You are on page 1of 12

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW).

At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

INDEX
S. NO. 1.0 1.1 1.2 1.3 1.4 1.4.1 1.5 1.6 1.7 1.8 2.0 3.0 4.0 5.0 5.1 5.2 5.3 5.4 5.5 6.0 PARTICULAR PROJECT DESCRIPTION INTRODUCTION DETAILS OF THE PROJECT AREA LOCATION MAP RAW MATERIAL REQUIREMENT PAGE NO. 1 1 1 3 4 4 5 6 6 7 4

COMPOSITION OF PPC & PSC PROCESS DESCRIPTION

ANTICIPATED ENVIRONMENTAL IMPACTS

DESCRIPTION OF THE ENVIRONMENT SOCIO ECONOMIC ENVIRONMENT

ENVIRONMENTAL MONITORING PROGRAM ADDITIONAL STUDIES PROJECT BENEFITS ENVIRONMENTAL MANAGEMENT PLAN AIR POLLUTION MANAGEMENT WATER ENVIRONMENT MANAGEMENT NOISE POLLUTION MANAGEMENT SOLID WASTE MANAGEMENT GREEN BELT DEVELOPMENT/PLANTATION CONCLUSION

7 7 7 8 8 8 8 9

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

EXECUTIVE SUMMARY 1.0 1.1 PROJECT DESCRIPTION INTRODUCTION


JK Lakshmi Cement Limited (JKLCL) is a part of JK Organization. With a diverse portfolio ranging from JK Tyres Ltd., JK Sugar Ltd. and JK Agri Genetics Ltd. to Fenner (India) Ltd., JK Paper Ltd. and JK Lakshmi Cement Ltd., JK Organization has touched the lives of millions of individuals. M/s JK Lakshmi Cement Limited (JKLCL) has proposed to set up a Cement Grinding Unit of 1.5 MTPA and DG sets (2X6 MW) at Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa). As per EIA Notification dated 14th September 2006 and as amended on 1st December, 2009, this project falls under Category B, Project or Activity-3 (b) 4, therefore this project requires Environmental Clearance from SEIAA, Orissa.

1.2

DETAILS OF THE PROJECT AREA.


TABLE - 1 SALIENT FEATURES OF THE PROJECT

S. No. A. B. 1. 2. 3. 4. 5. 6. C. 7. 8.

Particulars Nature & Size of the Project

Details Proposed Cement Grinding Unit of 1.5 MTPA and DG sets (2X6 MW)

9.

Location Villages Ghantikhal, Radheyshampur Tehsil Athagarh District Cuttack State Orissa Latitude 20 31'19.62 to 20 32'17.50"N, 85 44'1.06"E to 85 44'31.17"E Longitude Toposheet No. 73 H/10, 73 H/11, 73 H/14, 73 H/15 Environmental Setting of the Study area NH - 42 is approx. 2.3 km in North direction National Highway from the proposed project site. SH-65 is approx. 4 km in NW direction from State Highway the proposed project site. Ghantikhal is approx. 1.0 km in South Nearest Railway Station direction from proposed project site. Rajathagarh is approx. 4.2 km in North direction from proposed project site.
3

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

10. 11. 12.

Nearest Airport Nearest Village Nearest Town Nearest Water bodies

13. Eco sensitive Zone (National Park, Wildlife Sanctuary, Biosphere reserve wildlife corridors etc.) Within 10 km radius of the project site.

Bhubaneswar is approx. 32 km in SSE direction from proposed project site. Radheyshampur is approx. 0.5 km in North direction from proposed project site. Cuttack is approx. 16 km in SE direction from proposed project site Sapua River is approx. 4.0 km in SE direction from proposed project site. Mahanadi River is approx. 4.3 km in SE direction from proposed project site. No Eco sensitive Zone viz. National Park, Wildlife Sanctuary, Biosphere reserve wildlife corridors falling with the 10 km radius of the project site.

14.

15.

16. D. 17. 18. 19. 20.

E. 21. 22. 23.

Kapivas R.F. ( 8.5 Km in NW) Deulia R.F. (~5.0 Km in NW) Ranibania R.F. (~5.7 Km in NW) Gadabola R.F. (~8 Km in NW) Adala R.F. (~7.0 Km in NW) Reserved / Protected Forest Oringa R.F. (2.5 Km in W) within 10 km. radius (Boundary Subasi R.F. ( in W direction) to boundary distance) Sukasana R.F. (7.5 Km in SW) Brahmanbasta R.F. (1.0 Km in E) Sankhaipoi R.F. (~5.2 Km in NE ) Baula R.F.(6.8 Km in E) Baniabandha R.F.(~10 Km in N) Suniamoh R.F. (5.0 Km in E ) Historical & Archeological No Historical & Archeological site falling Important Place within 10 km radius of the project site Major Requirements Land 119 Acres (Proposed). Water Requirement 700 m3/day from Groundwater/Surface Water Manpower Requirement 80 Person Power The proposed grinding unit would require approximately 10.85 MW (say 11 MW) of power. This requirement shall be met from the Orissa Electricity Board / DG sets (for Cost Details Capital cost of the project Rs. 155 crores Capital Cost for EMP Rs. 12 Crores Recurring Cost/annum Rs. 1.10 Crores/annum

