Professional Documents
Culture Documents
\
|
=
= = =
-
-
AFR
AFR
EA
Fuel mole
N moles O moles
AFR
MW
MW
AFR AFR
hr kg
hr kg
m
m
AFR
Measured
Air
Fuel
Measured
Measured
fuel
air
Measured
The material balance
( ) ( )
2 2 2 2 2 2 23 12
76 . 3 75 . 17 76 . 1 dO cN O bH aCO N O H C + + + + +
C: 12 =a(1) a =12
H: 23 =b(2) b =11.5
O: 1.76 x 17.75 x 2 =a(2) +b(1) +d(2)
62.5 =2a +b +2d
62.5 =24 +11.5 +2d
27 =2d d =13.5
N: 1.76 x 17.75 x 3.76 x 2 =c(2)
235 =2c c =117.5
( )
2 2 2 2 2 2 23 12
5 . 13 5 . 117 5 . 11 12 76 . 3 2 . 31 O N O H CO N O H C + + + + +
The percentage of the emissions on a molar basis of O2 and CO2 and compare to the
results in Table 7 on a dry basis.
Calculated Percentage of CO
2
=8.4%
Calculated Percentage of O
2
=9.4%
59
Both the CO
2
and O2 emissions are consistent with the measured data in Table 7.
The heat release from the engine has been calculated.
( ) ( ) ( ) ( )
( ) ( ) ( )
(
A + + A + + A + =
(
A + + A + + A + + A + =
+ =
- - -
- - - -
-
-
-
-
2
2
2
2
2
2
2
2
2
2
2
2
O
o
f O
N
o
f N
f
o
f f R
O
o
f O
N
o
f N
O H
o
f O H
CO
o
f CO P
R P
f f
h h n h h n h h n h
h h n h h n h h n h h n h
h h
n
W
n
Q
The number of moles shown below and the necessary enthalpy values with the units of
kJ /kg-mol
( )
2 2 2 2 2 2 23 12
5 . 13 5 . 117 5 . 11 12 76 . 3 2 . 31 O N O H CO N O H C + + + + +
( ) ( ) ( ) ( )
( ) ( ) ( ) ( )
( ) ( ) ( ) ( ) | |
| |
| |
( ) ( ) ( ) ( ) ( ) ( ) | |
| | mol kg kJ h
h
mol kg kJ h
h
h
h
R
O N f
R
P
P
O N O H CO
P
O N
O H CO
P
=
+ + + + + =
=
+ + =
+ + + =
(
+ + +
+ + + +
=
/ 000 , 014 , 7
0 0 2 . 31 0 0 5 . 117 0 000 , 014 , 7 1
/ 5 . 000 , 145 , 5
768 , 204 880 , 693 , 1 5 . 888 , 582 , 2 760 , 460 , 4
168 , 15 5 . 13 416 , 14 5 . 117 599 , 224 5 . 11 730 , 371 12
682 , 8 850 , 23 0 5 . 13 669 , 8 085 , 23 0 5 . 117
904 , 9 125 , 27 820 , 241 5 . 11 364 , 9 154 , 31 520 , 393 12
2 2
2 2 2 2
2 2
2 2
60
(
=
(
=
(
= =
-
-
sec
10 065 . 1 0383 . 0
167
4 . 6
5
mol kg
hr
mol kg
mol kg
kg
hr
kg
MW
m
n
f
f
f
(
= = =
-
-
sec
4 . 28
88 . 0
25 kJ kWe W
W
Generator
Electric
q
( )
( )
( )
kWt
kJ
Q
kJ kJ
Q
mol kg
kJ mol kg kJ
Q
mol kg
kJ mol kg kJ
Q
h h n W Q
h h
n
W
n
Q
R P f
R P
f f
3 . 48
sec
3 . 48
sec
9 . 19
sec
4 . 28
5 . 999 , 868 , 1
sec
10 065 . 1
sec
4 . 28
000 , 014 , 7 5 . 000 , 145 , 5
sec
10 065 . 1
sec
4 . 28
5
5
=
(
=
(
+
(
=
(
+
(
=
(
+
(
+
(
=
+ =
+ =
-
-
-
- - -
-
-
-
-
The amount of heat captured by the heat recovery system is approximately 36 kWt from
Tables 2, 3, and 4, which leaves about 12 kWt for radiant and convective losses to the
space from the engine and losses in the pipes and heat exchangers, which is realistic.
3.1.3.4 Heat Recovery Analysis
The steam generator and the coolant heat exchanger have been analyzed using
temperature heat transfer or T-Q diagrams. T-Q diagrams are an effective way of
describing the operation of heat exchangers by showing the stream temperatures versus
61
heat transfer between them. The required area for heat transfer between the streams, A,
can be calculated from the following function:
}
A
=
T U
dq
A ,
where
U =heat transfer coefficient,
dq =heat transfer,
AT =temperature difference between the two streams
Heat Transfer (kWt)
T
e
m
p
e
r
a
t
u
r
e
(
o
F
)
0 10 15 5
0
300
400
500
600
Steam Generate T-Q Diagram
200
100
Exhaust at 25 kWe
Domestic Hot
Water
Saturated Steam
(87psig)
700
800
900
1000
Condensate
Exhaust at 6 kWe
20 25
Figure 17: Summer Operation of the Steam Generator T-Q Diagram
Figure 17 shows the T-Q diagram for the steam generator during summer operation with
exhaust entering on the left at a high temperature. The heat in the exhaust is transferred to
the water inside the steam generator, which evaporates at a rate of 65 lbs/hr (28 kg/hr) at
62
87 psig (6 bar) or 18 kWt. This steam generator uses a pool of water, which is directly
replenished rather than preheating make up condensate, however condensate entering at
212
o
F (100
o
C) could be preheated. As shown on the right side of the T-Q diagram,
additional energy is available from the exhaust which leaves the steam generator at
approximately 360
o
F (160
o
C). Domestic Hot water is typically delivered at 140
o
F (60
o
C),
and is supplied from city water at 50
o
F (10
o
C). Recovering additional heat from the
exhaust (8 kWt) to heat domestic hot water represents approximately a 40% increase in
the heat recovery potential, and would increase the CHP efficiency from 78% to 87%.
However, the downside of reducing the exhaust temperature down to below 100
o
C is that
the moisture in the exhaust will condense, which can form rust in the exhaust pipes.
Therefore, it is necessary to build these sections out of stainless steel.
Additionally, Figure 17 shows the operation of the steam generator when the engine
generator is operating at 6 kWe. The effect of operating at lower loads is that the exhaust
temperature and flow rate are lower, thus reducing steam production.
Figure 18 shows the T-Q diagram for the coolant heat exchanger during both summer and
winter operation. Using engine coolant heat to heat the water used for space heating in
the winter is somewhat problematic as the required temperatures are relatively low,
which forces the temperature of the engine coolant to the relatively low temperature of
185
o
F, where as an ideal temperature would be about 195
o
F as shown in Figure 18.
During winter operation the water side of the exchanger typical has a flow rate of four
gallons per minute with an inlet temperature of 95
o
F and an outlet temperature of 110
o
F.
63
During the summer, a higher temperature is desired for the regeneration of a solid
desiccant, and therefore a higher over all temperature is maintained.
Heat Transfer (kWt)
T
e
m
p
e
r
a
t
u
r
e
(
o
F
)
0 20 10 15 5
90
150
170
190
210
Coolant Heat Exchanger T-Q Diagram at 25kWe
130
110
Summer Operation
Winter Operation
Coolant (12 GPM)
Water (12 GPM)
Coolant (2 GPM)
Water (4 GPM)
Figure 18: T-Q Diagram for Coolant Heat Exchanger at 25 kWe
To remedy the relatively low coolant operating temperatures during the winter, two
options exist. First, the water flow rate could be further reduced with an improved control
system, which would shift the winter operation water line up to a higher temperature. The
second, option is to bypass some of the water around the coolant heat exchanger
essentially reducing the flow. The two flows would then be mixed and the desired
temperature achieved.
3.1.4 Systems Integration Potential
The CHP system is made up of dozens of components, which include four primary
control systems:
64
- engine generator
- automatic transfer switch / soft load controller
- coolant heat recovery
- steam generator
As this system was assembled from disparate components resolving communications
compatibility issues cost a lot of time and money. Integrating these controllers would
reduce installation time and cost. Furthermore, it would simplify the operation of the
CHP system as each controller has its own user interface.
The heat recovery system captures reject heat from the engine and converts it to steam
and hot water via to heat exchangers. The steam could be used in a double effect
absorption chiller to provide cooling during the summer to a building. The steam
generator in this CHP system provides saturated steam at 87 psig (6 bar) and 360
o
F
(160
o
C), therefore the exhaust temperature is approximately 370
o
F (165
o
C). The
remaining exhaust heat could be used to make domestic hot water at 140
o
F (60
o
C) or
drive a single effect absorption chiller.
The coolant energy could be used to drive the desiccant regeneration process of the
ventilation system, which is necessary to provide dehumidified air to the IW.
Alternatively, the coolant energy could be used to drive a single effect absorption chiller
to provide additional cooling.
65
3.2 Steam Driven Double Effect Absorption Chiller
Drs. Hongxi Yin and Ming Qu have both completed dissertations on the steam driven
double effect absorption chiller and the solar thermal high pressure hot water driven
double effect absorption chiller respectively. Each dissertation includes extensive
descriptions of both their components and operation. These chillers were selected as
models for this dissertation as they have both been previously tested and analyzed, both
are on site to allow visual inspection, and both are very compact designs as compared to
other manufacturers models. The chillers are nearly identical except for the high
temperature generator as one is designed for steam and the other is designed for high
pressure hot water. Furthermore, the high pressure hot water unit includes an auxiliary
natural gas burner.
3.2.1 System Components
Figure 19 shows a complete cross section of the absorption chiller including the inputs
and outputs of the system. The auxiliary equipment originally installed with this system
will not be included as it was replaced by the CHP system.
66
Figure 19: Steam Driven Absorption Chiller Flow Diagram [31]
This packaged system includes; the absorption chiller, cooling tower, control system,
pumps, valves, and sensors. The same concept of creating a packaged system out of the
chiller components is applied in packaging the biodiesel CHP system, absorption chiller,
and ventilation unit.
3.2.2 Input / Output
The Inputs for this system include:
- High pressure steam
- Chilled water return
- Electricity to operate pumps, fan, control system, etc.
- Treated water (for the cooling tower)
The outputs for this system include:
- Chilled water supply
67
- Water vapor (from cooling tower)
- Condensate
- Data 1 (Internal control system with separate display)
- Data 2 (4-20mA and 0-5 V converted to BACNET and available on the web)
Finally, extensive information exists on the instrumentation used to operate and monitor
the absorption chiller as shown in Figure 20. This information will be helpful in
determining which points are necessary for operation.
Figure 20: Absorption Chiller Process and I nstrumentation Diagram [31]
Figure 21 shows one of the user interface screens for the absorption chiller system.
T3
Timingwater Empty
SteamSupply
CWV
B1 T1
CHWR
Citywater
RP
CHWP
B2
Cable
T6
L2
SP
T12
T9 T2
CHWS
C
o
n
tr
o
lle
r
T10
Condensate
T8
T13
T11
M
E
-
L
G
R
2
5
T7 P1
T14
SV
L3
CWP
L4
Air
L5
T5
T18 T17
T15
T16
L1
F6
Hot HumidAir
F2
F1
T19
T21
T20
T22 P4
P5 T23
F8
P2
P3
T
T28P10
P11 T29
T30
H0
T0
Campus
Building
CHWS
CHWR
CHWR
CHWS
Cable
T25 P7
F6
F7
Citywater
1
HWR
HWS
2
3
4
5
6
7
8 9
10
RPH
RBPV
CWBPV
CTV
DD
DV
ALC control panel
Chiller control panel
Chiller
Chiller
ALC inputs
ALC
ESB
CTW
CR
H
W
R
H
W
S
Absorption
SS
BFT
TLHX
WS
BFP
Chiller
68
Figure 21: Automated Logic Absorption Chiller User I nterface
The chiller is a very compact unit with a width of 1,143 mm (45 inches) a depth of 660
mm (26 inches) and a height of 1,829 mm (76 inches). The unit does include onboard
controls; however a separate panel is required for running auxiliary equipment. Much of
this auxiliary equipment is not necessary when the unit operates in a CHP mode, and was
only necessary during the stand alone testing phase of the project.
3.2.3 Operating Description and Results
As shown in Table 9, the test program used by Dr. Yin varies five operational parameters
and measures and calculates the effect on the chillers performance and capacity.
69
Table 9: Absorption Chiller Test Program and Results [31]
The data in Table 9 provides the necessary information for creating an empirical
operating model of the chiller, which can be integrated with the output of the steam
generator from the CHP system.
Figure 22 provides insight into the operation of the absorption chiller and shows how
each component within the packaged absorption chiller operates versus cooling load.
Figure 22: Absorption Chiller Component Heat Transfers vs. Cooling Load [31]
0
4
8
12
16
20
24
28
32
0 2 4 6 8 10 12 14 16 18 20
Actual cooling load (kW)
H
e
a
t
t
r
a
n
s
f
e
r
o
n
c
h
i
l
l
e
r
c
o
m
p
o
n
e
n
t
(
k
W
)
.
Cooling tower Absorber Evaporator HTRG
LTRG Condenser HTHX LTHX
HRHX BPHX
Cooling tower
Absorber
Evaporator
HTRG
LTRG
Condenser
HTHX
LTHX
HRHX
BPHX
70
The evaporator is where the cooling takes place and the primary heat input is into the
high temperature regenerator (HTRG). The cooling tower shows how much heat is
rejected to atmosphere and how much can be captured. These pieces of data further refine
the simulation model and provide insight into what quantity of energy is required to
operate the chiller, and how much energy is produced and rejected.
3.2.4 Systems Integration Potential
Opportunities for improving the chiller system include integration of controls and
recovering cooling tower heat. The control system requires several operational inputs that
are also required for the heat recovery system which could be shared. Furthermore, a
common control system would simplify writing control algorithms for automatic startup,
operation and shutdown.
As can be seen in Figure 22 about 28 kWt of low quality thermal energy is available at
around 35
o
C (96
o
F) from the cooling tower, which would be sufficient for preheating
domestic hot water during the summer as city water typically arrives at 13
o
C (55
o
F).
Using a heat exchanger rather than a cooling tower would most likely save on first cost as
well as operating costs as removing heat using a pump versus a fan is more efficient [32].
Finally, removing the cooling tower would also save on operating costs for cooling tower
water and chemicals to treat the cooling tower water that is evaporated.
71
3.3 Ventilation System with Enthalpy Recovery and Solid
Desiccant Dehumidification
The ventilation system in the IW has operated for several years and employs both a
passive enthalpy recovery wheel and an active desiccant dehumidification wheel to
condition the air, as well as a heat pump for providing the required heating or cooling
loads of the ventilation air. In her dissertation work at CMU, Dr. Chaoqin Zhai operated
this piece of equipment and focused her work on the performance modeling of the
desiccant wheel and its operation.
3.3.1 System Components
The ventilation unit itself is an example of systems integration. The unit includes a fan
for air handling, two energy wheels (one active, one passive), and a heat pump for
primary heating and cooling. These subsystems are all operated by a single controller and
are packaged by one company. The acceptance of these systems would be greatly reduced
if building operators had to assemble them on site. Instead, the unit arrives on a single
skid and only requires power, gas, and duct connections to operate.
Figure 23: Plan View of Ventilation Unit [33]
72
The ventilation unit is also very compact. All of the components are placed inside with an
overall width of 1,753 mm (69 inches) a depth of 737 mm (29 inches) and a height of 991
mm (39 inches). The integrated and packaged enthalpy recovery wheel, desiccant wheel,
heat pump, and necessary controls needed to make this system work serve as an example
for a systematic integration of the three IWESS components.
3.3.2 Input / Output
The Inputs for this system include:
- electricity to operate fans, wheels and control system (208 V, 3 phase)
- outside air for ventilation, desiccant regeneration, and heat pump operation
- return air (from conditioned space)
- natural gas (for desiccant regeneration)
The outputs for this system include:
- dehumidified ventilation air
- exhaust (from desiccant regeneration)
- exhaust air (from the heat pump)
- exhaust air (from the space)
- data (4-20mA and 0-5 V converted to BACNET and available on the web)
While the same user interface capability exists for the ventilation system, there is no
graphical interface like the CHP and chiller systems have in Figures 13 and 21.
73
3.3.3 Operating Description and Results
Figures 24 through 26 describe how the components of the ventilation system operate and
how they affect each other.
Figure 24: I nterior View of the Ventilation Unit [33]
Figure 24 shows the operation of the ventilation unit.
1. Outside air enters the unit (and mixes optional return air).
2. The outside air passes through the passive energy recovery wheel.
3. The air goes through a DX coil for cooling and moisture removal.
4. Part of the air passes through an active desiccant and is warmed and dehumidified
by the desiccant wheel.
5. The warmer, drier air is mixed with the cool bypassed air and sent to the space at
the set point humidity and temperature.
74
6. A separate outside air stream (regeneration air) is heated by a gas burner to
regenerate the desiccant in the desiccant wheel, and is then rejected to atmosphere.
The flow diagram shown in Figure 25 provides additional insight into how the ventilation
system operates.
Figure 25: Ventilation Unit Flow Diagram [33]
Figure 26: Psychrometric Chart for Ventilation System Operation [33]
Figures 27 through 29 were developed to show the cost and benefit of operating the
ventilation system.
75
Figure 27: Enthalpy Removal Breakdown by Component [33]
Figure 27 shows that the majority of the sensible heat removal is handled by the heat
pump and then followed by the enthalpy recovery module. Nearly zero enthalpy is
removed by the desiccant wheel, which makes sense as the moisture is removed by an
adiabatic process and the temperature increases as shown in Figure 26.
Figure 28 shows that the moisture removal by the active desiccant does account for 52%
of the total moisture removal. Some moisture is removed at the heat pump by the DX coil
due to condensation, and the remainder is transferred to the exhaust air as it picks up
moisture from the enthalpy recovery module.
Figure 28: Moisture Removal Breakdown by Component [33]
76
Finally, Figure 29 shows that the active desiccant module has the highest operating cost
mainly due to the high cost of natural gas. Therefore, if reject heat were used to
regenerate the desiccant rather than burning natural gas, the operating cost of ventilation
system would decrease by approximately half. This represents a major opportunity for
using reject heat from the CHP system.
Figure 29: Operating Cost Breakdown by Component [33]
The following has been quoted directly from Dr. Zhais thesis justifying the feasibility of
integrating the ventilation system with the CHP system.
A procedure has been outlined to develop operating strategies for the active
desiccant wheel integrated CHP system. The validated performance model has
been applied in predicting the supply air conditions from the integrated system
under different settings of the control variables. Performance maps that relate the
supply air conditions and different settings of the control variables have been
constructed for the proposed system in the IWESS project. These performance
maps show that the desired supply air condition can be achieved with certain
settings of the control variables, namely the regeneration air temperature, the
regeneration air flow rate, the leaving DX air condition, the wheel rotation speed,
and the bypass ratio. The settings of the control variables to achieve the desired
supply air condition are not unique. It is an optimization problem to determine the
control settings to achieve the lowest system operating energy consumption or
cost, in which the system operating energy consumption or cost is the objective
function, and different control factors are the variables. [33]
77
The detailed controls of this process are outside the scope of this dissertation; however,
the plumbing, sensor inputs and outputs, and heat transfer calculations will be conducted
to facilitate the integration.
