Professional Documents
Culture Documents
FECHA:
Descripcin
Und.
Metrado
Precio (S/.)
6/4/2011
Parcial (S/.)
01.01
m2
4,552.31
57.02
259,572.72
01.02
m2
989.60
95.37
94,378.15
01.03
m2
423.32
42.57
18,020.73
01.04
m2
27.96
56.91
1,591.20
02
m2
10,362.81
17.39
180,209.27
02.02
m2
1,882.03
21.34
40,162.52
02.03
m2
1,052.14
26.13
27,492.42
02.04
450.38
12.06
5,431.58
02.05
3,280.08
13.65
44,773.09
02.06
478.40
18.74
8,965.22
02.07
m2
1,052.14
27.49
28,923.33
335,957.42
CIELORRASOS
03.01
m2
4,147.27
30.13
124,957.25
03.02
m2
223.68
20.28
4,536.23
03.03
m2
219.90
29.80
6,553.02
04
373,562.80
02.01
03
TOTAL
ALBAILERIA
136,046.50
PISOS Y PAVIMENTOS
04.01
m2
3,826.82
25.46
97,430.84
04.02
m2
568.50
66.59
37,856.42
04.03
m2
200.80
70.86
14,228.69
04.04
m2
289.99
13.47
3,906.17
04.05
m2
1,562.58
38.33
59,893.69
213,315.80
m2
50.45
18.90
953.51
953.51
m2
223.68
54.13
12,107.80
12,107.80
m2
1,838.76
31.26
57,479.64
57,479.64
58,766.82
05
05.01
06
06.01
07
07.01
08
ZOCALOS
ZOCALO CERMICO CELIMA CEMENTO GRIS EXTRA 0.10x0.40M
REVESTIMIENTO DE GRADAS Y ESCALERA
REVESTIMIENTO DE GRADAS Y ESCALERAS DE TERRAZO
CUBIERTAS
CUBIERTA LADR.PASTELERO ASEN.DE BARRO 3CM.+FRAGUA C/MOR. 1:5
PINTURA
08.01
m2
4,147.27
14.17
08.02
m2
1,882.03
12.04
22,659.64
08.03
m2
10,362.81
12.04
124,768.23
09
09.01
m2
80.64
224.76
18,124.65
09.02
m2
301.56
133.84
40,360.79
09.03
pza
648.00
3.58
2,319.84
09.04
m2
143.73
235.02
33,779.42
09.05
m2
95.82
907.02
86,910.66
09.06
250.80
67.43
16,911.44
20,615.76
10
250.80
82.20
10.02
m2
6.93
721.65
5,001.03
10.03
m2
12.60
1,073.34
13,524.08
und
15.00
46.10
691.50
11.02
pza
36.00
56.29
2,026.44
11.03
pza
112.00
56.29
6,304.48
11.04
pza
36.00
56.29
2,026.44
11.05
pza
36.00
56.29
2,026.44
11.06
pza
36.00
56.29
2,026.44
11.07
pza
6.00
133.29
799.74
11.08
pza
36.00
62.46
2,248.56
11.09
pza
36.00
18.42
663.12
11.10
pza
2.00
2,520.54
5,041.08
23,854.24
12.01
m2
410.59
139.24
57,170.55
12.02
m2
834.08
177.91
148,391.17
13
39,140.88
CERRAJERIA
11.01
12
198,406.80
CARPINTERIA METALICA
10.01
11
206,194.69
CARPINTERIA DE MADERA
205,561.72
VARIOS
13.01
GLB
1.00
616.61
616.61
13.02
m2
99.47
1,992.24
198,168.11
13.03
GLB
1.00
1,066.61
1,066.61
13.04
m2
382.91
22.92
8,776.30
208,627.63
S/. 2,011,209.43
Presupuesto
Subpresupuesto
ARQUITECTURA
Partida
01.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
9.4000
EQ. 9.4000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.7500
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA GRUESA
m3
und
BOL
CAL HIDRATADA DE 30 Kg
BOL
AGUA
m3
p2
Equipos
HERRAMIENTAS MANUALES
Partida
01.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
5.5000
EQ. 5.5000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA GRUESA
m3
und
BOL
CAL HIDRATADA DE 30 Kg
BOL
AGUA
m3
p2
Equipos
HERRAMIENTAS MANUALES
Partida
01.03
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
10.0000
EQ. 10.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1113
OPERARIO
hh
1.1111
PEON
hh
0.5555
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA GRUESA
m3
LADRILLO CORRIENTE 6 x 12 x 24 CM
und
BOL
CAL HIDRATADA DE 30 Kg
BOL
p2
Equipos
HERRAMIENTAS MANUALES
Partida
01.04
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
9.4000
EQ. 9.4000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.7500
Materiales
kg
ARENA GRUESA
m3
und
BOL
CAL HIDRATADA DE 30 Kg
BOL
AGUA
m3
p2
Equipos
HERRAMIENTAS MANUALES
Partida
02.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
15.0000
EQ. 15.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
AGUA
m3
p2
Equipos
HERRAMIENTAS MANUALES
%MO
REGLA DE MADERA
HE
Partida
02.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
0.0469
12.0000
EQ. 12.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
p2
Equipos
HERRAMIENTAS MANUALES
%MO
REGLA DE MADERA
HE
Partida
02.03
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
0.0420
13.0000
EQ. 13.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
1.7000
PEON
hh
0.8500
Materiales
ARENA FINA
m3
BOL
AGUA
m3
Equipos
HERRAMIENTAS MANUALES
%MO
ANDAMIO METALICO
hm
Partida
02.04
Rendimiento
m/DIA
Cdigo
Descripcin Recurso
0.4200
16.0000
EQ. 16.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.3300
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
CAL HIDRATADA DE 30 Kg
BOL
p2
Equipos
HERRAMIENTAS MANUALES
Partida
02.05
Rendimiento
m/DIA
Cdigo
Descripcin Recurso
%MO
14.0000
EQ. 14.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.3300
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
CAL HIDRATADA DE 30 Kg
BOL
p2
Equipos
HERRAMIENTAS MANUALES
Partida
02.06
Rendimiento
m/DIA
Cdigo
Descripcin Recurso
%MO
10.0000
EQ. 10.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.3300
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
CAL HIDRATADA DE 30 Kg
BOL
p2
Equipos
HERRAMIENTAS MANUALES
Partida
02.07
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
8.0000
EQ. 8.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
p2
Equipos
HERRAMIENTAS MANUALES
Partida
03.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
16.0000
EQ. 16.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
2.3994
PEON
hh
1.2001
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
AGUA
m3
Equipos
HERRAMIENTAS MANUALES
%MO
ANDAMIO METALICO
hm
Partida
03.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
1.2000
16.0000
EQ. 16.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
1.0000
PEON
hh
1.2001
Materiales
CLAVOS PARA MADERA C/C 3"
kg
ARENA FINA
m3
BOL
CAL HIDRATADA DE 30 Kg
BOL
AGUA
m3
p2
Equipos
HERRAMIENTAS MANUALES
%MO
ANDAMIO METALICO
hm
Partida
03.03
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
1.2000
20.0000
EQ. 20.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
1.0000
Materiales
und
Equipos
HERRAMIENTAS MANUALES
Partida
04.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
80.0000
EQ. 80.0000
Unidad
Cuadrilla
Mano de Obra
OPERADOR DE EQUIPO LIVIANO
hh
0.5250
CAPATAZ
hh
0.3000
OPERARIO
hh
3.0000
OFICIAL
hh
1.0000
PEON
hh
6.0000
Materiales
ARENA FINA
m3
BOL
AGUA
m3
REGLA DE MADERA
p2
Equipos
HERRAMIENTAS MANUALES
%MO
hm
Partida
04.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
0.5000
6.0000
EQ. 6.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
0.3300
Materiales
ARENA GRUESA
m3
BOL
PORCELANA BLANCA
kg
AGUA
m3
p2
Equipos
HERRAMIENTAS MANUALES
Partida
04.03
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
38.8000
EQ. 38.8000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
2.0000
OFICIAL
hh
2.0000
PEON
hh
2.0000
Materiales
CEMENTO PORTLAND TIPO I (42.5KG)
BOL
MARMOLINA
kg
GLB
Equipos
HERRAMIENTAS MANUALES
Partida
04.04
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
120.0000
EQ. 120.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
4.0000
PEON
hh
5.0000
Materiales
CLAVOS Fo No C/C 3"
kg
BOL
p2
Equipos
CAMION CONCRETERO 6x4 300 HP 6 M3.
Partida
04.05
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
hm
0.0400
7.9000
EQ. 7.9000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
0.1000
PEON
hh
0.5000
Materiales
CUBIERTA DE POLIESTIRENO
m2
m2
Equipos
HERRAMIENTAS MANUALES
Partida
05.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
10.0000
EQ. 10.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.0667
OPERARIO
hh
0.6667
PEON
hh
0.2200
Materiales
ARENA FINA
m3
BOL
PORCELANA
kg
AGUA
m3
Equipos
HERRAMIENTAS MANUALES
%MO
Partida
06.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
18.0000
EQ. 18.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.5000
OFICIAL
hh
0.5000
PEON
hh
1.0000
Materiales
CEMENTO PORTLAND TIPO I (42.5KG)
BOL
MARMOLINA
kg
GLB
Equipos
HERRAMIENTAS MANUALES
Partida
07.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
13.7000
EQ. 13.7000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.8000
PEON
hh
0.8000
Materiales
ARENA FINA
m3
m3
und
BOL
kg
AGUA
m3
Equipos
HERRAMIENTAS MANUALES
%MO
Partida
08.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
20.0000
EQ. 20.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
1.0000
Materiales
ANDAMIO DE MADERA
p2
IMPRIMANTE
gln
gln
Equipos
HERRAMIENTAS MANUALES
Partida
08.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
30.0000
EQ. 30.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
1.0000
Materiales
ANDAMIO DE MADERA
p2
IMPRIMANTE
gln
gln
Equipos
HERRAMIENTAS MANUALES
Partida
08.03
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
30.0000
EQ. 30.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
1.0000
Materiales
ANDAMIO DE MADERA
p2
IMPRIMANTE
gln
gln
Equipos
HERRAMIENTAS MANUALES
Partida
09.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
2.0000
EQ. 2.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
OFICIAL
hh
1.0000
Materiales
CLAVOS PARA MADERA C/C 1"
kg
kg
gln
und
p2
Equipos
HERRAMIENTAS MANUALES
%MO
SIERRA CIRCULAR
hm
0.2000
CEPILLADORA ELECTRICA
hm
0.2000
Partida
09.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
2.1600
EQ. 2.1600
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
Materiales
1.0000
kg
gln
p2
pln
Equipos
HERRAMIENTAS MANUALES
Partida
09.03
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
12.0000
EQ. 12.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
0.1001
Materiales
BISAGRA CAPUCHINA PLOMA 3 1/2" X 3 1/2"
PAR
Equipos
HERRAMIENTAS MANUALES
Partida
09.04
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
0.9000
EQ. 0.9000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.1125
OFICIAL
hh
0.1125
Materiales
MUEBLE ALTO P/COCINA MELAMINA
m2
Equipos
HERRAMIENTAS MANUALES
%MO
Partida
09.05
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
0.9000
EQ. 0.9000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
1.0000
OFICIAL
hh
0.1125
Materiales
MUEBLE BAJO P/COCINA MELAMINA
m2
Equipos
HERRAMIENTAS MANUALES
Partida
09.06
Rendimiento
m/DIA
Cdigo
Descripcin Recurso
%MO
20.0000
EQ. 20.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
2.5000
PEON
hh
3.7500
Materiales
CLAVOS PARA MADERA C/C 2"
kg
kg
gln
p2
Equipos
HERRAMIENTAS MANUALES
Partida
10.01
Rendimiento
m/DIA
Cdigo
Descripcin Recurso
%MO
8.0000
EQ. 8.0000
Unidad
Mano de Obra
Cuadrilla
hh
0.7000
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
CEMENTO PORTLAND TIPO I (EN FCA.)S-PUB
BOL
kg
kg
PLOMO ELECTROLITICO
kg
Equipos
HERRAMIENTAS MANUALES
%MO
WINCHE MANUAL
hm
0.0500
hm
0.1000
hm
0.5000
Partida
10.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
1.2000
EQ. 1.2000
Unidad
Cuadrilla
Mano de Obra
OPERADOR DE EQUIPO PESADO
hh
0.5200
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
SOLDADURA CELLOCORD P 3/16"
kg
pza
pza
pza
pln
Equipos
HERRAMIENTAS MANUALES
%MO
und
hm
0.5000
Partida
10.03
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
0.5000
EQ. 0.5000
Unidad
Cuadrilla
Mano de Obra
OPERADOR DE EQUIPO PESADO
hh
0.5200
OPERARIO
hh
1.0000
PEON
hh
0.5000
Materiales
SOLDADURA CELLOCORD P 3/16"
kg
pza
pza
pza
pln
Equipos
HERRAMIENTAS MANUALES
%MO
und
hm
Partida
11.01
Rendimiento
und/DIA
Cdigo
Descripcin Recurso
0.5000
1.0000
EQ. 1.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.1250
Materiales
CERRADURA EXTERIOR DE DOS GOLPES
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.02
Rendimiento
pza/DIA
%MO
4.0000
EQ. 4.0000
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
CERRADURA INTERIOR
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.03
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
4.0000
EQ. 4.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
CERRADURA INTERIOR
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.04
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
4.0000
EQ. 4.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
CERRADURA INTERIOR
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.05
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
4.0000
EQ. 4.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
CERRADURA INTERIOR
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.06
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
4.0000
EQ. 4.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
CERRADURA INTERIOR
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.07
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
4.0000
EQ. 4.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
TRANSFORMADOR PARA CHAPA ELCTRICA
pza
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.08
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
12.0000
EQ. 12.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
Materiales
BISAGRA VAIVEN BATIENTE 2 1/2" x 2 1/2"
und
Equipos
HERRAMIENTAS MANUALES
Partida
11.09
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
%MO
12.0000
EQ. 12.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
Materiales
PICAPORTE DE ALUMINIO DE 6"
pza
Equipos
HERRAMIENTAS MANUALES
%MO
0.8000
Partida
11.10
Rendimiento
pza/DIA
Cdigo
Descripcin Recurso
0.5000
EQ. 0.5000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.0313
PEON
hh
0.0625
Materiales
SISTEMA LEVADIZO A CONTROL REMOTO
und
Equipos
HERRAMIENTAS MANUALES
Partida
12.01
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
25.0000
EQ. 25.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
1.0000
PEON
hh
1.5000
Materiales
VENTANA CON MARCO DE ALUMINIO (CONFORME PLANOS) m2
VIDRIO TRANSPAR.INCOLOR TRIPLE
p2
Equipos
HERRAMIENTAS MANUALES
Partida
12.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
15.0000
EQ. 15.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.0400
OPERARIO
hh
0.4000
PEON
hh
0.6000
Materiales
VENTANA CON MARCO DE ALUMINIO (CONFORME PLANOS) m2
MAMPARAS DE ALUMINIO (INCLUYE VIDRIOS) Y CHAPAS
m2
Equipos
HERRAMIENTAS MANUALES
Partida
13.01
Rendimiento
GLB/DIA
Cdigo
Descripcin Recurso
%MO
1.0000
EQ. 1.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.1000
PEON
hh
1.0000
Materiales
LIMPIEZA PERMANENTE DE OBRA
GLB
Equipos
HERRAMIENTAS MANUALES
Partida
13.02
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
20.0000
EQ. 20.0000
Unidad
Cuadrilla
Mano de Obra
CAPATAZ
hh
0.1000
OPERARIO
hh
0.2250
Materiales
TABLERO DE GRANITO E=1"
Equipos
m2
HERRAMIENTAS MANUALES
Partida
13.03
Rendimiento
GLB/DIA
Cdigo
Descripcin Recurso
%MO
1.0000
EQ. 1.0000
Unidad
Cuadrilla
Mano de Obra
OPERARIO
hh
0.1000
PEON
hh
1.0000
Materiales
LIMPIEZA FINAL DE OBRA
GLB
Equipos
HERRAMIENTAS MANUALES
Partida
13.04
Rendimiento
m2/DIA
Cdigo
Descripcin Recurso
%MO
50.0000
EQ. 50.0000
Unidad
Cuadrilla
Mano de Obra
PEON
hh
4.0000
Materiales
TIERRA DE CHACRA O VEGETAL
m3
Equipos
HERRAMIENTAS MANUALES
%MO
MOTONIVELADORA DE 125 HP
hm
1.0000
tectura
Fecha presupuesto
6/4/2011
57.02
Cantidad
Precio S/.
