(NOVEMBER 2010)
November 2010
www.wapda.gov.pk
PREFACE
Energy and water are the prime movers of human life. Though deficient in oil and gas, Pakistan has abundant water and other energy sources like hydel power, coal, wind and solar power. The country situated between the Arabian Sea and the Himalayas, Hindukush and Karakoram Ranges has great political, economic and strategic importance. The total primary energy use in Pakistan amounted to 60 million tons of oil equivalent (mtoe) in 2006-07. The annual growth of primary energy supplies and their per capita availability during the last 10 years has increased by nearly 50%. The per capita availability now stands at 0.372 toe which is very low compared to 8 toe for USA for example. The World Bank estimates that worldwide electricity production in percentage for coal is 40, gas 19, nuclear 16, hydro 16 and oil 7. Pakistan meets its energy requirement around 41% by indigenous gas, 19% by oil, and 37% by hydro electricity. Coal and nuclear contribution to energy supply is limited to 0.16% and 2.84% respectively with a vast potential for growth. The Water and Power Development Authority (WAPDA) is vigorously carrying out feasibility studies and engineering designs for various hydropower projects with accumulative generation capacity of more than 25000 MW. Most of these studies are at an advance stage of completion. After the completion of these projects the installed capacity would rise to around 42000 MW by the end of the year 2020. Pakistan has been blessed with ample water resources but could store only 13% of the annual flow of its rivers. The storage is fast depleting due to sedimentation. In contrast US has developed 497% storage capacity of annual flow of River Colorado; Egypt possesses 281% of River Nile and India 35% on Sutlej-Bias Basin. All these statistics warrant construction of number of reservoirs to enhance availability of water which stands at 1070 cubic meter per capita. Anything below 1000 cubic meter tantamounts to a crisis situation. The hydropower potential in Pakistan is over 100,000 MW with identified sites of 55000 MW. Currently, studies under way include Diamer Basha (4500 MW), Bunji (7100 MW) and Kohala (1100 MW) amongst many others. Pakistan with 185 billion tons of coal reserves, the fourth largest in the world, is under utilizing this resource. In the overall energy mix, the share of coal power is only 7% as compared to world average of 40%. Coal is the main source for producing cheaper electricity and the Government has decided to enhance the share of coal in the overall energy mix of upto 18% in 2030. The Government is striving hard to minimize the gap between consumption and generation of electricity at affordable rate. The Government Power Policies of 1995 and 2002 have encouraged many private sector foreign and local investment through the Independent Power Producers (IPPs).
CONTENTS
DESCRIPTION
Water and Power Sector Development Pakistans Hydropower Potential River-wise Summary Hydel Stations in Operation Hydropower Projects under construction Hydropower Projects Which Can Be Undertaken For Implementation during Next Five Years
PAGE
01 03 03 04 04 05 06 08 12 13
th
HYDROPOWER PROJECTS
Diamer Basha Dam Project Transmission Scheme for Dispersal of Power from Diamer-Basha Hydropower Project to Major Load Centres in the National Grid Tarbela 4th Extension Transmission Scheme for Dispersal of Power from Tarbela 4 Ext Hydropower Project to Gatti Faisalabad Kohala Hydropower Project Transmission Scheme for Dispersal of Power from Kohala Hydropower Project to Gujranwala Munda Dam Project Transmission Scheme for Dispersal of Power from Munda Dam Project to Peshawar Kurram Tangi Dam Multipurpose Project Bunji Hydropower Project Transmission Scheme for Dispersal of Power from Bunji Hydropower Project to Major Load Centres in the National Grid Keyal Khwar Hydropower Project Golen Gol Hydropower Project Dasu Hydropower Project Lower Spat Gah Hydropower Project Lower Palas Valley Hydropower Project Akhori Dam Project Thakot Hydropower Project Pattan Hydropower Project Phandar Hydropower Project Basho Hydropower Project Lawi Hydropower Project Harpo Hydropower Project Yulbo Hydropower Project Shyok Dam Project Suki Kinari Hydropower Project Trappi Hydropower Project
14 15 16 17 17 18 19 19 20 21 22 24 25 26 27 28 29 30 31 32 33 34 35 36
37
DESCRIPTION
Mahl Hydropower Project Gulpur Hydropower Project Kotli Hydropower Project Transmission Scheme for dispersal of power from NeelumJhelum Hydroelectric Project to 500 kV Gakhar Grid Gujranwala Ultra Mega Power Project/Park Repair & Maintenance/Rehabilitation of Mangla, Tarbela & Warsak Hydel Power Stations
PAGE
38 39 40 41 42 43
46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61
REGIONAL DAMS
Winder Dam Project Darawat Dam Project Ghabir Dam Project Tank Zam Dam Project Naulong Dam Project Hingol Dam Project Garuk Dam Project Pelar Dam Project Nai Gaj Dam Project Bara Multipurpose Dam Project Daraban Dam Project Papin Dam Project Sukleji Dam Project Treatment of Effluent Water of RBOD (Pilot Project) Canal Lining
Implementation Schedule/Financing Requirements Existing Installed Generation Capacity Peak Demand Projections (2009-2030) Demand Forecast (2009-2030)
62 62 63 63
in the years ahead so that the remaining 20 million acres of cultivable land can be brought under plough. Water conservation and increased water productivity must also be encouraged. It is an economically unsustainable fact that the total water storages capacity in the country is only 15 MAF representing 13% of the total annual flows of 136 MAF. Countries in Asia, Africa and the Americas have a storage capacity many times greater. To address this problem the Government of Pakistan (GoP) is developing feasibility and detailed engineering studies for nearly 20 MAF of water storage and 25,000 MW of hydel power. This is apart from thermal power being developed by the private sector, Independent Power Producers (IPPs) and the Government. To achieve the above objectives the GoP through WAPDA and the private sector plans to concentrate on the following water and power projects in the next few years: (i) Construction of large dams including Diamer-Basha Dam for Public/Private Partnership (ii) Construction of Hydropower Projects (iii) Construction of Medium/ Small Water Storage Dams (iv) Construction of Canals (v) Construction of Transmission Lines for dispersal of Power from Hydropower Project to Load Centres of National Grid. These projects would create additional water storages, generate cheap indigenously developed electricity and prevent flood damages. All these measures would also ensure food security, employment generation and above all poverty alleviation.
