You are on page 1of 1

PROJECT TITLE:

WORK TITLE:

PRE-CONCRETING INSPECTION CHECK LIST


DATE LOCATION BUILDING ELEMENT OF STR GRADE OF CONCRETE CONCRETE SUPPLIER START OF INSPECTION FINISH OF INSPECTION OK NO

PROJECT OWNER:

CONSULTANT:

CONTRACTOR:

: : : : : : : :

SUBMITTAL DESCRIPTION No. 1 RFI 2 Shop Drawing 3 Method of Statement 4 Mix Design SETTING OUT DESCRIPTION No. 1 Gridline Position (tolerance 6mm if 3m; tolerance 3mm if < 3m) 2 Structural Finish Level (SFL) 3 Verticality WORKS BELOW LOWEST FLOOR LEVEL DESCRIPTION No. 1 Remove Stagnant Water and Soft Soil 2 Sand or Hardcore 3 Anti Termite Treatment (if needed) 4 Lean Concrete FORM WORK DESCRIPTION No. 1 Free from Cracks, Defects and Rubbish 2 Tight Joint and Gaps (seal if must) 3 Adequate Supported and Propped (rib max 300mm) 5 Dimension (Length, Width & Height) 6 Concrete Level Marked REINFORCEMENT DESCRIPTION No. 1 Correct Grade, Size, Number and Spacing 2 Adequate Lapping, Chairs and Spacer 3 Rebar Securely and Properly Tied in Place 4 Covers as Required 5 Free from Oil, Dust, Soil, and Loose Rust 6 Adequate Starter Bar (if needed) CONCRETING DESCRIPTION No. 1 Correct Grade and from Approved Supplier 2 Placing within 2 Hours from Dispatching (check DO) 3 Sufficient Slump (as per approved mix design) 4 Sufficient Sample 5 MEP Opening/ Embedded (if any) EQUIPMENT & TOOLS DESCRIPTION No. 1 Slump Test Tools (cone, bar, platform & tape meter) 2 Sample Cube Tools (cube, bar, cart, shove, trowel) 3 Crane with Concrete Container or Concrete Pump 4 Concrete Vibrator (with min. 1 stand by) 5 Concreting Recorder (forms & tools) 6 Curing Material (compund/ goni/ carpet) 7 Lighting (for night concreting). INSPECTED BY: VERIFIED BY:

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

OK

NO

REMARKS

DATE:

DATE:

You might also like