1.00 EXCAVATION
As per
contractor's
Visual+TC same as
1.10 Naturre of Soil/Rock B Random scheme for SR √
review Columnn 7
excavaton/appd.
drg.
Initial Ground Level & Measuremen
1.20 C 100% _do_ _do_ SR √
Foundation Layout t
100% for C &
1.30 Final Pit / bed Level C/B _do_ _do_ _do_ SR √ Random by AG
Random for B
2.00 FILL MATERIALS ( For borrowed fill materials as per site requirement
Note 1 :- Minimum 2
2.10 Grain Size Analysis B Physical Note 1 IS 2720(PT IV) IS 2720(PT IV) SR/TR √
samples in every 2000 cum
of each type and source of
fill materials
2.20 Liquid and Plastic Limit B _do_ Note 1 IS 2720(PT V) IS 2720(PT V) SR/TR √
2.30 Shrinkage Limit B _do_ Note 2 IS 2720(PT VI) IS 2720(PT VI) SR/TR √ Note 2 : Min. 2 samples in
every 5000 cum of each
type and source of fill
2.40 Free Swell Index B _do_ Note 2 IS 2720(PT XI) IS 2720(PT XI) SR/TR √
material.
Random for
b) Dry Density by
each
proctor needle B _do_ ASTM-D1588 ASTM-D1588 SR/TR √
compactor
penetraction
layer
IS 2720 & IS
2.80 Sand B _do_ Random IS 2720 & IS 383 SR/TR √
383
CAST-IN -SITU
3.00
CONCRETE
3.10 Materials
3.1.1 a) Manufacture's TC as IS 8112 Grade IS 8112 Grade
Manufacturers's TC for each
per I.S -8112 & A Review 100% 43 IS-1489 43 IS-1489 TC √
batch to be reviewed
I.S - 1489(PART- I) (Part-I) (Part-I)
Cement to be stored on
b) Storage of Cement B Visual 100% IS - 4082 IS - 4082 SR √ raised platfarm in a weather
Cement tight covered store.
3.1.2
Note 5 :- Once for each
IS - 2386(Part- IS - 2386(Part- coarse aggregate stock
a) Moisture Content B Physical Note - 5 III) IS-456 & IS III) IS-456 & IS SR / TR √ when there is rain has to be
-383 -383 done everyday before start
of concreting.
b) Praticle Size & Shape
While
These test will be carried
( sieve Analysis, establishing
SR / out while establishing
determination of design mix & IS - 2386(Part- I) IS - 2386(Part-
B _do_ Lab.repor √ design mix and results shall
material finer than 75 once per 100 & IS -383 I) & IS -383
t be intimated to site for
Micron, flakines index, Cum or part
review and approved
elongation index, there of sourse
angularty number
c) Deleterious material
& Organic impurities
( determination of clay Once per
IS - 2386(Part- IS - 2386(Part- SR / TR &
lumps, fine silt, fine source & every
B _do_ II) IS-456 II) IS-456 Lab.repor √
dust, lightweight pieces, change of
& IS -383 & IS -383 t
soft praticle & source
estimation organic
impurities)
While
establishing These test will be carried
d)Specific gravity, bulk design mix & IS - 2386(Part- IS - 2386(Part- SR / TR & out while establishing
density, voids, water B Physical once for each III) IS-456 III) IS-456 Lab.repor √ design mix and results shall
absorption source & for & IS -383 & IS -383 t be intimated to site for
every change review and approved
of source
IS - 2386(Part- IS - 2386(Part-
SR / TR & The result should be
f) Alkali aggregate VI) ASTM- VI) ASTM-
B _do_ _do_ Lab.repor √ supported by petrographic
reactivity test C1260 & IS C1260 & IS
t examination
-383 -383
3.1.4
100 ml of water should not
a) Test for acidity and
require more than 5ml 0.02
alkalinity by
Quaterly for IS-3025 (Part-22 N NaOH ( using
neutralization of water B Testing IS - 456 TR √
each source & 23), IS - 456 phenolphathalinc Indicator )
using indicator and
and 25ml of 0.02 N
chloride content
sulphuric acid.
