You are on page 1of 12

CONT. No.

: PERSIAN GULF STAR OIL COMPANY


TJ/BINA JV
PROJECT:
PLAN/PRJ UNIT PHASE DISC.

REF. No.:

3034-00-ED-PI-DCR-50005-A0 DOCUMENT CODE


PAGE 1 OF 11

DOC. TYPE

SER. No. REV. No

DATE

BANDAR ABBAS GAS CONDENSATE 3034 00 ED PI DCR 50005 A0 JAN 2009 REFINERY PROJECT

PROJECT SPECIFICATION FOR Pipe Rack & Structure Loading

A0
REV.

29.01.09
DATE

IFA
DESCRIPTION

A.FAMILI
PREPARED

J.DARZI
CHECKED

M.DARVISH
APPROVED

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 2 of 12

l.Objective
Work instruction for calculation of loads is required for each engineering discipline to execute the detailengineeringworkforprojects.

2.Scope
Thisinstructionprovidescalculationanddefinitionofpipingloadsthatshallbe transmitted tocivil andstructuredepartment. This practice is applicable for all design projects in the fields of oil, gas, petrochemical, mining plant,andotherindustrialfacilities.

3.References
ASMEB31.12001PowerPiping ASMEB31.32004ProcessPiping APIRP520Sizing,selectionandinstallationofpressurerelievingdeviceinrefineries EJMAStandardofexpansionjointmanufacturersassociation SP22605022JobSpecificationForPipingFlexibilityAnalysis SP22605023JobSpecificationForPipeSupportElement

4.LoadDefinitions
4.1. Uniform Loads
All future and empty surfaces in the pipe rack (surface occupied by pipes with line size less than 20) are considered as having water filled piping of a diameter equal to the average of the system. The following table (table 1) and formula will be used for vertical load on the pipe rack (KN/m2) as a function of the average size . Maximum amount of load calculated due to formula and table should be considered. Table 1 Average of Piping 2 or less 1 3 1.5 4 2 6 2.5 8 3 10 3.5 12 4

Weight(KN/m2)

W: Full of Water Pipe Weight n: Number of pipe that can be placed in rack or sleeper in one meter width, due to 50 mm gap between outer edges of pipes

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 3 of 12

4.2. Concentrated loads


Concentrated piping load shall be the summary of the following loads and should be shown in table likethefollowingtable2. ConcentratedLoadwillbeconsideredfor: 1.Linesizeequalorgreaterthan20 2.Singlelineonshortbeamssameasflarelines 3.Aircoolerssupport 4.Otherspecialcase Table2 Loads(KN) Ref.NodeNo. LoadDefinition Fx(EastWest) Fy(Vertical) Fz(NorthSouth) WeightNocontent(WNC) Hydrostatictest* Sustain Operating Occasional *)IfApplicable 4.2.1.EmptyPipeLoad(WeightNoContent) Pc

Inthiscase,Wconsistsof: Pipingcomponentssuchaspipe,valve,flangeandfittings Hot&ColdInsulation. 4.2.2.HydrostaticTestingLoads P Inthiscase,Wconsistsof: Pipingcomponentssuchaspipe,valve,flangeandfittingswithfullofwaterweight FormoreinformationHydrostatictestSpecificationshouldbeconsidered. 4.2.3.SustainLoads P InSustaincase,Wconsistsof:

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 4 of 12

Pipingcomponentssuchaspipe,valve,flangeandfittings Hot&ColdInsulation WeightofServiceFluid: - Fullwaterweightforliquidline - 30%offullwaterweightforsteam/liquid,gas/liquidandvapormixturelines - 50%fullwaterweightforcatalystandpneumaticallyconveyedline - zeroweightforgasandvaporlines,unlessotherwisespecified However,whenthespecificgravityisgreaterthan1.0,theactualweightofthefluidshallbeused. Any concentrated weight (such as valve, flange and fittings) shall be added proportionally to the calculatedloads. 4.2.4.OperatingLoad The Operating Load shall be sum of the forces & moments produced by Sustain, Thermal Expansion,FrictionandThrustLoadcontractionofattachedpiping. Operating Load needs to be calculated only for Axial and/or Lateral restraints as a concentrated loadbasedonthesumofthefollowingloads: 4.2.4.1.Sustainload Referto4.2.3. 4.2.4.2.ThermalLoad Thermal Load shall be approximated to 0.5 of Sustained Load for Axial restraints and 0.3 of Sustained Load for Lateral restraints (sustain load should be consider for effective length describe laterin4.5.) Sustainloadinthiscaseissustainloadofpipingbetweentwosupportinsamedirection. 4.2.4.3.FrictionLoad Friction Load is required to be calculated for axial restraints. For an anchor on a pipe support (except on pipe rack) Friction Force may be neglected. Friction Forces for 3" and smaller pipelines maybeneglected. Friction force atanchorpointofpiperackorpipesleepershallbecalculatedasfollows: FF= WE WE=CxWxLE FF:Frictionforce(KN) WE:EffectiveWeightofpipingcomponents(KN) LE:EffectiveLength(m),Pipelengthbetweentwounidirectionalconsecutiverestraints (i.e.twoconsecutiverestraintsinXdirection) C:Constant(Table3)

