Item Task

Start

End

2015 2016 2017 2018 2012 2013 2014 S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
byanasak 04/17/2013

Phase 1 Field Work Phase 1 Data Interpretaon Phase 1 Data Summary Report Reference Area Data Analyses Baseline Ecological Risk Assessment (BERA) Process Human Health Risk Assessment (HHRA) Process Upland Sites Data Review Groundwater Evaluaon Point Sources Evaluaon Non-Point Sources Evaluaon Modeling Workshops Sources Sampling Approach Memo Monthly Updates to USEPA on Key Technical Issues Phase 2 Work Plan (and Revisions to Supporng Plans) Phase 2 Field Work Phase 2 Data Interpretaon Preliminary Modeling Results Memo Modeling Approach Memo (2) Dra Baseline Ecological Risk Assessment Report Dra Human Health Risk Assessment Report Remedial Invesgaon Report Preliminary Alternaves Memo Feasibility Study Work Plan Feasibility Study Field Program Work Plan Feasibility Study Field Program Iniaon Rened Alternaves Memo Feasibility Study Report

2/2012 7/2012 1/2012 11/2012 3/2013 11/2012 Ongoing Ongoing Ongoing Ongoing -4/2013 Ongoing 4/2013 4/2014 5/2014 11/2013 5/2014 4/2015 4/2015 11/2015 11/2015 11/2015 11/2015 8/2016 5/2017 9/2017

1/2013 4/2015 7/2012 5/2013 12/2013 7/2015 TBD 9/2013 9/2013 7/2013 -11/2013
2/21

12/7

6/20

11/14

2/2014

5/2014

8/2014

10/2014

2/2015

5/2015

Ongoing 3/2014 3/2015 6/2015 8/2014 1/2015 3/2016 3/2016 4/2016 7/2016 7/2016 7/2016 8/2017 12/2017 11/2018

1/10

10/17 12/12 4/18 6/13 8/2 11/14 3/21 5/16 7/25 9/12

Monthly update meengs will include overview update on all areas of the Phase 2 WP; and focused discussions on individual topics based on schedule above. Monthly meengs will connue beyond 2013.

20 21 22 23 24 25 26 27

I:\Projects\Newtown_Creek\Project_Management\Project Schedule\GANTT EPA\NCRollUp_04.17.2013 .pdf

Legend:

Workshop with USEPA In-person monthly meengs with USEPA Approximate meframe

Newtown Creek Project Schedule Updated April 17, 2013 Newtown Creek RI/FS