Oil 35%
B. 1 2
241.159
4
1421.2
HYDROPOWER PROJECTS WHICH CAN BE UNDERTAKEN FOR IMPLEMENTATION DURING NEXT FIVE YEARS
S# 1. 2. 3. 4. 5. 6. 7. Project River Location GB KPK KPK FATA/KPK AJK KPK GB KPK/GB/AJK FATA/ KPK KPK Capacity (MW) 4500 106 960 84 1100 4320 7100 1500 740 2800 ~ 23,210 Earliest Project Initiation 2010 2010 2010 2011 2010 2012 2012 2011-2015 2012 2013
Diamer Basha Indus Golen Gol Chitral Tarbela 4th Ext. Indus Kurram Tangi Kurram Kohala Jhelum Dasu Indus Bunji Indus Others (Bara, Tank Zam 8. Matiltan & Palas Valley etc.) 9. Munda Swat 10. Patan Indus Total
HYDROPOWER PROJECTS
1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. 16. 17. 18. 19. 20. 21. 22. 23. 24. 25. 26. 27. 28. 29. 30. 31. 32. 33. 34. 35. Diamer Basha Dam Project Transmission Scheme for Dispersal of Power from Diamer-Basha Hydropower Project to Major Load Centres in the National Grid Tarbela 4th Extension Transmission Scheme for Dispersal of Power from Tarbela 4th Extension Hydropower Project to Gatti Faisalabad Kohala Hydropower Project Transmission Scheme for Dispersal of Power from Kohala Hydropower Project to Gujranwala Munda Dam Project Transmission Scheme for Dispersal of Power from Munda Dam Project to Peshawar Kurram Tangi Dam Multipurpose Project Bunji Hydropower Project Transmission Scheme for Dispersal of Power from Bunji Hydropower Project to Major Load Centres in the National Grid Keyal Khwar Hydropower Project Golen Gol Hydropower Project Dasu Hydropower Project Transmission Scheme for Dispersal of Power from Dasu Hydropower Project to Major Load Centres in the National Grid Lower Spat Gah Hydropower Project Lower Palas Valley Hydropower Project Akhori Dam Project Thakot Hydropower Project Pattan Hydropower Project Phandar Hydropower Project Basho Hydropower Project Lawi Hydropower Project Harpo Hydropower Project Yulbo Hydropower Project Suki Kinari Hydropower Project Shyok Dam Project Trappi Hydropower Project Matiltan Hydropower Project Mahl Hydropower Project Gulpur Hydropower Project Kotli Hydropower Project Transmission Scheme for Dispersal of Power from Neelum-Jhelum Hydropower Project to Rawat & Gujranwala Ultra Mega Power Project/Park Rehabilitation of Tarbela, Mangla & Warsak Hydel Power Stations
REGIONAL DAMS 36. Winder Dam Project 37. Darawat Dam Project 38. Ghabir Dam Project 39. Tank Zam Dam Project 40. Naulong Dam Project 41. Hingol Dam Project 42. Garuk Dam Project 43. Pelar Dam Project 44. Nai Gaj Dam Project 45. Bara Multipurpose Dam Project 46. Daraban Dam Project 47. Papin Dam Project 48. Sukleji Dam Project
THE PROJECT
The project is located on Indus River, about 315 km upstream of Tarbela Dam, 165 km downstream of the Gilgit-Baltistan capital Gilgit and 40 km downstream of Chilas (refer location map). The proposed dam would have a maximum height of 272 m, and impound a reservoir of about 8.1million acre feet (MAF), with live storage of more than 6.4 MAF. Mean annual discharge of Indus River at the site is 50 MAF. Thus the dam will impound 15% of the annual river flow. The dam project would cover an area of 110 km2 and extend 100 km upstream of the dam site upto Raikot Bridge on Karakoram Highway (KKH).
The dam is located at the boundary of Gilgit-Baltistan (GB) and Khyber Pakhtunkhwa (KPK) in such a way that the right abutment and the right Power House is in GB while the left bank of the dam and the left Power House is in Khyber Pakhtunkhwa. WAPDA offices and Colony including that of the Consultants shall be in the Thor Nallah Valley in GB while the Contractors Camp and fabrication yard and workshop shall be in Khyber Pakhtunkhwa
The present demand of electricity in country is above 17,000 MW, which is estimated to cross 30,000 MW by the year 2017. A large-scale injection of power thus becomes inevitable. Hydropower will provide the required electricity at affordable price. Contribution of 4500 MW power from Diamer Basha Dam will go a long way in alleviating this situation. Main Features Main Dam Maximum Height Type Diversion System
272 m Roller Compacted Concrete (RCC) 2 No. Diversion tunnels 1 No. Diversion channel Upstream and Downstream Cofferdams 1160 m 8.1 MAF (10.0 BCM) 6.4 MAF (7.9 BCM) EI.1060 m 2 4500 MW Two, one each under the right and left abutment 12 each of 375 MW 19000 Gwh/year Rs.894,257 million (US$ 11.17 Billion) 15.3% 1.43 8.04%
Reservoir Level Gross capacity Live capacity Min. operation level Power House(s) Total installed capacity Location and type No. of units Average generation PC-I approved cost E.I.R.R. (Base Case) Benefit / Cost Ratio (Discount Rate 12%) F.I.R.R.
PROJECT BENEFITS
Availability of about 6.4 MAF annual surface water storage for supplementing irrigation supplies during low flow periods Harnessing of renewable source of clean and cheap energy through installed capacity of 4500 MW Average Annual Generation 19000 GWh Extend Life of Tarbela reservoir by blocking the sediments Additional Annual Generation at Tarbela 1111GWh Reduction of dependence on thermal power, thus saving foreign exchange Employment opportunity, particularly to the locals, during the construction and operation Creation of massive infrastructure leading to overall socio-economic uplift of the area and standard of living of people The Project will pay back its cost in 8 years Annual Earning of Rs.232.8 Billion.
RESETTLEMENTACTION PLAN
The Income level in the project areas is extremely low. The Resettlement Action Plan envisages poverty alleviation. The compensation to be paid for involuntary resettlement would include prescribed possible entitlement as applicable in legislation. Affectees would be resettled in 9 model villages in the close vicinity, with better living condition. Their means of livelihood would be ensured. Affectees would be provided 5 Marla plots free of cost in developed model villages with all civic amenities and also 6 Kanal agricultural land for cultivation on payment. The total cost of PC-I (Part-I) Land Acquisition & Resettlement is estimated Rs.60 billion. Estimated Resettlement plan cost is Rs.12.245 billion. In order to resolve the issue of Resettlement/Land Acquisition, Prime Minister of Pakistan constituted Ministerial Committee, wherein Chief Minister Gilgit Baltistan was an observer and this committee unanimously approved Rs. 40 billion as Land Acquisition charges, agreed by all the stake holders. Council of Common Interests (CCI) under the chairmanship of Prime Minister has approved this project in its meeting held on July 18, 2010.
Due to the construction of the Project over 50,000 trees would be lost. The trees are to be planted on 1:3 ratio for preservation and improvement of ecosystem. The cost of compensation for the lost trees and planting the new trees and is estimated at about US$ 7 million.
o Anticipated damage to fish stocks due to discharge of effluent in river water o Two fish hatcheries shall be built for fish culture o o o o o o ROCK CARVINGS Protection of damage to rock carvings at the dam site and in the quarry areas. Physical relocation of most important rock carving objects, where feasible; Documentation of all important rock carving objects; Production of replicas of carvings for exhibition; Establishment of Gilgit-Baltistan Rock Carvings Exhibition Centre. Special Project to preserve Rock Carving under the guidance of Dr. Harald Hauptmann in association with Rogers Kolachi Khan & Associates (The Cultural Heritage & Development Consultants)
10
Project Implementation Implementation of the dam appurtenant structures shall be through international competitive bidding comprising of the following five lots:o Rs. in Million
Sr. No. 1.
2. 3. 4. 5.
Description of work Contract Lot-1 (Concrete Dam and Related Structures including Diversion Tunnels and Permanent Access Bridge) Contract Lot-2 (Underground Works and Related Structures (Left and Right Banks) Contract Lot-3 (Hydro-Mechanical Equipment and Hydraulic Steel Structures ) Contract Lot-4 (Power Plant Generation Equipment (Left and Right Bank) Contract Lot-5 (Electrical High Voltage Equipment and Power Plant Electrical Equipment (Left and Right Bank).