Parcial S/.
0.0851
19.07
1.62
0.8511
15.63
13.30
0.6383
12.32
7.86
22.79
0.0200
4.66
0.09
0.0300
38.14
1.14
44.0000
0.61
26.84
0.2278
14.12
3.22
0.1300
4.00
0.52
0.0070
1.83
0.01
0.5800
3.00
1.74
33.57
3.0000
22.78
0.68
0.68
95.37
Cantidad
Precio S/.
Parcial S/.
0.1455
19.07
2.77
1.4545
15.63
22.73
0.7273
12.32
8.96
34.47
0.0025
4.66
0.01
0.0680
38.14
2.59
79.0000
0.61
48.19
0.4820
14.12
6.81
0.1300
4.00
0.52
0.0100
1.83
0.02
0.5800
3.00
1.74
59.88
3.0000
34.46
1.03
1.03
42.57
Cantidad
Precio S/.
Parcial S/.
0.0890
19.07
1.70
0.8889
15.63
13.89
0.4444
12.32
5.48
21.07
0.0025
4.66
0.01
0.0118
38.14
0.45
32.0000
0.61
19.52
0.0400
14.12
0.56
0.0520
4.00
0.21
0.0400
3.00
0.12
20.87
3.0000
21.07
0.63
0.63
56.91
Cantidad
Precio S/.
Parcial S/.
0.0851
19.07
1.62
0.8511
15.63
13.30
0.6383
12.32
7.86
22.79
0.0200
4.66
0.09
0.0300
38.14
1.14
44.0000
0.61
26.84
0.2200
14.12
3.11
0.1300
4.00
0.52
0.0070
1.83
0.01
0.5800
3.00
1.74
33.46
3.0000
22.78
0.68
0.68
17.39
Cantidad
Precio S/.
Parcial S/.
0.0533
19.07
1.02
0.5333
15.63
8.34
0.2667
12.32
3.29
12.64
0.0200
4.66
0.09
0.0200
38.14
0.76
0.1200
14.12
1.69
0.0050
1.83
0.01
0.5800
3.00
1.74
4.30
3.0000
12.65
0.38
0.0250
2.80
0.07
0.45
21.34
Cantidad
Precio S/.
Parcial S/.
0.0667
19.07
1.27
0.6667
15.63
10.42
0.3333
12.32
4.11
15.80
0.0220
4.66
0.10
0.0180
38.14
0.69
0.1170
14.12
1.65
0.8500
3.00
2.55
4.99
3.0000
15.80
0.47
0.0280
2.80
0.08
0.55
26.13
Cantidad
Precio S/.
Parcial S/.
1.0462
15.63
16.35
0.5231
12.32
6.44
22.80
0.0160
38.14
0.61
0.1170
14.12
1.65
0.0040
1.83
0.01
2.27
3.0000
22.79
0.68
0.2585
1.50
0.39
1.07
12.06
Cantidad
Precio S/.
Parcial S/.
0.0500
19.07
0.95
0.5000
15.63
7.82
0.1650
12.32
2.03
10.80
0.0100
4.66
0.05
0.0040
38.14
0.15
0.0150
14.12
0.21
0.0200
4.00
0.08
0.1500
3.00
0.45
0.94
3.0000
10.80
0.32
0.32
13.65
Cantidad
Precio S/.
Parcial S/.
0.0571
19.07
1.09
0.5714
15.63
8.93
0.1886
12.32
2.32
12.34
0.0100
4.66
0.05
0.0040
38.14
0.15
0.0150
14.12
0.21
0.0200
4.00
0.08
0.1500
3.00
0.45
0.94
3.0000
12.34
0.37
0.37
18.74
Cantidad
Precio S/.
Parcial S/.
0.0800
19.07
1.53
0.8000
15.63
12.50
0.2640
12.32
3.25
17.28
0.0100
4.66
0.05
0.0040
38.14
0.15
0.0150
14.12
0.21
0.0200
4.00
0.08
0.1500
3.00
0.45
0.94
3.0000
17.28
0.52
0.52
27.49
Cantidad
Precio S/.
Parcial S/.
0.1000
19.07
1.91
1.0000
15.63
15.63
0.5000
12.32
6.16
23.70
0.0100
4.66
0.05
0.0180
38.14
0.69
0.1000
14.12
1.41
0.3100
3.00
0.93
3.08
3.0000
23.70
0.71
0.71
30.13
Cantidad
Precio S/.
Parcial S/.
1.1997
15.63
18.75
0.6001
12.32
7.39
26.14
0.0090
4.66
0.04
0.0160
38.14
0.61
0.1170
14.12
1.65
0.0040
1.83
0.01
2.31
3.0000
26.14
0.78
0.6000
1.50
0.90
1.68
20.28
Cantidad
Precio S/.
Parcial S/.
0.5000
15.63
7.82
0.6001
12.32
7.39
15.21
0.0300
4.66
0.14
0.0150
38.14
0.57
0.0550
14.12
0.78
0.0730
4.00
0.29
0.0040
1.83
0.01
0.6400
3.00
1.92
3.71
3.0000
15.21
0.46
0.6000
1.50
0.90
1.36
29.80
Cantidad
Precio S/.
Parcial S/.
0.0400
19.07
0.76
0.4000
15.63
6.25
0.4000
12.32
4.93
11.94
0.5000
35.00
17.50
17.50
3.0000
11.94
0.36
0.36
25.46
Cantidad
Precio S/.
Parcial S/.
0.0525
15.63
0.82
0.0300
19.07
0.57
0.3000
15.63
4.69
0.1000
13.52
1.35
0.6000
12.32
7.39
14.83
0.0510
38.14
1.95
0.4550
14.12
6.42
0.0820
1.83
0.15
0.0525
1.81
0.10
8.61
3.0000
14.82
0.44
0.0500
31.50
1.58
2.02
66.59
Cantidad
Precio S/.
Parcial S/.
0.1333
19.07
2.54
1.3333
15.63
20.84
0.4400
12.32
5.42
28.80
0.0300
38.14
1.14
0.2680
14.12
3.78
1.0500
10.00
10.50
0.0400
1.83
0.07
1.0500
20.31
21.33
0.0600
1.81
0.11
36.94
3.0000
28.80
0.86
0.86
70.86
Cantidad
Precio S/.
Parcial S/.
0.4124
15.63
6.45
0.4124
13.52
5.58
0.4124
12.32
5.08
17.10
2.0000
14.12
28.24
0.8000
25.00
20.00
0.2000
25.00
5.00
53.24
3.0000
17.11
0.51
0.51
13.47
Cantidad
Precio S/.
Parcial S/.
0.2667
15.63
4.17
0.3333
12.32
4.11
8.27
0.0120
4.66
0.06
0.2000
14.12
2.82
0.7000
3.00
2.10
4.98
0.0027
78.79
0.21
0.21
38.33
Cantidad
Precio S/.
Parcial S/.
0.1013
19.07
1.93
0.1013
15.63
1.58
0.5063
12.32
6.24
9.75
1.0200
3.00
4.02
1.0200
24.74
25.76
29.78
3.0000
9.75
0.29
0.29
18.90
Cantidad
Precio S/.
Parcial S/.
0.0534
19.07
1.02
0.5334
15.63
8.34
0.1760
12.32
2.17
11.52
0.0210
38.14
0.80
0.1870
14.12
2.64
0.1950
10.00
1.95
0.0040
1.83
0.01
0.0800
20.31
1.62
7.02
3.0000
11.53
0.35
0.35
54.13
Cantidad
Precio S/.
Parcial S/.
0.2222
15.63
3.47
0.2222
13.52
3.00
0.4444
12.32
5.48
11.95
1.2000
14.12
16.94
0.8000
25.00
20.00
0.2000
25.00
5.00
41.94
2.0000
11.95
0.24
0.24
31.26
Cantidad
Precio S/.
Parcial S/.
0.4672
15.63
7.30
0.4672
12.32
5.76
13.06
0.0040
38.14
0.15
0.0420
10.00
0.42
17.0000
0.79
13.43
0.1120
15.00
1.68
4.7600
0.50
2.38
0.0040
1.83
0.01
18.07
1.0000
13.06
0.13
0.13
14.17
Cantidad
Precio S/.
Parcial S/.
0.4000
15.63
6.25
6.25
1.0000
5.00
5.00
0.1300
15.00
1.95
0.0400
21.00
0.84
7.79
2.0000
6.25
0.13
0.13
12.04
Cantidad
Precio S/.
Parcial S/.
0.2667
15.63
4.17
4.17
1.0000
5.00
5.00
0.1300
15.00
1.95
0.0400
21.00
0.84
7.79
2.0000
4.17
0.08
0.08
12.04
Cantidad
Precio S/.
Parcial S/.
0.2667
15.63
4.17
4.17
1.0000
5.00
5.00
0.1300
15.00
1.95
0.0400
21.00
0.84
7.79
2.0000
4.17
0.08
0.08
224.76
Cantidad
Precio S/.
Parcial S/.
0.4000
19.07
7.63
4.0000
15.63
62.52
4.0000
13.52
54.08
124.23
0.0750
4.00
0.30
0.0380
4.50
0.17
0.1200
10.00
1.20
1.1000
1.50
1.65
15.0000
5.00
75.00
78.32
5.0000
124.23
6.21
0.8000
10.00
8.00
0.8000
10.00
8.00
22.21
133.84
Cantidad
Precio S/.
Parcial S/.
3.7037
15.63
57.89
57.89
0.1320
4.50
0.59
0.2640
10.00
2.64
13.0100
3.50
45.54
1.0600
24.00
25.44
74.21
3.0000
57.89
1.74
1.74
3.58
Cantidad
Precio S/.
Parcial S/.
0.0667
19.07
1.27
0.0667
15.63
1.04
2.31
1.0000
1.20
1.20
1.20
3.0000
2.31
0.07
0.07
235.02
Cantidad
Precio S/.
Parcial S/.
1.0000
15.63
15.63
1.0000
13.52
13.52
29.15
1.0000
205.00
205.00
205.00
3.0000
29.15
0.87
0.87
907.02
Cantidad
Precio S/.
Parcial S/.
8.8889
15.63
138.93
1.0000
13.52
13.52
152.45
1.0000
750.00
750.00
750.00
3.0000
152.45
4.57
4.57
67.43
Cantidad
Precio S/.
Parcial S/.
1.0000
15.63
15.63
1.5000
12.32
18.48
34.11
0.0600
4.50
0.27
0.0700
4.66
0.33
0.1700
10.00
1.70
3.0000
10.00
30.00
32.30
3.0000
34.11
1.02
1.02
Cantidad
82.20
Precio S/.
Parcial S/.
0.7000
15.00
10.50
1.0000
15.63
15.63
0.5000
12.32
6.16
32.29
0.0500
15.00
0.75
0.0500
20.00
1.00
2.1250
0.50
1.06
0.0500
10.00
0.50
0.1000
15.00
1.50
1.0000
15.00
15.00
1.0500
15.00
15.75
35.56
2.0000
32.29
0.65
0.0500
100.00
5.00
0.1000
12.00
1.20
0.5000
15.00
7.50
14.35
721.65
Cantidad
Precio S/.
Parcial S/.
3.4667
15.00
52.00
6.6667
15.63
104.20
3.3333
12.32
41.07
197.27
0.6000
20.00
12.00
0.9300
15.00
13.95
0.2500
15.00
3.75
0.1000
10.00
1.00
0.3820
104.00
39.73
70.43
2.0000
197.27
3.95
8.0000
50.00
400.00
3.3333
15.00
50.00
453.94
1,073.34
Cantidad
Precio S/.
Parcial S/.
8.3200
15.00
124.80
16.0000
15.63
250.08
8.0000
12.32
98.56
473.44
0.6000
20.00
12.00
0.9300
15.00
13.95
0.2500
15.00
3.75
0.1000
10.00
1.00
0.3820
104.00
39.73
70.43
2.0000
473.44
946.88
8.0000
50.00
400.00
8.0000
15.00
120.00
1,466.88
46.10
Cantidad
Precio S/.
Parcial S/.
1.0000
15.63
15.63
15.63
1.0000
30.00
30.00
30.00
3.0000
15.63
0.47
0.47
56.29
Cantidad
Precio S/.
Parcial S/.
0.2000
19.07
3.81
2.0000
15.63
31.26
35.07
1.0000
20.17
20.17
20.17
3.0000
35.07
1.05
1.05
56.29
Cantidad
Precio S/.
Parcial S/.
0.2000
19.07
3.81
2.0000
15.63
31.26
35.07
1.0000
20.17
20.17
20.17
3.0000
35.07
1.05
1.05
56.29
Cantidad
Precio S/.
Parcial S/.
0.2000
19.07
3.81
2.0000
15.63
31.26
35.07
1.0000
20.17
20.17
20.17
3.0000
35.07
1.05
1.05
56.29
Cantidad
Precio S/.
