Professional Documents
Culture Documents
Foundations
SITE CLEARANCE
1 6
MODULE 1 SHEET 1
Groundworks
Before any foundation construction can begin on site a number of preparatory activities need to be undertaken. These activities are generally termed groundworks. Typical groundwork activities include: Site clearance. Site preparation. Excavation of foundation trenches. Groundwater control.
Site Clearance
It is normal practice for any above ground clearance requirements, such as removal of trees, bushes, walls, slabs, buildings etc to be shown on a site plan. This plan may show the position of services, both above and below ground, allowing these to be cleared if necessary or avoided for safety if to be left alone. Construction sites vary a great deal, and clearance procedures will, of course, be different on each one. A greeneld site out of town may only require soil removal, whereas a browneld site, having been previously developed, may need extensive demolition and clearance of concrete slabs etc before any excavation can commence.
Contaminated Ground
Due to the increase in use of browneld sites, and regulations imposed by the government, many sites have to be decontaminated before structures can be built on them. This often involves the contaminated soil being totally removed from site and being replaced by clean soil when the site is landscaped.
Protection of Trees
Trees may have a preservation order placed on them by the local authority. This protects the tree from displacement or removal. The removal of other trees generally is subject to agreement with the planning authority before the work on site commences (usually at planning stage). When trees have to be protected, a barrier should be erected around each tree to prevent accidental damage. Care should be taken to avoid damaging branches that overhang the working area.
SECTION
MODULE 1 SHEET 2
Foundations
SITE CLEARANCE
Removal of Waste
Waste material can be removed by lorry or skip to a licensed landll site, or if the waste is inert, such as brick rubble or subsoil, it can be used as ll in certain earthworks. This will generally reduce the cost of removal of the waste to the contractor. Burning of rubbish on building sites is not normally allowed. On browneld sites, where masonry and concrete demolition is required, it is often cost-effective for the material to be crushed and used for hardcore in the contract (if acceptable to the architect and building control).
SECTION
Foundations
SITE CLEARANCE
1 6
MODULE 1 SHEET 3
This photograph shows the organic vegetable or topsoil layer on top of the lighter coloured subsoil below. The vegetable soil is excavated separately from the subsoil excavation, and the material is usually stockpiled in a spoil heap. This stockpile is sited on an area of the site which is not required for building operations. The vegetable soil is then used for landscaping purposes when the building is completed externally, any shortfall being brought in from external sources. Alternatively, excess soil may be sold or simply transported to another site.
SECTION
MODULE 1 SHEET 4
Foundations
SITE CLEARANCE
Cut and ll techniques are used to provide a level base for construction on sloping sites (see gure above). This method requires compaction of lled areas of soil, in layers. The soil for lling may be won from the cut areas. The cut area will be already sufciently compact. Fill is used when part of the site is below the required level, and soil, or other suitable material, is imported to the site to raise the work area. This method requires compaction of the lled area in layers. After completion of the nal grading and levelling of the site, the excavation of foundations can commence.
SECTION
Foundations
SITE CLEARANCE
1 6
MODULE 1 SHEET 5
Trench Excavation
Trenches must be excavated for foundations, drainage pipes and services. On small scale works, such as extensions to houses etc, hand tools such as pickaxes, spades, shovels and wheelbarrows are used for manual excavation of soil.
When the depth of excavation exceeds 1.2 metre, and/or the excavation becomes larger, mechanical methods of soil removal must be employed. Factors that inuence the choice of methods for excavation include: Volume of subsoil to be excavated. Nature of the site. Type of soil (e.g. stone requires mechanical excavation). Time constraints (how much time available for excavation). Safety of operatives.
SECTION
MODULE 1 SHEET 6
Foundations
SITE CLEARANCE
Mechanical Excavators
The most common machine used for the excavation of trenches is the backactor. There are many types of machine in a variety of sizes. The backactor has a clawing action that scoops soil from an excavation and deposits this, either in a temporary spoil heap, or into a dumper/lorry for disposal elsewhere.
Modern backactor machine (wheeled) the photo on the left shows the backactor bucket clearly
The wheeled backactor (shown above) is very versatile and can move about a site quickly. The tracked excavator with backactor can turn through 360, and is usually larger allowing greater volumes of soil to be excavated in a given time period.
