You are on page 1of 8

Downloaded from FaaDoOEngineers.

com
DISTRIBUTION SYSTEM PLANNING
Author : Ajit Kesari IAS CMD,Central Discom, Bhopal Co-Authors: Er. K.C. Jain and Er. Rinku Das (National Seminar on Best Practices in Electricity Distribution 18 - 20 Jan.06, Mumbai) INTRODUCTION In power system, Distribution plays a very important part as the consumers are directly affected by its efficiency. For meeting different future needs of the distribution system, up gradation of the existing system, to increase the efficiency and to reduce the technical losses, proper planning is very essential. The problem associated with planning of up gradation of transmission and distribution system in big cities as well as rural areas, is very complex. The unprecedented rate of growth in big cities on account of rapid growth of population, industrialization, urbanization of high load density pockets with multi storied complexes and in rural areas increase of deep tube wells manifold on account of low underground water level huge number of electric pumps are connected to system during agricultural season, has compelled the utility to plan much ahead to meet the present demand as well as future demand keeping in view the quality of supply. It is well known fact that Distribution System was totally neglected in all the utilities and practically nominal funds were provided for up gradation of sub transmission and Distribution system, resulting in huge technical losses in the Distribution System. The study shows that 1% reduction of losses in India is equivalent in addition of 1200 MW generation capacity. This is equivalent to saving in investment of Rs. 5000 crores. This shows that a high percentage of distribution losses in our country are a matter of national concern. Minimization of transmission and distribution losses will certainly result in an increase in the efficiency of the transmission and distribution system, which is only possible by proper planning of the system. The planning of distribution system needs a lot of variable to be taken care of. The Planning requires factors like rapid load growth, funds, ecological consideration, availability of land etc. The Planning Process. 1. General : Distribution planning studies can be carried out in different manner, each with different objectives and requirements. The Planning can be done, medium/long term planning and short term planning. 2. Medium/long tern planning

Downloaded from FaaDoOEngineers.com


Medium/long term planning is normally carried out as a part of a master plan for whole distribution company. It normally considers a 5 to 15 years time frame and is based on the state/national as well as local load forecasts, industrialization plan and agricultural load forecasts. The main purpose of this type of plan is: 3. To verify the present capacity of lines and sub station. To verify additional capacity and investments required to meet the load growth for putting new 33/11KV sub station, new 33 KV lines, 11KV feeders. Tie up for additional power-power purchase agreement. Up gradation of existing transmission capacity. Up gradation of existing network to develop strategies for reduction of technical losses. Estimation of funds required. Tie up with the financial agencies for funds.

Short term planning: Before planning the distribution system, the first and foremost work is study the existing system, present loss level and immediate action to be taken to meet the requirement of consumers, to provide interrupted and quality supply to the consumers. In present scenario, it has been noted that 11 KV and 33 KV feeders are loaded 100% more than their rated current carrying capacity resulting into very high technical losses. The purpose of short term planning is: To develop specific case studies and projects in a systematic manner. To adjust capacity of 33 KV,11 KV feeders, power transformer, distribution transformers and LT Lines. Immediate action to bifurcate heavy loaded 33 KV, 11 KV feeders. Augment conductor with the proper size of conductors. Reduce length of LT lines maximum 0.5 km per transformer. Implement projects for proper maintenance. To calculate required investments. Tie up the funds with the financial institutions.

Downloaded from FaaDoOEngineers.com


4. Study of existing system: Before making any distribution planning the most important part is study of the existing system. In the electrical distribution system three type of network are normally available. Radial. Loop Network (cross loop) In radial network, as the feeder is radial, load transfer in case of break down is not possible, as such feeder can be loaded to its maximum capacity and in case of break down unless and until fault is detected and repaired quite a good area remains in dark. In loop arrangement two feeders are connected to each other so that in case of breakdown, in one portion the faulty section can be isolated and rest of the portion can be switched on. In this type of system normally feeder is loaded to 70% of its capacity so that during the break down, feeder can share the load of other feeder also. In cross Loop Network, flexibility further increases as it provides multiple path and in case of break down in any line, supply can be resumed very quickly isolating the faulty system. In this type of net work normally, feeders should be loaded to 70% of their current carrying capacity. This system is highly reliable, but very costly. In big cities the concept of 33 KV ring main is very popular and two ring main are laid one outer and one inner. The outer ring main is laid using panther conductor and inner ring main is laid by using dog conductor. By using these two types of ring mains flexibility of the system is excellent and at the time of breakdown supply can be immediately switched on from other 132 KV sub station. While making any Distribution planning for metros the aspect of outer and inner 33 KV ring main is extremely essential and should be included for providing uninterrupted supply.

