You are on page 1of 46

Reliance Engineering Associates Private Limited

SPECIFICATION G GS 005

Shop and Field Painting

24/10/02

Issued as Specification

TKH

MGC

SVKR

Rev

Date

Revision

By

Chkd

Appr

Client

G GS 005 Rev 0

Page 1 of 46

Reliance Engineering Associates Private Limited Contents


1. Scope .. 3 2. Application Standards, Codes and Regulations . 3 3. General 4 4. Surface Preparation . 4 5. Coating Preparation and Application . 8 6. Inspection 9 7. Work to be Performed 12 8. Coating System .. 12 9. Coating Schedule 12 10. Colour Schedule 13 11. Appendices i) Appendix A : Coating System 15 ii) Appendix B : Coating Colour Schedule 21 iii) Appendix C : Identification of Services .. 22 iv) Appendix D : Coating Schedule (Other than Marine environment) . 30 v) Appendix E : Coating Schedule (Marine environment) 41

G GS - 005 Rev 0

Page 2 of 46

Reliance Engineering Associates Private Limited 1. Scope


1.1 This specification covers the surface preparation , method of application and material to be used for all coating of equipment, vessels, machinery, steel structures and piping. 1.2 Buildings shall not be painted under this specification. For building painting requirements, see building drawing and specifications. 1.3 The painting of topside facilities of marine structures are addressed under this specifications. For splash and submerged zone coating refer to marine structure specifications. 1.4 In general, shop fabricated equipment will be delivered to the job site coated with a shop applied system or manufactures standard finish in accordance with the requirements of this specification. 1.5 Identification of colour bands on all piping as required including insulated aluminium clad, galvanised, SS and non-ferrous piping are included.

2.

Applicable Standards, Codes and Regulations

2.1 Work shall be performed in accordance with the following Codes and Standards. Equivalent Indian Standards may be used subject to Reliances Approval. Works shall be in accordance with the Painting manufactures recommendations. 2.2 US Specifications of Steel Structures Painting Council, SSPC Volumes I and II

Swedish Standard SIS 05 59 00 British Standard 381C 1980 British Standard 729 1981 British Standard 4232 1967 British Standard 1710 1975 British Standard 4800 1981 British Standard 5493 1977 NACE

Surface preparation Standards for Painting Steel Surface Colour for Identification, Coding and Special Purposes Hot dip Galvanised Coatings on Iron and Steel Articles Surface finish Blast Cleaned Steel for Painting Identification of Pipeline Paint Colours for Building Purposes Code of Practice for Protective Coating of Iron and Steel Structures against Corrosion National Association of corrosion Engineers,USA

G GS - 005 Rev 0

Page 3 of 46

Reliance Engineering Associates Private Limited


2.3 If conflicts occur between this specification, the Painting manufacturers recommendations and the referenced standards, Reliances Specialist shall be contacted for clarification.

3. General
3.1 References to SSPC shall be understood to refer to Steel Structures Painting Council Standards. 3.2 Work described shall be performed by the Painting Contractor and all tools, equipment, Paints, solvents, etc., necessary to complete the work shall be furnished by him. 3.3 The Painting Contractor shall comply with all applicable laws, regulations, ordinances, etc., of the city, country, state, province or nation pertaining to his work and painting materials. It is mandatory requirement that all operatives working to this procedure take full cognisance and implement necessary safety precautions. 3.4 Reliances Inspector shall have free access at all times to the work being performed by the Contractor. 3.5 Painting Manufacturers latest approved published instructions for application and system combinations of coatings shall be followed. Superimposed primers and coatings shall be compatible. In the event of conflicts, differences shall be brought to the Contractors painting specialist for resolution. 3.6 For equipment that has received shop prime coat, the Field Painting Contractor shall touch-up prime coat and apply additional coats in accordance with the Painting Schedule. It is the Contractors responsibility to ensure compatibility between shop and field applied paint systems. 3.7 Proper precautions shall be taken to protect other surfaces from abrasive blasting, coating over spray and spatter. Damage to other surfaces or equipment shall be repaired by the Field Painting Contractor at his expense (see paragraph 10.6). 3.8 The Field Painting contractor shall submit surface preparation and application procedures for review and acceptance by the Reliance. 3.9 Stainless steel, Aluminium and other high-alloy materials shall not be coated unless otherwise specified. Austenitic stainless steels operating between 50oC and 200oC are at risk under certain common conditions to pitting corrosion or even stress corrosion cracking. For this reason these substrates will be protected as indicated in Appendix B. 3.10 Painting Manufacturers instructions shall be followed as far as practicable at all times for proper storage to avoid exposure as well as extremes of temperature.

4. Surface Preparation
4.1 Metals

G GS - 005 Rev 0

Page 4 of 46

Reliance Engineering Associates Private Limited


4.1.1 Adhesion of the paint film to surface depends largely on the degree of cleanliness of the metal surface. Proper surface preparation contributes more to the success of the paint protective system. Weld spatter shall be removed and sharp or rough welds rounded and contoured. Sharp edges shall be removed, chamfered or broken. Surfaces to be painted shall be free of all grease, oil, loose rust and loose mill scale. Oil and grease shall be removed by solvent cleaning method as in SSPC-SP-1. Rust, mill scale, weld spatter, flux shall be removed by methods indicated in the Painting Schedule. The surface profile depth indicated under Appendix A shall be achieved by using a medium that has good angularity of form, sharp cutting edges and is substantially free from half rounds. If sand is used as the blasting medium it shall be delivered to site in trucks. Each truck load shall be identified with a batch number and each batch shall be tested for Chloride content (maximum allowable chloride level 0.03%) and pH value (the value should be nearly neutral i.e., pH 6 to pH 8). The tests shall be carried by owner, or by supplier with third party test certificate. The third party shall be an approved agent approved by owner. Profile measurements of abrasive blast cleaned surface shall be made with a Keane Tator profile comparator, Clemtec anchor profile chips, Testex Press-O-Film or other contractor accepted method suitable for the abrasive being used. Prior to any coating application the substrate shall be checked for soluble salt contamination using a suitable salt contamination meter (SCM 400). The maximum allowable level of contamination shall be 5 gm/cm 2. Surfaces that do not meet this criteria shall be reprocessed. Should this problem occur on a frequent basis the abrasive medium shall be reexamined for quality and if necessary changed. 4.1.9 Surfaces prepared for coating shall be coated the same day and before any visible rusting occurs. (The time elapsed between blast cleaning and commencement of painting shall under no circumstances exceed 4 hours, but in any case must commence before signs of degradation occur). 4.2.0 The coating usually has a specific adhesion requirement and proper selection of abrasive is most important. Generally, an abrasive is classified according to the following characteristics: a) Size - Usually by US sieve sizes (i.e., 16x40 mesh or 1.19 mm x 0.42 mm) b) c) d) Shape - Irregular, round. Sharp Hardness - Usually by Mohrs Hardness scale of the present element Colour - Light or dark

4.1.2

4.1.3

4.1.4

4.1.5

4.1.6

4.1.7

4.1.8

e) Chemical components - Abrasives shouldnt contain undesirable components that

G GS - 005 Rev 0

Page 5 of 46

Reliance Engineering Associates Private Limited


would remain on surface being cleaned. f) Specific Gravity or Weight - Heavy abrasives clean faster and impact much better while light weight abrasives are primarily used for polishing. g) pH of Abrasive - A neutral pH within the range of 7.0 1 is desirable. Salt water washed abrasives are not recommended. h) Availability and Cost Metal etching will remove mill scale, rust and other containment from metal to produce a white metal surface condition with an etch (anchor pattern) on the surface. Light cleaning removes only old paint and loose rust. 4.2.2 Criteria for selection of abrasives are certain key physical and chemical properties of the abrasives. Not all abrasives provide the same surface cleanliness. An abrasive effective for a commercial blast may not provide a near white or white metal blast cleaned surface. The coating system will therefore also influence the choice of abrasive for surface preparation. 4.2.3 A consistent range of abrasive particle sizes must be maintained to produce a consistent surface and cleaning rate. 4.2.4 The cleaning rate is affected with abrasive breakdown value. The greater the particle breakdown the poorer the cleaning rate. Manufacturers certificate should contain the breakdown value. 4.2.5 If the abrasive source is near seawater, routine checking for soluble chlorides is a must. 4.2.6 Visual inspection shall be carried-out to detect any sharp edges, weld spatter or visible laminations. Where these are discovered they shall be ground smooth prior to coating. TABLE 2 : ABRASIVE CHART Abrasive
Steel Shot Steel Grit Iron Grit Alum.Oxide Silicon Carbide Garnet Slag-Coal Slag-Nickel Slag-Copper Flint Sand Limestone Zirconium Glass beads