3.3.4 Systems Integration Potential
The desiccant wheel requires a large thermal input, currently in the form of natural gas
combustion, to regenerate the desiccant wheel, which has become saturated from
incoming air. The operation of the desiccant wheel contributes about 62% of the total
operating cost of the ventilation system including the heat pump and the enthalpy
recovery wheel [19]. In lieu of burning natural gas, it has been proposed to use coolant
energy from the engine generator to regenerate the desiccant. This would reduce the
operating costs by about 62%, as the reject coolant heat from the engine would be free
minus the pumping power required to move the thermal energy from the coolant heat
exchanger to the air to water heat exchanger mounted in the ventilation unit.
The setup in the IW would not be ideal as there would be several hundred feet of piping
required to move the heat from the engine to ventilation unit. This would be another
reason for creating a compact packaged unit that would cut down on the overall piping
length.
The control systems could also be integrated to reduce cost and simplify operation. It so
happens that the manufacturer for the ventilation controls is the same as the manufacturer
for the supervisory controls and the ATS/SLC controls. A few sensors (two temperatures
78
and water flow) could be shared between the control system on the engine coolant side
and the regeneration heat exchanger to reduce some first cost as well.
Perhaps the largest first cost saving in creating an integrated CCHP/V package would be
the replacement of the heat pump by a heated and chilled water coil as is also suggested
by Dr. Zhai [33]. Detailed costs are not available at this time, but it is reasonable to
assume that the first cost of a heating and a cooling coil, a control valve and a pump are
much cheaper than an entire heat pump. Furthermore, there would also be operating cost
reductions, as running a pump for the heating and cooling coils would be cheaper than
operating the compressor in the heat pump.
79
4.0 Preliminary Design Guide
This section has two parts: a generic guide for the preliminary design of a cogeneration
system that provides power, cooling, heating, and ventilation to a building and a specific
example based on the biodiesel fueled CHP system designed, installed, operated and
evaluated at Carnegie Mellon University. The design process is iterative; however seven
steps in sequence are recommended. Throughout the design process engineers should be
aware of local code requirements as they affect decisions.
4.1 Generic Design Steps
The general procedure for designing a CHP system is to:
1. determine the electrical and thermal loads, load profiles and the required flow
rates and temperatures of cooling and heating streams.
2. determine which fuel types are locally available, how they are distributed, and
their cost.
3. determine what energy grids are available, what their operating conditions and
costs are, and if it is possible to interface with them.
4. select a prime mover that best fits the load profile and load proportions.
5. select auxiliary and heat recovery equipment to match the prime mover and the
fluids used to transfer energy.
6. choose an operating strategy (thermal or electrical load follow, base load
operation, etc.)
7. evaluate the options on a capital, operating, and environmental cost basis.
80
As these seven steps are carried out the following documents should be created:
1. flow diagram,
2. material and energy balances,
3. equipment descriptions,
4. operating descriptions,
5. process and instrumentation diagram,
6. preliminary layout, and
7. cost estimates for equipment
These documents provide the basis for equipment procurement, detailed design,
installation, and operation.
4.1.1 Loads
The first task is to identify the energy loads for the CHP system. These include, but are
not limited to: electrical (lighting, pumps, fans, computers, etc.), space cooling and
heating, ventilation, dehumidification, and process energy. Lawrence Berkley National
Labs (LBNL) publishes generic annual load values for U.S. buildings on a square foot
basis shown in Table 10 [6].
U.S. Commercial Office Building Energy I ntensity (kBTU/ft2-year)
Space
Heating
Water
Heating
Cooling Cooking Ventilation Lighting Refrigeration
Office
Equipment
Other
33.2 11.0 11.4* 1.4 6.1 18.9 0.3 11.1 7.8
*Electrical energy for operation of a vapor compression chiller.
Table 10: Typical U.S. Commercial Building Loads
81
Table 10 shows thermal and electrical loads assuming average furnace and chiller
efficiencies of 80% and COP =3.2 respectively. The cooking load is not specified as an
electrical or thermal load in the LBNL report. Ventilation energy is assumed to be for a
forced air system that delivers the heating, cooling, and fresh air. The information in
Table 10 gives annual energy demands; however, to properly size and evaluate a CHP
system, peak and base loads and annual hourly load profiles are required.
The full table with IWESS systems applied is shown in Appendix C, which shows the
steps necessary for transforming the average load data for electricity, heating, cooling,
and ventilation into a form for the IWESS systems. These values along with a
conditioned square footage of a building will provide annual total loads for many
building types.
Hourly load data can come from metered data or from building energy simulations.
Simulation data should be used carefully and it is reasonable to add a safety factor of 1.1
when sizing the system, however metered data is best. Over sizing systems will lead to
inefficiency, but reality dictates that metered data are not always readily available. When
analyzing hourly data it important to find the peak (maximum) and base (minimum)
electrical and thermal loads. Details about these loads such as voltage, temperatures, flow
rates, and pressures should be determined as appropriate.
4.1.2 Fuel Selection
There are many fuels available for the operation of CHP systems including: natural gas,
petroleum products (gasoline, Diesel, etc.), biomass (biogas, biodiesel, ethanol, solids),
82
coal, and waste fuels (waste coal, garbage, etc.). Many of these fuels are associated with a
particular type of prime mover. They vary in energy content, cost, availability, and
emissions. The CHP system designer must determine what options are available based on
this list of criteria and tabulate them to assist in the selection of a prime mover, and in the
estimation of the operating costs of the system.
4.1.3 Energy Grids
The availability of energy is an important consideration in the design of a CHP system
for a building. Energy grids can come in many forms; electrical, natural gas, chilled water,
steam, heated water, compressed air, etc. The most common energy grid is the electric
utility grid. The interface with the electric utility grid must be coordinated with the local
electric utility, which will have individual requirements governing the operation of CHP
systems, which will detail voltages, power quality requirements, and cost structures for
providing and accepting power. Larger systems may be required to generate a certain
amount of power.
Thermal grids (steam, chilled water, etc.) are operated by some large utilities or by
smaller private entities. Similar to the electric utility grid, CHP system designers must
contact the grid operators to determine if it is possible to interface with the grids. Typical
performance requirements for interfacing with thermal grids include; temperatures,
pressures, and flows. Furthermore, these temperatures, pressures, and flows may change
throughout the year as thermal demands change throughout the year.
83
The ultimate goal of interfacing with energy grids is to have a source and sink for all the
forms of energy generated by the CHP system and needed by the facility. Many types of
commercial buildings have varying loads throughout the year, whereas CHP systems
operate most efficiently at steady state. Energy grids provide level load profiles for
buildings so that the CHP system can operate independently of the local building loads.
Also, importantly the energy grid can act as a back up in case of a plant failure.
4.1.4 Prime Movers
The fourth step is to select a prime mover that will provide sufficient thermal and/or
electrical energy at the proper conditions. Table 11 lists the prime movers most
frequently considered for CHP systems in buildings along with some of their
performance characteristics. Based on the building load profiles and the fuel data one or
more prime movers will emerge as the best fit for a particular application. As previously
stated, the design process is iterative. Therefore, some prime mover options may be
eliminated in subsequent steps.
Prime Mover Fuels
Electrical
Efficiency
Recoverable Heat
CHP
Efficiency
Heat to
Power
Ratio
Boiler +Steam
Turbine
Nat. gas, coal, waste
fuels, biomass 10 - 15 %
45 - 65 % low quality
steam 65 - 80 % 4.3
Gas Turbine Natural gas, biogas 15 - 25 % 45 - 55 % 600
o
F exhaust 60 - 80 % 2.8
IC Engine
-Diesel Diesel, biodiesel 30 - 40 %
15 - 20 % 190
o
F coolant,
15 - 20 % 900
o
F exhaust 60 - 80 % 1.6
-Spark
Gasoline, E85,
natural gas 20 - 30 %
15 - 30 % 190
o
F coolant,
15 - 20 % 900
o
F exhaust 50 - 80 % 2.0
Fuel Cell
-SOFC Natural gas 35 - 45 % 25 - 35 % 500
o
F exhaust 60 - 80 % 0.8
-PEM Hydrogen 35 - 45 % 25 - 35 % 300
o
F exhaust 60 - 80 % 0.8
Table 11: Prime Mover Performance Summary
84
4.1.5 Auxiliary and Heat Recovery Equipment
The fifth step in the design process is to select auxiliary heat recovery equipment that
uses exhaust, coolant or steam to meet the desired loads. This equipment may include:
- heat exchangers
- absorption chillers (single and double effect)
- dehumidifiers
- thermal storage arrangements
Section 2.5 discusses the temperature and medium of these thermal outputs with respect
to engine type. There are several ways of transferring heat and there are several types of
heat exchangers that are tailored to particular mediums and applications. An important
tool in selecting and designing equipment for recovery and utilization of thermal energy,
heat, in CHP systems is the T-Q diagram as shown in Figures 16 and 17. T-Q diagrams
should be constructed for each exchange of thermal energy in the system. It may be
necessary to contact several manufacturers to determine the best match for the selected
prime mover and fuel. An effective method for determining if a heat exchanger will meet
the design requirements is using a T-Q diagram, and plotting the inlet and outlet
temperatures versus the heat transfer.
At this point, it is possible to start to develop a preliminary flow diagram so that the CHP
system designer can get an over view of the options thus far. There may be multiple flow
diagrams at this point as a single prime mover and fuel may not have been selected yet,
but there is sufficient information to get started. The preliminary flow diagrams allow the
85
designer to visualize what forms of energy are available and what the loads are. As
information becomes available and decisions are made in subsequent steps, the flow
diagram is revised. Furthermore, it is prudent to develop multiple designs in parallel
using different components and eliminating options as details become available.
4.1.6 Operating Strategy
The sixth step in designing a CHP system is determining an operating strategy. There are
many options available to engineers but they primarily include:
- steady state operation at either the peak or base, minimum, loads of the system
- thermal or electrical load following operation
Load following may be based on a thermal or electrical load and partially depends on the
available auxiliary equipment and grid types. Electrical load follow is a mandatory
operating method unless battery storage or a grid interconnection exists as more
electricity can not be generated than is consumed, stored or dissipated. Both battery
storage and grid interconnection may be expensive, yet they allow the CHP system to
operate much more efficiently allowing electricity to flow to and from the utility grid so
the CHP operator only has to focus on effectively recovering and utilizing heat.
Design operation typically takes on two forms: base loading and peak loading. Design
operation is defined as operating the prime mover at a constant load and importing or
exporting thermal and electrical energy as appropriate. Base loading has the prime mover
generating the minimum amount of thermal and/or electrical energy that will always be
used by the building. The caveat to this mode of operation is that back up sources of
86
heating, cooling, and electricity must be available to cover the load variability. These
backups can come from standard boilers and chillers and/or the utility grids (electrical
and thermal).
Peak design operation on the other hand has the prime mover operating at a setting that
will always generate sufficient electrical and thermal energy to meet any building load.
The downside to this mode of operation is that there will be instances when there are
excess amounts of thermal and electrical energy, which will have to be exported to an
energy grid or rejected. Rejecting energy decreases over all efficiency, but extra
equipment will not be required to meet peaks (boilers and chillers).
The decisions regarding operating strategies including startup and shut down will
establish the requirements for the sensor, actuator and control system components and
will provide the basis for the piping and instrumentation diagram.
4.1.7 CHP System Evaluation
Evaluation in this step has a dual meaning. First, if multiple CHP system options exist the
designer must weigh these options on an engineering, economic, and environmental basis.
The second meaning of evaluation is that the CHP system designer should determine a
way of evaluating the efficiency, economic, and environmental performance as required
by the conditions set by regulatory bodies, the system owner and the system operator.
Regulatory bodies may want information on the quantity of emissions generated. Owners
may be interested in how much money has been saved by operating the CHP system.
87
CHP system operators may need information to diagnose problem and determine if the
system is operating properly.
The result of this step is to determine the best CHP system configuration and operating
conditions to meet the demands of the building, which are economic.
4.2 Design of Biodiesel Fueled CHP System
A biodiesel fueled CHP system was designed, installed, operated and evaluated according
the design guide described above.
4.2.1 Load Profiles
The thermal and electrical load profiles from the Intelligent Workplace (IW) were
developed from a combination of metered and name plate data. A decision was made
early on that the CHP system would be designed to meet the peak loads of the IW to
demonstrate a facility that could be powered entirely by renewable fuels. Using data on
existing HVAC, lighting, and plug loads a peak electrical demand of approximately 20
kWe was determined.
Metered data for the double effect steam absorption chiller was available, which showed
the peak demand as 16 kWt in the form of saturated steam at 87 psig (6 bar) with a flow
rate of 65 lb/hr (29 kg/hr).
Furthermore, metered data for the heating system showed a peak heating demand of
approximately 40 kWt at 40
o
C (104
o
F), which can change rapidly as he IW does not have
88
a lot of thermal mass, therefore outdoor temperature changes are felt in the building
relatively quickly. The heating season typically lasts from early October to late March.
The heating system was fed by the steam grid which operated at about 7 psig (0.5 bar)
during the winter. Note, the main steam supply pressure is 150 psig (10 bar) during the
winter, but this is stepped down inside the buildings on campus as appropriate.
An additional load that was identified is regenerating the desiccant dehumidification
wheel in the ventilation system. Desiccant regeneration, like the chiller is also a seasonal
load, however it is steadier than the chiller load. The metered data of the ventilation
system showed a required temperature for regenerating the desiccant of approximately
195
o
F (95
o
C) with a peak demand of about 20 kWt.
4.2.2 Fuel Selection
Local fuels that were available included natural gas and biodiesel fuel. As this was a
demonstration facility, it was decided that using a renewable fuel was the most important
design consideration when selecting a fuel. Another group on the Carnegie Mellon
University campus had just commercialized a biodiesel refining process. This new
commercial entity agreed to donate the fuel for this system, which also made it the most
economic fuel choice by default.
Distribution of the biodiesel was not as simple as natural gas, which has a pipe line
infrastructure in Pittsburgh, PA. Provision for filling fuel storage tanks had to be made,
which were addressed during the detailed design and layout phase.
89
4.2.3 Energy Grids
Carnegie Mellons campus has many energy grids including; electric, steam, and chilled
water. These grids are connected to every building on campus; the steam and chilled
water are generated at a central plant.
The local utility, Duquesne Light, was contacted to determine what their requirements
were for installing a utility paralleled engine generator with a capacity of between 20 and
30 kWe. Due to the configuration of the Carnegie Mellon campus, electricity enters the
campus at two points. Therefore, it is unlikely that the 20 to 30 kWe system would be
noticed in a campus system that draws between two and five megawatts of electricity
from Duquesne Light. Based on this information, Duquesne Light set no requirements for
grid protection on this system. It was assumed that if there was a grid outage and the
generator was operating it would immediately be over loaded by the huge electrical
demand from the campus, which would cause the engine generator to shut down.
Additional protections were put in place as this is a demonstration facility, which will be
discussed further during auxiliary equipment.
The campus chilled water and steam grids are operated year round by Carnegie Mellons
facilities management service. The university agreed to allow the CHP system to
interface with the campus thermal grids to allow for importing and exporting of steam
and chilled water. The chilled water operates year round at approximately 45
o
F (7
o
C).
The steam grid also operates year round to prevent thermal expansion and contraction;
90
however the pressures vary from about 15 psig (1 bar) in the summer to 150 psig (10 bar)
during the winter. The fall and spring pressures are approximately 40 psig (3 bar).
Another smaller grid was available in the building: a hot water grid. This grid is not
campus wide, but was considered as a possible outlet for thermal energy. The building
hot water grid has an operating range of 26
o
C to 40
o
C (78
o
F to 105
o
F).
4.2.4 Prime Movers
Three options were available, microturbines, Diesel engines, and fuel cells. Fuel cells
were eliminated quickly as the cost was too high, approximately 100 times the cost of the
microturbine and Diesel engines per kWe. The smallest microturbine available at the time
was a 30 kWe unit, which corresponds to approximately 90 kWt at 530
o
F (270
o
C), much
too large for this system.
Diesel generator sets are available from many manufacturers that would provide about 20
kWt of high temperature exhaust. A 32 kWe Diesel engine generator was selected from
J ohn Deere. J ohn Deere was ultimately selected for two reasons, it was locally supported
and J ohn Deere showed interest in the work. Next, as this is a prime power setup, as
opposed to a backup power setup, the engine would not be operated at full power (32
kWe) for an extended period of time. An 80% power rating is reasonable for prime power
applications or 25 kWe. Assuming that Diesel engines are about 33% electrically
efficient, it was assumed that a Diesel engine operating at 25 kWe would produce
approximately 25 kWt exhaust and coolant heat each. Based on this reasoning, a Diesel
engine generator set was selected. Because of the high steam pressure and temperature
91
required by the two stage absorption chiller the amount of available exhaust energy was
closer to 18 kWt, and therefore diminished the operation of the heat recovery system.
Specification sheets from engine manufacturers typically dont include part load values
or exact values for CHP systems. Conservative estimates are recommended.
4.2.5 Auxiliary and Heat Recovery Equipment
Sizing the heat recovery is where the first major difficulty arose for this system
configuration, as there are no commercially available steam generators in the 10-30 kWt
size range. The smallest steam generator available for exhaust heat recovery was a 200
kWt unit from Vaporphase, Inc. The consequence of using a steam generator of this size
is that the heat up time is very long, approximately nine hours from cold start to steady
state, not including heating up the pipes. However, as a proof of concept, this was
deemed an acceptable configuration. A high pressure hot water system would be
recommended for a new system that would also include the purchase of an absorption
chiller.
Next, the remaining thermal energy stream from the engine coolant needs to be handled.
A plate and frame heat exchanger was selected to recover this energy and transfer it to
water that is utilized in the IWs heating system. The configuration of the IWs existing
heating system allowed for the dual use of the hot water pipes for space heating in the
winter and regenerating desiccant in the summer as the loads are not simultaneously
active. It should be noted that this is not a common system configuration. Many buildings
use what is called a four pipe heating system in which hot and cold water is available to
the heating and cooling system as many buildings have to heat and cool at the same time,
92
especially during the spring and fall. The passive design of the IW allows for the use of
what is incorrectly assumed to be an inferior two pipe system. The IW does not require
heating and cooling at the same time, and therefore an entire set of pipes can be
eliminated as shown in Figure 30 below.
Figure 30: I W Heating and Cooling System Flow Diagram\
The coolant energy has a use during the summer for regenerating the desiccant and in the
winter for space heating, however there are no reliable loads in the spring and fall.
Therefore, a remotely mounted radiator is used to dump excess coolant energy to the
atmosphere as there must always be an outlet for the coolant energy to prevent the engine
from over heating. An alternative to this would have been to purchase a single effect
absorption chiller to generate additional chilled water that could be exported to the
93
chilled water grid, or to make a connection with the domestic hot water system of the
building.
Finally, the electrical energy needs to be sent to the power grid. The advantage of
connecting power to the utility grid is that it allows operational freedom to produce the
reject heat in the quantity required. If a CHP system does not have the flexibility to
export electricity, the prime mover must always match the electrical demand other wise
the electrical circuits will overload. As electrical and thermal demands dont necessarily
coincide, too much waste heat could be generated, or not enough. The requirements of
the utility paralleling gear (Automatic Transfer Switch / Soft Load Controller ATS/SLC)
are up to the local utility. Typically for very small systems, less than 100 kWe, the
utilitys requirements are minimal. However, as this is a demonstration facility, a much
more complex ATS/SLC was selected, which could provide additional operational
flexibility and realism for larger systems.
