Professional Documents
Culture Documents
3: Project Design
Contents
1.0 Introduction .......................................................................................1 1.1 Steps for Design ................................................................................1 1.1.1 Demand Assessment.....................................................................1 1.1.2 Detailed Engineering Design...........................................................1 1.2 Standard Manuals for Reference...........................................................2 1.2.1 Road Projects ..............................................................................2 1.2.2 Water Supply Projects ...................................................................2 1.2.3 Sewerage Projects ........................................................................2 1.2.4 Solid waste Projects......................................................................2 2.0 Design of Road Projects .....................................................................2 2.1 Road width and Designs Traffic Volumes ...............................................3 2.2 Design Approach & Criteria..................................................................5 2.3 Design of Flexible Pavement ................................................................5 2.3.1 Traffic- CV/Day Annual traffic census 24 X 7.....................................5 2.3.2 Wheel loads.................................................................................5 2.3.3 Climate .......................................................................................5 2.3.4 Terrain Plain or Hilly .....................................................................6 2.3.5 Pavement Thickness .....................................................................6 2.4 Design Traffic ....................................................................................6 2.5 Design Period ....................................................................................8 2.6 CBR Value ........................................................................................8 2.7 Other Parameters ............................................................................ 13 2.7.1 Footpath ................................................................................... 13 2.7.2 Medians .................................................................................... 14 2.7.3 Verge ....................................................................................... 14 2.7.4 Parking Lanes ............................................................................ 14 2.7.5 Bus Bays................................................................................... 14 2.7.6 Kerb ......................................................................................... 15 2.8 Location and Space for Services ......................................................... 15 3.0 Design of Water Supply Projects.................................................... 18
3.1 Water Quality and Quantity ............................................................... 18 3.2 Design Period .................................................................................. 19 3.3 Population Forecast .......................................................................... 19 3.4 Per capita water Supply .................................................................... 19 3.5 Unit Operations of Water Treatment Plant............................................ 19 3.5.1 Aeration.................................................................................... 20
3.5.2 Coagulation and Flocculation ........................................................ 20 3.5.3 Clariflocculators ......................................................................... 22 3.5.4 Sedimentaion ............................................................................ 22 3.5.5 Filtration ................................................................................... 23 3.5.6 Slow Sand Filter ......................................................................... 23 3.5.7 Rapid Sand Filtration Plant........................................................... 25 3.5.8 Disinfection ............................................................................... 29 3.5.9 Water Treatment Plant ................................................................ 31 3.6 Quality Standards ............................................................................ 32 3.7 Distribution System.......................................................................... 36 3.7.1 Design of Pressure Pipelines......................................................... 36 3.7.2 Minimum Pipe Sizes .................................................................... 37 3.7.3 Pipe and Material of Construction.................................................. 37 3.7.4 Modified Hazen Williams Formula ............................................... 38 3.7.5 Residual Pressure ....................................................................... 39 3.8 Case Study of Rajkot City.................................................................. 40 4.0 Design Criteria of Sewerage Projects ............................................... 43 4.1 Objective ........................................................................................ 43 4.2 Main Considerations ......................................................................... 43 4.2.1 Engineering Considerations .......................................................... 43 4.2.2 Environmental Considerations ...................................................... 44 4.2.3 Process Considerations................................................................ 44 4.3 Design Period .................................................................................. 44 4.4 Population Forecast .......................................................................... 45 4.5 Sewage Generation .......................................................................... 45 4.5.1 Sewage flows............................................................................. 45 4.5.2 Peak factors .............................................................................. 45 4.5.3 Self Cleansing Velocities .............................................................. 46 4.6 Flow Characteristics ......................................................................... 47 4.6.1 Velocity at Minimum Flow ............................................................ 48 4.6.2 Minimum Size of Sewer ............................................................... 48 4.6.3 Minimum Depth of cover ............................................................. 48 4.6.4 Maximum Depth of Sewer Invert .................................................. 49 4.6.5 Ground Water Infiltration............................................................. 49 4.6.6 Sewer hydraulics ........................................................................ 49 4.6.7 Material of construction ............................................................... 50 4.6.8 Joints ....................................................................................... 50 4.6.9 Type of bedding ......................................................................... 51 4.7 Sewer Appurtenances ....................................................................... 56 4.7.1 Manholes .................................................................................. 56 4.7.2 Scrapper Manholes ..................................................................... 57 4.7.3 Ventilation Shafts ....................................................................... 57 4.8 Sewage Pumping Stations ................................................................. 57
ii
4.8.1 Types ....................................................................................... 57 4.8.2 Design Considerations................................................................. 57 4.9 Sewage Treatment Plant ................................................................... 58 4.9.1 Plant and Process Design Parameter.............................................. 58 4.9.2 Process Design Parameters .......................................................... 59 5.0 Storm Water Drainage...................................................................... 66 5.1 Introduction .................................................................................... 66 5.2 Design Methodology ......................................................................... 68 5.3 Design of under ground Strom Water Network ..................................... 69 5.3.1 Modified Rational Method............................................................. 69 5.3.2 Hydrograph Design Method.......................................................... 69 5.3.3 Simulation Method...................................................................... 69 6.0 Solid Waste Management ................................................................. 70 6.1 Key Features MSW Rules 2000 ........................................................ 70 6.2 Composition of waste ....................................................................... 70 6.3 Collection of Municipal Solid Waste (MSW)........................................... 72 6.4 Segregation of Municipal Solid Waste.................................................. 72 6.5 Storage of Municipal Solid Waste........................................................ 73 6.6 Transport of Municipal Solid Waste ..................................................... 73 6.7 Processing of Municipal Solid Waste.................................................... 73 6.8 Disposal of Municipal Solid Waste ....................................................... 74 6.9 Design System for SWM.................................................................... 74 6.10 Street sweeping ............................................................................. 74 6.11 Secondary storage ......................................................................... 74 6.12 Sample Financial Estimates for implementation of Solid Waste Management Plan.................................................................................. 74 6.13 Design Criteria of Landfill Site Selection............................................. 78 6.14 Case Study of Rajkot DPR ............................................................... 79 6.15 Environmental Settings ................................................................... 81
iii
1.0 Introduction
Design is a crucial aspect and should be an integral part of all the stages of a project. In developing countries it has been experienced that evaluation reports cite problems of poor design owing to reasons such as: Inclusion of components that are inappropriate to local conditions Underestimation of resource needs and availability Inadequate or inappropriate specifications Lack of financial contingency planning Improper location etc.
CEPT, Ahmedabad
The width and layout of urban road cross-sections depend on many factors, the chief amongst them being the classification of road, design speed and the volume of traffic expected. Other considerations are requirements of parking lanes, busbays, loading-unloading bays, occurrences of access points, volume of pedestrians and cyclists, width of drains, location of sewer lines, electricity cables and other public utility services. Actual width of each element should be based on traffic volumes and other functional requirements explained in parts 6.2.1 through 6.2.11 of IRC 86-1983.
The Equivalency factors for the passenger car unit (PCU) are shown in the table 2.2 below.
Vehicle Type
Passenger car, tempo, auto, jeep, vans, or agricultural tractor Truck, bus, agricultural tractor-trailer
Equivalency Factor
1.0 3.0
CEPT, Ahmedabad
Sr. No.
3 4 5 6 7
Vehicle Type
Motor-cycle, scooter and cycle Cycle-rickshaw Horse drawn vehicle Bullock cart Hand-cart
Equivalency Factor
0.5 1.5 4.0 5.0 6.0
Tentative Capacities of Urban Roads between Intersections are presented in table 2.3 below. Table 2.3: Tentative Capacities of Urban Roads No of traffic lanes and widths Traffic flow Capacity in PCUs per hour for various traffic conditions
Roads with no frontage access, standing vehicles, little traffic 2 lane (7-7.5 m) 3-lanes 4-lane (14 m) 6-Lane (21 m)
Source: IRC 86; 1983
Road
with
Roads with free frontage access, vehicles heavy traffic 1200 750 2000 2400 2000 2200 3000 parked and cross
no very cross
frontage access but no standing vehicle and high capacity intersections 1500 1200 2500 3000 2500 2500 4200
One way Two way One way One way Two way One way Two way)
Carriageway widths recommended are shown in table 2.4 below. (IRC 86; 1983) Table 2.4: Recommended Carriageway Widths Description Single lane without kerbs 2-lane without kerbs 2- lane with kerbs 3-lane with or without kerbs 4-lane with or without kerbs 6- lane with or without kerbs
Source: IRC 86; 1983 Note: 1. For access roads to residential areas, a lower lane width of 3 m is permissible.
Minimum width of a kerbed urban road is 5.5 m including allowance for a stalled vehicle.
