PROJECT TEAM: Decraene, Robert Roman, Hediberto (ED) Sheehan, Courtney Wondimu, Mariamawit
1|P age
Resource Accountability Matrix (RAM/RACI).............................................................................................. 12 Project WBS .............................................................................................................................................. 13 Microsoft-Project Schedule ........................................................................................................................ 21
Six-Month Pro Forma Profit and Loss Statement .................................................................................................... 32
Appendix B ................................................................................................................................................ 53
MONTHLY TEAM FEEDBACK FORM ........................................................................................................................ 53
2|P age
3|P age
Scheduled Completion:
Executive Overview
History Owner Fred Zarko started the first Oldies Soda Shoppe in 1910. Ever since then Oldies continues to be a place where people of all ages come to enjoy not only the ice cream, but also the old fashion Americana atmosphere it represents. Recently Oldies executive management has approved a global initiative project with clear goal of adding critical value to the business. The Oldies Strategic Globalization Initiative project will accomplish the proposed expansion of Oldies Soda Shoppe into the international marketplace t o realize growth potential on a global scale. The global expansion plan is designed to support a growth strategy of which implementation of an international pilot location will work to expand Oldies strategic objective of worldwide operational expansion. The project will create new opportunities on a global scale for the Company, thus aligning the strategic goals with the planned portfolio of international market growth. It is the first planned project of its type for Oldies and upon successful completion , will springboard the Company into the international marketplace. The projects objective is to globally expand Oldies soda shoppe by opening a pilot international store in Sao Paulo Brazil. The successful completion of this project will depend mainly on three factors: project completion within a $12 million assigned budget; a grand opening within 8-10 months of project charter approval; and within the quality standards set by Oldies. The Project scope includes planning, implementation, and opening of an international pilot location in Sao Paulo Brazil. The project does not include purchasing a pilot store location and the team will not alter designs set by Oldies. The high-level Project Milestones include: Project Milestones 1. International City Analysis 2. Pilot store location selection 3. Site Renovation 4. Employee staffing and Training 5. Inventory Acquisition 6. Approval and Grand Opening
4|P age
Project Description
Project Objectives
Project Scope
5|P age
Resource Requirements
The following resources are vital to the success and completion of Oldies global initiative project. Each resource has specific requirements and duties that are expected in order to be successful in this International expansion project: Amount Core Project Team: (* = Member) Description Each team member works in a project management role using a diverse set of expertise and skills Each is responsible for a supporting role to the Project Manager leading specific deliverables of the project Manage international expansion project Project Management Professional Certified (PMP) Primary contact for all project events Complete responsibility for project delivery and high-level authority over control of various resources as needed in order to complete the project in accordance with our customers strategic goals Able to maintain deliverables within budget, schedule, and scope Implement planning/scheduling systems and risk tools systems throughout each new project Plan, monitor, evaluate, and appropriate project budget/funding Plan and implement Change Management contingencies Responsible for resource acquisition and management, monitoring resource pool, and allocation of resources as required for an efficient coverage of project activities & events Experienced with internal scheduling functions and management consulting operations Proven effective recruitment strategies Develops & manages risk-management & loss-prevention plans Initiates policies to comply w/ safety legislation & industry practices Develops & manages cost effective plans to reduce asset liability Liaison to attorneys, insurance companies and individuals, pertaining to any occurrence that may result in asset loss Requires a bachelor's degree in a related area and at least 7 years of experience in the field. Responsible for all IT requirements to include: outsourcing IT resource requirements, managing IT contracts and contractors, and ensuring all IT requirements are fulfilled
6|P age
Director of Operations: **James Rockwell Director of Supply & Vendor Management: **Robert Davy Subject Matter Experts (SME) & Project Personnel Translator: Nancy Salvador Legal: Jose Marquez, International Law Services
Must be fluent in Portuguese Responsible for translation between Project team and local (Brazil) Nationals who are stakeholders in this particular project International relations attorney responsible for handling any law related issues and requirements Provides legal advice and representation in all legalities pertaining to this particular business expansion Responsible for all renovation requirements from start to end including, but not limited to estimates, schedules, materials, and purchase orders Supervises the installation of equipment and components in assigned field Requires technical knowledge to assist installing contractors and all technical sub-contracting necessary to accomplish the site renovation Requires a bachelor's degree and 6-8 years of experience in the field or in a related area Licensed & Insured Willing to accept a Fixed-Price Contract agreement
7|P age
1 As Needed
IT Support Specialist:
2 Full Time
Administrative Support:
1 Full Time
Sales Associates:
6 Full Time
Assistant Manager:
2 Full Time
Store Manager:
1 Full Time
8|P age
Function
Senior Management (BOD) Project Manager
Role
Project sponsor; is consulted in high-level planning and signs off final approvals for budget, schedule, and scope. Responsible for team charter, project charter, project plan. Accountable for location identification/acquisition, completion of Marketing strategy and implementation, and overall completion on time and within budget of project. Oversees all planning, executing, installation and testing of hardware/software/POS networking systems. Oversees market analysis/strategy/implementation.
