You are on page 1of 4

Micro-Generation Connection (MGC) Application

For Connection of Micro-Generation Facilities of 10 kW


This form is applicable to individual or multiple generating units at the Customers facility with total nameplate rating of 10 kW or less. Your generation facility must generate electricity from a renewable energy source that is wind, water, solar radiation, or agricultural biomass. Inverter-based generating units must not inject DC greater than 0.5% of the full rated output current at the point of connection of the generating units. The generated harmonic levels must not exceed those given in the CAN/CSA-C61000-3-6 Standards. Refer to Distributed Generation Technical Interconnection Requirements - Interconnections at Voltages 50kV and Below (http://www.hydroonenetworks.com/en/customers/generators/generation_connections/distribution/stakeholder_consultation/default.asp For generation size up to 10 kW, a Connection Impact Assessment will not be required and Entegrus Powerlines will not perform such an assessment. There may be a limitation on the number of microgeneration facilities that can be connected to the same distribution feeder. IMPORTANT: All fields below are mandatory, except where noted. Incomplete applications may be returned by Entegrus Powerlines. Please return the completed form by mail or email to: Entegrus Powerlines Attn: MicroFIT Connections 320 Queen ST. Chatham, Ontario N7M 5K2 Email: matthew.meloche@entegrus.com Telephone: 519-352-6300 x 290 (1-866-804-7325) NOTE: Applicants are cautioned NOT to incur major expenses until Entegrus Powerlines approves to connect the proposed generation facility. The following information is required for all generators with total generation of up to 10 kW. Date of Application microFIT reference number*
(*not required for Net Metering applications)

(dd / mm / yyyy)

(dd / mm / yyyy)

1. Project/Customer Name 2. Proposed In-Service Date 3. Project Information Owner Company/ Person: Contact: Mailing Address: Telephone: Fax: E-mail:

Middlesex Power Distribution Corporation Micro-Generation Connection Application Form - Rev.1, Aug 4, 2010 Entegrus Powerlines Micro-Generation Connection Application Form - Rev.2, Feb 17, 2012

Page 1 of 4

Engineering Consultant (Electrical) (optional) Company/ Person: Contact: Mailing Address: Telephone: Fax: E-mail: 4. Project Location Address City/Town/Township Lot Number(s) Concession Number(s)

5. Connection to Entegrus Powerlines Distribution System a) Connection voltage to Entegrus Powerlines distribution system: kV b) Station: c) Feeder: 6. Program Type a) microFIT (Complete all sections) b) Net Metering to microFIT Conversion i. Existing Net Metering Customer upgrading generation size and/or technology/ fuel type, up to 10 kW (Complete all sections) ii. Existing Net Metering Customer with no upgrades in generation size and/or technology/ fuel type, up to 10 kW (Complete sections 6, 7 and 8 only) c) Net Metering (Complete all sections) 7. Customer Status Existing Entegrus Powerlines Customer? If yes, Entegrus Powerlines Account Number: Name of Account Holder*:
(*must be the same name as applicant)

Yes No - - Yes No - RT kW single phase kW kW

Are you a GST registrant? If yes, provide your GST registration number: 8. Project Size Number of Units Nameplate Rating of Each Unit Generator connecting on Existing Total Nameplate Capacity Proposed Total Nameplate Capacity 9. Fuel Type Wind Turbine Solar / Photovoltaic Cells (Rooftop) Biomass Bio-gas

three phase

Hydraulic Turbine Solar / Photovoltaic Cells (Ground Mount) Bio-diesel Other, please specify

Middlesex Power Distribution Corporation Micro-Generation Connection Application Form - Rev.1, Aug 4, 2010 Entegrus Powerlines Micro-Generation Connection Application Form - Rev.2, Feb 17, 2012

Page 2 of 4

10. Customer Owned Step-up Interface Transformer (if applicable) Transformer rating kVA High voltage winding connection Delta Wye Grounding method of wye connected high voltage winding neutral Solid Ungrounded Impedance grounded: RXohms Low voltage winding connection Delta Wye Grounding method of wye connected low voltage winding neutral Solid Ungrounded Impedance grounded: RXohms Note: The term High Voltage refers to the connection voltage to Entegrus Powerlines distribution system and Low Voltage refers to the generator / inverter output voltage. 11. Generator / Inverter Information (For generation facilities installing more than one type of generator, complete section 10) Manufacturer: Model No. Number of phases Single Phase Three Phase Nameplate rating: kW Generator / Inverter AC output voltage Volts Type of inverter: Self-commutated Line- commutated Other, please specify Are power factor correction capacitors automatically switched off when generator breaker opens? Yes No Is the generator / inverter paralleling equipment and / or design pre-certified and meets anti-islanding test requirements? Yes No If answer to the above question is Yes, to which standard(s), e.g. CSA C22.2 No. 107.1-01, UL1741, etc. Method of synchronizing the generator / inverter to Entegrus Powerlines system Manual Automatic Maximum inrush current upon generator or inverter connection (Iinrush/ Irated) per unit 12. Grid Interface Controller (if applicable) Manufacturer: Model Number:

13. Type of Connection Select the Single Line Diagram below that is appropriate for your connection to the Entegrus Powerlines distribution system: Figure 1 - Net Metering Connection Figure 2 - Parallel Metering Connection

Middlesex Power Distribution Corporation Micro-Generation Connection Application Form - Rev.1, Aug 4, 2010 Entegrus Powerlines Micro-Generation Connection Application Form - Rev.2, Feb 17, 2012

Page 3 of 4

Figure 1: Net Metering Configuration

Figure 2: Parallel Metering Configuration

Disclosure

By submitting a MGC Application, the Proponent authorizes the collection by Entegrus Powerlines, of the information set out in the MGC Application and otherwise collected in accordance with the terms hereof, the terms of Entegrus Powerlines Conditions of Service, Entegrus Powerlines Privacy Policy and the requirements of the Distribution System Code and the use of such information for the purposes of the connection of the generation facility to Entegrus Powerlines distribution system.
Middlesex Power Distribution Corporation Micro-Generation Connection Application Form - Rev.1, Aug 4, 2010 Entegrus Powerlines Micro-Generation Connection Application Form - Rev.2, Feb 17, 2012

Page 4 of 4