The backactor can be tted with various size buckets. The choice of which will depend upon the width of trench required.
SECTION
Foundations
SITE CLEARANCE
1 6
MODULE 1 SHEET 7
Groundwater Control
Care must be taken when excavating soil as it is possible that the water table level may be reached. This is the point at which the water level stands naturally in the ground. The amount of water (and therefore the water table level) in a given soil depends on the season, the composition of the soil and the nature of the land. Low lying areas are likely to have a high water table, whilst higher ground may typically have a lower water table. Water in soil can be classied by its position in the ground: Water can be classied as either: Surface water. Ground water. Subsoil water.
Rain, snow etc on the surface
Surface water run off from the surface Ground water water held in the subsoil Subsoil water water held in the ground below the water table
SECTION
MODULE 1 SHEET 8
Foundations
SITE CLEARANCE
A vacuum piston pump being used to reduce ground water from an excavation
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 9
Purpose of a Foundation
The purpose of a foundation is to spread the load, from the structure above, over an adequate bearing area of the subsoil, and to provide a stable, level base on which to build. Although foundations are normally out of sight, the effect of any movement of a foundation is likely to be very noticeable in the structure above. The foundation is sandwiched between the forces from the structure and those from the ground thus subjecting it to compressive forces, so the foundation must be constructed from a material that is strong enough to resist any forces being imposed upon it.
SECTION
MODULE 2 SHEET 10
Foundations
TYPES OF FOUNDATIONS
Foundations are required to prevent undue settlement and consequent fracture of the building due to unequal loads and stresses at various points and to distribute these loads evenly over an area.
The foundation then, requires both strength and stability to full its role. The strength is related to the materials used to construct the foundations, but the stability depends on the way in which the foundation transmits the load to the subsoil, and the way in which the subsoil reacts. The strength of a material is a measure of its power to resist forces placed upon it. Some materials will resist both tensile and compressive forces; others will resist compressive but not tensile forces. It is therefore very important to know both the nature of the forces acting on a material and how the material reacts to such forces. The forces which act on a foundation are the weight of the building acting downwards, and the supporting resistance of the ground underneath which acts upwards (see gure above).
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 11
Wall
Foundation
45
As long as the foundation does not extend beyond this 45 line at its base, the forces within it can be assumed to be compressive only. To maintain this, however, when the wall becomes wider, the foundation should also become wider and deeper.
SECTION
MODULE 2 SHEET 12
Foundations
TYPES OF FOUNDATIONS
The effects of spreading of loads on foundations This widening and deepening of the foundation is unlikely to be economical though. The amount of excavation and concrete required would result in a very heavy and expensive structure. Solving the problem The solution is to make the foundation wider without making it thicker. This will ensure the load is spread over an adequate area of ground to support it safely. In this case, there is a tendency for the foundation to bend across its width and this in turn results in tensile forces in the bottom of the foundation. In this case, a material which is strong in tension and compression must be used to reinforce the foundation. The material most commonly used is steel reinforcement. Steel reinforcement can be either steel bars or steel mesh which is encased within the concrete.
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 13
Bearing Pressure
The bearing capacity of a foundation is the force per unit area imposed by the foundation on the subsoil beneath it. The bearing pressure of the subsoil is the force per unit area that the subsoil is capable of supporting.
Factor of Safety
Subsoil is a mixture of solid particles, air and water. As with any other material it has to be a certain strength to resist compressive forces, but it will fail if it is overloaded. In order to provide a factor of safety, it is usual to design a foundation so that the bearing pressure on the ground, imposed by the structure through the foundation, is about one third of the bearing pressure of the subsoil. Since on any particular building site it is necessary to take the subsoil as it is found, it is the foundation which has to be designed to provide a safe bearing pressure. This can be carried out in one of two ways: 1. By spreading the load over a wide area so that the force per unit area imposed upon the soil is reduced. 2. By taking the load to a greater depth where the subsoil is stronger and the force per unit area that the subsoil can carry is greater.
