You are on page 1of 12

MARCH 1991

by Ron Vogel, Computers and Structures, Inc. March, 1991

LRFD-COMPOSITE BEAM DESIGN WITH METAL DECK

INTRODUCTION
This is the companion paper to the "STEEL TIPS" dated January 1987 entitled "Composite Beam Design with Metal Deck". The original paper used allowable stress design (ASD). This "STEEL TIPS" utilizes the same three original examples but designed by the Load and Resistance Factor Design (LRFD) Method. The purpose is to show the design procedure, the advantages of the method, and the ease of using the AISC First Edition (LRFD) for design. Three main areas have been revised from the ASD Approach: 1. Determination of effective slab width 2. Shored and unshored construction requirements 3. Lower bound moment of inertia may be utilized. A number of papers have been written about these differences and the economies of the LRFD method. The reader is referred to the list of references included.

Table 1 S U M M A R Y OF SECTION I3.1 ITEM Effective Width, on each side of beam (lesser of the 3 values) General AISC-LRFD SUMMARY b = Beam Length/8 (L/8) = Beam Spacing/2 (s/2) = Distance to Edge of Slab hr < Wr > ds < Hs = = tc > 3.0 in. 2. 0 in. 3/4 in. hr + 1 1/2 in. hr + 3 in. 2.0 in. (Height of Rib) (Width of Rib) (Welded Stud Diameter) (MinimumStud Height) (Maximum Stud Height value for computations) (Minimum concrete above deck) SPECIFICATION SECTIONS I3 & I5

I3.5a

15.1 I5.2

Material Horizontal Shear Force (lesser of the 3 values) Strength of Stud

Hs > 4ds = 0.85f'cAc = AsFy -- Qn Qn = 0.5 Asc (f'c Ec) (but not more than Asc Fu) = 0.5 Asc (f'c wc)3/4 (using E = wcl'5fxc in above formula) = 6 ds = 4 ds Longitudinal Transverse

I5.3

I5.6

Shear Connector Placement and Spacing

(See LRFD Manual Fig. C-I5.1, pg. 6-177)

Table 2 AISC-LRFD RULES - F O R M E D M E T A L DECK

(Sections I3.5b and I3.5c)

I T E M

RIBS PERPENDICULAR NEGLECT (N0'85 [ r r j W r l { S r S 1}-< 1'0

RIBS PARALLEL INCLUDE ' [hrrJ [ h r - 1} < 1.0 06wrl,

1. Concrete Area Below Top of Deck 2. Stud Reduction Factor

3. Maximum Stud Spacing 4. Deck Welding 5. Minimum Width of Rib

32 in. 16 in. 2 in.

NOT SPECIFIED NOT SPECIFIED NOT SPECIFIED

Page 2 Steel Tips March 1991

Typical Design Problems


Example 1. Design a composite interior floor beam (without cover plate) for an office building. See Beam A in Figure 1. Solution: 1. Design for construction loads: a. Strength design

- - I .

i1
40'

BAt
^ ^
30' -'

wu= s [1.6 (D.L. + L.L.)] = 10 [1.6 ( 57 + 20 )] / 1000 = 1.23 kip/ft (Load factor for D.L. assumed same as for L.L. during placement of concrete.) B Mu - wuL2 - (1'23)(30)2 - 139 kip-ft 8 8 Mu (12)(139) _ 51 in.3 (Minimum) Zreq- qFy- (0.9)(36)

b. Servicibility design Limit construction deflection to 1 in. (without construction L.L.)

