Professional Documents
Culture Documents
1.1 General
The unprecedented growth of personalized vehicles and the unplanned road infrastructure have made the provision for parking an important aspect of transportation planning. Since most of the places are frequented by public and busy with floating population, the demand for parking is very high. On-Street parking is observed on all roads. This has reduced the capacity of the carriageway and endangering pedestrians and motorists alike. The frontage of almost all the roads has been convertedinto commercial land use without taking into account the demand for parking of vehicles. There is no planned parking space available.
CHAPTER-II INTRODUCTION
2.1 General:
The multi-storey car parking is planned for parking 256 cars. A place which is near airport having good transport facilities is chosen. The basic provisions for parking area, fire safety, security room, workshop, electric room, toilet and other common areas are provided. The proposed site for construction is near Coimbatore airport. This s 1km from national highway. The site is clear and ready for construction.
2.4 Planning:
The multi-storey car parking is planned for parking 256 cars. The provision for parking area, workshop, electric room, fire safety, security room and other required areas necessary for standard construction are provided. We have planned to provide rooms for drivers working here. In this project we have planned to provide Hydraulic Jack for lifting of cars to different floors. The project is planned to construct in an area for about 1.63 acres, with plot area 2 acres and location is near Coimbatore airport. Here we have planned to provide parking lot of size 5.5m x 2.5m, 2 lift of size 1.83m x 1.83m per each lift, 4 hydraulic jack of size 6m x 5.5m per each jack, a workshop room of sie 6m x 12m, a fire safety room of size 6m x 3m, a electric room of size 6m x 10m, 2 toilet rooms of size 4m x 7m per each room, 2 security rooms of size 3m x 3m per each room, a canteen of size 6m x 6m, a rest room of size 6m x 8m a office room of size 6m x 4m and a store room of size 6m x 7m. The parking area is alone planned to elevate for 3 storeys (ie) G + 3. Others structures are planned to built only in ground floor.
3.2.3.2 Drop
The drop in each direction shall have a length of not less than one third of panel length in that direction.
Limiting moment of resistance factor for singly reinforced resistance rectangular section
STEP 1 : CLEAR SPAN The flat slab shall be designed without drop panels and the supporting column shall have column head of 400mm height with 45 inclination and additional vertical height of 400mm. As per IS 456-1978, the column of circular section shall be treated as square section having the same cross sectional area. Therefore let a be the size of the square column.
=1.06m
=7.69m STEP 2 : ESTIMATED THICKNESS OF THE FLAT SLAB The flat slab remains continuous over minimum of three span (direct design method) For slabs without drops:
Where
For HYSD steel of Fe415 grade =0.96% =1.4 Estimated effective depth
Let the overall estimated thickness be 200mm (more than 125mm minimum thickness specified
STEP 3 : ESTIMATED LOADS (A) Characteristic Dead Load It consists of the weight of finishing surface plus the self weight of the slab. Weight of finishing surface Self weight of slab =1k N/ = =5k N/ Total Wd (B) Characteristic live Load Live load Total Load=wd + w1 =7.5k N/ =6 + 7.5 =13.5k N/ (C) Factored (design) load in the panel Wfd =1.5 x (wd + w1) =1.5 x 13.5
=20.25k N/
=6k N/
STEP 4 : WIDTH OF THE STRIPS FOR INTERIOR PANEL (A) Width of strip along AB (long span) Span AB, l1=10m Span BC, l2 =8.75m Width of column strip 0.25 l2 <0.25 l1 = 0.25 x 8.75 =2.18m (adopted) = 0.25 x 10 =2.5m
Width of strip 0.25 l2 >0.25 l1 = 0.25 x 10 =2.5m = 0.25 x 8.75 =2.18m (adopted)
STEP 5 : FACTRED (DESIGN) MOMENT FOR SPAN (A) Width of strip along AB (long span) l1=10m, ll-n = 8.94m, l2 = 8.75m Total design load over an area, l2 x ll-n WFd WFd = 1.5 (Wd + W1) x l2 x ll-n = 20.25 x 8.75 x 8.94 = 1584 kN Total factored design moment along the direction AB Mo.AB = = =1770.12 kNm
(B) Total design moment, Mo along BC (short span) l1=8.75, ll-n = 7.69, l2 = 10m Total design load over an area, l2 x l1-n WFd WFd = 1.5 (Wd + W1) x l2 x ll-n = 20.25 x 10 x 7.69 = 1557.22 kN Total factored design moment along the direction BC Mo.AB = = =1496.87 kNm STEP 6 : NEGATIVE AND POSITIVE DESIGN MOMENTS In an interior span, the total design moment Mo is distributed in the following proportions in each direction (A) Distribution of total design moment MO.AB Negative design moment, Mn.AB Mn.AB Positive design moment, MP.AB Mp.AB = 0.35 MO.AB = 0.35 x 1770.12 = 619.54 kNm (B) Distribution of total design moment MO.BC = 0.65 MO.AB = 0.65 x 1770.12 = 1150.57 kNm
Negative design moment, Mn.BC Mn.BC Positive design moment, MP. BC Mp.BC = 0.35 MO.BC = 0.35 x 1496.87 = 523.90 kNm STEP 7 : EFFECTS OF PATTERN OF LOADING The effects of pattern of loading for negative and positive BM maybe seen before distribution of these Moments across the panel width. = 0.65 MO.BC = 0.65 x 1496.87 = 972.96 kNm
The ratio of
exceeds 0.5
(A) For the distribution along AB The ratio of flexural stiffness of the columns above and below the slab to the flexural stiffness of the Slabs at a joint in the direction along AB.