4.2.1

Type
Metallic Metallic Metallic Oxide Oxide Oxide Conglomerate Conglomerate Conglomerate Silica Silica Oxide Mineral Oxide

Major Component
Iron Iron Iron Alumina Silicon Carbide Iron-Silica Iron-Alum Silica Iron-Alum Silica Iron-Alum Silica Silica Silica CaCO2 Silica Silica

Shape
Round Angular Angular Angular Angular Irregular Irregular Irregular Irregular

Hardness (*)
Hard ** Hard ** Hard Hard Hard Hard Hard Hard Very Hard Medium Medium Soft Hard Medium Soft/ Medium

Sp. Gravity
7.2 7.6 7.4 3.8 3.8 4.0 2.8 3.2 3.3 2.7 2.7 2.4 4.5 2.7 1.0

Sharp Irregular Irregular Round Round Round / Plastic beads Organic Polymer resin Irregular * Soft materials are < 4 on Mohrs hardness scale; Medium 4 6; Hard 6 ** Various Hardness available

G GS - 005 Rev 0

Page 6 of 46

Reliance Engineering Associates Private Limited

TABLE 3 : CLEANING RATES WITH TYPICAL ABRASIVES Abrasive Consumption (lbs / Sq Ft) 2.6 3.6 3.1 5.5 3.6 3.2 Production rate (Sg Ft / Min.) 4.75 3.55 4.58 3.06 2.69 3.83

Abrasive Silica Sand 16/40 Mesh Garnet 36 Grit Aluminium Oxide 36 Grit Steel Grit G-40 Crushed Flint 12/30 Mesh Copper Slag 16/40 Mesh

Remarks 1.5 Mil Etch Dusty 1.5 Mil Etch Very little dusty 1.5 Mil Etch Very little dusty 2.5 Mil Etch No Dust 3 Mils 2 Mil Etch

TABLE 4 : International Standards of Blast Cleaning Cleaning Method


Hand tool cleaning Power tool cleaning White metal Near white metal Commercial blast Brush-off blast

Swedish Std
ST2 ST3 SA3 SA 2 1/2 SA2 SA1

ISO Std
SA3 SA 2 1/2 SA2 SA1

SSPC Std
SSPC SP2 SSPC SP3 SSPC SP5 SSPC SP10 SSPC SP6 SSPC SP7

NACE Std
NACE = 1 NACE = 2 NACE = 3 NACE = 4

TABLE 5 : Surface profiles with various Abrasives Abrasive


Very Fine Sand Coarse Sand Iron Shot Iron grit No.G16 Copper slag 1.5 2.0 mm grain size

Mesh Size
80 12 14 12 -

Max. height of Profile


37 microns (1.5 Mils) 70 microns (2.8 Mils) 90 microns (3.6 Mils) 200 microns (8.0 Mils) 75 100 microns (3 - 4 Mils)

G GS - 005 Rev 0

Page 7 of 46

Reliance Engineering Associates Private Limited 5 Coating Preparation and Application


5.1 Coatings and primers shall be delivered to the job site in the original containers bearing the manufacturers name , product designation, batch number, shelf life and date of manufacture. Before application, they shall be stirred or agitated until the ingredients are completely mixed. Material which have exceeded the manufacturers recommended shelf life shall not be used. Materials shall not be used or mixed into a new batch after its recommended pot life has been exceeded. Material shall be used on a first-in, first-out basis.

5.2 To facilitate proper stirring, the paint containers shall have mouth at the top centre. 5.3 Field application shall be by brush, roller or spray gun. Local regulations regarding spray and roller coating shall be observed. A smooth uniform film shall be applied to the surfaces to be coated. 5.4 The temperature of the substrate must be a minimum of 3oC above the dew point during abrasive blast cleaning and coating. The substrate temperature shall be a minimum of 5oC and a maximum of 60oC during coating application. 5.5 Painting shall be applied in strict accordance with the painting manufacturers latest published instructions. In particular, the manufacturers recommended curing or drying time shall be allowed between coats of primer and finish. Thickness of the painting shall be in accordance with the Painting schedule or the manufacturers latest published instructions. In the event of conflict, differences shall be brought to the attention of the Reliances painting specialist for resolution. 5.6 Paints, catalysts and thinners shall be stored in well ventilated buildings free from excessive heat, sparks, flames and direct sunlight. Paints stored for short times on the job site shall be protected from direct sunlight during the summer months. 5.7 For Field joint coating where blast cleaning is not possible, minimum ST2 surface preparation to be achieved. The field paint shall be compatible to ST2 surface finish as well as to existing paint at the adjoining area. 5.8 The life time of any protective system is determined by the dry film thickness of the paint system present on weld seams and sharp edges. Special attention should be given to sharp edges to ensure that they are covered with an adequate coating thickness. 5.9 Two component (base and hardener) coatings like Air drying epoxy, Polyurethane coatings etc shall be mixed in the ratio recommended by manufacturer to ensure proper and complete curing of the coatings. Improper ratio leads to problems like soft / nondried film, poor performance, etc. The base and hardener are to be separately mixed first to obtain a homogenous mixture. The hardener is to be added to the base slowly, with continuous mixing / agitation and not the reverse. Power agitation is preferred over hand mixing. 5.10 Any addition of thinner to achieve the application viscosity should be made only after the components are thoroughly mixed. Avoid using excess thinner than the recommended volumes, since this will lead to lower DFT build up, sagging, longer curing time, etc.

G GS - 005 Rev 0

Page 8 of 46

Reliance Engineering Associates Private Limited

5.11

Painting should not be undertaken during fog or mist conditions or when rain or snow is imminent, when the surface to be painted is wet with condensation or when condensation can occur during the initial drying period of the paint. The volume solids figure given in the product data sheets of paints is the percentage of the film obtained from a given wet film thickness under specified application and conditions. The theoretical coverage can be determined from the formula below: Theoretical coverage (m2 / Litr) = Volume solids (%) x 10 Measured dft (in microns) Pump pressure and correct tip sizes will be used to produce the most desirable spray size pattern and thickness on airless spray equipment. When using conventional spray equipment, the operator will ensure that the gun parts and outlets are maintained in a clean and working order to ensure the best of cosmetic appearance upon application. Coating containing heavy or metallic pigments that have a tendency to settle shall be kept in suspension by continuous use of a mechanical agitator whilst being applied, to ensure uniformity over the surface area (e.g., zinc MIOs pigmented materials). All edges, corners, webs and inaccessible areas, shall be strip coated prior to full application. To ensure integrity of WFT/DFT over surface areas.

5.12

5.13

5.14

5.15

5.16

6 Inspection
6.1 6.2 Inspection will be performed by an inspector authorised by Reliance. Prime coats shall be inspected and cleaned when required by Reliances Inspector, before applying finish coats. Dry film thickness shall be measured after each coat by Reliances Inspector using a Mikrotest, Elcometer, or Reliance accepted equal. The Painting Contarctors supervisor shall have in his possession at all times a wet film thickness gauge for continuous check of the wet film as applied. Defective work shall be corrected by the Painting Contractor at his sole expense. When more than one prime coat or finish coat is specified, use a contrasting colour in the first coat to distinguish between the first and second coats. The average value of thickness readings taken over any square meter of a scheduled area should be equal or exceed the nominal thickness specified and in no case should any reading be less than 75% of the nominal thickness.

6.3

6.4

6.5 6.6

6.7

G GS - 005 Rev 0

Page 9 of 46

Reliance Engineering Associates Private Limited


6.8 Areas where coating thickness either thin or too thick are to be marked and Paint contractor to carry-out repair at such areas. The surface areas shall be inspected to find holidays, runs, sags etc. Holidays, if detected shall be coated before full drying taking place. Runs and sags will be brushed out. Determination of the thickness of each coat in a multi-coat system should be an inspection hold-point. When using magnetic gages to measure multi-coat systems, the average of the first coat must be determined prior to application of second coat. Readings taken after the second coat is applied will obviously be the total thickness of the two coats combined, and the specific thickness of the second coat can only be determined by subtracting the average thickness obtained from the first coat reading.