Figure 1
Given: Span length, L = 30 ft. Beam spacing, s = 10 ft. Slab thickness, tc = 2.5 in. Concrete strength, f'c = 3.0 ksi Concrete weight, wc = 145 pcf (n = 9) Steel yield stress, Fy = 36 ksi 3 inch metal deck, ribs perpendicular to beam (hr = 3 in., wr = 6 in.) No shoring permitted. Do not reduce live load. Loads: Concrete slab including reinforcing steel and metal deck 54 Framing 3 Mechanical 4 Ceiling 6 Partition 20 Total D.L. Live Load 87 psf 100 psf

5wL4 (5)[(10)(57)](30)4(1728) Ireq= 384EA- (384)(29,000,000)(1.0) - 358 in.4 (Minimum) 2. Composite Beam Design: a. Trial design for required flexural strength wu = 10 [1.2(87)+1.6(100)]/1000 = 2.64 kip/ft Mu = wuL2 (2.64)(30)2 T = 8 = 297 kip-ft

For a trial size use formula in LRFD Manual pg. 4-9. 12Mu (3.4) Beam Weight = {d 2} +Yc ) Fy where q = 0.85 and assume a = 1 in. d (in.) 14 16 18 21 396 396 396 396 12Mu(3.4) Fy d +Yc a
-

WT (#/ft) 33 31

Size

(in.) 12.0 13.0 14.0 15.5

(in.3) (in.4) W14X34 54.6 W16X31 54.0 340 375 510 843

28 W18X35 66.5 26 W21X44 95.4

Construction Loads, D.L. 57 psf (concrete & framing) L.L. 20 psf (men & equipment) Select W18X35. For simplicity, the entire 57 psf construction load is considered as live load during concrete placement. NOTE: The original Steel Tips design, based upon ASD, used Grade 50 steel.

Steel Tips March 1991 Page 3

b. Verify flexural strength


' b

I o. o
o

o. ' %..;;',
n i

. .v .* .. . ' , ) .o ? o .o: .
i

Effective concrete width (AISC I3.1) lesser of,

d/2

b = (2)(30)(12) _ 90 in. and 8 b = (2)(10)(12) _ 120 in. 2 Use 90 in. Design for full composite action Tmax= AsFy= (10.3)(36)= 371kips (Governs) Cmax = q f'c b tc = (0.85)(3.0)(90)(2.5) = 574 kips Tmax 371 a - { f'c b (0.85)(3.0)(90) 1.62 in. a/2 = 0.81 in. (larger than 0.5 in. assumed) Y2 = Yc - = 5.5 - 0.81 = 4.69 in. qMn= qAsFy/d + Y21= (0.85)(371)I1--- +4.693 = 4270 kil2n. = 356 kip-ft or from Table on LRFD Manual pg. 4-23 with Y2 = 4.69 in. PNA = TFL (Top flange location) Y1 =0in. = 371 kips (AsFy) By 14.69 - 4.501 *mn= [".-.-.0-.5-J (364- 351)+ 351 kip-ft.
a

1
Figure 2

.,.

o.

'

. .' . _.i _ t

Figure 3

Yc

tie
Y 2

= 356 kip-ft

> 297 kip-ft

O.K.

d/2 + Yc ' a/2 d/2

c. Calculate shear studs For full composite action Qn = AsFy= 371 kips Assume 3/4 inch diameter by 5 inch long studs. Qn = 0.5Asc(f'c wc)3/4 = (0.5)(0.442) [(3)(145)]3/4 = 21.1 kips (<AscFu = 0.442(60)= 26.5 kips) Check flange thickness

Figure 4

tf= 0.425 > ds/2.5 = 0.3 in.

O.K.

Page 4 Steel Tips March 1991

Stud Reduction Factor (S.R.F.) 0.85 Jwr Hs /2 lTrr - 1} < 1.0

d. Design for deflection Deflection after initial construction deflection


A =-

(Nr)

lJ

085
(mr)

6 I5,0_
13.0 -

Nr

S.R.F. 1.13 <1.0 0.80 0.65

Use 1.0 0.80 0.65

5wL 4(5)(10) [(87 - 57 + 100) ] (30)4 1728 384E Itr (384)(29,000,000)Itr 817. -m. Itr See Table 3 for Moment of Inertia, Itr computations.