Parcial S/.
0.2000
19.07
3.81
2.0000
15.63
31.26
35.07
1.0000
20.17
20.17
20.17
3.0000
35.07
1.05
1.05
56.29
Cantidad
Precio S/.
Parcial S/.
0.2000
19.07
3.81
2.0000
15.63
31.26
35.07
1.0000
20.17
20.17
20.17
3.0000
35.07
1.05
1.05
Cantidad
133.29
Precio S/.
Parcial S/.
0.2000
19.07
3.81
2.0000
15.63
31.26
35.07
1.0000
15.00
15.00
1.0000
82.17
82.17
97.17
3.0000
35.07
1.05
1.05
62.46
Cantidad
Precio S/.
Parcial S/.
0.0667
19.07
1.27
0.6667
15.63
10.42
11.69
1.0000
50.42
50.42
50.42
3.0000
11.69
0.35
0.35
18.42
Cantidad
Precio S/.
Parcial S/.
0.5333
15.63
8.34
8.34
1.0000
10.00
10.00
10.00
1.0000
8.34
0.08
0.08
UIPO E INSTALACION
2,520.54
Cantidad
Precio S/.
Parcial S/.
0.5000
15.63
7.82
1.0000
12.32
12.32
20.14
1.0000
2,500.00
2,500.00
2,500.00
2.0000
20.14
0.40
0.40
139.24
Cantidad
Precio S/.
Parcial S/.
0.0320
19.07
0.61
0.3200
15.63
5.00
0.4800
12.32
5.91
11.53
1.0000
40.00
40.00
10.7600
8.12
87.37
127.37
3.0000
11.52
0.35
0.35
Cantidad
177.91
Precio S/.
Parcial S/.
0.0213
19.07
0.41
0.2133
15.63
3.33
0.3200
12.32
3.94
7.68
1.0000
40.00
40.00
1.0000
130.00
130.00
170.00
3.0000
7.68
0.23
0.23
616.61
Cantidad
Precio S/.
Parcial S/.
0.8000
15.63
12.50
8.0000
12.32
98.56
111.06
1.0000
500.00
500.00
500.00
5.0000
111.06
5.55
5.55
1,992.24
Cantidad
Precio S/.
Parcial S/.
0.0400
19.07
0.76
0.0900
15.63
1.41
2.17
99.5000
20.00
1,990.00
1,990.00
3.0000
2.17
0.07
0.07
1,066.61
Cantidad
Precio S/.
Parcial S/.
0.8000
15.63
12.50
8.0000
12.32
98.56
111.06
1.0000
950.00
950.00
950.00
5.0000
111.06
5.55
5.55
22.92
Cantidad
Precio S/.
Parcial S/.
0.6400
12.32
7.88
7.88
1.0000
10.00
10.00
10.00
3.0000
7.88
0.24
0.1600
30.00
4.80
5.04
PRESUPUESTO - ESTRUCTURAS
TIEMPO:
180 DAS
Item
01
01.01
01.02
Descripcin
glb
1.00
80,640.00
80,640.00
mes
4.00
250.00
1,000.00
glb
1.00
900.00
900.00
glb
1.00
1,200.00
1,200.00
glb
1.00
225.50
225.50
mes
4.00
11,100.00
44,400.00
Total
glb
1.00
8,220.80
8,220.80
128,365.50
OBRAS PRELIMINARES
Movilizacin y desmovilizacin
glb
1.00
2,400.00
2,400.00
m2
2,804.60
2.30
6,452.03
glb
1.00
13,721.56
13,721.56
mes
4.00
7,968.31
31,873.24
62,667.63
glb
1.00
35,041.35
35,041.35
35,041.35
m3
452.91
39.08
17,698.29
m3
593.82
9.73
5,776.94
m2
1,382.68
3.30
4,555.96
m3
206.44
24.00
4,954.56
Conformacin de base
m3
515.69
15.31
7,895.95
m2
868.25
43.02
37,355.24
01.03
01.03
03.02
P.Parcial
Limpieza permanente
OBRAS PRELIMINARES
03.01
P.Unitario
OBRAS PROVISIONALES
03
Metrado
02
Unid
MOVIMIENTO DE TIERRAS
78,236.95
ESTRUCTURAS
CONCRETO SIMPLE
Concreto 210 kg/cm2 - Cimiento
m3
80.01
246.54
19,725.70
m2
468.85
50.46
23,658.06
m3
165.92
450.82
74,800.61
m3
82.06
107.95
8,858.71
m3
26.20
190.85
5,000.37
m2
21.20
38.85
823.70
m2
657.07
20.91
13,738.57
146,605.72
CONCRETO ARMADO
ZAPATA
Concreto 210 kg/cm2 - Zapata
m3
99.20
244.28
24,233.02
m2
187.96
56.51
10,621.70
kg
4,720.88
3.89
18,358.27
22,650.43
53,212.98
MUROS DE CONCRETO
Concreto 210 kg/cm2 - Muros de Concreto
m3
52.18
434.08
m2
341.99
27.13
9,278.55
kg
3,635.23
4.36
15,841.09
Curado
m2
341.99
1.30
443.27
48,213.34
COLUMNAS
Concreto 210 kg/cm2 - Columnas
m3
75.56
290.18
21,926.07
m2
809.17
42.06
34,032.33
kg
14,156.56
3.84
54,346.17
Curado
m2
809.17
1.30
1,048.81
m3
40.40
274.47
11,088.47
m2
347.80
38.20
13,285.93
kg
4,400.88
4.20
18,479.03
Curado
m2
347.80
1.30
450.80
111,353.38
PLACAS
43,304.23
VIGAS
Concreto 175 kg/cm2 - Vigas
m3
164.16
283.50
46,540.07
m2
1,039.33
53.07
55,153.51
kg
24,540.03
3.84
94,207.67
Curado
m2
1,039.33
1.30
1,347.13
m3
227.97
279.05
63,614.18
m2
1,970.67
41.30
81,379.06
kg
16,827.85
3.84
64,601.08
1,464.00
2.13
3,112.25
13,643.00
2.50
34,113.79
m2
1,970.67
1.30
2,554.29
197,248.37
LOSAS ALIGERADAS
Curado
249,374.65
LOSA MACIZA
Concreto 210 kg/cm2 - Losa Maciza
m3
28.80
275.92
7,946.62
m2
146.02
36.80
5,373.54
kg
2,191.92
3.84
8,414.65
Curado
m2
146.02
1.74
253.51
m3
11.24
273.15
3,070.24
m2
69.79
77.58
5,414.20
kg
722.53
3.84
2,773.75
Curado
m2
69.79
1.74
121.17
21,988.32
ESCALERAS
11,379.36
CISTERNA
Concreto 245 kh/cm2 - Cisterna
m3
45.14
333.39
15,049.22
m2
295.31
51.78
15,290.62
kg
3,467.22
3.84
13,310.45
43,650.29
S/.
1,230,642.06
PARTIDA:
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Subcontratos
Unidad
PARTIDA:
Cuadrilla
Cantidad
m2
80.0000
80,640.00
Precio S/.
1,008.00
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Subcontratos
ALQUILER DE BAO PORTTIL
PARTIDA:
Unidad
Cuadrilla
Cantidad
mes
1.0000
250.00
Precio S/.
250.00
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
900.00
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
Precio S/.
Subcontratos
INST. PROV. DE AGUA EN CAMPAMENTO
PARTIDA:
glb
1.0000
900.00
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
1,200.00
Precio S/.
Subcontratos
INST. PROV. DE LUZ EN CAMPAMENTO
PARTIDA:
glb
1.0000
1,200.00
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
225.50
Precio S/.
Subcontratos
INST. PROV DE TELEFONO Y FAX
PARTIDA:
glb
1.0000
225.50
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
Cuadrilla
Cantidad
Precio S/.
hh
POLICIA
mes
2.0000
1,800.00
SEGURIDAD - PROTEPERSA
mes
3.0000
2,500.00
%MO
0.0000
11,100.00
Materiales
Equipos
HERRAMIENTAS MANUALES
Unidad
11,100.00
Subcontratos
PARTIDA:
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
8,220.80
Precio S/.
Subcontratos
LIMPIEZA DE MATERIAL SOBRE EL TERRENO
m2
2,936.0000
2.80
PARTIDA:
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
2,400.00
Precio S/.
Subcontratos
MOVILIZACIN Y DESMOVILIZACIN
PARTIDA:
viajes
8.0000
300.00
MO :
300.00
EQ :
HH :
0.1093
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Cantidad
Precio S/.
Mano de Obra
hh
0.10
0.0027
19.07
OPERARIO (TOPOGRAFO)
hh
1.00
0.0267
15.63
OFICIAL
hh
PEON
hh
3.00
0.0800
13.52
12.32
Materiales
CLAVO P/ MADERA
kg
0.0050
2.52
YESO
bls
0.0250
12.00
MADERA TORNILLO
p2
0.0264
3.50
PINTURA ESMALTE
gln
0.0020
32.00
Equipos
HERRAMIENTAS MANUALES
PARTIDA:
Cuadrilla
CAPATAZ
Unidad
2.30
3.0000
1.45
TEODOLITO
%MO
hm
1.00
0.0267
8.80
NIVEL
hm
1.00
0.0267
3.75
Subcontratos
RENDIMIENTO
MO :
0.00
EQ :
HH :
619.2000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO (TOPGRAFO)
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
13,721.56
Precio S/.
19.07
1.00
206.4000
15.63
2.00
412.8000
12.32
13.52
Materiales
CLAVO P/ MADERA
kg
0.0050
3.20
YESO
bls
0.0250
12.00
MADERA TORNILLO
p2
0.0264
3.50
PINTURA ESMALTE
gln
0.0020
35.00
%MO
3.0000
8,311.73
Equipos
HERRAMIENTAS MANUALES
TEODOLITO
hm
1.00
206.4000
15.00
NIVEL
hm
1.00
206.4000
10.00
3.0000
HM :
Subcontratos
PARTIDA:
MO :
HH :
EQ :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Cantidad
Precio S/.
Mano de Obra
hh
19.07
OPERARIO
hh
15.63
hh
PEON
Cuadrilla
CAPATAZ
OFICIAL
Unidad
7,968.31
13.52
mes
3.0000
2,562.56
HERRAMIENTAS MANUALES
%MO
3.0000
7,687.68
MATERIALES DE LIMPIEZA
mes
1.0000
50.00
Materiales
Equipos
Subcontratos
PARTIDA:
MO :
0.00
EQ :
HH :
3.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
CAPATAZ
Cuadrilla
Cantidad
hh
OPERARIO
Precio S/.
19.07
hh
15.63
OFICIAL
mes
1.0000
2,812.16
PEON
mes
2.0000
2,562.56
HERRAMIENTAS MANUALES
%MO
3.0000
7,937.28
MONTACARGA DP 35
MES
1.0000
1,911.36
MES
1.0000
520.00
Materiales
Unidad
10,606.76
Equipos
Subcontratos
PARTIDA:
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
35,041.35
Precio S/.
Subcontratos
IMPLEMENTOS DE SEGURIDAD (CAPECO)
PARTIDA:
%CD
1.5000
2,336,089.99
MO :
3.00
EQ :
HH :
2.9333
HM :
COSTO DIRECTO :
39.08
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.2667
Precio S/.
19.07
15.63
13.52
1.00
2.6667
12.32
3.0000
37.94
Materiales
Equipos
HERRAMIENTAS MANUALES
%MO
Subcontratos
PARTIDA:
MO :
300.00
EQ :
HH :
0.0853
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
9.73
Precio S/.
CAPATAZ
hh
0.20
0.0053
19.07
OPERARIO
hh
1.00
0.0267
15.63
OFICIAL
hh
PEON
hh
2.00
0.0533
12.32
3.0000
1.18
13.52
Materiales
Equipos
HERRAMIENTAS MANUALES
%MO
hm
1.00
0.0267
133.20
hm
1.00
0.0267
186.21
MO :
700.00
EQ :
HH :
0.0183
HM :
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
3.30
Precio S/.
Mano de Obra
CAPATAZ
hh
OPERARIO
hh
0.10
0.0011
19.07
15.63
OFICIAL
hh
1.00
0.0114
13.52
PEON
hh
0.50
0.0057
12.32
Materiales
Equipos
HERRAMIENTAS MANUALES
3.0000
0.25
MOTONIVELADORA 125 HP
hm
1.00
0.0114
120.00
hm
1.00
0.0114
146.08
PARTIDA:
%MO
MO :
7.00
EQ :
HH :
1.2571
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.1143
24.00
Precio S/.
19.07
15.63
13.52
1.00
1.1429
12.32
3.0000
16.26
Materiales
Equipos
HERRAMIENTAS MANUALES
%MO
Subcontratos
SUBC. RELLENO DE MATERIAL PROPIO
PARTIDA:
m3
18.00
MO :
600.00
EQ :
HH :
0.0947
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
PEON
Cuadrilla
Cantidad
15.31
Precio S/.
0.10
0.0013
19.07
hh
1.00
0.0133
13.52
hh
6.00
0.0800
12.32
0.1800
35.00
15.63
Materiales
MATERIAL GRANULAR
m3
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
1.19
MOTONIVELADORA 125HP
hm
1.00
0.0133
120.00
hm
1.00
0.0133
146.08
TRACTOR ORUGA
hm
1.00
0.0133
188.79
hm
1.00
0.0133
128.96
MO :
300.00
EQ :
HH :
0.2933
HM :
Subcontratos
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
PEON
Cuadrilla
Cantidad
43.02
Precio S/.
1.00
0.0267
19.07
hh
2.00
0.0533
13.52
hh
8.00
0.2133
12.32
m3
0.0650
250.00
%MO
3.0000
3.86
15.63
Materiales
ASFALTO LQUIDO
Equipos
HERRAMIENTAS MANUALES
CARGADOR FRONTAL CAT
hm
1.00
0.0267
150.00
VOLQUETE 10M3
hm
1.00
0.0267
145.00
PLANTA DE ASFALTO
hm
1.00
0.0267
475.00
RODILLO PAVIMENTADOR
hm
1.00
0.0267
85.00
25.00
3.5520
EQ :
HM :
Subcontratos
PARTIDA:
RENDIMIENTO (m3/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
246.54
Precio S/.
CAPATAZ
hh
0.10
0.0320
19.07
OPERARIO
hh
1.00
0.3200
15.63
OFICIAL
hh
2.00
0.6400
13.52
PEON
hh
8.00
2.5600
12.32
Materiales
CEMENTO PORTLAND TIPO I
bls
9.7300
15.55
m3
0.5300
41.62
ARENA GRUESA
m3
0.5200
37.82
Equipos
HERRAMIENTAS MANUALES
3.0000
45.80
MEZCLADORA 9-11p3
hm
1.00
0.3200
14.50
VIBRADOR DE CONCRETO
hm
1.00
0.3200
5.30
13.00
1.2923
EQ :
HM :
%MO
Subcontratos
PARTIDA:
RENDIMIENTO (m2/da)
COSTO DIRECTO :
50.46
ENCOFRADO
Cdigo
1
Descripcin Recurso
Mano de Obra
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
Cuadrilla
Cantidad
0.10
1.00
1.00
Precio S/.