6.9

6.10 Holiday or spark testing shall be done for immersion service to find the nicks, scrapes, and pin holes in the coating film. Holiday testing shall be done after application of either the next to last, or last coat of paint. 6.11 After all the coats of paint have been applied, the inspector should verify that the appropriate clean-up is done, and that any abrasions, nicks, or scrapes are repaired as required. If the coating is within the specification the item will be offered to the client or representative inspector where required. 6.12 Occasionally, there is a need to test the adhesion of the coatings after application. Measuring adhesion by Tape Test as described in ASTM D 3359 shall be used for adhesion test. 6.13 Surface preparation and coating shall be documented using the Format No. 1 (Surface preparation and Coatings Inspection Form).

G GS - 005 Rev 0

Page 10 of 46

Reliance Engineering Associates Private Limited


FORMAT No. 1 :SURFACE PREPARATION AND COATING INSPECTION FORM
PAGE _____ OF ______ REPORT No. : _____________________ PROJECT : _____________________ CONTRACTOR : _____________________ COMPLEX : _____________________ UNIT No. : __________ EQUIPMENT No. : ___________________ LINE No. : ___________________________ SUBSTRATE : STEEL / CONCRETE / OTHER ENVIRONMENTAL CONDITIONS COATING WORK ACTIVITY TIME DRY BULB TEMP oC WET BULB TEMP oC RELATIVE HUMIDITY % DEW POINT oC SURFACE TEMP oC BLOTTER TEST DATE : __________________________ DAY : __________________________ SHIFT : __________________________ INSPECTOR : ____________________ COATING SPEC No. / REV : ________ ________________________________

PRE-SURFACE PREPARATION SP 1 : _____________________________________________ MASKING / PROTECTION : ____________________

SURFACE DEFECTS : _______________________________________________________________________________________ ___________________________________________________________________________________________________________ SURFACE PREPARATION METHOD : ________________________________________________________________________________________________ ABRASIVE TYPE / SIZE / STORAGE : _________________________________________________________________________ CLEANLINESS SPEC : ________________________________ ACTUAL : ___________________________________ PROFILE SPEC : _____________________________________ ACTUAL : ___________________________________ EQUIPMENT : ______________________________________________________________________________________________ COATING MATERIALS AND MIXING: PRODUCT (S) : _____________________________________________________________________________________________ BATCH No(s) / QUANTITIES / EXPIRATION DATE : _____________________________________________________________ THINNERS / BATCH No(s) / THINNING RATIO : --_______________________________________________________________ STORAGE : _________________________________________ MIXING : ___________________________________ INDUCTION TIME : __________________________________ POT LIFE EXPIRATION TIME : ________________ MATERIAL TEMPERATURE : _________________________ COATING / LINING APPLICATION : START TIME : _____________ FIISH TIME : ________________ COAT : PRIMER / PRIMER T.U. / SECOND / SECOND T.U. / THIRD / THIRD T.U. / OTHER___________________________ METHOD : _________________________________________ WFT : ______________________________________ RECOAT TIME / TEMP : ______________________________ CURE TIME / TEMP: _________________________ EQUIPMENT : ______________________________________________________________________________________________ APPLIED COATING VISUAL INSPECTION (FILM IMPERFECTIONS) : ______________________________________________________________ DRY FILM THICKNESS : SPEC _______________ ACTUAL ________________ METHOD ____________________ HOLIDAY TEST : ____________________________________________________ METHOD ____________________________ OTHER TESTING : ____________________________________________________ METHOD ____________________________ TOUCH UP AND REPAIR : ____________________________________________ METHOD : ___________________________ COMMENTS : (USE REVERSE SIDE) INSPECTORS SIGNATURE

G GS - 005 Rev 0

Page 11 of 46

Reliance Engineering Associates Private Limited 7.


7.1

Work to be Performed
Work to be performed by the Field Painting Contractor includes the furnishing of materials and applying the painting in accordance with this specification. Loading/Unloading and handling of materials, equipment and tools shall be performed by the Field Painting Contractor. Field cleaning of pipe and equipment that is required prior to painting shall be performed by the Field Painting Contractor. This includes removal of dirt and dust which normally accumulates during storage and construction. Work shall be protected against damage during all stages of application by the Field Painting Contractor. The Field Painting Contractor shall be responsible for damage caused by wind blown overspray or spatter. The Field Painting Contractor shall take adequate precautions to prevent spattering and over spray of adjacent equipment, paving, structures, vessels, etc., by the use of drop cloths and shields. The Field Painting Contractor shall protect name plates, name tags, glasses on temperature indicators, pressure gauges, level instruments, etc., by masking or applying a heavy coat of lubricant. Operating mechanisms such as valve stems and valve positioners must also be protected. Masking and lubricant applied by the Field Painting Contractor shall be removed by him after completion of all work. The Filed Painting Contractor shall clean all spatter and over spray from equipment, vessels, tanks, piping, insulation, structures. A daily clean-up of the work area shall be made by the Field Painting Contractor to remove cartons, cans and other discarded containers or equipment.

7.2

7.3

7.4

7.5

7.6

7.7

8.

Coating System
Coating systems are listed in Appendix A. Only those products listed shall be used unless alternate products are approved by Reliance.

9.

Coating Schedule

9.1 Surface preparation, priming and finish coating for all vendor supplied equipment, vessels, exchangers, pumps, instrument panels etc. shall be in accordance with the schedule shown in Appendix D. 9.2 The paint system shall be applicable to carbon steel and low alloy (9% chrome or less) 9.3 All vendor supplied items like equipments,vessels, exchangers, pumps, instrument panels etc shall conform to Appendix D. 9.4 Regardless of insulation requirements, stainless steel including austenitic shall not be painted. All stainless steel shall be unprotected.

G GS - 005 Rev 0

Page 12 of 46

Reliance Engineering Associates Private Limited

9.5 Insulated Tanks shall not be painted. All other Tankages shall be painted in accordance with the Appendix D (other than Marine environment) or Appendix E (Marine environment). 9.6 All Piping will be painted in accordance with the Appendix D or E. 9.7 Galvanising shall only be used on stair treads, open grid flooring and steel gratings. All other structural parts to be painted in accordance with Appendix D or Appendix E.

10. Colour Schedule


10.1 In order to identify the contents of pipelines, colour code painting is required to be carried-out. The system of colour coding consists of basic identification colour together with colour bands. 10.2 The basic identification colour can be applied either on the entire length of the pipe or over a small length, minimum of 300 mm, and vary distinct from Primary and Secondary colour bands as shown in Appendix C. 10.3 The ground colour shall be as given in Appendix B. Ground colour will be applied to the entire surface of equipment except on precision machined surfaces, non-ferrous and threaded parts. On the pipes, the ground colour will be applied over the outer surface of uninsulated pipes. Valves on the pipelines shall be painted with the same ground colour. 10.4 The Service identification colour bands shall be in accordance with Appendix C. The colour band system is based on BS 1710. Colour bands as shown in Figure 1 are used over uninsulated as well as insulated piping (on cladding). 10.5 The colour bands serve the purpose of identification as well as flow direction. 10.6 Identification colour bands to be provided for Uninsulated and Insulated Process and Utility Piping. 10.7 Aluminium colour (ground colour as mentioned in Appendix B) shall be Non Leafing grade

G GS - 005 Rev 0

Page 13 of 46

Reliance Engineering Associates Private Limited 11. Appendices


Appendix A Appendix B Appendix C Appendix D Appendix E : Coating Systems : Coating Colour Schedule : Identification of Services Colour Coding of Piping : Coating Schedule (Other than Marine Environment) : Coating Schedule Marine environment

G GS - 005 Rev 0

Page 14 of 46

Reliance Engineering Associates Private Limited Appendix A Coating Systems


TYPE 01 DESCRIPTION Inorganic Zinc Silicate Primer Dry film thickness Required surface profile: Maximum temperature resistance: Minimum Volume solids 75 microns 50 microns 400oC 58 ASTM D2697

02

High Temperature Silicone Acrylic Dry film thickness : Required surface preparation: 50 microns Clean,dry inorganic zinc primer (type 01) 200oC 37 ASTM D2697

Maximum temperature resistance Minimum Volume solids

03

High Temperature Silicone Aluminium Dry film thickness: Required surface preparation: 25 microns Clean,dry inorganic zinc primer (type 01) 600oC (1)

Maximum temperature resistance Minimum Volume solids

49 ASTM D2697

These materials must generally be exposed to 175 o C or higher to fully cure. Coating must be capable of curing to handle at ambient temperature.

