2.0 January 2011 January 2013 State Procurement Board 8226 5001
Contents
Overview ..............................................................................................................3 Object of the Act...................................................................................................3 What is Life Cycle Costing? ....................................................................................3 Benefits of Utilising Life Cycle Costing ....................................................................3 When to Undertake Life Cycle Costing ....................................................................4 How to Undertake Life Cycle Costing ......................................................................4 Limitations of Life Cycle Costing.............................................................................6 Further Information and Resources ........................................................................7 Related Policies and Guidelines ..............................................................................7 Attachment 1 Example of a Life Cycle Costing Analysis .........................................8
Page 2 of 9
Overview
This guideline provides information and practical advice in relation to the application of life cycle costing (LCC) to the procurement of goods (and related services). In reading this guideline, procurement practitioners will gain an understanding of: what LCC is; the impact of LCC on procurement decisions; the benefits of applying LCC; when and how to undertake LCC analysis; and the limitations of applying the LCC methodology.
The Australasian Procurement and Construction Council (APCC) also identifies and promotes the benefits of undertaking LCC when procuring goods and related services. The APCC notes in the context of value for money, products and services which have lower environmental impacts across their life cycle compared with competing products and services should be preferred. Encouraging a life cycle (or total cost of ownership or whole of life) costing approach to quantify the total cost of procuring products complements the objectives of this Life Cycle Costing Guideline.
Each procurement or project will have its own unique features and level of complexity and each LCC plan should be customised to suit the particular circumstances of the procurement. The Australian/New Zealand Standard Life Cycle Costing An Application Guide (AS/NZS 4536:1999) outlines this process in more detail. Public authorities are required to maintain appropriate documentation to support evaluation decisions made utilising LCC analysis. 1. Develop a Plan The first step in undertaking LCC analysis is to develop an LCC plan, commensurate with the value and complexity of the goods being procured. This LCC plan will, amongst other considerations: define the expected outputs and outcomes of the proposed LCC analysis; delineate the scope of the proposed LCC analysis; and identify any underlying conditions, assumptions, limitations or constraints.
Page 4 of 9
2. Identify the cost elements This guideline adopts the use of five cost categories, each comprising individual cost elements. These cost categories are: Acquisition costs the initial cost of obtaining the completed goods, including the purchase price, design, planning, freight, installation and initial training costs; Lifetime operating costs the costs (excluding maintenance costs) incurred during the life of the goods, including energy consumption, safety, contract and supplier management, and insurance; Lifetime maintenance costs the costs incurred in maintaining the dependability of the goods during their life, including performance management, consumables, spare parts, minor repairs or labour; Disposal costs the costs of removing or disposing of a good after its economic life has ended, including costs to decommission, dismantle, transport, dump or transition; and Residual value the expected value of the good at the time it is sold or disposed of.
Each cost category contains a number of individual cost elements. Cost elements influence or determine the total costs over the life of the goods. These elements can be identified and estimated from sources including an analysis of historic data or previous usage patterns, the opinion and advice of experts or industry sources, or advice and data from manufacturers or suppliers. Each cost element must be clearly defined, with an estimated dollar value, for a defined number of years in which the costs are expected to occur. The amount of time spent on estimating the cost and frequency should be commensurate with the size, risk and complexity of the proposed procurement. When identifying the cost elements, anticipated costs relating to the procurement must be included, such as any automatic cost of living increases or indexed costs that potentially impact on the cost of the procurement over its life. For example, if the maintenance costs for a particular procurement are scheduled to increase by a predetermined 5% per annum, this should be reflected in the cost structure. 3. Create a cost structure Once all key cost elements have been identified against each cost category, they can be placed into an LCC structure. An example LCC structure, for the purchase of a new hot water unit, is provided as Attachment 1. In this example, two competing hot water units are being considered, Option A and Option B. This example demonstrates the principles involved in establishing a cost structure. It is recognised that actual procurements and projects are often more complex than illustrated in the example and that the structure may need to be customised to suit the particular procurement being considered.