Local 87680
Foreign 58480
6.4 8 7 7
11
Present Status Detailed Engineering Design of Diamer Basha Dam Project (DBDP) was completed in June2008. PC-I for Land Acquisition and Resettlement was approved by Executive Committee of National Economic Council (ECNEC) on 6.11.2008 for Rs. 60 billion. Main PC-I for DBDP was approved by ECNEC on 20.08.2009 for Rs.894.257 billion. Resolution on Consensus of Diamer Basha Dam Project approved from Council of Common Interest (CCI) on 18.07.2010. Rs. 92 million were released to DCO Kohistan Khyber Pakhtunkhwa for acquisition of land for contractors camp. In June 2010, Rs. 1000 million has been released by Govt. of Pakistan to WAPDA for acquisition of land in Gilgit-Baltistan and released to the Land Acquisition Collector. Pre-qualification of contractors and selection of project consultants shall be started soon.
I
1 2
II Project Implementation
1 Pre-construction Activities Including Project Colony in Thor Valley, Land Acquisition, Relocation of KKH
2.1 Tendering Process Upto Award 2.2 Mobilization of Contractor(s) 2.3 Construction
12
PROJECT LAYOUT
TRANSMISSION SCHEME FOR DISPERSAL OF POWER FROM DIAMER BASHA DAM PROJECT
Diamer Basha Dam Hydro Power Project (HPP) has a generation capacity of 4500 MW and it is expected to be commissioned by year 2018-19. The location of Diamer Basha HPP is on Indus River, 315 km upstream of Tarbela Dam. The 765 kV HVAC Transmission Scheme for Dispersal of Power from Diamer Basha HPP to the major load centers in the National Grid is envisaged as under: 765 kV Transmission Lines from Basha HPP to a newly proposed 765 kV Substation at Gujar Khan (3x407 km) 765 kV Transmission Lines from Gujar Khan to a newly proposed 765 kV Substation at Lahore (2x260 km) In & Out of 500 kV Rewat Gujranwala Transmission Line at Gujar Khan A new 765 kV Substation at Gujar Khan A new 765 kV Substation at Lahore
The contract for feasibility study for evacuation of power from Northern Areas has been awarded to JV comprising of P.B. (UK), Teshmont (Canada) and Mirza Associate Pakistan on 26.06.2009.
13
Dam Spillway
(Already constructed) Irrigation Concrete/Steel Lined 45 ft to 36 ft 2997 ft (Already constructed) 485 ft (147.82 m) 9000 ft (27434 m) (Already constructed) 960 MW 800
PRESENT STATUS
The revised PC-II of the subject project stands approved by Central Development Working Party (CDWP) on 08.06.2010. Consultancy Services agreement signed with JV of Mott MacDonald UK and Conye et Billier France on 10.06.2010 and order to commence issued on 11.06. 2010. The consultants have started the survey work at site and are in process of establishing site office at Tarbela. Their experts are frequently visiting site to collect data and related information.
14
TRANSMISSION SCHEME FOR DISPERSAL OF POWER FROM TARBELA 4TH EXTENSION HYDROPOWER PROJECT
Tarbela 4th Extension Hydropower Project has a generation capacity of 960 MW and it is expected to be commissioned in six years. The location of Tarbela 4th Extension Hydropower Project is on Indus River present Tarbela Dams already constructed 4th tunnel. The 500 kV Transmission Scheme for Dispersal of Power from Tarbela 4th Extension Hydropower Project to Faisalabad the major load centers in the National Grid is envisaged as under: 500 kV Transmission Lines from Tarbela 4th Extension Hydropower Project to Faisalabad.
The estimated cost of the above Power Dispersal Scheme for Tarbela 4th Extension Hydropower Project is about US$ 150 million.
15
SALIENT FEATURES
Installed Capacity (MW) Gross Head (m) Design Discharge (m /sec) Mean Annual Energy (Gwh) No. & Type of Turbines Type of Dam Height of Dam (m) Head race Tunnel length (m) Total Base Cost (Million US$) EIRR (%) Benefit Cost Ratio Estimated construction period (years)
3
1100 320 425 4800 4 (Francis) RCC 57 17760 2155 19.9 1.83 6
Transmission Scheme for Dispersal of Power from Kohala Hydropower Project to Gujranwala Estimated Cost of US$ 130 million.
16
LOCATION This project is proposed to be constructed on Swat River about 5 Km upstream of Munda Head Works in Mohmand Agency (FATA), Khyber Pakhtunkhwa. OBJECTIVES
SWAT
CHAKDARA
RIVER
SWAT
RIVER
MALAKAND
UPPE R
SW AT L NA CA
Co Le m ft B m a an nk d Ar ea
A CANA L
LO WE R
SHERPAO
SWAT CANAL
RIG CO H T MM BA AN NK D AR EA
R L RIVE KABU
SHABQADAR
DOAB
i. ii. iii.
ER
K CA AB N UL A L RIV ER
UTMANZAI
CHARSADDA
KA BU L
RI
VE R
RISALPUR CANTONMENT
RIV
BARA
PESHAWAR
NOWSHERA
IS
LA MA B
AD
SALIENT FEATURES Type of Dam Height of Dam Gross Storage Live Storage Dead Storage Flood Storage Power Houses Installed Capacity Command Area Left Bank Culturable Command Area Project Cost Construction Period PRESENT STATUS Feasibility completed in March 2000. Revised PC-II for Detailed Engineering Design and Tender Documents amounting to Rs.652.000 million approved by CDWP in its meeting held on October 11, 2008. Expression of Interest (EOI) for short listing of Consultants for Detailed Engineering Design and Prepaation of Tender Documents invited from local and foreign consulting firms on November 23, 2010. Concrete Faced Rock fill Dam 698.820 Ft. 1.290 MAF 0.676 MAF 0.314 MAF 0.081 MAF 740 MW (Annual Energy 2407 GWh) 16940 Acres 10057 Acres Rs 119 Billion (US$ 1401 Million) 7 Years
Transmission Scheme for Dispersal of Power from Munda Dam Project to Peshawar Estimated Cost of US$ 22 million.
17
322 ft 1.20 MAF-1.48 BCM 0.90 MAF-1.11 BCM 83.4 MW (350 GWh) 3,62,380 ACRES (including new area of 84,380 Acres) 277,500 Acres
Gross Storage Live Storage Power Houses (5 Nos) Command Area Supplementing existing System of Civil & Marwat Canals
Project Benefits
Irrigated Agriculture Development Hydropower generation Socio-economic uplift of the area. Employment opportunities during the construction and maintenance of the Project. Development of Fisheries. Rs.125.60 Million
Approved by ECNEC on 25.02. 2005 Rs. 59 Billion (Equivalent to US$ 700 Million) M/s Pakistan Engineering Services (PES) JV appointed as Consultants for the preparation of feasibility and Detailed Engineering Design of the project.
Feasibility study, Detailed Engineering Design and Tender Documents completed in March, 2005 and redesigned for elevated height in 2007. Project Director appointed for construction of the Project. Invitation for pre-qualification of Contractors invited on 30th November, 2010.