0.0615
0.6154
0.6154
19.07
15.63
13.52
12.32
p2
Kg
Kg
4.8200
0.1400
0.1800
3.50
2.92
2.92
%MO
3.0000
19.11
m2
m2
1.0000
1.0000
6.07
6.90
EQ :
HM :
Materiales
MADERA TORNILLO
CLAVOS
ALAMBRE NEGRO
Unidad
Equipos
HERRAMIENTAS MANUALES
Subpartidas
HABILITACIN
DESENCOFRADO
PARTIDA:
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
Materiales
CONCRETO PREMEZCLADO f'c 175kg/cm2 - YURA
Equipos
HERRAMIENTAS MANUALES
BOMBA DE CONCRETO
VIBRADOR DE CONCRETO
Subcontratos
Cuadrilla
Cantidad
450.82
Precio S/.
0.20
5.00
0.1067
2.6667
4.00
2.1333
19.07
15.63
13.52
12.32
m3
1.0500
340.00
%MO
m3
hm
3.0000
0.6300
0.5333
70.00
30.00
5.30
1.00
PARTIDA:
EQ :
HM :
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
0.10
1.00
2.00
8.00
Materiales
CEMENTO PORTLAND TIPO I
PIEDRA MEDIANA
ARENA GRUESA
HORMIGN
bls
m3
m3
m3
3.70
0.42
0.42
0.85
Equipos
HERRAMIENTAS MANUALES
MEZCLADORA 9-11p3
%MO
hm
1.00
0.0667
0.6667
1.3333
5.3333
107.95
Precio S/.
19.07
15.63
13.52
12.32
16.00
35.00
30.00
28.00
3.0000
0.6667
95.42
14.50
30.00
0.8267
EQ :
HM :
Subcontratos
PARTIDA:
RENDIMIENTO (m3/da)
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
Materiales
CEMENTO PORTLAND TIPO I
PIEDRA CHANCADA 1/2"
ARENA GRUESA
bls
m3
m3
Equipos
HERRAMIENTAS MANUALES
MEZCLADORA 9-11p3
VIBRADOR DE CONCRETO
%MO
hm
hm
Cuadrilla
Cantidad
190.85
Precio S/.
0.10
2.00
0.0267
0.5333
1.00
0.2667
19.07
15.63
13.52
12.32
8.4300
0.5500
0.5400
16.00
40.00
30.00
3.0000
0.2667
0.2667
12.13
14.50
5.30
15.00
1.1200
EQ :
HM :
1.00
1.00
Subcontratos
PARTIDA:
RENDIMIENTO (m2/da)
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
38.85
Precio S/.
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
0.0533
0.5333
0.5333
19.07
15.63
13.52
12.32
p2
Kg
Kg
2.5000
0.0100
0.0150
3.50
2.92
2.92
%MO
3.0000
16.56
m2
m2
1.0000
1.0000
6.07
6.90
80.00
0.9200
EQ :
HM :
Materiales
MADERA TORNILLO
CLAVOS
ALAMBRE NEGRO
0.10
1.00
1.00
Equipos
HERRAMIENTAS MANUALES
Subcontratos
HABILITACIN
DESENCOFRADO
PARTIDA:
RENDIMIENTO (m2/da)
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
Materiales
CEMENTO PORTLAND TIPO I
HORMIGN
bls
m3
Equipos
HERRAMIENTAS MANUALES
MEZCLADORA 9-11p3
%MO
hm
Cuadrilla
Cantidad
0.20
2.00
1.00
6.00
1.00
20.91
Precio S/.
0.0200
0.2000
0.1000
0.6000
19.07
15.63
13.52
12.32
0.2700
0.0900
16.00
28.00
3.0000
0.1000
12.25
14.50
26.00
3.7538
EQ :
HM :
Subcontratos
PARTIDA:
RENDIMIENTO (m3/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.20
0.0615
19.07
OPERARIO
hh
2.00
0.6154
15.63
OFICIAL
hh
2.00
0.6154
13.52
PEON
hh
8.00
2.4615
12.32
Unidad
Materiales
CEMENTO PORTLAND TIPO I
bls
9.74
15.55
ARENA GRUESA
m3
0.52
30.00
m3
0.53
37.82
3.0000
49.44
Equipos
HERRAMIENTAS MANUALES
%MO
MEZCLADORA 9-11p3
hm
1.00
0.3077
15.05
hm
1.00
0.3077
5.30
20.00
2.0400
EQ :
HM :
Subcontratos
PARTIDA:
RENDIMIENTO (m2/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0400
19.07
OPERARIO
hh
1.00
0.4000
15.63
OFICIAL
hh
2.00
0.8000
13.52
PEON
hh
2.00
0.8000
12.32
Materiales
MADERA TORNILLO
p2
7.8900
CLAVOS
kg
0.1500
3.50
2.52
%MO
3.0000
27.69
250.00
0.0672
EQ :
HM :
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
RENDIMIENTO (kg/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Cantidad
Precio S/.
Mano de Obra
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0700
2.49
kg
0.0600
2.52
3.0000
0.99
0.0320
1.55
EQ :
Equipos
HERRAMIENTAS MANUALES
CIZALLA
PARTIDA:
Cuadrilla
CAPATAZ
Unidad
%MO
hm
1.00
Subcontratos
HH :
1.6533
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.20
0.0533
19.07
OPERARIO
hh
2.00
0.5333
15.63
OFICIAL
hh
PEON
hh
4.00
1.0667
12.32
1.05
360.00
3.0000
22.49
13.52
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
m3
Equipos
HERRAMIENTAS MANUALES
%MO
hm
BOMBA DE CONCRETO
m3
0.2667
5.30
1.0500
30.00
EQ :
HM :
1.00
Subcontratos
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0229
19.07
OPERARIO
hh
1.00
0.2286
15.63
OFICIAL
hh
1.00
0.2286
13.52
PEON
hh
2.00
0.4571
12.32
Materiales
MADERA TORNILLO
p2
4.1800
3.20
CLAVOS
kg
0.2200
2.92
ALAMBRE NEGRO
kg
0.0800
2.92
%MO
3.0000
12.73
250.00
0.0672
EQ :
HM :
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
RENDIMIENTO (kg/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.61
FLETE DE ACERO
kg
1.0500
0.20
ALAMBRE NEGRO
kg
0.0600
2.92
3.0000
0.99
0.0320
6.51
200.00
0.0440
EQ :
HM :
Equipos
HERRAMIENTAS MANUALES
CIZALLA
%MO
hm
1.00
Subcontratos
PARTIDA:
RENDIMIENTO (m2/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
14.20
%MO
3.0000
0.57
20.00
2.6000
EQ :
HM :
Materiales
CURADOR DE CONCRETO SIKA
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
RENDIMIENTO (m3/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Cantidad
Precio S/.
Mano de Obra
hh
0.50
0.2000
19.07
OPERARIO
hh
2.00
0.8000
15.63
OFICIAL
hh
PEON
hh
4.00
1.6000
12.32
1.05
209.00
13.52
Materiales
m3
Equipos
HERRAMIENTAS MANUALES
Cuadrilla
CAPATAZ
Unidad
%MO
3.0000
36.03
BOMBA DE CONCRETO
m3
1.0500
30.00
hm
0.4000
5.30
Subcontratos
1.00
PARTIDA:
25.00
1.6320
EQ :
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0320
19.07
OPERARIO
hh
1.00
0.3200
15.63
OFICIAL
hh
2.00
0.6400
13.52
PEON
hh
2.00
0.6400
12.32
Materiales
MADERA TORNILLO
p2
5.1600
3.50
CLAVOS
kg
0.1700
2.52
ALAMBRE NEGRO
kg
0.3000
2.52
%MO
3.0000
22.15
250.00
0.0672
EQ :
HM :
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
RENDIMIENTO (kg/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.49
ALAMBRE NEGRO
kg
0.0600
2.52
Equipos
3
HERRAMIENTAS MANUALES
CIZALLA
4
%MO
3.0000
0.99
1.00
0.0320
1.55
200.00
0.0440
EQ :
HM :
hm
Subcontratos
PARTIDA:
RENDIMIENTO (m2/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
14.20
%MO
3.0000
0.57
40.00
1.5000
EQ :
HM :
Materiales
CURADOR DE CONCRETO SIKA
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
RENDIMIENTO (m3/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
Precio S/.
Mano de Obra
CAPATAZ
hh
0.50
0.1000
19.07
OPERARIO
hh
4.00
0.8000
15.63
OFICIAL
hh
PEON
hh
3.00
0.6000
12.32
m3
1.0500
209.00
13.52
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
21.80
BOMBA DE CONCRETO
m3
1.0500
30.00
hm
0.2000
5.30
25.00
1.6320
EQ :
HM :
1.00
Subcontratos
PARTIDA:
RENDIMIENTO (m3/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
Precio S/.
Mano de Obra
CAPATAZ
hh
0.10
0.0320
19.07
OPERARIO
hh
1.00
0.3200
15.63
OFICIAL
hh
2.00
0.6400
13.52
PEON
hh
2.00
0.6400
12.32
Materiales
MADERA TORNILLO
p2
4.18
3.50
CLAVOS
kg
0.22
2.52
ALAMBRE NEGRO
3
kg
0.08
2.52
3.0000
22.15
250.00
0.0672
EQ :
HM :
Equipos
HERRAMIENTAS MANUALES
%MO
Subcontratos
PARTIDA:
RENDIMIENTO (kg/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.61
FLETE DE ACERO
kg
1.0500
0.20
ALAMBRE NEGRO
kg
0.0600
2.92
Equipos
HERRAMIENTAS MANUALES
CIZALLA
%MO
hm
3.0000
0.99
1.00
0.0320
1.55
MO :
200.00
EQ :
HH :
0.0440
HM :
Subcontratos
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
0.10
Cantidad
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
14.20
%MO
3.0000
0.57
Equipos
HERRAMIENTAS MANUALES
Cuadrilla
Materiales
CURADOR DE CONCRETO SIKA
Unidad
Subcontratos
PARTIDA:
MO :
40.00
EQ :
HH :
2.1000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.50
0.1000
19.07
OPERARIO
hh
5.00
1.0000
15.63
OFICIAL
hh
3.00
0.6000
13.52
PEON
hh
2.00
0.4000
12.32
m3
1.0500
209.00
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
30.58
BOMDA DE CONCRETO
m3
1.0500
30.00
hm
0.2000
5.30
1.00
Subcontratos
PARTIDA:
MO :
20.00
EQ :
HH :
2.0400
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0400
19.07
OPERARIO
hh
1.00
0.4000
15.63
OFICIAL
hh
2.00
0.8000
13.52
PEON
hh
2.00
0.8000
12.32
Materiales
MADERA TORNILLO
p2
6.6900
3.50
CLAVOS
kg
0.2400
2.52
ALAMBRE NEGRO
kg
0.2100
2.52
%MO
3.0000
27.69
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
250.00
EQ :
HH :
0.0672
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
PEON
hh
1.00
0.0320
13.52
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.49
ALAMBRE NEGRO
kg
0.0600
2.52
Equipos
HERRAMIENTAS MANUALES
CIZALLA
%MO
hm
3.0000
0.99
1.00
0.0320
1.55
MO :
200.00
EQ :
HH :
0.0440
HM :
Subcontratos
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
14.20
%MO
3.0000
0.57
Materiales
CURADOR DE CONCRETO SIKA
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
40.00
EQ :
HH :
1.8400
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.20
0.0400
19.07
OPERARIO
hh
5.00
1.0000
15.63
OFICIAL
hh
PEON
hh
4.00
0.8000
12.32
m3
1.0500
209.00
13.52
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
Unidad
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
26.25
BOMBA DE CONCRETO
m3
1.0500
30.00
hm
0.2000
5.30
1.00
Subcontratos
PARTIDA:
MO :
25.00
EQ :
HH :
1.6320
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0320
19.07
OPERARIO
hh
1.00
0.3200
15.63
OFICIAL
hh
2.00
0.6400
13.52
PEON
hh
2.00
0.6400
12.32
Materiales
MADERA TORNILLO
p2
5.1300
3.50
CLAVOS
kg
0.1100
2.52
ALAMBRE NEGRO
kg
0.1000
2.49
%MO
3.0000
22.15
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
250.00
EQ :
HH :
0.0672
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cantidad
Precio S/.
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.49
ALAMBRE NEGRO
kg
0.0600
2.52
3.0000
0.99
0.0320
1.55
Equipos
HERRAMIENTAS MANUALES
%MO
CIZALLA
PARTIDA:
Cuadrilla
CAPATAZ
Unidad
hm
1.00
Subcontratos
MO :
1,600.00
EQ :
HH :
0.0455
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
CAPATAZ
hh
0.10
OPERARIO
hh
1.00
OFICIAL
hh
1.00
PEON
hh
9.00
0.0005
Precio S/.
