Professional Documents
Culture Documents
The main issue with the influent pump stations is that they were sized to pump future peak flows with only two (2) pumps operating without accounting for the current and average conditions. Therefore, the influent pump stations are oversized for the daily average flow rates that are currently being experienced. In addition, the diurnal flows to the WWTP vary significantly with influent flow rates as low as 700 to 1,000 gpm during the night and on weekends. The reduced speed capacity (approximately 75 percent of speed due to flow required to open the check valve) of the NSPS and SSPS pumps are approximately 5,600 gpm (8 mgd) and 2,250 (3.2 mgd), respectively. These reduced speed capacities are significantly larger (by a factor of two) than the current average daily flows from these pump stations. Both pump stations cycle ON and OFF throughout the day, which results in significant hydraulic surging to the headworks of the WWTP. The continuous surging caused by the pumps at the SSPS and NSPS causes hydraulic and treatment process performance problems with essentially all of the WWTP liquid stream treatment processes.
3-1
Chapter 3_Final_NSPS_SSPS.docx
Chapter 3
The existing comminutors were removed during the BNR/ENR upgrade, because the non-clog centrifugal pumps that were installed were supposed to be capable of handling a high concentration of large solids. However, the pumps have experienced ongoing ragging / plugging problems that require manual removal of the debris. These pumps also exhibited some vibration issues during the initial pump performance tests at certain operating speeds. According to Salisbury maintenance personnel, some effort has been made to program the pumps to avoid operating at the speeds that have caused vibration issues in the past. During a recent inspection by Brown and Caldwell, the vibration issues were not readily apparent during startup and operation of the pumps. After further discussions with Salisbury maintenance personnel, BC and the City have agreed that the past vibration issues have been rectified through the reprogramming effort. During construction, the flow meter planned for installation on the main header from the NSPS was deleted which makes it impossible to determine the actual flow from the pump station. Both the NSPS and SSPS are located in residential areas and currently do not have odor control systems installed.
Chapter 3_Final_NSPS_SSPS.docx
3-2
Chapter 3
Vertical, Non-clog Centrifugal 12 / 10 6 3,750 120 200 75% Speed, 2800 gpm
Vertical, Non-clog Centrifugal 8 / 6 5 1,575 175 200 75% Speed, 1180 gpm
24
N/A
Chapter 3_Final_NSPS_SSPS.docx
3-6
Chapter 3
Upon initial plant flow or during low flow conditions, the Jockey pump is started first upon reaching high level and run to maintain level setpoint. If this pump reaches full speed and high level is still active, the Lead Duty pump is started and the Jockey pump stops. If the wetwell level remains within the normal operating range under Jockey pump control, it will operate to maintain a setpoint level. Upon low level, the Jockey pump will stop, and restart upon reaching high level. Additional pumps are started or stopped based on control loop pump speed control signal (not VFD feedback speed) percentages. When the VFD speed is called to be above or below a certain percentage for a certain period of time, one additional pump is started or stopped, respectively. Initial settings are 95% for start, 50% for stop, and from 30 seconds for the delay. Speed is used in-lieu of level to reduce deviations from the setpoint allowed. The Level setpoint changes depending on the number of pumps running as discussed in the paragraph above. The three existing large pumps will be rotated through modes of Lead, Lag and Standby on a daily basis. Hardwired pump equipment related shutdowns including, but not limited to: High motor temperature, VFD fault, and submersible pump moisture detected if applicable. Normally reset at the VFD. Other modes of operation are as follows: Process Control System (PCS) [MANUAL] Control Mode When the Control Mode is selected for [MANUAL] at the PCS, the operator shall be capable of starting and stopping each of the pumps via [STARTISTOP] device control module at the PCS. If a pump is placed "Out of Service" in the pump sequence control matrix, no pump control shall be provided at the PCS. The pump operating speed shall be adjusted at the PCS via a speed control command displayed on the screen. The pump operating speed shall apply to any pump operating in the [MANUAL] control mode such that all pumps are operating at the same speed, except for the jockey pump. The speed of a pump shall not be allowed to be adjusted to a speed below the "Pump Minimum Operating Speed" setting selected at the PCS. Any pump that is running shall shut down when the "Wet Well Low Level" set point is reached. The pumps shall be capable of being restarted from the PCS as long as the level in Influent Wet Well is above the "Wet Well Low Level" set point. Off Mode When the Control Mode is selected for [OFF] at the PCS, the pump will not run and will be taken out of the LEAD, LAG, STANDBY sequence.
Figure 3-4 illustrates a schematic of the process flow through the pump station, including the new pumps, dimminutors and flow meters.
3.4.2 Dimminutor
The dimminutor shall be provided with a dedicated controller to control operation of the machine as well as a local HAND/ OFF/ AUTO switch. The controller shall have sensors designed to detect motor overload and initiate momentary reversal of cutter operation to cure the condition, and then resume normal operation. If the overload clears, normal operation shall be maintained. If the overload reoccurs, the process shall be repeated. If the overload still remains after three attempts within 30 seconds, the controller shall lock out the dimminutors control circuits and initiate alarm through dry contacts to an external circuit.
Chapter 3_Final_NSPS_SSPS.docx
3-7
Chapter 3
Chapter 3_Final_NSPS_SSPS.docx
3-10
Chapter 3
areas would result in a gross over sizing of the equipment. Additionally, the odor control units would be very large and unsightly. Water Supply: If a potable water supply is brought to the station, installation of a backflow prevention valve on the water main prior to any point of use is required. An air break shall be provided between any potable water and sewage handling equipment which might cause contamination of the potable water system. Any new connections between the potable water supply and sewage handling equipment will be designed to meet these standards. Safety Features: Safety features such as hand-rails, fixed grab bars or other provisions for safe access, operation and maintenance must be provided. Any newly modified areas will have applicable safety features installed. Force Mains: Velocity: At a minimum pumping rate, a velocity of at least 2 feet per second is recommended. The planned jockey pumps will be supplied with a minimum flow rate such that the minimum velocity in all discharge force mains will be maintained at or above 2 feet per second.
3.7 Constructability
Modifications to the North and South Pump Stations will consist of the addition of a jockey pump, dimminutors, and odor control equipment to both facilities. Structural adjustments will need to be made in order to facilitate proper placing of the dimminutors, however these are expected to be minor. The installation of the jockey pumps will require the existing suction piping to be re-engaged. This will involve the installation of a new gate valve, and a re-arrangement of the piping for the dry-wells sump suction piping. It is anticipated that this work can be completed in such a manner as to not interfere with the operation of the pump stations. At the North Side Pump Station, there is one operational influent line, through the existing dimminutor chamber and one line with no entry to the wetwell through the dimminutor room. The construction will need to be phased in such a manner that the dimminutor room is brought online while using the dimminutor chamber. Then the opposite can occur. The equipment is being sized such that only one influent line will be necessary at any given time. At the South Side Pump Station, the dimminutor room is the only influent line to the pump stations wetwell. Therefore, each dimminutor channel with have to be taken offline one at a time, for device installation, in order to keep the pump station online at all times. The North Side Pump Station currently only has a flow meter installed on the 18 discharge line. During this upgrade a flow meter on will be installed on the 24 discharge line. It is expected that this line will be taken offline in order to install the meter using existing shut-off valves while the other discharge line is used in order to keep the pump station operational. Both facilities will require a connection to a water line, as well as a power connection and a drain line to and influent sewer or the pump station wetwell. The installation of the ductwork and the equipment is expected to be completed so that the pump stations operations are not impacted.
Chapter 3_Final_NSPS_SSPS.docx
3-11