1 2 3

with Itr for gross area, A = 0.46 in. or L/783 with lower bound Itr, A = 0.56 in. or L/643 A DL = 0.13 in. ALL = 0.43 in. or L/837 O.K, (with lower bound Itr = Ilb) The beam may be cambered for the initial construction deflection A= ( Ireq /Assumeddefiection. Iprovided

Assume 14 stud locations possible per 1/2 beam 14 (21.1) = 295 kips Remaining stud force = 371 - 295 = 76 kips Use twice reduction for doubled stud locations [ (2) (0.8) - 1] 21.1 = 12.7 kips Total per 1/2 beam = 14 + 76/12.7 = 14+6=20 (distributed as shown in Figure 5) Total = 40 Studs.

358 A = /5--i-) 1.0 = 0.70 in. Camber 3/4 in, e. Check for shear strength Vu = [1.2(10)(87) + 1.6(10)(100)]15 / 1000 = 39.7 kips qbVn = 0.6)Fydtw = (0.90)(0.6)(36)(17.7)(0.3) = 103 kips or from Table on page 3-31 of the LRFD Manual q bVn = 103 kips > 39.7 kips O.K.

B M Span

I II II I I I l l I I I I I I I

Figure 5

Steel Tips March 1991 Page 5

Table 3 Moment of Inertia Calculation


Type n Y i n ? A Y ) y Io Ad2 Itt

(in.2)
10.3 25.0 35.3

(in.)
8.85 21.95

(in.)

(in.4)
510

(in.4)
887 365 1252

(in.4)

1. Gross section

91 549 640

18.13

523

1775 1775

2. Neglecting tensile concrete 3. Reduced concrete area, equal to XJ'On/F,,

No tensile concrete for this example. Therefore, Itr is same as for gross section. 10.3 10.3 20.6 8.85 17.7 + 4.69 91 231 322 510 _3_1 511 473 473 946

15.60

1457

NOTES: 1. Itr = 1457 in.4 is considered the "Lower Bound" moment of inertia, Iib and may be found directly from Table on Page 4-49 of the LRFD Manual. For Y2 = 4.69 in. W18x35 and Y1 = [4.69-4.501 Itr = 1430 + l' --Y--4-' 'J (1500-1430) = 1457 in.4 Itr = lib 2. Modular ratio, n = 9 3. Effective concrete width, b = 90 in. 4. Slab thickness, tc = 2.5 in. 5. Ac = 90 (2.5) = 225 in.2 6. Transformed concrete area, A'c = Ac/n = 25.0 in.2

Figure 6

7. y = - _.,n

_.,Ay

8. d = y - y

9. Itr = _fio + A d 2

NOTE: The purpose and advantage of using the lower bound Itr value found in the LRFD Manual tables is to avoid the above computations. If the deflections using the lower bound Itr are acceptable, the actual deflections will be conservatively less. Lower bound Itr is based upon the area of the beam and an equivalent concrete area of and is applicable for full as well as partial composite action.

Page 6 Steel Tips March 1991

Example 2. Design a composite interior girder (without cover plate) for an office building. See Girder B in Figure 1. The 3-inch deck ribs are oriented paralled to the girder. Girder is assumed loaded as shown in Figure 7. Solution: 1. Design for construction loads: Assume Framing D.L. = 10 psf Concrete Weight = 50 psf as L.L. Construction L.L. = 20 psf

P
I

P
I

Pu = (10)(30)[1.2(10) + 1.6(50 + 20)] / 1000 = 37.2 kips MuPL_ (37.2)(40)_ 744 kip-ft 2 2

L
Given:

4olo
Figure 7
Span length, L = 40 ft. Beam spacing, s = 30 ft. Slab thickness, tc = 2.5 in. Concrete Strength, f'c = 3.0 ksi Concrete weight, wc = 145 pcf Steel Yield Stress, Fy = 50 ksi No shoring permitted. (n = 9)

12Mu_ (12)(744)_ 198 in.3 (Minimum) Zreq- bFy (0.9)(50)

2. Composite Girder Design a. Trial design for required flexural strength Pu = (10)(30)[1.2(90) + 1.6(60)]/1000 = 61.2 kips Mu- PL2_ (61.2)(40)2 - 1224 kip-ft For a trial size use formula in LRFD Manual pg. 4-9. 12Mu (3.4) Beam Weight = {-Yc } d - 2 qFy where q) = 0.85 and assume a/2 = 2 in.