18
SALIENT FEATURES
Installed Capacity (MW) Gross Head (m) Design Discharge (m3/sec) Mean Annual Energy (GWh) No. & Type of Turbine Type of Dam Height of Dam (m) Headrace Tunnels Estimated Project Cost(Billion US$) Estimated construction period 7100 445 1900 24088 20 (Francis) Gravity RCC 190 5 No (7.8 km long) 6.8 9 Years
PRESENT STATUS
Hydro Planning Organization in association with short term consultants finalized the PreFeasibility report in March 2005. ECNEC approved the PC-II for carrying out feasibility study and detailed design on 14.12.2005 for Rs.832.716 million inclusive of FEC of Rs.232.733 million. Revised PC-II amounting to Rs.2089.0 Million has been submitted to Ministry of Water & Power in October 2009. Consultancy Contract Agreement signed on 25.4.2007 for Feasibility study, Detailed Engineering design and preparation of tender document with a joint Venter of the following Consultancy firms: M/s Mott MacDonald Ltd (Lead Partner) M/s Sogreah Consultants SAS M/s Nippon Koei Co. Ltd. M/s MM Pakistan (Pvt) Ltd M/s DMC Draft Feasibility report completed by the Consultants. Draft Detailed design report submitted by the Consultants and is under review by various formations within WAPDA however, some field investigations and Model studies for Spillway, Low-Mid Level Outlets, Tailrace and Comprehensive Model are in progress at Irrigation Research Institute (IRI) Nandipur. Exploratory Adits in Dam Area have been completed. The Contract for award of Adits in Powerhouse and Surge Areas is at final stage. For 1.6 Km long exploratory Adit to MMT/ Fault zone, FWO proposal is under review.
Transmission Scheme for Dispersal of Power from Bunji Hydropower Project to Major Load Centres in the National Grid Estimated Cost of US$ 1.6 billion.
19
SALIENT FEATURES
Installed Capacity (MW) Gross Head (m) Design Discharge (m /sec) Mean Annual Energy (GWh) No. & Type of Turbine Type of Dam Height of Dam (m) Estimated Project Cost (million EURO) EIRR (%)
3
20
SALIENT FEATURES
Installed Capacity (MW) Gross Head Design Discharge (m3/sec) Mean Annual Energy (GWh) No. & type of Turbine Estimated Project Cost (Mill. US$) Implementation Period (Months) 106 435 30 436 3, Pelton 130 48
PRESENT STATUS
Feasibility Study completed by HEPO/GTZ in 1997 is updated in 2005. Construction of boundary wall for O&M colony started on 8.7.2006. Consultants, a joint venture of PES, FICHTNER, Engineering Associates appointed for Detailed Design and preparation of Tender Documents. Pre-qualification documents for Construction of Lot:2, Lot:3.1, Lot:3.2 & Lot:4 finalized after vetting from GM (CCC) and CE (NTDC). Tender submission date 10.04.2008 for Construction of O&M Staff colony. Study for Detailed Design and Preparation of Tender Documents will be completed during this month. Tender Document for Lot:2 Civil Work received from Consultants and sent to GM(CCC) for vetting. Comments from Hydro Planning are sent for incorporation. Advertisement for pre-qualification of Contractors for Lot-2, Lot-3.1, 3.2 & 4 has been placed. About 43 firms submitted the pre-qualification documents. Evaluation of EOI is in progress. Hiring of Consultants for construction supervision is in progress. Request for Technical & Financial Proposal (RFP) is being sent to pre-qualified Consultants. Pre-qualification of Contractors/ Firms is in progress. Cost of Works has been agreed by the following donors: Saudi Development Fund for Civil Works (US$ 40 Million) Kuwait Development Fund for E&M Works (US$ 37 Million) OPEC for Transmission Lines (US$ 30 Million)
21
SALIENT FEATURES
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 River Capacity (MW) Annual Energy (GWh) Gross Head (m) Design Discharge (m /s) Dam Height (m) Type of Dam Gross Storage Capacity (MAF) Power Tunnel (Km) Powerhouse Type Type of Turbines No. of Units Dam Crest Level Normal Reservoir Level (m) Spillway Crest (m) Tail Water Level (m) Total Base Cost (Million US$) Detailed Design study period Estimated Construction period (years)
3
Indus 4320 21300 210 2600 233 above bed rock Roller Compacted Concrete 1.15 3.1 (average) Underground Vertical Francis 8 957 950 930 738 5206 18-months 8
BACKGROUND
The Feasibility Study of the Project completed on 28th February, 2009 by a Joint Venture of M/s NESPAK (Lead Firm), ACE, MWH and COLENCO in association with Binnie & Partners. The Prequalification of Consulting firms/JV for phase-II preparation of Detailed Engineering Design and Tender Documents completed. The three joint ventures had been prequalified. Three pre-qualified Firms/JVs have submitted the Technical and Financial proposals on the due date i.e. 08.10.2009. Evaluation of Technical Proposal has been completed by Standing Committee under GM (P&D). The case for approval of Technical Evaluation and opening of Financial Proposals has been deferred by Authority in its meeting held on 20.02.2010. The World Bank has been requested about the status of in-eligibility of M/s Lahmeyer International, Germany.
22
23
150 0
2000
2000
2000
SALIENT FEATURES
INDUS RIVER
LAYOUT PLAN
2500
Installed Capacity Gross Head (m) Design Discharge Mean Annual Energy No. & Type of Turbine Type or Dam Height of Dam (m) Headrace Tunnel Pressure Shaft Construction Period Estimated Project Cost EIRR FIRR
496 MW 745 m 81 m /sec 2106 GWh 3, Pelton CFRD 57 m 12.5 km 1143 m 5 Year 697 Million US$ 18.4% 13.5%
3
1000 1000
DASU
1000
3000
POW ER HOUSE
JALK OT NA LA
SURGE TANK
3000
JH UL NAL A
1500
GOSHALI
HEADRACE TUNNEL
12.5 Km, 5.5 m
THOKI
GA
2000
SP AT GA H
K BA LA NA
SACHOI
GA
B
2000
2000
2500 DOGAH
3000
2500
PROPOSED ACCESS RO AD
2500
3000
SP AT GA H
BAJA KUNDAIR
2000
FSL 1510m .
DAM
LEGEND
KHEL BAIK NALA
3000 2500
BAJ AN ALA
KHEL BAIK
MOSE
2500
3000
3000
2000
2000
2000
2500
2000
PRESENT STATUS
The CDWP approved the PC-II for feasibility study on 07.03.2005 for Rs.177.80 Million including FEC of Rs. 95 Million. KfW of Germany has provided financing for carrying out Pre-feasibility studies of 03 projects in Spat Gah and Feasibility study of Lower Spat Gah Hydropower Project. The feasibility report has been prepared by a Joint Venture: ILF (Germany), Pyory (Austria) and ACE (Pakistan) and report has been finalized in June 2010. The detailed engineering design and tender documents would take 24 months.
FINANCIAL REQUIRMENTS
The financial requirements for pre-construction and construction activities are : Year Million US $ 1 29.0 2 30.3 3 127.3 24 4 100.1 5 105.0 6 146.9 7 154.3
1500
1500
Installed Capacity Gross Head (m) Design Discharge Mean Annual Energy No. & Type of Turbine Type or Dam Height of Dam (m) Headrace Tunnel Pressure Shaft
KAYAL KHW AR
ER RIV
2000
POW ER HOUSE
2000 1500 1000
S DU IN
SURGE TANK
1000
SARCHOY
ACCESS ROAD
1500
PALAS VALLEY
R NA CHO
2500
3000
SALIENT FEATURES
1000
2000
1500
KKH
1500
2500
LAYOUT PLAN
A AB AN ILK SH A AL DN
3000
1500
3000
2500
LA
2500
55 m 18.5 km 1200 m Construction Period 5 Year Estimated Project Cost 763 Million US$ EIRR 20.8% FIRR 15.6%
2000
DAM
2000
IAL NALA
KUZ PARO
2500
LEGEND
2000 RIVER NULLAH HEADRACE TUNNEL ROAD (KKH) VILLAGE
SHAR
2500
2500
2000
3000
PRESENT STATUS
The CDWP approved the PC-II for feasibility study on 07.03.2005 for Rs.196.70 Million including FEC of Rs.133.900 Million. KfW of Germany has provided financing for carrying out Pre-feasibility studies of 03 projects in Palas valley and Feasibility study of Lower Palas Hydropower Project. The feasibility report has been prepared by a Joint Venture: ILF (Germany), Pyory (Austria) and ACE (Pakistan) and report has been finalized in June 2010. The detailed engineering design and tender documents would take 24 months.