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 5 of 12

Table3Constant Loopwithmiddlestop Loopwithoutmiddlestop Pipelinewithoutloop W:UnitSustainedLoad(KN/m) :CoefficientofStaticfriction(Table4) Table4FrictionCoefficient SteeltoSteel 0.3 SteeltoTeflon 0.1 SteeltoConcrete 0.5 4.2.4.4.ThrustLoadduetoExpansionJointandMechanicalJointandDischargeReaction When expansion joint or mechanical joint is used, thrust load caused by an internal pressure and an extension or compression of expansion joint shall be taken into consideration for pipe rack design. The reaction forces and moments caused by the exhaust of fluid from safety valves, control valves, and other discharging piping components shall be taken into consideration of the design. Discharge reactionforcescausedbysafetyvalvesshallbecalculatedaccordingtoANSIB31.1forsteamservices, and API RP 520 for other services. Discharge reaction forces due to other piping components shall be calculated according to the project specification. These loads can also be taken from vendor datasheet.Thisloadistobeincludedintheoperatingloadsummation. 4.2.5.OccasionalLoad Earthquake Load shall becalculated only for Axialand/or Lateral restraints as a concentrated load asfollows: ConcentratedLoads:P(kg)=0.3xUnitWeight(Kg/m)xEffectiveLength*(m) * Effective Length = Pipe length between two unidirectional consecutive restraints (i.e. two consecutiverestraintsinXdirection) 1 0.5 0.8

ForExampleinFig.1,SupportmanusedGuidefornodenumbers1,2,3,4,5,6and7andalsouseLine Stopatnodenumbers3and6.FollowintableNo.4willbeuseful.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 6 of 12

NodeNumber 2 3 4 5 6

Table4 EffectiveLength Xdirection Zdirection 0.5(H3+H4) 0.5(H2+H3) 0.5(L1+L2+H1+H2) 0.5(H1+L1+L2+L3+L4) 0.5(L1+H1+H2+H3+H4) 0.5(L1+L2+H1+H2) 0.5(L2+L3)

Fig1.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 7 of 12

5. Information Drawing For Equipment


5.1. General Any external loads & moments due to piping attached to the vertical vessels (towers) which cause lateral deflection of the equipment shall be taken into consideration for penetration hole Sizing and shall be informed to the manufacturers or civil design group whichever is responsible for the job. Access platforms for equipments are designed based on live load 250 kg/m2. When acting load exceeds the design load, the load shall be clearly shown on the information drawing. Concentrated loads greater than 100kg on the platform caused by piping support including its location shall be clearly shown on the information drawing. Location, elevation, fixed and sliding sides of equipment saddles and anchor bolts arrangement shall be shown on the information drawing. In general requirement of davit for equipment is informed by project group, however necessity of davit required for removal of safety valves, heavy piping components, etc. shall be studied and when davit is required, its type and location shall be shown on the information drawings. Type and dimensions of davit shall be in accordance with relevant standard drawings. Davits shall be designed for maximum lifted load but not less than a total load of 500 kg.

5.2. Equipment loads Equipment weights including empty, operating and test condition shall be shown. If test at site is not a design case or the equipment shall be tested in positions other than installed position, this shall be clearly indicated on the drawing. Equipment dynamic parameters including eccentricity, rotor mass and allowable settlement, for both nominal operation and starting shall be specified by vendor. Equipment preliminary total forces and moments for wind and earthquake shall be specified by equipment engineer. Vendor shall specify the exact loads and moment on each individual support. Equipment center of gravity (empty and operating). Elevation of any lateral support and its loading. Loads of lay down area or maintenance loads.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 8 of 12

Loads on overhead cranes or equipment monorails (if required according to project specifications). Any other considerable loads or moments exerted on equipment produced by piping external stress.

6. Information Single line Drawing for Structures


The information single line drawing for structures shall include the followings: The drawing shall be composed of plan, elevation and detail, and necessary dimensions and column No's shall be shown on the drawings. Construction of structure whether made of concrete or steel shall be reported by civil engineer and shown on the drawings. All dimensions of beams and columns on Single Line Drawing(SLD) are schematic and should be checked and finalized by civil department. Stairway and ladder location and elevation shall be, shown on information drawings by HSE team. In case of steel structure, the fire proofing, if necessary shall be shown on information drawings by HSE team. Floor shall be made of concrete unless otherwise specified. Standard floor is designed based on live load 500 kgim2. When the acting load exceeds the design load, the area and acting load shall be clearly shown on the drawing.