CEPT, Ahmedabad
2.3.3 Climate
Temperature is an important factor affecting the performance of Flexible pavement (Hot or Cold). Most of our country comes under hot climate. In urban scenario, the traffic is heterogeneous. There is sizable bicycle traffic. There is sizable pedestrian traffic. The demand for road can be estimated by a classified volume count of traffic. This survey should be conducted for seven days throughout 24 x 7 surveys. All vehicle categories including non motorised traffic like bicycles, animal driven carts etc. There should be a separate pedestrian survey. An Origin Destination (OD) survey to estimate preference for a particular route may also be carried out. Locations attracting heavy traffic demand such as Government offices, commercial centres, hospitals, educational institutes, religious and other places of interest may be marked and traffic generated should be estimated. A detailed socio economic study is required for understanding and future trends. Planning must provide for future requirements. It is usually found that the future projections are overtaken by faster developments, people start development faster than estimated years the grade of bitumen to be used in surface layers. The grade of bitumen in urban scenario, the traffic is heterogeneous. There is sizable bicycle traffic. There is sizable pedestrian traffic. The demand for road can be estimated by a classified volume count of traffic. This survey should be
CEPT, Ahmedabad
conducted for seven days throughout 24 x 7 surveys. All vehicle categories including non motorised traffic like bicycles, animal driven carts etc. There should be a separate pedestrian survey. An Origin Destination (OD) survey to estimate preference for a particular route may also be carried out. Locations attracting heavy traffic demand such as Government offices, commercial centres, hospitals, and educational institutes, religious and other places of interest may be marked and traffic generated should be estimated. A detailed socio economic study is required for understanding and future trends. Planning must provide for future requirements. It is usually found that the future projections are overtaken by faster developments. Considerations for different climate are given in annexure 6 of IRC 37 2001.
CEPT, Ahmedabad
Computation of design Traffic In terms of cumulative number of standard axle to be carried by the pavement during design life. N = {365 X r Where N = The cumulative number of standard axles to be catered for in design in terms of million standard axles - msa. A = Initial traffic in the year of completion of construction duly modified as shown below. D = Lane distribution factor F = Vehicle damage factor, VDF n = Design life in years r = Annual growth rate of commercial vehicles { this can be taken as 7.5% if no data is available} (1+r)n 1} xAxDxF
A = P (1 + r)x
Where, P = Number of commercial vehicle as per last count X = Number of years between the year of last count and the year of completion of construction
Distribution
Factor (D)
F = Vehicle damage factor (VDF). It is a multiplier to convert the number of CV of different axle load and axle configuration to the number of standard axle load repetition. VDF depends on vehicle configuration, axle load, terrain, type of road. Where sufficient information of axle load is not available then the VDF value considered are presented in table 2.6
CEPT, Ahmedabad
Table 2.6: Vehicle Damage Factor Initial Traffic volume in terms of Commercial Vehicles per Day 0-150 150-1500 More than 1500
Source: IRC 37
Terrain Rolling / Plain 1.5 3.5 4.5 Hilly 0.5 1.5 2.5
In view of the concept of cumulative axle loads, it is now possible to design a flexible pavement for a definite period.
r - Traffic Growth: From the datas available for the last five or ten years traffic census traffic growth can be determined. In absence of adequate data, an average value of 7.5 % per annum growth rate may be adopted.
CEPT, Ahmedabad
The material is statically compacted in three layers at MDD & OMC determined by a standard proctor test as per IS 2720 part:7 for light compaction or IS2720- part:8 for heavy compaction as per the requirement.
The sample is subjected to 4 days soaking. There after a plunger of 50 mm dia. is allowed to penetrate in the material at the rate of 1.25 mm/min. The required loads required causing 2.5 mm & 5.0 mm penetrations are recorded. These loads are then expressed as percentages of standard/loads, which are the loads for corresponding penetrations in standard crushed stone aggregates.
As per the IS requirements three samples shall have to be tested for CBR and the average CBR value of three samples is taken as final CBR provided the CBR value of all three samples are within the permissible limit of variation. CBR (Percent)
5 5 10 10 30 31 and above
Source: IRC 37; 1998 Fig2.2: PAVEMENT THICKNESS DESIGN CHART FOR TRAFFIC 1-10 MSA
CEPT, Ahmedabad
CBR 3 % 1 2 3 5 10 CBR 2% 1 2 3 5 10 CBR 4% 1 2 3 5 10 CBR 5% 1 2 3 5 10 CBR 6% 1 2 3 5 10 CBR 7% 1 2 3 5 10 CBR 8% 375 425 460 505 580 20 PC 20 PC 20 PC 25 SDBC 40 BC 390 450 490 535 615 20 PC 20 PC 20 PC 25 SDBC 40 BC 430 490 530 580 660 20 PC 20 PC 20 PC 25 SDBC 40 BC 480 540 580 620 700 20 PC 20 PC 20 PC 25 SDBC 40 BC 660 715 750 795 850 20 PC 20 PC 20 PC 25 SDBC 40 BC 550 610 645 690 760 20 PC 20 PC 20 PC 25 SDBC 40 BC
CEPT, Ahmedabad
10
Binder Course ( mm )
1 2 3 5 10 1 2 3 5 10
375 425 450 475 550 375 425 450 475 540
225 225 250 250 250 225 225 250 250 250
150 150 150 150 200 150 150 150 150 200
CBR 9 % & 10 %
Fig 2.3: pavement thickness design chart for traffic 10-150 msa
CEPT, Ahmedabad
11
CEPT, Ahmedabad
12
Total Thickness (mm) 640 660 540 570 585 605 635 655 540 565 580 600 630 650
PAVEMENT COMPOSITION Bituminous Surfacing BC (mm) 50 50 40 40 40 40 50 50 40 40 40 40 50 50 DBM (mm) 140 160 50 80 95 115 135 155 50 75 90 110 130 150 Base = 250 Sub base = 200 Base = 250 Sub base = 200
2.7.1 Footpath
The minimum width of footpath should be 1.5 meters. They should have well maintained surface with cross fall neither so flat as to be difficult to drain nor so steep as to be dangerous to walk upon. The cross fall within the range of 2.5 to 3 % should meet requirement
Of
CEPT, Ahmedabad
13
2.7.2 Medians
Width of median is dictated by a variety of conditions. Widths will depend on the available right-of-way, terrain, turn lanes, drainage and determinants. Wide medians are preferred where space and cost considerations permit. Minimum widths of median at intersections to accomplish various purposes should be as follows:(i) Pedestrian refuge;(ii) Median lane for protection of vehicle making right turn, 4.0 m but 7.5 m is recommended; (iii) 9 to 12m is required for Uturns. Absolute minimum width of median in urban areas is 1.2m; a desirable minimums 5m. As far as possible, the median should be of uniform width in a particular section. However, where changes are unavoidable, a transition of 1 m to 15 to 1 in 20 must be provided.
2.7.3 Verge
Verges are required between carriage way and property line not only to accommodate. Lighting columns, traffic signs, underground services etc., but also to provide appropriate clearance to ensure proper vehicle placement and development of full carriageway capacity. Where road width is restricted, full width between carriage way and property line should be paved and used for pedestrian sidewalk/cycle track. Where possible, a minimum verge of 1 m width should be kept. They should be suitably levelled, trimmed and provided with a cross fall of 5 per cent if turned and 3 per cent if cobbled or surface dressed. This should be increased if poles, kerb-height, or excessive cross fall discourage parking close to the kerb and also where either parked vehicles frequently overlap on to the adjacent traffic lane or the parking lane is likely to be used as a peak hour traffic lane.
CEPT, Ahmedabad
14
for single bus stop and 7 m for multiple bus stop. Suitable arrangement should be made for drainage of surface water from busbays. Sufficient footpath should be ensured behind the busbays.
2.7.6 Kerb
It is desirable that roads in urban areas are provided with kerbs. Kerbs may be barrier type, semi barrier type or mountable type. Appropriate situations for use of each type are indicated below: Barrier type : Built up areas adjacent to footpaths with considerable pedestrian traffic. Semi-barrier type : on the periphery of the roadway where Pedestrian traffic is light and a barrier type could to reduce traffic capacity. Mountable type: within the roadway at canalization sections medians outer separators and raised medians on bridges. Each figure shows two varieties of each type of kerb with gutter and without gutter. Kerbs with gutter should always be used at drainage edges of pavement.
CEPT, Ahmedabad
15
Illustration: In Ahmedabad city Navrangpura area is in plane terrain. The soil available is having California Bearing Ratio 5 %. Traffic surveys have been carried out on nearby road. Traffic count has been yielded a PCU figure of 3500 in the peak hours and a Commercial Vehicle per Day (CVD) figure of 500. It is expected that about 2000 PCU and 200 number of CVD are likely to be diverted to the new proposed road. The road will have all residence opening directly on to the road (free access). As there are residential units already, parking can not be prohibited. There is cross traffic traffic moving in al directions. The socioeconomic surveys have indicated that the traffic growth rate on the new proposed road could be 7.5%. AMC has decided to construct new road within two years and the design life of the road is 10 year. What will be the ROW / CW and Crust thickness of the new proposed road? The problem could be solved as below. First the geometrical design. As this is an urban arterial road the ROW is to be 60 meters. (as per table no. 2.1 ) As PCU on new road is 2000 the CW is to be four lane two way (as per table no.2.3 ) Crust design Present traffic 200 CVD A = P(1+r)n A= 200(1+ 7.5/100)2 R= 7.5% Construction period = 2 years A = 200(1.155625) A= 231.25 Say 230 CVD N = 365x {(1+r)n - 1}x A x D x F r N = 365 x {(1 + 7.5/100)10 1} x 230 x 0.40 x 3.5 7.5/100 D = 0.4 from table 2.5 F = 3.5 from table 2.6 N = 365 {2.06 1) x 322 .075 N = 1661090 Standard Axles N = 1661090 / 10,00,000 N = 1.6 msa Million standard axles
CEPT, Ahmedabad
16
Say 2 msa CBR = 5% Total crust thickness = 490 mm Sub base course = 215 mm Base course = 225 mm Surfacing course = 50 mm BM + 20 mm PC Some typical road cross sections for widening, construction and overlay are presented below.