Reports to
Project Owners Senior Management/ BOD
Accountable for contractor identification/acquisition, store/materials/furniture, consulted throughout renovation and employee training and a part of the approving party for site evaluation/testing. Director of Project Consulted throughout planning, execution, and Controls & Budget monitoring and controlling phases on all aspects of the project pertaining to budgetary concerns. Director of Responsible for identifying stakeholders and Resource Mgt. employee acquisition and training.
Senior Management/ BOD Senior Management/ BOD Senior Management/ BOD Senior Management/ BOD
9|P age
Director of Risk
Responsible for risk analysis, mitigation and contingency strategies, risk monitoring, and risk management plans. Responsible for contractor/inventory analysis and acquisition.
IT Specialist
Team leader for all planning, executing, installation and testing of hardware/software/POS networking systems. Responsible for installation and testing of hardware/software/POS networking systems. Responsible for procurement contracts and fulfillment of vendor invoices.
IT Support
IT Specialist
Responsible for market analysis/strategy/implementation, and store opening promotional activities. Responsible for work site acquisition, facilities tours, lease agreement. Consulted throughout planning, execution, and monitoring and controlling phases on all aspects of the project.
Director of Operations Senior Management/ BOD /Project Team Director of Resource Mgt.
Director of IT Mgt. Oversees store associates and ensures operations in-store run smoothly. Responsible for organizing grand opening/celebration activities. Director of Marketing Responsible for site demolition, renovation, build out.
Director of Operations
10 | P a g e
11 | P a g e
Director of IT Mgt.
Project Manager A R R R A
Contractor Lead
Task Name Identify Stakeholders Team Charter Project Charter Develop Proj. Plan Market Analysis Location Identification & Acquisition Marketing Strategy & Implementation Contractor Identification & Acquisition Order Store Equip., Materials, & Furniture Site Renovation Equipment Install Employee Acquis. & Training Purchase & Obtain Inventory Site Eval. & Testing Celebration Grand Opening Contract/Project Close-Out & Approval
I C A R
R A A
I A A
R A R
R R
Project Team A C A I I
IT Specialist
IT Support
R R A
A C C C
C I I C C C R R I R R
A A
I A A I A A C C
A A R A A A A
A R A A C
C R I
Project WBS
WBS Task Name Duration Start Finish Predecessors
1 1.1 1.1.1 1.1.1.1 1.1.1.2 1.1.2 1.1.2.1 1.1.2.2 1.1.2.3 1.1.2.4 1.1.2.5 1.1.3 1.1.3.1 1.1.3.2 1.1.3.3 1.1.3.4 1.1.3.5 1.1.3.6 1.1.4 1.1.4.1 1.1.4.1.1 1.1.4.1.2 1.1.4.1.3 1.1.4.1.4 1.1.4.1.5 1.1.4.1.6 1.1.4.1.7 1.1.4.1.8 1.1.4.1.9 1.1.4.2 1.2 1.2.1 1.2.1.1 1.2.1.2 1.2.1.3 1.2.1.3.1