(I) Stiffness coefficient for slab Size of equivalent square column (diameter of column is 1200mm)
c/c distance between the columns c1 =[ = 1063mm Along AB, l1=10m Along BC, l2=8.75m C1/l1 =1.06/10 =0.106 C2/l2 =1.06/8.75 =0.121 As per SP24 1983, stiffness factor for slab without drop panel
(II) Stiffness coefficient for column Length of column section a = 100mm = 0.1m Depth of 45 degree capital (below the soffit of the slab) b1 = 440mm
= 0.44m lc = 2.8 + 0.1 + 0.1 = 3m a/lc b1/lc = 0.1/3 =0.44/3 =0.146 Column stiffness coeffients for columns with 45 degree tapered capital for above ratios For upper (capital) end, Kc For lower (base) end, Kc = 4.964 = 5.474
= 0.315 Ec kNm
x (1.2)4
= 0.285 Ec kNm
= 123.05
= 0.875
=1.25 From table 9.1 (as per IS 456 1978) by interpolation c min c min is less than c = 123.05 Therefore, the correction for pattern of loading in the direction AB is not necessary. (A) For the direction along BC =0.7
The ratio of flexural stiffness of the columns above and below the slab to the flexural stiffness of the slab at a joint in the direction along is:
1. Stiffness coefficient for slab. Size of equivalent square column (diameter of column is 1200mm) c1 =1063mm c/c distance between columns Along BC, l1 = 8.75m Along AB, l2 = 10m =[
= 0.121
= 0.106 From table 9.2, stiffness factor for the slab without drop panel (as per SP 24 : 1983) K Ks Ks = 4.26 = x x (0.2)3
(ii) Stiffness coefficient for column Length of column section (considered rigid) A = 100mm =0.1m Depth of 45 capital (below the soffit of slab) b1 lc = 440mm = 2.8 + 0.1 + 0.1 = 3m
= 0.033 ~ 0.35
= 0.146 From 9.5 table, column stiffness coefficient for colums with 45 tapered capital For upper (capital) end for above ratios Kc For lower (base) end. Kc = 4.964 = 5.474
Kc Kc
x (1.2)4
= 0.315 Ec kNm
= 0.285 Ec kNm
= 92.44
= 0.875
=1.25 From table 9.1 (as per IS 456 1978) by interp c min = 0.9 c min =0.9 less than c = 89.98 The correction for pattern of loading in the direction BC is not needed STEP 8: DISTRIBUTION OF BM ACROSS THE PANEL WIDTH (A) Across the strip of span AB (i) Negative moment at an interior support (a) Column strip : 75% of the total ve moment in the panel at this support is resisted by the column strips. Therefore, the moment resisted by each column strip (Since MnAB=1150.57 kNm) 1/2 Mnc = x 0.75 MnAB = x 0.75 x 1150.57 = 431.46 kNm (b) Middle strip : The ve moment resisted by the middle strip Mnm = 0.25 Mnm = 0.25 x 1150.57 = 287.64 kNm Check : ( 431.46 + 287.64 + 431.46 ) = 1150.56 kNm (ii) Positive moment at an interior support
(a)Column Strips : 60% of total +ve moment in the panel is resisted by the column strips. Therefore, the moment resisted by each column strips Mp.AB x Mp.c = 619.54 kNm
=
=(
= 185.86 kNm (b) Middle strips : The +ve moment resisted by the middle strips
Mpm
=0.40
Mp.AB
= 0.40 x 619.54 = 247.816 kNm Check : 185.86 + 247.81 + 185.86 (B) Across the strips of span BC (i) ve moment at an interior suppor Column strips : 75% of total -ve moment in the panel at this support is resisted by the column strips. Therefore, the moment resisted by each column strip (since Mn.BC = 972.96 kNm) 1/2 Mnc = x 0.75 MnBC = x 0.75 x 972.96 = 619.53 kNm
= 364.86 kNm (c) Middle strips : The -ve moment resisted by the middle strips Mnm
=0.25
Mn. BC
= 0.25 x 972.96 = 247.24 kNm Check : 364.86+ 243.24 + 364.86 = 972.96 kNm
(ii) Positive moment at an interior support. (a) Column strips : 60% of total positive moment in the panel is by the column strips. Therefore, the moment resisted by each column strip (since Mn.BC = 972.96 kNm) MpBC 1/2 Mpc = 523.90 kNm = x 0.60 x MnBC = x 0.60 x 523.90 = 157.57 kNm (b) Middle strips : The +ve moment resisted by the middle strips. Mp.m
=0.40
Mp. BC
= 0.40 x 523.90 = 209.56 kNm Check : 157.17+ 209.56 + 157.17 STEP 9: STRIP OF SPAN AB A. Strip of span AB (i) Negative moment = 523.90 kNm