FINANCIAL REQUIRMENTS
The financial requirements for pre-construction and construction activities are : Year Million US $ 1 32.0 2 33.5 3 140.2 25 4 110.2 5 115.6 6 161.8 7 169.6
2500
2500
3000
2500
2000
Feasibility Study Report completed on Jan. 26, 2006. PC-II for Detailed Engineering Design and Tender Documents of the Project amounting to
Rs. 818.00 Million submitted on June 23, 2006 for approval of ECNEC which is awaited. PC-I for land acquisition and resettlement of Affectees under approval of ECNEC. Pre-qualification of consultants for detailed engineering design completed. RFP for inviting financial and technical proposals of Consultants for detailed engineering design in progress.
26
SALIENT FEATURES
Installed Capacity (MW) Gross Head (m) Design Discharge (m3/sec) No. & Type of Turbines Mean Annual Energy (Gwh) Height of Dam (m) Tunnel Length (km) Estimated Project Cost (Billion US$) Study period (month) 2800 138 2900 8, Francis 14095 60 19.8 6 24
PRESENT STATUS
Identified by MONENCO in Inventory and Ranking Study in November 1984 and reviewed by Hydro Planning Organization(HPO), WAPDA Capacity reviewed and updated by Hydro Planning Organization (HPO). Cost of Feasibility study is Rs.719.628 Millions. Local Cost Component Rs.416.488 Millions Foreign Cost Component Rs.303.139 Millions
PC-II for Feasibility Study submitted by MOW&P to Planning and Development Division for approval by the Planning Commission. Working Paper received from Planning and Development Division (Energy Wing), Planning Commission. Para-wise replies to the querries in working paper made on February 24, 2010.
27
SALIENT FEATURES
Installed Capacity (MW) Gross Head (m) Design Discharge (m3/sec) No. & Type of Turbines Mean Annual Energy (Gwh) Height of Dam (m) Tunnel Length (km) Estimated Project Cost (Billion US$) Study period (month) 24 2800 150 2600 8, Francis 15230 104 18.0 6
PRESENT STATUS
Identified by MONENCO in Inventory and Ranking Study in November 1984 and reviewed by Hydro Planning Organization, WAPDA. Capacity reviewed and updated by HPO. Cost of Feasibility study is Rs.731.233 Millions. Local Cost Component Foreign Cost Component Rs.373.731 Millions Rs.357.502 Millions
PC-II for Feasibility Study has been approved by CDWP on 17.09.2009. GoP have issued administrative approval for execution of project studies on 27.10.2009. Consultants/Jvs have submitted EOI documents. The evaluation for prequalification of Consultants will start shortly.
28
SALIENT FEATURES
Installed Capacity Gross Head Design Discharge Mean Annual Energy No. & Types of Turbine Estimated Project Cost Study Period (months) Implementation Construction Period 80 MW 237 m 40 m3/sec 350 GWh 4, Pelton US $ 70 Mill 18 Months 48 Months
PRESENT STATUS
Feasibility was completed by HEPO, WAPDA with GTZ under Technical Assistance Program. PC-II for Detail Engineering Design and preparation of Tender Documents approved by CDWP on 30.04.2007 for Rs. 120.376 million. 7 No. Firms/Joint Ventures submitted their EOI Documents for Pre-qualification. 5 Firms/Joint Ventures were prequalified and RFP documents prepared on QBS were issued to shortlisted firms/JVs. The evaluation of Technical Proposal was done by Project Committee and Standing Committee (SC) headed by GM(P&D). The evaluation of Technical Proposals was submitted to Authority for vetting the ranking and to allow for opening of Financial Proposals. On 19/02/2009, Authority directed to revise the proposals on the basis of Quality Cost Based Selection (QCBS) instead of QBS, in addition to evaluating the technical proposals taking into account the previous performance of firms specifically on WAPDA projects. The RFP was revised on QCBS and got vetted from CCC and donor agency (AFD) and issued to prequalified Firms/JVs. Authroity approved final evaluation and ranking of Technical Proposal and directed concerned authorities for opening of Financial Proposal. The Standing Committee opened Final Proposals on 26.02.2010 and ranked the Consulting Firms on the basis of Financial and Technical Proposals (QCBS). The office of General Manager (P&D) put up case to Authority for final approval and for negotiations with top ranked Firms. Authority approved ranking and asked the Project Authorities for negotiation with top ranked firm. Contract negotiations with top ranked firm completed and Joint Note was put to Authority for approval. Authority approved Contract Agreement on 27.09.2010. Contract Agreement has been signed between WAPDA and Phandar Hydro Consultants i.e. M/s. FHC-JV on 22.10.2010.
29
PRESENT STATUS
Feasibility report has been completed by HEPO (WAPDA) with technical collaboration of GTZ of Germany in 2002. PC-II for Detail Design and Tender Documents was approved by CDWP in its meeting held on 2711-06 for Rs. 91.243 million. 5 Firms/Joint Ventures were prequalified and RFP document were issued on Quality Base Selection (QBS) Method. The evaluation of proposal was done by project committee and Standing Committee and report was submitted to Authority. In February 2009 the Authority directed to revise RFP on Quality Cost Based Selection (QCBS) instead of QBS, in addition to evaluating the technical proposals taking into account the previous performance of firms specifically on WAPDA projects. In March 2009 during the meeting with kfW in Frankfort Germany, KfW offered to finance small to medium size Hydropower projects in collaboration with AFD. Consequently WAPDA sent two feasibility studies of Basho and Harpo Hydropower Projects for consideration. AFD/KfW fact finding mission visited the projects sites from 16th to 18th July 2009. The mission committed to finance updation/review of feasibility study from GRANT in the 1st Phase and after successful review/updation of feasibility financing will be provided for Detailed Engineering Design, preparation of Tender Documents and construction of projects from LOAN in the 2nd Phase. Accordingly WAPDA prepared RFP documents for review of feasibility study only and submitted to AFD/KfW. AFD/KfW has suggested certain amendments in RFP documents which are being incorporated and the document are under process through Central Contract Cell (CCC), WAPDA. M/s ACE ranked 1st in the composite evaluation under QCBS(80:20) for updation of feasibility of Basho HPP. M/s Afd indicated that they are not convinced to award the contract to M/s ACE. Keeping in view the above situation, bidding process for Basho HPP has cancelled with the approval of worthy Chairman WAPDA. New process of hiring the consultant has been started under the guidance of M/s Afd to undertake the updation of feasibility study.