Based on all of this information several flow diagrams were generated and frequently
revised as details emerged on equipment, pipe sizes, and sensor and actuator
requirements.
Due to the scattered nature of this CHP installation, the heat recovery equipment had to
be placed in a relatively distant location from the absorption chiller. Therefore, piping
losses (thermal and pressure) had to be considered as the piping distance is about 220 feet
(67 meters) including a 70 foot (21 meter) vertical rise. A pressure drop of 5 psi (0.3 bar)
94
and a thermal loss of 2.5 kWt were calculated based on these estimates as shown in
Appendix D. Therefore, a minimum of 18.5 kWt was needed to drive the absorption
chiller. It was decided to add a little padding to this number and set the requirements to
20 kWt.
4.2.6 Operations
A specific operational strategy was not selected for this project as one of the research
goals of this project is to compare operational strategies. The control system and
infrastructure in place for this system allow the system to thermal load follow, electrical
load follow, base load, and peak load. There is an extra cost associated with this decision,
but as a demonstration facility cost was not a driving factor.
4.2.7 Evaluation
The fuel type, prime mover, and auxiliary equipment were selected relatively quickly for
this application as there were a lot of constraints on equipment selection between the
existing chiller and ventilation systems, the energy grids, and the demands of the building.
The long term evaluation of all facets of this system was the primary focus of this project,
and is outlined in section 3. The evaluation of this system was meant to satisfy CHP
system designers, builders, operators, owners, and regulators as well as educational
entities. Therefore, there is a great emphasis on data acquisition and dissemination. Over
200 data points are continuously measured and available on the web.
95
4.2.8 Submittals
Flow diagrams, material and energy balances, equipment descriptions, operating
descriptions, process and instrumentation diagrams, preliminary layout, and cost
estimates for equipment were all created and submitted to an engineering firm for
detailed evaluation and the creation of construction drawings.
The engineering firm created a detailed flow diagram, and a layout which had to balance
educational/scientific goals. The detailed flow diagram and the layout went through
several iterations as the educational and scientific goals werent always understood by the
engineering firm. Code requirements often clashed with scientific requirements, however
eventually a compromise was met. Upon completion of the construction drawings, bids
were sought and awarded for placing and connecting the equipment, installing
instrumentation and controls, and commissioning the system. Details on the construction
process can be viewed on the project website:
http://www.cmu.edu/iwess/components/biodiesel_engine/installation/index.html
96
5.0 TRNSYS Modeling
An overall TRNSYS model has been programmed by Flore Marion to simulate the
performance of individual and combined systems in various operational modes. Many of
the IWESS components have been modeled using TRNSYS in order to develop generic
models for future building HVAC design. These models include the absorption chiller,
the engine generator with heat recovery, and the ventilation system. The purpose of the
model is to estimate what fraction of the thermal requirements of the IW can be met by
the biodiesel CHP system in various operational modes and what portion of the thermal
output must rejected to the surroundings.
5.1 IWESS Model
The IWESS model is built out of three main components, the biodiesel fueled CHP
system, the double effect absorption chiller, and the enthalpy recovery ventilation system.
Each of these systems has had a previously developed empirical model, which was
implemented in TRNSYS. Empirical models had to be used as computational models
were to calculation intensive. The model uses three measured data files which include the
heating, cooling, and regeneration loads of the IW. The outputs include the electrical
generation, fuel demand, and the necessary flows and temperatures of the thermal streams.
5.1.1 Biodiesel Fueled Engine Generator with Heat Recovery
Modeling
The design of the engine generator with heat recovery model has been completed and
tested at 6, 12, 18 and 25 kWe. The first model used manufacturers specifications as
97
inputs [34]. The model has been validated using measured data, which as shown in
section 3.1.3 very closely matches the specifications of the manufacturer. The look up
tables developed for this engine generator are shown in Appendix E. Using the look up
table a simple TRNSYS module for the CHP system was developed that equates fuel
flow to electricity generation, hot water generation via the coolant heat exchanger, and
steam production via the steam generator.
Figure 31: CHP system input / output module
5.1.2 Double Effect Steam Driven Absorption Chiller
A complex Engineering Equation Solver (EES) model was developed for the absorption
chiller sub-system. However, this model was to computationally intensive for TRNSYS
to run so a table look up model was developed and implemented in TRNSYS.
The TRNSYS absorption chiller model is based on empirical data collected during the
operation of the chiller over various loads [35]. The operating data has been distilled to a
simple relationship, which equates cooling capacity with heat input.
Figure 32 shows the input and output of the chiller model.
98
Cooling
Demand
Absorption
Chiller
Module
High Pressure
Steam Flow
and Pressure
Figure 32: Double effect absorption chiller input / output module
5.1.3 Ventilation Unit with enthalpy recovery and solid desiccant
wheel.
The ventilation system has also been modeled in TRNSYS, and is also quite complex.
For the purposes of the integrated system model, empirical data for the regeneration
demand from the ventilation system were used to create a table look up model that relates
regeneration demand to a demand of hot water from the CHP system [36]. Figure 33
shows the simple input / output module for the ventilation system.
Ventilation
Module
Regeneration
Demand
Hot Water
Flow and
Temperature
Figure 33: Ventilation system input / output module
5.1.4 Computational Model Issues
While it is possible to use computational models rather than empirical models there are
several drawbacks. First and foremost, the performance of the systems and how they
interact with each other in every time step must be calculated. Building a computational
model was carried out; however the system was so complex that it had to be run in small
simulation time increments (about two weeks) with a time step of five minutes to get
99
accurate results. While, this is sufficient for scientific purposes it is ineffective as a
design tool.
To illustrate some of the computations necessary the following is the process by which
cooling is delivered.
1. A cooling demand is set by the building load file.
2. The chiller then calls for steam by calculating how much steam is required to
meet the new cooling demand.
3. Steam is drawn from the steam generator, which calls on the engine to adjust its
output to provide the correct amount of heat to the steam generator based on its
heat transfer characteristics.
4. Next the engine calculates the amount of fuel necessary to meet the new demand.
Simultaneously the coolant loop is operating which also has various thermal demands,
and calculates how much heat should be recovered and rejected. On top of that an over all
control strategy is running that decides which form of heat is more important, coolant or
exhaust.
Figure 34 shows the combined computational model for the CHP system with all of the
components needed to operate the system including the pipes and valves themselves.
100
Figure 34: Combined TRNSYS Model
5.1.5 Combined IWESS Model
To resolve the performance issues of the computational model it was decided to use the
look up tables and simplify the entire program so that a full year simulation could be run
in a relatively short amount of time.
To simplify the entire program the following steps were taken:
1. The engine generator with coolant heat recovery were merged into a single
component based on a look up table.
101
2. The ventilation system was reduced to a table look up model that relates the
regeneration load to the coolant heat demand on the engine.
3. The chiller system was also reduced to a cooling load file setting a thermal
demand on the steam generator, which was fed the engine outputs of exhaust
temperature and flow rate.
These steps resulted in the model shown in Figure 35, which is much easier to understand
and operate. Furthermore, the simplified model can now be run for a full year.
Figure 35: Combined/Simplified I WESS TRNSYS Model
The model shown in Figure 35 operates in the following way. Three empirical load files
for heating, cooling, and regeneration demands are shown on the left side of Figure 35.
These load files are fed into the controller, where the user sets an operational mode, base
load, thermal load follow, or regeneration load follow. The controller outputs a control
102
signal to the engine component, which then outputs the proper temperatures, pressures,
and flows generated by the CHP system.
The model allows the user to adjust a number of different system characteristics with
relative ease.
1. The engine component uses two data files that are based on the look up tables
shown in Appendix F that can be easily replaced if operational changes are
desired.
2. The controller can operate in different modes by double clicking the controller
and selecting a different mode.
-Mode 0: Operate at 100% (25 kWe)
-Mode 1: Thermal Load Follow (Cooling, Heating)
-Mode 2: Regeneration Load Follow
3. The load files (heating, cooling, regeneration) can be altered by double clicking
on the icons and linking a new load file, which can be based on measured or
simulated data from a model.
Three simulations were conducted using the integrated TRNSYS models for the 25 kWe
model. The first simulation is a peak design operation simulation which has the engine
running at its highest efficiency point, 25 kWe. The excess steam and electricity will be
103
exported to the CMU campus grid, and the excess coolant energy will be rejected to
atmosphere.
The second operational mode is a thermal load follow mode where the engines output
changes to match heating and cooling demands. Excess electricity will be exported to the
grid, and electricity shortfalls will be made up by the grid. Excess coolant energy will be
dumped to atmosphere via the remote radiator, and regeneration energy short falls will be
made up by the natural gas burner in the ventilation system.
The third operational mode is also thermal load follow mode where the engines output
change to match the regeneration demand of the desiccant regeneration load. Similarly
heating, cooling, and electrical surpluses and short falls will be made up by the grid.
5.1.6 IWESS Simulations
The following runs show the results of the IWESS simulation runs for three modes, 1)
design operation at 25 kWe, 2) following the heating and cooling loads, and 3) following
the regeneration load. The results shown are the statistics generated for; number of hours
loads are not met, total net energy exported or imported, and average efficiency. Note,
hourly electrical data was not available as the data acquisition system stopped collecting
data periodically, however the meters themselves continued to collect data which
includes the annual totals, but not individual hours. Therefore, hours of electrical load not
met and an electrical load follow mode are not possible at this time.
104
5.1.6.1 Mode Zero: Design Operation
The IWESS system operating at a constant 25 kWe with a constant 18 kWt exhaust
energy output and 18 kWe coolant energy. The output of the engine is compared to the
demand of the IW for heating, cooling, dehumidification, and electricity. The excess
electrical and exhaust energy (in the form of steam) is exported to the rest of campus,
while the coolant energy is rejected to the atmosphere with a radiator.
Mode Zero Results: Design Operation at 25 kWe
Annual Net Energy Export 1,015,470 MJ
Annual Net Thermal Energy Export 706,442 MJ
Annual Net Electrical Energy Export 309,028 MJ
Hours of Operation 8,760 Hours
Heating Hours Not Met 351 Hours
Cooling Hours Not Met 191 Hours
Regeneration Hours Not Met 265 Hours
Total Energy Used 1,791,999 MJ
Total Fuel Consumption 19,921 Gallons
Total Fuel Energy Consumption 2,712,360 MJ
Average Annual Efficiency 66%
Table 12: IWESS Design Operation Simulation Results
The base load operation has an overall CHP efficiency of 66%. The lower CHP
efficiency is due to the heat rejected by the coolant system as it does not have the ability
to be exported. If additional uses for coolant energy could be found, the over all
efficiency would increase towards 80%.
5.1.6.2 Mode One: Thermal Load Follow
The IWESS system is operating at a variable output matching the thermal load (cooling
or heating) of the IW.
105
Mode One Results: Thermal Load Follow
Annual Net Energy Import 104,613 MJ
Annual Net Thermal Energy Export 31,827 MJ
Annual Net Electrical Energy Import 136,440 MJ
Hours of Operation 5,158.5 Hours
Heating Hours Not Met 2,773 Hours
Cooling Hours Not Met 2,986 Hours
Regeneration Hours Not Met 3,184 Hours
Total Energy Used 834,821 MJ
Total Fuel Consumption 9,025 Gallons
Total Fuel Energy Consumption 1,228,845 MJ
Average Annual Efficiency 68%
Table 13: IWESS Thermal Load Follow Simulation Results
A substantial increase in the number of hours of cooling and heating was not achieved.
There are two reasons for this; first the controller is only adjusted every 30 minutes due
to the limitations of the software. The controller is setup to supply either heating or
cooling, not both at the same time. If the IWs load changes from heating to cooling in
the same 30 minute period, the controller will only cover the larger load, and not cover
both. It is unusual that the number of heating hours not met does not increase
substantially as well, however the data clearly shows that the heating load is typically
larger than the cooling load when both are present.
These loads are typically small, for example on 13 November at 9:00 in the morning
there is a 142.3 kJ cooling load in the IW. At 9:30 there is a 64.4 kJ heating load and a
32.2 kJ cooling load. At 10:00 there is a 176.7 kJ heating load and no cooling load. These
loads are tiny, yet the statistical analysis still shows that the cooling load for 9:30 was not
met. In the future it may be possible to have a finer resolution of both measured data and
simulation results to reduce these statistical analysis problems.
106
The analysis of this data would lead to the conclusion that the IWs control system is not
fined tuned enough to prevent this fast transition from heating to cooling as is intended in
the design. The loads that are causing this issue are very small and probably do not need
to be addressed by the HVAC system, but that intelligence currently does not exist in the
IWs HVAC control system. An alternative solution to adjusting the control system is
increasing the thermal mass of the IW by using phase change materials, which would
help moderate the changing thermal demands due to the IWs light weight construction.
The second reason for the increase in unmet hours of heating, cooling, and regeneration is
due because the control system does not allow the engine to run when it is operating
below 25% capacity. The engine is not operating for 3,574.5 hours, and any small heating,
cooling, or regeneration load during those hours is not met. Furthermore, just like the
mode zero operation, there are 807 hours of peak operation that cant be met with this
system.
Overall this operational mode is an improvement in efficiency due to rejecting less
coolant energy; however, the quantity of hours the heating and cooling load is not met
would not be acceptable.
5.1.6.3 Mode Two: Regeneration Load Follow
This operational mode only uses the desiccant regeneration load to set the demand on the
engine. The coolant energy is used to meet the regeneration load and the exhaust and
electrical outputs are used in the IW or exported to the campus grids if the demand in the
IW is low enough.
107
Mode Two Results: Regeneration Load Follow
Annual Net Energy Export 390,334,042 MJ
Annual Net Thermal Energy Import 389,883,120 MJ
Annual Net Electrical Energy Import 450,922 MJ
Hours of Operation 1,042.0 Hours
Heating Hours Not Met 5,486 Hours
Cooling Hours Not Met 2,927 Hours
Regeneration Hours Not Met 7,136 Hours
Total Energy Used 71,217 MJ
Total Fuel Consumption 800 Gallons
Total Fuel Energy Consumption 108,900 MJ
Average Annual Efficiency 65%
Table 14: IWESS Regeneration Load Follow Simulation Results
This mode is not very effective for operation of the IWESS system. The number of hours
of cooling, heating, and dehumidification not met is very large. Counter intuitively the
number of hours not met for dehumidification rose dramatically. This is because the
regeneration load is typically small (less than 7 kWt) and the limitations set on the engine
controller does not allow the system to operate at electrical loads below 6 kWe due to low
efficiency and therefore it is incapable of producing less than 7 kWt. Therefore, during all
the low load conditions, the engine is off, which is shown in the table with only 1,042 run
hours. In the other operational modes the system focused on meeting the peak thermal
demands so there was usually enough coolant heat in the system to meet the minimal
regeneration loads with the consequence of dumping some to atmosphere.
The CHP efficiency is reduced most likely because the engine consistently operates at a
lower rating, which reduces the over all efficiency even though very little heat is rejected
to the atmosphere. To compensate for this low rating, a thermal storage system may be
included that allows the engine to run at peak efficiency for short periods of time.
108
5.1.6.4 I WESS Simulation Discussion
As previously stated, CHP systems operate most efficiently at a steady state, and high
performance buildings reduce loads to the point where systems can be turned off. When
using a thermal load follow approach in a high performance building, the CHP systems
load will drop to the point at which it is no longer desirable to operate the system.
Therefore, it is recommended to have both a electrical and thermal grid in order to
maximize the effectiveness of the CHP system when it is used in a high performance
building.
5.2 BAPP Model
A hypothetical system based on the 25 kWe system has been created that operates at
200kWe for the Building As Power Plant (BAPP) concept. A 200 kWe system was used
as this is the correct size for the peak electrical power of the BAPP. A 200 kWe Diesel
engine specification sheet was also available to compare with the 25 kWe Diesel engine
during the scale up shown in Appendix G. As discussed in the design guide, there are
many ways to size a CHP system for a building, and 200 kWe unit was selected as an
example. Finally, the BAPP design is still under development and as such subject to
change. Therefore, a modified version of the IW load file multiplied by a factor of 10 was
used for this simulation as reliable hourly thermal loads are not available at this time for
the BAPP.
5.2.1 Engine Modification
The engine specifications used for this system had to be adjusted to suit a CHP system.
Larger engines in the U.S. use an intercooler in the turbocharger to cool the incoming
109
fresh air to increase its density and produce more power, therefore, meeting tougher EPA
standards, which are based only on electrical power production per gram of various types
of pollution (CO, NO
X
, SO
X
, and PM
2.5
). This heat is currently dumped to the space
surrounding the engine using an air-to-air heat exchanger. Instead of dumping this heat to
the air, it will be combined with the water jacket coolant system like the 25 kWe engine.
To estimate the effect of combining the turbocharger heat rejection and the engine block
heat rejection, the following steps are taken.
Given:
-Engine block heat rejection =83.7 kWt
-Coolant (50/50 propylene glycol) flow rate =265 liters/min
-Coolant outlet temperature =95
o
C
-Air charge heat rejection =40.4 kWt
Calculations:
-Determine engine coolant inlet temperature
( )
| |
| |
| | | | | | C C C
C kg
kJ kg
kW
C T
c m
Q
T T
T T c m Q
o o o o
in
out in
in out engine
7 . 89 3 . 5 95
559 . 3
sec
417 . 4
7 . 83
95 = =
(
=
=
=
-
-
- -
-Combine water jacket and air charge reject heats and determine new flow rates.
110
| | | | | |
( )
( )
| |
| | | | ( )
(
=
(
=
=
= + = + =
-
-
-
- -
- - -
min
7 . 394
sec
58 . 6
7 . 89 95 559 . 3
1 . 124
1 . 124 4 . 40 7 . 83
arg
liter kg
C C
C kg
kJ
kWt
m
T T c
Q
m
T T c m Q
kWt kWt kWt Q Q Q
o o
coolant
in out
coolant
in out
coolant
coolant
er turboch engine coolant
The next step is to determine the part load heat transfer rates given what is known about
the 25kWe engine.
Power Level Coolant Heat Transfer
6 kWe 6.4 kWt
12 kWe 9.9 kWt
18 kWe 13.1 kWt
25 kWe 18.1 kWt
Table 15: IWESS 25 kWe CHP Coolant Heat Exchanger Results vs. Power Level
Assuming similar proportions as shown above, below are the estimated heat transfer rates
for the 200 kWe engine.
Power Level Coolant Heat Transfer
50 kWe 43.9 kWt
100 kWe 67.9 kWt
150 kWe 89.8 kWt
200 kWe 124.1 kWt
Table 16: Estimated BAPP 200 kWe CHP Coolant Heat Exchanger Results vs. Power Level
Similarly, air flow rates are estimated the same way based on the 25kWe engine data.
111
Power Level Air Flow Rate
6 kWe 138 kg/hr
12 kWe 144 kg/hr
18 kWe 153 kg/hr
25 kWe 165 kg/hr
Table 17: IWESS 25kWe CHP Air Flow Rate vs. Power Level
Power Level Air Flow Rate
50 kWe 878 kg/hr
100 kWe 916 kg/hr
150 kWe 974 kg/hr
200 kWe 1050 kg/hr
Table 18: Estimated BAPP 200 kWe CHP Air Flow Rate vs. Power Level
Using the estimated information in the tables above and the 200 kWe engine generator
specification sheet, look up tables for the 200 kWe engine were created shown in
Appendix H, a similar TRNSYS simulation files was created for the 200 kWe system.