19.07
15.63
13.52
0.0450
12.32
1.0300
1.50
%MO
3.0000
0.56
Materiales
LADRILLO TECHO TIPO BOVEDILLA h=15 cm
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
1,000.00
EQ :
HH :
0.0176
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.20
0.0016
19.07
OPERARIO
hh
0.00
0.0000
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
2.00
0.0160
12.32
1.0300
2.20
%MO
3.0000
0.23
Materiales
LADRILLO TECHO TIPO BOVEDILLA h=20 cm
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
200.00
EQ :
HH :
0.0440
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
0.10
Cantidad
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
14.20
%MO
3.0000
0.57
Materiales
CURADOR DE CONCRETO SIKA
Unidad
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
45.00
EQ :
HH :
1.6356
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.20
0.0356
19.07
OPERARIO
hh
5.00
0.8889
15.63
OFICIAL
hh
PEON
hh
4.00
0.7111
12.32
m3
1.0500
209.00
13.52
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
23.33
BOMBA DE CONCRETO
m3
1.0500
30.00
hm
0.1778
5.30
1.00
Subcontratos
PARTIDA:
MO :
30.00
EQ :
HH :
1.3600
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cantidad
Precio S/.
hh
0.10
0.0267
19.07
OPERARIO
hh
1.00
0.2667
15.63
OFICIAL
hh
2.00
0.5333
13.52
PEON
hh
2.00
0.5333
12.32
Materiales
MADERA TORNILLO
p2
5.9100
3.50
CLAVOS
kg
0.1400
2.52
ALAMBRE NEGRO
kg
0.1000
2.52
%MO
3.0000
18.46
Equipos
HERRAMIENTAS MANUALES
Cuadrilla
CAPATAZ
Unidad
Subcontratos
PARTIDA:
MO :
250.00
EQ :
HH :
0.0672
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.49
ALAMBRE NEGRO
kg
0.0600
2.52
3.0000
0.99
0.0320
1.55
Equipos
HERRAMIENTAS MANUALES
CIZALLA
%MO
hm
1.00
Subcontratos
PARTIDA:
MO :
200.00
EQ :
HH :
0.0440
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
23.00
%MO
3.0000
0.57
Materiales
CURADOR DE CONCRETO CHEMA
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
35.00
EQ :
HH :
1.4857
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.50
0.1143
19.07
OPERARIO
hh
1.00
0.2286
15.63
OFICIAL
hh
2.00
0.4571
13.52
PEON
hh
3.00
0.6857
12.32
1.0500
209.00
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
m3
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
20.38
BOMBA DE CONCRETO
m3
1.0500
30.00
hm
0.2286
5.30
1.00
Subcontratos
PARTIDA:
MO :
10.00
EQ :
HH :
4.0800
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0800
19.07
OPERARIO
hh
1.00
0.8000
15.63
OFICIAL
hh
2.00
1.6000
13.52
PEON
hh
2.00
1.6000
12.32
Materiales
MADERA TORNILLO
p2
5.7400
3.50
CLAVOS
kg
0.1000
2.52
ALAMBRE NEGRO
kg
0.0800
2.52
%MO
3.0000
55.37
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
250.00
EQ :
HH :
0.0672
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.49
ALAMBRE NEGRO
kg
0.0600
2.52
3.0000
0.99
0.0320
1.55
Equipos
HERRAMIENTAS MANUALES
CIZALLA
Unidad
%MO
hm
Subcontratos
1.00
PARTIDA:
MO :
200.00
EQ :
HH :
0.0440
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
hh
OPERARIO
hh
OFICIAL
hh
PEON
hh
Cuadrilla
Cantidad
0.10
0.0040
Precio S/.
19.07
15.63
13.52
1.00
0.0400
12.32
gln
0.0500
23.00
%MO
3.0000
0.57
Materiales
CURADOR DE CONCRETO CHEMA
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
10.00
EQ :
HH :
6.5600
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
333.39
Precio S/.
CAPATAZ
hh
0.20
0.1600
19.07
OPERARIO
hh
2.00
1.6000
15.63
OFICIAL
hh
1.00
0.8000
13.52
PEON
hh
5.00
4.0000
12.32
m3
1.0500
209.00
Materiales
CONCRETO PREMEZCLADO f'c 210kg/cm2
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
88.16
BOMBA DE CONCRETO
m3
0.6300
30.00
VIBRADOR DE CONCRETO
hm
0.8000
5.30
1.00
Subcontratos
PARTIDA:
MO :
15.00
EQ :
HH :
2.7200
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
51.78
Precio S/.
CAPATAZ
hh
0.10
0.0533
19.07
OPERARIO
hh
1.00
0.5333
15.63
OFICIAL
hh
2.00
1.0667
13.52
PEON
hh
2.00
1.0667
12.32
Materiales
MADERA TORNILLO
p2
3.7500
3.50
CLAVOS
Kg
0.1000
2.52
ALAMBRE NEGRO
Kg
0.1500
2.52
%MO
3.0000
36.92
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
250.00
EQ :
HH :
250.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
3.84
Precio S/.
CAPATAZ
hh
0.10
0.0032
19.07
OPERARIO
hh
1.00
0.0320
15.63
OFICIAL
hh
1.00
0.0320
13.52
PEON
hh
12.32
Materiales
ACERO CORRUGADO fy=4200 kg/cm2
kg
1.0500
2.49
ALAMBRE NEGRO
kg
0.0600
2.52
3.0000
0.99
0.0320
1.55
Equipos
HERRAMIENTAS MANUALES
CIZALLA
%MO
hm
1.00
Subcontratos
PARTIDA:
MO :
5.70
EQ :
HH :
2.2456
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
92.84
Precio S/.
CAPATAZ
hh
0.10
0.1404
19.07
OPERARIO
hh
1.00
1.4035
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.50
0.7018
12.32
78.0000
0.67
Materiales
LADRILLO KK 18 HUECOS 9x12.5x23
CEMENTO
bls
0.3356
15.55
ARENA GRUESA
m3
0.0410
37.82
MADERA TORNILLO
p2
0.5800
3.50
3.0000
33.26
1.4035
1.50
MO :
7.00
EQ :
HH :
1.8286
HM :
Equipos
HERRAMIENTAS MANUALES
ANDAMIO SIMPLE
%MO
hm
1.00
Subcontratos
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
32.35
Precio S/.
Mano de Obra
CAPATAZ
hh
0.10
0.1143
19.07
OPERARIO
hh
1.00
1.1429
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.50
0.5714
12.32
Materiales
LADRILLO KK 18 HUECOS 9x12.5x23
44.0000
0.67
CEMENTO
bls
0.1535
15.55
ARENA GRUESA
m3
0.0188
37.82
MADERA TORNILLO
p2
0.5800
3.50
3.0000
27.08
1.1429
1.50
Equipos
HERRAMIENTAS MANUALES
ANDAMIO SIMPLE
%MO
hm
1.00
Subcontratos
PARTIDA:
MO :
7.00
EQ :
HH :
1.8286
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
32.06
Precio S/.
CAPATAZ
hh
0.10
0.1143
19.07
OPERARIO
hh
1.00
1.1429
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.50
0.5714
12.32
Materiales
LADRILLO KK 18 HUECOS 9x12.5x23
33.0000
0.67
CEMENTO
bls
0.0901
15.55
ARENA GRUESA
m3
0.0110
37.82
MADERA TORNILLO
p2
0.5800
3.50
3.0000
27.08
1.1429
1.50
MO :
30.00
EQ :
HH :
0.3822
HM :
Equipos
HERRAMIENTAS MANUALES
ANDAMIO SIMPLE
%MO
hm
1.00
Subcontratos
PARTIDA:
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
14.08
Precio S/.
Mano de Obra
CAPATAZ
hh
0.10
0.0267
19.07
OPERARIO
hh
1.00
0.2667
15.63
OFICIAL
hh
0.0000
13.52
PEON
hh
0.0889
12.32
0.33
Materiales
CEMENTO PORTLAND
bls
0.2500
16.00
ARENA FINA
m3
0.0120
30.00
MADERA TORNILLO
p2
0.5800
3.50
3.0000
5.77
0.5000
3.50
Equipos
HERRAMIENTAS MANUALES
ANDAMIO
%MO
hm
1.00
Subcontratos
PARTIDA:
MO :
16.00
EQ :
HH :
0.8000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
CAPATAZ
Unidad
hh
Cuadrilla
0.10
Cantidad
0.0500
17.63
Precio S/.
19.07
OPERARIO
hh
OFICIAL
hh
PEON
hh
1.00
0.50
0.5000
15.63
0.0000
13.52
0.2500
12.32
Materiales
CEMENTO PORTLAND
bls
0.1335
15.55
ARENA FINA
m3
0.0150
37.82
MADERA TORNILLO
p2
0.5800
3.50
3.0000
11.85
0.5000
1.50
Equipos
HERRAMIENTAS MANUALES
%MO
ANDAMIO
hm
REGLA DE MADERA
p2
0.39
CLAVOS D3 3"
kg
0.10
1.00
Subcontratos
PARTIDA:
MO :
12.00
EQ :
HH :
1.0667
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0667
19.07
OPERARIO
hh
1.00
0.6667
15.63
OFICIAL
hh
0.0000
13.52
PEON
hh
0.3333
12.32
0.50
Materiales
CEMENTO PORTLAND
bls
0.1335
15.55
ARENA FINA
m3
0.0150
37.82
MADERA TORNILLO
p2
0.5800
3.50
%MO
3.0000
15.80
0.6667
1.50
Equipos
HERRAMIENTAS MANUALES
Unidad
21.95
ANDAMIO
hm
REGLA DE MADERA
p2
0.0250
CLAVOS D3 3"
kg
0.0220
Subcontratos
1.00
PARTIDA:
MO :
6.50
EQ :
HH :
1.7641
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
30.86
Precio S/.
CAPATAZ
hh
0.10
0.1231
19.07
OPERARIO
hh
1.00
1.2308
15.63
OFICIAL
hh
0.0000
13.52
PEON
hh
0.4103
12.32
0.33
Materiales
CEMENTO PORTLAND
bls
0.1170
15.55
ARENA FINA
m3
0.0160
37.82
%MO
3.0000
26.64
0.6667
1.50
Equipos
HERRAMIENTAS MANUALES
ANDAMIO
hm
REGLA DE MADERA
p2
0.3880
CLAVOS D3 3"
kg
0.1000
1.00
Subcontratos
PARTIDA:
MO :
18.00
EQ :
HH :
0.6370
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
10.22
Precio S/.
Mano de Obra
CAPATAZ
hh
0.10
0.0444
19.07
OPERARIO
hh
1.00
0.4444
15.63
OFICIAL
hh
0.0000
13.52
PEON
hh
0.1481
12.32
0.33
Materiales
CEMENTO PORTLAND
bls
0.0160
15.55
ARENA FINA
m3
0.0020
37.82
9.62
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
REGLA DE MADERA
p2
0.0730
CLAVOS D3 3"
kg
0.0060
Subcontratos
PARTIDA:
MO :
10.00
EQ :
HH :
1.2800
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
22.03
Precio S/.
CAPATAZ
hh
0.10
0.0800
19.07
OPERARIO
hh
1.00
0.8000
15.63
OFICIAL
hh
0.0000
13.52
PEON
hh
0.4000
12.32
0.50
Materiales
CEMENTO PORTLAND
bls
0.1300
16.00
ARENA FINA
m3
0.0140
30.00
%MO
3.0000
18.96
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
30.00
EQ :
HH :
0.5867
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.20
0.0533
19.07
OPERARIO
hh
1.00
0.2667
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
1.00
0.2667
12.32
Materiales
CEMENTO
bls
0.1120
15.55
ARENA FINA
m3
0.0040
37.82
17.0000
0.75
m3
0.0420
35.00
%MO
3.0000
8.47
LADRILLO PASTELERO
TIERRA DE CHACRA
Unidad
10.62
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
40.00
EQ :
HH :
1.2400
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
19.05
Precio S/.
CAPATAZ
hh
0.20
0.0400
19.07
OPERARIO
hh
0.00
0.0000
15.63
OFICIAL
hh
2.00
0.4000
13.52
PEON
hh
4.00
0.8000
12.32
Materiales
ARENA FINA
m3
0.0030
30.00
TIERRA DE CHACRA
m3
0.0700
35.00
%MO
3.0000
16.03
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
25.00
EQ :
HH :
0.4587
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
10.61
Precio S/.
CAPATAZ
hh
0.10
0.0320
19.07
OPERARIO
hh
1.00
0.3200
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.33
0.1067
12.32
Materiales
CEMENTO
bls
0.0777
16.00
ARENA FINA
m3
0.0110
30.00
MADERA TORNILLO
p2
0.5800
3.50
%MO
3.0000
6.93
0.3200
3.50
Equipos
HERRAMIENTAS MANUALES
ANDAMIO
hm
1.00
Subcontratos
PARTIDA:
MO :
6.00
EQ :
HH :
2.1333
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
40.49
Precio S/.
CAPATAZ
hh
0.10
0.1333
19.07
OPERARIO
hh
1.00
1.3333
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.50
0.6667
12.32
Materiales
CEMENTO
bls
0.2570
15.55
ARENA FINA
m3
0.0330
37.82
MADERA TORNILLO
p2
0.5800
3.50
%MO
3.0000
31.60
1.3333
3.50
Equipos
HERRAMIENTAS MANUALES
ANDAMIO
hm
REGLA DE MADERA
p2
0.0270
CLAVOS D3 3"
kg
0.0090
1.00
Subcontratos
PARTIDA:
MO :
80.00
EQ :
HH :
1.0300
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
23.42
Precio S/.
Mano de Obra
CAPATAZ
hh
0.30
0.0300
19.07
OPERARIO
hh
3.00
0.3000
15.63
OFICIAL
hh
1.00
0.1000
13.52
PEON
hh
6.00
0.6000
12.32
Materiales
CEMENTO
bls
0.3930
16.00
ARENA FINA
m3
0.0420
30.00
Equipos
HERRAMIENTAS MANUALES
%MO
MEZCLADORA
hm
1.00
3.0000
14.01
0.1000
14.50
Subcontratos
PARTIDA:
MO :
12.00
EQ :
HH :
1.0667
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
59.90
Precio S/.
CAPATAZ
hh
0.10
0.0667
19.07
OPERARIO
hh
1.00
0.6667
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.50
0.3333
12.32
Materiales
CEMENTO
bls
0.2620
16.00
ARENA FINA
m3
0.2700
30.00
m2
1.0500
20.00
FRAGUA BLANCA
kg
6.0000
1.68
HERRAMIENTAS MANUALES
%MO
3.0000
15.80
CORTADORA DE MAYOLICA
hm
1.0000
0.26
Equipos
Subcontratos
PARTIDA:
MO :
12.00
EQ :
HH :
2.0667
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
31.79
Precio S/.
CAPATAZ
hh
0.10
0.0667
19.07
OPERARIO
hh
1.00
0.6667
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
2.00
1.3333
12.32
0.1596
16.00
Materiales
CEMENTO
bls
ARENA FINA
m3
0.0090
30.00
%MO
3.0000
28.12
MO :
12.00
EQ :
HH :
0.7333
HM :
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
TERRAZO (m2)
RENDIMIENTO (m2/da)
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Unidad
Cuadrilla
Cantidad
45.99
Precio S/.
Mano de Obra
CAPATAZ
hh
0.10
0.0667
19.07
OPERARIO
hh
0.00
0.0000
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
1.00
0.6667
12.32
Materiales
CEMENTO
bls
0.0662
16.00
ARENA FINA
m3
0.0112
30.00
TERRAZO
m2
1.0500
33.00
3.0000
9.48
0.6667
0.26
Equipos
HERRAMIENTAS MANUALES
%MO
CORTADORA DE MAYOLICA
hm
1.00
Subcontratos
PARTIDA:
MO :
20.00
EQ :
HH :
0.4400
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Cuadrilla
Cantidad
Precio S/.
CAPATAZ
hh
0.10
0.0400
19.07
OPERARIO
hh
0.00
0.0000
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
1.00
0.4000
12.32
Unidad
34.78
Materiales
CEMENTO
bls
0.0777
16.00
ARENA GRUESA
m3
0.0110
30.00
gal
0.6670
41.00
Equipos
HERRAMIENTAS MANUALES
4
%MO
3.0000
5.69
Subcontratos
PARTIDA:
MO :
10.00
EQ :
HH :
1.1467
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
23.01
Precio S/.