(a) Column strips : the width of column strip of the interior panel is 2.18m Therefore, the moment per meter width Mnc/meter = = 197.91kNm/m (b) Middle strips : the width of middle strip of the interior panel is 4.39m Therefore, the moment per meter width Mnm/meter = = 65.52 kNm/m (ii) Positive moment (a) Column strips : the width of column strip of the interior panel is 2.18m Therefore, the moment per meter width Mnc/meter = = 85.25kNm/m (b) Middle strips : the width of middle strip of the interior panel is 4.39m Therefore, the moment per meter width Mnm/meter = = 56.45 kNm/m (A) Strip of span BC
(i) Negative moment (a) column strip : width = 2.18m Therefore, the moment per meter width Mnm/meter = = 168.36 kNm/m Middle strip : width = 5.64m Therefore, the moment per meter width Mnm/meter = = 43.12 kNm/m (ii) Positive moment (a) Column strips : Width = 2.18m Therefore, the moment per meter width Mnm/meter = = 37.15 kNm/m
STEP 10: EFFECTIVE DEPTH OF FLAT SLAB The absolute maximum factored B.M out of eight value of the step 9 is 197.91kNm/m The effective depth of the flat slab 0.36 fck x x (1-0.42 x ) bd2 = MFD
x1000 x d2] = 197.91 x 10 3456 (1-0.2016)d2 3456d2 696.72d2 2759.28d2 d Assume d = 275mm Let the effective cover be 25mm Therefore, overall thickness of slab D=300mm STEP 11 : SLAB REINFORCEMENT The spacing of bars in flat slab shall not exceed 2 times the slab thickness 2x300 = 600mm2 = 197.91 x 10 =197.91 x 106 =197.91 x 106 =267.81mm
Therefore, provide 12mm diameter HYSD steel bars shall be provided Ast = = 113.04mm2 (A) Reinforcement along the span AB (i) Negative moment reinforcement (a) Column strips 0.87 fy Ast d (1) = MFD ) =197.91 x 106 =197.91 x 106
= 46.25mm Therefore,provide bars 12 nos @ 100mm spacing at top (b) Middle strips 0.87 fy Ast d (1) = MFD ) =65.52 x 106 =0 =696.57mm2 = x 1000
x 1000
= 162.28mm Therefore,provide bars 12 nos @ 160mm spacing at top (c) Column strips 0.87 fy Ast d (1) = MFD ) =85.25 x 106
(d) Middle strips 0.87 fy Ast d (1) = MFD ) =56.45 x 106 =0 =595.34mm2 = x 1000
x 1000
= 189.87mm Therefore,provide bars 12 nos @ 185mm spacing at bottom (B) Reinforcement along the span BC (ii) Negative moment reinforcement (e) Column strips 0.87 fy Ast d (1) = MFD ) =167.36 x 106 =197.91 x 106 =1982.25mm2 = = x 1000 x 1000
x 1000
= 251.43mm Therefore,provide bars 12 nos @ 250mm spacing at bottom (a) Column strips 0.87 fy Ast d (1) = MFD ) =72.09 x 106 =0 =770.99mm2 = = x 1000 x 1000
(b) Middle strips 0.87 fy Ast d (1) = MFD ) =37.15 x 106 =0 =385.40mm2
x 1000
x 1000
= 293.29mm Therefore,provide bars 12 nos @ 250mm spacing at bottom For flat slab without drops, the reinforcement bars in the column strips and middle strips shall be kept straight, the projection of negative reinforcement in to the span from the column shall be as follows (A) (i) Coloumn Strips Along AB
(a) 50% at top Projection = half the size of square column + 0.31l-n =( x 1.06 + (0.3 x 8.94)) =3.21m (b) 50% at top Projection =( x 1.06 + (0.2 x 8.94)) =3.21m (ii) Middle Strips : (100% at top)
(c) 50% at top Projection = half the size of square column support + 0.221l-n =( x 1.06 + (0.22 x 8.94)) =2.94m (B) Along BC
(i) Column strips: (a) 50% at top Projection = half the size of square column support + 0.31l-n =( x 1.06 + (0.22 x 7.69)) =2.83m (b)50% at top Projection =( x 1.06 + (0.2 x 7.69)) =2.06m (ii) Middle Strips : (100% at top) (d) 50% at top Projection = half the size of square column support + 0.221l-n =( x 1.06 + (0.22 x 7.69)) =2.22m
STEP 12 : SHEAR IN FLAT SLABS The diameter of column head is 2000mm and the effective depth of flat slab, d is 275mm. The diameter of critical section for two way round the column head (DE+ = (2000+ = 2275mm Peripheral distance bo factored share force at critical section = x 2.275 =7.143m )
= 1.5 (Wd + W1) (l . l2 (DE + d)2) = 1.5 (6 + 7.5) (10 x 8.75 (2.275)2) = 1689.60KN