SECTION
MODULE 2 SHEET 14
Foundations
TYPES OF FOUNDATIONS
Wall tends to tilt when ground moves, and cracks can occur
Foundation will tend to tilt since the ground movement is greater at the outer edge
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 15
Tree roots tend to accelerate this process by absorbing water in the soil and consequently drying it out. The roots of certain trees can often extend out in all directions greater than the tree. When a site has been cleared of trees, the reverse can happen. The roots no longer dry out the subsoil which in turn becomes wet and swells, resulting in heave, and possible cracking of the structure.
Cracks in external brickwork are often stepped and diagonal. The walls tend to be drawn outwards and downwards by the movement in the ground. Care must be taken when building near trees.
SECTION
MODULE 2 SHEET 16
Foundations
TYPES OF FOUNDATIONS
At least 1.00m
Note! No ground movement should occur if the foundation is at a depth of more than 1.80m
Depth at least 1.00m below ground level will produce only very slight movement which will not affect foundation
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 17
Tension cracks appear when stress exceeds the concretes own resistance. Failure will occur through bending
Un-reinforced strip
Reinforcing the foundation to resist the forces that cause bending and cracking The foundation can be reinforced by inserting steel reinforcement bars or mesh into the concrete. This will reduce the tendency of the foundation to crack or bend.
SECTION
MODULE 2 SHEET 18
Foundations
TYPES OF FOUNDATIONS
Foundation Types
Foundations are generally described by their shapes. Pad foundation For single loads which are transmitted down a brick pier, concrete column or steel stanchion, the most common foundation is a square or rectangular block of concrete of uniform thickness known as a pad foundation.
Pad foundation
In order to spread the load over a greater area it is necessary either to make the pad thicker or use reinforced concrete.
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 19
Strip Foundation Under a wall, where the loading on the foundation is continuous, the support is commonly a continuous strip of concrete known as a strip foundation. The width of the strip will depend on the load to be carried and the strength of the ground. The traditional or shallow strip foundation consists of a continuous strip of un-reinforced mass concrete under the walls. This type of foundation is suitable for most subsoils and structural loadings associated with low to medium rise domestic and industrial buildings.
Strip foundation
In order to reduce failure through bending and shear, the foundation concrete has to be a minimum 150mm thick, and the projection from the face of the wall to the edge of the foundation concrete has to be at least equivalent to the concrete thickness. The diagram below shows the dimensions which will satisfy the current Building Regulations.
The depth D must be 150mm minimum and must be equal to, or greater than, the projection P and the distance P must be equal on either side of the wall.
SECTION
MODULE 2 SHEET 20
Foundations
TYPES OF FOUNDATIONS
Wide strip foundations If the use of traditional strip foundations is likely to overstress the bearing strata (the layer of ground on which the foundation sits), a wide strip foundation can be employed. The wide strip foundation would be designed to transmit the foundation loads across the full width of the strip. This might necessitate the foundation thickness being increased to overcome the bending and shear stress. In some cases, the thickness of concrete could become uneconomic and so reinforcement is used. Both longitudinal and transverse reinforcement are added to ensure the applied loads are supported without failure of the strip.
Longitudinal reinforcement
Transverse reinforcement
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 21
Stepped strip foundation On sloping sites it is usual to step the foundation to follow the line of the ground and therefore reduce the amount of excavation required. A second benet of using stepped foundations is that the foundation is more likely to remains seated in the same strata of ground, avoiding potential differential settlement. When constructing stepped foundations, the construction starts at the lowest level of the site.
Building regulations relating to stepped foundations states: The minimum overlap L should be equal to twice the height of the step S or the foundation thickness T or a width of 300mm whichever is the greatest.
Height of step = two courses 150mm
SECTION
MODULE 2 SHEET 22
Foundations
TYPES OF FOUNDATIONS
In some cases, the working space required to build on top of a concrete strip foundation would make the strip wider than it would need to be to carry the load. In these circumstances, an economical alternative is the narrow strip foundation (or trench ll foundation as it is sometimes known). A narrow strip is excavated by the mechanical excavator and backlled with mass concrete. The bricklayer can then build off the foundation from ground level. A high standard of accuracy in constructing such a foundation is required, particularly if drains are to be let through the foundation. It is normal practice to box out drainage holes across the trench when pouring the concrete; this allows any drainage pipe or other services to pass through the foundation without risk of fracture at a later date. This foundation is often used where tree roots exist, the face of the trench being lined with polythene sheeting before pouring the concrete. This ensures that the concrete has a more smooth and dense surface. This tends to divert roots and avoids any potential root ingress into any holes in the foundation.