CEPT, Ahmedabad
17
CEPT, Ahmedabad
18
In case of ground water and surface water with storage which are well protected, where the water has turbidity below 10 NTU and they are free from colour and odour, plain disinfection by chlorination is adopted before supply. In surface
CEPT, Ahmedabad
19
waters with turbidity not exceeding 50 NTU and where sufficient area is available, plain sedimentation followed by slow sand filtration and disinfection are practiced.
3.5.1 Aeration
Aeration is necessary to promote the exchange of gases between the water and the atmosphere.
CEPT, Ahmedabad
20
and resultant intensity to mixing is based on the rate of power input to the water and G can be measured or calculate in terms of power input by the following expression: Where, G = Temporal mean velocity gradient, s-1 P = Total input of power in water, watts; = Absolute viscosity of water, N.s/m2; and Vol= Volume of water to which power is applied, m3 Two types of mechanical mixers of coagulant: Rapid rotation of impellers /blades Mixing with the aid of a jet / impingement on a jet Rapid rotation of impellers /blades: Propeller type impellers are commonly employed in flash mixers with high RPM speed of 400 to 1400 rpm Detention time should be of 30 to 60 sec. is provided. Power requirements 1 to 3 Watts per m3 / hr The ratio of impeller diameter to tank diameter is 0.2 to 0.4 and The ratio of tank height to diameter is 1:1 to 3:1 is preferred for proper dispersal. Types of Slow Mixers 1. Gravitational or Hydraulic Type Flocculators a. Horizontal Flow Baffled Flocculator 2. Mechanical Type of Flocculator Paddle flocculators are widely used in practice. The design criteria are depth of tank = 3 to 4.5 m; detention time, t = 10 to 40 min. normally 30 min; velocity of flow = 0.2 0.8 m/s normally 0.4 m/s; total area of paddles = 10 to 25% of the cross-sectional 0.4 m/s is area of the tank; range range of of peripheral velocity of blades = 0.2 0.6 m/s; 0.3recommended; velocity gradient; G = 10 to 75 s-1 range of dimensionless factor Gt= 104 105 and power consumption; 10.0 to 36.0 kw/mld, outlet velocity to settling tank where water has to flow through pope or channel = 0.15 to 0.25 m/s to prevent settling or breaking of floes. For paddle flocculator, the velocity gradient is given by
CEPT, Ahmedabad
21
Ap=area of paddle (m2), Volume of water in the Flocculator (m3) Vp= Velocity of the tip of paddle (m/s), VW= Velocity of the water adjacent to the tip of paddle (m/s) The optimum value of G can be calculated
In which G= Optimum velocity Gradient, s-1 t = time of flocculation, min; and c= alum concentration (mg/l)
3.5.3 Clariflocculators
Clariflocculators are widely used in the country in water and wastewater treatment. The coagulation and sedimentation processes are effectively incorporated in a single unit in the clariflocculator. All these units consist of 2 to 4 floculating paddles placed equidistantly. Settling zone The rectangular tanks have lengths commonly upto 30 m but larger lengths upto 100 m have also been adopted. The length to width ration of rectangular tanks should preferably be from about 3:1 to 5:1. the narrower the tank, the less chance there is for setting up of cross currents and eddies due to wind action, temperature changes and other factors involved. In very large size tanks where the depth is necessarily great, it may be advisable to provide longitudinal baffles to confine the flow to definite straight channels. The diameter of the circular tank is governed by the structural requirement of the trusses that carry the scraping mechanism. Circular tanks up to 60 m in diameter are in use but are generally up to 30 m to reduce wind effects. Square tanks are generally smaller usually with side upto 20 m. Square tanks with hopper bottoms having vertical flow have sides generally less than 10 m to avoid large depths. The decomposition of the sludge adversely affects the settling process. Depths commonly used in practice very from 2.5 to 5 m with 3.0 being a preferred value. Bottom slopes may range from 1% in rectangular tanks to about 8% in circular tanks. The slopes of sludge hoppers range from 1.2:1 to 2:1 (Vertical: horizontal).
3.5.4 Sedimentaion
There are two types of Sedimentation tanks. 1. Horizontal Flow Tanks and 2. Vertical Flow Tanks
CEPT, Ahmedabad
22
1. Horizontal Flow Tanks in the design of a horizontal flow tank, the aim is to achieve as nearly as possible the ideal conditions of equal velocity at all points laying on each vertical line in the settling zone. The direction of flow in the tanks is substantially horizontal. Among the representative designs of the horizontal flow settling tanks, the following may be mentioned: 2. Vertical Flow Tanks Vertical flow tanks normally combine sedimentation with flocculation. These tanks are square or circular in plan and may have hopper bottoms. The influent enters at the bottom.
3.5.5 Filtration
The purpose of filtration is the removal of particulate impurities and flocs from the water being treated. In this regard, the filtration process is the final step in the solids removal process which usually includes the pre-treatment processes of coagulation, flocculation and sedimentation. The degree of treatment applied prior to filtration depends on the quality of water. Typical surface loading rates and detention periods are presented in table3.1
Table3.1: Common Surface Loading and Detention Periods Surface Loading m3/m2/d* Tank Type Range
Plain Sedimentation Horizontal flow, circular Vertical clarifiers * at average design flow
Source: CPHEEO Manual 1999
flow
(upflow)
CEPT, Ahmedabad
23
Design Consideration
Design period 10 years
Plant capacity It would be convenient to convert the daily required volume to a design flow Q, the quantity of water to be treated per hour rather than per day. Thus for a given daily out put the size of plant depends on duration of filter operations. Filtration Rate and No. of filters It is desirable to design filter for a normal filtration head of 0.1 m/hr. Min. of two filter units should be provided. This will restrict the over load rate to 0.2 m/hr when one unit is taken out for cleaning and would ensure uninterrupted productions. For a given area, the optimum number and size of filters which will be only 10% more expensive than the minimum 2 bed unit are given in TABLE.3.2
Table 3.2: Recommended Nos. of Slow Sand Filters for given Plan Areas. Area in sq. m.
Upto 20 20 to 249 250 to 649 650 to 1200 1201 to 2000
Source: CPHEEO Manual 1999
No. of Beds.
2 3 4 5 6
Depth of Filter Box The elements that determine the depth of the Filter Box and their suggested depths are free board ( 0.2m ), supernatant water reservoir (1.0m), filter sand (1.0m), supporting gravel (0.3m), and under drainage system (0.2m) with a total depth of 2.7m. The use of proper depths for these elements can reduce cost of filter box considerably without adversely affecting efficiency.
Description Depth Supernatant water Free board Depth Initial Final (minimum) Size of sand Effective size Uniformity coefficient of filter sand of
CEPT, Ahmedabad
24
Description
Description (U,C)
0.3 m
bricks pipes
perforated
0.2 m
5 6
2.7m 20-30ml
Filter Sand and Gravel: Undue care in the selection and grading of sand for slow sand filters is neither desirable nor necessary. Use of builder grade or locally available sand can keep the cost low. Similarly, rounded gravel, which is often quite expensive and difficult to obtain, can be replaced by hard, broken stones to reduce cost. Guidelines for design of Slow Sand Filter are in Table 3.3.
CEPT, Ahmedabad
25
Filter Sand: Filter sand is defined in terms of effective size and uniformity
coefficient. Effective size is the sieve size in millimetres that permits 10% by weight to pass. Uniformity in size is specified by the uniformity coefficient which is the ratio between the sieve that will pass 60% by weight and the effective size. Shape, size and quality of filter stand shall satisfy the following norms: Sand shall be of hand and resistant quartz or quartzite and free of clay, fine particles, soft grains and dirt of every description. Effective size shall be 0.45 to 0.70 mm Uniformity coefficient shall not be more than 1.7 nor less than 1.3 Ignition loss should not exceed 0.7 % by weight. Soluble fraction in hydrochloric acid shall not exceed 5.0% by weight Silica content should be not less than 90% Specific gravity shall be in the range between 2.55 to 2.65 Wearing loss shall not exceed 3%
Depth of Sand: Usually the sand layer has a depth of 0.6 to 0.75m, but for
higher rate filtration when the coarse medium is used, deeper sand beds are suggested. The standing depth of water over filter varies between 1-2 m. The free board above the water level should be at least 0.5 m so that when air binding problems are encountered, it will facilitate the additional levels of 0.15 to 0.30 m of water being provided to overcome the trouble.
CEPT, Ahmedabad
26
Step-1
Suppose Water demand is 9 mld of a city
Step-2
According to Morrel and Wallance formula, the number of units of a filter plant, N = 1.22 x Sqrt of Q =1.22x 3 = 3.66 say 3 nos.