Downloaded from FaaDoOEngineers.com


Alternative layouts for Primary and Secondary Network, 33 and 11 kV

Radial Distribution System. Single path to each group of customers Lowest construction cost system Simple to plan, design and operate Most widely type of system used ( 98% in North America)

Loop Distribution System.

Double path to each group of customers Medium cost system Moderately simple to plan, design and operate Most widely used system in Europe Loss of feeder result only in temporary data requirement loss of supply

Network Distribution System.

Multiple paths to each group of customers High cost system Complex to plan, design and operate Only used in large city centers and for critical loads Highest reliability

5.

The overall No reserve lossplanning of feeder loss of supply

The process include activities updating all distribution system statistics, Used such in as urban evaluating changes in technical and economical Used planning in criteria urban as well as Used in rural areas areas evaluating and updating load forecasts, voltage and consumer category a areas forecast which will have a horizon of 10 to 15 years.

Downloaded from FaaDoOEngineers.com


6. Principle Areas Of Activity The principal areas of activities associated with a distribution planning are mainly: (i) Study of Existing Load Data. (ii) Future load growth study. (iii) Power factor /reactive load study. (iv) Study of thermal capability of conductors - capacity of feeders/circuits. (v) Economic Impacts. (i) Existing Load Data study: In Central Discom, there are 347 Nos. of 33 KV feeders out of which 65 Nos. are urban feeders and balance 282 Nos. are rural feeders. In urban areas, after study of all the parameters of existing feeders through CYMDIST software, various steps were taken like augmentation of existing Racoon conductor by Dog conductor, bifurcation of feeder and installation of Capacitor Bank in 33/11 KV sub station. The voltage regulations after execution of above works are within permissible limit. Loading of 282 No. 33 KV rural feeder is as below : 33 KV feeders having load more than 300 Amp. 31 Nos. 33 KV feeders having load between 250-300 Amp. 25 Nos. 33 KV feeders having load between 200-250 Amp. 56 Nos. 33 KV feeders having load between 150-200 Amp. 28 Nos. Less than 150 Amp. 142 Nos.

Similarly, in Central Discom there are 1749 Nos. 11 KV feeders out of which 358 Nos. are urban feeders and 1391 Nos. are rural feeders. In first phase, study of all the 11 KV urban feeders was conducted through CYMDIST software and according to the datas of the study action was taken for bifurcation of feeders, augmentation of conductor capacity and putting new 33/11 KV sub station. All the 11 KV feeders of urban areas are having Racoon conductor and load of the feeder is within 100 Amp. only. The voltage regulation are within permissible limit. In second phase, study of 11 KV rural feeders is being done. The existing all the feeders are laid on ACSR weasel conductor. Length of feeders is from 4 Kms - 100 Kms and voltage regulation is varying from 3% to 24%. The breakup of the feeders on the basis of load is as follows: No. of feeders having load more than 200 Amps. No. of feeders having load between 150-200 Amps. No. of feeders having load between 100-150 Amps. No. of feeders having load between 75-100 Amps. Less than 75 Amps. 180 Nos. 170 Nos. 790 Nos. 172 Nos. 79 Nos.

The study of 180 Nos. 11 KV feeders, having load more than 200 Amp. is being conducted in first phase through CYMDIST software and as per the results, action proposed is being taken shortly.

Downloaded from FaaDoOEngineers.com


(ii) Future Load growth study : The use of load forecasts are extremely important in Planning the Distribution System. These forecasts are mainly used for : Power Purchases Reinforcement of Distribution System Expansion Planning. Demand Side Management. Tariff Application. Monitoring of loss reduction programme. The forecasts may be done, short term, medium term or long term. Accuracy expected: The worldwide study has indicated that three out of the four forecasts made, are over estimated. Thus, planning becomes irrelevant. Therefore, we have taken care in forecasting the load growth. Historical load growth data was the major basis in anticipating the future load growth. Steps Involved : (iii) Data Collection. Data validation. Selection of methodologies. Development of assumptions. Development of energy and demand forecasts. Comparison with the historical load growth data.