= v = = 0.8601 N/mm2 Or permissible shear stress The grade of concrete is M20. The permissible shear stress in flat slab in concrete (limit state method of design) v v =0.25 (fck)1/2 =0.25 (20)1/2 = 1.118 N/mm2 When the shear reinforcement is not provided the nominal shear stress calculated at the critical section shall not exceed KsTc Ks c Ks KsTc = (0.5 + c) and not greater than 1.0 = (1.00 for circular column = 1.0 = 1 x 1.118 =1.118 N/mm2 v = 0.8601 N/mm2 not greater than (KsTc=1.118 N/mm2) Therefore Stisfiled
SIDE RATIO:
Side ratio, = = 2 2m
Hence the slab is to be designed as two way slab value = 32 = = = 156.25mm Adopt depth Effective cover (d) Assume 10 mm dia bars Effective cover Overall depth (D) = 20+ x10=25mm = d + d = 150 + 25 = 175mm =150mm = 20mm
LOAD CALCULATION:
Self weight concrete = 0.175 x 1 x 25 x 1 = 4.375 kN/m2 Live Load Floor finish Total load (W) = 7.5 kN/m2 = 1 kN/m2 = 4.375 + 7.5 + 1 = 12.875 kN/m2 Factored load (Wu) = 12.875 x 1.5 = 19.31kN/m2 = L x B x density of
Two adjacent edges contines = = 1.97 x y no: 91) Mu (x) =0.09101 x 19.312 x 5.152 = 46.18kNm Mu (y) =0.047 x 19.312 x 5.152 = 24.07kNm = 0.09101 =0.047 (IS 456 : 2000, pg
24.07 x 106
= 426.98mm2
x 1000
= 79.5mm75mm
Sy
x 1000
EDGE STRIP
Ast(min) = = 0.12% of bd x 1000 x 150
DEPTH RATIO
Basic value value = 32 = = = 156.25mm Adopt depth Effective cover (d) =150mm = 20mm = 32
Assume 10 mm dia bars Effective cover Overall depth (D) = 20+ x10=25mm = d + d = 150 + 25 = 175mm
= 5.23m Effective length LOAD CALCULATION: Self weight concrete = 0.175 x 1 x 25 x 1 = 4.375 kN/m2 Live Load Floor finish Total load (W) = 7.5 kN/m2 = 1 kN/m2 = 4.375 + 7.5 + 1 = 12.875 kN/m2 = L x B x density of = 5.15m
Wu
Sx
= 97.31mm90mm
Sy
x 1000
= 197.1mm190mm Maximum permitted spacing: a) 3xd = 3 x 150 = 450mm b) 450mm Provide 10mm @ 90mm spacing
EDGE STRIP
Ast(min) = 0.12% of bd = x 1000 x 150
= 436.27mm400mm Maximum permitted spacing: c) 5xd = 5 x 150 = 750mm d) 450mm Provide 10mm @ 400mm c/c spacing
= 0.612 N/mm2 c(max) Hence shear is safe and design is ok = 2.8N/mm2 [table 20]
SIDE RATIO
Side ratio = =1.12m Hence the slab is to be designed as two way slab.
DEPTH RATIO:
Basic value Basic value Depth (d) = 32 = = = 273.43mm Adopt depth Effective cover (d) Effective cover Overall depth (D) =275mm = 20mm = 20+ x10=25mm = d + d = 275 + 25 = 300mm
LOAD CALCULATION:
Self weight concrete = 0.35 x 1 x 25 x 1 = 7.5 kN/m2 Live Load Floor finish Total load (W) = 7.5 kN/m2 = 1 kN/m2 = 7.5 + 7.5 + 1 = 16 kN/m2 Wu = 16 x 1.5 = 24 kN/m2 = L x B x density of
Mu (x)
Mu (y)
Sx Sy
= 66.62mm90mm = x 1000
= 98.37mm90mm Maximum permitted spacing: e) 3xd = 3 x 150 = 450mm f) 450mm Provide 10mm @ 90mm spacing
EDGE STRIP
Ast(min) = = 0.12% of bd x 1000 x 275
= 330mm
= 237.96mm200mm Maximum permitted spacing: g) 5xd = 5 x 150 = 750mm h) 450mm Provide 10mm @ 400mm c/c spacing
= 0.39N/mm2 K=1 [ for 300dmm depth) (IS 456:2000, page no : 72] % of steel = = = 0.4285 = 0.4285 (table no : 19, page no:85, IS 456 : 2000] cxk = 0.4285 x 1 = 0.4285 N/mm2 c(max) Hence v< c< k< c(max) Hence shear is safe and design is ok = 2.8N/mm2 [table 20] x 100 x100
CHAPTER-IV INTRODUCTION
4.1 General
Multi-storied buildings are usually constructed for offices, residential flats, hotels, hospitals,social centers etc. The framing of multi-stored building consists of colums and beams which supports roof and floor load. A multi-stored, Multi-planned frame is a complicated statically indeterminate structure. It consists of a number of beams and columns built monolithically, framing network. The doors and walls are supported on beams which transmit the load to the colums.A building frames is objected to both verticals as well as horizontal loads. The vertical loads consist of the dead weight of the structural components such as beams, slabs, columns, etc and live load. Structural behavior of the multi-storied buildings subjected to the lateral forces complex and highly indeterminate. There are three are three recognized types of joints between beams and columns, simper, semi rigid and rigid joints. Frames with flexible joints have no internal resistance against horizontal loads.
