You are on page 1of 10

PrePre-Installation Requirements

HAF/2

HAF/2

Machine Data
The figure on the cover may not exactly represent the delivery state of the machine.

Machine Data
Type
Number
Ident number
Year of manufaction

HAF/2
MA 14668-9-1
1-5501-415017-3
2011

Electrical Data
Voltage

3 x 415 V 5%

Power consumption

50 Hz 5%
2.0 kVA

Manual
Pre-Installation Requirements
Printed

GB-27989
10.10.2011

Frequency

Imprint
Publisher

HERZOG Maschinenfabrik GmbH & Co.


Auf dem Gehren 1
D-49086 Osnabrck
info@herzog-maschinenfabrik.de

E-Mail

Permission for any entire or partial copying or reprinting must always be


obtained from the publisher.

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

Contents

Contents
V-01

V-02

V-03
V-04
V-05

Requirements of the installation site ...................................................... 4


Space required for operation and maintenance ..................................... 4
Space required....................................................................................... 4
Ground, foundation ................................................................................ 5
Ground ................................................................................................... 5
Energy requirements.............................................................................. 6
Electricity................................................................................................ 6
Compressed air...................................................................................... 6
Spraying unit .......................................................................................... 6
Suction unit ............................................................................................ 6
Supply and waste connections............................................................... 7
Connections ........................................................................................... 7
Safety devices for the operator .............................................................. 8
Suction unit (option) ............................................................................... 8
Permissible environmental impact, emissions ....................................... 9
Permissible environmental impact ......................................................... 9
Emissions............................................................................................... 9

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

V-01 Requirements of the installation site


Space required for operation and maintenance

V-01 Requirements of the installation site

GB-00204

Space required for operation and maintenance

GB-00335

Space required

GB-12380

bd 224877-9

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

V-01 Requirements of the installation site


Ground, foundation

Ground, foundation

GB-00345

Ground

GB-12381

bd 224878-9

Standing surface
Weight
Load bearing capacity of the ground
Foundation
Ground

0.36 m
350 kg
2
975 kg/m
not required
level, capable of bearing the machine load
GB-12384

NOTE
Laying rubber or felt strips is recommended if the installation site is uneven.
Rubber- or felt strips
bd224879-7

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

V-02 Energy requirements


Electricity

V-02 Energy requirements

GB-00207

Electricity

GB-12382

3-Phase AC
Permissible deviation
Neutral conductor
Frequency
Permissible deviation
Power lead

Voltage customer specific


5%
not required
50 Hz, 60 Hz
5%
2 KVA

Compressed air
Excess pressure
Permissible contamination
Consumption

min.
5 bar
max. 10 bar
filtered with 40 m pore size
free of oil and water
3
max. approx. 100 dm N / sample
medium approx. 20 - 30 dm3N / sample

Spraying unit
max. approx. 20 cm3/min
3
medium approx. 10 cm /min

Coolant consumption

Suction unit
Suction unit for spray
Static pressure Pst at intake approx. 800 Pa
Suction power Vmax at intake max. approx. 3.5 m3/min

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

V-03 Supply and waste connections


Connections

V-03 Supply and waste connections

GB-00209

Connections

GB-30467

Connections

1 = Suction connection ( 60 mm)


2 = Compressed air connections ( 6 mm)
3 = Equipotential bonding
4 = Electrical cable bush (M25)

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

V-04 Safety devices for the operator


Suction unit (option)

V-04 Safety devices for the operator

GB-00211

Suction unit (option)

GB-00212

If coolants are used in sample preparation, the resulting vapours must be


extracted from the machine area and led into open air.
If no suction device was purchased with the machine as an option, the
customer must provide a suction device.
Local safety regulations apply to the operation of the spraying device with
dangerous substances.

14668-9-1

GB-27989

Pre-Installation Requirements

HAF/2

V-05 Permissible environmental impact, emissions


Permissible environmental impact

V-05 Permissible environmental impact, emissions

GB-00213

Permissible environmental impact

GB-00214

Ambient temperature

max. + 40C
min. + 10C
max. 1000 m
92 % relative
0.2 g

Elevation of the installation site


Humidity
Vibrations

CAUTION!
Aggressive air components are not permissible.

GB-06585

Emissions
Noise emission in correct use
Peak noise levels

75 dB (A)
81 dB (A)

The noise emission is depending on the sample material and the milling depth.
The processing of brass causes more noise than the processing of aluminium.

14668-9-1

GB-27989

Pre-Installation Requirements

HERZOG Maschinenfabrik GmbH & Co. Auf dem Gehren 1 D-49086 Osnabrck

You might also like