Check for
g) Compaction B _do_ Random - segregation as SR √
per IS- 456
I) Cleanliness, provision
Before
of chute & arrangement
C Visual 100% - clearance for SR
for transprotation of
concreting
concrente
Check period of
j) Check for segregation B Physical Random - curing as per IS SR
456
5.00
The grid shall be 300 mm
a) Ultrasonic Test on top
A UT 100% IS- 13311 IS- 13311 UT report √ c/c or as required by site
deck of TG foundation
engineer
One Sample
every IS- 1199 & IS- IS- 1199 & IS-
e) Workability B Physical SR/TR √ According to mix design
2(two)hrs. from 456 456
mixing plant
f) Water cement ratio B Physical Random IS- 1199 IS- 1199 SR/TR √ According to mix design
At random at
g) Cement content B Physical the time of IS- 1199 IS- 1199 SR/TR √ According to mix design
batching
10.0
a) Test on Bricks SR/TR √
Visual & As per IS
i) Dimn. & colour A IS- 1077 IS- 1077 SR/TR √
Measurment standard
ii) Compressive Specn. & Is std. Specn. & Is std. Efflorescence shall be
Strength,water As per IS IS-1077, IS- IS-1077, IS- checked at each source. Pre
A Physical SR/TR √
absorption, warpage, standard 3495(part- I to 3495(part- I to conditional of bricks shall be
efflorescence IV) IV) as per IS Std.
b)Test on Concrete
Bricks
Cement used in mortar shall
confim to either IS 269 or
Brick Masonary b) Test on Mortar
IS 455. Sand shall confirm
to IS 2116-1980
i)Compressive Strength
Consistency and water
retentivity for each C Test Random IS- 2250 IS- 2250 SR/TR √
portion of wall plaster &
ceiling
c) Masonry Construction
i) IS-2212,IS-
Visual & Is-2212,IS- 1905 SR/Insp
Workmanship,verticality B 100% 1905 √
Measurment Tech.Specn. Report
, and alignment Tech.Specn.
11.0
i) where a materials is
manufacured or fabricated
as per spec & drg , separate
QP will be application and
contrator should submit to
APL for approval. ii ) For
Asper
Asper applicable TR?TC for aluminum door and window,
applicable IS
i) Material A Review 100% IS std.& test as √ check for anodisation as per
std.&
Tech,Specn. per IS applicable speci.
Tech,Specn.
iii) For
aluminium cladding, grade
of aluminimum to be
checked iv) All test shall be
carried out at manufactures
work before desptch.
Sheeting Work
Storage should be on raised
plaform, profile sheet, if
used, will be kept covered
Sheeting Work
in wheather proof storage
to avoid any exposur to
Manufacturer's Manufacturer's
water. Principele of first in
ii) Storage at site B Visual 100% recommendatio recommendatio SR
and first out shall be applied
n n
for erection the sheet. The
sheet packet shall be
stacked neatly clear off the
ground at an angle to the
ground to drain moisture.
ii) Installation,
Visual &
alignment & B 100% As per Specn As per Specn SR √
Measurment
workmenship
iii) Check for level & Visual &
B _do_ _do_ _do_ SR
slope Measurment
iv)Proper installation of
B _do_ _do_ _do_ _do_ SR
flashing
v) Fixing including
B _do_ _do_ _do_ _do_ SR
opening location
vi) Fastener for sheeting
B _do_ _do_ _do_ _do_ SR
work
22 Finishing Items
219.65 1254
22.1 Plastering Raw
Material
a)Fine Sand
Once per 100
m3 or part
thereof or Tech Specn. IS - Tech Specn. IS -
i) General Quality B Visual change of 1905 SL 1905 SL SR √
source no.6,3.4 no.6,3.4
whichever is
earlier
b) Glavanised
hexagonal wire Testing for all
B Review 100% IS- 3150 IS- 3150 TC √
netting for characterics asper code
plastering
c) Plaster of Paris
One sample
IS-2547, IS - IS-2547, IS -
_do_ B Test per 50 m3 or TR √
1542,IS- 2333 1542,IS- 2333
part thereof
Final inspection i) Check finish surfece
for defect like blistering,
B Visual Random IS-1661 IS-1661 SR √
cracking & irregularity
of surface texture
Finish plaster surface shall
not show any deviation
ii) Truness of finish Measuremen
B Random Specn. See remark SR √ more than 4mm when
plaster surface t
checked with straingth edge
of 2 m length
Min. 18 mm
thick for out
iii) Check thickness of
B _do_ _do_ _do_ side & 12 mm SR √
plaster over brick
thick for inside
iv) Chck thickness of surface of
Min.thick
plaster over concrete B _do_ _do_ _do_ motar should SR √
ceiling be 6 mm.