Figure 36: BAPP TRNSYS Simulation
The scaled up version of this model for the Building As Power Plant (BAPP) is nearly
identical to the IWESS model, however, the load and engine data files were altered using
to use a larger engine.
112
5.2.2 BAPP Simulations
The following runs show the effect of operating an IWESS style system for BAPP using
a 200 kWe engine generator instead of a 25 kWe engine generator. A 200 kWe engine
generator was selected as this is the peak power demand of the BAPP.
5.2.2.1 Mode Zero: Design Operation
The BAPP CHP system is operating at a constant 200 kWe with a constant 111 kWt
exhaust energy output and 124 kWt coolant energy. The output of the engine generator is
compared to the demand of the IW for heating, cooling, dehumidification, and electricity.
The excess electrical and exhaust energy (in the form of steam) is exported to the rest of
campus, while the coolant energy is rejected to the atmosphere with a radiator.
Mode Zero Results: Design Operation at 200 kWe
Annual Net Energy Export 38,543 MJ
Annual Net Thermal Energy Import 3,165,375 MJ
Annual Net Electrical Energy Export 3,203,918 MJ
Hours of Operation 8,760 Hours
Heating Hours Not Met 3,531 Hours
Cooling Hours Not Met 2,050 Hours
Regeneration Hours Not Met 2,956 Hours
Total Energy Used 13,006,500 MJ
Total Fuel Consumption 119,965 Gallons
Total Fuel Energy Consumption 16,333,612 MJ
Average Annual Efficiency 80%
Table 19: BAPP Design Operation Simulation Results
The base load operation shows a high efficiency, however the simulation results show
that there was a substantial shortfall of thermal energy for the building, although there
was a lot of excess electricity to make up for it so the BAPP using this operational
method is a net energy exporter. A true BAPP should at the very least have a net export
of all forms of energy, and probably export all forms of energy for every hour. The high
113
efficiency is probably due to the fact that the engine is operating constantly at its most
efficient load, 200 kWe, and the fact that there is a large thermal load, which is using up
most of the coolant energy so little energy is rejected to atmosphere.
5.2.2.2 Mode One: Thermal Load Follow
The BAPP CHP system is operating at a variable output matching the thermal load
(cooling or heating) of the IW.
Mode One Results: Thermal Load Follow
Annual Net Energy Import 2,363,485 MJ
Annual Net Thermal Energy Import 2,058,830 MJ
Annual Net Electrical Energy Import 304,655 MJ
Hours of Operation 5,165 Hours
Heating Hours Not Met 5,817 Hours
Cooling Hours Not Met 2,981 Hours
Regeneration Hours Not Met 3,450 Hours
Total Energy Used 5,663,109 MJ
Total Fuel Consumption 54,107 Gallons
Total Fuel Energy Consumption 7,366,797 MJ
Average Annual Efficiency 77%
Table 20: BAPP Thermal Load Follow Simulation Results
Similar to the IWESS thermal load follow simulation the number of hours the loads are
not met is very high, however in addition to the issues stated in section 5.3.1.2, the 200
kWe system is under sized for the thermal load, therefore more hours are not met. On the
other hand, as the CHP system is smaller relative to the load it rejects less heat, therefore
operating at a higher efficiency.
5.2.2.3 Mode Two: Regeneration Load Follow
This operational mode only uses the desiccant regeneration load to set the demand on the
engine generator. The coolant energy is used to meet the regeneration load and the
114
exhaust and electrical outputs are used in the BAPP or exported to the campus grids if the
excess is available.
Mode Two Results: Regeneration Load Follow
Annual Net Energy Import 7,008,961 MJ
Annual Net Thermal Energy Import 4,146,361 MJ
Annual Net Electrical Energy Import 2,862,600 MJ
Hours of Operation 1,042 Hours
Heating Hours Not Met 5,653 Hours
Cooling Hours Not Met 2,942 Hours
Regeneration Hours Not Met 7,283 Hours
Total Energy Used 504,924 MJ
Total Fuel Consumption 4,706 Gallons
Total Fuel Energy Consumption 640,713 MJ
Average Annual Efficiency 79%
Table 21: BAPP Regeneration Load Follow Simulation Results
Similar to the IWESS regeneration load follow simulation, the BAPP regeneration load
follow system has relatively few hours of operation. It also has a high efficiency as the
majority of the heat is captured.
5.2.2.4 BAPP Simulation Discussion
It appears that the selected CHP system for this application is too small to fulfill the role
of Building As Power Plant as there is insufficient thermal output for heating, cooling,
and regeneration even in the base load operation. Furthermore, according to Dr. Volker
Hartkopf, there should always be an excess of electricity, steam, and chilled water
generated by the BAPP CHP system to truly meet the goals of the BAPP concept.
Another prime mover should probably be selected to meet the estimated loads. That said,
the BAPP load files are estimates, and there have been several design revision in the last
five years that may not be included in the latest EnergyPlus file that was created in 2003.
115
In order to meet the varying loads of the BAPP, a modular CHP system approach might
be attempted. As the load is frequently below 50 kWe (25% of engine rating); several
smaller engine generators may be linked to operate together. For example, if eight 25
kWe engine generators were combined, then the CHP system could efficiency operate a
power level as low as 6 kWe, or 3% of the 200 kWe engine generator total rating. This
would probably also entail using several smaller absorption chillers and ventilation
systems rather than single large units.
116
5.3 Data Center CHP Operation
Data center load profiles are completely different than commercial buildings. The
computational equipment inside the data centers dominates the buildings power and
cooling demands. An average electrical load for a data center is approximately 250 watts
per square foot (2.7 kW/m
2
), and that load is nearly directly translated into an equivalent
cooling load [37]. Furthermore, the load is nearly constant day and night as well as
seasonally for most locations as the envelope load and occupant load is typically less than
2 watts per square foot, which is negligible compared to the equipment load [37].
Therefore, the CHP system can be operated at a near constant set point. Finally, typically
there is no heating load or latent cooling load (dehumidification) for data centers so all
the thermal energy should be routed to absorption cooling [37].
Using this information, a CHP system is applied to a hypothetical data center with a peak
electrical load of 200 kWe, which translates into a 200 kWt cooling load. At 250 Watts
per square foot, this translates to an 800 square foot building, which is small for a data
center however this concept can easily be scaled up. The only change would be the
proportions of the heat and electricity generated which is discussed at length in section
2.2.
As there is no latent cooling load requiring dehumidification, it makes sense to use the
coolant energy from the Diesel engine to drive a single effect absorption chiller.
Furthermore, the outlet temperature from the double effect absorption chiller is
117
approximately 160
o
C, which can be used in single effect chiller as well as a single effect
chiller can operate with a COP of 0.7 at temperature as low as 70
o
C [17].
The double effect absorption chiller receives a heat input of 95.6 kWt at a temperature of
485
o
C and an outlet temperature of 160
o
C [38]. With a COP of 1.1, this translates into
105.2 kWt of cooling. Next, the exhaust is cooled down further to 80
o
C, which translates
into an additional 23.5 kWt. 80
o
C is assumed reasonable as the exhaust cant be cooled
all the way down to the desorber inlet temperature of the 70
o
C. A single effect chiller
with a COP of 0.7 would generate 16.5 kWt of cooling.
Finally, 124.1 kWt of coolant energy is available in the coolant system from the engine
block and the turbocharger. Again using the same single effect chiller with a COP of 0.7,
86.9 kWt of cooling is generated.
The total cooling potential of the combination single and double effect absorption chiller
is estimated to be 208.6 kWt, which is nearly the precise load of the building. This
demonstrates what a great match CHP systems are for data centers.
All totaled, 200 kWe of electricity and 209 kWe of cooling is delivered using 524 kWc of
fuel energy to yield a combined efficiency of 78%.
Unfortunately, it is unlikely that the reject heat from the absorption chillers will find a
substantial use. Most stand-alone data centers have a low occupancy rate so a large
118
domestic hot water load is unlikely in contrast to the IWESS and BAPP systems
described above. It may be possible to use this heat for thawing of sidewalks and parking
lots where a winter climate is present. In the case that a data center can be part of a
community, many potential uses such as heating swimming pools, preheating domestic
hot water, etc. exist. Furthermore, if a data center is part of a larger office complex
additional systems integration strategies may be available.
The primary energy for operating the CHP system at 200 kWe would require about 52
kg/hr of biodiesel fuel or about 17,092 GJ per year. On the other hand, 200 kWe of grid
electricity would require 19,710 GJ of coal per year plus the electricity for cooling, which
is 200 kWt of cooling with a COP of 3.2 translates into 62.5 kWe or 6,159 GJ per year or
a total of 25,869 GJ per year. The CHP system uses about one third less primary energy
than the utility system, to provide adequate power and cooling.
Furthermore, data centers, like most mission critical systems, require back up power.
Therefore, the first cost increase for a CHP system is the slight cost increase associated
with switching the vapor compression chillers to absorption chillers and the necessary
heat recovery equipment and controls. Keep in mind, it is best to direct fire absorption
chillers when possible so the only systems integration cost should be exhaust ducting and
coolant piping, controls (sensors, dampers, valves, etc.), and insulation between the
engine and the chillers.
119
6.0 Systems Integration
This final chapter is devoted to the development of an integrated example system that
includes power generation; chilled water, heated water, conditioned dehumidified air, and
domestic hot water producer. This system is designed around the existing IWESS
components of the engine generator, heat recovery, absorption chiller, ventilation system,
and auxiliary equipment.
The purpose of this example is to show potential designers and user of such a system the
opportunities for simplifying the overall system. Users typically want a finished product,
not parts to be assembled. For example, computer users typically buy a finished computer
from manufacturer or store. While there typically is some assembly required such as
connecting a power cord, monitor and other peripherals, the assembly requires no tools
and can be accomplished quickly.
The CHP system installed at CMU is more closely related to building a computer from
individual components such as a mother board, CPU, hard drive, power supply, etc. This
job requires a lot more know how, and possibly some specialized tools. Furthermore, the
IWs CHP system, along with many other building components, have the added difficulty
of speaking different languages (like mixing MAC and PC components) and different
fittings or connectors that dont match. The interface between these systems often
requires customized solutions, which are time and cost intensive.
120
To alleviate these issues, similar to a Dell or HP, the parts are selected by a manufacturer
that work well with each other and are packaged in such a way that the connections are
made quickly. This concept is not limited to computers; Freightliner & Paccar do not
make the engines and axles in their trucks. These parts are purchased from Cummins and
Caterpillar, two previously mentioned engine generator manufacturers and integrated into
the overall system. Also, if a significant volume of units are sold, suppliers may change
specifications to suit a large customers requests.
6.1 Individual Systems Integration
The first step to integrating separate sub-systems is to understand how the systems are
related. There are five major IWESS components; the CHP sub-system, the absorption
chiller sub-system, the ventilation sub-system, the domestic hot water sub-system, and
the energy grids. Each of these sub-systems is made up of smaller components.
The CHP sub-system shown in Figure 37, has five major pieces including the engine
generator, the ATS/SLC, the exhaust heat recovery unit, the coolant heat recovery unit
and the supervisory controls. The engine generator is then made up of four additional
components; the Diesel engine, the generator, the radiator, and the engine controls all of
which were made by four different manufacturers and integrated by a fifth company.
As there is a large market for backup power generation, the engine generator is available
fully integrated from many dealers. The remainder of the parts are shipped separately and
are integrated onsite, which is labor intensive.
121
Exhaust
Heat
Recovery /
Steam
Generator
Engine
Generator
Intelligen
Controls
Coolant
Heat
Recovery
ALC Controls
Radiator
Automatic
Transfer
Switch /
Soft Load
Controller
Hot Air
Pneumatic
Controls
Hot Exhaust Electricity
Hot
Water
Loop
Condensate
Fuel
Control
Data
Control
Data
Air
Steam
Compressed
Air
Figure 37: CHP Major Component Diagram
The absorption chiller components shown in Figure 38 are all designed and built by
Broad and shipped as a single unit. However, an absorption chiller will not operate as a
stand alone system because it requires a heat input and a heat rejection output. The Broad
chiller incorporates a cooling tower for rejecting heat. The original heat input system was
an electric boiler not shown in Figure 38 as it has been replaced by the CHP system.
Absorption
Chiller
Cooling
Tower
Broad Controls
Treated
Water
High Pressure
Steam
Electricity
Warm,
Humid Air
Control
Data
Chilled Water
Loop
Air
Figure 38: Absorption Chiller Major Component Diagram
122
Finally, the ventilation sub-system shown in Figure 39 has five main components, four of
which are made by one supplier. The control sub-system was outsourced yet integrated
by the main manufacturer. The ventilation sub-system is the only component within
IWESS that is able to operate without the addition of auxiliary equipment.
Figure 39: Ventilation System Major Component Diagram
The second step is to understand the quantity and quality, temperature, of the heat being
dealt with in the thermal energy cascade of Figure 40. The concept of the energy cascade
is to use the highest form of fuel or energy to create the highest quality product: from
electricity, to chilled water, to dehumidified air, to domestic hot water, and to hot water
for space heating. Using an engine generator poses an additional challenge as two sources
of energy (exhaust and coolant) are being generated simultaneously; therefore they must
be handled simultaneously.
123
Engine Generator
Absorption
Chiller
Exhaust Heat
Recovery (DHW)
Exhaust Heat
Recovery (SH)
Hot Water Return
Hot Water Supply
City Water / Preheated DHW
Regeneration Heat
Exchanger
Outside Air
Regeneration Air
Coolant Heat
Exchanger
Hot Water Return
Hot Water Supply
Domestic Hot
Water Preheat
City Water
Preheated DHW
Chilled Water Return
Chilled Water Supply
Electricity
Domestic Hot Water
Fuel Energy
Exhaust
Coolant
To DHW Preheat (See bottom)
Figure 40: CCHP/V Energy Cascade
After the qualities of the heat sources are understood, T-Q diagrams need to be developed
to understand the heat transfer processes and select proper heat transfer equipment. The
energy cascade shown in Figure 40 is not the only possible configuration, but this is the
one that was chosen for the IWESS system. Alternatives such as using high temperature
exhaust to generate steam to drive a turbine or using low temperature exhaust to melt
snow gives an idea of the possible range of applications.
The third step to integrate separate systems is to understand the inputs and outputs of
each system in the forms of energy, material and data. As described in section 3 and
shown in Table 22; the CHP system, the chiller system, and the ventilation system are
well understood.
124
Existing IWESS Configuration Inputs / Outputs
CHP System Absorption Chiller System Ventilation System
Inputs Outputs Inputs Outputs Inputs Outputs
Fuel
(Biodiesel)
Electricity Electricity Exhaust
Fuel (Natural
Gas)
Dehumidified
Air
Air Exhaust
High Pressure
Steam
Condensate
Outside and
Return Air
Regeneration
Exhaust Air
Condensate
High Pressure
Steam
Chilled Water
Return
Chilled Water
Supply
Regeneration
Air
Exhaust Air
Hot Water
Return
Hot Water
Supply
Makeup Water
(Cooling Tower)
Steam (Cooling
Tower)
Electricity
Compressed
Air
Table 22: IWESS I nput / Output Table
The three IWESS systems shown in Figures 37 through 39 are integrated into a system as
shown in Figure 41. The integrated system takes advantage of some of the waste heat
sources from the CHP to drive the absorption chiller and the desiccant regeneration
processes. The advantage of this system configuration over the stand alone systems is that
there is now a demand for both low and high temperature heat during the summer
increasing the operation time of the CHP system, and increasing the year round energy
efficiency.
125
Terminal
Heating
Units
Terminal
Cooling
Units
Domestic
Hot Water
Absorption
Chiller
Cooling
Tower
Broad Controls
Heat
Pump
Module
Enthalpy
Recovery
Module
Desiccant
Module
ALC Controls
Regen Burner
Exhaust
Heat
Recovery /
Steam
Generator
Engine
Generator
Intelligen
Controls
Coolant
Heat
Recovery
ALC Controls
Radiator
Automatic
Transfer
Switch /
Soft Load
Controller
Hot Air
Pneumatic
Controls
Hot
Exhaust
Electricity Fuel
Treated
Water
High
Pressure
Steam
Electricity
Natural
Gas
Return
Air
Electricity
Regeneration
Air Exhaust
Outside
Air
Dehumidified
Supply Air
Exhaust
Air
Control
Data
Control
Data
Control
Data
Control
Data
Air
Regen Coil
Hot
Water
Loop
Pump
Chilled Water
Loop
Pump
Regeneration
Air Supply
Pump
Natural
Gas
Electricity
City
Water
DHW
Exhaust
Warm,
Humid Air
Air
Figure 41: Major Component Piece-wise Systems Integration
Figure 41 is a very complex setup with many components outlined in Table 23.
System
Major
Components
Minor
Components Controllers
Heat
Rejection
ATS / SLC Radiator ATS / SLC Radiator
Engine Generator
Intelligen
Controls
Exhaust
Coolant Heat
Exchanger
ALC Controls
CHP System
Steam Generator
Pneumatic
Controls
Absorption
Chiller
Absorption Chiller Cooling Tower Broad Controls
Cooling
Tower Steam
Enthalpy Recovery
Wheel
Regeneration
Burner
ALC Controls
Regeneration
Exhaust Air
Heat Pump Regeneration Coil
Ventilation
System
Desiccant Wheel
Domestic Hot
Water
DHW Storage Tank DHW Controller Exhaust
Table 23: IWESS Component List
126
6.2 Packaged Systems Integration
This section describes how the three individual systems might be packaged so they can
work together more effectively. As discussed in section 3, the potential for further
systems integration and reduction of components and subsystems to reduce first and
operation cost and simplify the operation of the combined system are now applied to the
IWESS system in Figure 42.
Figure 42: Packaged CCHP/V System
127
System Major Components
Minor
Components Controllers Heat Rejection
ATS / SLC Radiator Radiator
Engine Generator Exhaust
Coolant Heat
Exchanger
CHP System
Exhaust Heat
Recovery
Absorption
Chiller
Absorption Chiller
Enthalpy Recovery
Wheel
Regeneration
Coil
Regeneration
Exhaust Air
Desiccant Wheel Heating Coil
Ventilation
System
Cooling Coil
Domestic
Hot Water DHW Storage Tank
Supervisory
Controller
Table 24: Packaged System Component List
Comparing Figure 41 and Table 23 with Figure 42 and Table 24 the system has been
greatly simplified with the removal of:
- 1 major component (heat pump)
- 2 minor components (regeneration burner and cooling tower)
- 7 control systems with their respective interfaces
- 2 heat rejections
Additions to Figure 42 include:
- 3 minor components (heating coil, cooling coil, and DHW preheat heat
exchanger)
- 1 supervisory controller that handles all control features with one interface
To further aid the understanding of the packaged system Figures 35 and 36 were created
to describe the operation of the packaged system in summer and winter modes.