Step-3
Maximum water demand =demand x peak factor=1.8x9000000 per day Hence per hour demand =(1.8x9000000) / 24 =675000 liter per hour
Step-4
Now let us assume rate of filtration is 4000 liter / hr/ sq.m Hence Total area required for filter beds = water demand/Rate of filtration = 67500/4000 sq.m = 168 .75 sq.m
Step-5
Area of each unit = 168.75 / 3 =56.25 Assuming L=1.5 B; Hence 1.5BxB =56.25 B2 = 56.25Hence B=6.12 say 6.15 m. Hence L=1.5 x6.15=9.20 m. H f 9 ld t it d d 3
id
d filt
ld b d
Preparation of Filter Sand: From a sieve analysis of the stock sand, the
coarse and fine portion of stock sand that must be removed in order to meet the size specifications, can be computed in terms of p1, the percentage of suitable stock sand that is smaller than desired effective size d, which is also equal to 10% b of the usable sand P2, the % of the stock sand that is smaller than the desired 60 percentile size d2. The percentage of suitable stock sand p3 is than=2(p2-p1)because the sand lying between the d1 and d2 sizes will constitute half the specified sand. To meet the specified composition, this sand can contain 0.1p3, i of a sand below d1,size. Hence the percentage of p4, below which the stock sand is too fine to use, is P4=p1-0.1p3=p1-0.2(p2-p1) =1.2p1-0.2p2 Likewise, the %age p5 above which the stock sand is too coarse for use is p5=p2+0.4% of usable sand =p2+0.4x2(p2-p1) = p2 + 0.8(p2-p1) = 1.8 p2 -0.8 p1 Size of gravel and depth of gravel layer shall be determined in accordance with the following rules: For strainer or wheeler type under-drain system, gravel shall be 2 mm minimum size, 50 mm maximum size and 0.3 to 0.5 m deep and
CEPT, Ahmedabad
27
For perforated pipe under-drain system, gravel shall be 2 mm minimum size and 0.5 m in depth
CEPT, Ahmedabad
28
3.5.8 Disinfection
CEPT, Ahmedabad
29
Objective: The primary objectives of the chlorination process are disinfection, taste and odour control in the system, preventing the growth of algae and other micro organisms that might interfere with coagulation and flocculation, keeping filter media free of slime growths and mud balls and preventing possible built up of anaerobic bacteria in the filter media, destroying hydrogen sulphide and controlling sulphurous taste and odour in the finished water, removing iron and manganese, bleaching of organic colour. It can also be used for flushing pipeline before it is brought into operation after carrying out repairs etc. However in such case chlorinator is adjusted to apply chlorine or hypochlorite solution at the rate of 50 ppm. heavily chlorinated water should be allowed to stand in the pipeline for at least 30 min. and preferably for 12 hours before being replaced with potable water. Chlorine reacts with water to form hypochlorous acid (HOCl) and Hydrochloric acid (HCl). This hydrolysis reaction is reversible. The hypochlorous acid dissociates into hydrogen ions (H+) and hypochlorite ions (OCl), free available chlorine is hypochlorous acid and hypochlorite ions. This free available chlorine can react with compounds such as ammonia, proteins, amino acids and phenol which may be present in the water, forming chloramines and chloro-derivatives which constitute the combined chlorine. Chlorination in presence of humic acid and fulvic acid forms Tri-halomethane (THM) which is a heath hazard. The combined available chlorine has less disinfecting properties as compared to free available chlorine. For more details please refer to Manual on Water Supply and Treatment, (1999 Edition).
CEPT, Ahmedabad
30
Process may be of Conventional or tapered flocculation with independent tank or in the form of a clarifier. 6. Sedimentation Tanks may be (circular or rectangular).If circular; it may have either clariflocculators with or without Scrapers. 7. Filters
CEPT, Ahmedabad
31
Filtration process may be by Slow Rapid sand filter or slow sand filter but, in both the cases they will have filter box and filter media 8. Clear Water Tanks Number and size clear water tank may be decided Capacity.
Guidelines
for
Physical
and
Chemical
Characteristic
Turbidity (NTU) Colour ()Units on Platinum Cobalt scale) Taste and Odour pH Total dissolved solids (mg/l) Total Hardness (as CaCO3) (mg/l) Chlorides (as Cl) (mg/l) Sulphates (as SO4) (mg/l) Fluoride (as F) (mg/l) Nitrates (as NO3) (mg/l) Calcium (as Ca) (mg/l) Magnesium (as Mg) (mg/l)
Acceptable
1 5 Unobjectionable 7.0 to 8.5 500 200 200 200 1.0 45 75 < 30
If there are 250 mg/l of sulphates, Mg content can be increased to maximum of mg/l with the reduction of sulphates at the rate of unit per every Units of sulphates 13 14 15 16 Iron (as Fe) (mg/l) Manganese (as Mn) (mg/l) Copper (as Cu) (mg/l) Aluminium (as Al) (mg/l) 0.1 0.05 0.05 0.03 1.0 0.5 1.5 0.2
CEPT, Ahmedabad
32
Sr. No.
17 18 19 20 21 22
Characteristic
Alkalinity (mg/l) Residual Chlorine (mg/l) Zinc (as Zn) (mg/l) Phenolic compound (as Phenol) (mg/l) Anionic detergent (mg/l) (as MBAS) Mineral Oil (mg/l)
Acceptable
200 0.2 5.0 0.001 0.2 0.01
TOXIC MATERIALS 23 24 25 26 27 28 29 30 Arsenic (as As) (mg/l) Cadmium (as Cd) (mg/l) Chromium (as hexavalent Cr) (mg/l) Cyanides (as CN) (mg/l) Lead (as Pb) (mg/l) Selenium (as Se) (mg/l) Mercury (total as Hg) (mg/l) Polynuclear aromatic hydrocarbons (PAH) (g/l) 0.01 0.01 0.05 0.05 0.05 0.01 0.001 0.2 0.05 0.01 0.05 0.05 0.05 0.01 0.001 0.2 Refer 31 Pesticides (total, mg/l) Absent to WHO for water Vol I-
guidelines drinking quality 1993 RADIO ACTIVITY 32 33 Gross Alpha activity (Bq/l) Gross beta activity (Bq/l) 0.1 1.0 0.1 1.0
CEPT, Ahmedabad
33
Recommended guidelines for physical and chemical parameters The figures indicated under the column Acceptable are the limits upto which water is generally acceptable to the consumers. Figures in excess of those mentioned under acceptable render the water not acceptable but still may be tolerated in the absence of an alternative and better source but upto the limits indicated under column Cause for Rejection above which the sources will have to be rejected. It is possible that some mine and spring waters may exceed these radio activity limits and in such cases it is necessary to analyze the individual radio-nuclides in order to assess the acceptability or otherwise for public consumption.
Guideline value
CEPT, Ahmedabad
34
Table 3.4 Recommended Treatments for Different Water Sources to Produce Water with negligible Virus Riska type of sources ground water protected, deep well; essentially free of faecal contamination unprotected, shallow wells; feacally contaminated surface water protected, impounded upland water; essentially free of faecal contamination unprotected impounded water or upland river; faecal contamination unprotected lowland contamination unprotected lowland faecal contamination rivers; rivers; faecal heavy pre-disinfection or storage, filtration, disinfection pre-disinfection or storage, filtration, additional treatment and disinfection not recommended for drinking water Recommended treatment disinfection filtration and disinfection disinfection filtration and disinfection
For all sources, the median value of turbidity before terminal disinfection must not exceed 1 nephelometric turbidity unit (NTU). Terminal disinfection must produce a residual of free chlorine of > 0.5 mg/litre after atleast 30 minutes of contact in water at pH < 8.0, or must be shown to be an equivalent disinfection process in terms of the degree of enterovirus inactivation (>99.99 %).
Filtration must be either slow and siltration or rapid filtration (sand, dual, or mixed media) proceeded by adequate congulation-flocculation (with sedimentation or floatation). Diatomaceous earth filtration or filtration process demonstrated to achieve > 99 % enterovirus reduction.
Disinfection should be used if monitoring has shown the presence of E.coli or thermo-tolerant coliform bacteria.
Source: W.H.O. guidelines for Drinking Water Quality - 1993 Note: The figures indicated under the column 'Acceptable' are the limits up to which water is generally acceptable to the consumers. Figures in excess of those mentioned under 'Acceptable' render the water not acceptable, but still may be tolerated in the absence of an alternative and better source but up to the limits indicated under column "Cause for Rejection" above which the sources will have to be rejected.
CEPT, Ahmedabad
35
Peak Factor
3.00 2.50 2.00
While designing the pipe section velocity through pipe section is assumed 0.8 to 1.6 m/s .As a rule of thumb for design assume higher velocity of 1.2 to 1.4 In normal case it is assumed 1.4 m/s With assumption of velocity diameter of the pipe section is determined by Q= [(/4)d2 ] v (where Q in m3/s)
CEPT, Ahmedabad
36
The pipe section and material is fixed for calculating head loss through the section. It is important to know the residual pressure of water flowing through the pipelines wherein the hydraulic gradient over its entire length lays above the crown / sofit of the pipelines. However the designed pipeline is governed by Hazen-Williams equation.
which can be used for computing the head loss due to friction in pipes. Where v is velocity of water flowing through the pipe. ,f ,L ,g ,D frictional factor length of the pipes is acceleration due to gravity Diameter of the pipe.