G GS - 005 Rev 0

Page 15 of 46

Reliance Engineering Associates Private Limited


TYPE 04 DESCRIPTION Zinc Rich Epoxy Primer Dry film thickness: Required surface preparation: Maximum temperature resistance: Minimum Volume Solids : 50 microns 25-35 microns 120oC 59 ASTM D2697

05

High Build MIO Epoxy Intermediate Dry film thickness: Required surface preparation : Maximum temperature resistance : Minimum Volume Solids : 125 microns Clean, dry epoxy primer (type 04) 120oC 55 ASTM D2697

The quantity of MIO in the main pigment shall be 80% by weight 06 Aliphatic Urethane Finish Dry film thickness : Required surface preparation : Maximum temperature resistance : Minimum Volume Solids : 75 microns Clean. Dry epoxy intermediate (type 05) 120oC 45 ASTM D2697

07

Zinc Free High Temperature Air Curing Finish Coat Dry film thickness : Required surface preparation : Maximum temperature resistance : 75 microns Clean, dry and salt free 600oC

08

High Build Epoxy for Stainless Steel Dry Film thickness : Required surface profile : 100 microns Sweep blast with aluminium oxide

G GS - 005 Rev 0

Page 16 of 46

Reliance Engineering Associates Private Limited


TYPE 09 DESCRIPTION Coal Tar Epoxy Dry film thickness: Required surface profile: 175 microns 75 microns

10

Amine Adduct Cured Epoxy Dry film thickness: Required surface profile: 80 microns 50 microns

11

Inorganic sealer top coat Wet film thickness : Dry film thickness: Maximum temperature resistance: Minimum volume solids: 50 microns 10 microns (mini.) 600 oC 6% ASTM D2697

12

Polysiloxane high heat coating Dry film thickness: Maximum temperature resistance: Minimum volume solids: 75 microns 600 oC 64% ASTM D2697

13

Inorganic Zinc Pre-construction Primer Dry film thickness: Maximum temperature resistance: 15-20 microns 400 o C

G GS - 005 Rev 0

Page 17 of 46

Reliance Engineering Associates Private Limited


TYPE DESCRIPTION

14

High Build Chlorinated Rubber Zinc Phosphate Primer Single pack chlorinated rubber medium plasticised with unsaponifiable plasticiser pigmented with zinc phosphate Dry film thickness: Required surface profile: Maximum temperature resistance: Minimum volume solids: 75 microns 50 microns 60 o C 45% ASTM D2697

Main pigment content shall be 40% by weight of total pigment (min.)

15

High Build Chlorinated Rubber MIO Paint Dry film thickness: Maximum temperature resistance: Minimum volume solids: 75 microns 60 o C 50% ASTM D2697

The quantity of MIO in the main pigment shall be 60% by weight.

16

Chlorinated Rubber Finish Single pack plasticised chlorinated rubber medium with chemical and weather resistant pigments. Dry film thickness: Maximum temperature resistance: Minimum volume solids: 50 microns 60 o C 40% ASTM D2697

Main pigment content shall be 90% by weight of total pigment (Mini.).

17

Synthetic Enamel (Suitable for over-coating primer types 01 and finish coat type16) Dry film thickness: Volume solids: 50 microns 40% ASTM D2697

G GS - 005 Rev 0

Page 18 of 46

Reliance Engineering Associates Private Limited


TYPE DESCRIPTION

18

Epoxy Finish Coat Dry film thickness: Minimum volume solids: 60 microns 45 ASTM D2697

19

High Build Epoxy Intermediate Dry film thickness: Minimum Volume solids: 100 microns 55 ASTM D2697

20

High Build Epoxy Intermediate Dry film thickness: Minimum Volume solids: 65 microns 55 ASTM D2697

G GS - 005 Rev 0

Page 19 of 46

Reliance Engineering Associates Private Limited


The products identified in the following table match with the Coating System in Appendix A TYPE COMPANY (Note 7)
CARBOLINE INTERNATIONAL AMERON BERGER ASIAN

01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20

Carbozinc 12 Carboline 1248 Carboline 4674 Carboline 658 Carboline 190HB MIO Carboline 133HB Carbomastic 15 Carbomastic 14 Carboline 187 Caroweld 11 HS

Interzinc 12 Intertherm 875 Intertherm 50 Interzinc 72 Interguard 400 Interthane 799 Intertherm 50 or Intern. XGP 639 Interplus 256 Intertuf 708 Interline 944 Intertherm 601 Interplate 11

Zinc Anode 11 Apcosil-605 Epilux 4HB Asian EZRP Amercoat 68HS Zinc Rich Primer PC 1299 Epilux 155HB Apcodur MIO Amercoat 383 MIO (RPL MIO) (RPL MIO) Berger Thane Apcothane HBPU Amercoat 450 SA 41 S/G (PC 1303) Apcotherm Amercoat 741 HR finish Amerlock 400 Amercoat SSPC.16 Epilux 555 Hb Apcodur CF655 Apcodur CF699 Epilux 78HBTL Amercoat 90 (Note 6) Amercoat 710 Amercoat PSX 892 HS Dimetcote DSP Linosol HB Red oxide ZP Primer Linosol MIO Apcocil-611 Asiochlor EHB ZP (PC 1417)

Dimetcote 9 FT Amercoat 891 Amercoat 878

CDC Interchlor HB Primer Multibond 2000 CDC Interchlor HB MIO Multibond 2001 Interchlor Finish -

Asiochlor HB MIO (PC 1416) Linosol Hi Build Asiochlor HB Coating CR Paint (PC 1226) Asian Epoxy HB Coating (PC 1262) Asian Epoxy HB Coating (PC 1262) -

NOTE All vendor supplied items to conform to Appendix 'B'. For potable water service Interline 925@400 microns DFT shall be used in lieu of Interline 944 An alternative to Intertuf 708 is Intertuf JXA 727/720 For potable water service, carboline 891 shall be used in lieu of carboline 187 After complete cure the coating shall be thoroughly rinsed with potable water prior to being placed in service Epilux 155 HB MIO shall be "RIL" grade only. Standard material shall NOT be used Apcodur-CF699 is approved for all services except POTABLE WATER
suitable for type of application , however Data Sheet should be checked to ensure compatibility for the Generally operating temperature and other special features.

G GS - 005 Rev 0

Page 20 of 46

Reliance Engineering Associates Private Limited

Appendix B :
CODE LETTER C

Coating Colour Schedule


DESCRIPTION COLOUR Aluminium BRITISH STD : 4800* -

Columns , Pressure Vessels, Exchangers Tankages : Heated (Except Acid, Caustic, Water)

Black White Sand

00 - E - 53 -

Refrigerated, Tanks inside battery limits All Tanks in Tank Farm Area Rotating equipment :

Pumps, Compressors, Turbines, Fans, Motors Uncovered moving parts that could cause injury

Light Grey Orange Light Grey

10 - A - 03 06 - E - 51 10 - A 03

Instrument Equipment Piping, Valves, Fittings etc : AIR services, unless galvanised Underground (Buried)

Light blue Black Fire Red Light Grey Yellow

20 - E - 51 00 E 53 04 E 53 10 A 03 08 E 51

Above ground Fire Water , Foam etc All other services except the above (Service identification bands Refer Appendix C ) Transition Flanges (between Above ground and Below ground) Structural Steel work (Unless Galvanised) and Concrete : Framework, Columns, Beams and Pipe Supports

Light Grey Black Yellow Light Grey Fire Red

10 - A - 03 00 E 53 08 E 51 10 A 03 04 E 53

Stairs, Platforms, Floor Plates, Kickplates Ladders, Ladder Cages, Hand rails

Electrical Equipment Fire Protection Materials and Equipment : Foamatic Hydrants, Water Hydrants, Extinguishers, Sprinkler Systems, Alarm Boxes, Fire doors, Connections and Cabinets for Fire Blankets and Hoses Safety Equipment : Safety Showers, Eyewash fountains, First Aid Equipments, etc.