128
Engine Generator
Building
Electric Grid
Absorption
Chiller
Exhaust Heat
Recovery
Building Chilled
Water Grid
Air
Exhaust
DHW Preheat
City
Water
Building Domestic
Hot Water Storage
Coolant Heat
Exchanger
Radiator
Passive
Energy
Wheel
Outside Air
Exhaust Air Chilled
Water
Coil
Preconditioned
Air
Return Air
Saturated Air
Active
Desiccant
Wheel
Dry Air
Supply Air
Regeneration
Heat
Exchanger
Outside Air
Regeneration
Air
Exhaust
Air
Pump
Pump
Pump
ATS/SLC Fuel Utility Grid
Figure 43: CCHP/V Summer Operation Flow Diagram
Figure 43 shows the summer operation setup of the packaged system. Electricity from the
engine generator is routed through the ATS/SLC and then passed on to the building or
utility grid. The exhaust heat recovery first goes to direct fire the double effect absorption
chiller as it needs the highest quality of heat. The exhaust is then used further to heat
domestic hot water. Both the chiller and domestic hot water systems can be bypassed if
there is no demand for heat. The low quality heat from the absorption chiller can be used
to preheat the incoming city water that will be used for domestic hot water. Part of the
chilled water from the absorption chiller is routed to the chilled water coil to provide
cooling and dehumidification for ventilation air. The coolant energy is used to heat
regeneration air for the desiccant dehumidification wheel or it can be rejected to
atmosphere.
129
Figure 44: CCHP/V Winter Operation Flow Diagram
Figure 44 shows the operation of CCHP/V system in the winter months. Similar to the
summer operation, the exhaust is first used in the domestic hot water system and then is
routed to the space heating system. The coolant energy is also used in the same heating
system. The ventilation system uses a heating coil to heat the ventilation air to its set
point after the enthalpy recovery wheel.
130
7.0 Contributions, Conclusions, and Future Work
7.1 Contributions
1. This dissertation includes the complete account of the preliminary design, detailed
design, installation, commissioning, test and evaluation of a biodiesel fueled CHP
system.
The partial load data is particularly important when applying CHP systems to high
performance buildings and developing an operating strategy. Typically, prime
mover manufacturers do not publish part load data as they believe this will reduce
their competitive advantage. However, part load data is necessary for designers of
CHP systems to make intelligent choices when selecting a prime mover.
The distillation of the 25 kWe operating data, as well as the method used for
estimating the part load data of the 200 kWe engine data may shed some light on
the part load of other engines, however it will not be as accurate as actual
measured data. This inaccuracy may lead to over or under sizing systems, further
discouraging the use of CHP systems.
2. A generic preliminary CHP design guide was developed to help novice CHP
designers determine what they need to know in general, and what type of
questions need to be asked.
131
There is currently a shortage of trained engineers who understand energy systems.
Therefore, it is important to provide documentation for new-comers to the field so
that they can start making a contribution right away rather than after years of
training. (The current energy problems this country and the world face will
provide employment for anyone who understands the potential solutions for many
years to come).
3. To further assist engineers in designing CHP systems to fit buildings, a generic
TRNSYS CHP model has been developed.
The model includes building load inputs from cooling, heating, and
dehumidification data files. These data files can come from either measured data
or simulation data. Using an empirical table lookup model based on the CHP
system operation; power level, fuel consumption, and temperatures and flow rates
for the exhaust and coolant streams are output.
Within the look table are the prime mover (engine generator) and the heat
recovery systems (steam generator and coolant heat exchanger). The model
controller allows for design operation of the CHP system as well as thermal load
follow (heating and cooling), and desiccant regeneration load follow.
4. An example of systems integration is explored for integrating an engine generator
with heat recovery, a double effect absorption chiller, and a ventilation system
132
with a solid desiccant wheel. There are a number of possible equipment
combinations for prime movers, heat recovery, and heat utilization.
While this dissertation just introduces the topic, it is hoped that other researchers
and equipment manufacturers will begin to design packaged systems that can
provide energy for approximately 75% of the building stock that is currently not
available to the CHP industry due to the small size of these buildings.
7.2 Conclusions
1. The CHP system operates most efficiently at its design load and when the system
can be tied to electric and thermal grids, which allow excess energy to be used by
other buildings. The 25 kWe CHP system was able to reach an average thermal
efficiency of 76% at its design electrical load. During intermediate seasons, the
coolant energy had to be rejected or the engine had to be operated at a lower
electrical load, therefore reducing efficiency to around 65%, which was reflected
in the TRNSYS simulations. Additional hot water loads for the coolant energy
should be developed, such as providing domestic hot water or exporting the hot
water to neighboring buildings.
2. The operation and evaluation of the CHP system has led to the discovery of many
issues that effect equipment selection. Operating CHP systems that have a coolant
loop tied to space heating by radiant systems introduces a problematic control
problem. The radiant heating system requires relatively low temperature water
(30-40
o
C), and the engine ideally operates at a higher temperature (80-90
o
C). The
133
installed IWESS CHP system needs an improved flow control system to maintain
higher coolant temperatures with its coolant heat exchanger. CHP system
designers need to be aware of this issue in order to operate the system efficiently.
A turbocharged Diesel engine may be a desirable prime mover selection; however
engineers need to be aware that backup power systems need to be modified to
prepare for part load operation. Furthermore, engine generator manufacturers
should be prepared to offer alternative turbochargers for CHP system designers
based on the operating profile of the CHP system.
3. Soy based biodiesel fuel was tested in the CHP system and compared to
petroleum based low sulfur Diesel fuel. Other than an increase in fuel
consumption due to the lower energy density of biodiesel fuel, the CHP system
performed similarly.
4. Design operation at peak connected with electrical and thermal grids is best for
maximizing efficiency. At the moment college campuses with electrical and
thermal grids appear to be the best fit for this technology as there is always a
demand for electricity, heating, cooling, and ventilation; the campus is always
occupied between classrooms, offices and dormitories. As the technology in
installed in more locations, the first and operating cost will be reduced, opening
additional markets.
134
5. The results from the IW and BAPP simulations lead to the conclusion that
additional thermal loads for the engine coolant must be sought. As CMU does not
have a campus hot water grid, two options are available to the mechanical systems
designers for the BAPP:
add a single effect absorption chiller to the system so that the medium
quality coolant energy can be used to create chilled water for the campus
grid.
integrate the BAPP hot water systems with neighboring buildings operated
in parallel with the steam grid.
Then first option is likely better as there is a chilled water grid so the entire
campus load is available whereas option two only offers heat to the immediately
adjacent buildings. If there is a sufficient budget available during the installation,
both should be included and tested.
7.3 Future Work
There are three main categories of future work. First, fully automating and integrating the
biodiesel fueled CHP system with the IWs daily operation. Second, provide design
support for the next CHP system on the Carnegie Mellon campus, most likely the BAPP.
Third, a path to commercialization for packaged CHP systems needs to be developed.
135
The automation and integration of the CHP system should be pursued in the next
development phase. Integrating the operation of the CHP system with inputs from the IW
including start up, power level, and shut down commands is necessary to show that this
CHP system can operate without direct user intervention. Additional tasks for the existing
CHP system include:
- The modeling of the current configuration of the CHP system, the absorption
chiller and the ventilation systems. The model and the physical system should be
upgraded to include domestic hot water provision, replacing the heat pump in the
ventilation system with hot and chilled water coils, and adding a single effect
chiller to recover exhaust heat. This represents the largest equipment cost savings
and heat utilization gain in the CCHP/V system.
- Fuel injection has been delayed approximately 15 degrees past top dead center in
the engine, which is causing late combustion. This was done intentionally to
reduce the combustion temperature and thus reducing NO
X
formation to meet
EPA regulation. Altering the engine timing should be explored when using
biodiesel fuels as the improved emissions may allow the engine to meet EPA
regulations with better combustion timing.
- The TRNSYS model does not allow for down time for maintenance. Statistics of
annual energy demands for the IW should be analyzed to determine the best time
frame of year for maintenance, when loads are near zero.
- Additional operational testing of the CHP system using a thermal load follow and
base load mode should be conducted. The engine will consume approximately
600 gallons of fuel per week.
136
- Additional emissions testing to fully characterize emissions including particulates
from various types of biodiesel fuel. Furthermore, the effect of engine timing on
emissions should be investigated as the engine does not currently operate at it
most efficient point.
- The long term effects of biodiesel fuel and continuous on the engine should be
explored and a maintenance program should be developed. There is a large body
of work already written for this topic, however it is typically meant for engines in
transportation applications. This testing will require a substantial fuel budget, but
facilities managers will be interested in the maintenance cycle of such systems.
For example, it is widely accepted that biodiesel fueled engines require less
frequent oil changes due to the increased lubricity of the biodiesel. In order to not
void the engines warranty, engine manufacturers will have to provide a reliable
maintenance program.
The next likely CHP project on the Carnegie Mellon campus is the Building As Power
Plant project. The following is a list of tasks and issues that should be resolved to aide in
the design and long term operation of the BAPP.
- As the simulation model of the BAPP is updated and design decisions are made,
the scaled up IWESS simulation file should be used to test various mechanical
system configurations and operational strategies in greater detail.
- Another addition to the TRNSYS model would be the ability to use multiple
engines using a modular approach to meeting the BAPPs loads. Instead of using
137
one 200 kWe engine, eight 25 kWe engine may be used or other combinations. A
modular CHP system allows for lower part load operation and/or higher
efficiency.
- A problem that will have to be tackled in the future if the BAPP concept is widely
accepted will be what happens with multiple BAPP facilities on a campus. The
current operational concept is based on few high performance buildings that
provide excess energy to other buildings that simultaneously heat and cool. Most
likely, modular CHP systems will be required as a campus filled with high
performance buildings and CHP systems will mimic the same issues of a single
CHP system in a single high performance building.
- A TRNSYS prime mover component design guide should be written so that prime
mover manufacturers can create component models for CHP system designers to
use in their simulations. It is not realistic for university researchers to install and
evaluate every type of prime mover and develop a component model. Prime
mover manufacturers will have detailed operating data for their products, which
could then be used to create TRNSYS components.
Finally, the CBPD should work to commercialize CHP systems by reducing the first costs
by a factor of 10 to 20. Figure 45 shows the complete cost break down by activity for the
design, procurement, installation, startup and commissioning of the CHP system for the
IW, which has a total cost of $675,781.47. That is $27,000 per kWe or if heat is included,
$11,000 per kW. The majority of the costs came from the complex installation process in
a building that did not easily accommodate the space requirements of this system.
138
Furthermore, as this is a first of a kind system, extra equipment, instrumentation and
controls were added to evaluate the system.
There is a lot of piping required to connect the engine generator with the steam generator
and the coolant heat exchanger. A significant part of the installation cost shown in Figure
45 can be attributed to long piping runs connecting the engine generator outputs to the
steam generator and the coolant heat exchanger. The remainder of the installation cost
includes electrical wiring for instrumentation and connecting the coolant heat exchanger
and steam generator outputs to the chiller, the IW, and the campus grids.
Biodiesel Fueled Engine Generator with Heat Recovery Cost Breakdown
Installation, $397,613.00,
60%
Other, $2,886.52, 0%
Capital Equipment,
$117,756.00, 17%
Engineering, $48,014.38, 7%
Instrumentation & Controls,
$90,818.85, 13%
Facilities, $18,692.72, 3%
Installation Other Capital Equipment Engineering Instrumentation & Controls Facilities
Figure 45: Cost Breakdown of CHP System
139
The cost of piping would still be necessary if the system were packaged and skid
mounted, but the runs could be much more compact than what is currently installed and
could be standardized. An installer would not have to work out connections between
separate components. Shorter pipe runs mean fewer pump and heat losses. Finally, fewer
connections to work out will reduce installation and engineering time, which are
expensive.
Another issue arises when combining many systems into a complex machine, the
operation of the system will become more complex. Research into user interfaces and
trouble shooting from the maintenance technicians and facilities managers points of
view should be investigated as ultimately they are the ones that must live with this system
on a daily basis.
The user interface and information gathered for the installed 25 kWe CHP system was
designed for the benefit of researchers. It likely that the quantity of information available
in the 25 kWe CHP would discourage maintenance technicians as they do not have the
time to sift through the large volumes of data generated by richly instrumented CHP
systems. Key data points should be identified that will benefit the users of the system.
Furthermore, having fewer data points will reduce the first cost of the CHP system.
Through standardization, systems integration and economies of scale a goal of reducing
first costs by a factor of 10 to 20 might well be realized.
140
References
1 Short-Term Energy and Summer Fuels Outlook. U.S. Department of Energy, Energy Information Agency.
http://www.eia.doe.gov/steo.
2 Electricity Flow, 2007 Energy Information Agency Annual Energy Review 2007, www.eia.doe.gov/
3 The Market and Technical Potential for Combined Heat and Power in the Commercial/Institutional
Sector. Prepared for U.S. Department of Energy, Energy Information Administration. Prepared by
ONSITE SYCOM Energy Corporation. J anuary 2000.
4 Market Potential for Advanced Thermally Activated BCHP in Five National Account Sectors. Prepared
for Oak Ridge National Laboratory. Prepared by Energy and Environmental Analysis, Inc. May 2003.
5 Market Potential for Advanced Thermally Activated BCHP in Five National Account Sectors. Prepared
for Oak Ridge National Laboratory. Prepared by Energy and Environmental Analysis, Inc. May 2003.
6 Diamond, Richard C. An Overview of the U.S. Building Stock. Lawrence Berkley National Laboratory.
J anuary 2001.
7 Power Scorecard. Pace University, Pace Law School Energy Project.
http://www.powerscorecard.org/tech_detail.cfm?resource_id=2
8 Casten, Thomas R. Turning Off The Heat: Why America Must Double Energy Efficiency to Save
Money and Reduce Global Warming. Prometheus Books, Amherst New York, 1998.
9 Ribarov L. A. and Liscinsky D. S., Microgrid Viability for Small-Scale Cooling, Heating, and Power,
J ournal of Energy Resources Technology -- March 2007 -- Volume 129, Issue 1, pp. 71-78.
10 Fumo N., Mago P. J ., and Chamra L. M., Evaluation of Cooling, Heating, and Power (CHP) Systems
Based on Building Energy-Rating, Energy Sustainability 2007, J une 2007, Long Beach, California USA.
11 Douglas M. E., Wagner T. C., Sahm M. K., and Wepfer W. J ., Economic Optimization of a Combined
Heating and Power System for an Office Building, Energy Sustainability 2007, J une 2007, Long Beach,
California USA.
12 Tucker C. T., Rethinking the Benefits of CHP, ASME Power, April 2005, Chicago, Illinois USA.
13 Betz, Fred, Chris Damm, David Archer, and Brian Goodwin. Biodiesel Fueled Engine Generator with
Heat Recovery. Proceedings of the 2008 ASME Energy Sustainability Conference. J acksonville, FL
August 2008. ES2008-54131.
14 U.S. Department of Energy, Oak Ridge National Laboratory, and Energy and Environmental Analysis,
Inc. Combined Heat and Power Installation Database. http://www.eea-inc.com/chpdata/
15 Discussion with Dr. Marc Portnoff. Director, Center for Advanced Fuel Technology, Carnegie Mellon
University.
16 Hennepin Energy Recovery Center (HERC):
http://www.co.hennepin.mn.us/portal/site/HCInternet/menuitem.3f94db53874f9b6f68ce1e10b1466498/?vg
nextoid=aad2c95fa29fc010VgnVCM1000000f094689RCRD
17 Herold, Keith E., Reinhard Radermacher, and Sanford A. Klein. Absorption Chillers and Heat Pumps.
CRC Press. 1996.
141
18 U.S. Department of Energy, Energy Efficiency and Renewable Energy. Appliances and Commerical
Equipment Standards: Commercial Unitary Air Conditioners and Heat Pumps.
http://www.eere.energy.gov/buildings/appliance_standards/commercial/ac_hp.html
19 Zhai, Chaoqin, David H. Archer, and J ohn C. Fisher. Integration Of The Active Desiccant Wheel In
CHP System Design . Proceedings of the 2008 ASME Energy Sustainability Conference. J acksonville, FL
August 2008. ES2008-54190.
20 Capstone Company Website. www.microturbine.com
21 Schmitt Enertec CHP Brochure/Specification Sheets. Provided by J im Sayre of Kraft Power.
22 PureComfort
TM
Brochure. United Technologies Company Power.
23 Ingersoll Rand Company Website. www.ingersollrand.com
24 U.S. Department of Energy. Energy Efficiency and Renewable Energy. Distributed Energy Program:
Distributed Energy Case Study Database. http://www.sentech.org/CaseStudy/
25 Unison Solutions, Inc. Site Visit to Sun Prairie, Wisconsin Waste Water Treatment Plant. March 12
th
2002.
26 J aaskelainen, Hannu E. and James S. Wallace. Operating Experience with a 240 kW Microturbine
Combined Heating, Cooling, and Power System. Proceedings of the 2008 ASME Energy Sustainability
Conference. J acksonville, FL August 2008. ES2008-54314.
27 Guider, T. P. Characterization of Engine Performance with Biodiesel Fuels. Masters Thesis, Lehigh
University. December 2008.
28 Department of Energy, Office of Energy Efficiency and Renewable Energy. 2004 Biodiesel Handling
and Use Guidelines.
29 National Biodiesel Board Published Biodiesel Emissions.
www.biodiesel.org/pdf_files/fuelfactsheets/emissions.PDF
30 Brown, J ack. Producing Biodiesel from Brassica Crops in the Pacific Northwest. National Biodiesel
Conference, San Diego, CA. February 6, 2006.
31 Yin, H. 2006, "An Absorption Chiller in a Micro BCHPApplication: Model Based Design and
Performance Analysis." PhD Thesis, Carnegie Mellon University, School of Architecture, 6 September.
32 Bell, Arthur A. HVAC Equations, Data, and Rules of Thumb. McGraw-Hill Professional; 1 edition,
J une 2, 2000.
33 Zhai, C., 2008, Performance Modeling of Desiccant Wheel Design and Operation, PhD Thesis, Carnegie
Mellon University.
34 Marion, Flore A., Sophie V. Masson, Frederik J . Betz, and David H. Archer. Cogeneration System
Performance Modeling Proceedings of the 2008 ASME Energy Sustainability Conference. J acksonville,
FL August 2008. ES2008-54256.
35 Masson, Sophie, Ming Qu, and David Archer. "Performance Modeling of A Solar Driven Absorption
Cooling System for Carnegie Mellon Universitys Intelligent Workplace. Proceedings of International
Conference of Enhanced Building Operation, 2006, Shenzhen, China.
142
36 Sophie Masson, Elisabeth Aslanian. TRNSYS Model of Hybrid Ventilation System. Internal Report.
Carnegie Mellon University CBPD.
37 Phone Discussion with Peter Rumsey of Rumsey Engineers regarding data center loads, 11:45 AM,
April 8
th
, 2009.
38 J ohn Deere 200 kWe specifications sheet for a 6.8L Diesel Engine, Model 6068HF485
143
Appendix
Appendix A: Steam System Schematic
Appendix B: CHP System Operating Log
Appendix C: IWESS Calculations for a Generic Building
Appendix D: Thermal Loss and Pressure Drop Calculations for the Steam System.