Oldie's Global Initiative Project Initiating Phase Identify Project Stakeholders Core Project Team Define Oldie's Subject Matter Experts (SME) High-level Meetings with Sponsor Introductions Delineate Core Project Roles Requirements and Acceptance Criteria Allocate Budget Identify Schedule Deadlines Compile Team Charter Team Management Plan Task Assignments Communication Plan Team Risks Ciritcal Success Factors Conflict Management Plan Project Charter Compile Project Charter Mission Statement of Work Business Need Assumptions Define SMEs Define Key Milestones Define Budget Baseline Define Major Risks Acceptance Criteria Obtain Sponsor Approval Planning Phase Project Plan Scope Statement Begin Drafting Project Plan Resource Requirements Project Schedule (WBS)
211 days 21 days 2 days 1 day 1 day 5 days 1 day 1 day 1 day 5 days 5 days 9 days 3 days 3 days 4 days 8 days 1 day 3 days 21 days 20 days 1 day 3 days 5 days 2 days 2 days 3 days 1 day 3 days 1 day 1 day 62 days 19 days 5 days 1 day 14 days 10 days
Mon 3/18/13 Mon 1/6/14 Mon 3/18/13 Mon 4/15/13 Mon 3/18/13 Tue 3/19/13 Mon 3/18/13 Mon 3/18/13 Tue 3/19/13 Tue 3/19/13 Mon 3/18/13 Fri 3/22/13 Mon 3/18/13 Mon 3/18/13 Mon 3/18/13 Mon 3/18/13 Mon 3/18/13 Mon 3/18/13 Mon 3/18/13 Fri 3/22/13 Mon 3/18/13 Fri 3/22/13 Mon 3/25/13 Thu 4/4/13 Mon 3/25/13 Wed 3/27/13 Mon 3/25/13 Wed 3/27/13 Thu 3/28/13 Tue 4/2/13 Mon 3/25/13 Wed 4/3/13 Thu 4/4/13 Thu 4/4/13 Mon 3/25/13 Wed 3/27/13 Mon 3/18/13 Mon 4/15/13 Mon 3/18/13 Fri 4/12/13 Fri 4/5/13 Fri 4/5/13 Fri 4/5/13 Tue 4/9/13 Mon 3/18/13 Fri 3/22/13 Tue 3/19/13 Wed 3/20/13 Fri 4/5/13 Mon 4/8/13 Wed 3/20/13 Fri 3/22/13 Mon 3/25/13 Mon 3/25/13 Tue 4/9/13 Thu 4/11/13 Fri 4/12/13 Fri 4/12/13 Mon 4/15/13 Mon 4/15/13 Wed 4/10/13 Thu 7/4/13 Wed 4/10/13 Mon 5/6/13 Wed 4/10/13 Tue 4/16/13 Tue 4/16/13 Tue 4/16/13 Tue 4/16/13 Fri 5/3/13 Tue 4/16/13 Mon 4/29/13 4
22 30 30
13 | P a g e
14 | P a g e
10 days Wed 6/12/13 Tue 6/25/13 5 days Wed 6/12/13 Tue 6/18/13 5 days Wed 6/19/13 Tue 6/25/13
14 days Wed 7/24/13 Mon 8/12/13 4 days 3 days 1 day 1 day 1 day 10 days 5 days 3 days 1 day 1 day 101 days 4 days 30 days 55 days 12 days 35 days 8 days 76 days 3 days Wed 7/24/13 Mon 7/29/13 Tue 7/30/13 Thu 8/1/13 Tue 7/30/13 Tue 7/30/13 127 127 127 133 134 135 127 74 138 141 142 127 143 146 146 124 127
Tue 7/30/13 Tue 7/30/13 Tue 7/30/13 Tue 7/30/13 Tue 7/30/13 Mon 8/12/13 Tue 7/30/13 Mon 8/5/13 Tue 8/6/13 Thu 8/8/13 Fri 8/9/13 Fri 8/9/13 Mon 8/12/13 Mon 8/12/13 Fri 5/31/13 Fri 10/18/13 Tue 7/30/13 Fri 8/2/13 Fri 5/31/13 Thu 7/11/13 Mon 8/5/13 Fri 10/18/13 Mon 8/5/13 Tue 8/20/13 Wed 8/21/13 Tue 10/8/13 Wed 10/9/13 Fri 10/18/13 Tue 7/30/13 Tue 11/12/13 Tue 7/30/13 Thu 8/1/13 Mon 1 day Mon 10/21/13 10/21/13 2 days Tue 10/22/13 Wed 10/23/13 3 days Tue 10/22/13 Thu 10/24/13 Tue 16 days Tue 11/12/13 10/22/13