30
SALIENT FEATURES
Installed Capacity (MW) Gross Head (m) Design Discharge m /sec Mean Annual Energy (Mil. KWh) No. & Type of Turbine Project Base Cost (Mill US$) EIRR (%) Implementation Period (Years)
3
31
SALIENT FEATURES
Installed Capacity Gross Head Design Discharge Energy Generated Penstock Length No. of Units Project Cost (including T. Line) Study Period for updation/ review of Feasibility Study Implementation Construction Period 33 MW 716 m 5.5 m3/sec 206 GWh 2885 m 3 Pelton US$ 44.6 Mill 7 Months 48 Months
PRESENT STATUS
Feasibility report has been completed by GM Hydro Planning Office (WAPDA) with the technical collaboration of GTZ of Germany in February 2002. PC-II for detailed Design and preparation of Tender Documents has been approved by CDWP on 22-11-2008 at a cost of Rs. 113.809 Million. 9 Firms/Joint Ventures submitted EOI documents for prequalification. 4 Firms/JVs have been prequalified. In February 2009 the Authority directed to revise RFP on Quality Cost Based Selection (QCBS) instead of QBS, in addition to evaluating the technical proposals taking into account the previous performance of firms specifically on WAPDA projects. In March 2009 during the meeting with kfW in Frankfort Germany, KfW offered to finance small to medium size Hydropower projects in collaboration with AFD. Consequently WAPDA sent two feasibility studies of Basho and Harpo Hydropower Projects for consideration. AFD/KfW fact finding mission visited the projects sites from 16th to 18th July 2009. The mission committed to finance updation/review of feasibility study from GRANT in the 1st Phase and after successful review/updation of feasibility financing will be provided for Detailed Engineering Design, preparation of Tender Documents and construction of projects from LOAN in the 2nd Phase. Authority has approved combined ranking of firm. EAD, GoP has approved financing agreement with Kfw, Germany.
32
PRESENT STATUS Desk Study and field reconnaissance initiated. The project is identified by MECO under CIDA grant during 1984 for a capacity of 710 MW. The capacity has been upgraded 2800 MW by HPO, WAPDA.
33
PRESENT STATUS The project is identified by MECO under CIDA grant during 1984. The capacity has been studied by HPO, WAPDA.
34
SALIENT FEATURES Installed Capacity Estimated Annual Energy Plant Factor Type Net Head Tunnel length Construction Period Estimated Cost Proposed Interconnection BACKGROUND Letter of Interest (LOI) was issued by PPIB on 15-11-2005 under the 2002 Power Generation Policy to a private power company, M/s SK Hydro (Pvt.) Ltd. for the development of the project. The company hired Mott McDonald as consultant for conducting the feasibility study of the project. A Panel of Experts monitored the feasibility study as per the requirements of the 2002 Policy. The Feasibility Study was completed in March 2008 and has been subsequently approved by the PPIB. PRESENT STATUS The tariff approved by NEPRA on 18-11-2008 The Generation License is under process in NEPRA LOS issuance is in process in PPIB 840 MW (4 210 MW, Pelton Wheel) 2958.1 GWh 40.2% Run-of-River 823.5 meters 21.4 km 6 years US $ 1138.93 million (2008 level) 500 kV line to Neelum Jhelum (85 km)
35
SALIENT FEATURES
Installed capacity Mean Annual Energy Dam height Dam Crest Reservoir Maximum Operating Level Live Storage Pressure pipe/tunnel Design discharge Maximum gross head Plant factor 30 MW 212.7 GWh 140 m 450 m 2600 ft 200,000 Acre-ft 1500 m 25 m 3/s 168 m 80.9%
PRESENT STATUS
Project identified by Hydro Planning Organization, WAPDA. PC-II for preparation of feasibility study is in process of approval from WAPDA.
36
SALIENT FEATURES Installed Capacity Firm Capacity Estimated Annual Energy Plant Factor Type Gross Head Tunnel length Construction Period Estimated Cost Proposed Interconnection BACKGROUND Feasibility Study of the project was carried out under the supervision of SHYDO by Sir William Halcrow & Partners Ltd. UK in 1996. LOS for developing the project in the private sector was issued by the Government of KHYBER PAKHTOONKHWA on 17-07-1996 under the 1995 Hydel Policy. It was originally valid upto 16.01.98 and was extended from time to time and as per last extension, it was valid until December 31, 2002 and its validity has now expired. The original LOS was issued to M/s Sachal Engineering who later entered into partnership with M/s Synergic Hydro Asia and proposed to develop the project with their collaboration. However, the project development could not be started mainly because the up-front tariff offered by GOP in the 1995 Hydel Policy was withdrawn in 1997 and subsequent tariff negotiations failed to reach a satisfactory conclusion. CURRENT STATUS The foreign partners ( M/s Synergic Energy) of the sponsors have withdrawn and it does not seem likely that they would be able to implement the project because of lack of expertise/resources. However, the sponsors have not withdrawn their right to develop the project. WAPDA was offered to implement the project with the collaboration of the Govt. of Khyber Pakhtoonkhwa. However, the Govt. of Khyber Pakhtoonkhwa will negotiate with the sponsors for an amicable solution for implementation of the project. 84 MW (3 28 MW, Francis turbines) 19 MW 346 GWh 47% Run-of-River 201 meters 6.5 km 4 years US $ 133 million (2002 level) 132 kV line to Madyan Grid Station (110 km)
37
PRESENT STATUS
The proposed Mahl Hydropower Propjet was originally offered by Private Power Infrastructure Board (PPIB) in 2005 to China International Water and Electric Corporation (CWE) and no response was received. It was thereafter transferred to Govt. of AJK for implementation of Project through public private partnership. The Govt. of AJK on 16.9.2009 and in April 2010 requested WAPDA to execute a MOU to implement the Project as a joint venture on terms mutually agreed upon. AJK Govt. has requested WAPDA to prepare feasibility and detailed engineering of this project. WAPDA Authority accorded approval for taking up project implementation under Public Private Partnership mode after completing all the codel formalities with Government of Pakistan and Government of AJK.
38
39
FEATURES
Installed Capacity Gross Head Design Discharge Mean Annual Energy 100 MW 10 m 135 m3/sec 465 million KWh Cheaper power to National Grid
40
The estimated cost of the above Power Dispersal Scheme for Neelum-Jhelum Hydroelectric Project is about US$ 225 million.
41
42
43
44
45
REGIONAL DAMS
Phase-I
BALOCHISTAN Sukleji Dam Basol Dam Badinzai Dam
PHASE-II (2010-2014)
SINDH
Salari Dam Nali Dam Khenji Dam Naing Dam Sita Dam Project Upper Makhi Dam Phase-II
46
SALIENT FEATURES
Type of the Dam Height of Dam Length of Dam Gross Storage Mean Annual Runoff Culturable Command Area Cropped Area Cropping Intensity Hydropower Generation Construction Period Cost of the Project EIRR Earth Core Rockfill Dam (ECRD) 102 FT 1696 FT 36,484 AF 40,365 AF 10,000 Acres 20,000 Acres 200% 300 KW 03 Years Rs.12.412 Billion 12.41%
CURRENT STATUS
The Project was approved by ECNEC in its meeting held on September 3, 2009. Ground Breaking Ceremony was graced by the President of Pakistan on January 1, 2010. Revised PC-1 amounting to Rs. 12.412 Billion cleared by CDWP in its meeting held on June 29, 2010 Letter of Acceptance issued to Techno Engineering-RSWI JV on February 15, 2010. The contractor is being mobilized.