CAPATAZ
hh
0.10
0.0800
19.07
OPERARIO
hh
1.00
0.8000
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.33
0.2667
12.32
Materiales
CEMENTO
bls
0.0777
16.00
ARENA GRUESA
m3
0.0110
30.00
m2
0.2000
18.00
%MO
3.0000
17.31
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
MO :
6.50
EQ :
HH :
1.3538
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Precio S/.
hh
0.10
0.1231
19.07
OPERARIO
hh
0.00
0.0000
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
1.00
1.2308
12.32
Materiales
ENCHAPE SPAZIO (PIEDRA KKALA GRIS 6X24X1.2 cm)
CEMENTO
m2
bls
1.0500
0.0185
25.00
16.00
ARENA GRUESA
m3
0.0022
30.00
%MO
3.0000
17.51
7.00
EQ :
Equipos
HERRAMIENTAS MANUALES
Cantidad
CAPATAZ
Cuadrilla
18.40
Subcontratos
PARTIDA:
MO :
HH :
1.8286
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
41.22
Precio S/.
CAPATAZ
hh
0.10
0.1143
19.07
OPERARIO
hh
1.00
1.1429
15.63
OFICIAL
hh
0.00
0.0000
13.52
PEON
hh
0.50
0.5714
12.32
Materiales
CEMENTO
bls
0.2620
16.00
ARENA FINA
m3
PORCELANA
kg
0.2700
0.1100
30.00
3.90
m2
1.0500
12.00
3.0000
27.08
1.1429
0.26
Equipos
HERRAMIENTAS MANUALES
%MO
CORTADORA DE MAYOLICA
hm
1.00
Subcontratos
PARTIDA:
MO :
4.00
EQ :
HH :
2.8667
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
OPERARIO
OFICIAL
PEON
hh
hh
hh
hh
Materiales
CEMENTO
ARENA FINA
PORCELANA
CERAMICO BLANCA CELIMA 20X20 cm
bls
m3
kg
m2
Equipos
HERRAMIENTAS MANUALES
CORTADORA DE MAYOLICA
Cuadrilla
Precio S/.
0.2000
2.0000
0.0000
0.6667
19.07
15.63
13.52
12.32
0.1870
0.0210
0.1950
1.0500
16.00
30.00
3.90
14.00
3.0000
2.0000
43.29
0.26
EQ :
HM :
%MO
hm
0.10
1.00
0.00
0.33
Cantidad
48.73
1.00
Subcontratos
PARTIDA:
RENDIMIENTO (m2/da)
Cdigo
1
Descripcin Recurso
Mano de Obra
CAPATAZ
OPERARIO
OFICIAL
Unidad
hh
hh
hh
Cuadrilla
0.10
1.00
0.00
Cantidad
0.0320
0.3200
0.0000
7.45
Precio S/.
19.07
15.63
13.52
PEON
hh
0.1067
12.32
bls
m3
0.0160
0.0020
16.00
30.00
%MO
3.0000
6.93
EQ :
HM :
Materiales
CEMENTO
ARENA FINA
Equipos
HERRAMIENTAS MANUALES
Subcontratos
PARTIDA:
RENDIMIENTO (u/da)
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
CAPATAZ
OPERARIO
OFICIAL
PEON
PARTIDA:
Cantidad
Precio S/.
0.0000
0.0000
1.0000
0.0000
19.07
15.63
13.52
12.32
PUERTA DE MADERA
1.0000
110.00
BISAGRAS CAPUCHINAS
1.5500
7.00
0.6000
330.00
Equipos
HERRAMIENTAS MANUALES
%MO
3.0000
13.52
EQ :
HM :
Materiales
Subcontratos
Cdigo
1
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Cuadrilla
134.78
hh
hh
hh
hh
0.33
Subcontratos
SUB CONTRATO DE CARPINTERIA METALICA
PARTIDA:
RENDIMIENTO (m2/da)
Unidad
Cuadrilla
Cantidad
1.00
225.00
Precio S/.
225.00
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
475.00
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Subcontratos
SUBC. METAL: REJILLAS METALICAS P/VENT. V6
PARTIDA:
Unidad
Cuadrilla
m2
Cdigo
1
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Subcontratos
SUMIN. E INSTAL. DE ESCALERA DE GATO
PARTIDA:
Unidad
475.00
MO :
0.00
HH :
0.0000
COSTO DIRECTO :
EQ :
HM :
Cantidad
35.00
Precio S/.
1.0000
35.00
MO :
0.00
HH :
0.0000
COSTO DIRECTO :
EQ :
HM :
Cdigo
1
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Unidad
Cuadrilla
Cantidad
350.00
Precio S/.
Subcontratos
SUBC. CARP. METALICA - REJA PERIMETRAL
PARTIDA:
1.0000
350.00
MO :
0.00
HH :
0.0000
COSTO DIRECTO :
EQ :
HM :
Cdigo
1
1.0000
Cuadrilla
RENDIMIENTO (m/da)
Precio S/.
Cantidad
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
2,500.00
Precio S/.
Materiales
Equipos
Subcontratos
SUBC. CARP. METALICA - REJA VEHICULAR
glb
PARTIDA:
2,500.00
Cdigo
1
Descripcin Recurso
Mano de Obra
Materiales
Equipos
1.0000
MO :
Unidad
Subcontratos
SUBC. SUM.E INSTAL.DE CARP. CRISTAL Y ALUM.
PARTIDA:
0.00
EQ :
HH :
0.0000
COSTO DIRECTO :
HM :
Cuadrilla
Cantidad
m2
417.00
Precio S/.
1.0000
417.00
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
Materiales
LIJA AL AGUA
PINTURA LATEX SUPERMATE CLASE A VENCEDOR
SELLADOR
PINTURA AL TEMPLE
IMPRIMANTE SU MAJESTAD
Cuadrilla
Cantidad
8.29
Precio S/.
plg
gln
gln
kg
kg
0.2000
0.0670
0.0167
1.1000
0.2500
1.5000
35.0000
29.0000
0.5000
0.4500
m2
1.0000
4.50
EQ :
HM :
Equipos
Subcontratos
SUB CONTRATO DE PINTURA
PARTIDA:
RENDIMIENTO (m2/da)
Cdigo
1
Descripcin Recurso
Mano de Obra
Materiales
Unidad
Cuadrilla
Cantidad
8.29
Precio S/.
PARTIDA:
LIJA AL AGUA
plg
gln
0.2000
0.0670
1.5000
35.0000
SELLADOR
gln
0.0167
29.0000
PINTURA AL TEMPLE
IMPRIMANTE SU MAJESTAD
kg
kg
1.1000
0.2500
0.5000
0.4500
m2
1.0000
4.50
Equipos
Subcontratos
SUB CONTRATO DE PINTURA
0.0000
EQ :
HM :
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Unidad
Materiales
LIJA AL AGUA
PINTURA LATEX SUPERMATE CLASE A VENCEDOR
SELLADOR
PINTURA AL TEMPLE
IMPRIMANTE SU MAJESTAD
Cuadrilla
Cantidad
8.29
Precio S/.
plg
gln
gln
kg
kg
0.2000
0.0670
0.0167
1.1000
0.2500
1.5000
35.0000
29.0000
0.5000
0.4500
m2
1.0000
4.50
Equipos
Subcontratos
SUB CONTRATO DE PINTURA
PARTIDA:
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
1
Descripcin Recurso
Mano de Obra
Materiales
LIJA AL AGUA
PINTURA ESMALTE VENCEDOR
SELLADOR
PINTURA AL TEMPLE
IMPRIMANTE SU MAJESTAD
Cuadrilla
Cantidad
Precio S/.
plg
gln
gln
kg
kg
0.2000
0.0670
0.0167
1.1000
0.2500
1.5000
30.0000
29.0000
0.5000
0.4500
m2
1.0000
4.50
Equipos
Subcontratos
SUB CONTRATO DE PINTURA
PARTIDA:
Unidad
7.96
RENDIMIENTO (m2/da)
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Unidad
Cuadrilla
Cantidad
8.18
Precio S/.
LIJA AL AGUA
plg
0.2000
1.5000
gln
0.0670
35.0000
SELLADOR
gln
0.0167
29.0000
PINTURA AL TEMPLE
kg
1.1000
0.5000
IMPRIMANTE SU MAJESTAD
kg
0.2500
0.4500
m2
1.0000
4.50
Equipos
Subcontratos
SUB CONTRATO DE PINTURA
PARTIDA:
MO :
10.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Unidad
Cuadrilla
Cantidad
520.71
Precio S/.
PAR
1.0000
1.8000
pza
1.0000
182.0000
und
1.0000
3.0000
1.0000
260.0000
1.0000
65.0000
CINTA TEFLON
pza
0.3000
1.2000
pza
1.0000
4.7500
pza
1.0000
3.8000
Equipos
Subcontratos
PARTIDA:
MO :
10.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Unidad
Cuadrilla
Cantidad
122.56
Precio S/.
PAR
1.00
1.80
PAR
1.00
1.80
und
1.00
105.00
pza
2.00
1.40
CINTA TEFLON
pza
0.30
1.20
MASILLA
kg
1.00
6.00
pza
1.00
4.80
Equipos
Subcontratos
PARTIDA:
MO :
10.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Unidad
Cuadrilla
Cantidad
84.86
Precio S/.
pza
1.00
und
1.00
4.50
und
1.00
22.00
CINTA TEFLON
pza
0.30
1.20
pza
2.00
9.00
Equipos
Subcontratos
40.00
PARTIDA:
MO :
30.00
EQ :
HH :
2.1600
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
208.10
Precio S/.
CAPATAZ
hh
0.10
0.0267
19.07
OPERARIO
hh
2.00
0.5333
15.63
OFICIAL
hh
1.00
0.2667
13.52
PEON
hh
5.00
1.3333
12.32
Materiales
CEMENTO PORTLAND
bls
8.4300
16.00
m3
0.5500
40.00
ARENA GRUESA
m3
0.5400
30.00
%MO
3.0000
28.88
Equipos
HERRAMIENTAS MANUALES
MEZCLADORA 9-11p3
hm
1.00
0.2667
14.50
VIBRADOR DE CONCRETO
hm
1.00
0.2667
5.30
Subcontratos
PARTIDA:
BANCAS (u)
RENDIMIENTO (u/da)
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
BANCAS
Unidad
Cuadrilla
und
Equipos
Subcontratos
PARTIDA:
Cantidad
1.0000
140.68
Precio S/.
140.68
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Materiales
Equipos
Subcontratos
Unidad
PARTIDA:
Cuadrilla
Cantidad
und
450.0000
6,750.00
Precio S/.
15.00
MO :
0.00
EQ :
HH :
0.0000
HM :
COSTO DIRECTO :
Cdigo
Descripcin Recurso
Mano de Obra
Unidad
Cuadrilla
Cantidad
2,070.00
Precio S/.
Materiales
CANTO RODADO NEGRO 2" -15kg
Equipos
Subcontratos
bls
138.0000
15.00
RAS
8.00
0.00
0.0000
80,640.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
costo
80,640.00
80,640.00
0.00
0.0000
250.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
250.00
250.00
0.00
0.0000
900.00
container
area
7560
30
252
84
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
900.00
900.00
0.00
0.0000
1,200.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
1,200.00
1,200.00
lb)
0.00
0.0000
225.50
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
225.50
225.50
0.00
11,100.0000
11,100.00
Parcial S/.
0.00
0.00
0.00
0.00
3,600.00
7,500.00
11,100.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.0000
8,220.80
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
8,220.80
8,220.80
0.00
0.0000
2,400.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
0.00
2,400.00
2,400.00
300.00
0.0533
2.30
Parcial S/.
0.05
0.42
0.00
0.99
1.45
0.01
0.30
0.09
0.06
0.47
0.04
0.23
0.10
0.38
0.00
0.00
Resumen
capataz
operario
oficial
peon
costo HH S/.
19.068279
15.6273899
13.5219979
12.3232149
19.07
15.63
13.52
12.32
0.00
412.8000
13,721.56
Parcial S/.
0.00
3,226.03
0.00
5,085.70
8,311.73
0.02
0.30
0.09
0.07
0.48
249.35
3,096.00
2,064.00
5,409.35
0.00
0.00
0.00
1.0000
7,968.31
Parcial S/.
0.00
0.00
0.00
7,687.68
7,687.68
0.00
0.00
230.63
50.00
280.63
0.00
0.00
mes)
0.00
1.0000
10,606.76
Parcial S/.
0.00
0.00
2,812.16
5,125.12
7,937.28
0.00
0.00
238.12
1,911.36
520.00
2,669.48
0.00
0.00
0.00
0.0000
35,041.35
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
35,041.35
35,041.35
3.00
0.0000
39.08
26.63
26.2549296
Parcial S/.
5.09
0.00
0.00
32.85
37.94
0.00
0.00
1.14
1.14
0.00
0.00
m (m3)
300.00
0.0000
9.73
Parcial S/.
0.10
0.42
0.00
0.66
1.18
0.00
0.00
0.04
3.55
4.97
8.55
700.00
0.0229
3.30
Parcial S/.
0.02
0.00
$
s/
44
188.87
66.5035211
186.209859
0.15
0.07
0.25
0.00
0.00
0.01
1.37
1.67
3.05
7.00
0.0000
24.00
Parcial S/.
2.18
0.00
0.00
14.08
16.26
0.00
0.00
0.49
0.49
0.00
0.00
600.00
0.0267
15.31
Parcial S/.
0.03
0.00
0.18
0.99
1.19
6.30
6.30
0.04
1.60
1.95
2.52
1.72
7.82
0.00
0.00
300.00
0.1067
43.02
Parcial S/.
0.51
0.00
0.72
2.63
3.86
16.25
16.25
0.12
4.00
3.87
12.67
2.27
22.92
0.00
0.00
25.00
0.6400
246.54
Parcial S/.
0.61
5.00
8.65
31.54
45.80
151.30
22.06
19.67
0.00
193.03
1.37
4.64
1.70
7.71
0.00
0.00
13.00
0.0000
50.46
Parcial S/.
1.17
9.62
8.32
0.00
19.11
16.87
0.41
0.53
17.80
0.57
0.57
6.07
6.90
12.97
3)
15.00
0.5333
450.82
Parcial S/.
2.03
41.68
0.00
26.28
70.00
357.00
357.00
2.10
18.90
2.83
23.83
0.00
0.00
12.00
0.6667
107.95
Parcial S/.
1.27
10.42
18.03
65.71
95.42
0.00
0.00
0.00
0.00
0.00
2.86
9.67
12.53
0.00
0.00
30.00
0.5333
190.85
Parcial S/.