Page 5 of 9
4. Discount the future costs Procurement related costs are generally incurred over the defined life of the goods (e.g. 7 years). While the majority of acquisition costs are generally incurred in year 0, operating and maintenance costs usually extend into the future. In the example provided in Attachment 1, the purchase price and installation costs are included as an initial one off cost, with other costs, such as service costs and energy consumption, occurring annually until the end of the estimated life of the goods. In general, a dollar spent in the future is worth less than a dollar spent now. Discounting these anticipated future costs requires the application of an appropriate discount rate (eg 10%) and enables all costs to be reflected back to their present value (known as Net Present Value or NPV). Discounting future costs to an NPV allows meaningful comparison of competing purchase options with different future cost profiles. As a rule of thumb, the discount rate is usually a combination of the current long-term expected interest rate minus the current long term expected inflation rate. However, it is important that specialist financial advice be sought before a particular discount rate is adopted. The relevant agency assigned Account Manager from the Finance Branch, Department of Treasury and Finance can provide an indication of the appropriate discount rate applicable for the period being considered. The discount rate used for the purposes of illustrating the case study in Attachment 1 is 10%. Each cost from year one to six has been discounted according to the number of years that will have elapsed since year 0. See Attachment 1 for a description of how this is calculated. As indicated by comparing Option A and B, the cost structure and the effect of discounting enables a meaningful comparison between the two options to be made, regardless of the varying costs. In summary, the example shows that although the initial purchase price of Option A is less than Option B, taking into account the total life cycle costs indicates that Option B presents greater value for money. For the purpose of approving procurement acquisition plans and purchase recommendations (including submissions to the Board), the actual proposed expenditure of the procurement (including the value of any extension options) is to be adopted, not the NPV. The scope of this guideline does not preclude consideration of more complex evaluation methodologies, such as, for example, sensitivity analysis and Equivalent Annualised Value (EAV). The Australian/New Zealand Standard Life Cycle Costing An Application Guide (AS/NZS 4536:1999) outlines these options in greater detail and is a useful supplement to this guideline, especially when undertaking LCC analysis for more complex procurements.
Page 6 of 9
The use of objective research, historical data, and the opinions of relevant experts, including industry sources, manufacturers and other users, can assist in minimising uncertainty and risk, providing more accuracy in the costs identified. Undertaking an LCC analysis may involve considerable time and effort and analysis should be commensurate with the nature and value of the procurement, so that the benefits outweigh the costs involved. It is also important that the identified costs for each year of the cycle be matched to the budget provided before any particular option is chosen. In some cases, different options will have budgeting implications beyond the initial purchase price. These must be considered before a supplier is chosen and recommended for approval.
State Procurement Board Secretariat Department of Treasury and Finance ph: (08) 8226 5001 fax: (08) 8226 5667 email: stateprocurementboard@sa.gov.au www.spb.sa.gov.au
Page 7 of 9
Hot Water System Option A Discount Rate 10% (#1) Multiplier Rate (#2)
1 Acquisition Costs Purchase Price Installation 2 Lifetime Maintenance Costs Annual service Programmed maintenance 3 Lifetime Operating Costs Energy Consumption 4 Disposal Costs Removal of Unit 5 Income from Residual Value (#3) Scrap metal value only TOTALS Net Present Value (1) 107
(#5)
1.0 45 5 45 5
0.91
0.83
0.75
0.68
0.62
0.56
28 6
4 6
14 10
2 10
(1) 56
(#4)
6
(#4)
12
(#4)
6
(#4)
6
(#4)
6
(#4)
15
(#4)
92.12
(#7)
56
(#6)
5.46
(#6)
9.96
(#6)
4.5
(#6)
4.08
(#6)
3.72
(#6)
8.4
(#6)
#1 A discount rate of 10% has been used for this example. Advice must be sought from the Finance Branch, Department of Treasury and Finance to determine the appropriate discount rate for each procurement. #2 Year 0s multiplier rate is 1. Each subsequent years multiplier rate can be calculated as follows: f = 1/(1+dr)^y where: dr = the discount rate per year (expressed as a decimal percentage) ^y = raised to the power of the year being considered (year 1=1, year 2=2 etc) #3 The residual value amount is treated as a negative for the purpose of calculating the total. #4 Individual totals are calculated by adding up the amounts for each item listed in the row above. #5 The total is calculated by adding up each of the individual yearly totals. This total can be validated by adding up the amounts for each item listed in the row above. #6 Individual NPV amounts are calculated by multiplying the individual year total by the multiplier rate (e.g. 12 x 0.83 = 9.96). #7 The NPV total is calculated by adding up each of the individual yearly totals.
Page 8 of 9
Totals ($000)
Yr 0
Yr 1
Yr 2
Yr 3
Yr 4
Yr 5
Yr 6
Hot Water System Option B Discount Rate 10% (#1) Multiplier Rate (#2)
1 Acquisition Costs Purchase Price Installation 2 Lifetime Maintenance Costs Annual service Programmed maintenance 3 Lifetime Operating Costs Energy Consumption 4 Disposal Costs Removal of Unit 5 Income from Residual Value (#3) Scrap metal value only TOTALS Net Present Value (1) 96
(#5)
1.0
58 10 58 10
0.91
0.83
0.75
0.68
0.62
0.56
14 3
2 3
7 5
1 5
(1) 71
(#4)
3
(#4)
6
(#4)
3
(#4)
3
(#4)
3
(#4)
7
(#4)
88.78
(#7)
71
(#6)
2.73
(#6)
4.98
(#6)
2.25
(#6)
2.04
(#6)
1.86
(#6)
3.92
(#6)
Page 9 of 9