Appendix E: 25 kWe Engine Generator TRNSYS Look Up Table
Appendix F: 25 kWe Engine Generator TRNSYS Operating Data Files
Appendix G: 25 kWe and 200 kWe Engine Generator Specification Sheets
Appendix H: 200 kWe Engine Generator Look Up Table and TRNSYS Operating Data
Files
Appendix A: Steam System Schematics
Appendix B: CHP System Operating Log
Month Start Finish
Setpoints
(% of
25kWe)
Comments
Total
Time
[min]
Nov '07
11/1/2007
15:15
11/3/2007
15:35
100%
Complete thermo test with steam
generation
2900
11/29/200
7 10:20
11/29/2007
10:20
50% Failed start due to coolant leak 0
11/29/200
7 14:55
11/29/2007
15:05
50% Engine test after coolant topped off 10
11/29/200
7 17:00
11/29/2007
18:45
100%
Coolant temperature ramp up time
test
105
Dec '07
12/3/2007
14:30
12/3/2007
17:00
100% 150
12/7/2007
15:10
12/8/2007
15:10
100%
Complete thermo test with steam
generation
1440
12/12/200
7 10:55
12/12/2007
11:05
50% ABSIC Demo 10
12/18/200
7 10:45
12/18/2007
11:00
50% Engine test 15
J an '08
1/2/2008
11:15
1/2/2008
11:55
50%, 100% Engine test after winter break 40
1/11/2008
15:45
1/11/2008
17:20
50%, 75% Dilution tunnel testing 95
1/12/2008
11:50
1/12/2008
13:45
50%, 100% Dilution tunnel testing 235
1/15/2008
16:05
1/15/2008
17:45
50% Dilution tunnel testing 100
1/16/2008
14:20
1/16/2008
17:25
50% Dilution tunnel testing 185
1/17/2008
12:05
1/17/2008
12:35
50% Engine warmup for later test 30
1/17/2008
14:20
1/17/2008
15:30
50% Dilution tunnel testing 70
1/18/2008
12:30
1/18/2008
15:55
50%, 100%
50% filter test +exhaust bag at
100%
205
1/24/2008
13:30
1/24/2008
20:00
50%, 75%,
100%
Complete filter test +exhaust bag
at 75%
390
1/25/2008
13:30
1/25/2008
14:45
50% Dilution tunnel testing 75
1/31/2008
11:30
1/31/2008
19:45
50%, 75%,
100%
Coolant heat exchanger part load
test
490
Feb '08
2/5/2008
10:10
2/5/2008
16:30
50%
Complete filter test +exhaust bag
at 50%
380
2/15/2008
14:25
2/15/2008
17:00
75%
Test engine after turbocharger
installation
155
2/19/2008
13:15
2/19/08
16:50
75% Filter test at 75% 215
2/21/2008
11:45
2/21/2008
17:25
75%, 100%
Turbocharger test and filter sample
test
340
2/28/2008
11:45
2/28/2008
19:30
50%, 75%,
100%
Pressure-Time experimental setup
test
585
Mar '08
3/5/2008
10:40
3/5/2008
21:45
25%, 50%,
75%, 100%
Complete thermo test with steam
generation
665
Apr '08
4/14/2008
13:25
4/14/2008
14:35
100% Engine test 60
4/16/2008
16:05
4/16/2008
17:50
100% Weigh Tank Test 105
May '08
Engine did not run during the month of May due to coolant system controls
malfunctions. 0
J un '08
6/5/2008
16:40
6/5/2008
17:10 50%
First engine test after coolant
control sys. repair 30
6/6/2008
17:05
6/6/2008
17:20 50%
Failed engine test due to coolant
control 10
6/6/2008
18:30
6/6/2008
18:40 50%
Failed engine test due to coolant
control 10
6/7/2008
11:30
6/7/2008
15:30
25%, 50%,
75%, 100% Engine coolant control system test 240
6/12/2008
12:05
6/6/2008
14:00 50%, 100% Engine coolant control system test 115
J ul '08
7/18/2008
14:55
7/18/2008
14:55 50% Failed engine test 5
7/18/2008
15:30
7/18/2008
16:55 50%
Engine Generator Demo for tour
group 85
7/26/2008
13:35
7/18/2008
18:25
25%, 50%,
75%, 100% Engine coolant control system test 290
7/30/2008
18:35
7/30/2008
23:55
25%, 50%,
75%, 100% Turbocharger Test 320
Aug '08
8/1/2008
11:45
8/1/2008
11:55 50%
Engine Generator Demo for tour
group 10
8/4/2008
10:45
8/6/2008
18:10 50%, 100% CHP +Absorption Chiller Test 3325
8/7/2008
11:20
8/7/2008
11:25 50% Failed engine test 5
8/21/2008
16:20
8/21/2008
17:10 50%
Engine cylinder pressure data
acquisition test 50
Sep '08
9/8/2008
15:50
9/8/2008
17:00 50%
Engine cylinder pressure data
acquisition test 70
9/23/2008
13:55
9/23/2008
17:30 50%, 100%
Testing cylinder pressure data
acquisition sytem 215
Oct '08
10/9/2008
14:25
10/9/2008
17:10 50%, 75% Transition to Biodiesel Fuel 165
10/14/200
8 12:00
10/15/2008
16:05
25%, 75%,
100%
Complete thermo test with steam
generation 1685
10/22/200
8 13:45
10/22/2008
19:25
25%, 50%,
75%, 100%
Testing for ME IC Engines lab
preparation 220
Nov '08
11/4/2008
14:00
11/4/2008
16:00 50%
Mechanical Engineering IC
Engines Lab 120
11/7/2008
9:20
11/4/2008
11:00 100%
Mechanical Engineering IC
Engines Lab: Failed 100
11/7/2008
11:35
11/7/2008
13:25 50% Engine warmup for later test 110
11/7/2008
13:50
11/7/2008
15:10 75%
Mechanical Engineering IC
Engines Lab 80
11/12/200
8 15:00
11/12/2008
17:30 100%
Makeup for ME IC Engines Lab
11-7-08 150
Dec '08
12/10/200
8 14:40
12/10/2008
15:25 50%
Demo for City of Pittsburgh
Engineers 45
12/18/200 12/21/2008 25%, 50%, Full Biodiesel Experiment 4775
8 11:40 19:15 75%, 100%
J an '09
1/12/2009
14:05
1/12/2009
15:20 50% Demo for Duetsche Welle reporter 15
Feb '09
2/26/2009
15:00
2/26/2009
16:15 50%, 100% Weigh Tank Test 75
2/27/2009
14:50
2/27/2009
17:30
25%, 50%,
75%, 100% Weigh Tank Test 160
Mar '09
3/11/2009
16:35
3/11/2009
16:45 50%
Engine Demo for Green Building
Alliance 10
Apr '09
4/2/2009
14:25
4/2/2009
14:45 50% Monthly Engine Test 20
4/14/2009
15:45
4/14/2009
19:35
25%, 50%,
75%, 100%
Transition back to Diesel Fuel /
Emissions Test 230
4/20/2009
11:10
4/20/2009
11:50 50% Pressure-Time experiment 40
4/20/2009
13:35
4/20/2009
14:25
25%, 50%,
75%, 100%
Pressure-Time experiment /
Emissions Test 50
Site Thermal Electrical
Space
Heating
Ventilation
Heating
Water
Heating
Cooling
Ventilation
Cooling
Cooling Cooking Ventilation Lighting Refrigeration
Office
Equipment
Other
Notes
Consumption (kBTU/ft2-Year) 101.2 44.2 57.0 33.2 0.0 11.0 0.0 0.0 11.4 1.4 6.1 18.9 0.3 11.1 7.8 Reference [1]
Consumption (kWh/m2-Year) 319.3 139.4 179.8 104.7 0.0 34.7 0.0 0.0 36.0 4.4 19.2 59.6 0.9 35.0 24.6 Conversion to Metric
Thermal & Electrical Loads 369.6 226.6 143.0 83.8 0.0 27.8 115.1 0.0 0.0 3.5 19.2 59.6 0.9 35.0 24.6 Assumptions 2 and 3
Separate Space/Ventilation Heating/Cooling 369.6 226.6 143.0 71.2 12.6 27.8 97.8 17.3 0.0 3.5 19.2 59.6 0.9 35.0 24.6 Assumption 4
Hydronic Energy Distribution 354.1 226.6 127.4 71.2 12.6 27.8 97.8 17.3 0.0 3.5 2.9 59.6 0.9 35.0 25.4 Assumption 5
Enthalpy Recovery 333.2 205.8 127.4 71.2 3.8 27.8 97.8 5.2 0.0 3.5 2.9 59.6 0.9 35.0 25.4 Assumption 6
Absorption Cooling 323.8 196.4 127.4 71.2 3.8 27.8 88.9 4.7 0.0 3.5 2.9 59.6 0.9 35.0 25.4 Assumption 7
Thermal & Electrical Demands 323.8 196.4 127.4 Total each category
CHP Applied to Electrical & Heating Requirements -0.8 0.0 -0.8 Assumption 8
IWESS Reductions = 47.4%
CHP (DG+Ventilation+Chiller) = 43.2% As can be seen, the majority of the energy reduction using the IWESS strategy comes from integration of heating, cooling, ventilation, and power
Assumptions:
1) Average consumption for a standard VAV commercial installation using natural gas and electricity. Other includes elevators and pumps.
2) Load: Average boiler, burner efficiency is 80%, therefore the actual load for space heating, water heating and cooking is 20% lower than the consumption [2].
3) Load: Average Chiller COP is 3.2 [3]
4) Separation: Space heating and cooling is separated from ventilation.15% of space heating and cooling goes into heating and cooling ventilation air [4].
5) Hydronic: Applying a hydronic heating and cooling distribution system rather than a ducted system reduces ventilation fan power by 85% as stated in step 3.
Further,the energy consumed by the fans is for heating and cooling is reduced by 95% and added to other [5,6]
6) Enthalpy: Use of an enthalpy recovery wheel on the ventilation air reduces the heating and cooling loads by 70% [7]
7) Absorption: Absorption Chillers are used to cover the cooling load, which changes the electrical input for the chillers to a thermal input using a COP of 1.1 [8]
8) DG+CHP: A cogeneration system is applied to cover the high temperature heat loadof 93.6 kWh/m2-year. Based on measured data the proportional amount of electricity
generated would be 128.2 kWh/m2-year and 110.5 kWh/m2/year of low temperature heat. The excess coolant heat is is dumped to atmosphere and the excess electricity
is exported to the grid [9].
References:
[1] 1992 Commercial Buildings Energy Consumption Survey, Table 2. Energy End-Use Intensities for All Major Fuels 1992
[2] http://www.eere.energy.gov/buildings/appliance_standards/residential/pdfs/furnaces_boilers/furnaces_fr_111907.pdf
[3] http://www.eere.energy.gov/buildings/appliance_standards/commercial/ac_hp.html
[4] "Hydronic Radiant Heating and Cooling", Lawrence Berkeley National Laboratory, Environmental Energy Technologies, Indoor Environment Department, Energy
Performance of Buildings Group. http://epb.lbl.gov/thermal/hydronic.html
[5] Feustel, Helmut E. and Corina Stetiu, "Hydronic Radiant Cooling - Preliminary Assessment". Energy and Buildings 22 (1995) 193-205
[6] Archer, David H and Fred Betz, "Comparision of Hydronic and Air Based Sensible Heat Transport". Carnegie Mellon University, CBPD 2008.
[7] Chaoqin's Dissertation
[8] Hongxi's Dissertation
[9] Betz, Fred, "Biodiesel Fueled Engine Generator with Heat Recovery Status Update". ABSIC Meeting at CMU. 12-12-07.
-0.8
A
p
p
e
n
d
i
x
C
:
I
W
E
S
S
S
y
s
t
e
m
C
a
l
c
u
l
a
t
i
o
n
s
0.0
102.8
-7.7
Energy Intensity
Total Energy
93.6
Low Temp. Thermal High Temp. Thermal Electrical
127.4
Heat Loss of Steam Carried Through Pipe
7/9/2007
Problem Statement
Determine the heat loss from steam at 160C (320F) carried at 29.5 kg/hr (65 lb/hr) through a
1.5 inch (0.0381 m) pipe for summer design conditions.
Find
TOTAL
Q
&
Schematic
Assumptions
Free convection only.
o Interior, pipe is inside the building.
o Exterior, pipe is surrounded by copper sheathing for 18 of 24 meters.
1
Given
Inner Pipe Diameter =1.61 in (0.041 m)
Outer Pipe Diameter =1.90 in (0.0483 m)
Insulation Thickness =2.50 in (0.0635 m)
Copper Sheath Thickness =1/16 in (0.0625 m)
Flow Rate =29.5 kg/hr (65 lb/hr)
Temperature =160C (320F)
Pipe Conductivity =56 W/m
o
K
Insulation Conductivity =0.055 W/m
o
K
J acket Conductivity =0.07 W/m
o
K
Calculations
hot cold
steam interior steam exterior
interior exterior
TOT
T T Q
R
T T T T Q
R R
=
= +
&
l
&
l
Note: Calculations being done on a unit length of one meter.
( )
( ) ( )
( )
pipe,out pipe,in insul,out pipe,out
interior
steam pipe,in pipe room insul,out insul
pipe,out pipe,in
exterior
steam pipe,in pipe room insul,out
ln /
1
2 2
ln / ln /
1 1
2 2 2 2
ln /
1 1
2 2 2
out in
r r
R
h r k
r r r r
R
h r k h r k
r r
R
h r k h r
= +
= + + +
= + +
( )
insul,out jacket,out
sheath jacket,out jacket
ln /
1
2 2
r r
h r k
+ +
I nterior
( ) ( )
4
5
4
5
steam
steam steam
pipe
3
W
steam mK
pipe
0.3
steam
6
6
0.3
steam
steam
28 10
0.0409 m
0.023Re Pr
Re 17290 (from pressure drop calculation)
28 10
Pr 1.02
27.5 10
0.023 17290 1.02
56.8
k
h Nu
D
k
D
Nu
Nu
Nu
=
=
=
=
=
= = =
=
=
2
[ ] ( )
[ ]
( ) ( )
[ ] ( )
2
2
steam
steam steam
pipe
W
steam
m K
mK
steam W
W W
steam pipe,in mK
m K
pipe,out pipe,in
mK
pipe W
W
pipe mK
insul
38.9
1 1 1
0.20
2 5.00 38.9 2 0.02045 m
ln /
ln 0.02413/0.02045
0.1655
0.000047
2 351.9 2 56
k
h Nu
D
h
R
h r
r r
R
k
R
=
=
= = = =
= = = =
=
( ) ( )
[ ] ( )
insul,out pipe,out
mK
W
W
insul mK
ln /
ln 0.08763/ 0.02413
1.29
3.73
2 0.346 2 0.055
r r
k
= = =
( )
2
air,int
insul,out
rd
W
m K
mK
air,int W
mK
interior steam pipe insul air,int W
int
1
2
18.26 (McAdams, Heat Transmission 3 Edition)
1 1
0.10
18.26 2 0.08763 10.06
0.20 0.00047 3.73 0.10 4.035
air
air
R
h r
h
R
R R R R R
q
=
=
= = =
= + + + = + + + =
=
( )
o o
W
m
int
160 C 25 C
33.5
4.035
1.874 W Q
=
=
Exterior
steam exterior
exterior
exterior steam pipe insul jacket air gap sheath air sheath air,ext
T T Q
R
R R R R R R R R R
=
= + + + + + + +
l
Note: R
sheath
only applies for 18 m of 24 m run R
air,ext
for 6 m.
( ) ( )
[ ] ( )
mK
steam W
mK
pipe W
mK
insul W
jacket,out insul,out
mK
jacket W
W
jacket mK
0.20
0.0005
3.73
ln /
ln 0.08843/0.08763
0.0091
0.201
2 0.440 2 0.07
R
R
R
r r
R
k
=
=
=
= = = =
3
air gap
air gap jacket,out
air gap
3
W
mK
2
1/6
8/27
9/16
1
(model as vertical plate)
2
26.3 10
0.387
0.825
0.492
1
Pr
L
L
L
R
h r
Nu k
h
L
k
Ra
Nu
=
=
=
= +
+
( )
6
6
3
2
15.86 10
Pr 0.705
22.5 10
Pr
L L
s
L
Ra Gr
g T T L
Gr
= = =
=
2
2
-6
m
sec
m
sec
o
o
K
1 m (unit length)
15.86 10
9.81
25 C
28 C based on estimated surface temperature from interior heat transfer calculation
1/ 1/ 298 K 0.0034
s
f
L
g
T
T
T
=
=
=
=
=
= = =
( ) ( ) ( )
( )
2
2
3
3 m
K
sec
2 2
6
m
sec
9.81 0.0034 28 25 K 1 m
15.86 10
392615673
s
L
g T T L
Gr
= =
=
( )( )
2
1/6
8/27
9/16
Pr 392615673 0.705 276794049
0.387
0.825 82.9
0.492
1
Pr
L
L L
L
Ra Gr
Ra
Nu
=
= = =
= + =
+
4
( )
2
3
W
mK
W
air gap
m K
mK
air gap W
sheath
sheath
sheath sheath
82.9 26.3 10
2.18
1 m
1 1
0.83
2.18 2 0.08843 1.21
L
Nu k
h
L
R
t
R
k A
= = =
= = =
=
2
length
sheath
W
sheath mK
m
m sheath
sheath
0.00159 m
401
1.321
0.00159
0
4011.321
t
k
A
R
=
=
=
=
air
air sheath
air
3
W
mK
1
26.3 10
1 m
L
R
h A
Nu k
h
L
k
L
=
=
=
=
2
1/6
8/27
9/16
6
6
0.387
0.825
0.492
1
Pr
15.86 10
Pr 0.705
22.5 10
L
L
Ra
Nu
= +
+
= = =
( )
3
2
Pr
L L
s
L
Ra Gr
g T T L
Gr
=
2
m
sec
K
o
9.81
1 m
0.0034
28 C
s
g
L
T
=
=
=
=
5
2
o
6
m
sec
25 C
15.86 10
392615673
276794049
L
T
Gr
Ra
=
=
=
=
( )
3
air
82.9
82.9 26.3 10
2.18
1
L
L
Nu
Nu k
h
L
= = =
2
mK
air,sheath W
air sheath
air,ext
air jacket,out
rd
W
air,out
m K
1 1
0.347
2.18 1.321
1
2
18.26 (McAdams, Heat Transmission 3 Edition)
R
h A
R
h r
h
= = =
=
=
18 6
18
mK
air,ext W
Exterior Exterior steam pipe insul jacket air gap sheath air,sheath air,ext
Exterior steam pipe insul jacket air gap sheath air,sheath
Exterio
1
0.10
18.26 2 0.08843
R
R R R R R R R R R R
R R R R R R R R
R
= =
+ = + + + + + + +
= + + + + + +
6
r steam pipe insul jacket air,ext
R R R R R = + + + +
( ) ( )
18
6
18 6
mK
Exterior W
mK
Exterior W
Exterior Exterior
0.20 0.00 3.73 0.20 0.83 0.00 0.35 5.31
0.20 0.00 3.73 0.20 0.10 4.23
18 m 6 m
steam exterior steam exterior
ext
R
R
T T T T
Q
R R
= + + + + + + =
= + + + + =
= +
&
interior exterior
140 18 140 6
674W
5.31 4.23
1874W 674W 2.5 kW
ext
tot
Q
Q Q Q
= + =
= + = + =
&
& & &
6
Determination of Steam Pipe Pressure Drop
6/18/2007
Problem Statement
Determine the pressure drop from the outlet of the steam generator to the absorption chiller inlet.