Green

14 C 39

Note : * Corresponding Equivalent / Nearest IS colour shade is enclosed in cl. 6.0 of Appendix C

G GS - 005 Rev 0

Page 21 of 46

Reliance Engineering Associates Private Limited

Table 1 : Identification of Services


PIPE CONTENTS BOILER FEED WATER COOLING WATER (FRESH) COOLING WATER (SEA WATER) DESALINATED WATER EFFLUENT WATER WATER WITH OIL POTABLE WATER DEMINERALISED WATER TREATED EFFLUENT WATER UTILITY WATER SEA WATER SOUR WATER CONTAMINATED WATER PROCESS WATER FIRE WATER (FRESH) FIRE WATER (SEA WATER) DIESEL FUEL OIL LUBE OIL SEAL OR GLAND OIL FLUSHING OIL FIRE FOAM BREATHING AIR INSTRUMENT AIR PLANT AIR SYMBOLS WB WC WC WD WE WO WP WA WT WU WS WX WK WR WF WM DL FO LO SO FL FF AB AI AP LIGHT GREY (For Air) 10-A-03 BROWN (For Oils) 06-C-39 RED RED 04-E-53 04-E-53 WHITE CRIMSON EMARALED GREEN SALMN PINK PURPLE RED PALE GREEN CREAM BEIGE GREEN (For Water) 12-D-45 BASIC IDENTIFICATION BAND PRIMARY IDENTIFICATION BAND CRIMSON WHITE WHITE SKY BLUE BROWN BROWN BLUE RED PURPLE BROWN PURPLE BLUE YELLOW VIOLET BROWN PURPLE 04-D-45 00-E-55 00-E-55 18-E-49 06-C-39 06-C-39 18-E-53 02-C-33 06-C-39 20-C-37 10-C-33 22-D-45 06-C-39 24-C-33 SECONDARY IDENTIFICATION BAND YELLOW BLACK WHITE 00-E-55 00-E-53 10-C-33

COMPLETE PIPE COMPLETE PIPE 00-E-55 04-D-45 14-E-53 04-C-33 24-C-33 04-E-53 14-C-31 08-C-31 10-B-17 LIGHT BLUE FOR COMPLETE PIPE LIGHT BLUE FOR COMPLETE PIPE LIGHT BLUE FOR COMPLETE PIPE

005 Rev 0

Page

of 46

Reliance Engineering Associates Private Limited

PIPE CONTENTS

SYMBOLS FG FS LG AG RT PA PB PC PD

BASIC IDENTIFICATION BAND

PRIMARY IDENTIFICATION BAND GREEN GREEN VIOLET PURPLE SEA GREEN BROWN YELLOW PURPLE PURPLE 14-C-39 14-C-39 22-C-37 24-C-39 16-C-37 06-C-39 10-E-49 24-C-33 24-C-33

FUEL GAS (SWEET) FUEL GAS (SOUR) FLUE GAS OVERHEAD GAS FROM AMINE PLANT REFRIGERANT GENERAL HYDROCARBONS HYDROCARBONS WITH SULPHUR HYDROCARBONS WITH HYDROGEN HYDROCARBONS WITH HYDROGEN & H2S HYDROCARBONS WITH SOUR WATER PROCESS BLOWDOWN GENERAL HYDROCARBONS HYDROCARBONS WITH SULPHUR HYDROCARBONS WITH HYDROGEN HYDROCARBONS WITH HYDROGEN & H2S HYDROCARBONS WITH SOUR WATER HYDROGEN NITROGEN COKER MAZE DRAIN CRACKED SLOPS HEAVY SLOPS LIGHT SLOPS

SECONDARY IDENTIFICATION BAND PALE 14-C-31 GREEN VIOLET 22-C-37 YELLOW 10-E-49

PE

BA BB BC BD

YELLOW OCHRE (For Gases either Gaseous or Liquefied)

VIOLET 08-C-35 BROWN YELLOW PURPLE PURPLE

22-D-45

GREEN

12-D-45

06-C-39 10-E-49 24-C-33 24-C-33

YELLOW 10-E-49

BE HY NI MD SC SH SL

VIOLET CHARCOAL WHITE BLACK BLACK BLACK BLACK

22-D-45 00-A-13 00-E-55 00-E-53 00-E-53 00-E-53 00-E-53

GREEN SKY BLUE YELLOW GREEN YELLOW GREEN YELLOW

12-D-45

18-E-49 10-E-49 12-E-53 12-C-33

G GS - 005 Rev 0

Page 23 of 46

Reliance Engineering Associates Private Limited


BASIC IDENTIFICATION BAND PRIMARY IDENTIFICATION BAND PINK 04-C-33 YELLOW LIGHT GREEN PALE GREEN 22-C-37 DARK GREEN YELLOW CREAM PALE GREEN PALE GREEN DARK GREEN GREEN GREEN YELLOW GREEN YELLOW
CHARCOAL GREY (For Steam

PIPE CONTENTS CATALYST MOLTEN SULPHUR CHEMICALS AMINES HIGH STRENGTH CAUSTIC (25% OR GREATER) SULPHURIC ACID HYDROCHLORIC ACID LOW STRENGTH CAUSTIC (LESS THAN 20% CONC.) LOW LOW PRESSURE STEAM LOW PRESSURE STEAM MEDIUM PRESSURE STEAM HIGH PRESSURE STEAM HIGH HIGH PRESSURE STEAM RELIEF & BLOWDOWN STEAM LOW LOW PRESSURE CONDENSATE LOW PRESSURE CONDENSATE MEDIUM PRESSURE CONDENSATE HIGH PRESSURE CONDENSATE HIGH HIGH PRESSURE CONDENSATE

SYMBOLS CT SU CH CA CB VA HA CC YS LS MS HS ZS BS

SECONDARY IDENTIFICATION BAND PALE GREEN DARK GREEN 14-C-39 14-C-31

10-E-49 12-C-33 14-C-31 14-C-39 10-D-45 10-B-15 14-C-31 14-C-31 14-C-39 14-E-51 12-D-43 12-E-51 12-C-33

VIOLET (For Chemical or Acid)

GREEN YELLOW 00-A-13 PALE GREEN DARK GREEN GREEN GREEN YELLOW GREEN YELLOW

YC LC MC HC ZC

& Condensate)

14-C-31 14-C-39 14-E-51 12-D-43 12-E-51

G GS - 005 Rev 0

Page 24 of 46

Reliance Engineering Associates Private Limited


1.0 Flow Direction Band markings and arrows shall be made at the unit battery limits and then on convenient location at the point of use. It is recommended to adopt one method for the entire plant. 1.1 Flow direction by bands 1.1.1
FIGURE 1 Basic Identification Colour Band Direction of Flow B Primary Colour Band

The coding shall be arranged as indicated in Figure 1.

Dia PA C Contents Code A D A

1.1.2

For Dia > 4, dimensions of A and D shall be 2 x Dia. (18 maximum) and dimensions of B and C shall be Dia / 2 (9 maximum). For Dia < 4 , A = 100 mm, B = 50 mm, C = 25 mm and D = 100 mm. Colour Band C is located on down stream side of Basic Identification colour bands and indicates direction of flow. In case of double direction flow, the band C will be located each side of band A. Flow direction by Arrows The arrows shall be situated in the proximity of the basic identification colour and painted White or Black in order to contrast clearly with the basic identification colour. Arrow size : - For pipes diameter 2 to 6, arrow to fit in a 25 mm x 100 mm rectangular. - For pipes diameter 8 and above, arrow to fit in a 50 mm x 150 mm rectangular. Where flow of fluid is possible in either direction, the arrows will be indicated one above the other and the arrow heads in opposite directions. The colour of both the arrows will be same.

1.1.3 1.1.4

1.2 1.2.1

1.2.2

1.2.3

G GS - 005 Rev 0

Page 25 of 46

Reliance Engineering Associates Private Limited


2.0 Identification with two colour bands (Primary and Secondary)

2.1. The procedure as indicated in Figure 2 shall be used to identify services (such as for fuel gas, hydrocarbons etc) with two colour bands (Primary and Secondary) as described in Table 1.

Figure- 2
Basic Identification Band Primary Band colour Secondary Band

D/3 D/3 D/3

Direction of Flow

A D

2.2 The dimensions of A, B, C and D are same as per para 1.1.2 and 1.1.3.

3.0

Hazardous Mediums Where the piping system carries a hazardous product, a panel of equal diagonal stripes (black and yellow colours) shall be superimposed on the pipe on both ends of the basic identification bands as detailed in Figure 3.