0.51
8.34
0.00
3.29
12.13
134.88
22.00
16.20
173.08
0.36
3.87
1.41
5.64
0.00
0.00
15.00
0.0000
38.85
Parcial S/.
1.02
8.34
7.21
0.00
16.56
8.75
0.03
0.04
8.82
0.50
0.50
6.07
6.90
12.97
80.00
0.1000
20.91
Parcial S/.
0.38
3.13
1.35
7.39
12.25
4.32
2.52
6.84
0.37
1.45
1.82
0.00
0.00
26.00
0.6154
244.28
Parcial S/.
1.17
9.62
8.32
30.33
49.44
151.46
15.60
20.04
187.10
1.48
4.63
1.63
7.74
0.00
0.00
20.00
0.0000
56.51
Parcial S/.
0.76
6.25
10.82
9.86
27.69
27.62
0.38
27.99
0.83
0.83
0.00
0.00
250.00
0.0320
3.89
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.66
0.15
2.82
0.03
0.05
0.08
0.00
0.00
)
30.00
Madera Tornillo
Clavos 2.52
Acero corrugado
Cizalla
3.5
2.52
2.49
1.55
1.3167
434.08
Parcial S/.
1.02
8.34
0.00
13.14
22.49
378.00
378.00
0.67
1.41
31.50
33.59
0.00
0.00
(kg)
35.00
0.0000
27.13
Parcial S/.
0.44
3.57
3.09
5.63
12.73
13.38
0.64
14.02
0.38
0.38
0.00
0.00
250.00
0.0320
4.36
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.74
0.21
0.18
3.13
0.03
0.21
0.24
0.00
0.00
200.00
0.0000
1.30
Parcial S/.
0.08
0.00
0.00
0.49
0.57
0.71
0.71
0.02
0.02
0.00
0.00
20.00
1.4500
290.18
Parcial S/.
3.81
12.50
0.00
19.71
36.03
219.45
219.45
1.08
31.50
2.12
34.70
0.00
0.00
25.00
0.0000
42.06
Parcial S/.
0.61
5.00
8.65
7.88
22.15
18.06
0.43
0.76
19.24
0.66
0.66
0.00
0.00
250.00
0.0320
3.84
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.61
0.15
2.77
0.03
0.05
0.08
0.00
0.00
200.00
0.0000
1.30
Madera Tornillo
3.5
Clavos 2.52
Acero corrugado
Cizalla
Alambre negro
2.52
2.49
1.55
2.52
Parcial S/.
0.08
0.00
0.00
0.49
0.57
0.71
0.71
0.02
0.02
0.00
0.00
40.00
1.2500
274.47
Parcial S/.
1.91
12.50
0.00
7.39
21.80
219.45
219.45
0.65
31.50
1.06
33.21
0.00
0.00
25.00
0.0000
38.20
Parcial S/.
0.61
5.00
8.65
7.88
22.15
14.63
0.55
0.20
15.39
0.66
0.66
0.00
0.00
250.00
0.0320
4.20
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.74
0.21
0.18
3.13
0.03
0.05
0.08
0.00
0.00
200.00
0.0000
1.30
Parcial S/.
0.08
0.00
0.00
0.49
0.57
0.71
0.71
0.02
0.02
0.00
0.00
Madera Tornillo
Clavos 2.52
Acero corrugado
Cizalla
Alambre negro
3.5
2.52
2.49
1.55
2.52
40.00
1.2500
283.50
Parcial S/.
1.91
15.63
8.11
4.93
30.58
219.45
219.45
0.92
31.50
1.06
33.48
0.00
0.00
20.00
0.0000
53.07
Parcial S/.
0.76
6.25
10.82
9.86
27.69
23.42
0.60
0.53
24.55
0.83
0.83
0.00
0.00
250.00
0.0320
3.84
Parcial S/.
0.06
0.50
Madera Tornillo
Clavos 2.52
Acero corrugado
Cizalla
Alambre negro
3.5
2.52
2.49
1.55
2.52
0.43
0.00
0.99
2.61
0.15
2.77
0.03
0.05
0.08
0.00
0.00
200.00
0.0000
1.30
Parcial S/.
0.08
0.00
0.00
0.49
0.57
0.71
0.71
0.02
0.02
0.00
0.00
40.00
1.2500
279.05
Parcial S/.
0.76
15.63
0.00
9.86
26.25
219.45
219.45
0.79
31.50
1.06
33.35
0.00
0.00
25.00
0.0000
41.30
Parcial S/.
0.61
5.00
8.65
7.88
22.15
17.96
0.28
0.25
18.48
0.66
0.66
0.00
0.00
250.00
0.0320
3.84
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.61
0.15
2.77
0.03
0.05
0.08
0.00
0.00
O (u)
1,600.00
0.0000
2.13
Parcial S/.
0.01
0.00
0.00
0.55
0.56
1.55
1.55
0.02
0.02
0.00
0.00
O (u)
1,000.00
0.0000
2.50
Parcial S/.
0.03
0.00
0.00
0.20
0.23
2.27
2.27
0.01
0.01
0.00
0.00
200.00
0.0000
1.30
Parcial S/.
0.08
0.00
0.00
0.49
0.57
0.71
0.71
0.02
8.475
0.02
0.00
0.00
45.00
1.2278
275.92
Parcial S/.
0.68
13.89
0.00
8.76
23.33
219.45
219.45
0.70
31.50
0.94
33.14
0.00
0.00
30.00
0.0000
40.30
Parcial S/.
0.51
4.17
7.21
6.57
18.46
20.69
0.35
0.25
21.29
0.55
0.55
0.00
0.00
250.00
0.0320
3.84
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.61
0.15
2.77
0.03
0.05
0.08
0.00
0.00
200.00
0.0000
1.74
Parcial S/.
0.08
0.00
0.00
0.49
0.57
1.15
1.15
0.02
0.02
0.00
0.00
35.00
1.2786
273.15
Parcial S/.
2.18
3.57
6.18
8.45
20.38
219.45
219.45
0.61
31.50
1.21
33.32
0.00
0.00
10.00
0.0000
77.58
Parcial S/.
1.53
12.50
21.63
19.71
55.37
20.09
0.25
0.20
20.54
1.66
1.66
0.00
0.00
250.00
0.0320
3.84
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.61
0.15
2.77
0.03
0.05
0.08
0.00
0.00
200.00
0.0000
1.74
Parcial S/.
0.08
0.00
0.00
0.49
0.57
1.15
1.15
0.02
0.02
0.00
0.00
10.00
0.8000
333.39
Parcial S/.
3.05
25.01
10.82
49.28
88.16
219.45
219.45
2.64
18.90
4.24
25.78
0.00
0.00
15.00
0.0000
51.78
Parcial S/.
1.02
8.34
14.42
13.14
36.92
13.13
0.25
0.38
13.76
1.11
1.11
Madera Tornillo
Clavos 2.52
Acero corrugado
Cizalla
Alambre negro
0.00
0.00
250.00
0.0320
3.84
Parcial S/.
0.06
0.50
0.43
0.00
0.99
2.61
0.15
2.77
0.03
0.05
0.08
0.00
0.00
5.70
1.4035
92.84
Parcial S/.
2.68
21.94
0.00
8.65
33.26
52.26
3.5
2.52
2.49
1.55
2.52
0.64
1.55
2.03
56.48
1.00
2.11
3.10
0.00
0.00
7.00
1.1429
32.35
Parcial S/.
2.18
17.86
0.00
7.04
27.08
29.48
2.39
0.71
2.03
2.74
0.81
1.71
2.53
0.00
0.00
7.00
1.1429
32.06
Parcial S/.
2.18
17.86
0.00
7.04
proprcion 1:4
27.08
22.11
1.40
0.42
2.03
2.45
0.81
1.71
2.53
0.00
0.00
30.00
0.5000
14.08
Parcial S/.
0.51
4.17
0.00
1.10
5.77
4.00
0.36
2.03
6.39
0.17
1.75
1.92
0.00
0.00
16.00
0.5000
17.63
Parcial S/.
0.95
7.82
0.00
3.08
11.85
2.08
0.57
2.03
4.67
0.36
0.75
0.00
0.00
1.11
0.00
0.00
12.00
0.6667
21.95
Parcial S/.
1.27
10.42
0.00
4.11
15.80
2.08
0.57
2.03
4.67
0.47
1.00
0.00
0.00
1.47
0.00
0.00
Rendimiento de capeco
6.50
0.6667
30.86
Parcial S/.
2.35
19.24
0.00
5.05
26.64
1.82
0.61
0.00
2.42
0.80
1.00
0.00
0.00
1.80
0.00
0.00
18.00
0.0000
10.22
Parcial S/.
0.85
6.95
0.00
1.83
9.62
0.25
0.08
0.00
0.32
0.29
0.00
0.00
0.00
0.00
0.00
m)
10.00
0.0000
22.03
Parcial S/.
1.53
12.50
0.00
4.93
18.96
2.08
0.42
2.50
0.57
0.57
0.00
0.00
30.00
0.0000
10.62
Parcial S/.
1.02
4.17
0.00
3.29
8.47
1.74
0.15
12.75
1.47
1.89
0.25
0.25
0.00
0.00
40.00
0.0000
19.05
Parcial S/.
0.76
0.00
5.41
9.86
16.03
0.09
2.45
2.54
0.48
0.48
0.00
0.00
25.00
0.3200
10.61
Parcial S/.
0.61
5.00
0.00
1.31
6.93
1.24
0.33
2.03
2.36
0.21
1.12
1.33
0.00
0.00
6.00
1.3333
40.49
Parcial S/.
2.54
20.84
0.00
8.21
31.60
4.00
1.25
2.03
3.28
0.95
4.67
0.00
0.00
5.61
0.00
0.00
80.00
0.1000
23.42
Parcial S/.
0.57
4.69
1.35
7.39
14.01
6.29
1.26
7.55
0.42
1.45
1.87
0.00
0.00
12.00
1.0000
59.90
Parcial S/.
1.27
10.42
0.00
4.11
15.80
4.19
8.10
21.00
10.08
43.37
0.47
0.26
0.73
0.00
0.00
12.00
0.0000
31.79
Parcial S/.
1.27
10.42
0.00
16.43
28.12
2.55
0.27
2.82
0.84
0.84
0.00
0.00
12.00
0.6667
45.99
Parcial S/.
1.27
0.00
0.00
8.21
9.48
1.06
0.34
34.65
36.05
0.28
0.17
0.46
0.00
0.00
20.00
0.0000
34.78
Parcial S/.
0.76
0.00
0.00
4.93
5.69
1.24
0.33
27.35
28.92
0.17
0.17
0.00
0.00
10.00
0.0000
23.01
Parcial S/.
1.53
12.50
0.00
3.29
17.31
1.24
0.33
3.60
5.17
0.52
0.52
0.00
0.00
6.50
0.0000
18.40
Parcial S/.
2.35
0.00
0.00
15.16
17.51
26.25
0.30
0.07
0.36
0.53
0.53
0.00
0.00
7.00
1.1429
41.22
Parcial S/.
2.18
17.86
0.00
7.04
27.08
4.19
8.10
0.43
12.60
13.03
0.81
0.30
1.11
0.00
0.00
4.00
2.0000
48.73
Parcial S/.
3.81
31.26
0.00
8.21
43.29
2.99
0.63
0.76
14.70
3.62
1.30
0.52
1.82
0.00
0.00
25.00
0.0000
7.45
Parcial S/.
0.61
5.00
0.00
1.31
6.93
0.26
0.06
0.32
0.21
0.21
0.00
0.00
0.00
0.0000
134.78
Parcial S/.
0.00
0.00
13.52
0.00
13.52
110.00
10.85
198.00
120.85
0.41
0.41
0.00
0.00
" (m)
0.00
0.0000
225.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
225
225.00
0.00
0.0000
475.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
475.00
475.00
0.00
35.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
35.00
35.00
0.00
0.0000
350.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
350.00
350.00
0.00
0.0000
2,500.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
2,500.00
2,500.00
0.00
0.0000
417.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
417.00
417.00
0.00
0.0000
8.29
Parcial S/.
0.00
0.00
0.30
2.35
0.48
0.55
0.11
3.79
0.00
0.00
4.50
4.50
0.00
0.0000
8.29
Parcial S/.
0.00
0.00
0.30
2.35
0.48
0.55
0.11
3.79
0.00
0.00
4.50
4.50
)
30.00
0.0000
8.29
Parcial S/.
0.00
0.00
0.30
2.35
0.48
0.55
0.11
3.79
0.00
0.00
4.50
4.50
m2)
0.00
0.0000
7.96
Parcial S/.
0.00
0.00
0.30
2.01
0.48
0.55
0.11
3.46
0.00
0.00
4.50
4.50
0.00
0.0000
8.18
Parcial S/.
0.00
0.00
0.30
2.35
0.48
0.55
3.68
0.00
0.00
4.50
4.50
10.00
0.0000
520.71
Parcial S/.
0.00
0.00
1.80
182.00
3.00
260.00
65.00
0.36
4.75
3.80
520.71
0.00
0.00
0.00
0.00
10.00
122.56
Parcial S/.
0.00
0.00
1.80
1.80
105.00
2.80
0.36
6.00
4.80
122.56
0.00
0.00
0.00
0.00
10.00
0.0000
84.86
Parcial S/.
0.00
0.00
40.00
4.50
22.00
0.36
18.00
84.86
0.00
0.00
0.00
0.00
30.00
0.5333
208.10
Parcial S/.
0.51
8.34
3.61
16.43
28.88
134.88
22.00
16.20
173.08
0.87
3.87
1.41
6.15
0.00
0.00
0.00
0.0000
140.68
Parcial S/.
0.00
0.00
140.68
140.68
0.00
0.00
0.00
0.00
0.00
0.0000
6,750.00
Parcial S/.
0.00
0.00
0.00
0.00
0.00
0.00
6,750.00
6,750.00
0.00
0.0000
2,070.00
Parcial S/.