47
SALIENT FEATURES
Height of Dam Gross Storage Live Storage Cultivable Command Area Cropped Area Cropping Intensity Hydropower Generation Cost of the Project EIRR 118 FT 121,790 AF 87,264 AF 25,000 Acres 50,000 Acres 200% 450 MW Rs.18.085 Billion 15.89 %
STATUS
PC-I amounting to Rs. 3.175 Billion approved by ECNEC in its meeting held on September 3, 2009. Revised PC-1 amounting to Rs. 18.085 Billion cleared by CDWP in its meeting held on June 29, 2010 for approval of ECNEC Ground Breaking Ceremony was graced by the President of Pakistan on January 2, 2010. Letter of Acceptance issued to M/s Sinohydro-MAJ JV on February 15, 2010. The Contractor mobilized to site w.e.f June 30, 2010. Contractor started construction of site camps, soil investigations. Completed the topographic survey of Dam Axis, Spillway and the topographic survey of command area.
48
SALIENT FEATURES
Type of Dam Height of Dam Length of Dam Catchment Area Mean Annual Flow Gross Storage Capacity Live storage Capacity Reservoir Area Spillway Design Flood Cultivable Command Area Cropped Area Cropping Intensity Power Generation Cost of the Project EIRR Earth Core Rock fill Dam 138 FT 3,117 FT 161 Sq. Miles 38,428 AF 66,200 AF 26,000 AF 1,544 Acres 47,675 Cusecs 15,000 Acres 30,000 Acres 200% 150 KW Rs.10.184 Billion 13.60%
STATUS
The Project was approved by ECNEC on Sept. 03, 2009. Ground Breaking graced by the President of Pakistan on January 21, 2010. Revised PC-I amounting to Rs. 10.184 billion cleared by CDWP in its meeting held on June 29, 2010 approval of ECNEC. Bids for construction opened on January 05, 2010. Five Firms submitted bids (M/s.Sinohydro-MAJ JV, M/s.Dongfang Electric Corporation-Technical Associates-Habib Construction JV, M/s.Xinjiang Beixin-Matracon JV, M/s.NEIE-LAC-JV, M/s.CWE). Letter of acceptance issued to M/s Dong Fang-Technical Assiciates and Habib Construction JV at a contract price of Rs.6.048 billion. The Contract agreement is in process for signing. The Contractor is being mobilized.
49
JANDOLA
KHIRGI
COMMAND AREA
(AREA= 70,000 ACRES)
DIS TY N O. 1
TO BU NNU
AY LW
A CK TR
DISTY
N O. 5
TANK
DIS
TY
D IST
MIN
NO .
SHAHBAZ
4
Y NO .6
CHAISAN KAC H
OR
DISTY NO. 7
T DIS YN
BAL OC H
R ANWAL
O. 2
KAHU C HINA
HA N
TO .K D.I
Objectives
Storage of flood water for: Irrigated agriculture development with high efficiency irrigation system for optimal use of land and water resources. Hydro power generation. Flood mitigation. Fisheries development. Recreation. Main Dam Height of Dam Gross Storage Live Storage Cultivable Command Area Cropped Area Cropping Intensity Hydropower Generation Cost of the Project EIRR CURRENT STATUS
On the desire of Govt. of Khyber Pakhtunkhwa the project has been taken in Phase-I. WAPDA initiated Detailed Engineering Design and Tender Documents to completed by January 2011. PC-I prepared and under review for finalization.
292 FT 345,000 AF 289,000 AF 35,000 Acres 70,000 Acres 200% 25.5 MW Rs. 19.90 Billion 14.03 %
50
51
SALIENT FEATURES Dam Type Maximum Height / Length Gross Storage Cultureable Command Area Cropped Area Cropping Intensity Installed capacity Estimated Cost EIRR Central Core Zoned Dam 179 ft / 2,500 ft 1,405,000 AF 80,000 Acres 160,000 Acres 200% 3.5 MW Rs.26.463 Billion 16.37%
CURRENT STATUS
PC-I Proforma (New Site) cleared by CDWP in its meeting held on November 19, 2009 and cleared for approval of ECNEC. Detailed Engineering Design and Tender Documents of the New Site is in progress Studies of the Project (New Site) in progress, to be completed by January 2011. Construction bids invited on December 13, 2010.
52
SALIENT FEATURES
Type of Dam Rockfill Height of Dam Length of Dam Reservoir Capacity Cultivable Command Area Cropped Area Cropping Intensity Cost of the Project EIRR Earth Core 184 ft 2323 ft 50,695 AF 13000 Acres 26,000 Acres 200% Rs1.790 Billion 12.50%
STATUS
PC-I amounting to Rs. 1.790 Billion approved by ECNEC in its meeting held on September 3, 2009. Tenders for construction invited on December 23, 2010.
53
SALIENT FEATURES
Type of Dam Height of Dam Reservoir Capacity Cultivable Command Area Cropped Area Cropping Intensity Power Generation Cost of the Project EIRR Concrete Gravity 132 ft 66,900 AF 8,000 Acres 16,000 Acres 200% 300 KW Rs.1.692 Billion 14.18%
STATUS
PC-I amounting to Rs. 1.692 Billion approved by ECNEC in its meeting held on September 3, 2009. Tenders for construction invited on December 29, 2010.
54
SALIENT FEATURES Dam Type Height of Dam Gross Storage Capacity Dead Storage Capacity Live Storage Capacity Culturable Command Area Cropped Area Cropping Intensity Installed Capacity Estimated Cost EIRR CURRENT STATUS
Earth Core Rock Fill Dam 194 ft 300,000 AF 140,000 AF 160,000 AF 40,000 Acres 80,000 Acres 200% 4.2 MW Rs.28.153 Billion 13.18%
PC-I amounting to Rs. 16.924 Billion approved by ECNEC in its meeting held on September 3, 2009. Revised PC-1 amounting to Rs. 28.153 Billion submitted to Ministry of Water & Power for arranging approval of ECNEC
Tenders for construction received on July 16, 2010. Technical proposal evaluated, three firms M/s NEIE-SMADB-LILLY-RMS JV, M/s Xinjiang Bexian-Metrocon JV & M/s Sinohydro-MAJ JV post qualified for opening of financial proposals. Financial proposals opened on November 8, 2010. Evaluation of Financial Proposals in process.
55
. 2. Objectives of the Project iv. Assured irrigation supplies to the existing irrigation schemes. v. Hydropower generation vi. Water supply. vii. Socio-economic uplift viii. Women emancipation.
SALIENT FEATURES Type Height of Dam Length of Dam Gross storage Capacity Reservoir Capacity Command Area Cropped Area Cropping Intensity Power Cost of the Project EIRR Earth core Rock fill 302 Ft 1477 Ft 85,363Acres ft 85363 AF 41,729 Acres 83,498 Acres 200% 5.8 MW Rs.14.208 Billion 15.25%
CURRENT STATUS The Project was approved by ECNEC in its meeting held on September 3, 2009. Updated PC-1 amounting to Rs. 5.828 Billion prepared and under Review for approval of ECNEC Tenders for construction invited on December 27, 2010.
56
SALIENT FEATURES
Type of Dam Height of Dam Length of Dam Catchment Area Mean Annual Flow Gross Storage Cultivable Command Area Cropped Area Cropping Intensity Cost of the Project EIRR Earth Core Rock fill 154 FT 1426 FT 410 Sq. Miles 50,274 AF 69,739 Acres 15,000 Acres 30,000 Acres 200% Rs.5.828 Billion 12.7%
STATUS
The Project was approved by ECNEC in its meeting held on September 3, 2009. Updated PC-1 amounting to Rs. 5.828 Billion prepared and under Review for approval of ECNEC Tenders for construction received on July 20, 2010. M/s. DESCON Engineering submitted the bid. Evaluation of bid is under process.