But, f is independent of the pipe material and therefore not in use. The Standard HazenWilliams formula commonly in use for Head loss calculation through pipe section Q=3.110-4 c D2.63 S0.54 Where Q is in KLd, C is H-W coefficient, D is in mm, And S is hydraulic loss in mt / mt
CEPT, Ahmedabad
37
The values of the Hazen Williamss coefficient C for new conduits and the values as recommended in the Manual on Water Supply and Treatment third edition-revised 1999,Ministry of Urban Development, Government of India to be adopted for design purposes are recommended as under in table 3.6.
Projection Method Cement Mortar lined Metallic Pipes Cast Iron , Ductile Iron and Mild Steel Pipes Non Metallic Pipes RCC Spun Concrete , Prestressed Concrete Up to 1200 mm dia. Above 1200 mm dia. Asbestos Cement PVC , GRP and other Plastic pipes
Source: CPHEEO manual 1990
@ The C value for new pipes included is for determining the acceptability of surface finish of new pipelines # The quality of galvanizing should be in accordance with the relevant standards to ensure resistance to corrosion throughout its design life. * For pipes of diameter 500 mm and above. The range of C values may be from 90 to 125 for pipes having diameters less than 500 mm. And Check the velocity of flow through pipe by equation V=4.567103CD0.63 S0.54 Where D is in mm and v is in m/s
CEPT, Ahmedabad
38
The results obtained by its use suffer from considerable inaccuracies. Thus its use resulted generally in over- designing of pipelines. may be nonavailability of design In spite of the fact that the modified H-W formula is more rational, it is not being widely used at present. One of the reasons aids for the same. Calculate actual Hydraulic loss as actual length of pipe section H Loss = S L /1000 mt. Where, S = slope, L = length Calculate cumulative hydraulic loss adding 10% extra loss for unaccounted losses flowing direction of water through pipe. Now considering the reduced level of source of supply and tail end of the pipe section calculate the Residual Pressure.
CEPT, Ahmedabad
39
Box-1 SampleCalculation
-5.1
Water discharge demanded in2011 one Q= 135 lpd mld Diameter main water ESR supplying from t of pipe day for is 3 6324
=2561220 =2.56
CEPT, Ahmedabad
40
to 28 lakhs gallons i.e. 12.75 M.L., provide ground storage 10 M.L. and elevated stage - 3 M.L.
Storage capacity 13 M.L. to be filled up in 14 hours. In let pipe capacity...... = 0.9285 ML/hr. = 0.2579 m3/ sec Assume velocity 1.2 mt/sec. The size of inlet main work out to 0.258 = A x 1.2 D= 523 mm Say 500 mm M.S. or 450 mm D.I. Size of ESR-GSR: Size of GSR . 10 ml capacity provide two compartment Capacity of one compartment - 5 ml = 5000 m3 Provide water depth 4.5 mt. Therefore area 5000m3 = 1111.11 sq.mt. 4.5 Provide rectangular size L X B = 1111.11 sq.mt. Assume L = 1.25 B Therefore, 1.25 B x B = 1111.11 Therefore, B2 = 1111.11 = 888.88 1.25 Therefore, B = 29.81 mt. Say 30 mt. therefore, L = 37.50 Provide GSR size 37.5 x 30 x 4.5 = 5062.5 m3 Size of ESR . Capacity of ESR is proposed of 3 ML. Therefore, provide ESR with shaft dia. - 15.0 mt. and water depth in container 6 mt Height of ESR 25 mts. 13 14
CEPT, Ahmedabad
41
(3)
Design of pumping machinery Provide electrically driven C.F. sets Total period of supply - 6 hrs. Quantity to be supplied - 17.02 ML present = 2836.66 m3/hr 21.79 ML Future = 3631.66 m3/hr Provide 3 set working for present demand Therefore, size 2836.66 = 945.55 Say: 946 m3/hr 3 For ultimate demand 4 sets will be working. Therefore, 946 x 4 = 3784 m3/hr > 3632 m3/hr
Therefore, provide six sets each having capacity ,946 m3/hr against head of 35 mt. Therefore K.W. = 946 x 35 x 1.15 = 129.61 367.2 x 0.8 Actual load 20 KW 800 KW For present stage 100% standby (3+3) For ultimate stage 50% standby (4+2) (4) Design of pipe size Rising main from P.H. to ESR Total quantity 946 x 4 = 3784 m3/hr Assume velocity 2 mt/sec. 1.051 = A x 2 d= 818 mm dia. Say 800 mm dia. for ESR Size of inlet Size of outlet Size of over flow Size of washout 800 mm dia 850 mm dia - 850 mm dia - 200 mm dia 1.051 m3/Sec. Say 130 KW Therefore, Total K.W. .. 130 x 6 = 780 KW
Refer Guidelines and Specification for Civil, Mechanical and Electrical works which are provided in CD
CEPT, Ahmedabad
42
CEPT, Ahmedabad
43
Soil bearing capacity and type of strata expected to be met at the time of construction. Onsite disposal facilities, including the possibilities of segregating the sullage water and sewage and reuse or recycle sullage water within the households.
Component
Collection System
Clarification
The system should be designed for the prospective population of 30 years as its
30
CEPT, Ahmedabad
44
Sr .N o
Component
Clarification
replacement is not possible during its use
Stations
Duplicating machinery within the pumping 30 station would be easier/cost of civil works will be economical for full design period. 15 Life of pumping machinery is Generally 15 years The construction may be in a Phased manner as initially the flows may not 30 reach the designed levels and it will be uneconomical to build the full capacity plant initially. Provision of design capacities in the
Pumping Machinery
Sewage Plant
Treatment
30
CEPT, Ahmedabad
45
Peak factor
3.00 2.50 2.25 2.00
For circular conduit Hydraulic radius R = D/4 Hence For circular conduit , V = (1/N ) 0.003968 D2/3 S1/2 And Qt = (0.2693/106 ) (1/N) D
8/3
S1/2
Where Qt = quantity of flow in mld D = dia . of the pipe in mm N = Manning`s coefficient of roughness S = slope of hydraulic gradient (generally slope of pipelines) Values of 1 in L (gradient) are obtained which are inverse values of slope i.e. 1/S The values of Manning`s Coefficient (Coefficient of Roughness) recommended for different pipe materials are given below.
CEPT, Ahmedabad
46
Type of Pipe Material Sault glazed stoneware pipes Cement Concrete Pipes. (with collar joint).
Spun concrete pipes (RCC & PSC) with Socket spigot joints (Design Value) Steel (a) Welded (b)Rivetted (c) Slightly tuberculated (d) With spun cement mortar lining Caste Iron (a) Unlined (b) With spun cement mortar lining Asbestos cement Plastic (smooth) 0.013 0.011 0.011 0.011 0.013 0.017 0.020 0.011 0.011
As the pipes used for sewers and drains are mostly stoneware , cement concrete , RCC and PSC , most of the design work is covered in using the value of N = 0.015 , 0.013 and 0.011. however for sewage pumping main CI and MS/Steel pipe could be used. Getting size and gradient is not final but, it should be checked for velocity of flow by expression Vt = (1/N) 0.003968 D2/3 S1/2 Where Vt is velocity of flow of discharge Qt Now it should be checked for minimum velocity v when ratio is Qp/Qt = v/Vt and Qf/Qt = v/Vt
CEPT, Ahmedabad
47
The partial flow elements viz. area, velocity, discharge etc. are expressed as ratios of the corresponding full flow values. These ratios are tabulated in the following table 4.3 Table 4.3: Hydraulic Check d/D
1.0 0.9 0.8 0.7 0.6 0.5 0.4 0.3 0.2 0.1
v/V
1.000 1.124 1.140 1.120 1.072 1.000 0.902 0.776 0.615 0.401
q/Q
1.000 1.066 0.968 0.838 0.671 0.500 0.337 0.196 0.088 0.021
D = Full Depth of flow (internal diameter of pipe) V = Velocity at full depth v = Velocity at depth partial q = Discharge partial (at present population and Q = Discharge at full future population)
In actual design the discharge ratio q/Q for the pipe is first known and the velocity of flow, depth etc. at the partial flow condition are required to be calculated. Table is given for values of ratio v/V and q/Q for different values of d/D
CEPT, Ahmedabad
48
With improved standards of workmanship and quality and availability of various construction aids, these values should tend to the minimum, rather than the maximum. These values should not mean any relaxation on the water tightness test requirements in Hydraulic testing of pipe sewers.
CEPT, Ahmedabad
49
If this practical situation is accepted, the sewer velocity criteria looses the significance with which it is all along associated. The sewer design therefore has to be guided by the limitations of depth and practicalities such as minimising the number of pumping stations (for obvious reasons).
4.6.8 Joints
Joints provided need to be of either collar joint or spigot & socket joint with a rubber ring.