Given
kg
lb
hr hr
length, 260 ft (79.25 m)
No. of bends 18
Pipe diameter, 1.61 in
Pressure, 87 psig
Rise, 90 ft
Mass flow rate, 65 (29.5 )
D
P
z
m
=
=
=
=
=
=
l
&
3
kg
msec
kg
m
0.000015
3.667
0.000 15 ft
No. of valves 5, includes 1 stop check
No. of tees 1
=
=
=
=
=
Schematic
Assumptions
1. There are no leaks in the pipe
2. Steam is saturated
3. Pipe material is commercial steel
4. Pipe bends are regular 90, threaded
5. Four valves are gate valves, fully open
1
Calculations
( )
3
3
3
2
2
2 2
3
lb
3 3
ft
lb
hr ft ft
hr sec 2
lb
ft
lb ft
sec
ft
1.61 in
2.04 in 0.014 ft
4 4
3.667 kg 2.2 lb m
0.23
m kg 35.31 ft
65
velocity, 20 186 5.61
0.23 0.014 ft
0.23 5.61 0.134 ft
Reynolds No., Re
1
m VA
D
A
m
V
A
VD
=
= = = =
= =
= = = =
= =
&
&
&
-5
lb
ft sec
5
lb
ft sec
17 290
10
kg 2.2 lb m
0.000 015 1.0 10
msec kg 3.28 ft
= =
Moody Diagram
( )( )
3
3 4
3
4
f
2
2
2
2
lb ft lbft
sec
ft ft sec
lbft
lb
ft sec
ft ft
sec
0.001 12
0.029
1
2
260 ft 1
0.029 0.23 5.61 203.65
0.134 ft 2
203.65
6.33 0.044 0 psi 303 Pa
32.17
F
F
F
D
f
p f V
D
p
p
=
=
=
= =
= = = =
l
Rise losses
( )( )( )
f
3 2 2
lb
lb ft
ft sec ft
0.23 32.2 90 ft 666.54 4.63 psi 32 kPa
z
p gz = = = = =
Minor losses
2
1
2
L
p K V =
Type K
L
Qty
90 threaded bend 1.5 18
Threaded tee 2.0 1
Stop Check Valve 2.0 1
Gate Valve 0.15 4
( ) ( ) ( ) ( ) 1.5 18 2.0 1 2.0 1 0.15 4 31.6
L
K = + + + =
2
( )( )
2
3 3 2
2
3 2
f
2
2
2
lb ft ft lb
sec
ft ft sec
ft lb
lb
ft sec
ft ft
sec
1
31.6 0.23 5.61 114.4
2
114.4
3.55 0.025 psi 170 Pa
32.2
0.044 psi 4.63 psi 0.025 psi 4.70 psi 32.4 kPa
m
m
TOT F z m
p
p
p p p p
= =
= = = =
= + + = + + = =
3
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 82.2 82.2 82.2 25% 119.2 149.2 168.9
50% 83.3 84.4 85 50% 175.1 210.6 231.8
75% 85 85.1 85.3 75% 256.0 323.6 366.8
100% 85.6 85.7 86 100% 386.2 484.9 553.9
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 35.5 44.8 49.1 25% 119.2 149.2 168.9
50% 34.2 43.5 47.8 50% 175.1 210.6 231.8
75% 40.5 49.8 54.1 75% 256.0 323.6 366.8
100% 44.8 53.1 57.4 100% 386.2 484.9 553.9
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 40.0 49.3 53.6 25% 545.1 545.1 545.1
50% 43.2 52.5 56.8 50% 545.1 545.1 545.1
75% 49.5 58.8 63.1 75% 545.1 545.1 545.1
100% 55.8 65.1 69.4 100% 545.1 545.1 545.1
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 232 232 232 25% 138 138 138
50% 312 312 312 50% 144 144 144
75% 410 410 410 75% 153 153 153
100% 503 503 503 100% 165 165 165
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 125 125 125 25% 7.1
50% 125 125 125 50% 13.5
75% 125 125 125 75% 20.9
100% 125 125 125 100% 29.7
A
p
p
e
n
d
i
x
E
:
2
5
k
W
e
T
R
N
S
Y
S
L
o
o
k
U
p
T
a
b
l
e
s
Winter Operation
Hot water outlet Temperature (C)
Coolant Engine FR (kg/hr)
Coolant heat exchanger FR (kg/hr)
Coolant engine outlet Temperature (C)
Hot water HX FR (kg/hr)
Coolant heat exchanger outlet Temperature (C)
Exhaust Temperature (C) Exhaust FR (kg/hr)
steam Temperature (SG outlet) (C) steam FR (SG outlet) (kg/hr)
power prod small bldg load medium bldg load high bldg load
25% 35.5 44.8 49.1
50% 34.2 43.5 47.8
75% 40.5 49.8 54.1
100% 44.8 53.1 57.4
power prod small bldg load medium bldg load high bldg load
25% 81.7 81.7 81.7
50% 82.8 83.9 84.5
75% 84.5 84.6 84.8
100% 85.1 85.2 85.5
power prod small bldg load medium bldg load high bldg load
25% 27.4 36.7 41
50% 27.4 36.7 41
75% 27.4 36.7 41
100% 27.4 36.7 41
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 128 128 128 25% 197 163 128
50% 128 128 128 50% 251 189 128
75% 128 128 128 75% 316 222 128
100% 128 128 128 100% 378 253 128
power prod small bldg load medium bldg load high bldg load
25% 2.4 2.4 2.4
50% 2.4 2.4 2.4
75% 2.4 2.4 2.4
100% 2.4 2.4 2.4
Stack Exhaust Temperature (C)
Coolant heat exchanger intlet Temperature (C)
Winter Operation
Coolant engine intlet Temperature (C)
Hot water intlet Temperature (C)
steam Pressure (SG outlet) (Bar)
SG Outlet Exhaust Temperature (C)
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 95 95 95 25% 3113 3113 3113
50% 95 95 95 50% 3113 3113 3113
75% 95 95 95 75% 3113 3113 3113
100% 95 95 95 100% 3113 3113 3113
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 93 93 93 25% 1038 2075 3113
50% 92 92 92 50% 1038 2075 3113
75% 91 91 91 75% 1038 2075 3113
100% 89 89 89 100% 1038 2075 3113
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 93 93 ambient 25% 2075 1038 0
50% 92 92 ambient 50% 2075 1038 0
75% 91 91 ambient 75% 2075 1038 0
100% 89 89 ambient 100% 2075 1038 0
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 92 92 92 25% 204 408 612
50% 92 92 92 50% 355 710 1064
75% 92 92 92 75% 469 939 1408
100% 92 92 92 100% 649 1297 1946
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 234 234 234 25% 138 138 138
50% 320 320 320 50% 144 144 144
75% 421 421 421 75% 153 153 153
100% 515 515 515 100% 165 165 165
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 160 160 160 25% 0 anything 6.9
50% 160 160 160 50% 0 anything 13.8
75% 160 160 160 75% 0 anything 20.7
100% 160 160 160 100% 0 anything 31.1
Summer Operation
Coolant Engine FR
Coolant heat exchanger outlet Temperature Coolant heat exchanger FR
Coolant engine outlet Temperature
steam Temperature (SG outlet) steam FR (SG outlet)
Hot water outlet Temperature Hot water HX FR
Exhaust Temperature Exhaust FR
Coolant radiator outlet temperature Coolant Radiator FR
power prod small bldg load medium bldg load high bldg load
25% 93 93 93
50% 92 92 92
75% 91 91 91
100% 89 89 89
power prod small bldg load medium bldg load high bldg load
25% 95 95 95
50% 95 95 95
75% 95 95 95
100% 95 95 95
power prod small bldg load medium bldg load high bldg load
25% 95 95 ambient
50% 95 95 ambient
75% 95 95 ambient
100% 95 95 ambient
power prod small bldg load medium bldg load high bldg load
25% 83 83 83
50% 83 83 84
75% 84 84 84
100% 84 84 84
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 165 165 165 25% 211 188 165
50% 165 165 165 50% 268 217 165
75% 165 165 165 75% 336 250 165
100% 165 165 165 100% 398 282 165
power prod small bldg load medium bldg load high bldg load
25% 6 6 6
50% 6 6 6
75% 6 6 6
100% 6 6 6
Summer Operation
Coolant heat exchanger intlet Temperature
Coolant engine intlet Temperature
steam Pressure (SG outlet) (bar)
Hot water intlet Temperature
SG Outlet Exhaust Temperature (C) Stack Exhaust Temperature (C)
Coolant radiator inlet temperature
Appendix F: TRNSYS Engine Data Files
Engine File
40 90 !hot water set point temperature
20000 50000 80000 !building load
25 50 75 100! electric load
35.52167757 119.1914489 82.2 81.7 119.1914489 35.52167757 0 0
0!Coolant engine intlet Temperature Coolant Engine FR Coolant engine outlet
Temperature Coolant heat exchanger intlet Temperature Coolant heat exchanger FR Coolant
heat exchanger outlet Temperature Coolant radiator inlet temperature Coolant Radiator FR Coolant
radiator outlet temperature
34.17709697 175.1046126 83.3 82.8 175.1046126 34.17709697 0 0
0
40.48793575 255.9781135 85 84.5 255.9781135 40.48793575 0 0
0
44.79877454 386.2456484 85.6 85.1 386.2456484 44.79877454 0 0
0
44.82167757 149.2492281 82.2 81.7 149.2492281 44.82167757 0 0
0
43.47709697 210.6255108 84.4 83.9 210.6255108 43.47709697 0 0
0
49.78793575 323.6270363 85.1 84.6 323.6270363 49.78793575 0 0
0
53.09877454 484.9089944 85.7 85.2 484.9089944 53.09877454 0 0
0
49.12167757 168.9485752 82.2 81.7 168.9485752 49.12167757 0 0
0
47.77709697 231.8469919 85 84.5 231.8469919 47.77709697 0 0
0
54.08793575 366.8306073 85.3 84.8 366.8306073 54.08793575 0 0
0
57.39877454 553.9321757 86 85.5 553.9321757 57.39877454 0 0
0
93 3113 95 95 1038 93 95 2075 93
92 3113 95 95 1038 92 95 2075 92
91 3113 95 95 1038 91 95 2075 91
89 3113 95 95 1038 89 95 2075 89
93 3113 95 95 2075 93 95 1038 93
92 3113 95 95 2075 92 95 1038 92
91 3113 95 95 2075 91 95 1038 91
89 3113 95 95 2075 89 95 1038 89
93 3113 95 95 3113 93 20 0 20
92 3113 95 95 3113 92 20 0 20
91 3113 95 95 3113 91 20 0 20
89 3113 95 95 3113 89 20 0 20
Exhaust and Hot Water Engine File
40 90
20000 50000 80000
25 50 75 100
27.4 545.1 40.02167757 138 232
27.4 545.1 43.17709697 144 312
27.4 545.1 49.48793575 153 410
27.4 545.1 55.79877454 165 503
36.7 545.1 49.32167757 138 232
36.7 545.1 52.47709697 144 312
36.7 545.1 58.78793575 153 410
36.7 545.1 65.09877454 165 503
41 545.1 53.62167757 138 232
41 545.1 56.77709697 144 312
41 545.1 63.08793575 153 410
41 545.1 69.39877454 165 503
83 204 92 138 234
83 355 92 144 320
84 469 92 153 421
84 649 92 165 515
83 408 92 138 234
83 710 92 144 320
84 939 92 153 421
84 1297 92 165 515
83 612 92 138 234
84 1064 92 144 320
84 1408 92 153 421
84 1946 92 165 515
Appendix G: 25 kWe and 200 kWe Engine Generator Specifications
Engine Performance Curves 4024 - Generator June 2004
Air Intake Restriction ................... 12 in.H
2
O (3 kPa)
Exhaust Back Pressure ........... 30 in.H
2
O (7.5 kPa)
Gross power guaranteed within + or - 5% at SAE J1995
and ISO 3046 conditions:
77 F (25 C) air inlet temperature
29.31 in.Hg (99 kPa) barometer
104 F (40 C) fuel inlet temperature
0.853 fuel specific gravity @ 60 F (15.5 C)
Conversion factors:
Power: kW = hp x 0.746
Fuel: 1 gal = 7.1 lb, 1 L = 0.85 kg
Torque: Nm = lb-ft x 1.356
All values are from currently available data and are subject
to change without notice.
Ref: Engine Emission Label
Tier-2 Emission Certifications: Certified by:
Notes:
ENGINE PERFORMANCE CURVE
- PRIME * - STANDBY *
10
(4.5)
20
(9)
30
(14)
F
u
e
l
-
-
l
b
/
h
r
(
k
g
/
h
r
)
20
(15)
10
(7)
40
(30)
30
(22)
35
(26)
45
(34)
15
(11)
25
(19)
Brake Power -- hp (kW)
PowerTech 2.4L Engine
Model: 4024TF270
43 hp (32 kW) Prime
48 hp (36 kW) Standby
Rating: Gross Power
Application: Generator
1800 RPM (60 Hz)
* Revised Data
Curve 4024TF270180048................................ Sheet 1 of 2
November 2003
Nominal Engine Power @ 1800 RPM
Prime Standby
HP kW HP kW
43 32 48 36
Generator
Efficiency
1
%
Fan Power
Power
Factor
Prime Rating
Standby
Rating
2
4 sec Standby
Block Load
Capability
3
hp kW kWe kVA kWe kVA
88* 2.4* 1.8* 0.8 27 34 30 38 100%
Note 1: Est. min. generator efficiency, with 5% fan power loss, to achieve Prime kVA (1500 rpm) / Standby kWe (1800 rpm).
Note 2: Based on nominal engine power.
Note 3: Results may vary by alternator and voltage regulator selection.
CARB; EPA
Engine Performance Curves 4024 - Generator June 2004
Engine Specification Data
All values at rated speed and power with standard options unless otherwise noted.
General Data
Model ................................................................4024TF270
Number of Cylinders ......................................................... 4
Bore and Stroke--in.(mm)..................... 3.4 x 4.1 (86 x 105)
Displacement--in.
3
(L) ...........................................149 (2.4)
Compression Ratio ................................................20.5 : 1*
Valves per Cylinder--Intake/Exhaust ............................ 1 / 1
Firing Order............................................................. 1-3-4-2
Combustion System.................................... Direct Injection
Engine Type................................................ In-line, 4-Cycle
Aspiration...................................................... Turbocharged
Engine Crankcase Vent System ................................ Open
Maximum Crankcase Pressure--in.H
2
O (kPa) ..........2 (0.5)
Physical Data
Length--in.(mm) ..................................................26.1 (662)
Width--in.(mm) .................................................. 22.3 (566)*
Height--in.(mm) ...................................................30.4 (772)
Weight, dry--lb (kg)...............................................553 (251)
(Includes flywheel housing, flywheel & electrics)
Center of Gravity Location
From Rear Face of Block (X-axis)--in.(mm)....7.6 (194)
Right of Crankshaft (Y-axis)--in.(mm) ...............0.6 (14)
Above Crankshaft (Z-axis)--in.(mm) ...............4.3 (108)
Max. Allow. Static Bending Moment at Rear
Face of Flywhl Hsg w/ 5-G Load--lb-ft (Nm) ....369 (500)
Thrust Bearing Load Limit (Forward)
Continuous--lb (N) ..................................... 1147 (5100)
Intermittent--lb (N)........................................629 (2800)
Air System Prime Standby
Maximum Allowable Temp Rise--Ambient Air to
Engine Inlet--F (C) ......................... 15 (8) ........15 (8)
Maximum Air Intake Restriction
Dirty Air Cleaner--in.H
2
O (kPa).... 25 (6.25) ...25 (6.25)
Clean Air Cleaner--in.H
2
O (kPa)....... 12 (3) ........12 (3)
Engine Air Flow--ft
3
/min (m
3
/min) ....... 99 (2.8)* . 106 (3.0)*
Intake Manifold Pressure--psi (kPa)....... 9 (64)* .....11 (75)*
Cooling System Prime Standby
Eng. Heat Rejection--BTU/min (kW)..1303 (23) .. 1412 (25)
Coolant Flow--gal/min (L/min).............24* (91*) ... 24* (91*)
Thermostat Start to Open--F (C) .......180 (82) .... 180 (82)
Thermostat Fully Open--F (C)...........201 (94) .... 201 (94)
Maximum Water Pump
Inlet Restriction--in.H
2
O (kPa) ...........28 (7) ........ 28 (7)
Engine Coolant Capacity--qt (L) ..........2.7 (2.6) .... 2.7 (2.6)
Recmd Pressure Cap--psi (kPa) ...........10 (69) ...... 10 (69)
Maximum Top Tank Temp--F (C) .. 221 (105)* .221 (105)*
Min. Coolant Fill Rate--gal/min (L/min) 2.5 (9.5) .... 2.5 (9.5)
Min. Air-to-Boil Temperature--F (C) .. 117 (47) .... 117 (47)
Electrical System 12 Volt 24 Volt
Recmd. Battery Capacity (CCA)--amp............750 ...... N/A
Max. Allow. Starting Circuit Resist.--Ohm...0.0012 ...... N/A
Starter Rolling Current
At 32 F ( 0 C)--amp...................................290 ...... N/A
At -22 F (-30 C)--amp ...............................370 ...... N/A
Exhaust System Prime Standby
Exhaust Flow--ft
3
/min (m
3
/min)......... 261 (7.4)* ...283(8.0)*
Exhaust Temperature--F (C) ...... 963(517)* ...1026 (552)*
Max. Allow. Back Press.--in.H
2
O (kPa).30 (7.5) ..... 30 (7.5)
Fuel System Prime Standby
Fuel Injection Pump (Stanadyne)................. Unit Pump
Governor Regulation....................................0%............ 0%
Governor Type................................... Electrical ... Electrical
Total Fuel Flow--lb/hr (kg/hr)................185 (84) .... 185 (84)
Fuel Consumption--lb/hr (kg/hr)........ 17.9(8.1)* ..19.8(9.0)*
Maximum Fuel Transfer Pump Suction--
ft (m) fuel.......................................... 10 (3.0 ..... 10 (3.0)
Max. Fuel Inlet Temp.--F (C) ........... 185 (85)* ...185 (85)*
Fuel Filter Micron Size @ 98 % Efficiency...... 5 ............... 5
Lubrication System Prime Standby
Oil Pressure at Rated Speed--psi (kPa) .......43 (296)*
Oil Pressure at Low Idle--psi (kPa) ...................... N/A*
In Pan Oil Temperature--F (C) ...... 226 (108)* . 232 (111)*
Performance Data Prime Standby
Rated Power--hp (kW) .......................... 43 (32) ...... 48 (36)
Rated Speed--rpm.................................... 1800 ......... 1800
Low Idle Speed--rpm ................................ N/A* .......... N/A*
BMEP--psi (kPa) ............................... 128 (883) .. 142 (981)
Friction Power @ Rated Speed--hp (kW)10(7.4)* ..10(7.4)*
Altitude Capability--ft (m) .........................10,000 (3050)*
Ratio--Air : Fuel..................................... 23.9:1* ...... 22.5:1*
Smoke @ Rated Speed--Bosch No. .......... 2.7* ........... 2.9*
Noise--dB(A) @ 1 m ................................... N/A........... N/A
Fuel Consumption -- lb/hr (kg/h) Prime* Standby*
25 % Power ......................................4.4 (2.0) ....... 6.0 (2.7)
50 % Power ......................................8.8 (4.0) ....... 9.9 (4.5)
75 % Power ....................................13.3 (6.1) ..... 14.6 (6.6)
100 % Power ..................................17.9 (8.1) ..... 19.8 (9.0)
* Revised Data
Curve 4024TF270180048.................................. Sheet 2 of 2
November 2003
Engine Performance Curves 6068 - Generator June 2007
Ref: Engine Emission Label
Tier-3 Emission Certifications: Certified by:
Notes:
ENGINE PERFORMANCE CURVE
Air Intake Restriction ................... 12 in.H
2
O (3 kPa)
Exhaust Back Pressure ........... 30 in.H
2
O (7.5 kPa)
Gross power guaranteed within + or - 5% at SAE J1995
and ISO 3046 conditions:
77 F (25 C) air inlet temperature
29.31 in.Hg (99 kPa) barometer
104 F (40 C) fuel inlet temperature
0.853 fuel specific gravity @ 60 F (15.5 C)
Conversion factors:
Power: kW = hp x 0.746
Fuel: 1 gal = 7.1 lb, 1 L = 0.85 kg
Torque: Nm = lb-ft x 1.356
All values are from currently available data and are subject
to change without notice.
