment L M-H M L-M M H H Labor LM LM MH H LM LM LM Production rate (Pc/hr) <20 <50 <10 <1000 <60 <200 <50
Sand L Shell-mold LM Plaster LM Investment MH Permanent mold M Die H Centrifugal M * L, low; M, medium; H, high.
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
59
Process economics
ME 4210: Manufacturing Processes and Equipment Prof. J.S. Colton GIT 2011
61