3 inch metal deck, ribs are parallel to girder.

Loads:

Concrete slab including reinforcing steel and metal deck 54 Framing Mechanical Ceiling Partition Total D.L. Live 6 4 6 20 d

12Mu(3.4)

Fy
(in.)

d q-Yc- a (in.)

WT (#fit)

Size

(in.3) (in.4) 1830 2100 2850

90 psf 21 100 psf 24 27 1175 1175 1175 14 15.5 17.0 84 W21X83 196 76 W24X76 200 69 W27X84 244

Live Load Reduction = 23.1 (1+ D/L) = 23.1 (1+ 90/100) = 43.9 % or = 0.08 (A - 150) = 0.08 (1200-150) =84% or = 40 % maximum Use 60 psf L.L. Select W24x76. or enter Table on page 4-33 of the LRFD Manual with Y2 = 3.5 in. (Yc - a/2) PNA = TFL (Full Composite Action) 4) Mn 1230 kip-ft > 1224 kip-ft
=

Steel Tips March 1991 Page 7

b. Verify flexural strength

I'
C g

b/n '--'1
, ': .. ' , . . . . . .

, " /. :o=:..; x,.-'Xx,.\.:

d/2 d l 2 + Y o - a / 2

'--"--:I

Effective concrete width lesser of, b = (2)(40)(12)/8 = 120 in. and b= (2)(30)(12)/2-= 360in. Use 120 in. Design for full composite action Tmax = AsFy = (22.4)(50) = 1120 kips (Governs) Cmax = 0.85f' cAc = (0.85)(3.0)[(4.0)(120)] = 1224kips For Ac see Figure 8. Y2 = Yc - = 5.5 - 2.01 = 3.49 in.
a

/c = 2.5b

+ 3.Ob = 4.Ob
2

Figure 8

4.82"

=
'k ,"1 't, ,'1

ct w

qbMn= qbAsFyld+ Y2)= (0.85)(1120)I2-+ = 1225 kip-ft > 1224 kip--ft O.K

3.49/12

assume-!-6"

_1_ 8"

_1_

8"

.!_

or from Table page 4-33 for Y2 = 3.5 and TFL OMn = 1230 kip-ft Tmax = Cabove + Cbelow Cabove= (0.85)(3.0)(120)(2.5)= 765 kips Cbelow = 1120 - 765 = 355 kips 355 depth = [(1/2)(120)] (0.85)(3.0) - 2.32 in. Centroid from top = a/2 a_ 2 (765)(1.25)+355(2.5+2.32/2) 1120 c. Design for deflection Initial deflection during construction A= 19PL3 (19)[(10)(30)(54 + 6)](480)3 384Eis (384)(29,000,000)(2100) = 1.62 in.

= 2.01 in.

Camber 1 1/2 inches. Composite deflection using Lower Bound Itr (Ilb). From Table on page 4-46 of LRFD Manual,

Assumption of a/2 = 2 in. O.K.

Figure 9

with Y2 = 3.5 PNA = TFL . Ilb = 4780 in4

D.L. = 90 psf Construction D.L. = 60 psf L.L. = 60 psf

19PL3 (19)[(10)(30)(90 - 60 + 60)1(480)3 ATL- 384EI(384)(29,000,000)(4780) = 1.07 inches or L/450 ALL= (60/90)(1.07)= 0.71 in. or L/673 O.K.

NOTE: The mooment of inertia using the gross area equals 5510 in.

Page 8 Steel Tips March 1991

d. Shear Connectors Example 3

Partial Composite Action


For full composite action

= AsFy = 1120 kips

Design Beam in Example 1 for pfial composite action.