STANDARD CONDITIONS
All OEM Gen Set Engine Applications must be pre-
screened for torsional vibration compatibility with the
respective alternator end hardware.
OEM Engine Application Engineering will perform this
computer-based analysis work upon request.
- PRIME - STANDBY
130
(59)
90
(41)
50
(23) F
u
e
l
-
-
l
b
/
h
r
(
k
g
/
h
r
)
20
(15)
220
(164)
260
(190)
140
(104)
180
(134)
60
(45)
100
(75)
Brake Power -- hp (kW)
300
(224)
PowerTech Plus
TM
6.8L Engine
Model: 6068HF485
286 hp (214 kW) Prime
315 hp (235 kW) Standby
[See Option Code Tables]
Rating: Gross Power
Application: Generator (60 Hz)
Target: 200 kWe Standby Market
* Revised Data
Curve 6068HF4851800315 ............................. Sheet 1 of 2
June 2007
Nominal Engine Power @ 1800 RPM
Prime Standby
HP kW HP kW
286 214 315 235
Generator
Efficiency
%
Fan Power
(6% of Standby)
Power
Factor
Prime Rating
2
Standby Rating
1,2
4 sec Standby
Block Load
Capability
hp kW kWe kVA kWe kVA
88-92 18.9 14.1 0.8 176-184 220-230 194-203 243-254 80%
Note 1: Based on nominal engine power. Derate 20% for 100% block load capability.
Note 2: kWe / kVA rating assumes 90% efficiency. Generator Efficiency % will vary.
CARB; EPA
Engine Performance Curves 6068 - Generator June 2007
All values at rated speed and power with standard options unless otherwise noted.
Engine Installation Criteria
General Data
Model ............................................................... 6068HF485
Number of Cylinders ......................................................... 6
Bore and Stroke--in. (mm).............. 4.19 x 5.00 (106 x 127)
Displacement--in.
3
(L) ...........................................415 (6.8)
Compression Ratio ................................................... 17.0:1
Valves per Cylinder--Intake/Exhaust ............................ 2 / 2
Firing Order....................................................... 1-5-3-6-2-4
Combustion System....................................... Unit Injection
Engine Type................................................ In-line, 4-Cycle
Aspiration...................................................... Turbocharged
Charge Air Cooling System................................... Air-to-Air
Engine Crankcase Vent System ................................ Open
Physical Data
Length--in. (mm) ...............................................45.7 (1161)
Width--in. (mm) ...................................................24.0 (611)
Height--in. (mm) ................................................41.6 (1058)
Weight, with oil--lb (kg).......................................1495 (678)
(Includes flywheel hsg., flywheel & electrics)
Center of Gravity Location
From Rear Face of Block (X-axis)--in. (mm) .15.5 (394)
Right of Crankshaft (Y-axis)--in. (mm) ........ -0.1 (-2.24)
Above Crankshaft (Z-axis)--in. (mm) ..............7.4 (189)
Max. Allow. Static Bending Moment at Rear
Face of Flywhl Hsg w/ 5-G Load--lb-ft (Nm) ..600 (814)
Thrust Bearing Load Limit --lb (N) Forward Rearward
Intermittent............................899 (4000) .....450 (2000)
Continuous ...........................495 (2200) .....225 (1000)
Max. Front of Crank. Torsional Vibration--DDA............ 0.25
Max. Continuous Damper Temp--F (C) ...............180 (82)
Electrical System 12 Volt 24 Volt
Min. Battery Capacity (CCA)--amp............ 800 ............ 570
Max. Allow. Start. Circt Resist.--Ohm.. 0.0012 ......... 0.002
Starter Rolling Current:
At 32 F ( 0 C)--amp ............................ 920 ............ 600
At -22 F (-30 C)--amp....................... 1300 ............ 700
Min. Volts at ECU while Cranking--volts.........6 .............. 10
Max. ECU Temperature--F (C) ....................221 (105)
Max. VTG Actuator Surface Temp.--F (C) ...356 (180)
Max. Harness Temperature--F (C) ..............248 (120)
Maximum Voltage From Engine Crankshaft/
Generator Shaft to Ground--VAC ........... 0.15.......... 0.15
Air System Prime Standby
Max. Allowable Temp Rise--Ambient Air to
Engine Inlet--F (C)......................... 15 (8) .........15 (8)
Maximum Air Intake Restriction
Dirty Air Cleaner--in.H
2
O (kPa)... 25 (6.25) ....25 (6.25)
Clean Air Cleaner--in.H
2
O (kPa). 15 (3.75) ....15 (3.75)
Engine Air Flow--ft
3
/min (m
3
/min) ....520 (14.7) ..619 (17.5)
Air Cleaner Efficiency--%..................................99.9
Charge Air Cooling System Prime Standby
Air/Air Exchanger Heat Rejection--
BTU/min (kW) ................................. 2298(40.37) . 3264(57.34)
Compress. Dischrg. Temp.(Rated)
@ 77 F (25C) Amb. Air--F (C) 365(185) .... 441(227)
Compress. Dischrg. Temp.(Max.)
@ 47C amb. and
80 kPa bar.--F (C) .....................000(000) .... 000(000)
Press. Drop, thru CAC--in.H
2
O (kPa)
Max. ...............................................64 (16) ....... 64 (16)
Min. ..................................................32 (8) ......... 32 (8)
Intake Manifold Pressure--psi (kPa) ...27 (188) ..... 37 (252)
CAC Out Temp @ 77F (25C) Amb.--F (C)
Max. .............................................126 (52) ..... 126 (52)
Min. ..............................................109 (43) ..... 109 (43)
CAC Out Temp @ any Ambient--F (C)
Max. ..............................................190 (88) ..... 190 (88)
Cooling System Prime Standby
Engine Heat Reject.--BTU/min (kW). 4766(83.7) ... 5404(94.9)
Coolant Flow--gal/min (L/min).............70 (265) ..... 70 (265)
Thermostat Start to Open--F (C) ......180 (82) ..... 180 (82)
Thermostat Fully Open--F (C)..........203 (95) ..... 203 (95)
Engine Coolant Capacity--qt (L) ........ 13 (11.9) .... 13 (11.9)
Min. Pressure Cap--psi (kPa) ..........14.5 (100) .. 14.5 (100)
Max. Top Tank Temp--F (C) ........... 230 (110) ... 230 (110)
Min. Coolant Fill Rate--gal/min (L/min) ... 3 (11) ......... 3 (11)
Min. Air-to-Boil Temperature--F (C) . 117 (47) ..... 117 (47)
Min. Pump Inlet Pressure--psi (kPa)....4.4 (30) ...... 4.4 (30)
Exhaust System Prime Standby
Exhaust Flow--ft
3
/min (m
3
/min)......1371 (38.8) 1514 (42.9)
Exhaust Temperature--F (C) ..........982 (528) ... 905 (485)
Max. Exhaust Restriction----in. H
2
O (kPa).......40 (10)
Min. Exhaust Restriction----in. H
2
O (kPa)..........16 (4)
Max. Bend. Moment, Turbo Out.--lb-ft (Nm) .5.2 (7.0)
Max. Shear on Turbo Outlet--lb (kg) ................24 (11)
Fuel System Prime Standby
ECU Description ...................................L14 Controller
Fuel System Description................................... HPCR
Fuel Injection Pump ................................. Denso HP3
Governor Type............................................ Electronic
Total Fuel Flow--lb/hr (kg/hr)..........161 (73.1) .... 174 (78.7)
Fuel Consumption--lb/hr (kg/hr)..........97 (44) ....... 110 (50)
Max. Fuel Inlet Temp.--F (C) .......................176 (80)
Fuel Temp. Rise, Inlt to Retrn--F (C)97.2(54) ... 100.8(56)
Max. Fuel Inlet Restriction--in. H
2
O (kPa) .......80 (20)
Max. Fuel Inlet Pressure--in. H
2
O (kPa) ........ NA (NA)
Max. Fuel Return Pressure--in. H
2
O (kPa) ......80 (20)
Lubrication System Prime Standby
Oil Press. at Rated Speed--psi (kPa). 49 (339) ..... 49 (339)
Oil Pressure at Low Idle--psi (kPa) ................ 15 (105)
Max. Oil Carryover in Blow-by--lb/hr (g/hr) 0.002 (1.0)
Max. Airflow in Blow-by--gal/min (l/min)......... 34 (130)
Max. Crankcase Pressure--in. H
2
O (kPa)......... 2 (0.5)
Performance Data Prime Standby
Rated Power--hp (kW) ................... 286 (214)...... 315 (235)
Rated Speed--rpm................................ 1800............. 1800
Low Idle Speed--rpm .............................1150..............1150
Rated Torque--lb-ft (Nm)........... 1536 (1133).. 1690 (1247)
BMEP--psi (kPa) .......................... 304 (2094).... 334 (2304)
Friction Power
@ Rated Speed--hp (kW) ........... 25 (18.7)....... 25 (18.7)
Altitude Capability--ft (m) ...................... 10,000 (3000)
Ratio--Air : Fuel................................. 23.0 : 1......... 24.0 : 1
Smoke @ Rated Speed--Bosch No. ...... 0.45.............. 0.77
Noise--dB(A) @ 1 m ................................ NA................ NA
Fuel Consumption -- lb/hr (kg/h) Prime Standby
25 % Power ...............................27.8 (12.6) ...... 30.3 (13.7)
50 % Power ...............................51.4 (23.3) ...... 56.2 (25.5)
75 % Power ...............................73.2 (33.2) ...... 80.4 (36.5)
100 % Power .............................97.2 (44.1) .... 109.7 (49.8)
* Revised Data
Curve 6068HF4851800315................................ Sheet 2 of 2
June 2007
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 82.2 82.2 82.2 25% 1477.4 2322.7 3158.2
50% 83.3 84.4 85 50% 2443.3 2335.8 2281.0
75% 85 85.1 85.3 75% 2406.1 3372.9 4108.6
100% 85.6 85.7 86 100% 4916.2 7900.3 11223.5
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 56.1 65.4 69.7 25% 1477.4 2322.7 3158.2
50% 58.9 58.9 58.9 50% 2443.3 2335.8 2281.0
75% 52.4 61.7 66.0 75% 2406.1 3372.9 4108.6
100% 63.4 71.7 76.0 100% 4916.2 7900.3 11223.5
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 60.6 69.9 74.2 25% 1135.6 1135.6 1135.6
50% 67.9 67.9 67.9 50% 1135.6 1135.6 1135.6
75% 61.4 70.7 75.0 75% 2271.2 2271.2 2271.2
100% 74.4 83.7 88.0 100% 2271.2 2271.2 2271.2
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 232 232 232 25% 138 138 138
50% 312 312 312 50% 144 144 144
75% 410 410 410 75% 153 153 153
100% 503 503 503 100% 165 165 165
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 125 125 125 25% 0 anything 7.1
50% 125 125 125 50% 0 anything 13.5
75% 125 125 125 75% 0 anything 20.9
100% 125 125 125 100% 0 anything 29.7
Winter Operation
A
p
p
e
n
d
i
x
H
:
2
0
0
k
W
e
T
R
N
S
Y
S
L
o
o
k
U
p
T
a
b
l
e
s Exhaust Temperature (C) Exhaust FR (kg/hr)
steam Temperature (SG outlet) (C) steam FR (SG outlet) (kg/hr)
Hot water outlet Temperature (C)
Coolant Engine FR (kg/hr)
Coolant heat exchanger FR (kg/hr)
Coolant engine outlet Temperature (C)
Hot water HX FR (kg/hr)
Coolant heat exchanger outlet Temperature (C)
power prod small bldg load medium bldg load high bldg load
25% 56.1 65.4 69.7
50% 58.9 58.9 58.9
75% 52.4 61.7 66.0
100% 63.4 71.7 76.0
power prod small bldg load medium bldg load high bldg load
25% 81.7 81.7 81.7
50% 82.8 83.9 84.5
75% 84.5 84.6 84.8
100% 85.1 85.2 85.5
power prod small bldg load medium bldg load high bldg load
25% 27.4 36.7 41
50% 27.4 36.7 41
75% 27.4 36.7 41
100% 27.4 36.7 41
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 128 128 128 25% 197 163 128
50% 128 128 128 50% 251 189 128
75% 128 128 128 75% 316 222 128
100% 128 128 128 100% 378 253 128
power prod small bldg load medium bldg load high bldg load
25% 2.4 2.4 2.4
50% 2.4 2.4 2.4
75% 2.4 2.4 2.4
100% 2.4 2.4 2.4
Winter Operation
steam Pressure (SG outlet) (Bar)
SG Outlet Exhaust Temperature (C)
Coolant engine intlet Temperature (C)
Hot water intlet Temperature (C)
Stack Exhaust Temperature (C)
Coolant heat exchanger intlet Temperature (C)
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 95 95 95 25% 23576.8 23576.8 23576.8
50% 95 95 95 50% 23576.8 23576.8 23576.8
75% 95 95 95 75% 23576.8 23576.8 23576.8
100% 95 95 95 100% 23576.8 23576.8 23576.8
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 93 93 93 25% 7858.9 15717.9 23576.8
50% 92 92 92 50% 7858.9 15717.9 23576.8
75% 91 91 91 75% 7858.9 15717.9 23576.8
100% 90 90 90 100% 7858.9 15717.9 23576.8
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 93 93 ambient 25% 15717.9 7858.9 0
50% 92 92 ambient 50% 15717.9 7858.9 0
75% 91 91 ambient 75% 15717.9 7858.9 0
100% 90 90 ambient 100% 15717.9 7858.9 0
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 92 92 92 25% 1405 2809 4214
50% 92 92 92 50% 2430 4859 7289
75% 92 92 92 75% 3229 6457 9686
100% 92 92 92 100% 4447 8894 13341
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 234 234 234 25% 878 878 878
50% 320 320 320 50% 916 916 916
75% 421 421 421 75% 974 974 974
100% 515 515 515 100% 1050 1050 1050
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 160 160 160 25% 0 anything 29
50% 160 160 160 50% 0 anything 68
75% 160 160 160 75% 0 anything 120
100% 160 160 160 100% 0 anything 176
Summer Operation
Coolant radiator outlet temperature Coolant Radiator FR
steam Temperature (SG outlet) steam FR (SG outlet)
Hot water outlet Temperature Hot water HX FR
Exhaust Temperature Exhaust FR
Coolant Engine FR
Coolant heat exchanger outlet Temperature Coolant heat exchanger FR
Coolant engine outlet Temperature
power prod small bldg load medium bldg load high bldg load
25% 93 93 93
50% 92 92 92
75% 91 91 91
100% 90 90 90
power prod small bldg load medium bldg load high bldg load
25% 95 95 95
50% 95 95 95
75% 95 95 95
100% 95 95 95
power prod small bldg load medium bldg load high bldg load
25% 95 95 ambient
50% 95 95 ambient
75% 95 95 ambient
100% 95 95 ambient
power prod small bldg load medium bldg load high bldg load
25% 83 83 83
50% 83 83 84
75% 84 84 84
100% 84 84 84
power prod small bldg load medium bldg load high bldg load power prod small bldg load medium bldg load high bldg load
25% 165 165 165 25% 211 188 165
50% 165 165 165 50% 268 217 165
75% 165 165 165 75% 336 250 165
100% 165 165 165 100% 398 282 165
power prod small bldg load medium bldg load high bldg load
25% 6 6 6
50% 6 6 6
75% 6 6 6
100% 6 6 6
Summer Operation
Stack Exhaust Temperature (C)
Coolant radiator inlet temperature
steam Pressure (SG outlet) (bar)
Hot water intlet Temperature
SG Outlet Exhaust Temperature (C)
Coolant heat exchanger intlet Temperature
Coolant engine intlet Temperature
200 kWe Engine TRNSYS Data File
40 90 !hot water set point temperature
200000 500000 800000 !building load
25 50 75 100! electric load
56.1456451 1477.416262 82.2 81.7 1477.4 82.2 -10 0 -10
58.9 2443.290746 83.3 82.8 2443.3 85.0 -10 0 -10
52.40294909 2406.104484 85 84.5 2406.1 85.3 -10 0 -10
63.3907125 4916.199385 85.6 85.1 4916.2 86.0 -10 0 -10
65.4456451 2322.726416 82.2 81.7 2322.726416 65.4 -10 0 -10
58.9 2335.785953 84.4 83.9 2335.785953 58.9 -10 0 -10
61.70294909 3372.873582 85.1 84.6 3372.873582 61.7 -10 0 -10
71.6907125 7900.282369 85.7 85.2 7900.282369 71.7 -10 0 -10
69.7456451 3158.214711 82.2 81.7 3158.214711 69.7456451 -10 0
-10
58.9 2281.04097 85 84.5 2281.04097 58.9 -10 0 -10
66.00294909 4108.56248 85.3 84.8 4108.56248 66.00294909 -10 0
-10
75.9907125 11223.4682 86 85.5 11223.4682 75.9907125 -10 0
-10
93 23576.8 95 95 7858.9 93 95 15717.9 93
92 23576.8 95 95 7858.9 92 95 15717.9 92
91 23576.8 95 95 7858.9 91 95 15717.9 91
90 23576.8 95 95 7858.9 90 95 15717.9 90
93 23576.8 95 95 15717.86667 93 95 7858.933333 93
92 23576.8 95 95 15717.86667 92 95 7858.933333 92
91 23576.8 95 95 15717.86667 91 95 7858.933333 91
90 23576.8 95 95 15717.86667 90 95 7858.933333 90
93 23576.8 95 95 23576.8 93 20 0 20
92 23576.8 95 95 23576.8 92 20 0 20
91 23576.8 95 95 23576.8 91 20 0 20
90 23576.8 95 95 23576.8 90 20 0 20
200 kWe Exhaust and Hot Water TRNSYS Data File
40 90
20000 50000 80000
25 50 75 100
27.4 1135.62 60.6456451 138 232
27.4 1135.62 67.9 144 312
27.4 2271.24 61.40294909 153 410
27.4 2271.24 74.3907125 165 503
36.7 1135.62 69.9456451 138 232
36.7 1135.62 67.9 144 312
36.7 2271.24 70.70294909 153 410
36.7 2271.24 83.6907125 165 503
41 1135.62 74.2456451 138 232
41 1135.62 67.9 144 312
41 2271.24 75.00294909 153 410
41 2271.24 87.9907125 165 503
83 1405 92 878 234
83 2430 92 916 320
84 3229 92 974 421
84 4447 92 1050 515
83 2809 92 878 234
83 4859 92 916 320
84 6457 92 974 421
84 8894 92 1049.58 515
83 4214 92 878 234
84 7289 92 916 320
84 9686 92 974 421
84 13341 92 1049.58 515