v) Curing of plaster Min.7 days
B _do_ _do_ _do_ SR √
surface curing time
22.2 Flooring & Finishing No ponding of water on
work Measuremen
i)Check for slope / levels B 100% Drg. Drg. SR √ finished surface to be
t
ensured
ii) Chipping of floor prior
to commencement of C Visual 100% _do_ _do_ SR
actual finishing work
iii) Curing of cement Measuremen Min.7 days
B 100% _do_ SR √
concrete floor t curing time
iv) Tiles for finish floors B Review 100% _do_ _do_ TC √
v) Polishing of tiled
B Visual 100% _do_ _do_ SR √
finish floor
22.3 Fencing & Gates
d) Thickness of Measuremen
B Random _do_ _do_ SR
elastomeric membrane t
33.1 i) Materials
a) Mineral wool B Review TC 100% IS- 8183 IS- 8183 TC √
b) Polysocyanurate / IS- 12436 , IS IS- 12436 , IS
B _do_ One per lot TC √
rigid phenolic foam slab 13204 13204
33.2 Installation & fixing Visual &
a) Mineral wool B Random Drg. & Specn. Drg. & Specn. SR √
Physical
b) Polysocyanurate / Visual &
B Random _do_ _do_ SR √
rigid phenolic foam slab Physical
· A' shall be witnessed by AG's FQA and Executing Dept., surveillance by Head AG's (FQA) Name of Owner : M/s. Adani Power Limited
· B' shall be witnessed by AG's Executing Dept and Surveillance by AG's FQA
· C' shall be witnessed by Contractor's FQA and AG's Executing Dept and Survelliance by AG's Authorized Engineer
For Simplex :
1.00 EXCAVATION
As per
contractor's
Visual+TC same as
1.10 Naturre of Soil/Rock B Random scheme for SR √
review Columnn 7
excavaton/appd.
drg.
Initial Ground Level & Measuremen
1.20 C 100% _do_ _do_ SR √
Foundation Layout t
100% for C &
1.30 Final Pit / bed Level C/B _do_ _do_ _do_ SR √ Random by AG
Random for B
2.00 FILL MATERIALS ( For borrowed fill materials as per site requirement
Note 1 :- Minimum 2
samples in every 2000 cum
2.10 Grain Size Analysis B Physical Note 1 IS 2720(PT IV) IS 2720(PT IV) SR/TR √
of each type and source of
fill materials
Degree of
2.70
Compaction fill
Note 4 :-
a) Dry density by Core
i) For Foundation
Cutter method IS 2720 ( Pt IS 2720 ( Pt
backfilling one for every 10
or Dry XXIX) OR IS XXIX) OR IS
founations for each
density by sand A/B _do_ Note 4 2720 (Pt XXVIII) 2720 (Pt XXVIII) SR/TR √
compacted layer.
displacement method OR IS 2720 (Pt OR IS 2720 (Pt
Ii) For area filling one in
or XIV) XIV)
every 1000 sqm. Area for
Relative Density Index
each compacted layer.
CAST-IN -SITU
3.00
CONCRETE
3.10 Materials
3.1.1 a) Manufacture's TC as IS 8112 Grade IS 8112 Grade
Manufacturers's TC for each
per I.S -8112 & A Review 100% 43 IS-1489 43 IS-1489 TC √
batch to be reviewed
I.S - 1489(PART- I) (Part-I) (Part-I)
Cement to be stored on
b) Storage of Cement B Visual 100% IS - 4082 IS - 4082 SR √ raised platfarm in a weather
Cement tight covered store.
c) Deleterious material
Once per
& Organic impurities IS - 2386(Part- IS - 2386(Part- SR / TR &
source & every
( determination of clay B _do_ II) IS-456 II) IS-456 Lab.repor √
change of
lumps, fine silt, fine & IS -383 & IS -383 t
source
dust,
Coarse Aggregate
While
establishing These test will be carried
d)Specific gravity, bulk design mix & IS - 2386(Part- IS - 2386(Part- SR / TR & out while establishing
density, voids, water B Physical once for each III) IS-456 III) IS-456 Lab.repor √ design mix and results shall
absorption source & for & IS -383 & IS -383 t be intimated to site for
every change review and approved
of source
IS - 2386(Part- IS - 2386(Part-
SR / TR & The result should be
f) Alkali aggregate VI) ASTM- VI) ASTM-
B _do_ _do_ Lab.repor √ supported by petrographic
reactivity test C1260 & IS C1260 & IS
t examination
-383 -383
One Sample
Slump test for medium high
every SR / TR &
IS - 456 ,IS- IS - 456, IS- workability & compaction
3.1.5 a) Workablity ( slump) B Physical 2(two)hrs. for Lab.repor √
1199 1199 factor test for medium and
every mixing t
low workability
plant
For trial mix min 6 cubes for
Min. 4 trial Mix each mix out of which 3
with & without cubes shall be tested at 7
CONCRETE b) Trial Mix (Cubes IS- 456, IS- 516, IS- 456, IS- 516,
admixture with days and remaining 3 cubes
compressive strength) A Physical IS- IS- SR/TR √
fly ash for each shall be tested for 28 days
Mix design 10262 10262
grade of comp. strength.Mix design
concrete test shall be carried out at
NCBM or CSMRS etc.
cubes per 100
m3 or part 3 cubes shall be tested at 7
c ) Crushing strngth( there of for days & remaining 3 cubes
A _do_ IS- 456, IS- 516 IS- 456, IS- 516 SR/TR √
work test cube) each grade of shall be tested for 28 days
concrete per comp. strenght.
shift whichever
is earlier
At random at SR / TR & As per printed report from
IS 1199 & appd IS 1199 & appd
d) Water cement ratio B Physical the time of Lab.repor √ computerised Batching
design mix design mix
batching t plant for each of concrete.