SECTION
Foundations
TYPES OF FOUNDATIONS
1 6
MODULE 2 SHEET 23
Short bored piles It is sometimes necessary to avoid constructing foundations on soil close to the surface. This is usually due to poor bearing capacity of the soil. If this so then one alternative method is to transfer the load on the foundation to a greater depth. In this situation an economical solution is the use of a short bored pile foundation. Short bored piles are formed by boring circular holes 300mm diameter to a depth of about 3m by means of an auger. The holes are then lled with concrete and reinforced with steel bars which are left projecting from the top. The piles are placed at the corners of the building and at intermediate positions along the walls. The piles support reinforced concrete ring beams which are cast in place in the ground on top of the piles. It is on to these ring beams that the brickwork is built.
SECTION
MODULE 2 SHEET 24
Foundations
TYPES OF FOUNDATIONS
Raft foundations Raft foundations are often used on poor subsoils for lightly loaded buildings and are designed to be capable of accommodating small settlements of the subsoil. A raft foundation covers the whole of the oor and wall area of the structure. The reinforced oor slab is generally thickened out substantially under all the walls, and the loads from the walls are subsequently transferred into the whole of the slab.
The simplest and cheapest form of raft is the thick reinforced concrete raft. Its rigidity enables it to minimise the effects of differential settlement.
SECTION
Foundations
TRANSFERRING LEVELS
1 6
MODULE 3 SHEET 25
SECTION
MODULE 3 SHEET 26
Foundations
TRANSFERRING LEVELS
Datum peg
Concrete thickness
SECTION
Foundations
TRANSFERRING LEVELS
1 6
MODULE 3 SHEET 27
Having set the rst peg to gauge from the datum, the level must be transferred all around the buildings foundation to provide a guide for the top of the concrete when poured. Optical levels are most commonly used to do this (see the levelling section in the Setting Out section). However, at times the, bricklayer will nd it more convenient to simply transfer the levels around the trench by the use of a straightedge and spirit level. The straightedge and spirit level are used as shown in the gure below. It is essential to REVERSE the level and straightedge at each peg reading. This ensures that any discrepancy in the straightedge or level is not repeated at every peg, but cancelled out at every other reading.
Datum peg Depth to be a multiple of brick courses
SECTION
MODULE 3 SHEET 28
Foundations
TRANSFERRING LEVELS
Another method of transferring levels around a trench is by the use of boning rods. Boning rods are made from timber and are usually painted so that they are easily seen. Boning rods are typically used in threes, the middle one being known as the traveller. Two known level pegs are required to be placed at either end of the trench. Boning rods are placed on both pegs and held upright. The other pegs can then be determined by sighting in between the two xed boning rods onto the traveller as shown below.
Line of sight Traveller Boning rods Levelling pegs
When all of the level pegs have been positioned, the bottom of the trench can be trimmed to give the required depth of concrete, e.g. 225mm. Soil must not be used to backll any depressions. Extra concrete should be used in this case; so for economy, great care should be taken to trim the trench base as accurately as possible.
SECTION
Foundations
TRANSFERRING LEVELS
1 6
MODULE 3 SHEET 29
As the edge of the slab must be supported above the ground, metal or timber formwork must be xed temporarily at the side of the foundation trench to the height of the oor slab which will be at datum level. As the formwork stands proud of the surrounding ground it is generally necessary to support it by strutting. This is to prevent the formwork moving when the concrete is poured. Boning rods or sight rails (permanent horizontal rails often xed above the proles at corners of the building when setting out) are set up, and the traveller is placed on top of the formwork when xing into place to determine the top level.
SECTION
Foundations
PLACING CONCRETE IN FOUNDATIONS
1 6
MODULE 4 SHEET 30
In shallow foundations two battens are often used as a chute to slide the concrete into place and the concrete is compacted by use of a shovel or hand tamp (heavy weight on a rod), before tamping it to level. Mechanical compaction such as a vibrating poker may alternatively be used.