16 | P a g e
Conduct General & Shift Manager Interviews 1.4.4.4.1.1 Certification Verification 1.4.4.4.1.2 Background Checks 1.4.4.4.1.3 Select Management Team 1.4.4.4.2 1.4.4.4.2.1 1.4.4.4.2.2 1.4.4.4.2.3 1.4.4.5 1.4.4.5.1 1.4.4.5.2 1.4.4.5.2.1 Conduct Staff Interviews Background Verification Employment Verification Select Staff Members Employee Training
Acquire Training Materials & Uniforms 1 day Management Training Orientation 1 day 1 day
168
17 | P a g e
16 days Fri 10/18/13 Fri 11/8/13 1 day Fri 10/18/13 Fri 10/18/13 Mon 2 days Tue 10/22/13 10/21/13 Mon Raw Ingredients 2 days Tue 10/22/13 10/21/13 Mon End Products 2 days Tue 10/22/13 10/21/13 Mon Confections 2 days Tue 10/22/13 10/21/13 Mon Disposable Materials 2 days Tue 10/22/13 10/21/13 Wed Develop Request for Suppliers (RFS) 8 days Fri 11/1/13 10/23/13 Wed Submit RFS To Potential Firms 2 days Thu 10/24/13 10/23/13 Obtain & Evaluate Returned Proposals 4 days Fri 10/25/13 Wed 10/30/13 Interview Acceptional Purveyors 2 days Thu 10/31/13 Fri 11/1/13 Supplier Selection 5 days Mon 11/4/13 Fri 11/8/13 Draft Contract Terms 2 days Mon 11/4/13 Tue 11/5/13 Finalize Contract Agreement Terms 1 day Wed 11/6/13 Wed 11/6/13 Obtain Contract Approval 2 days Thu 11/7/13 Fri 11/8/13 Mon Order Inventory 1 day Mon 11/11/13 11/11/13 Receive & Stock Inventory 10 days Tue 11/12/13 Mon 11/25/13 Mon Site Evaluation & Testing 26 days Mon 12/23/13 11/18/13
18 | P a g e
Mon 12/9/13 Tue 12/10/13 Mon 12/9/13 Mon 12/9/13 Tue 12/10/13 Tue 12/10/13 Mon 19 days Thu 12/12/13 11/18/13 2 days Mon 12/9/13 Tue 12/10/13 Wed 2 days Thu 12/12/13 12/11/13 Mon 2 days Tue 11/19/13 11/18/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 3 days Tue 12/10/13 Thu 12/12/13 4 days Fri 12/13/13 Wed 12/18/13 2 days Thu 12/19/13 Fri 12/20/13 Mon 1 day Mon 12/23/13 12/23/13 Mon 1 day Mon 12/23/13 12/23/13 Mon 1 day Mon 12/23/13 12/23/13 Mon 1 day Mon 12/23/13 12/23/13 21 days Mon 12/9/13 Mon 1/6/14 15 days Mon 12/9/13 Fri 12/27/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 1 day Mon 12/9/13 Mon 12/9/13 7 days Tue 12/10/13 Wed 12/18/13 1 day Thu 12/19/13 Thu 12/19/13
205 210
205 205 205 205 205 205 205 220 221 222
20 | P a g e
Microsoft-Project Schedule
21 | P a g e
22 | P a g e
23 | P a g e
24 | P a g e
25 | P a g e
Budget Plan
Oldie's Soda Shoppe, Inc. Global Initiative Revised Budget as of: 7 April 2013
Resource, Work Task, &/or Objective Cost per Unit $35.00 $30.00 $0.00 $0.00 $30.00 $30.00 $30.00 $22.00 Unit Type hours hours hours hours hours hours hours hours # Units 40 40 40 40 40 40 40 40 Original Budget $1,400.00 $1,200.00 $0.00 $0.00 $1,200.00 $1,200.00 $1,200.00 $880.00 $0.00 $7,080.00 $1,400.00 $0.00 $0.00 $2,000.00 $0.00 $0.00 $0.00 $3,400.00 $1,400.00 $0.00 Project Expenditures Project Balance