57
SALIENT FEATURES
Type of Dam Height of Dam Length of Dam Catchment Area Mean Annual Flow Gross Storage Capacity Live Storage Reservoir Area Design Flood Cultivable Command Area Cropped Area Cropping Intensity Installed Capacity Cost of the Project EIRR Concrete Gravity 105 FT 460 FT 417 Sq. Km 136,426 AF 89,600 AF 48,600 AF 2,790 Acres 46,900 Cusecs 18,000 Acres 36,000 Acres 200% 200 KW Rs.8.609 Billion 19.95%
STATUS
Bids for construction opened on December 21, 2010 PC-I approved by ECNEC on September 3, 2009. Updated PC-I amounting to Rs. 8.609 Billion submitted to Ministry of Water & Power for approval of ECNEC.
58
Salient Features Dam Height Dame Length Gross Storage Capacity Canal Capacity Command Area Power Generation Status PC-II Proforma (Rs. 38.603 million) for Feasibility Study, Detailed Engineering Design & Tender Documents was approved by DDWP on Oct. 10, 2005. Inception report received from the Consultants in August 2006. The Consultants concluded that the dam at site A is not technically feasible and recommended to carryout the studies at site X. PC-II for carrying out the studies at Site C is under preparation. Consultants M/s. BARQAAB along with WAPDA Engineers visited the site on June 10-14, 2008 and will submit their report on Site-C shortly. 110 ft 1466 ft 42,000 AF 70 Cusecs 12000 Acres 100/150 KW
59
Useable Flows Marginal Flows Hazardous Flows Treatment Plants to be Installed Benefits of Pilot Project
28% (376 cfs) 23% (309 cfs) 49% (658 cfs) 5 Nos. (40 cfs each)
40 cfs of water after treatment will irrigate upto 10,000 acres of barren land Project Base Cost. = Rs.1984.00 M Project Revenues (Annual) = Rs. 566.00 M Project O&M Cost (Annual) = Rs.190.00 M Net Annual Savings = Rs.376.00 M Project Life = 30 years Benefit Cost Ratio = 1.53:1 EIRR = 20.10 %
Total Project: Total additional water available after treatment Additional area to be irrigated Net annual benefits (Revenue) Cost of one plant of 40 cfs (Pilot Project) Cost of five plants of 40 cfs each 985,000 AF 350,000 Acres Rs13.227 Billion Rs2 Billion/US$ 24 Million Rs10 Billion/US 120 Million
This project is submitted for the US Assistance under FODP for 05 Plants of 40 cfs for treatment of effluent water for drinking, agriculture, fishing and other economic uses.
60
CANAL LINING
Canals / Distributaries Lining 11% lined (5100 km out of 46,400 km length) Proposed Lining of Canals (Sindh) Rohri Canal Dadu Canal Rice Canal Benefits Saving of 2881 cusecs (5700 AF per day) can irrigate an additional area of 0.492 MA Agriculture benefits of Rs11.305 billion per year from saving of canal water seepage Reduction in water-logging Increase in yields and increase in conveyance efficiency Provision of extra jobs and contribution to enhancing per capita income. COST / BENEFITS OF THE PROJECT
CANALS \ CCA (M Acres) ROHRI CANAL / 2.46 DADU CANAL / 0.48 RICE CANAL / 0.47 TOTAL / 3.41 LENGTH DISCHARGE SAVINGS MILES CUSEC CUSEC 208.0 131.5 82.0 16,500 13,600 5,600 35,700 1736 755 777 3,268* ADDITIONAL AREA ACRES 520,800 226,499 39,072 ADDITIONAL Cost of Lining BENEFITS (Rs. In Billion) Rs M/Year 9912 5104 354 15,370** 135 65 52 252***
***Rs 388.6 M / km
STATUS A team of M/s Huesker Germany, headed by Mr. Christoph Hessing arrived in Pakistan on April 14,2010 and visited Sukkur Barrage and three canals on April 15-16,2010. M/s. Huesker Germany confirmed after site visit that lining under flowing water is technically feasible using Incomat material. Pilot Project of 5km length at Rohri Canal from rd 135 to RD 150 (26 miles d/s of Sukkar Barrage) to be implemented before taking up entire project. M/s. Huesker have agreed to take-up pilot project and start the work within two months time. PC-I for Pilot project is to be completed by June 30,2010 costing Rs.2,413 million for 5 km. Pilot Project to be implemented in 9 months. Cost of Pilot Project Cost of Total Project Total = = = Rs2.5 Billion / US$ 30 Million Rs252 Billion/ US$ 3,000 Million Rs.254.5 Billion/US$ 3,030 Million
Pilot Project/Main Project in submitted for German Assistance in the field of Lining of Canal and Transfer of technology of the production/local manufacturing of INCOMAT Material produced by M/s HUESKER Germany
61
Sr. #
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Project
Reservoir Project Cost Capacity 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 2021-22 2022-23 2023-24 2024-25 2025-26 2026-27 2027-28 2028-29 2029-30 (Rs. Million) (MAF)
2675 3465 1600 652
Status
Under Construction
Allai Khwaar Khan Khwar Duber Khwar Jinnah Neelum Jhelum Diamer Basha Golen Gol Kurram Tangi Tarbela 4th Ext. Munda Kohala Keyal Khwar Phandar Basho
ROR
1675 1790 464
8392 3929
ROR
3032 4300 1296 499
ROR
240 400 300
9127 940
ROR
5250 9415 15932 18045 19674 22631 23718 15691
ROR
240 49920 47040 64080 76240 79120 88400 89360 65680 37280 32080 32400
6.50
2121 4453 3306 2574
ROR
10201 21117 13671 8504
ROR
17440 21600 11280 6080
53493 56400
14400 14400 14400
7200
7200
14400
740 1100 122 80 28 33 70 4320 7100 600 496 665 2800 2800 800 3000 2200 1600 520
0.70
17240 17240 34480 34480 34480 34480
ROR
459 331 1083 1918 3060 2990 1809
ROR
1120 1680 1680 1120
ROR
640 1280 1280
ROR
720 1440 1440
Under Study
15 16 17 18 19 20 21 22 23 24
Harpo Lawi Dasu Bunji Akhori Lower Spat gah Palas Valley Pattan Thakot Dudhnial
ROR
58 59 845 1643 2351 1659 455
ROR
31200 62400 62400 93600 124800 124800 62400 62400
7070 624000
27352
0.67
54704 54704 82056 109408 109408 54704 54704
0.06
26400 26400 52800 52800 52800 52800
6.00
4912 4912 9824 9824 9824 9824
ROR
5336 5336 10672 10672 10672 10672
ROR
72000 96000 96000 96000 72000 48000
0.06
72000 96000 96000 96000 72000 48000
0.16
21600 28800 36000 36000
1.00
81000 108000 108000 108000 81000 54000
144000 540000
50400 33600
Future Projects
25 26 27 28
0.12
50400 67200 67200 67200
0.05
99000 132000 132000 132000 99000 66000
5.50
36000 48000 60000 60000 36000
5.00
Total
ROR* Run of River
36111
12558
80996 107285 146837 146179 197722 287151 279331 300464 286648 313184 340400 382400 304424 354600 340800 389400 364800 328200 313200 209400 135600
Detailed Design & Tender Documents
Feasibility Study
Implementation
5022 MW 2469 MW
Demand
100000
Supply
113695 106565
80000
80566 76200
MW
60000 36217 20594 20000 17008 0 2009 2010 2015 19477 24474 33028
54359 52909
40000
2020
2025
2030
Years
*Projected demand includes captive power also. Average growth rate is expected to be about 8%
63