SECTION
MODULE 4 SHEET 31
Foundations
PLACING CONCRETE IN FOUNDATIONS
Trench struts
Before placing concrete into the formwork, it is important to ensure that the inside of the formwork has been treated with a releasing agent, e.g. mould oil. This will allow the formwork to be removed after the concrete has set, without damaging the concrete. It is also very important that the bottom of the trench be compacted to give a sound, rm base. If the base is soft it may be necessary to lay a hardcore foundation to the base. In deep foundations it is necessary to use a chute to allow the concrete to slide down from the ready-mix lorry, dumper or barrow into the foundation as near as possible to its nal position.
SECTION
Foundations
PLACING CONCRETE IN FOUNDATIONS
1 6
MODULE 4 SHEET 32
Unlike strip foundations, which may often be deep within a trench, most raft foundations are at ground level or just below. There should not be a danger of falling concrete being segregated, but chutes will still be required to place the concrete into the centre of the concreted area.
SECTION
MODULE 4 SHEET 33
Foundations
PLACING CONCRETE IN FOUNDATIONS
A further benet of using a mechanical beam vibrator/compactor is that it helps to ensure that the concrete is free of excess air, thereby making the concrete stronger and more durable.
Beam compactor
SECTION
Foundations
PLACING CONCRETE IN FOUNDATIONS
1 6
MODULE 4 SHEET 34
Ready-mix Concrete
To ease the burden of mixing and placing and levelling concrete for foundations, most builders use ready-mix concrete. Ready-mix concrete is durable, versatile and highly economical. Ready-mix concrete is a mixture of ne and coarse aggregate, along with water and cement and various additives. Once the ingredients are combined, a chemical reaction occurs between the cement and the water and this paste hardens around and between the aggregates to form the hard mass known as concrete. Different additives can be included in the mix to make the wet concrete more workable by making it more uid and increasing the setting time of the concrete without it losing any strength when it is set. This allows this type of concrete to be placed easily, usually by means of a chute or, in some cases, by pumping it into place. New innovations in mix design have led to a series of new types of ready-mix concrete. These new types of concrete have been designed to make the placement and compaction of foundation concrete easier and simpler by making them more uid, and in some cases, self-levelling. Some of these new types include such names as Self-compacting concrete, Foundation ow and Supao. The advantages of these types of concrete over traditional concrete are: Speed of application. Accuracy of placement. Reduction in overall cost. Reduction in levelling and compaction time. Good surface nish. Care must be taken when placing this type of concrete into foundation formwork as it is a heavy uid mixture that weighs approximately 2.3 tonnes per cubic metre.
SECTION
MODULE 4 SHEET 35
Foundations
PLACING CONCRETE IN FOUNDATIONS
A full load of 6 cubic metres can weigh 14 tonnes, and a fully loaded mixer truck can weigh over 20 tonnes. Therefore care must be taken when bringing this type of truck onto the site as it may get bogged down if the site is wet, or it might cause the sides of trenches to collapse and dislodge the formwork if it is allowed to get too close to the trench. This type of concrete needs to be laid on well compacted ground that has been covered with a sheet of plastic or polythene. This will prevent moisture loss into absorbent ground, thus preventing the concrete from drying out too quickly prior to levelling and nishing. It also allows the hardened concrete to slide over the ground without undue restraint as it expands and contracts due to climatic temperature changes. Unless the topsoil can be compacted to give a sound base, it should always be removed and replaced with a foundation of hardcore covered with a layer of sand which should be compacted until rm.
SECTION
Foundations
PLACING CONCRETE IN FOUNDATIONS
1 6
MODULE 4 SHEET 36
SECTION
Foundations
BRICKWORK BELOW GROUND LEVEL
1 6
MODULE 5 SHEET 37
SECTION
MODULE 5 SHEET 38
Foundations
BRICKWORK BELOW GROUND LEVEL
SECTION
Foundations
BRICKWORK BELOW GROUND LEVEL
1 6
MODULE 5 SHEET 39
SECTION
MODULE 5 SHEET 40
Foundations
BRICKWORK BELOW GROUND LEVEL
Foundation Blocks
The use of foundation blocks is now very common. The blocks used are a very dense strong block that can support the brickwork and blockwork built above ground level. The use of these, rather than bricks or concrete blocks in two separate walls, speeds up the work considerably. This method also eliminates the need to ll the cavity with weak concrete ll. When building in this way it will be necessary to change to brickwork on the outer or face wall. This usually occurs two or three brick courses below ground level.
