sibin raj 195 posts since 25 Sep, 2010 PR creation date for Availability control in ME51N 12 Dec, 2012 1:37 PM

Hi Experts, How to make budget check for an order based on creation date of PR in ME51N. Now the check is on delivery date. If the delivery date is in next year, we are getting budget exceeded error since no budget is maintained for that order. We have activated availability control in our system. Now system is checking Delivery date year for checking budget. How to make PR creation date as validation check?

Regards, Sibin

sibin raj 195 posts since 25 Sep, 2010 Re: PR creation date for Availability control in ME51N 24 Dec, 2012 1:07 PM

Hi All, Can any one explain the link between KO24 and ME51N link? If we are not maintaining budget in KO24, we are getting ths budget exeec error. Can we make this error validation based on PR creation date rather than PR Delivery date? At present system is checking delivery date with budget maintained in internal order.

Regards, Sibin

sibin raj 195 posts since 25 Sep, 2010 Re: PR creation date for Availability control in ME51N 25 Dec, 2012 8:44 AM

Generated by Jive on 2013-03-20+01:00 1

PR creation date for Availability...

Can any one tell me which is the user exit being called at the time of budget check for internal orders? Can we change the condition in program? We want to make validation based on PR creation date instead of PR Delivery date?

Regards, Sibin

Jrgen L 25,853 posts since 1 Sep, 2005 Re: PR creation date for Availability control in ME51N 25 Dec, 2012 10:07 AM

moved from SAP ERP - Logistics Materials Management (SAP MM) to SAP ERP Financials - Controlling

especially the last 2 questions are not MM related. And the experts for KO24 can be found in the FICO forums.

Ajay Maheshwari - Freelance SAP Trainer 8,737 posts since 21 Mar, 2008 Re: PR creation date for Availability control in ME51N 26 Dec, 2012 4:52 AM

Hi

I am not sure if there exists any config for the same.. Ideally, the budget that did not get consumed in current year must be carried fwd to the next year... You must execute KOCO and KOCF at year end

br, Ajay M

sibin raj 195 posts since 25 Sep, 2010 Re: PR creation date for Availability control in ME51N 26 Dec, 2012 6:02 AM

Hi Ajay,

Generated by Jive on 2013-03-20+01:00 2

PR creation date for Availability...

At month end we are carry forwarding the budget. But at the start of december, if we raise a PR which is supposed to be delivered in next year, this budget error pop up is getting displayed. Is it a standard functionality to check budget control based on PR delivery date? Can we change it to PR creation date?

Regards, Sibin

venkat K 244 posts since 6 Feb, 2008 Re: PR creation date for Availability control in ME51N 26 Dec, 2012 5:40 AM

Hi Sibin,

I think in Internal Oreder Availability control it is not possible however if go for funds management it is possible.

Regards,

Venkat