SR / TR &
e) Cement content B _do_ _do_ _do_ _do_ Lab.repor √ _do_
t
IS - 9103, ASTM IS - 9103, ASTM
f) Admixture for Testing Admixture Brand shall be
B 100% - C- 494 & appd - C- 494 & appd TR √
concrete review TC approved by site.
design mix design mix
Check for
g) Compaction B _do_ Random - segregation as SR √
per IS- 456
I) Cleanliness, provision
Before
of chute & arrangement
C Visual 100% - clearance for SR
for transprotation of
concreting
concrente
Check period of
j) Check for segregation B Physical Random - curing as per IS SR
456
One Sample
every IS- 1199 & IS- IS- 1199 & IS-
e) Workability B Physical SR/TR √ According to mix design
2(two)hrs. from 456 456
mixing plant
f) Water cement ratio B Physical Random IS- 1199 IS- 1199 SR/TR √ According to mix design
At random at
g) Cement content B Physical the time of IS- 1199 IS- 1199 SR/TR √ According to mix design
batching
11.0
i) where a materials is
manufacured or fabricated
as per spec & drg , separate
Asper
Asper applicable TR?TC for QP will be application and
applicable IS
i) Material A Review 100% IS std.& test as √ contrator should submit to
std.&
Tech,Specn. per IS APL for approval. ii ) For
Tech,Specn.
aluminum door and window,
check for anodisation as per
applicable speci.
ii) Installation,
Visual &
alignment & B 100% As per Specn As per Specn SR √
Measurment
workmenship
iii) Check for level & Visual &
B _do_ _do_ _do_ SR
slope Measurment
iv)Proper installation of
B _do_ _do_ _do_ _do_ SR
flashing
v) Fixing including
B _do_ _do_ _do_ _do_ SR
opening location
vi) Fastener for sheeting
B _do_ _do_ _do_ _do_ SR
work
22 Finishing Items
219.65 1254
22.1 Plastering Raw
Material
d) Thickness of Measuremen
B Random _do_ _do_ SR
elastomeric membrane t
All elastomeric membrane shall
be fully dreid to perform
e) Testing for dampness testing with water ponds
created on min 5% of area of
below elastomeric B Physical Random _do_ _do_ SR √ nominal size 6 m x 6 m for a
membrance height of 25 to 30 mm at
critical location fo r a period of
48 hours.
f) Sealing of Joints of
panels of wearing B _do_ _do_ _do_ _do_ SR √
course
31.1 Manufactures's TC shall be
a) Materials & Is-2566 & Tech Is-2566 & Tech
B Review TC One per lot TC √ correlated with cousignment
accessories specn. specn. received
b) Surface finish,
freedom from crack and B Visual 100% _do_ _do_ SR
Vitreous China
other defects
sanitary items
10% subject to
c) Dimension and Measuremen min.of 3 Tolerance limit as per relevant
B _do_ _do_ SR
construction t nos.for each part of IS 2566
type of items
a) Materials / Manufactures's test certificate
31.4 Relevant IS Drg. Relevant IS Drg.
component including B Review TC 100% TC √ with the cousignment shall be
Specn. Specn. reviewed .
valve
10% subject to
b) Surface finish,
G.I.,C.I., P.V.C Pipes min.of 3
freedom from crack and B Visual _do_ _do_ SR
and fitting nos.for each
other defect
type
Toleranceas per
Measuremen
c) Dimn. & construction B _do_ _do_ IS- 1729, IS- SR
t
1536, IS1230
31.5 a) Materials & IS- 458, IS- 651, IS- 458, IS- 651, Correlated manufactures's test
B Review TC 100% TC √ certificate with the consigment
accessories Tech specn Tech specn shall be reviewed
Concrete and stone b) Surface finish,
ware pipes freedom from crack and B Visual Random Relevant IS Relevant IS SR
other defect
Measuremen IS- 458, IS- 651, IS- 458, IS- 651,
c) Dimn. & construction B 5% of each lot SR
t Tech specn Tech specn
31.6 After installation of
pipes
· A' shall be witnessed by AG's FQA and Executing Dept., surveillance by Head AG's (FQA) Name of Owner : M/s. Adani Power Limited
· B' shall be witnessed by AG's Executing Dept and Surveillance by AG's FQA
· C' shall be witnessed by Contractor's FQA and AG's Executing Dept and Survelliance by AG's Authorized Engineer
For Simplex :