Professional Documents
Culture Documents
21
243
244
Chapter 21
complete shutdowns or projects in the shortest time period, the more essential application of network analysis becomes.
245
agers can remain abreast of overall project progress and take necessary action as soon as possible to protect Earliest Completion Time and stay within project budget. Accordingly, CPM facilitates project tracking by providing alarms when:
246
Chapter 21
@ ,
__
8
149 149
event. They cannot originate from the middle of another activity. When this situation seems to occur, most likely the envisioned activity is really two activities with an additional event separating them. The better activities are defined, the easier they are to manage. Each activity should represent only one resource-some portion (one or more individuals) of a specific crew responsible to one supervisor).
0 Earliest Event Time (ET) is the earliest day of the project that
all activities leading into the event can be completed. All activities leading into the same event must be checked in order to determine the latest to complete. Add activity duration to Earliest Event Time of the preceding event (Tail Event) to determine the earliest day of the project that each activity can be completed. The greatest result determines Earliest Event Time for the event in question. Work the network left to right, in numerical sequence. Check Event 2 before Event 3, before Event 4,etc. We will use Event 6 to clarify this explanation:
Activity
Tail Event ET 35 20 26
Duration
+ + +
16 12 18
=
=
51 32 44
51
0 Latest Event Time (LT) is the latest point (day) of the project
that an event can be achieved without extending duration and completion of the overall project. Latest Event Times are determined by working the network backward (right to left) in much the same fashion as it was worked forward (left to right) to determine Earliest Event Times. There is no need to calculate LT for events on the critical path because there is no float. Therefore ET and LT are equal. Just post the same number in the right-hand quadrant. All LTs off the critical path must be calculated. Work in descending order of event numbers. Again check all paths back to each event. Subtract activity duration from the Latest Event Time of the succeeding event. The smallest result determines Latest Event Time. If the result for an activity yielding a larger number were to be posted, there would be at least one path through which completion could not be reached on schedule. Project duration would be extended. We will use Event 7 for clarification:
248
Chapter 21
Tail Event ET
72
11 14
= =
99
Float is the amount of delay that can be absorbed at each event before it adversely impacts subsequent activities, events, and possibly project completion date. CPM defines three forms of float, allowing project managers and planners to quickly assess the impact of project delays: Total Float is the amount of delay in activity start or increase in activity duration that can be absorbed without delaying project completion. Free Float is the amount of delay in activity start or increase in activity duration that can be absorbed without impinging upon the timely start of any immediate successor activity. This would occur if the delayed activity caused Earliest Event Time to be missed. Independent Float is the amount of delay in activity start or the increase in activity duration that can be absorbed without diminishing float available to any other activity (predecessor or successor).
Again, there is no Float on the Critical Path. Earliest and Latest Event Times are equal for all Events on the Critical Path.
249
-5-r
......
Figure 21.2 Compinted Bar Chart Schedule and work Force Leveling Chart