Reduction Factor = 0.6 [hr J[


% /

('"'1[

1 _ < 1.0

SOLUTION: a. Determine required shear studs

= 0.6

-1 = 0.8 Estimate number of shear studs for partial composite action using the following approximate equation

Use 0.8 for stud reduction factor. Qn = (0.8)(21.1) = 16.9 kips (See Example 1)

No. 1120 - - - - -- 67 Studs Qn 16.9 67 Studs are required from Zero to Maximum Moment.

M u Mp ' [Mn - *Mp )


-

,Qn
Qn

No.-

Where Mu = Moment demand Mp = Steel Beam Capacity with ) = 0.85 Mn = Full Composite Beam Capacity Mu = 297 kip-ft {Mp = Fy Z = (0.85) (36) (66.5)/12 = 170 kip-ft {Mn = 356 kip-ft = AsFy = 371 kips Qn = 21.1 kips = [356-170) ,21.1) 0.47 (17.6)= 8.2 Try 9 studs on each 1/2 beam.

Total = 134

$uds,

Use equal spacing for full length. e. Check Shear Vu --- 1.5 (Pu) = 1.5 (61.2) = 92 kips Vn = (0.6 Fy) d tw = (0.9) (0.6) (50) (23.92) (.44) = 284 kips > 92 kips Q.K.

NOTE: The original Steel Tips design, based upon ASD, used a W27X94 with 92 studs.

Total = 18 studs. b. Check flexural strength

Qn = (9)(21.1) = 190 kips From Eq. C-I3-4 in commentary of LRFD Manual 190 a = 0.85f'cb- (.85)(3.0)(90)- 0.83 in. Y2= Yc-a/2= 5.5-0.41 = 5.09

From Table on page 4-23 of the LRFD Manual for W18X35 Y2 = 5.0 - 5.09 in. Qn = 187 - 190 kips ( PNA = BFL approx.) ) Mn = 296 kip-ft (approx. equal 297 kip-ft required) O.K. Therefore, partial composite action with 18 total studs is adequate for the required moment.

Steel Tips March 1991 Page 9

c. Check deflection For deflection computation use the lower bound value given in the Table on page 4-49 of the LRFD Manual. For W18x35 PNA = BFL + Y2 = 5.0 + _ 4 Ilb = 1170 in. A TOTAL = (1775/1170) 0.46 = 0.70 in. ADL = 0.16 in. ALL = 0.54 in. or L/667 O.K. Obviously any number of studs from 9 (47%) to that for full composite action may be used (per 1/2 Beam Span) with the associated increase in moment capacity and decrease in deflection.

DISCUSSION With the use of the First Edition AISC-LRFD manual, composite beam design can be simplified, particulary with partial composite action. As in the past, AISC has tried to incorporate enough tables and charts to make repetitive design computations easier. Determining preliminary beam sizes, number of welded studs and composite beam deflections is now very straight forward. With a minimum of assumptions (i.e. location to the compressive force, Y2) preliminary comparative designs can be done in minutes with the use of the tables. The reader is encouraged to read the LRFD Manual PART 4 (Composite Design), PART 6 (Specifications and Commentary), especially Section I on Composite Members, and the other references listed. The number of articles dealing with LRFD composite members design is growing as designers are becoming more familiar with the method and the AISC-LRFD manual.

. a/2

Location of . effec'ive concrete

..-'-'T
...[.. (

Y2{ m. t 1) I ' - - : t (pt s)


Y1 (varies - Sgure below)

Y1 = Distance from top of steel flange to any of the seven tabulated PNA locations. qn (@ point 5) + qn (@ point 7) qn (@ point 6) = qn (@ point 7) = .25AsFy 2

4equ

spaces

Bo$/l{
Top Flange

I1
Flange Locations

BFL

PNA

Figure 10

Page 10 Steel Tips March 1991

N O M E N C L A T U R E

Ac A'c As
Asc

BFL C D.L. E Ec Fy Fu Hs IIb Io Itr L L.L. Mn Mp Mu Nr

P PNA

Q.