Dia. Of Pipe section flowing collected wastewater to treatment plant = sqrt of [(Qd 4) / (3.14 V)] =sqrt of [ (2561220 4) /( 1000 24 60 60 3.14 0.80) ] = 0.217 mt. = 250 mm
8/3
Gradient = 1/s = 1/ 0.00248 = 1 in 403.22 mt = 1 mt fall in 403 mt length Design Velocity V = (1/N ) 0.003968 D2/3 S1/2 = (1/.013) 0.003968 2502/3 0.002481/2 = 0.603 mt/sec q / Qd ratio = 1.84 /2.56 =0.72 , from above table for q/Qd v/V ratio = 1.08 ; therefore v = 1.08 0 .603 mt/sec = 0.65 mt/sec which is > 0.3 mt/sec O.K Qf /Qd = 2.05/2.56 =0.800 From above table for Qf / Qd , v/v ratio = 1.109 Therefore v = 1.109 0.603 mt./sec
CEPT, Ahmedabad
50
CEPT, Ahmedabad
51
Load Factor: The load factors for the different classes of bedding are given in Table 4.5. Table 4.5: Load Factors for Different Classes of Bedding Class of bedding
A A A a b c
Condition
Concrete cradle-plain concrete and lightly tamped backfill Concrete cradle-plain concrete with carefully tamped backfill Concrete cradle RCC Arch type plain concrete RCC with P - 0.4 %
Load Factor
2.2 2.8 Up to 3.4 2.8 Up to 3.4 Up to 4.8
d crown)
RCC with P 1.0 % (P is the ratio of the steel to the area of concrete at the Shaped bottom or compacted granular bedding with
B C D
carefully compacted backfill Shaped bottom or compacted granular bedding with lightly compacted backfill Flat bottom trench
The granular material used must stabilize the trench bottom in addition to providing a firm and uniform support for the pipe. Well graded crushed rock or gravel with the maximum size not exceeding 25mm is recommended for the purpose. Where rock or other unyielding foundation material is encountered, bedding may be according to one of the Classes A,B or C but with the following additional requirements. Class A: The hard unyielding material should be excavated down to the bottom of the concrete cradle. Class B or C: The hard unyielding material should be excavated below the bottom of the pipe and pipe bell to a depth of atleast 15cm. The width of the excavation should be atleast 1.25 tomes the outside dia of the pipe and it should be refilled with granular material. Total encasement of non-reinforced rigid pipe in concrete may be necessary where the required safe supporting strength can not be obtained by other bedding methods. The load factor for concrete encasement varies with the thickness of concrete. The effect of M-200 concrete encasement of various thickness on supporting strength of pipe under trench conditions is given in fig.
CEPT, Ahmedabad
52
Supporting strength in Embankment Conditions The soil pressure against the side of a pipe placed in an embankment may be significant in the vertical load of the structure. Classes of Bedding for projecting conduits The beddings which are generally adopted for projecting conduits laid under the embankment conditions of installation are illustrated in figure 4.1. The classification of the bedding is as under: Class A: In this case the conduit is laid on a mat of concrete. Class B: the conduit is laid on accurately shaped earth to fit the bottom of the pipe and the sides are filled with thoroughly damped earth. CLASS C : In this type of bedding the conduit is laid on accurately shaped earth to fit the bottom surface of the conduit. For rock foundations the conduit is laid on a layer of granular cushion and the sides of the conduit are filled up. CLASS D: The conduit is laid on earth not shaped to fit the bottom of the conduit. In case of rocky soil the conduit is laid on a shallow granular cushion. Load Factor The load factor for rigid pipes installed as projecting conduits under embankments or in wide trenches is dependent on the type of bedding. The magnitude of the active lateral soil pressure and on the area of the pipe over which the active lateral soil pressure and on the area of the pipe over which the active lateral pressure acts. The load factor for projecting circular conduits may be calculated by the formula 1.431 L1 = Where L1 = the load factor N z q = A parameter dependent on the type of bedding = a parameter dependent upon the area over which the lateral pressure acts = the ratio of total lateral pressure to total vertical load on pipe. Nzq
effectively and
Positive Projecting Conduits The ratio q for positive projecting conduits may be estimated by the formula q = (mk /C0) [(H/B0) + (m/2)] Where, k = The Rankines ratio which may be taken as 0.33. The value of N for different types of bedding for circular pipes are given in table 6.7
CEPT, Ahmedabad
53
Fig 4.1 Classes of Bedding for Projecting Conduits Table4.6: Values of N for Different Pipe Beddings Type of Bedding
A Reinforced concrete cradle A - Plain concrete cradle B C D
Source: CPHEEO manual 1993
Value of
CEPT, Ahmedabad
54
Table 4.7: Values of Z For Different Pipe Beddings Fraction of conduit on which lateral pressure acts m
0.00 0.3 0.5 0.7 0.9 1.0
Source: CPHEEO manual 1993
Other Beddings
0.000 0.217 0.423 0.594 0.655 0.638
Negative Projective Conduits The load factor for negative projecting conduits may be determined by the equations (6.15) and (6.16) with value of k of 0.15. Provided the side fills are well compacted. Imperfect Trench Conditions The equations for positive projecting conditions will hold good for those conditions as well. Conduits under Simultaneous Internal Pressure and External Loading Simultaneous action of internal pressure and external load gives a lower supporting strength of a pipe than what it would be if the external load acted alone. If the bursting strength and the three edge strength of a pipe are known. The relation between the internal pressure and external loads which will cause failure may be computed by means of the formula t = T (1-s2) S where t = internal pressure in kg/cm2 at failure when external load is simultaneously acting T = bursting strength of a pipe in kg/cm2 when no external load is simultaneously acting s = three- edge bearing load at failure in kg/linear metre when there is no internal pressure simultaneously acting. Relationship between the different elements in structural design .6.17
The basic design relationship between the different design elements are as follows for grid pipes
Safe working strength = Ultimate three edge bearing strength Factor of safety
CEPT, Ahmedabad
55
Recommendations The factor of safety recommended for concrete pipes for sewers is 1.5 which is considerably less as compared to that for most engineering structures which have a factor of safety of atleast 2.5. As the margin of safety against the ultimate failure is low, it becomes imperative to guarantee that the loads imposed on sewer pipes are not greater than the design loads for the given installation conditions. In the order to achieve this objective the following process are recommended. Width of the trench specified for a particular job should be minimum in consonance with the requirements of adequate working space to allow access to all parts and joints of pipes. Specification should lay proper emphasis on the limit of the width of trench to be adopted in the field which should not exceed that adopted in the design calculations. Any deviations from this requirement during the construction should be investigated for their possible effect on the load coming on the pipe and steps should be taken to improve the safe supporting strength of pipe for this condition of loading by adopting suitable Bedding or such other methods when necessary. The field Engineer should keep in touch with the Design Engineer throughout the duration of the project and any deviation from the design assumptions due to the exigencies of work should be immediately investigated and corrective measures taken in time. All pipes used on the work should be tested as per the IS specifications and test certificates of the manufactures should be furnished for every consignment brought to the site. Whenever shoring is used, the pulling out of planks on completion of work should be carried out in stages and this should be properly supervised to ensure that the space occupied by the planks is properly backfilled. Proper backfilling methods both as regards to selection of materials, methods of placing and proper compaction should be in general agreement with the design assumptions.
CEPT, Ahmedabad
56
However, additional manholes are to be provided on junctions of the street avoiding standard distance.
CEPT, Ahmedabad
57
Sr. No 1
Item
Oxidation Ditch
Performance BOD removal (%) Coliform removal(%) Land Requirement( m2/capitat excluding post treatment) Energy Requirement KWH/Person/Y ear
80-90 60-90
95-98 60-90
75-85 60-90
75-85 60-99.9
75-85 Insignificant
0.18-0.25
0.20-0.30
0.15-0.20
0.30-0.40
2.0-2.8
0.15-0.20
12-15
7-11 Trickling filter arms, recycle pumps, sludge scrappers, thickeners, digester equipments,
16-19
12-15
nil
Equipment Requirement
Aerators
nil
CEPT, Ahmedabad
58
Sr. No
Item
Oxidation Ditch
5 6
Level of Supervision
Skilled
Simplest
Cost(in lacs) Capital cost 35 25 /MLD O&M 1.5 0.75 Cost/MLD/Year Source: Master Plan of Somdrup Jonkha Bhutan, 2007
15 1.25
9 1.25
General
The Plant shall be designed, selected and installed taking into account site ambient conditions, local conditions and location. The following site conditions shall apply ambient temperature (plant room) - 35oC annual average temperature - 30oC Relative humidity (maximum) - 75% Altitude - 125 m site conditions - semi-arid
The plant shall be designed for an ambient temperature of 40 C and making due allowance in his designs for the increased temperatures experienced by Plant exposed to direct sunlight.