Team Charter
Project Manager Director of Resource Management Senior Management (Oldie's Management Team) BOD (Oldie's Management Team) Director of IT Management Director of Project Controls & Budget Director of Risk Management Project Team Total Task 1 $1,400.00 $1,200.00 $0.00 $0.00 $1,200.00 $1,200.00 $1,200.00 $880.00 $0.00 $7,080.00 $1,400.00 $0.00 $0.00 $2,000.00 $0.00 $0.00 $0.00 $3,400.00 $1,400.00 $0.00
26 | P a g e
$0.00
Market Analysis
Project Manager Director of Marketing (Oldie's Management Team) Operations Marketing Staff (Oldie's Marketing Team) SME Senior Management (Oldie's Management Team) BOD (Oldie's Management Team) Total Task 2 $35.00 $0.00 $0.00 $50.00 $0.00 $0.00 hours hours hours hours hours hours 40 40 40 40 40 40
$0.00
Project Charter
Project Manager Senior Management $35.00 $0.00 hours hours 40 40
40 40 40 40 40
$0.00
40 40 40 40 40 40 40 4 180
$0.00 $0.00 $1,200.00 $1,200.00 $1,000.00 $800.00 $2,000.00 $9,200.00 $27,000.00 $0.00 $45,000.00 $1,400.00 $880.00 $1,200.00 $1,200.00 $0.00 $2,000.00 $1,200.00
$0.00 $0.00 $1,200.00 $1,200.00 $1,000.00 $800.00 $2,000.00 $9,200.00 $27,000.00 $0.00 $45,000.00 $1,400.00 $880.00 $1,200.00 $1,200.00 $0.00 $2,000.00 $1,200.00
27 | P a g e
$0.00
$0.00 $0.00
hours hours
40 40
$0.00
Total Task 6
$0.00
40 40 40
$0.00
$0.00
hours
40
$0.00 $1,600.00
$0.00
$0.00 $1,600.00
28 | P a g e
$0.00
Equipment Installation
Equipment/Furniture Vendor Contractor Lead IT Specialist IT Support Total Task 10 Legal & License Manager SME Director of Operations (Oldie's Management Team) Director of Resource Management Director of Marketing (Oldie's Management Team) Operations Marketing Staff (Oldie's Marketing Team) Admin Support Total Task 11 Director of Supply & Vendor Management (Oldie's Management Team) Admin Support Legal & License Manager Director of Operations (Oldie's Management Team) Director of Project Controls & Budget Total Task 12 $0.00 $0.00 $25.00 $20.00 hours hours hours hours 9 40 30 30 $0.00 $0.00 $750.00 $600.00 $1,350.00 $1,200.00 $2,000.00 $0.00 $1,200.00 $0.00 $0.00 $400.00 $4,800.00 $0.00 $0.00 $750.00 $600.00 $1,350.00 $1,200.00 $2,000.00 $0.00 $1,200.00 $0.00 $0.00 $400.00 $4,800.00
$0.00
$0.00
$0.00
40 40 40 40
$0.00 $0.00 $1,000.00 $800.00 $0.00 $5,600.00 $1,400.00 $1,200.00 $400.00 $0.00 $0.00 $0.00 $0.00 $3,000.00 $1,400.00 $600.00 $0.00 $0.00 $400.00 $0.00 $0.00 $0.00 $2,400.00
$0.00 $0.00 $1,000.00 $800.00 $0.00 $5,600.00 $1,400.00 $1,200.00 $400.00 $0.00 $0.00 $0.00 $0.00 $3,000.00 $1,400.00 $600.00 $0.00 $0.00 $400.00 $0.00 $0.00 $0.00 $2,400.00
30 | P a g e
$0.00
$0.00
Celebration
Project Manager Store Manager Director of Marketing (Oldie's Management Team) Operations Marketing Staff (Oldie's Marketing Team) Admin Support $35.00 $15.00 $0.00 $0.00 $10.00 hours hours hours hours hours 40 40 40 40 40