Source: Pre-feasibility Report & Site Visit Report

1.3

Location Map

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

1.4 Raw Material Requirement


M/s JK Lakshmi Cement Limited

Figure no. 1.3 Location Map

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

The raw materials required for the proposed grinding unit & productions of PSC (Portland Slag Cement) & PPC (Pozollana Portland Cement) are as mentioned below: Table 2 Source Cement plant, Durg (C.G.) Aarti Steel Ltd. Steel plants of Jajpur, Angul & other steel plants RSMML Rajasthan mines / Visakhapatnam (chemical gypsum) Indian Oil Corporation depot

Raw Material Clinker Fly ash Blast furnace slag

Quantity PPC/PSC(TPD) 3150 for PPC 2250 for PSC 1125 for PPC 2025 for PSC

Distance

Mode of transportation By Road / Railway wagons By Road By Road

650 km Adjacent Nearby industries exist within 100 km 1500 km Rajasthan / 500 km Visakhapatnam Bhubaneswar 50 km

Gypsum

225 for PPC 225 for PSC

By Railway wagons

HSD/ Furnace oil for DG set

2500 KL per annum

By Road

Source: Pre-feasibility Report

1.4.1
S.No. 1. 2. 3. 4.

Composition of PPC & PSC


Raw Material Clinker Fly ash Gypsum Slag Source: Pre Feasibility Report % for PSC 50 Nil 5 45 % for PPC 70-75 20-25 5 Nil

1.5

PROCESS DESCRIPTION
A. Clinker Handling
6

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

Clinker from Durg Cement Plant will be received by railway wagons and will be unloaded by wagon tippler. Clinker will be transported to clinker silo by covered belt conveyor. Then transported to clinker hopper at cement grinding section by covered belt conveyor. B. Fly Ash Handling Transported to the plant by road in closed bulk tankers From the silos to the mill by pneumatic system C. Gypsum storage, handling and crushing Gypsum received by wagon will be unloaded by wagon tippler or manually at the storage yard designated for gypsum storage. Gypsum shall be crushed in the roll crusher and bag filter with adequate capacity will be installed in crusher. Gypsum shall be conveyed to cement mill hopper for feeding to cement mill. D. Cement Production Clinker and gypsum extracted from their respective hoppers, fed to the Roller Press and Cement Mill (closed circuit) Fly Ash and Slag extracted from their respective Silo/hoppers, fed to the Cement Mill directly, Ground to the desired fineness and ground cement is stored in cement silos E. Cement Packing and Dispatch Rotary electronic packing machines will do packing of Cement. Loading of cement in trucks/wagon shall be done by automatic loading machines.

1.6

DESCRIPTION OF THE ENVIRONMENT

Baseline study of the study area (i.e. 10 km radius from the project boundary) was conducted during Summer Season (March, 2011 to May, 2011). Baseline study included ambient air quality, ambient noise level, water quality, soil quality, land use pattern, demography, flora & fauna found separately in the core & buffer zone etc.

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

Ambient Air Quality Monitoring reveals that concentrations of PM2.5 for all the 8 AAQM stations ranged between 14.81 g/m3 to g/m3 28.44. The concentration of PM10 ranged between 35.67 g/m3 to 59.11 g/m3.The maximum & minimum concentrations of SO2 were found to be 6.03 g/m3 & 7.64 g/m3 respectively whereas concentrations of NO2 ranged between 11.27 g/m3 & 16.68 g/m3. The ground water analysis for all the 8 sampling stations shows that pH varies from 7.07 to 7.91, total hardness varies from 54.00 mg/l to 181.80 mg/l & total dissolved solids varies from 93 mg/l to 221 mg/l. Soil Samples indicate pH value ranging from 6.40 to 6.98, which shows that the soil is moderately alkaline in nature. Organic Matter ranges from 1.19 to 1.82 in the soil samples. Nitrogen is found to be in better amount as it ranges from 150.03 kg/ha to 240.75 kg/ha and Phosphorous in medium amount i.e. from 35.46 kg/ha to 77.46 kg/ha, respectively, whereas the Potassium is found to be ranging from 55.39 kg/ha to 167.85 kg/ha.

1.7

SOCIO-ECONOMIC ENVIRONMENT
The population as per 2001 Census records is 80685 (for 10 km radius buffer zone). Scheduled Caste fraction of the population of the study area (10 km) is 16.98% and Scheduled Tribe is 11.01% Literacy rate is 61.88%. Total no. of households is 16695.