CEPT, Ahmedabad
59
chamber to discharge point. Hydraulic Detention Time shall be 60 seconds minimum at peak flow.
flow (minimum) f) screen at peak flow Flats of screen Tapered in g) the direction of flow (front x back x depth ) h) i) Clear opening between two flats at back Free board above TWL 12 mm 0.5 m 10 mm x 8 mm x 75 mm 1.2 m/sec
CEPT, Ahmedabad
60
i) j)
Filed
correction
factor
for
surface loading Detention time (minimum) Minimum depth of wall in grit chamber mm) at outlet weir
0.80 60 sec
k)
excluding corner filling of 300 Organic matter in washed grit not to exceed Free board above TWL
0.9
l) m)
3 0.5
% m
CEPT, Ahmedabad
61
Note: All piping/channels and launder of primary settling a) tank shall be designed for peak flow including any other flows as per layout plan with minimum velocity of 0.6 m/sec at average flow. All peripheral launder of primary settling tank shall b) c) d) be designed for peak flow with velocity of 0.9 m/sec and any other flow as per layout plan. 0.5 50 m mm Free Board of peripheral launder (minimum) Free fall in peripheral launder /trough with respect to weir crest (bottom-most portion of V Notch).
E. Aeration Tank
a) b) Peak flow Average flow 114.75 51 One c) Number of tanks tank with two compartments to deal with avg. flow plus all other flow as per Detention time at average flow + d) 25% of avg. flow return sludge + all other flows as per f) g) h) i) j) k) l) m) n) o) p) volume (check) MLSS in aeration tank MLVSS in aeration tank Food to micro-organism ratio (F/M) (i.e. kg BOD5 @ 27C/kg MLVSS) Sludge age (c) minimum Free board above TWL Oxygen requirement Oxygen transfer required at layout plan. 0.3 0.6 2000 mg/1 80% of MLSS 0.2-0.4 10 days 1.0 m 1 kg O2 /kg of BOD 3 @ 27 c removed 2.0 1.5 1.22 0.015-0.026 Kg/ kW. Hr. mg/1 kg O2/KWhr KW/m3 Kg BOD 3 27c loading/m3 of tank Six hours minimum layout plan. mld mld
standard condition (min) Dissolved oxygen to be maintained in the aeration tank (minimum) Field transfer rate of aerators (minimum) FTR Mixing requirement of KW
CEPT, Ahmedabad
62
All pipes/channel to secondary settling tanks shall a) be designed for peak flow including other flows as per b) c) d) layout plan layout 0.50 m 0.05 m All weir and troughs of secondary settling tanks shall be designed for peak flows as per plan with velocity of 0.9 m/sec. Free board (minimum) Free fall in peripheral launder /trough with respect to weir crest (bottom-most portion of V Notch).
CEPT, Ahmedabad
63
G. Digesters
a)
b) c) d) e) f) g) h) i) j) k) l) m) n) o) p)
4
50% 1.07 60 30 30 15 8 2 0.75 1 V to 4 H Gas mixing unconfined 0.005 1 50-80 0.05-0.10 5 15-35
H. Gas Holder
a) b) c) d) e) Gas production in sludge digester Gas is to be utilized in plant. Storage capacity of gas. Gas to be burnt Number of units required 0.9 Future (not in present contract) 1 100% 2 nos day m3/kg destroyed of VSS
CEPT, Ahmedabad
64
M. Pipeline
a) b) Pipeline for Main plant by pass from inlet chamber to final disposal point Pipeline from distribution chamber ahead of PST to main plant bypass
CEPT, Ahmedabad
65
c) d) e) f) g) h) i) j) k)
Pipeline from distribution chamber ahead of aeration tank to main plant bypass Treated effluent pipeline from SST to common collection chamber and pipeline from common collection chamber to final disposal point Channel From inlet chamber to screen chamber Channel from Screen chamber to grit chamber. Channel from Grit chamber to parshall flume. Pipeline from distribution chamber of PST to PST Central feed well Pipeline from PST outlet to distribution chamber of aeration tank Pipeline from outlet of Aeration Tank to of central feed well SST Washout for aeration tank shall be provided and connected to bypass line for emptying the unit by gravity with a minimum size of 450 mm dia DI, K-9 class pipeline with valve of same size
Standard indicated in table below are for treated sewage to be disposed into inland water bodies e.g. River However these standards vary as per the geographical location of the town
Sample Effluent from PST Compliance Requirement BOD < 150 mg/1 SS < 250 mg/1 BOD < 20 mg/1 Effluent from SST SS < 30 mg/1 pH 6 to 9
Source: DPR of Drainage and STP for Rajkot City
Refer Guidelines and Specification for Civil, Mechanical and Electrical works which are provided in CD
CEPT, Ahmedabad
66
permitted.
The frequency of such permissible flooding may vary from place to Though such
place, depending upon the characteristics of the drainage area. considering the economy in the cost
The estimation of such runoff reaching the storm water drains therefore is dependent on: Intensity and duration of rainfall Characteristics of the drainage area Time required for such flow to reach the storm water drains.
Estimation of Run off The runoff reaching the drain is given by the rational method viz. Q = 10 CIA Where,Q is the runoff in m3 / hour C is the coefficient of runoff I is the intensity of rainfall in mm / hour A is the area of drainage zone in hectares Storm frequency considered for the design is adopted as frequency of once a year. In absence of data from IMD, based on general equation by British Ministry of Health, the intensity of rainfall adopted for the design is 20 mm / hour and the duration of storm (t) in minutes, expressed by the mathematical formula adopted is as under : i = 1000 t + 20 Source: Sanitary Engineering by Prof. Vinayak N. Gharpure From this formula, for different values of intensities, corresponding values oft are worked out. These values of i &t are plotted on graph and the values of intensity (i) can be determined for any given time of concentration (tc) i.e. tc = inlet time + time of flow in the drain tc = t(i) + t(f) The portion of rainfall which finds its way to the drains is dependent on the imperviousness and the shape of the drainage area, apart from the duration of storm. The percentage of imperviousness for built-up area is considered as 90% and for the open area is considered as 20%. estimated. Therefore, the weighted average imperviousness of the drainage area for the flow, concentrating at a point is
CEPT, Ahmedabad
67
Diameter wise Length of Storm Water Drain Pipes in meter Besides, as required by the client, the storm water drains are proposed on both sides of the roads; so that road cutting is avoided while giving consumer connection to the plot holders. For the collection and disposal of storm water, RCC pipes are proposed as storm water drains. Manholes are proposed on straight stretches of pipe drains at distance of 30 m, staggered on both sides of drains. Besides, additional manholes are also provided at change of direction of drains as well as size of drainpipes. Catch pits, outlet structures are also proposed at various locations to collect and discharge the storm water in the drainage system.
CEPT, Ahmedabad
68
Method Rational
Intensity duration relationship Rainfall hyetographs
Hydrograph Simulation
UK Wallingford runoff model Fixed runoff coefficients SCS runoff model Time of entry peak flows pipe full velocity Linear reservoir model MuskingumCunge Overflows Pumps On-line and Off-line storage Muskingum-Cunge Backwater Overflows Pumps On-line & Off-line storage Tide levels Flap valves Surcharge
Ancillary structures
Source:
CEPT, Ahmedabad
69
Paper
Glass
Metals
Inert
Percentage 2.91 2.95 4.71 3.18 6.43 0.56 0.35 0.46 0.48 0.94 0.33 0.32 0.49 0.59 0.8 43.59 48.38 44.73 49.07 53.9
CEPT, Ahmedabad
70
12 15 9 3 4
Quantity of waste India produces about 42 million tons of urban solid waste annually. The current municipal solid waste generation is estimated to be approximately 0.4 kilograms per person per day. Waste generation ranges from 0.2 kilograms to 0.6 kilograms per capita per day in cities ranging from 1 lakh to more than 50 lakh population.
Table 6.3 Quantity of Municipal Solid Waste in Indian Urban Centres Population Range (in million)
< .1 0.1 to 0.5 0.5 to 1.0 1.0 to 2.0 2.0 to 5.0 >5
Density of waste Knowledge of the density of a waste i.e. its mass per unit volume (kg/m3) is essential for the design of all elements of the solid waste management system viz. Community storage, transportation and disposal. For example, in high income countries, considerable benefit is derived through the use of compaction vehicles on collection routes, because the waste is typically of low density. A reduction of volume of 75% is frequently achieved with normal compaction equipment, so that an initial density of 100 kg/m3 will readily be increased to 400 kg/m3. In other words, the vehicle would haul four times the weight of waste in the compacted state than when the waste is loose. The situation in low-income countries is quite different: a high initial density of waste precludes the achievement of high compaction ratio. Consequently, compaction vehicles offer little or no advantage and are not cost-effective.
CEPT, Ahmedabad
71
Moisture Content Moisture content of solid wastes is usually expressed as the weight of moisture per unit weight of wet material. Moisture Content (%) =
Wet weight dry weight wet weight x100
A typical range of moisture contents is 20 45% representing the extremes of wastes in an arid climate and in the wet season of a region having large precipitation. Values greater than 45% are however not uncommon. Moisture increases the weight of solid waste and therefore the cost of collection and transport. Consequently, waste should be insulated from rainfall or other extraneous water.
