You are on page 1of 8

Date: 29-06-2013 TO, M/s.

Kumar Builders,

Mumbai
Kind Attn: Ms. Shefali Sancheti. Sub:Quotation for Shell Structure works of Residential Building (Ground + 1 Podium + 13 Upper Floors) Sub Structure & Super Structure Work (RCC, Block work, Int. Plaster, Ext. Plaster & Waterproofing) at proposed Bldg. No. 153 on Plot bearing survey No. 236/A, CTS No. 194 Pt. of Ghatkopar Village, Pantnagar, Ghatkopar (East), Mumbai.

Respected Sir, We thank you for inviting us to quote for work under subject matter above. We are pleased to submit herewith the quotation complete in all respect with. The rates have been quoted for in respect to the scope of works mentioned hereafter. The Construction of abovementioned residential building shall be carried out complete in all respect for the scope of work described hereunderRate excluding Piling

Approximate Built-up Area Rate per Sq. Ft. Built-up Area

: 39983 Sq. Ft. (to be ascertained with final VFC Drawing) : Rs. 621/-

Note The Built up Area are subjected to change as per final drawings (Cement, Concrete and Steel will be provided by the developer free of cost at site.)

Basic rate of Steel Basic rate of Cement Basic rate of Sand Basic rate of Aggregate Basic rate of Block

Rs. 45,000 / M.T. Rs. 260 / Bag of 50kg Rs. 6,000 / Brass Rs. 2,400 / Brass Rs. 4,200 / Cu. M.

The total final amount shall be evaluated on basis of actual total built-up area constructed on site on the basis of the mode measurement describe hereunder and duly certified by the Architect. The rates shall be calculated on basis of the mode of measurement defined hereunder to arrive at the total contract value.

Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

Built-up AREA Calculation Built up area shall be calculated on following table & before start of work & accordingly payment schedule shall be decided.

BUILT UP AREA STATEMENT FOR BUILDING (Ground +1 Podiums + 13 Upper Floors)


Sr.No 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. Details Ground Floor 1st Podium 1st Floor 2nd Floor 3rd Floor 4th Floor 5th Floor 6th Floor 7th Floor 8th Floor 9th Floor 10th Floor 11th Floor 12th Floor 13th Floor Total: Area in sqft.

Note : - The above area is approx. Actual area for payment shall be ascertained a per final VFC
drawings. Measurement of Construction Area shall be on the following basis: 1. 2. 3. 4. F.S.I. area statement including staircase, Lift Lobby Lift Shaft Ground floor (staircase, lift lobby + lifts + society room etc. ) Terrace at Lower floors - Created due to top of Flat - Created additional terrace by cantilever Balcony / Service corridor / Service Slab - Up to 600mm - More than 600mm Staircase Room Lift Machine Room Overhead Tank Terrace at Roof level Refuge Area (a) inside bldg (b) outside bldg Podium & stilt Service ducts ( if enclosed and with slab ) 100% 100% 100% 0% 50% 50% 100% 100% Nil Nil Nil 50% 50% 50% 50%

5. 6. 7. 8. 9. 10. 11. 12.

Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

Measurements: The site In-charge will jointly measure all the works in progress with the contractors authorized agent. Such measurement will be recorded in the measurement sheets by the contractor and will be signed by representative of Site In-charge. For the purpose of taking joint measurement, the co ntractors representative shall be bound to be present whenever required by the Engineer In-Charge. Payment Schedule to the contractor: The contractor will be paid as per the payment schedule. Payment Schedule: Consider following assumptions for: a. Concrete - 1.6 Cft / Sft BUA b. Steel - 6 Kg / Sft BUA Item No. 1 2 3 4 5 6 7 Item Description Quantity Unit

Cement Concrete Steel Reinforcement @ 6 kg / Sq. ft. BUA Labour Charges Formwork / Shuttering Material Charges Machinery and Equipments Charges Excavation Masonry - Block Work (AAC Blocks) Masonry - Block Work (AAC Blocks) - External - 6"thk. Masonry - Block Work (AAC Blocks) - Internal - 4"thk.

