NOTE: (Boiler Requirements)

Chimney:
The flue should be designed to EN 13384 and be
sealed against water ingress.
The flue pipe must rise continually and must be
thermally insulated. Flue should incorporate a
draught regulator and Explosion flap in line.
Acoustic:
HERZrecommends that the entire heating system
(i.e. boiler plant, fuel delivery augers, flue gas
cyclones, heater pipes, etc....) is impact with
silencers (noise compensators). In particular when
using a cyclone dust separator, flexible connectors
must be fitted on the inlet and discharge. If required,
the flue should be fitted with an attenuator.
Heating water:
Heating water quality should be in accordance with
OENORMH 5195 and/or EN 12828 and/or VDI
2034.
Earth Bonding:
The entire heating systemshould be earth bonded.
In case of pellet firing plants the clutch set system
Storz A 110 has to be likewise merged into the
potential equalization.
Power supply:
A power supply (230/400V) for the pellet supplier
has to be installd near the clutch set system.
In case of remote visualization or maintenance the
telephone connection for the 56K modemmust be
installed by the customer.
Power supply for boiler (firematic +BioMatic):
3x400V +N +PE, 50 Hz.
max. fuse (slowacting) 16A for firematic, 20A for
BioMatic.
Power supply for boiler (firestar, minifire, pelletstar):
~230V +N +PPE, 50 Hz.
Max. fuse 10A slowly-acting.
For personal security a Fl protective circuit-breaker
shall be provided.
Buffer tank:
HERZrecommends by all automatic biomass
heating systems to use a specific dimensioned
buffer tank. For hand filling systems this buffer tank
is regulation
Antifreeze:
The heating systemshould be filled with the
appropriate quantity of anti-freeze fromthe installer.
Fire protection system:
HERZrecommend in heating rooma temperature
control instand of a flue-gas control
Statics:
For all constructional components (ceilings, walls,
etc.) a static certificate fromthe client will be
needed. This is not the responsibility of the
boiler-suppliers.
Health and Safety instructions
Louvers should be installed to provide sufficient free
air for the boilers. (Observe country-specific
regulations.)
Take care when opening the combustion chamber
inner door. Do not leave the door opened when
boiler is unattended.
Isolate the power supply to the boiler before opening
the bio control unit or undertaking any maintenance
work.
Do not store fuel or other materials within the boiler
room. Furthermore storage of materials, don't
needed for maintenance or operating is not allowed.
While blowing in the fuel storage roomwith pellets,
the boiler has to be turned off.
The fuel store should be secured to prevent
unauthorised access.
If the capacity of the wood pellets fuel store is
more than 20 m, it must have sufficient
ventilation to provide 3 air changes per hour.
Also,
Smoking, or naked flames are strictly forbidden!
Keep pellets dry!
Be aware of the risk of injury due to movable
parts!
Keep children away!
In case where entry a pellet store is required:
The store should be ventilated at least 30
minutes before any personnel enter!
Do not enter the pellet store alone!
Turn off the boiler at the main isolator and lock
the isolator off.
The boiler must be used with the correct
specification fuel.
The boiler should be turned off and isolated whilst
pellets are being blown into the fuel store.
The ash should be emptied into a temporary storage
receptacle and left to cool for at least 96 hours prior
to being disposed of.
The Health and Safety handbook should be read
prior to any maintenance work being undertaken.
The Health and Safety instruction should be
observed at all times.
Date
Scale
Drawing number.:
Name Date
necessary course need chimney [Pa]:
All meassures of the boiler installation are up to encasement.
chimneyheight [m]:
Authority
Constructor
Foreman
Planner
if stock >50 m^3)
temperature controller for conveyning screw
manual actuate extinguishing installation (to establish by others
for filling altidude
Conveyor screw
chimneydiameter [mm]:
range of performance: [kW]
Heating main switch
Fire extinguisher
Herz
TB...
HLE...
with "TB"
3
Control box
Fire fighting water container 6
8
7
4
2
1
Wood chips (NORM M 7133)
Wood pellet (NORM M 7135)
according to order
All break-throughs by fire-steady walls (F90), which for the assembly the plant
are necessary, must after the completion be disguised again fire-steadily and/or
locked.
All structural measures for adherence to the TRVB H118 are to be kept by the
customer.
Air ventilation : (to outside)
For adherence to this demand we recommend 5cm^2 per KW of performance,
however a supply air cross section of min. 400 cm2.
With rectangular openings aspect ratio should not more largely than 1,5: 1 its,
with covering is to be made an appropriate addition, so that the free cross
section achieves the demand specified above. Fire protection regulations in
accordance with TRVB H 118 and/or country-specific regulations regarding
cross sections are to be kept by the client.
The dimensions for ingress of all components to deliver must be controll by the
client so this is his reach of responsibility.
HERZ Energietechnik GmbH
Herzstrae 1, 7423 Pinkafeld
sterreich/Austria
Phone: +43 (0) 3357 / 42 84 0, Fax.: +43 (0) 3357 / 42 84 0 - 190
E-mail office-energie@herz.eu, Web: www.herz.eu
HERZ Energietechnik GmbH
Herzstrae 1, 7423 Pinkafeld
sterreich/Austria
Phone: +43 (0) 3357 / 42 84 0, Fax.: +43 (0) 3357 / 42 84 0 - 190
E-mail office-energie@herz.eu, Web: www.herz.eu
Confirmation by Client or
field represantive
date / signature
Offerdrawing
2012-07-17
1:50
HERZ Romania
10
lt. EN 13384
Max. 8,0 mfor wood chips
lt. EN 13384
300 - 1000
Wood Chips
1000 BioControl x 3 BioFire
H
E
R
Z
B
ioF
ire 1000
Kesselgewicht ohne W
asser:
7.075 kg
W
eight of boiler without water:
7.075 kg
H
E
R
Z
B
ioF
ire 1000
Kesselgewicht ohne W
asser:
7.075 kg
W
eight of boiler without water:
7.075 kg
H
E
R
Z
B
ioF
ire 1000
Kesselgewicht ohne W
asser:
7.075 kg
W
eight of boiler without water:
7.075 kg
+-0,00
min. RH =2865
Boilerrrom
+-0,00
min. SH =8000
Storrageroom
This drawing serves only as a planning tool for internal use and should not
be used as a construction drawing. Contravention does HERZno
responsibility for any subsequent costs.
Changes only by HERZwith CADallowed.
for BioFire BioControl
chimneyattachment
H1...effectiv level chimneyattachment
H2...effectiv chimney height (EN 13384)
H3...total chimney height
Flexi connectors
Thermally insulated and continuously
rising to chimney connection
Draft regulator and explosions relief
finerydoor
bind BioMatic construction in the
potential equalisation
Schematic diagram
H
2 = E
N
13384
H
3 H
1
keep care of the
maintenance of the
agitatorgear
put our equipment actuate
by manuall
access opening
(referral)
brickwork
cover for
access opening
WOODCHIPS
~350 kg/m3
PELLETS
~650 kg/m3
Detail slapping and
breakthrough
fit intermediate floor to the angle
of the agitator
z.B.: of wood or cement
auger channal
look detail
A B
400V 230V
A max.150 max.200
min. 40 B min. 40
defaults of fire
protection systemhave
to adhered by side
230V/400V
close breaktrough in
compliance with
countryregulations
platecover - on side
no burnable attachment
access hatch in compliance with
countryregulations
on site lagging - bodyclangdecoupling
(rockwool) min. 250 mm(compressed)
with a fusionpoint > 1.000C