Professional Documents
Culture Documents
SAFETY
Complacency and poor working practices could lead to serious incidents in the Asia region, says Joe Eades
HAVE, over the course of my career working in the process industries, seen evidence of growing complacency in safety culture and a general lack of understanding of process safety guidelines. This is exacerbated by ever-present financial pressures to reduce costs, resulting in decreased spending on safety and training. This has undoubtedly led to many incidents over the years throughout the world. Often these have happened within companies and countries previously thought to have excellent safety records and an effective approach to safety. But many of these incidents have a strangely familiar similarity to them. As an example, while working in Asia, Ive seen some routine work practices that are becoming commonplace in the region. If we ignore them, these practices will undoubtedly lead to more incidents and possibly major events. These practices include pneumatic testing of process systems, a copy-and-paste approach to design, and a vendor-knows-best mentality. These are sometimes done with little or no understanding of the underlying process and without due assessment of the risks. Any of them, and many more like it, could potentially lead to a significant incident in the Asia region. Just because it hasnt happened yet, it doesnt mean it wont.
could it?
26 www.tcetoday.com november 2012
pneumatic testing
As a young engineer in Europe I was taught that hydro-testing is the preferred, safe practice for investigating leaks in piping networks. By contrast, the alternative pneumatic test (using compressed air) should only be used in exceptional circumstances, and only then with a detailed risk assessment to justify its use. However, when I started work in Asia I was shocked to discover that pneumatic testing is commonplace in construction in order to save time and money, with no regard for the hazard and potential consequences. Companies favour this method, but at what risk? Pneumatic testing is done at ambient conditions so does it really test the mechanical integrity of the system? It only tests to 110% of design pressure, compared with 150% for hydraulic testing (under BS5500). In hydraulic testing the weight of the water used is an additional load on the supports and system, which gives a higher degree of confidence that the main layer of protection from the hazard in the pipework prevents a loss of containment, both in normal operation and during any process deviation. In 2009, in Shanghai, a contractor was carrying out pneumatic testing for an LNG terminal, when a section of pipework blew out, nearly flattening the site due to the amount of stored energy in the system. This resulted in one worker being killed and injuries to a further 15. The asset loss was significant and the project was delayed by six months. Surely we should be using pneumatic testing by exception, not the norm? Just because few incidents have yet occurred, people are becoming increasingly complacent about its use. Long term, it also raises the issue of effects on the integrity of the plant that is meant to contain the hazards and prevent a loss of containment.
In many cases in Asia, many of the concept design and processes were performed in Europe or the US and the detailed design carried out locally. If thats the case, how confident would you be that the design has been challenged adequately?
design by copy-and-paste
How often have you heard the phrase we copied this design from one in... and therefore we dont need to do any new engineering design or risk assessment for it? Another example could be for a technical transfer of a process or a design but not taking into account the impact of the changes in base assumptions. In many cases in Asia, many of the concept design and processes were performed in Europe or the US and the detailed design carried out locally. If thats the case, how confident
(Pictured left) Reactor vessel failure at the UKs Stanlow oil refinery (1990) an example of why, in Asia, pneumatic testing should be the exception, not the rule november 2012 www.tcetoday.com 27
tce
SAFETY
As a profession each of us has a responsibility to build up a broad skill set, to voice our concerns and document them. If you dont it could be your reputation on the line if something does go wrong later.
28
hundreds or thousands of times more than the initial saving or worse still, a fatality. Quite often, operational and commissioning personnel are not involved in the initial design process, and therefore the design team does not have a good grasp of the process and the hazards. In most cases equipment manufacturers are not process experts but experts in mechanical equipment fabrication, sometimes with a controls E&I (electrical and instrumentation) background. Users are happy to supply a vague or poorly-defined URS (user requirements specification), to put the onus on the equipment supplier to offer solutions (based on best practice) solutions. What the user fails to understand is that it is their responsibility to define the process and limitations of the process since the equipment supplier will offer as close to a standard design as possible. In many cases this design may not be fit for purpose or even suitable for the process. In Fayetteville, US in 1991, an operational team worked directly with a vendor to install and commission a thermal oxidiser, to abate vent emissions, from a process plant. On a hot day, the emissions from the plant were higher than the equipment was designed for and it exploded. There were lapses on both sides and the vendor had not previously tested its interlocks adequately. Something that never ceases to amaze me is how many vendors standard commissioning documentation today is still totally inadequate, quite often a 12 page checklist that does not actually test more than that the loops work rather than challenging the functionality, or the safety systems, trips and interlocks. Can a vendor prove that they really carried out their duty of care or is it a deliberate strategy to make
a profit by coming back (as a variation) to fix the non-functioning plant after a client signs it off as passed? Customers have a clear responsibility to monitor and approve the documentation any supplier offers before carrying out the work.
Joe Eades (joe.eades@ispahan.com) is the managing director of Ispahan Group and vice chairman of the IChemE board in Singapore