EHS MINUTES OF MEETING

Project Name: KAUST Research Park Utility Plants Prepared By: Richard Wang Purpose of Meeting: Weekly Meeting of HSE Department ATTENDEES CNCEC Richard Wang Leon Liang Md. Anwar Hossain Mojumder Dawood naveed Rui Bao None Description of Project: EPC Date of Meeting: 18th-Oct-2012 Date of Report: Location of Meeting: Site Office OWNER OTHERS None Distribution: Attendees Plus: Serial. No: CNCECKAUST-HSE-MOM-0005

ITEM

DESCRIPTION

ACTION BY

DUE DATE

STATUS

Summary of this week from 11st to 17th Oct


1. Completed TBT 6 time. 2. Completed DTRA 6 time. 3. Completed HSE Inspection 2 times. 3.1 Villa safety audit on 14th Oct, 2012. 3.2 Site inspection on 16th Oct, 2012. 4. Completed staff internal ID: 1 pcs (1 management staff) Total 90 staffs ID completed (including 48 construction staff and 42 management staff) 5. Hold HSE Training 3 times. 5.1 Completed orientation course for 3 new comers (Vehicle Drivers) on 13rd Oct 2012.

MOM-0005

Page 1

5.2 Completed orientation course for 1 vehicle drivers on 17th Oct 2012.

5.3 Held internal training for HSE staff on 13rd Oct 2012.

MOM-0005

Page 2

Work plan for next week form 18th to 24th Oct.


9 Prepare vehicle sticker of CNCEC. The sample of vehicle sticker has been submitted SAPMT for review. Pepare carry out color code for October with red color. The store office who name is Fu Guiliang, and his contact phone No. is 0515142538 (54) Electrical Tool/Equipment check by Electric Engineer on 18th Oct, 2012. Camp /Villa Track safety issues improvement. We will inspection to Villa next Sunday. The safety inspection for Villa has been finished by Richard Wang on 1st Oct, detail inspection form and corrective action please see appendix 1. Human Resource & Training Information We will hold internal training for all safety staff by Anwar next week. Completed camp evacuation chart Found fire-fighting emergency response team for camp. The team members minimum requirement 6 person, and then, well give him training and exercise. Team leader: Ma Laiming (Admin) Team member: Zhou Liangzhong (Chief cook) Shi Lei (Cook) Lu Changhui (Cook) He Guangming (Labor) MOM-0005 Anwar Richard Wang Sun Bo Started after SAPMT approved. 22nd Oct. Open

10

11

Richard Wang Daud

Electrician will inspection on this afternoon(1 1st Oct)

On-going

12

Anwar

On-going

13

Anwar/Rich ard Wang Ma Laiming Richard Wang

10th Oct

On-going

Page 3

Sun Bo 14

(Supervisor)

As per construction information from PM, we may start the backfilling for the 3 buildings next week, we need ready everything see below for make sure backfilling start in time. Orientation for drivers. Certification confirmation both drivers and vehicles. Prepared DTRA & JHA for backfilling and transport. Training for construction supervisor or engineers for DTRA All information about backfilling provide by Admin & construction department. Backfilling for operation room of RO will be start from 20th Oct (the related information sourced Mr.Faiyaz).

HSE Dprt.

As per construction schedule

Concern: The 3 drive licenses whom operation heavy


equipment for backfilling con not provide to HSE department including 1 roller, 1 loader and 1 JCB. 15 HSE Department staff task

MOM-0005

Page 4