$0.00
Total Task 16 ITEMIZED PROGRAM TASK BUDGET Total Task 1 Total Task 2 Total Task 3 Total Task 4 Total Task 5 Total Task 6 Total Task 7 Total Task 8 Total Task 9 Total Task 10 Total Task 11 Total Task 12 Total Task 13 Total Task 14 Total Task 15 Total Task 16 Overall Project Totals
$600.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$600.00 $7,080.00 $3,400.00 $6,680.00 $45,000.00 $7,880.00 $20,000.00 $3,000.00 $1,600.00 $41,200.00 $1,350.00 $4,800.00 $2,800.00 $5,600.00 $3,000.00 $2,400.00 $600.00 $156,390.00
31 | P a g e
Feb-14 % 26,000 100.0 26,000 100.0 3,900 3,900 22,100 15.0 15.0 85.0
Mar-14 % 30,000 100.0 30,000 100.0 4,500 4,500 25,500 15.0 15.0 85.0
Apr-14 % May-14 % 40,000 100.0 58,000 100.0 40,000 100.0 6,000 6,000 34,000 15.0 15.0 85.0 58,000 100.0 8,700 8,700 49,300 15.0 15.0 85.0
85.0 205,700
20,000 125.0 1,600 10.0 400 2.5 2,100 13.1 2,540 15.9 75 0.5 1,000 6.3 4,333 27.1 32,048 200.3 -18,448 115.3
20,000 76.9 2,600 10.0 400 1.5 2,100 8.1 2,540 9.8 75 0.3 1,000 3.8 4,333 16.7 33,048 127.1 -10,948 -42.1
20,000 66.7 3,000 10.0 400 1.3 2,100 7.0 2,540 8.5 75 0.3 1,000 3.3 4,333 14.4 33,448 111.5 -7,948 -26.5
50.0 10.0 1.0 5.3 6.4 0.2 2.5 10.8 86.1 -1.1
34.5 10.0 0.7 3.6 4.4 0.1 1.7 7.5 62.5 22.5
27.8 120,000 9.7 24,000 0.6 2,400 2.9 12,600 3.5 15,240 0.1 450 1.4 6,000 6.0 4,333 52.0 185,023 33.0 20,677
49.6 9.9 1.0 5.2 6.3 0.2 2.5 1.8 76.5 8.5
32 | P a g e
TYPE
Kickoff Meeting Team Meetings Senior Leadership Meeting Technical/ Operations Meetings Monthly Project Status Meetings Individual Performance Meetings Risk Management Meetings Change Approval Meetings Unexpected Events
WHEN
Once on 03/18/13 8am EST Weekly 8am EST Monday Bi-Monthly Friday 10am EST As Needed N/A N/A Monthly Last Friday 11am EST Monthly Last Friday 8am EST Bi-Monthly Wednesday 8am EST Monthly Last Wed. 11am EST As Needed N/A
AUDIENCE
Face to face Conf. Call Face to face Conf. Call Face to face
1. Project Sponsor 2. Core Project Team 3. Director of Operations 1. Core Project Team 2. SME (As requested) 1. Project Manager 2. Project Sponsor (Dir. Marketing) 3. Director of Operations 1. Core Project Team 2. Project Stakeholders 3. SME (As requested) 1. Project Sponsor 2. Core Project Team 3. Stakeholders 1. Project Manager 2. Individual Core Team Member 1. Core Project Team 2. SME (As requested) 1. Change Control Board
Face to face Conf. Call Face to face Conf. Call Face to face Conf. Call
TBD
35 | P a g e
36 | P a g e
The approval authority for all proposed project change requests is the Change Control Board (CCB). The CCB is responsible for reviewing all change requests, determining the additional risk resulting from the changes, identify any impact to the scope, cost, and schedule, and to approve or deny all change requests.