1586 239.89 39982.99 39982.99 39982.99 39982.99

Cu. M. MT Sq. ft. BUA Sq. ft. BUA Sq. ft. BUA Sq. ft. BUA

29194 14085 39982.99

Sq. ft. Sq. ft. Sq. ft. BUA

Water Proofing Plaster

Internal Gypsum Plaster Internal Gypsum Plaster - Ceiling Internal Gypsum Plaster - Wall 31986 63973 76718 39982.99 39982.99 Sq. ft. Sq. ft. Sq. ft. Sq. ft. Sq. ft. BUA

10 11 12

External Plaster Water & Electricity Charges Anti Termite Treatment

Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

SCOPE OF WORK (R.C.C., Block Masonry, Plaster & Waterproofing)


a) The specified work shall consist of Sub Structure & Super Structure Work (RCC, Block work, Int. Plaster in Kitchen, toilet & Common area and Ext. Plaster) Contract on Sq. ft. basis with Part Material (Only cement and steel shall be supplied by Developer at Site at Free of Cost) in accordance with the plan given by the Developer to the Contractor with specification, rates etc. given in Bill of quantities appearing hereunder and as described more particularly herein.

b) The Developer shall provide drawings approved by Architects/ Struct ural consultants to the contractor to execute the work at Site. 1. CONCRETE Proving Beams, Columns, Slabs, Chajjas, Lifts Machines Room, Lift Well, Lintels, Copings, UG & OH Water Storage Tanks, R.C.C. Staircase & other Walls in Site machine mixed concrete complete with the grade of concrete as per detailed specifications of R.C.C. Consultant including all formworks, reinforcement and inserts required to carry on the said works. Formwork for slabs shall be 12mm ply form.

2.

MASONRY All masonry woks shall be Block masonry as per Architectural drawings and specifications. External masonry shall be of block 150mm thick constructed in C:M 1:5. Internal partition wall and elevation masonry shall be constructed in half brick walls in C:M 1:5. R.C.C. runners with required reinforcement shall be provided at mid-depth of the half brick walls. All masonry works will be carried out in proper line, level & plumb.

3.

PLASTER All Internal walls & Ceilings shall be rendered with Gypsum Plaster. External plaster shall be finished with 5-10mm thick plaster in C.M. 1:4 with a thickness of 6-10mm over the backing coat.

4.

WATER PROOFING All Toilets and terrace water proofing shall be of Brickbat / Chemical Water Proofing

Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

Terms and Conditions


1) The basic rate shall include all transportation, loading VAT or any other taxes applicable. 2) Services tax and VAT applicable shall be paid by the owner. 3) WATER AND ELECTRICITY (Free of Cost at Site) a) Construction Water: Water required for construction purpose shall be arranged at one source only by the Developer at free of cost at Site. The Contractor shall make the arrangement for storage of the construction water and distribution, including the piping, pumping and its distribution up to the place of works. b) Electricity: Electricity required for construction purpose, labour hutments and general illumination in and around the work place shall be arranged and borne by the Developer at one source only at free of cost at site. General common area lighting arrangement to be in scope of main contractor. Water and Electricity as available for the work will be supplied at one point at free of cost at site c) Water supply shall be provided free of cost at point for the labour hutments and drinking purpose.

4) Bills shall be made as per the mode of the payment attached herewith. Payments against R.A. Bills shall be paid within 7-10 days from the date of submission of the R.A. Bill. 5) Advance (5% of Contract Amount) against mobilization shall be paid to the Contractor and may be recovered from 2nd R.A. Bill onwards @ 5% of the bill amount. 6) No retention for the value of the works executed shall be deducted from R.A. Bills on the general completion of works. No Balance shall be held by the builder after the completion of work. 7) Cement and Steel shall be supplied by Developer at site free of Cost. RMC shall be supplied by the Developer with Rs.150/- pumping charges. 8) The period of completion of the works shall be 12 months (plus 3 months Grace Period), Subject to Availability of VFC Drawing & Front. 9) Delay in execution of works due to a delay from our end either in terms of elements etc. shall be admitted by us for a period of 30 days in all. A delay beyond shall be claimed as idle charges at the rate of Rs. 50,000/week against idle labour, equipment, machinery etc. Also in case of unexpected delay the rates shall be liable for a escalation. The Site In Charge or his Senior officer appointed by the Developer shall look after Co-ordination of work and shall be authorized to inspect the work of Contractor, in way and manner as may be desired by the Developer.

10)

Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

11)

In case of work for which no such specification is supplied by the Developer, such work shall be carried out in accordance to with the instructions of the Developers Site in charge and General Manager Technical.

12)

Insurance by the Contractor: a) The contractor shall take the appropriate insurance policies to cover all risks involved in course of execution of work related to labour, personnel, Machinery or otherwise. b) The contractor shall be liable for any liability, loss, claim arising in respect of any damage to property or in respect of personal injury or death of any person appointed by the contractor or any sub contractor engaged by the Contractor or for any loss caused on account of any act of Contractor to any other Person or Property. c) Contractor shall cover insurance, which he may be required under any law from time to time or otherwise to secure himself against risk of accident etc. The Developer may ask the Contractor to take any other specific policy provided always that Developer shall not be liable for any peril which can be insured or otherwise.