SECTION
Foundations
BRICKWORK BELOW GROUND LEVEL
1 6
MODULE 5 SHEET 41
Stepped Foundations
When building foundation brickwork on stepped foundations extra care should be taken. Work must always start at the lowest level. The rst course is set out as for ordinary strip foundations but care should be taken when ranging in the rst course due to the differences in level. The concrete foundation should be marked out as stated previously for level foundations. It is wise to check that each step in the foundation is in multiple brick courses at this stage. Before commencing to lay bricks it is important to set out the bond dry to avoid broken bond or reverse bond (starting with a header rather than a stretcher or vice versa, possibly resulting in a half bat in the wall). This is less likely to be a problem when you are building block footings as the blocks are generally used up to the point where the walls are levelled around. The bonding of brickwork is then done on top of the levelled blockwork. Once the corner bricks, have been established and laid, a line can be stretched diagonally between the corners, and this will help to mark the positions of the wall at each step and will help to maintain the true line of the wall.
Height of step = two courses 150mm
SECTION
MODULE 5 SHEET 42
Foundations
BRICKWORK BELOW GROUND LEVEL
Stepped Foundations
When the wall positions have been determined, the corner can be built and the wall completed as shown below. When all the brickwork or blockwork on the steps has been built up to level, the remainder of the footings are built as for normal masonry foundations.
SECTION
Foundations
BRICKWORK BELOW GROUND LEVEL
1 6
MODULE 5 SHEET 43
NOTE: It is generally simpler to build walls from a raft foundation than from a foundation within a trench. Once all the work has been nished up to DPC level, and the mortar has set and achieved strength, then the excavation will require backlling and any surplus subsoil to be removed from the site.
SECTION
Foundations
SOLID GROUND FLOORS
1 6
MODULE 6 SHEET 44
SECTION
MODULE 6 SHEET 45
Foundations
SOLID GROUND FLOORS
The damp-proof membrane sheeting should be laid on top of the blinding and should be lapped onto the horizontal DPC of the brickwork to form a continuous membrane.
SECTION
Foundations
SOLID GROUND FLOORS
1 6
MODULE 6 SHEET 46
Compaction of hardcore Hardcore must be compacted in 100mm layers maximum thickness. This should prevent any unacceptable settlement beneath the nished solid oor. The main item of small plant which is used to compact hardcore is a plate compactor. The whole area of the foundation base has to be completely compacted and consolidated, and care must be taken not to damage or disturb the brickwork when using the compactor. For small areas a hand tamp can be used.
SECTION
MODULE 6 SHEET 47
Foundations
SOLID GROUND FLOORS
Insulation The Building Regulations require ground oors to be insulated to prevent heat loss. There are several types of insulation available such as expanded polystyrene and rigid foam insulation. Insulation should always be laid above the DPC membrane preferably under the oor slab, or alternatively under the oor nish. If it is not it could cause the insulation to become damp which will impair its performance.
SECTION
Foundations
SOLID GROUND FLOORS
1 6
MODULE 6 SHEET 48
Oversite concrete The concrete placed inbetween the ground oor walls is known as oversite concrete. The brickwork or blockwork on the internal walls acts as shuttering for the concrete. Oversite concrete should be at least 100mm thick. (If placed on insulation it is usual to have a minimum of 150mm thickness.) The thickness of hardcore should be at least equal to the concrete thickness. There is no need to trowel nish the concrete unless it is the nished oor of the building such as in a garage or store. A tamped nish is preferable to allow a oor screed to properly adhere to the oversite concrete. Sometimes, a solid oor has a oating oor or battened oor constructed on top of it. In this case it is necessary to nish the oor with a smooth wood oat nish.