When penetration hole is required for piping, the size and location of the hole shall be shown on the drawing. When trolley beam for maintenance is necessitated, the fixing place, beam length, elevation and acting crane load shall be shown on the information drawing. Design basis of hoist beam shall be in accordance with relevant design practice. When floating type heat exchanger is installed in the structure, the fixing place of hoisting beam and acting live loads including connecting pipe weight shall be clearly shown on the drawing. When insert plate is required for concrete structure, fire proofed column and/or beam; the type, location and live loads shall be clearly shown on the drawing. When interconnecting of platform is necessitated, the connecting location and elevation of the platform and its size shall be shown on the drawing together with the continued dwg. No.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 9 of 12

Equipment installed on structure shall be shown. The equipment outline by double-dotted chain line, and the equipment No. and saddle location shall be shown on the drawing as shown on FIG.2.

Fig. 2. Work split between equipment and structure design group is shown as per FIG.3.

Fig. 3

For installation of horizontal and vertical bracing, the fixing shape and location shall be determined by close contact with the related engineering group in advance, and shall be shown on the drawing.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 10 of 12

7. Information Drawing For Shelter Structures


For preparation of the information drawing for shelter structures, Sect. 6 of this document shall be applied in addition to the following: When overhead traveling crane is installed, the size, shape and hook elevation of the crane shall be shown on the drawing. When sidewall is necessary, the required area shall be shown on the drawing.

8. Information Drawing for Special Pipe Stanchion/posts and Support Foundation


Generally supports with height more than 2000 mm and or weight more than 1000 Kgf shall be designed by the project civil design group. Any other decision other than these criteria shall be coordinated between piping and civil design group and shall be indicated in project standard pipe support specification. Piping is responsible to provide adequate information for these types of supports for project civil design group. The information drawing for pipe stanchions/posts and support foundation shall include the followings: The location of pipe stanchion/posts and support foundation shall be specified on a foundation location list document. This document shall include information such as: Foundation centerline coordination Bottom of base plate elevations Tag of relative supports As a rule, the details such as shape, dimensions and loading data of stanchions/posts shall be shown on a separate sheet as information drawing. Requirement of fireproofing for stanchions/posts shall be specified on information drawing by HSE team. For all supports with height less than 2000mm and weight less than l000 kgf (based on the agreement between civil and piping design groups) which shall be installed on the ground surfaces, the following provision shall be taken into consideration: Supports on paved area, which shall be fixed by expansion bolts, do not require any specific information drawings and coordination with civil group.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 11 of 12

Care shall taken by civil design group for paved areas, which need precast or cast in-situ pocket. Location of these supports shall be specified on the underground composite drawings or slab-on grade plans, which will be prepared by project civil design group.

9. Information Drawing For Operating Platform


When operating platform is required for valve operation, the following information shall be included in the drawing: The location of platform shall be shown on a copy of plot plan drawing. (Pipe stanchion and support foundation information drawing may be used.) As a rule, the details such as shape, dimension, loading data, etc. shall be shown on a separate sheet as information drawing. When penetration hole is required for piping, the size and location of the hole shall be shown on the drawing. Design live load for platform shall be 500 kg/m2. When the acting live load exceeds the design load, the area and acting live load shall be clearly shown on the drawing. When bracing is necessitated, the fixing shape and location shall be determined by close contact with the related engineering group in advance and shall be shown on the drawing.

10. Steel Structure Loading


10.1. Vertical Run
For vertical runs this step should be considered: - Vertical loads must be considered for all beams during vertical runs. - Vertical loads must be considered equal to the weight of vertical run and half of horizontal line till to nozzle or next weight support. Just for example fig.4 is useful. In this figure vertical loads should be applied to all supportable beams. -Guide loads must be considered for suitable beams with respect to safe vertical guide span. -Guide loads must be considered equal to 0.5 vertical loads.

TJ/BINA JV

CONT. No.:

REF.
50005

No.:

3034-00-ED-PI-DCR-

PROJECT: BANDAR ABBAS GAS CONDENSATE REFINERY PROJECT

Page 12 of 12

-Special case is better to analyzed with Caesar II. (In analyzed case, related loads only applied for essential beams according to stress analysis)

10.2. PSV load


PSV loads should be calculated with attached excel file.

10.3. Other loads


All other loads must be generated by stress man judgment or (if necessary) by approximate stress analysis.

T.L FIXED Min. Min. FIXED

GUIDE

GUIDE

GUIDE Min. L/3

GUIDE Min. L/3

Fig.4

L L

You might also like