MF AB
=0
MF BA MF BC
MF CB
MFCD MFDC Table 4.3.1.1 Load and FEM: SL No MEMBER 1 2 BC CD LOAD (kN/m 37.5 37.5
=0 =0
Table 4.3.1.2 DISTRIBUTION FACTOR Joint B Member BA BC C CB CD K 0.308 E1 0.114 E1 0.114 E1 0.308 E1 0.422 E1 K D.F 0.729 0.270 0.270 0.729
0.422 E1
Table 4.3.1.3 DISTRIBUTION TABLE: Joing B BA D.F F.E.M 1ST distribution 0.729 0 174.41 BC 0.270 -239.25 64.59 C CB 0.270 239.25 -64.59 CD 0.729 0 -174.41
0 174.41
-32.29 -206.95
32.29 206.95
0 -174.41
RB + RC
MB=0 -Rc x 8.75 + 206.95 + 37.5 x 8.75 x 4.375 206.95 = 0 -8.75 Rc Rc RB + 164.0 RB MA=0 = -1435.57 = 164.0kN = 328.12kN
=0 = -53kN
Since RA + RB RA + 53 Therefore RA
SHEAR FORCE DIAGRAM:
=0 =0 = -53kN
MF AB MF BA MF BC
MF CB
MFCD MFDC
=0 =0
Table 4.3.1.1 Load and FEM: SL No MEMBER 1 2 BC CD LOAD (kN/m 24.4 24.4 FEM(kNm) -73.2 -73.2
Table 4.3.2.2 DISTRIBUTION FACTOR Joint B Member BA BC C CB CD K 0.34 E1 0.17 E1 0.17 E1 0.34 E1 0.51 E1 K D.F 0.67 0.34 0.34 0.67
0.51 E1
Table 4.3.1.3 DISTRIBUTION TABLE: Joing B BA D.F F.E.M 1ST distribution Carry Over Total 0 49.044 -12.44 -60.76 12.44 60.79 0 -49.044 0.67 0 49.044 BC 0.34 -73.2 24.88 C CB 0.34 73.2 -24.88 CD 0.67 0 -49.044
RB + RC
=24.4 x 6 = 146.4 kN
RB MA=0 -RB x 3 + 49.04 -RB Since RA + RB RA + 16.3 Therefore RA SHEAR FORCE DIAGRAM:
= 73.2kN
=0 = -16.3kN =0 =0 = -16.3kN
LOAD CALCULATION
Self weight of the slab = (7.5 x 2.5 x 0.3 x 25)/10 = 14.1 kN/m Self weight of the beam =(0.3 x 0.85 x 25) = 6.4 kN/M2
MAIN REINFORCEMENTS
Mu (516.5 x 106) = 0.87 fck Ast d [1-Ast fy / fck bd] = (0.87 x 415 Ast x 300) [1-415 Ast / (20 x 300 x 800)] Therefore, Ast =2210.8 mm2
Provide 8 bars of 16 mm diameter (Ast = 2411.52mm2) Mu (438.75 x 106) = 0.87 fck Ast d [1-Ast fy / fck bd] = (0.87 x 415 Ast x 300) [1-415 Ast / (20 x 300 x 800)] Therefore, Ast =1798.7 mm2
SHEAR REINFORCEMENT
v=(Vu
/ bd)
Pt=(100 Ast/bd)
Hence shear reinforcement are required Balance shear = [201.6 (0.66 x 0.3 x 0.8)] = 201.44kN Using 8 mm diameter two-legged stirrups the spacing is : Sv = (0.87 x fy asvd)/vus =(0.87 x 415 x 2 x 50 x 800) / (201.44 x 103) = 143.39mm >0.75d =(0.75 x 500) =375mm Adopt a spacing of 140mm near supports gradually increasing to 300mm towards c/c of span
LOAD CALCULATION
Self weight of the slab = (3.5 x 2.5 x 0.3 x 25)/6 = 10.9 kN/m2 Self weight of the beam =(0.3 x 0.55 x 25) = 4.1 kN/M2 Self weight of the walls = (0.23 x 1 x 20)
= 4.6 kN/m2 Finishes Total dead load Live load Total load = 1 kN/m2 = 20. kN/m26 = 7.5 kN/m2 = 28.1 kN/m2
MAIN REINFORCEMENTS
Mu (137.7 x 106) = 0.87 fck Ast d [1-Ast fy / fck bd] = (0.87 x 415 Ast x 300) [1-415 Ast / (20 x 300 x 500)] Therefore, Ast =866.7 mm2
Provide 2 bars of 25 mm diameter (Ast = 981.25mm2) Mu (103.4 x 106) = 0.87 fck Ast d [1-Ast fy / fck bd] = (0.87 x 415 Ast x 300) [1-415 Ast / (20 x 300 x 500)] Therefore, Ast =627.2 mm2
SHEAR REINFORCEMENT
v=(Vu
/ bd)
= 0.84 N/mm2 Pt=(100 Ast/bd) = (100 x 981.25/300 x 500) =0.65 Refer table 19 (IS code : 456) read out:
v
=0.53N/mm2
Hence shear reinforcement are required Balance shear = [126.45 (0.53 x 0.3 x 0.5)] = 126.37kN Balance shear =126. 37 kN
Using 8mm diameter two-legged stirrups the spacing is : Sv = (0.87 x fy asvd)/vus =(0.87 x 415 x 2 x 50 x 800) / (201.44 x 103) = 143.39mm Sv>0.75d =(0.75 x 500) =375mm Adopt a spacing of 140mm near supports gradually increasing to 300mm towards c/c of span
=12 [from IS 456:2000] Kt Kc Kf (L/d)max = 1.2 =0.75 =1 = 26 x 1.2 x 0.75 x 1 = 23.4mm 12 < 23.4mm (L/d)actual < (L/d)max Hence deflection is safe.