Figure - 3
Direction of flow Equal Width Bands ** Basic Identification Bands B Primary Colour Band 45
o

PA A Contents Code Hazard Marking B C A D A B A Hazard Marking

Note : 1) ** Stripes of Black 00-E-33 & Yellow 08-E-51 2) All other dimensions are as per para 1.1.2 & 1.1.3

G GS - 005 Rev 0

Page 26 of 46

Reliance Engineering Associates Private Limited


4.0 Details of Contents Code Indication 4.1 The contents code indications shall be painted either in White or in Black in order to contrast clearly with the colour of paint on the pipe or equipment. For insulated lines the code indications shall be painted over the cladding of the insulation. The name of fluid flowing inside a pipeline shall be indicated. The line number shall also be painted on the pipelines. The pressure or temperature of the fluid inside the pipeline shall not be indicated. The contents code indication as described above shall be painted at following locations or such other places where quick identification is deemed necessary. Pipe lines : At all junctions, both sides of valves, both sides of service appliances and at intervals of 30 Mtr on straight pipe lengths For long straight lengths of pipelines, e.g., transfer lines, the interval of 30Mtr for code indication may be varied at the discretion of the Reliance. 4.4 The size of lettering for code indication on the insulated as well as uninsulated pipes is as follows. These sizes are only indicative and may be varied by the Reliance Engineer. For Pipes For Pipes For Pipes : Diameter 2 NB - 25 mm letters

4.2

4.3

: Diameter 3 to 6 NB - 50 mm letters : Diameter 8NB and above - 80 mm letters

5.0

Code Indication for Small Diameter Pipes Code indication marking by paint may not be done for uninsulated pipelines of nominal diameter 1 and below and for insulated lines less than 1 diameter. For such pipes, the indication markings shall be punched on lead tags secured to the pipe. Such tags shall be provided at locations described in section 4.3 above. The size of the tag and the method of tying it with pipeline shall be as per advice of the Reliance Engineer.

G GS - 005 Rev 0

Page 27 of 46

Reliance Engineering Associates Private Limited


6.0
SL No. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Equivalent / Nearest IS Colour Shades


SHADE NAME CHARCOAL / CHAR. GREY BLACK WHITE RED PURPLE SALMON PINK / PINK CRIMSON FIRE RED BROWN ORANGE CREAM YELLOW YELLOW LT GREY CREAM BEIGE YELLOW YELLOW YELLOW GREEN YELLOW / LT GREEN GREEN YELLOW GREEN GREEN YELLOW GOLD.YELLOW PALE GREEN GREEN / DARK GREEN GREEN EMERALD GREEN SEA GREEN SKY BLUE BLUE PURPLE BLUE LT. BLUE VIOLET SHADE NAME 00-A-13 00-E-53 00-E-55 02-C-33 04-C-33 04-D-45 04-E-53 06-C-39 06-E-51 08-C-31 08-C-35 08-E-51 10-A-03 10-B-15 10-B-17 10-C-33 10-D-45 10-E-49 12-C-33 12-D-43 12-D-45 12-E-51 12-E-53 14-C-31 14-C-39 14-E-51 14-E-53 16-C-37 18-E-49 18-E-53 20-C-37 20-E-51 22-C-37 IS CODE / BERGER IS 671 BERGER-589 BERGER-435 IS 540 IS 536 IS 415 IS 557 IS 442 IS 361 IS 356 IS 631 BERGER-095 IS 364 IS 352 IS 222 IS 365 IS 216 IS 278 IS 219 IS 354 IS 218 IS 275 IS 226 IS 280 IS 299 IS 102 IS 177 IS 176 IS 166 BERGER-134 BERGER-712

G GS - 005 Rev 0

Page 28 of 46

Reliance Engineering Associates Private Limited


Sl No. 34 35 36 SHADE NAME VIOLET PURPLE PURPLE SHADE NAME 22-D-45 24-C-33 24-C-39 IS CODE / BERGER IS 108 BERGER-728 IS 796

G GS - 005 Rev 0

Page 29 of 46

Reliance Engineering Associates Private Limited

Appendix D :

Coating Schedule (Other than Marine Environment)

G GS 005 Rev 0

Page 30 of 46

Reliance Engineering Associates Private Limited


C Painting Schedule Columns/Pressure Vessels/Exchangers/Heaters
SURFACE PREPARATION , PRIMING & COATING FIRST COAT INTERMEDIATE FINISH COAT COAT
TYPE WHERE APPLIED TYPE WHERE APPLIED TYPE WHERE APPLIED MIN. TOTAL DFT MICRONS

SURFACE PREP CODE DESCRIPTION


TYPE WHERE DONE

REMARKS

Ca

To be insulated fireproofed upto 400o C Uninsulated upto 120o C and nonfireproofed vessels skirts Uninsulated 121o C to 175o C Uninsulated 176o C to 400o C Ladders,platforms including framing and steel supports other than vessel clips, handrails, stair treads, open grid flooring, toe boards, floor plates Austenitic stainless steel. Operating between 50oC and 120o C Austenitic stainless steel. Operating between 120oC and 200o C Stair treads, open grid flooring, steel gratings

SA3 / 2 1/2

Shop

01

Shop

07

Shop

150

Cb

SA2 1/2 SA3 / 2 1/2 SA3 / 2 1/2

Shop

04

Shop

05

Shop

06

Shop

245 Primed surface to be free of zinc salts prior to finish coating As Cc above notes. Finish coat 03 may not fully cure until equipment is in service. Where not galvanised use systems Cb except as identified under code Ch Surface to be blast cleaned with Vasilgrit or other suitable Aluminium oxide abrasive. Surface to be blast cleaned with Vasilgrit or other suitable Aluminium oxide abrasive

Cc

Shop

01

Shop

02

Shop

125

Cd

Shop

01

Shop

03

Field

100

Ce

SA2 1/2

Hot dip galvanise to BS 729. Min. Coating WT 610 grams/m

Cf Cg

See Remark SA 2 1/2 See Remark SA 2 1/2 SA 2

Shop Shop

02 at (30 DFT)

08 at (100 DFT) 02 at (30 DFT)

Shop Shop

100 60

Ch

Shop

3 Coats Bituminous paint to BS:3416 Type 1 applied by dipping, DFT 40 microns per coat

120

G GS - 005 Rev 0

Page 31 of 46

Reliance Engineering Associates Private Limited


C Painting Schedule Columns/Pressure Vessels/Exchangers/Heaters
SURFACE PREPARATION , PRIMING & COATING
CODE DESCRIPTION SURFACE PREP
TYPE WHERE DONE

FIRST COAT
TYPE WHERE APPLIED

INTERMEDIATE COAT
TYPE WHERE APPLIED

FINISH COAT
TYPE WHERE APPLIED

MIN. TOTAL DFT MICRONS 200

REMARKS

Ci

Direct buried vessels upto 400o C Note 3 Note 4 Note 5

07 11 Shop Note 3 Note 4 For this service the coating shall be Amercoat 741 applied @ 125 microns D.F.T. The coat (Amercoat 710 ) shall be applied after previous coat has fully cured only This system will only be used in tandem with cathodic protection. SA 3 / 2
1/2

Shop

01

Shop

Shop or Field

Cj

All vessels operating above 400o C

SA2 1/2

Shop

12

Shop

75

G GS - 005 Rev 0

Page 32 of 46

Reliance Engineering Associates Private Limited


F Painting Schedule Tankage
SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED MIN. TOTAL DFT MICRONS

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

REMARKS

Fa

External Insulated

No

Painting

Where preparation is carried out in a shop or offsite it is mandatory that the first coat to be carried out at the same location Primed surface to be free of zinc salts prior to finish coating. Shop built tanks will be shop painted Drinking water grade, approved National Water Council Certificate required. Shop built tanks will be shop painted Shop built tanks will be shop painted. This system for corrosive service only. Shop built tanks will be shop painted

Fb

External Uninsulated upto 120oC

SA2 1/2

Field

01

Field

20

Field

18 (Note 1)

Field

200

Fc

External Uninsulated 121oC to 175oC

SA2 1/2

Field

01

Field

02 or 07

Field

125

Fd

Internal Potable water

SA2 1/2

Field

10

Field

10

Field

10

Field

240

Fe

Internal Industrial water, Ballast water, Slop Water, Demineralised Water

SA2

Field

09

Field

09

Field

350

Ff

Internal

SA2 1/2

Field

10

Field

10

Field

10

Field

240

G GS - 005 Rev 0

Page 33 of 46

Reliance Engineering Associates Private Limited


F Painting Schedule Tankage (Continued)
SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED MIN. TOTAL DFT MICRONS

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

REMARKS

Fg

External Underside of all Tanks External Austenitic stainless steel operating between 50o C and 120o C External Austenitic stainless steel operating between 121o C and 200o C

SA2 (Note 2)

Field

09

Field

175

A strip 75 mm wide at plate edge shall be left bare to avoid welding contamination

Fh

No

Painting

Fi

No

Painting

Note 1: Tankage within the Tank Farms that are designated Code Fb shall be camouflaged, as such they shall be finish painted with 60 microns of paint Type 18 to ensure a dull appearance.