CEPT, Ahmedabad
72
CEPT, Ahmedabad
73
3 cmt volume 4 cmt volume Calculate secondary containers = [(Projected Population 0.210)Density] Decided container
6.12 Sample Financial Estimates for implementation of Solid Waste Management Plan
Total population (2001) : 30,871 Total population (2005) : 38,097 Total Households (HHs) : 8466 (Household size : 4.5) ( as per above HH size) (Source: Economical Survey, NSSO,2002)
CEPT, Ahmedabad
74
: 7485 : 981
Solid waste generation (2005) Assuming one person generates 220 gm / day : 8.38 tonnes /day Assuming 30 % extra for other institutes : 10.89 tonnes/day
Door to door waste collection from all residential and commercial area Street sweeping Secondary storage of wastes at fixed locations on streets Transportation of waste from secondary storage points to the landfill site Disposal, Composting of waste
B. Door to door waste collection from all residential and commercial area a. Collection of waste from non-slum residential HHs In this areas, Tricycles and Auto tippers will be provided. Total HH = 7485 One Auto tipper can collect waste from 1000 HHs. If 3 auto tippers are provided : no of HH covered : 3000 One Tricycle can collect waste from 300 HHs. No of Tricycles required = 4485 / 300 = 14.95 = 15
Auto tipper = 3 Tricycle = Workers = 15 18
b. Door to door waste collection from slum areas In this area, community bins of capacity 40 liters will be provided for every 15 HHs. No of HHs = 981 No of community bins required = 981 / 15 = 65.4 To empty those bins, 3 handcarts will be provided.
Handcarts = 3 Workers =3 Community bins = 65
c. Door to door collection from commercial areas In this area, tricycles will be provided which will cover, 400 shops each. Total shops (commercial properties) = 1773 (source: Property tax data, 2005)
CEPT, Ahmedabad
75
Assuming 3 km stretch of roads covered by commercial area, where litterbins of 40 liters capacity each, will be provided to collect the waste generated by the passer-by. Providing one litterbin per 60 meters of road length. No of litterbins required = 3000 / 60 = 50 nos.
Litterbins = 50
C. Street Sweeping: The roads in the whole town will be divided into 4 categories as per the requirement of sweeping: Total road length in town: 65 km (including NH no 8) One Sweeper will sweep 1000 RML (running meter length) of road per day. Road Class
A B C D
Frequency cleaning
Daily Twice a week Once a week Once a fortnight
of
Workers required
= 12 = (18 * 2 )/6 = 6 = (30*1)/6 = 5 = (5 * 0.5 )/6 = 0.41 = 1
= 24 = 24
D.Secondary storage of wastes at fixed locations on streets Assuming 60 % of the total waste generated to be wet waste = 6.6 tonnes/day Dry waste = 4.4 Tonnes/day Providing containers of size 4 cum (storage capacity = 1.6 tonnes) for wet waste collection and of size 2 cum (storage capacity = 0.8 tonnes) for dry waste collection. Number of containers required = 4 cum size : 4 + 2 (extra for replacement) = 6 2 cum size : 6 + 2 (extra for replacement) = 8
CEPT, Ahmedabad
76
Activity
Door to Door collection of waste (Res+com) Waste collection from slums Street Sweeping Transportation (2 vehicles) Absentees (8 %) Total
No of workers
18 + 5 3 24 8 4 62
Primary Collection
No of workers required = 62 48 = 14
Table 6.6: Financial Estimates Units to be procured (units required available) Total Cost
Activity
Equipment required
No of units required
Rate / unit
CEPT, Ahmedabad
77
Sub -Total CONTAINERS For Wet waste 4 cum capacity For Dry waste 2 cum capacity Commercial area Slum Area Container placement Container Container Litterbins Community bins Platform 6 8 50 65 6 35,000 23,000 300 300 2000 Subtotal 6 8 50 65 6
4,75,530
STREET SWEEPING
Handcarts Brooms Supadi Patra 24 24 24 30 35 Subtotal Total 9,16,030
(Please note that the cost Shown above is indicative and may vary from place to place)
CEPT, Ahmedabad
78
Sample Terms of References for Design of landfill site & EIA sets for following objectives _ To visit the proposed site, in order to assess whether the site confirms to the preliminary location criteria for site identification. To collect the baseline information on the quantity of waste generation, type of waste. To estimate the land area required for the disposal of the solid waste generated for 30 years. To collect the information in and around the proposed site area limited to technical aspects such as Air, Surface Water, Soil, Geology, Hydrogeology and Meteorology To develop surface drainage pattern of the site area at regional and local level in order to ascertain the surface drainage run-on direction as well as magnitude To develop the Land Use & Land Cover Mapping based on Remote Sensing IRS-1C To carry out the Soil Investigation of the proposed site area. To carry out the ambient air quality monitoring in order to ascertain the background contamination level. To carry out the ground water quality monitoring in order to ascertain the background contamination level. To assess potential impacts on all components of environment resulting from the construction & operation of a Municipal Landfill Facility. To carry out Risk Analysis and suggest abatement methods for adverse environmental impacts likely to occur during the operation of Municipal landfill facility.
As per 2001 census the population of the Rajkot city is 10.02 lacs which is growing at the rate of 4.05% annually. As per the house hold survey and actual quantification at Sold Waste Processing plant, it is observed that waste generation in Rajkot city is about 325 gm/capita/day. Integrated Solid Waste Processing Plant at Rajkot is operated by a private operator and is functioning very efficiently since December -2005. It is recorded that about 68 % of total
CEPT, Ahmedabad
79
waste is being processed and converted in to about energy pallet, manure green cock and eco bricks. Rajkot Municipal Corporation Landfill Estimation of the area, height and capacity required for land fill site. ( Pl. refer CPHEEO Manual Annexure: 17.1 ) Present population = 1243250 Average annual Growth rate = 4.00% Design active period =30 years. Present waste generation = 325 gms /capita /day Total waste generation per year at present = 1243250*325* 365/(1000*1000) = 147480 tones Total biodegradable waste goes to processing plant is 68 % of total waste = 147480 *0.68 tones = 100286 tones Total non biodegradable waste goes to land fill site
is 32% of total waste. = 147480 * 0.32 = 47194 tones
Waste generated after 30 years = 153068 tones Total waste generated after 30 years = 3003929 tones Total volume of waste in 30 years (taking density
of the waste is 0.90 t/cum. As inert waste is more) = 3003929/0.85 = 3534034 cum.
Total volume of daily cover in 30 years Taking 10 cm. soil cover for lift ht. 1.5m. = 0.1 * 3534034
= 353403 cum.
and allowing the total ht. 10mt. so taking k = 0.25 = 0.25 * 3534034
= 883508cum.
Volume likely to become available within 10 years Due to settlement, as waste having more inert material Taking m =0.05 = 0.05 * 3534034
= 176701 cum.
First estimate of landfill capacity = 3534034+353403+883508-176701 = 4594244 cum. Area required for land filling for 10mt. ht. = 4594244/10 = 459424 sq.mt. Area required for infrastructural facility = 15% of land filling area = 0.15 * 459424 = 68914sq.mt.
Total area required = 459424 + 68914 = 528338 sq.mt. Total area required in hectare = 528338/10000 = 52.83 hectare Say = 53 hectare
CEPT, Ahmedabad
80
LOCATION / KNOCK OUT CRITERIA A Location Criteria given in Guidelines developed for the Management of Municipal Waste by the Ministry of Urban Development was used to select the site on prima facie as the first step of site assessment and investigation. The objective of this step is to exclude the areas, which can be discarded for the setting up of landfill. The selection of an appropriate site for a landfill is dependent on several criteria, some of which absolutely exclude the possibility of establishing a landfill in certain sites. The following key factors are considered in evaluating these criteria: Historical, religious or other important cultural sites or heritage Existing or planned drinking water protection and catchments areas High flood prone area Area with unstable ground like swamps, moors and / or marshes Areas with an extreme morphology (steep slopes, danger of landslides or avalanches etc.) Areas endangered by swallow holes, collapse sites, deep digging etc. Areas nearer than 500 meters to populated areas Closer than 100 meters to river boundaries Areas nearer than 20 km to airports National parks, nature protection areas and nature monuments, areas with a large number of fauna and flora
CEPT, Ahmedabad
81
References
Manual of Ministry of Road Transport and Highway (MORTH) Indian Road Congress (IRC codes) IRC 86-1983 Geometric Design for Urban Roads in Plains IRC 81-1997 Flexible Road Pavements BIS code 2720 various parts for tests on soils BIS Code 2386 various parts for tests on aggregates Manual on Water Supply and Treatment Plant third edition revised - 1999 constituted by CPHEEO- Central Public Health and Environment Engineering Organization, Ministry of Urban Development, New Delhi, G.O.I Manual on Sewerage and Sewage Treatment second edition 1993 constituted by CPHEEO- Central Public Health and Environment Engineering Organization, Ministry of Urban Development, New Delhi, G.O.I Municipal Solid Waste (Management and Handling) Rules, 2000 Manual on Solid Waste Management- First edition 2000 constituted by CPHEEO- Central Public Health and Environment Engineering Organization, Ministry of Urban Development, New Delhi, G.O.I Detailed Project Report for Water Supply of Rajkot Municipal Corporation Detailed Project Report for Drainage and STP of Rajkot Municipal Corporation Detailed Project Report for SWM of Rajkot Municipal Corporation
CEPT, Ahmedabad
82