Area of concrete (in.2) Area of concrete modified by modular ratio (in.2) Area of steel (in.2) Area of welded stud (in.2) Bottom of flange location Compressive force (kips) Dead load (psf) Modulus of elasticity of steel (29,000,00 psi) Modulus of elasticity of concrete (ksi) Minimum yield strength of steel (ksi) Minimum tensile strength of steel (ksi) Welded stud height (in.) Lower bound moment of inertia (in.4) Moment of inertia (in. Transformed moment of inertia (in.4) Span length (ft) Live load (psf) Nominal flexural strength 0dp-ft) Plastic bending moment (kip-fO Factored Moment (Required flexural strength) (kip-ft) Number of stud connectors in one rib at a beam intersection Factored point load (kips) Plastic neutral axis Welded stud shear capacity (kips)

S.R.F. T TFL Va Vu Y1 Y2 Yc Z
a

b d ds f'c hr n tc

tf tw
W c Wr wu

Stud reduction factor Tensile force (kips) Top of flange location Shear capacity (kips) Shear demand (kips) Distance from top of beam flange (in.) Distance from top of beam to concrete flange force (in.) Total thickness of concrete fill and metal deck (in.) Plastic section modulus (in.3) Effective concrete flange thickness (in.) Effective concrete flange width (in.) Depth of steel beam (in.) Welded stud diameter (in.) Concrete compressive strength at 28 days. (ksi) Nominal rib height of metal deck (in.) Modular ratio (E/Ec) Thickness of concrete above metal deck (in.) Steel beam flange thickness (in.) Steel beam web thickness (in.) Unit weight of concrete (lbs./cu. ft) Average metal deck rib width (in.) Factored uniform load (kip/fO Deflection (in.) Resistance factor

REFERENCES
,

"Manual of Steel Construction, "First Edition, AISC, Chicago, 1986. STEEL TIPS, "Composite Beam Design with Metal Deck," Steel Committee of California, January 1987. STEEL TIPS, "The Economies of LRFD in Composite Floor Beams," Steel Committee of California, May 1989. Smith, J.C., "Structural Steel Design - LRFD Approach," John Wiley & Sons, Inc., N.Y., 1991. Salmon, C. and Johnson, J., "Steel Structures," Third Edition, Harper & Row, N.Y., 1990. McCormac, J., "Structural Steel Design - LRFD Method," Harper & Row, N.Y.,1989. Vinnakota, S., et al., "Design of Partially or Fully Composite Beams, with Ribbed Metal Deck, Using LRFD Specifications," AISC Engineering Journal, 2nd Quarter, 1988.

2. 3. 4. 5. 6. 7.

Steel Tips March 1991 Page 11

T H E STEEL C O M M I T T E EO F CALIFORNIA
Northern California 43 Quail Court, No. 206 Walnut Creek, CA 94596 (415) 932-0909 Southern California 9420 Telstar Ave., No. 207 El Monte, CA 91731 (818) 444-4519

SPONSORS
Adams & Smith Allied Steel Co., Inc. Artimex Iron Co., Inc. Bannister Steel, Inc. Bethlehem Steel Corporation C. A. Buchen Corporation Butler Manufacturing Co. Cochran-Izant & Co., Inc. Geneva Steel The Herrick Corporation Hoertig Iron Works Hogan Mfg., Inc. Junior Steel Co. Lee & Daniel McLean Steel, Inc. Martin Iron Works, Inc. Nelson Stud Welding Co. Oregon Steel Mills Palm Iron & Bridge Works PDM Strocal, Inc. Reno Iron Works Riverside Steel Construction H. H. Robertson Co. Schrader Iron Works, Inc. Stockton Steel Stott Erection, Inc. U.S. Steel Corporation Verco Manufacturing, Inc. The local structural steel industry (above sponsors) stands ready to assist you in determining the most economical solution for your products. Our assistance can range from budget prices and estimated tonnage to cost comparisons, fabrication details and delivery schedules.

Funding for this publication provided by the California Field Iron Workers Administrative Trust.

You might also like