1.8

ANTICIPATED ENVIRONMENTAL IMPACTS


The key emissions generated from Plant process are particulate matter. High efficiency bag house will be installed in grinding unit to meet the PM (Particulate Matter) emission level. Fugitive emission shall through controlled by proper covered storage facilities for raw material & product. Installation of bag filters and proper water sprinkling shall be carried out at the material transfer points. No industrial waste water will be generated from grinding unit. Domestic effluent will be generated mainly from office toilets and township, which will be disposed off in soak pits via septic tank. There will be no discharge outside the plant.

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

No Solid waste will be generated from the proposed Cement Grinding Process. During operational phase noise will be generated from compressors, motors, grinding mills in the grinding unit. Ear plugs will be provided to persons working in high noise zone.

2.0

ENVIRONMENTAL MONITORING PROGRAM


Table: 3 Environmental Monitoring Program

S. No. 1. 2. 3. 4. 5.

DESCRIPTION Meteorological Data Ambient Air Quality Stack monitoring Water Quality Noise Level Monitoring

FREQUENCY OF MONITORING Daily Quarterly/ Half Yearly Quarterly/ Half Yearly Quarterly/ Half Yearly Quarterly/ Half Yearly

3.0

ADDITIONAL STUDIES
The Additional Studies conducted as per the additional Terms of References issued vide SEAC letter no. F. No 122/SEAC-212 & Letter dated 1st March, 2011 are Risk Assessment & Rain water Harvesting Plan.

4.0

PROJECT BENEFITS

The companys management will recruit the semi skilled & unskilled workers from the nearby villages, hence rapidly increasing the social status of the villagers. The company will act as a catalyst for accelerating the all-round development process in the surrounding villages of the project site. It will provide services to ensure that the full-benefits of development schemes of the Government and other agencies reach to the villagers. Fly ash and Slag will be used in proposed cement grinding unit which are generated from captive thermal power plant and steel plant as solid waste exist in vicinity of the proposed project site.

5.0
5.1

AIR POLLUTION MANAGEMENT


9

ENVIRONMENTAL MANAGEMENT PLAN

M/s JK Lakshmi Cement Limited

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

The major sources of pollution are particulate matter from grinding unit. Installation of proper pollution control equipment like Bag Houses, Bag filters and better maintenance will help in reducing such emissions. Fly ash, and Finish Product will be stored in silos. Clinker will be stored in silos /covered stock piles and gypsum will be stored in covered shed. Covered conveyors will be utilized for transportation inside the plant. Personal Protective equipments like dust mask will be provided to the workers. Green belt will be developed all along the plant boundary as dust preventive barrier. Regular Ambient Air Quality Monitoring will be done. 5.2 WATER POLLUTION MANAGEMENT There will be no waste water generation from the proposed grinding unit. The domestic effluent generated will be disposed off in soak pits via septic tank. There will be no discharge outside the plant. Rain water harvesting will be done within the plant premises. 5.3 NOISE POLLUTION MANAGEMENT Proper care will be taken by incorporating sound-proof enclosures for equipments and providing earmuffs and earplugs for operators. Proper maintenance, oiling and greasing of machines at regular intervals will be done to reduce generation of noise. Noise attenuating devices like earplugs and earmuffs will be provided to the workers exposed to high noise level. Green belt will be developed all along the plant boundary . Noise level monitoring shall be done on regular basis. 5.4 SOLID WASTE MANAGEMENT

M/s JK Lakshmi Cement Limited

10

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

No solid waste will be generated from the proposed grinding unit. However, material collected by the dust collectors (Bag House/Bag Filters) will automatically be recycled in the process. JKLCL will implement the following measures for solid waste management within the plant premises: Maintenance to prevent spillage and leakage Recycling of the collected spillage JKLCL, to prevent spillage and leakage will implement the following maintenance. The maintenance include inventory for the leakage/ spillage, and to investigate and prevent: Holes in bends etc. caused by the abrasive character of the materials. Deterioration of flexible joints, flaps and seals. 5.5 GREEN BELT DEVELOPMENT/ PLANTATION Approx. 33% of the total project area will be developed under green belt/plantation. Green belt will be developed all along the plant boundary as dust preventive barrier. The trees will be planted at suitable grid spacing to encourage proper growth. Tree plantation will be done every year in the campus to develop dense green belt. Species will be selected as per CPCB guidelines & local forest department. Green belt will be developed all along the plant boundary as dust preventive barrier.

6.0

CONCLUSION

M/s JK Lakshmi Cement Limited

11

Proposed Cement Grinding Unit (1.5 MTPA) and DG Sets (2X6MW). At Villages: Ghantikhal, Radheyshampur, Tehsil: Athagarh, District: Cuttack (Orissa)

Executive Summary of Draft EIA Report

As discussed, it is safe to say that the project is not likely to cause any significant impact on the ecology of the area, as adequate preventive measures will be adopted to control the various pollutants within permissible limits. Green belt development around the area would also be taken up as an effective pollution mitigative technique, as well as to control the pollutants released from the premises of JKLCL. More over this Grinding Unit will help to mitigate the disposal problem of fly ash generated from captive power plants located in the vicinity.

M/s JK Lakshmi Cement Limited

12

You might also like