MDTA 2011 ANNUAL INSPECTION REPORT


Bridge No. B-Y037021 Bridge Data & Information Bridge Name: WB TA BRIDGE OVER Carries: I-895 SB Crossing: I-695 No. of Spans: 004 Interim Bridge Inspection An interim inspection of the bridge was performed in accordance with the latest edition of the MDTA Inspection Manual. This interim inspection combined a visual and hands-on inspection such that an overall assessment of the structure could be made, to establish whether the bridge has been maintained in good repair, working order and condition. Findings during the interim inspection are intended to supplement the previous hands-on inspection report. Elements with a condition rating of 4 or less, or a repair rating of E or 1 received a hands-on inspection, with a visual inspection of all other bridge elements. Using this methodology, the condition of the bridge was assessed, and compared to previous SI&A data. Changes to SI&A were updated where appropriate and supported by findings of the interim inspection. General Photo and SI&A Ratings SI&A 58 - Deck 59 Superstructure 60 - Substructure 61 - Channel 62 - Culvert Executive Summary Bridge B-Y037021 is a four span (28-0, 70-2, 70-2, and 33-0) simply-supported multi-beam steel bridge constructed in 1957, carrying I-895 SB over I-695. The overall bridge is in fair condition. The 2011 NBI Ratings for Items 58, 59, and 60 are based on an interim level inspection using visual inspection techniques unless the item was previously rated a 4 or less. Whitman, Requardt & Associates, LLP assumes no responsibility for the presence of any defects that cannot be detected by such visual inspection techniques. 2010 6 5 5 N N 2011 6 5 5 N N County: 005-BALTIMORE City 0 Year Built: 1957

Baltimore Harbor Tunnel INTERIM BRIDGE REPORT

Date 5/10/2011

Letters of Concerns: See Attached LOCs if any Inspection Company: Whitman, Requardt & Associates, LLP Inspection Crew: AC, FJO, MPU, WTR

Inspection Team Leader QC Engineer:

Wilson Reakes Jeff Lomax (QC) Name Signature

38374 25461 PE Number

2 Page of 5

MDTA 2011 ANNUAL INSPECTION REPORT


Bridge No. B-Y037021

Baltimore Harbor Tunnel INTERIM BRIDGE REPORT

Date 5/10/2011

New or Updated Notes and Repair Recommendations Listed below are new or updated condition notes, repair recommendations and photos added during the interim bridge inspection. For a complete list of items, refer to most recent hands-on inspection report. Condition Notes for items 58-62 Cond. Cond. Rating Ratin 2011 g 2010 4 4 Element # Location Condition Description Notes Photos MDTA Repair

58.05 - Scuppers Span 02 59.14 - Bearings 4 5 Span 01 The masonry plates for Bearing Nos. 5 - 7 at the South Abutment exhibit up to 35% loss of bearing due to section loss of the shim plates. Bearing Nos. 2, 3 and 6 at the North Abutment exhibit gaps between the bearing plates. Bearing No. 2 moves vertically under live load. The masonry plate for Bearing No. 6 exhibits up to 100% loss of bearing and can be moved manually. The supporting concrete below Bearing No. 6 appears to be sound. There is a 1'-8" wide x 8'-0" high x 4" deep spall with exposed and corroded reinforcement in the southeast corner of Column No. 2 at Pier No. 2. 2 2 The downspout from the scupper at Pier No. 2 is missing. 1 2

Span 04

60.04 - Columns 4 5 Span 02 3 1

Repair Recommendations for items 58-62 MDTA Repair Item No. Element # Location 58.05 - Scuppers 2010-B-Y037021-00068 Span 02 MODIFIED 2011: Replace the missing downspout at the Pier No. 2 scupper in Span No. 2. 1 2 - High Priority Condition Description Notes Photos MDTA Repair

59.14 - Bearings 2011-B-Y037021-00017 Span 01 Replace the shim plates for Bearing Nos. 5 - 7 at the South Abutment. Install shims at Bearing Nos. 2,3, and 6 at the North Abutment. 2 2 - High Priority

2011-B-Y037021-00013 Span 04

1 - First Priority

3 Page of 5

MDTA 2011 ANNUAL INSPECTION REPORT


Bridge No. B-Y037021

Baltimore Harbor Tunnel INTERIM BRIDGE REPORT


60.04 - Columns Remove unsound concrete around 8'-0" x 1'-8" x up to 4" deep corner spall with exposed reinforcing steel in southeast corner of Pier 2 Column 2. Blast clean and epoxy coat the exposed reinforcement. Patch the exposed concrete area. 3

Date 5/10/2011 1 - First Priority

2011-B-Y037021-00016 Span 02

4 Page of 5

MDTA 2011 ANNUAL INSPECTION REPORT


Bridge No. B-Y037021

Baltimore Harbor Tunnel INTERIM BRIDGE REPORT

Date 5/10/2011

Photos
PHOTO NO.:1 Location: Pier No. 2 Direction: North West Description: Missing downspout at scupper location

Element #: 58.05 Rating: 4 MdTA Repair: 2 - High Priority

5 Page of 5

MDTA 2011 ANNUAL INSPECTION REPORT


Bridge No. B-Y037021 PHOTO NO.:2 Location: Bearing No. 6 at the North Abutment Description: Gap between bearing plates and loss of bearing for the masonry plate

Baltimore Harbor Tunnel INTERIM BRIDGE REPORT

Date 5/10/2011

Element #: 59.14 Rating: 3 MdTA Repair: 1 - First Priority

PHOTO NO.:3 Location: Southeast corner of Column No. 2 at Pier No. 2 Direction: North West Description: Spall with exposed and corroded reinforcement

Element #: 60.04 Rating: 4 MdTA Repair: 1 - First Priority