0.00
0.00
2,070.00
2,070.00
0.00
0.00
0.00
0.00
PRESUPUESTO GENERAL
Item
01
01.01
01.02
01.03
01.03
02
03
03.01
03.02
Descripcin
Unid
Metrado
P. Unit
P.Parcial
Total
1.00 80,640.00
4.00
250.00
1.00
900.00
1.00
1,200.00
1.00
225.50
4.00 11,100.00
80,640.00
1,000.00
900.00
1,200.00
225.50
44,400.00
128,365.50
1.00
8,220.80
1.00
2,400.00
2,804.60
2.30
1.00 13,721.56
4.00
7,968.31
8,220.80
2,400.00
6,452.03
13,721.56
31,873.24
62,667.63
1.00 35,041.35
35,041.35
35,041.35
452.91
593.82
1,382.68
206.44
515.69
868.25
39.08
9.73
3.30
24.00
15.31
43.02
17,698.29
5,776.94
4,555.96
4,954.56
7,895.95
37,355.24
78,236.95
80.01
468.85
165.92
82.06
26.20
21.20
657.07
246.54
50.46
450.82
107.95
190.85
38.85
20.91
19,725.70
23,658.06
74,800.61
8,858.71
5,000.37
823.70
13,738.57
146,605.72
99.20
187.96
4,720.88
244.28
56.51
3.89
24,233.02
10,621.70
18,358.27
53,212.98
52.18
341.99
3,635.23
341.99
434.08
27.13
4.36
1.30
22,650.43
9,278.55
15,841.09
443.27
48,213.34
75.56
809.17
14,156.56
809.17
290.18
42.06
3.84
1.30
21,926.07
34,032.33
54,346.17
1,048.81
111,353.38
40.40
347.80
4,400.88
347.80
274.47
38.20
4.20
1.30
11,088.47
13,285.93
18,479.03
450.80
43,304.23
164.16
1,039.33
24,540.03
1,039.33
283.50
53.07
3.84
1.30
46,540.07
55,153.51
94,207.67
1,347.13
197,248.37
227.97
1,970.67
16,827.85
1,464.00
13,643.00
1,970.67
279.05
41.30
3.84
2.13
2.50
1.30
63,614.18
81,379.06
64,601.08
3,112.25
34,113.79
2,554.29
249,374.65
28.80
146.02
275.92
36.80
7,946.62
5,373.54
09.06
10
10.01
10.02
10.03
11
11.01
11.02
11.03
11.04
11.05
11.06
11.07
11.08
11.09
11.10
12
12.01
12.02
13
13.01
ALBAILERIA
MURO DE SOGA LADRILLO KING-KONG C/M 1:4x1.5 CM
MURO DE CABEZA LADRILLO KING-KONG C/M 1:4x1.5 CM
MURO DE CANTO LADRILLO KING-KONG C/M 1:4x1.5 CM
MURO DE LADRILLO KING-KONG C/M 1:4x1.5 CM ESP=0.20M
REVOQUES ENLUCIDOS Y MOLDURAS
TARRAJEO EN MUROS INT. FROTACHADO MEZ. C:A 1:4 E=1.5 CM
TARRAJEO EN MUROS EXT. FROTACHADO MEZ. C:A 1:4 E=1.5 CM
TARRAJEO DE VIGAS SUPERFICIE MEZ. C:A 1:4 E=1.5 CM
VESTIDURA DE DERRAMES ANCHO=10 CM. MEZ. C:A 1:4 E=1.5 CM
VESTIDURA DE DERRAMES ANCHO=15 CM. MEZ. C:A 1:4 E=1.5 CM
VESTIDURA DE DERRAMES ANCHO=25 CM. MEZ. C:A 1:4 E=1.5 CM
TARRAJEO EN VIGAS SUPERFICIE MEZ. C:A 1:4 E=1.5 CM
CIELORRASOS
CIELORRASOS CON MEZC. C:A 1:4 CON CINTAS E=1.5 CM
TARRAJEO EN FONDO DE ESCALERA
FALSO CIELO RASO
PISOS Y PAVIMENTOS
CONTRAPISO E=48 mm BASE 3.8 cm MEZC. 1:5 ACAB. 1 cm PASTA 1:2
PISO DE CERMICA DE COLOR 40x40 CM. DE 1ERA (CELIMA)
PISO DE TERRAZO LAVADO COLOR GRIS E=4CM
PISO DE CEMENTO PULIDO BRUADO E=1" MEZCLA 1:2
PISO LAMINADO DE MADERA 9MM X 1.206 X 0.191M
ZOCALOS
ZOCALO CERMICO CELIMA CEMENTO GRIS EXTRA 0.10x0.40M
REVESTIMIENTO DE GRADAS Y ESCALERA
REVESTIMIENTO DE GRADAS Y ESCALERAS DE TERRAZO
CUBIERTAS
CUBIERTA LADR.PASTELERO ASEN.DE BARRO 3CM.+FRAGUA C/MOR. 1:5
PINTURA
PINTURA LTEX EN CIELO RASO 2 MANOS
PINTURA LTEX EN MUROS EXTERIORES 2 MANOS
PINTURA LTEX EN MUROS INTERIORES 2 MANOS
CARPINTERIA DE MADERA
PUERTAS DE MADERA TABLEROS REBAJADOS DE 4.5 MM. DE CEDRO
PUERTA CONTRAPLACADA DE 45 MM TRIPLAY
BISAGRA CAPUCHINA DE 3 1/2" X 3 1/2"
MUEBLE ALTO DE COCINA MELAMINA C/PUERTAS MACISA
MUEBLE BAJO DE COCINA CON TABLERO POSTFORMADO
C/PUERTAS DE MELAMINA MACISA
BARANDA DE MADERA PUMAQUIRO SEC. 2"x2"
CARPINTERIA METALICA
BARANDA DE TUBO FO. GDO. PASAMANO 1 1/2"-PARANTE 1" X 1M.ALT
PUERTA METLICA CALLE COMUN 1.65 x 2.10M
PUERTA METLICA ESTACIONAMIENTO 3.00 x 2.10M
CERRAJERIA
CHAPA PARA EXTERIOR, CON LLAVES INTERIOR Y EXTERIOR 2 GOLPES
CERRADURA PARA PUERTA PRINCIPAL PESADA
CERRADURA PARA PUERTA INTERIOR
CERRADURA PARA BAO PRINCIPAL
CERRADURA PARA BAO DE SERVICIO
CERRADURA PARA BAO DE DORMITORIO PRINCIPAL
CERRADURAS P/RECIBIDOR ELECTRICO
BISAGRA VAIVEN DOBLE EFECTO ALUMINIZADO
PICAPORTE DE SUPERFICIE 6"
SISTEMA PUERTA LEVADIZA CON CONTROL REMOTO
INCL. EQUIPO E INSTALACION
VIDRIOS, CRISTALES Y SIMILARES
VENTANAS DESDE LA V-01A HASTA V-23
MAMPARAS DESDE M-01 AL M12
VARIOS
LIMPIEZA PERMANENTE DE OBRA
kg
m2
2,191.92
146.02
3.84
1.74
8,414.65
253.51
21,988.32
m3
m2
kg
m2
11.24
69.79
722.53
69.79
273.15
77.58
3.84
1.74
3,070.24
5,414.20
2,773.75
121.17
11,379.36
m3
m2
kg
45.14
295.31
3,467.22
333.39
51.78
3.84
15,049.22
15,290.62
13,310.45
43,650.29
m2
m2
m2
m2
4,552.31
989.60
423.32
27.96
57.02
95.37
42.57
56.91
259,572.72
94,378.15
18,020.73
1,591.20
373,562.80
m2
m2
m2
m
m
m
m2
10,362.81
1,882.03
1,052.14
450.38
3,280.08
478.40
1,052.14
17.39
21.34
26.13
12.06
13.65
18.74
27.49
180,209.27
40,162.52
27,492.42
5,431.58
44,773.09
8,965.22
28,923.33
335,957.42
m2
m2
m2
4,147.27
223.68
219.90
30.13
20.28
29.80
124,957.25
4,536.23
6,553.02
136,046.50
m2
m2
m2
m2
m2
3,826.82
568.50
200.80
289.99
1,562.58
25.46
66.59
70.86
13.47
38.33
97,430.84
37,856.42
14,228.69
3,906.17
59,893.69
213,315.80
m2
50.45
18.90
953.51
m2
223.68
54.13
12,107.80
12,107.80
m2
1,838.76
31.26
57,479.64
57,479.64
m2
m2
m2
4,147.27
1,882.03
10,362.81
14.17
12.04
12.04
58,766.82
22,659.64
124,768.23
206,194.69
m2
m2
pza
m2
m2
80.64
301.56
648.00
143.73
95.82
224.76
133.84
3.58
235.02
907.02
18,124.65
40,360.79
2,319.84
33,779.42
86,910.66
250.80
67.43
16,911.44
198,406.80
m
m2
m2
250.80
6.93
12.60
82.20
721.65
1,073.34
20,615.76
5,001.03
13,524.08
39,140.88
und
pza
pza
pza
pza
pza
pza
pza
pza
pza
15.00
36.00
112.00
36.00
36.00
36.00
6.00
36.00
36.00
2.00
46.10
56.29
56.29
56.29
56.29
56.29
133.29
62.46
18.42
2,520.54
691.50
2,026.44
6,304.48
2,026.44
2,026.44
2,026.44
799.74
2,248.56
663.12
5,041.08
23,854.24
m2
m2
410.59
834.08
139.24
177.91
57,170.55
148,391.17
205,561.72
GLB
1.00
616.61
616.61
953.51
13.02
13.03
13.04
m2
GLB
m2
99.47
1.00
382.91
1,992.24
1,066.61
22.92
198,168.11
1,066.61
8,776.30
208,627.63
S/. 3,033,223.86
151661.19
151661.19
S/. 3,336,546.24
600578.3238
S/. 3,937,124.57
CALCULOS
JB=
ALTURA=
prom N HIJOS
EPP $
charlas $
baos $
T.C
8
5%
2
0.2
0.06
0.05
2.8
OPERARIO
%
JB
BUC
32.00%
ASIG ESCOLAR
16.67%
GRATIFICACION
22.22%
DOMINICAL
17.63%
VACACIONES
11.54%
FERIADOS
4.41%
ALTURA
0.00%
MOVILIDAD
7.2
OVEROL
0.6
INDEMNIZACION
15%
ESSALUD
9%
SCTR
3%
POLIZA
SUMA
1HH
EPP $
charlas $
baos $
HORAS
tiempo de ejecucion
HH
HH
HH
01 ao
del
capataz 25% mas
jornal basico
desde
desde
1-Jun-09
1-Jun-10
OPERARIO
S/. 42.80
40.1
OFICIAL
S/. 37.50
36.1
PEON
S/. 33.60
32.3
S/. 45.50
S/. 14.56
S/. 7.58
S/. 10.11
S/. 8.02
S/. 5.25
S/. 2.01
S/. 0.00
S/. 7.20
S/. 0.60
S/. 6.83
S/. 7.69
S/. 2.56
0.17
S/. 118.08
0.2
0.06
0.05
S/. 14.76
S/. 0.56
S/. 0.17
S/. 0.14
total HH
S/. 15.63
capataz
%
JB
BUC
32.00%
ASIG ESCOLAR
16.67%
GRATIFICACION
22.22%
DOMINICAL
17.63%
VACACIONES
11.54%
FERIADOS
4.41%
ALTURA
0.00%
MOVILIDAD
7.2
OVEROL
0.6
INDEMNIZACION
15%
ESSALUD
0.09
SCTR
0.03
POLIZA
SUMA
1HH
EPP $
charlas $
baos $
S/. 56.88
S/. 18.20
S/. 9.48
S/. 12.64
S/. 10.03
S/. 6.56
S/. 2.51
S/. 0.00
S/. 7.20
S/. 0.60
S/. 8.53
S/. 9.61
S/. 3.20
0.17
S/. 145.60
0.2
0.06
0.05
S/. 18.20
S/. 0.56
S/. 0.17
S/. 0.14
total HH
S/. 19.07
Resumen
capataz
operario
oficial
peon
oficial
%
JB
BUC
30.00%
ASIG ESCOLAR
16.67%
GRATIFICACION
22.22%
DOMINICAL
17.63%
VACACIONES
11.54%
FERIADOS
4.41%
ALTURA
0.00%
MOVILIDAD
7.2
OVEROL
0.6
INDEMNIZACION
15%
ESSALUD
0.09
SCTR
0.03
POLIZA
SUMA
1HH
EPP $
charlas $
baos $
S/. 38.90
S/. 11.67
S/. 6.48
S/. 8.64
S/. 6.86
S/. 4.49
S/. 1.71
S/. 0.00
S/. 7.20
S/. 0.60
S/. 5.84
S/. 6.50
S/. 2.17
0.17
S/. 101.23
0.2
0.06
0.05
S/. 12.65
S/. 0.56
S/. 0.17
S/. 0.14
total HH
S/. 13.52
costo HH S/.
S/. 19.07
S/. 15.63
S/. 13.52
S/. 12.32
peon
%
JB
BUC
30.00%
ASIG ESCOLAR
16.67%
GRATIFICACION
22.22%
DOMINICAL
17.63%
VACACIONES
11.54%
FERIADOS
4.41%
ALTURA
0.00%
MOVILIDAD
7.2
OVEROL
0.6
INDEMNIZACION
15%
ESSALUD
0.09
SCTR
0.03
POLIZA
SUMA
1HH
EPP $
charlas $
baos $
0.2
0.06
0.05
total HH
S/. 34.90
S/. 10.47
S/. 5.82
S/. 7.76
S/. 6.15
S/. 4.03
S/. 1.54
S/. 0.00
S/. 7.20
S/. 0.60
S/. 5.24
S/. 5.84
S/. 1.95
0.17
S/. 91.64
S/. 11.46
S/. 0.56
S/. 0.17
S/. 0.14
S/. 12.32
RATIOS
Descripcin
Item
01
02
03
04
05
06
07
08
PROYECTO A CONSTRUIR
Total
Ratio - $/m2
CONCEPTO A
Total
Ratio - $/m2
RESIDENCIAL LA RIVIERA
Total
Ratio - $/m2
128,365.50
78,236.95
899,461.85
2,011,209.43
0.00
0.00
0.00
0.00
4.03
7.14
103.52
173.47
11.81
15.12
24.44
18.49
210,365.54
69,500.45
1,000,523.00
2,500,230.12
0.00
0.00
0.00
0.00
6.88
15.32
98.49
161.79
13.36
16.06
19.49
13.33
180,795.23
90,365.12
956,125.23
3,256,145.23
0.00
0.00
0.00
0.00
4.47
6.05
102.93
178.67
11.18
17.81
30.86
13.10
347,918.00
254,072.77
912,545.00
3,783,336.52
0.00
0.00
0.00
0.00
2.65
6.29
114.41
169.39
11.61
15.88
21.99
15.33
COSTO DIRECTO
3,117,273.73
203.65
3,780,619.11
344.72
4,483,430.81
365.07
5,297,872.29
357.55
155,863.69
155,863.69
21.48
44.71
302,449.53
189,030.96
27.58
43.99
448343.081
358674.4648
29.21
45.29
370851.06
423829.7829
20.83
43.38
3,429,001.10
224.01
4,272,099.59
345.39
5,290,448.36
301.1201035
6,092,553.13
388.1754308
TOTAL
15,307.28
AREA TECHADA(M2)
12,369.00
17569.23
15695.36