Note 2: Where carboline Carbomastic 14 or Apcodur CF 655 (Asian) is used as the primer for the underside of tank plate , a commercial blast to SA 2 is acceptable. ( This does not apply to any immersion services)

G GS - 005 Rev 0

Page 34 of 46

Reliance Engineering Associates Private Limited


G Painting Schedule Rotating Equipment (Including Pumps, Compressors, Fans, Motors, etc.)
SURFACE PREPARATION , PRIMING & COATING MIN. INTERMEDIATE TOTAL SURFACE PREP FIRST COAT FINISH COAT COAT DFT WHERE WHERE WHERE WHERE MICRONS TYPE TYPE TYPE TYPE DONE APPLIED APPLIED APPLIED 1. All except Gb as for codes Ca to Cg 2. Machinery and drivers, instruments and associated valves may be finish coated with manufacturers standard coating system. Note: This standard will be subject to Reliance approval Manufacturers should notify detauls of the proposed paints systems to facilitate repair and maintenance. This system must be capable of the withstanding the enviornmental conditions for a period 5 years to Re 3 on European scale of degree of rusting. As for the system Cb with the exception that surface preparation will be to Standard ST3 Refer to Codes Cf and Cg.

CODE

DESCRIPTION

REMARKS

Ga

External

Total system to be shop applied

Gb Gc

Moving Parts Austenitic stainless steel

Total system to be shop applied

G GS - 005 Rev 0

Page 35 of 46

Reliance Engineering Associates Private Limited


J Painting Schedule Instrumentation Equipment
SURFACE PREPARATION , PRIMING & COATING CODE Ja Jb DESCRIPTION Housing and Equipment Supports Control panels
SURFACE PREP TYPE WHERE DONE FIRST COAT TYPE WHERE APPLIED INTERMEDIATE COAT WHERE TYPE APPLIED FINISH COAT TYPE WHERE APPLIED

MIN. TOTAL DFT MICRONS

REMARKS Housing to be finished coated in seller works All panels must display a smooth finish appearance. Hammered or stippled etc. Are not acceptable.

Shop or Shop or 245 06 Field Field This equipment shall have its surface prepared, primed and finished in accordance with manufacturers standards. Note: This standard will subject to Reliance approval. The system must be cable of withstanding the environmental conditions for a period of 5 years to Re 3 on the European scale of degree of rusting. Shop 04 Shop 05

Jc

Austenitic stainless steel

Refer to Codes Cf and Cg.

G GS - 005 Rev 0

Page 36 of 46

Reliance Engineering Associates Private Limited


L Painting Schedule
Piping, Valves and Fittings
CODE DESCRIPTION
o

SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE SURFACE PREP FIRST COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE DONE APPLIED APPLIED SA2 1/2 Shop 01 Shop Note 4 -

FINISH COAT TYPE 06 WHERE APPLIED Field

MIN. TOTAL DFT MICRONS

REMARKS

La1

La2

CS/AS Systems above 60 C but less than 120oC and not require steam out (Uninsulated) CS/AS Systems (i) above 120oC but less than 200oC (ii) Systems operating below 120oC but require steam out (Uninsulated) Systems above 200oC but less than 400o C (Uninsulated) Systems upto 120oC that require Colour coating 1) Piping upto 60oC but not require steam out

150

For PP insulated portion Type 01 to be applied. For PP insulated portion, generally no paint is required but Type 01 may be applied.

SA2 1/2

Shop

01

Shop

Note 4

02

Field

125

La3

SA2 1/2

Shop

01

Shop

Note 4

07 (Note 7)

Field

150

For PP insulated portion, generally no paint is required but Type 01 may be applied.
e.g. Fire water piping

Lb

SA2 1/2

Shop

01

Shop

Note 4

06

Field

150

SA2 1/2

Shop

14

Shop

15

Lc

2)Flare(OSBL)

Shop or Field

16

Field

200

Type 15 to be applied in shop within 28 days of Primer application. This is also applicable for hot insulated piping upto 120o C which require steam out.

Lh1

Hot insulated piping

120o C

SA2 1/2

Shop

01

Shop

Lh2

Hot insulated piping > 120o C

Note: The coating system for Off the Shelf valves could be manufactures standards subject to Reliances approval. The system must be capable of withstanding the environmental conditions for a period of 5 years to Re 3 on the European scale of degree of rusting. Contd. on next page

G GS - 005 Rev 0

Page 37 of 46

Reliance Engineering Associates Private Limited


L Painting Schedule Piping, Valves and Fittings (Continued)
SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED 07 (Note 1) 11 (Note 2) Shop or Field Cathodic Protection by sacrificial anode Note 3) Note 5

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

MIN. TOTAL DFT MICRONS

REMARKS

Le Lf

Austenitic stainless steel operating 50oC and 120oC Austenitic stainless steel operating 121oC and 200oC Closed drain buried piping operating above 65oC Operating below 65o C

Lg1

SA2 1/2

Shop

01

Shop

Shop

200

Lg2

SA2 1/2

Shop

09

Shop

75

Note 1:

For this service , the coating shall be Amercoat 741 applied at 125 microns DFT

Note 2: This coating ( Amercoat 710) is a low solids sealer coat that shall only be applied after previous coat has fully cured Note 3: Note 4: Note 5: Note 6: It is mandatory that this system is protected by sacrificial anode cathodic protection Intermediate coat exempted External surface protection by coating and wrapping Field joint Coating Temperature from 0oC to 204oC : CDC Paint HM 21 (Primer 75 microns) and HM1248 (Intermediate-75 microns) with ST 2 surface preparation.

Note 7: Colour band as per Appendix C to be provided if Type 07 paint is not available in Light Grey colour

G GS - 005 Rev 0

Page 38 of 46

Reliance Engineering Associates Private Limited


M Painting Schedule

Structural Steelwork and Concrete


SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED MIN. TOTAL DFT MICRONS

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

REMARKS

Ma

General not concrete encased

SA3 / 2 1/2

Shop

14 (Note 1)

Shop

15

Shop

16

Field

200

Mb

General concrete encased

SA3 / 2 1/2

Shop

14

Shop

16

Field or Shop (Note 2)

125

i) Primed surface to be free of zinc salts prior to finish coating ii) Intermediate coat to be applied within 28 days of primer application. Primed surface to be free of zinc salts prior to finish coating Where no galvanised, use system Cb except as identified under code Md (Note 3)

Mc

Stair Treads, Open Grid Floor plates Stair Treads, open grid flooring, steel gratings Structural steel protection with light weight proofing Ladder, Handrails. Toe boards, Platforms including framing and steel supports

SA2 1/2

Hot dip galvanised to BS 729 Min. coating Wt. 610 grams/m

Md Me

SA2 1/2

3 Coats of Bituminous paints to BS 3416 Type 1 applied by dipping. DFT 40 microns per coat As per Mb above

120 . Refer remarks of Code Ma (Note 1)

Mf

SA2 1/2

Shop

14

Shop

15

Shop

16

Field

200

Note 1: Reliance Fabrication shop may apply Pre-Construction, based on requirement (but not mandatory) primer Type 13, DFT 15 to 20 microns. Note 2 : If fireproofing is applied away from job site, the finish paint coating over steelwork shall also be applied at the same location Note 3 : Repair to Damaged Galvanised Surfaces - Damaged areas of galvanised structures shall be feathered back to sound coating and cleaned as per SSPC-SP3. The area shall be coated with a high zinc dust content galvanising repair coating such as METAL FLUX or approved equal.

G GS - 005 Rev 0

Page 39 of 46

Reliance Engineering Associates Private Limited


P Painting Schedule Electrical Equipment
SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED MIN. TOTAL DFT MICRONS

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

REMARKS

Pa

Motors, Switchgears, Std Equipment Junction Boxes Equipment Supports, Motor Control Stations Austenitic stainless steel Cabble tray and Ladder Rack

This equipment shall be prepared, primed and finished in accordance with manufacturers Standards. The system must be capable of withstanding the environment conditions for period of 5 years to Re 3 on the European scale of rusting SA2 1/2 Shop 04 Shop 05 Shop or Field 06 Shop or Field 245

Pb Pc Pd

Manufacturers Standard will be subject to Reliance approval .Shop fabricated supports will be painted in the shop.