37 | P a g e
Project Sponsor: Approving authority for any budget/funding allocations Approving authority for changes to the schedule's baseline Approving authority for changes to the project scope CCB Chair person
Project Manager: Responsible for receiving and logging change requests from project stakeholders Responsible for each initial change analysis pertaining to risk, cost, schedule, and scope prior to CCB Responsible for clarifying any open issues or concerns by coordinating with the individual(s) requisitioning the change Responsible for revising or editing documentation for any approved changes as needed Approves validates low impact requests CCB participant
Project Team/Stakeholders: Responsible for utilizing standard request forms for any change requests Responsible for providing detailed and accurate information when submitting change request forms Responsible for providing feedback pertaining to any potential impact on proposed changes
38 | P a g e
39 | P a g e
Risk Identification
Inability to form the needed partnerships to keep the business going Decreased market share Causes unfavorable working conditions and threatens the existence of the business in Sao Paulo Communication and business operations negatively affected Low quality product
H H
H M
006. Technological The technological Risk progress in chosen city 007. Quality Gap in quality Assurance Risks standards 008. Contractor and Supplier Risk 009. Crime High Dependency on Contractors /suppliers Organized crime prevalent in Brazil Sao Paulo is a coastal city and there is risk of extreme weather conditions
Director of IT Management Project Manager, Store Manager Project Manager Project Manager Project Manager and Director of IT Management
Delay in schedule Project over budget Project quality affected Based on its impact, crime can be devastating to the business Threatens the existence of the business in Sao Paulo
41 | P a g e
Currency Risk: Fluctuations in exchange and inflation rate Consequences Schedule Budget Quality Measures Put in place a contingency budget Type Delay in Project Schedule Over Budget No effect on quality Type Preventative Impact L H N/A Effect H
3.
Social Risk: language and cultural barrier Consequences Schedule Budget Quality Type May delay schedule No effect on Budget Communication is affected Impact L N/A M
42 | P a g e
Competition: The type and size of direct and indirect competition in Sao Paulo, Brazil Consequences Schedule Budget Quality Type No effect on project schedule Project may be over budget No effect on quality Type Preventative Effect H Impact N/A M N/A
Measures Prepare a thorough Marketing strategy that addresses existing competition in Brazil 5.
Political Risk: Political instability in Brazil Consequences Schedule Budget Quality Measures Assess Brazils political climate during Market Analysis before choosing the country for the Pilot Location Modified Probability Modified Consequence From M to L Brazil is a politically stable country so political instability has a very remote probability of happening and thus has reduced impact on business Type Delay in project schedule No effect on budget No effect on quality Type Preventative Impact H N/A N/A Effect H
43 | P a g e
Measures Assess Brazils technological progress during Market Analysis before choosing the country for the Pilot Location Modified Probability Modified Consequence 7. From M to L
Brazil is a technologically advanced country thus technology risk has reduced impact on business
Quality Assurance Risks: Gap in quality standards Consequences Schedule Budget Quality Type Delay in schedule Project over Budget Quality of final product affected Impact L M H
Measures Administer quality performance tests before acquisition on all supplier sites to ensure products are per US quality standards Have back up supplier plans in case of quality assurance problems
Type Preventative
Effect H
Mitigation
44 | P a g e
Measures Do a thorough research on the contractor/supplier before hiring Have back up contractors/ suppliers
Effect H H
9.
