You are on page 1of 4

49 Whitehall

Date of Issue COST PLAN Item Description Measured Costs 250.00 11,565.00

4th May 2011

Provisional Cost 0.00 0.00

PRELIMINARIES THE WORKS

Sub-Total

11,815.00

0.00

SUB-TOTAL ADD - PROVISIONAL SUMS PROFESSIONAL FEES Architectural & Interior Design Fees Building Services Design Fees STATUTORY FEES Local Authority Plan Fees Local Authority Inspection Fees

11,815.00 0.00

By Client Direct By Client Direct

By Client Direct By Client Direct

TOTAL CONTRACT SUM (EXCLUDING OPTIONS & VAT)

11,815.00

Page 1 of 4

49 Whitehall

Date of Issue COST PLAN

4th May 2011

Item

Description

Unit

Quantity

Rate

Measured Costs

Provisional Cost

PRELIMINARIES (Based on Monday - Friday working week) Site Management Site Cleanliness Drop and wait lorries No 1 250.00 INCL

To Summary

250.00

0.00

Page 2 of 4

49 Whitehall

Date of Issue COST PLAN

4th May 2011

Item

Description

Unit

Quantity

Rate

Measured Costs

Provisional Cost

THE WORKS

Supply and install 1no. Electric heater in each toilet on the main staircase, each heater c/w thermostat and will be time controlled. Include new power supply from the basement plant room. New wiring to heaters contained in surface mounted mini trunking.

item

6,150.00

6,150.00

Mechanical isolation of heating system, including complete drain down of gas supply at the meter. Removal of radiators in each toilet area.

item

1,650.00

1,650.00

To supply and fit a replacement sump pump (assumption is made that the power supply and controls are working correctly)

item

305.00

305.00

Identification labels for boiler/gas decommissioning etc. Builders work to repair floor and re-tile before and after works are completed in the toilet areas. To carry out all of the above works outside of normal working hours

item item

1 1

210.00 1,150.00

210.00 1,150.00

item

2,100.00

2,100.00

End of Section To Summary

11,565.00

0.00

Page 3 of 4

49 Whitehall

Date of Issue COST PLAN

4th May 2011

Item

Description

CLARIFICATIONS All stated rates, costs, provisional sums and totals are exclusive of VAT. The cost of all Statutory, Planning and Local Authority Fees are excluded. We have assumed that the cost of all power, gas, oil and water consumed during the course of the works will be paid directly by the client. We have only allowed to carry out works as costed and described within this document. TERMS We have based this cost plan on the following payment terms; Payment in full on completion. CONDITIONS We have assumed that a JCT Standard Form of Building Contract will be used on this project. PROGRAMME TBA

Page 4 of 4

You might also like