Refer to Codes Cf and Cg. SA2 1/2 Hot dip galvanised to BS 729 . (Minimum coating thick, as detailed BS 729 per Steel selection)

G GS - 005 Rev 0

Page 40 of 46

Reliance Engineering Associates Private Limited

Appendix E :

Coating Schedule (Marine Environment)


: Same as Appendix D : Same as Appendix D

1) C Painting Schedule Columns / Pressure Vessels / Exchangers / Heaters 2) G Painting Schedule Rotating Equipment (Including Pumps, Compressors, Fans, Motor, etc) 3) J Painting Schedule Instrumentation Equipment 4) P Painting Schedule Electrical Equipment

: Same as Appendix D : Same as Appendix D

G GS - 005 Rev 0

Page 41 of 46

Reliance Engineering Associates Private Limited


F Painting Schedule Tankage
SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED MIN. TOTAL DFT MICRONS

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

REMARKS

Fa

External Insulated

No

Painting Where preparation is carried out in a shop or offsite it is mandatory that the first coat to be carried out at the same location Primed surface to be free of zinc salts prior to finish coating. Shop built tanks will be shop painted Drinking water grade, approved National Water Council Certificate required. Shop built tanks will be shop painted Shop built tanks will be shop painted. This system for corrosive service only. Shop built tanks will be shop painted

Fb

External Uninsulated upto 120oC

SA2 1/2

Field

01 (60 microns)

Field

19

Field

18 (Note 1)

Field

220

Fc

External Uninsulated 121oC to 175oC

SA2 1/2

Field

01 (60 microns)

Field

02 or 07

Field

110

Fd

Internal Potable water

SA2 1/2

Field

10

Field

10

Field

10

Field

240

Fe

Internal Industrial water, Ballast water, Slop Water, Demineralised Water

SA2 1/2

Field

09

Field

09

Field

350

Ff

Internal

SA2 1/2

Field

10

Field

10

Field

10

Field

240

G GS - 005 Rev 0

Page 42 of 46

Reliance Engineering Associates Private Limited

F Painting Schedule Tankage (Continued)


SURFACE PREPARATION , PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT TYPE WHERE APPLIED TYPE WHERE APPLIED TYPE WHERE APPLIED

SURFACE PREP CODE DESCRIPTION TYPE WHER E DONE

MIN. TOTAL DFT MICRONS

REMARKS

Fg

External Underside of all Tanks External Austenitic stainless steel operating between 50oC and 120oC External Austenitic stainless steel operating between 121oC and 200o C

SA2 1/2 (Note 2)

Field

09

Field

A strip 75 mm wide at plate edge shall be left bare to avoid welding contamination

Fh

No

Painting

Fi

No

Painting

Note 1: Tankage within the Tank Farms that are designated Code Fb shall be camouflaged, as such they shall be finish painted with 60 microns of paint Type 18 to ensure a dull appearance. All other tanks shall be finish painted with 60 microns of paint Type 06 Note 2: Where carboline Carbomastic 14 or Apcodur CF 655 (Asian) is used as the primer for the underside of tank plate , a commercial blast to SA 2 is acceptable. ( This does not apply to any immersion services)

G GS - 005 Rev 0

Page 43 of 46

Reliance Engineering Associates Private Limited


L Painting Schedule Piping, Valves and Fittings
CODE DESCRIPTION
o

SURFACE PREP TYPE WHERE DONE

SURFACE PREPARATION ,PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED

MIN. TOTAL DFT MICRONS

REMARKS

Lb1

Lb2

CS/AS Systems above 60 C but less than 120oC and not require steam out (Uninsulated) CS/AS Systems (i) above 120oC but less than 200oC (ii) Systems operating below 120oC but require steam out (Uninsulated) Systems above 200oC (Uninsulated) but less than 400o C CS Systems upto 120oC that require Colour coating 1)CS Piping upto 60oC but not require steam out

SA2 1/2

Shop

01

Shop

Note 4

06

Field

150

For PP insulated portion Type 01 to be applied. For PP insulated portion, generally no paint is required but Type 01 may be applied. For PP insulated portion, generally no paint is required but Type 01 may be applied. e.g. Fire water piping

SA2 1/2

Shop

01

Shop

Note 4

02

Field

125

Lb3

SA2 1/2

Shop

01

Shop

Note 4

07 ( Note 7)

Field

150

Lb

SA2 1/2

Shop

01

Shop

Note 4

06

Field

150

Lc Lh1

2)Flare System upto 60oC

SA2 1/2

Shop

01

Shop

15

Shop or Field

16

Field

200 This is also applicable for hot insulated piping upto 120o C which require steam out.

Hot insulated piping

120 C

SA2 1/2

Shop

01

Shop

75

Lh2

Hot insulated piping >120oC

Note: The coating system for Off the Shelf valves could be manufactures standards subject to Reliances approval. The system must be capable of withstanding the environmental conditions for a period of 5 years to Re 3 on the European scale of degree of rusting.

G GS - 005 Rev 0

Page 44 of 46

Reliance Engineering Associates Private Limited


L Painting Schedule Piping, Valves and Fittings (Continued)
SURFACE PREPARATION, PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT TYPE WHERE APPLIED TYPE WHERE APPLIED TYPE WHERE APPLIED

SURFACE PREP CODE DESCRIPTION TYPE WHER E DONE

MIN. TOTAL DFT MICRONS

REMARKS

Le Lf Lg1

Austenitic stainless steel operating 50oC and 120oC Austenitic stainless steel operating 121oC and 200oC Closed drain buried piping operating above 65oC Operating below 65oC Note 1:

SA2 1/2 Shop

01 Shop

07 (Note 1) Shop 11 (Note 2) Shop or Field 200 Cathodic Protection by sacrificial anode ( Note 3) (Note 5)

Lg2

SA2 1/2

Shop

09

Shop

75

For this service , the coating shall be Amercoat 741 applied at 125 microns DFT

Note 2: This coating ( Amercoat 710) is a low solids sealer coat that shall only be applied after previous coat has fully cured Note 3: Note 4: Note 5: Note 6: It is mandatory that this system is protected by sacrificial anode cathodic protection Intermediate coat exempted External surface protection by coating and wrapping Field joint Coating Temperature from 0oC to 204oC : CDC Paint HM 21 (Primer 75 microns) and HM 1248 (Intermediate-75 microns) with ST 2 surface preparation. Colour band as per Appendix C to be provided if Type 07 paint is not available in Light Grey colour

Note 7:

G GS - 005 Rev 0

Page 45 of 46

Reliance Engineering Associates Private Limited


M Painting Schedule ( MTF Area) Structural Steelwork and Concrete
SURFACE PREPARATION , PRIMING & COATING INTERMEDIATE FIRST COAT FINISH COAT COAT WHERE WHERE WHERE TYPE TYPE TYPE APPLIED APPLIED APPLIED MIN. TOTAL DFT MICRONS

CODE

DESCRIPTION

SURFACE PREP TYPE WHERE DONE

REMARKS

Ma

General not concrete encased

SA3/ SA 2 1/2

Shop

01 (60 microns)

Shop

15

Shop

16 (60 microns)

Field

185

Mb

General concrete encased

SA3/ SA2 1/2

Shop

01

Shop

16

Field or Shop (Note 2)

125

Primed surface to be free of zinc salts prior to finish coating Intermediate coat to be applied within 28 days of primer application. Primed surface to be free of zinc salts prior to finish coating Where no galvanised, use system Cb except as identified under code Md (Note 3)

Mc

Stair treads, Open Grid Floor plates Stair treads, open grid flooring, steel gratings Structural steel protection with light weight proofing Ladder, Handrails. Toe boards, Platforms includiung framing and steel supports

SA2 1/2

Hot dip galvanised to BS 729 Min. coating Wt.610 grams/m2

Md Me

SA2 1/2

3 Coats of Bituminous paints to BS 3416 Type 1 applied by dipping. DFT 40 microns per coat As per Mb above

120 .

Mf

SA2 1/2

Shop

01 (60 microns)

Shop

15

Shop

16

Field

200

Refer remarks of Code Ma (Note 1)

Note 1: Reliance Fabrication shop may apply Pre-Construction, based on requirement (but not mandatory) primer Type 13, DFT 15 to 20 microns. Note 2 : If fireproofing is applied away from job site, the finish paint coating over steelwork shall also be applied at the same location Note 3 : Repair to Damaged Galvanised Surfaces - Damaged areas of galvanised structures shall be feathered back to sound coating and cleaned as per SSPC-SP3. The area shall be coated with a high zinc dust content galvanising repair coating such as METAL FLUX or approved equal.

G GS - 005 Rev 0

Page 46 of 46

You might also like