LOAD CALCULATION
Load on beam due to two way slab= x h(a+b) x D x density Where D is the depth of slab = x 2 x ( 2 + 6) x 0.15 x 25 =30kN Uniformly distributed load (udl) =30/6 Total load from slab to beam Brickwork load Live load Floor finishes = 5kN/m = 1 x 0.23 x 3 x 20 = 2 kN/m2 = 1 kN/m2
Design load, Wu
=1.5 x 24.67
= 37kN CALCULATION
Mu = 0.125 x WuL2 = 0.125 x 37 x 62 = 166.50 kNm Vu = 0.5 x WuL = 0.5 x 37 x 6 = 111 kN
MAIN REINFORCEMENT
Mu(limit) = 0.138 x fck x bd2 = [0.138 x 20 x 230 x 5002] x 106KNm = 158.7kNm Mu > Mu(limit) It is doubly reinforced section Mu > Mu(limit) =(166.50 158.70) =[0.138 x 20 x 230 x 5002] x 10-6 KNm
= 158.7 kNm Mu > Mu(limit) It is doubly reinforced section Mu - Mu(limit) =(166.50 158.70) = 158.7 kNm fsc Es ={0.0035 [(0.48 x 500) -25]/ (0.48x500)} x (2x105) =627 N.mm2 But fsc < 0.87 fy = 0.87 x 415 Asc (7.8 x 106) / [361 x (500-25)] = 361 N/mm2 = [(Mu - Mu(limit)/fsc (d-d))] = 45.48mm2 ={0.0035 (Xu(max) d) / Xu(max) } x
Provide 2 bars of 12 mm dia (Asc=226.08mm2) Ast 2 =(Asc x fsc) / 0.87fy =(45.48 x 361) / (0.87 x 415) = 45.47mm2 Ast 1 = (0.36 fckb Xu(limit) / 0.87 fy =(0.36 x 20 x 230 x 0.48 x 500)/ (0.87 x 415) = 1100.75mm2 Total tension reinforcement Ast = (Ast 1 + Ast 2)
Ast
SHEAR REINORCEMENT
V
Pt
=0.68N/mm2
Since Tv>Tc Hence Shear reinforcement is required Vus =(Vu Tc bd) =(111-(0.68 x 230 x 500) x 103) =32.80kN Using 8mm dia 2 legged stirrups Sv =(0.87 x fyAscd)/Vus =(0.87x415x2x25x500)/
(32.8 x 103) =275mm Sv>0.75d =(0.75 x 500) =375mm Adopt a spacing of 250mm near supports gradually increasing to 300mm towards c/c of span
LOAD CALCULATION
Load on beam due to two way slab = x h(a+b) x D x density + (1/2 x b x h x D x density) Where D is the depth of slab = x 2 x ( 2 + 6) x 0.15 x 25 (0.5 x 6 x 3 x 0.15 x 25) =63.75kN Uniformly distributed load (udl) =63.75kN + 10 = 10.6 kN
Total load
Design load, Wu
CALCULATION
Mu = 0.125 x WuL2 = 0.125 x 37 x 62 = 205.2 kNm Vu = 0.5 x WuL = 0.5 x 45.6 x 6 = 136.8 kN
MAIN REINFORCEMENT
Mu(limit) = 0.138 x fck x bd2
= [0.138 x 20 x 230 x 5002] x 106KNm = 158.7kNm Mu > Mu(limit) It is doubly reinforced section Mu > Mu(limit) fsc =(205.2 158.70)=46.5kNm ={0.0035 (Xu(max) d) / Xu(max) } x Es ={0.0035 [(0.48 x 500) -25]/ (0.48x500)} x (2x105) =627 N.mm2 But fsc < 0.87 fy = 0.87 x 415 Asc (46.5x 106) / [361 x (500-25)] = 361 N/mm2 = [(Mu - Mu(limit)/fsc (d-d))] = 271.1mm2
Provide 2 bars of 16 mm dia (Asc=401.92mm2) Ast 2 =(Asc x fsc) / 0.87fy =(271.1 x 361) / (0.87 x 415) = 271mm2 Ast 1 = (0.36 fckb Xu(limit) / 0.87 fy =(0.36 x 20 x 230 x 0.48 x 500)/ (0.87 x 415) = 1100.8mm2
SHEAR REINORCEMENT
V
Pt
=0.68N/mm2
=(136.8-(0.68 x 230 x 500) x 103) =136.72kN Using 8mm dia 2 legged stirrups
Sv
103) =66mm Sv>0.75d =(0.75 x 500) =375mm Adopt a spacing of 65mm near supports gradually increasing to 300mm towards c/c of span
LOAD CALCULATION
Dead la load of RC slab = 1x1x0.3x25 = 7.5kN/m2 Weight of floor finish Total dead load Assume each interior column take Load from an area = 10 x 8.75 = 87.5m2 Dead load from floor = 8.5 x 87.5 =743.75kN = 1 kN/m2 =8.5 kN/m2
Dead load of wall & self weight of beam=0 (no wall & beams are provided in flat slab) Total dead load from each floor Including self weight of column, load from each flor = 800kN = 743.75kN