Crime: Organized crime prevalent in Brazil Consequences Schedule Budget Quality Measures Choose a pilot store location in safe part of city Install a security system to secure the store Hire a security team to guard the location Type Delay in schedule Project over budget Project products quality affected Type Preventative Preventative Preventative Impact M M M Effect H H H
45 | P a g e
008 009
010
Measure Develop local partnerships with banks that have the needed knowledge and expertise in Regulatory Laws of Brazil. Put in place a contingency budget Hire a translator Hire a local store manager and staff when store opens Prepare a thorough Marketing strategy that addresses existing competition in Brazil Assess Brazils political climate during Market Analysis before choosing the country for the Pilot Location Assess Brazils technological progress during Market Analysis before choosing the country for the Pilot Location Administer quality performance tests before acquisition on all supplier sites to ensure products are to US quality. Have back up supplier plans in case of qual. ass. problems Do thorough research on contractor/supplier before hiring Have back up contractors/ suppliers Choose a pilot store location in a safe part of the city Install a security system to secure the store Hire a security team to guard the location Have proper insurance coverage Prepare a disaster and recovery plan
46 | P a g e
Approvals
Type Name Project Manager Approval: Signature Robert Decraene, MPM, PMP Date 3/17/2013
Customer/Sponsor Approval:
3/17/2013
Signed off by: Robert Decraene, MPM, PMP Hediberto Roman, MPM, PMP Courtney Sheehan, MPM, PMP Mariamawit Wondimu, MPM, PMP
48 | P a g e
Appendix A
CHANGE REQUEST FORM 1. Identification Project Name: Control No. (from CR Log): Requestor: Date Submitted: Brief Description:
High [ ]
Medium [ ]
Low [ ]
Scope [ ]
Budget [ ]
Schedule [ ]
Quality [ ]
2. Detailed Impact Analysis Impact on Cost : Impact on Schedule: Impact on Resources: Impact on Quality: Risks involved with change: Risks involved without change: Final Review Results: Review Date: (MM/DD/YYYY) Priority: (check one) 3. Change Approvals
49 | P a g e
High [ ]
Medium [ ]
Low [ ]
50 | P a g e
Description of Change
Priority*
Change Owner
*Status (New, In Review, Work in Progress, Testing, Rejected, Closed) *Priority (Low, Medium, High) Status Description
Description
Request is being Reviewed by Change Control Board Change Request approved & assigned, and is being implemented Change Request has been completed and is now being tested
Status
New
51 | P a g e
In Review
Work in Progress
Priority Description
Priority
High
Medium
Low
52 | P a g e
Appendix B
MONTHLY TEAM FEEDBACK FORM
Please answer the following questions What are the teams current objectives? How do you feel about the direction of the project? Outstanding Good Adequate Needs improvement What kind of job are we doing as we move toward our project goals? Outstanding Good Adequate Needs improvement How do you rank team participation? Outstanding Good Adequate Needs improvement How is our project processes working? Outstanding Good Adequate Needs improvement How would you rank the decision making process? Outstanding Good Adequate Needs improvement
Poor
N/A
Poor
N/A
Poor
N/A
Poor
N/A
Poor
N/A
How do you rank team member appreciation and respect? Outstanding Good Adequate Needs improvement
Poor
N/A
What kind of job are we doing as it relates to adhering to meeting guidelines? Outstanding Good Adequate Needs Poor improvement What is the best thing about our team? What is the biggest challenge for our team? Additional Feedback Please list any areas in which our team could be improved:
N/A
Personal Information Providing the following information is optional. First Name: Last Name: Address: City: State: ZIP Code: Telephone: Gender: Age: Would you like someone to contact you regarding your responses on this survey? Yes No Thank you for taking the time to fill out our survey. We rely on your feedback to help us improve our services. 53 | P a g e