CLIENT: M/s.

MADHUCON PROJECT LTD, HYDERABAD

HVAC L2 PROJECT SCHEDULE - MADHUCON 2 x 150 MW POWER PLANT PROJECT, NELLORE


Duration 131 days Start Fri 6/17/11 Finish Fri 12/16/11 11 14 17 20 23 26 July 2011 29 2 5 8 11 14 17 20 23 26 August 2011 29 1 4 7 10 13 16 19 22 25 28 September 2011 31 3 6 9 12 15 18 21 24 27 October 2011 30 3 6 9 12 15 18 21 24 27 November 2011 30 2 5 8 11 14

VENDOR: TRAC FUJICO AIR SYSTEMS LIMITED


December 2011 2 5 8 11

ID 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

Task Name HVAC SYSTEM DESIGN, ENGINEERING, SUPPLY, TESTING & COMMISSIONIN

17

20

23

26

29

14

17

DESIGN & ENGINEERING

67 days

Fri 6/17/11

Mon 9/19/11

Receipt of LOI Receipt of Civil drawings First Submission of Shop Drawing Submission of Technical Data Sheets / GA Drawings Approval / Comments on First Shop Drawing Approval / Comments of Technical Data Sheets / GA Drawings Submission of Final Shop Drawing Re-submission of Technical Data Sheet / GA Drawing Approval of Shop Drawing Approval of Technical Data Sheet / GA Drawing Estimation of Quantities Ordering Major Equipments Ordering of Materials other than Major Equipments

1 day 1 day 5 days 1 day 5 days 5 days 5 days 1 day 5 days 5 days 5 days 6 days 15 days

Fri 6/17/11 Thu 6/23/11 Fri 7/8/11 Thu 7/14/11 Wed 7/13/11 Wed 7/13/11 Mon 7/25/11 Fri 7/29/11 Thu 7/28/11 Fri 7/29/11 Fri 8/5/11 Fri 8/5/11 Fri 8/19/11

Fri 6/17/11 Thu 6/23/11 Thu 7/14/11 Thu 7/14/11 Tue 7/19/11 Tue 7/19/11 Fri 7/29/11 Fri 7/29/11 Wed 8/3/11 Thu 8/4/11 Thu 8/11/11 Fri 8/12/11 Thu 9/8/11

SUPPLY OF MATERIALS

40 days

Wed 8/31/11

Tue 10/25/11

Double Skin Air Handling Unit DX Type Packaged Type Air Conditioners Ventilation Fans MS Piping Chilled Water Pipe Insulation Manual Valves 2 Way Valves GI Ducting Volume Control Damper Diffuser / Grille / Collar Damper Thermal Insulation Acoustic Insulation Under Deck Insulation Electrical Control Panel for AHUs & Fans Instruments Heaters

6 days 6 days 6 days 6 days 10 days 8 days 5 days 23 days 6 days 6 days 6 days 6 days 6 days 6 days 6 days 6 days

Tue 10/18/11 Mon 9/26/11 Mon 9/26/11 Mon 9/19/11 Mon 10/3/11 Thu 10/20/11 Tue 10/25/11 Wed 8/31/11 Fri 9/30/11 Fri 9/30/11 Tue 9/20/11 Tue 9/20/11 Tue 9/20/11 Fri 10/14/11 Fri 10/14/11 Fri 10/14/11

Tue 10/25/11 Mon 10/3/11 Mon 10/3/11 Mon 9/26/11 Fri 10/14/11 Mon 10/31/11 Mon 10/31/11 Fri 9/30/11 Fri 10/7/11 Fri 10/7/11 Tue 9/27/11 Tue 9/27/11 Tue 9/27/11 Fri 10/21/11 Fri 10/21/11 Fri 10/21/11

INSTALLATION OF HVAC WORKS Double Skin Air Handling Unit DX Type Packaged Type Air Conditioners Ventilation Fans MS Piping Chilled Water Pipe Insulation Manual Valves 2 Way Valves GI Ducting Volume Control Damper Diffuser / Grille / Collar Damper Thermal Insulation Acoustic Insulation Under Deck Insulation Electrical Control Panel for AHUs & Fans Instruments Heaters

52 days 22 days 22 days 22 days 45 days 30 days 26 days 26 days 43 days 16 days 25 days 30 days 22 days 22 days 15 days 15 days 7 days

Fri 9/30/11 Wed 10/26/11 Tue 10/4/11 Tue 10/4/11 Tue 10/4/11 Tue 11/1/11 Tue 11/1/11 Tue 11/1/11 Mon 10/3/11 Mon 10/10/11 Tue 11/1/11 Thu 10/20/11 Fri 9/30/11 Fri 9/30/11 Wed 10/26/11 Tue 11/15/11 Mon 10/24/11

Mon 12/12/11 Thu 11/24/11 Wed 11/2/11 Wed 11/2/11 Mon 12/5/11 Mon 12/12/11 Tue 12/6/11 Tue 12/6/11 Wed 11/30/11 Mon 10/31/11 Mon 12/5/11 Wed 11/30/11 Mon 10/31/11 Mon 10/31/11 Tue 11/15/11 Mon 12/5/11 Tue 11/1/11

TESTING AND COMMISSIONING OF ENTIRE HVAC SYSTEM

10 days

Mon 12/5/11

Fri 12/16/11

Project: Project1 Date: Fri 6/24/11

Task Split

Progress Milestone

Summary Project Summary

External Tasks External Milestone

Deadline

1 THE ABOVE SCHEDULE IS SUBJECT TO THE APPROVAL OF ALL TECHNICAL DOCUMENTS, SHOP DRAWINGS, AVAILABILITY OF SITE CLEARANCES AND PAYMENTPage AT ON TIME