Dead load on ground floor column of 4 storey building =800 x 4 = 3200kN Live load from each storey =7.5x10x8.75
=656.25kN Live load 4th floor 3rd floor 2nd floor 1st floor Reduction (kN) Loads to be
considered (kN_ 656.25 656.25 656.25 656.25 0.3x656.25 0.20x656.25 0.10 x 656.25 0x656.25 Total load 196.875 131.25 65.625 0 393.75kN
Assume 1% as the longitudinal steel in the column Let the gross area of the column is Ag Therefore area of steel reinforcement is Asc Area of concrete is Ac Ac Pu Pu 5390.625 x 103 = 0.01Ag =(Ag - Asc) =(Ag-0.01Ag) = 5390.625 0.4fck Ac + 0.67fy Asc =0.4x20 (Ag -0.01 Ag) + 0.67 x 415 x 0.01 Ag Ag =503.77 x 103mm2
Therefore the side of the square column=(Ag)1/2 = 709.76mm We adopt 1200 x 1200mm as side of the column Ac =(Ag-0.01Ag) = 0.99Ag = 0.99(503.77 x 103)
= 498.73x103mm2 Asc =0.01(503.77 x 103) 5037.7mm2 [ Provide 11 numbers of 25mm dia bars with a nominal cover of 40 mm (5399.60mm2) Or { Provide 14nos of 22mm dia bars with a nominal cover of 40mm (5321.85mm2)
LATERAL TIES
of the dia of largest longitudinal bar = x 25 =6.25mm = x 22 = 5.5mm = 6mm Provide 6mm dia of lateral ties
PITCH
Least lateral dimension of column =1200mm 16x25 16x22 300 mm =400mm = 352mm
LOAD CALCULATION
Dead la load of RC slab = 1x1x0.3x25 = 7.5kN/m2 Weight of floor finish Total dead load Assume each interior column take Load from an area = 10 x 5 = 50m2 Dead load from floor = 8.5 x 50 =425kN Assume each column takes load from = 10+10 = 1 kN/m2 =8.5 kN/m2
= 20m long beam Dead load f wall = 0.23 x 1 x 20 = 4.6kN/m2 Dead load of beam = 0.3 x 0.85x25 = 6.375kN/m2 Total load = 4.6 + 6.375 = 10.975kN/m2 Dead load of wall & self weight of beam=10.975 x 20
=219.5kN Total dead load from each floor = 425 + 219.5 =644.5kN Including self weight of column, load from each flor = 700kN
Live load 4th floor 3rd floor 2nd floor 1st floor
Reduction (kN)
Loads
to
be
considered (kN_ 375 375 375 375 0.3x375 0.20x375 0.10 x 375 0x375 Total load 112.5 75 37.5 0 225kN
= 2800kN
= 225kN = 1.5(d.1+1.1) = 1.5(2800 + 225) = 4537.5kN
Assume 1% as the longitudinal steel in the column Let the gross area of the column is Ag Therefore area of steel reinforcement is Asc Area of concrete is Ac Ac Pu Pu = 0.01Ag =(Ag - Asc) =(Ag-0.01Ag) = 4537.5kN 0.4fck Ac + 0.67fy Asc
5390.625 x 103
Ag
=424.04x103mm2
Therefore the side of the square column=(Ag)1/2 = 651.18mm We adopt 1200 x 1200mm as side of the column Ac =(Ag-0.01Ag) = 0.99Ag = 0.99(424.04 x 103) = 419x103mm2 Asc =0.01(424.04 x 103) =4240.4mm2 [ Provide 14 numbers of 20mm dia bars with a nominal cover of 40 mm (4561.59mm2) Or { Provide 14nos of 22mm dia bars with a nominal cover of 40mm (5321.85mm2)
LATERAL TIES
of the dia of largest longitudinal bar = x 20=5mm = x 22= 5.5mm
PITCH
Least lateral dimension of column =1000mm 16x25 16x22 300 mm Provide 300mm c/c of lateral ties =352mm = 320mm
= 11m length of beam Dead load f wall = 0.23 x 1 x 20 = 4.6kN/m2 Dead load of beam = 0.23 x 0.525x25 = 3.01875kN/m Total load = 4.6 + 3.01875 = 7.61875kN/m Dead load of wall & self weight of beam=7.61875 x11
=83.806kN Total dead load from each floor = 180 + 83.806 =263.806kN Including self weight of column, load from each flor Live load from each floor = 275kN = 2x6x5 = 60kN Total dead load Total live load Design load ` = 275kN = 60kN = 1.5(d.1+1.1) = 1.5x(275 + 60) = 502.kN