Power factor and reactive loading study: A thorough study was made on the existing power factor and existing load on the system and as per the data obtained from CYMDIST software study, necessary compensation was provided by installation of 11 KV capacitor bank on 33/11 KV sub station. The result obtained by capacitor bank are placed at Annexure-I. Thermal capability of conductor: The thermal capacity of line circuit is dependent on the size of the conductor and type of environmental factors i.e. ambient temperature, wind speed and solar radiation. Economic Impacts: On analysis of the data derived through CYMDIST study, it is concluded that pay back period is hardly between 24 30 months and the results obtained from CYMDIST software have been used for preparing the loss reduction model of the company.

(iv)

(v)

CASE STUDY MP Madhya Kshetra Vidyut Vitaran Company Limited, Bhopal is one of the leading utility who has established Distribution System Planning Cell. Further, the National Tariff Policy has become mandatory for power utilities to be adopted within one years to segregate technical and commercial losses.

Downloaded from FaaDoOEngineers.com


In first phase, we have taken up short term system planning and we have established the equipment and network data base. From field, the data of all 33 KV and 11 KV feeders like length of feeders, size of conductor, configuration of pole, present loading, annual input and single line diagram were collected. Load forecasts were made for next five years on the basis of the historical load growth data. We further collected information like: 1) 2) Details of existing capacitor installed at 33/11 KV sub station. Details of existing 33/11 KV sub station with capacity of transformer, no. of feeders, loading etc.

In Central Discom, there are 282 No. 33 KV rural feeders and have been strung with Racoon conductor having current carrying capacity of 200 Amps. We selected all the 33 KV feeders having loading more than 150 Amps. for study and analysis. The detailed study was conducted through CYMDIST software which is a proven tool for finding technical losses at each voltage level of the distribution companies. This software provides two types of studies. a) Voltage drop analysis. b) Short circuit analysis. After study and getting the data different configuration were made like: a) Capacitor placement. b) Augmentation of the conductor of feeder. c) Bifurcation of the feeder. After putting this again, analysis was made and it was concluded that losses can be reduced substantially by adopting all of the three or combination of two or only by adopting any one method depending upon loading condition and voltage regulation. Initially study was conducted on selected 20 feeders and afterwards study of heavily loaded 224 rural feeders was done. It was observed that there are 49 feeders having losses more than 10% and 52 feeders were identified having losses between 5 -10%. On analyzing the results, in few cases it was observed that even after placement of Capacitor Bank proposing new 33 KV feeder and augmenting the conductor size, the voltage regulation were not coming within permissible limits. Study was further made by identifying locations for putting 132/33 KV sub stations. In short term studies, we have identified 5 No. such locations. Similarly, a study was conducted of 11 KV feeders and a conclusion was made i) ii) iii) iv) For putting Addl. Power Transformer in the existing sub station. Erection of new 33/11 KV sub station, thereby reducing length of 11 KV lines. Bifurcation of existing 11 KV feeders. Augmentation of conductor of existing feeders.

Downloaded from FaaDoOEngineers.com


The details of the results derived through study are placed at Annexure. CONCLUSION In the context of chronic power shortage, shooting price of the fuel and need for conservation of available fossil fuel resources, the urgency of elimination of high losses in transmission and distribution system is well justified. High percentage of losses in our country is a matter of national concern. The main cause of these high losses is laying of unplanned distribution system in the country. Proper distribution system planning, financial support and implementation of the planning will bring down the losses and consumers will get uninterrupted quality supply. The Rajadhyaksha Committee, constituted by Govt. of India, has also recommended that distribution system planning is a backbone of power industry and if distribution system would be neglected, entire power system will collapse. The Committee in its recommendation given in para 4.111 has also mentioned that proper planning should be done for reducing T&D losses. Further, the Power Economic Committee in 1971 has also recommended that transmission and distribution system planning should be done expeditiously and should be implemented. It is unfortunate that no attention was paid on the recommendations of these Committees and no efforts were made and distribution system was totally neglected. As such, it is extremely essential now to immediately do the short term and long term distribution system planning; funds should be arranged and should be implemented. ******

You might also like