The contractor shall comply with conditions and observe all acts, rules and Regulations including the following:a) Employees state Insurance Act, 1948: As applicable to himself, his employees or any other persons engaged or employed in course of work or in work related to Contract. The Contractor shall maintain all cards and records as required under the act in respect of employees and payments and the contractor shall secure the agreement of the sub-contract to maintain such records. Any expenses incurred for the contributions making contributions or maintaining records shall be in the contractors account. b) Workman Compensation and employees Liability Insurance: - The Contractor alone shall be liable for compensation payable under workman compensation Act or any other law in force. The Contractor shall take insurance policy for all the contractors employees engaged in th e performance of this contract to cover all risks. If any of the work is given on Sub-Contract, the contractor shall require the sub-contractor to provide for compensation of workmen and also to provide Developers liability insurance for the latters empl oyees if such employees are not covered under the contractors insurance. c) Minimum wages Act:- Wages shall be paid as per the prevailing Government Rules and records must be maintained as required.

13) Labour Laws:a) The contractor shall comply with all rules and regulations, obligations and restrictions imposed under the labour laws or any other law in force. The contractor will also ensure compliance with all the regulations for all his subcontractor as regards to applicable Central, State, Municipal and local laws. The Contractor further agrees to indemnify the Developer from any liability or penalty which may be imposed by the Central, State, Municipal or local authorities and also from all claims, suits or proceedings in respect thereof. b) Notwithstanding anything contained herein, the relationship between Developer and Contractor is on principal to principal basis and Developer shall not be liable for acts of Contractor in any way whatsoever and Contractor is not agent of the Developer. c) The Contractor further agrees and undertake as under:Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

(i) No labour below the age of eighteen years shall be employed at the site. Also no family of labours will be allowed at site. (ii) Contractor shall arrange required medical facility for his workers. (iii) Wearing safety gadget/particularly glows, harness safety helmet & safety shoes are Compulsory for all the workers, Supervisors and engineers etc. but if they do not do so, the Site-in charge will levy fine/penalty as deemed fit by him regularly. iv) The contractor shall comply with the provision of the Apprentices act, 1961 and the rules and orders issued there under from time to time. The contractor shall also be Liable for any pecuniary liability arising on account of any violation by him of the Act and indemnify Developer in respect thereof. The Developer may frame its own rule to levy penalties. 14) Safety: The Contractor at his own cost shall take all safety measures to prevent accidents, mishaps etc. on site and otherwise in course of work. Safety helmets, safety belts and all safety equipments as may be required and safety instructions shall be given by the contractor to his work force and staff wherever required. No person either labour or staff or visitor must be present at site without helmet. Safety nets of Minimum of 1000 wide inside the compound or as per requirement on site to be provided by the contractor at the periphery of the building, at the Contractors Own cost. The Contractor will provide necessary safety training to all the persons employed on the premises and protect their health and personal safety at your own cost. Any injured person has to be provided proper medical aid without any loss of time. Rates are all inclusive and among other things include the following:All the cost of material such as river sand, metal, Blocks, plasticizer, retarders (construction chemicals), Safety net and binding wire as required for quality construction with speed in mind. All shuttering material such as 12 mm ply (no plates), Beam bottom, steel props, runners, spans and the required tools and tackles required for the same (1 New Set of slab shuttering & 2 sets of bottoms) shall be brought by contractor at site with additional half set of slab shuttering without additional cost. All machinery etc. for lifting, shifting, placing, or transferring the materials for the purpose of construction wherever if required should be one by the Contractor. All necessary equipment for quality checks of material such as stilt contained, sieve analysis, cube moulds, flakiness,dust, porosity, as required will be brought by the contractor. Compulsory helmet, safety belt and safety shoes for the people (workers as well as managers).Daily cleaning the site and maintaining good housekeeping. Following all the laws w.r.t. to maintain records for labours such as their payment, PF, etc. workmen compensation insurance, working hours as per BMC rules, and following all law and order as per prevailing, and coming in future. Hope you find offer reasonable and competitive in accordance to your requirements. We look forward to be associated with you for the said works. We assure of our best services in terms of quality and timely completion of the project.
Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

For PHEENIX CONSTRUCTIONS Partner

Corporate Office: 5/6, Ground Floor, Embassy Apartments, 291, Bellasis Road, Opp. ST Depot, Mumbai Central, Mumbai 400 008. Tel: +91 22 23012971. Email: info@pheenixconstructions.com
Rose Group Company

You might also like