Ast
= 0.01Ag = 469.9mm2
Ast
= Ast/ast
LATERAL TIES
Diameter = x 16=4mm = 6mm Adopt 6mm dia lateral ties
PITCH
Least lateral dimension of column =250mm 16xd 16x22 Provide 256mm = 250-40-40 = 170mm 48x6 288>170mm Hence safe =288mm =16x16 = 256mm
= 11m length of beam Dead load f wall = 0.23 x 1 x 20 = 4.6kN/m2 Dead load of beam = 0.23 x 0.525x25 = 3.01875kN/m Total load = 4.6 + 3.01875 = 7.61875kN/m Dead load of wall & self weight of beam=7.61875 x11
=83.806kN Total dead load from each floor = 180 + 83.806 =263.806kN Including self weight of column, load from each flor Live load from each floor = 275kN = 2x6x5 = 60kN Total dead load Total live load Design load ` = 275kN = 60kN = 1.5(d.1+1.1) = 1.5x(275 + 60) = 502.kN
Ast
= 0.01Ag = 469.9mm2
Ast
= Ast/ast =2.33
So provide 4 rods
LATERAL TIES
Diameter = 6mm Adopt 6mm dia lateral ties = x 16=4mm
PITCH
Least lateral dimension of column =250mm 16xd 16x22 Provide 256mm = 250-40-40 = 170mm 48x6 288>170mm Hence safe =288mm =16x16 = 256mm
Assume self weight of footing taken As 10% of column load =(10/100) x 5390.625 =539kN Total load = 5390.625 + 539 = 5929.68 / 450 =13.71m2 Size of footing =(13.17)1/2 =3.63m Therefore,size of footing = 4m x 4m
DEPTH OF FOOTING
Mu D2 D Therefore depth,d Avoid shear failure = 0.138 fckbd2 =[50860 x 106)/(0.138x20x4000)]2 =678.7mm =678.7mm =700 x 2 =1400mm Total depth =1400 + 50 +8 =1458mm
MAIN REINFORCEMENT
M 5086 x 106 = 0.87fyastd{1-(fyast/fckbd)} =0.87x415xastx1400 [1-(415xAst)/20x4000x1400)] Ast2-269879.5Ast+2719432 Ast =0 =10483.7mm2
Assuming 32mm dia bars Ast =(3.14 x 322/4) =803.84mm2 Number of bars =Ast/ast =10483.7/490.62 =21.3 =21numbers Provide 21nos of 25mm dia barss
Hence safe
=759.2kN =(544.69x103)/(3630x1200) Permissible =0.25x(fck)1/2 =1.11N/mm2 0.125<1.11 Hence safe So it is safe against punching shear
=36 Actual bearing stress =(5390.625 x 103)/(1200x1200) =3.74 3.74<32.67 Hence safe Therefore, Size of footing Depth of footing Main reinforcemet side =4m x 4m = 1.458 =14 numbers of 32mm dia for both
Assume self weight of footing taken As 10% of column load =502.4x10/100 =50.24kN Safe bearing capacity of soil Area of footing required =450kN/m2 =552.64/450 =1.228m2 Side of square footing =(1.228)1/2 =1.10m Provide a square footing of 2m x 2m
BENDING MOMENT
Projection of footing from face of column =(2-0.5)/2 =0.75m
DEPTH OF FOOTING
MR = 2.98bd2
Effective depth required to resist the Bending moment, D =[(70.65x106)/(2.98x2000)]1/2 =108mm =110mm
TENSION REINFROCEMENT
Maximum bending moment = 70.65x106mm =0.87x415xastx216 [1-(4.8x10-5)Ast2] Ast2-20833Ast+18872916.6 Ast =0 =1898.3mm2
DEVELOPMENT LENGTH
Development length required for the
Tension bars Ld =(16x230)/(4x1.2) =667mm Projection of footing from the face of the column Providing an end cover of 50mm 700mm>667mm Hence safe = 750mm
=134.14kN Nominal shear stress Tvy =(134.14x103)/(2000x216) =0.31N/mm2 (from table 19, IS 456:2000] Tcy Tvy=Tcy Hence ok. =0.34
BUILDING DRAWINGS
STRUCTURAL DRAWINGS
REFERENCE:
1. N. Krishna raju, Design of Reinforced Concrete Structures, CBS Publishers & Distributors Pvt. Ltd, New Delhi. 2. Dr. B.C.Punmia, Soil Mechanics and Foundation S. Chand & Co., New Delhi. 3. IS 456-2000 Code Of Practice. 4. SP 16 1980( Design Aids for Reinforced to IS 456)