Professional Documents
Culture Documents
Concrete is strong in compression, but weak in tension. i.e. It may crack when pulled apart, but not when squeezed together. Tensile strength is provided to concrete structures by the incorporation of steel reinforcement. Concrete shrinks and thus cracks. The inclusion of steel reinforcement (at close centres) will restrict the width of cracks that for in concrete as it shrinks. Steel reinforcement rusts, expands and spalls the concrete if it is placed too close to the concrete surface or if the concrete does not include sufficient cement to protect the steel.
Set out below are the typical quantities for lesser volumes of 20 MPa concrete mix.
Source: Cement Concrete & Aggregates Australia
Grade 20 Concrete Mix 1 cement : 2 sand : 4 gravel (by volume) Cement (Number of 40Kg bags) Sand (m3) Gravel [20mm Coarse Aggregate] (m3) Water (litres)
Volume of Concrete (m3) 0.2 2 0.1 0.2 50-60 0.4 3 0.2 0.4 70-80 0.6 5 0.3 0.6 140-150 0.8 7 0.4 0.8 180-200 1.0 8 0.5 1.0 220-230
Set out below are the typical quantities for a 25 MPa concrete mix.
Source: Cement Concrete & Aggregates Australia
Grade 25 Concrete Cement (40Kg bags) Sand (m3) 20mm Coarse Aggregate (m3) Water (litre) Copyright: Quasar Management Services Pty Ltd 0.2 2 0.1 0.2 50-60
Volume of Concrete (m3) 0.4 0.6 4 6 0.2 0.3 0.4 0.5 70-80 140-150
The design of buildings with conventional masonry veneer and cavity masonry walls involves: Increasing the stiffness of the footings or beams & slabs Incorporating articulation joints in the masonry walls to break up the structure, thus preempting the formation of any cracks.
Reinforced Masonry Walls Connected to Concrete Slab Single leaf reinforced hollow concrete masonry superstructures built integrally with the concrete footings, incorporating steel starter bars, vertical wide spaced reinforcement and a continuous horizontal bond beam are capable of cantilevering and spanning large distances without cracking.
Copyright: Quasar Management Services Pty Ltd
Strength The strength of the concrete, and hence its ability to support loads, can be severely diminished by too much water in the mix. Cracking As water evaporates from concrete during the hardening process, there is a tendency for earlyage cracking and drying shrinkage cracking. The .width and extent of cracks will increase as the amount of water is increased. Delamination If concrete is too wet when finished, it could dry and shrink at the surface, which remaining moist underneath, causing delamination to occur. Abrasion / Surface Dusting - Excessive moisture in concrete can lead to reduced abrasion resistance of the surface, leading to dusting and possibly to exposure of the coarse aggregate Durability Concrete with excess water will be more prone to penetration by water and salts , and may exhibit increased risk of reinforcement corrosion and spalling of the surface Copyright: Quasar Management Services Pty Ltd (concrete cancer).
Source: Ryan, W.G. & Samarin, A., Australian Concrete Technology, Longman Cheshire, 1992
Historically, the choice of permissible slump was the prerogative of the Engineer, and specifications of 80 mm and 100 mm were common.
The Ryan & Samarin recommendation for reinforced footings is 50 mm to 100 mm, while the recommended slump for pavements and slabs is 50 mm to 80 mm.
A value of 100 mm is now reflected in BCA Volume 2 Clause 3.2.3.1 (a) (iii).
Source: Ryan, W.G. & Samarin, A., Australian Concrete Technology, Longman Cheshire, 1992
Copyright: Quasar Management Services Pty Ltd
The fluidity of fresh concrete may be measured by the slump test. Concrete slump is determined by moulding fresh concrete in a 300 mm high steel cone. The mould is then removed and the fresh concrete will settle. The slump (the distance down from the top of the cone) can be measured. The slump test gives an indication of the quantity of water in the fresh concrete, although slump is also influenced by the grading of the fine and coarse aggregate, the shape of the aggregate and the quantity of cement.
Handles 300 1.5 mm thick galvanized sheet steel cone Foot plates 100
Slump
From this chart, it is clear that: If no other adjustments to a mix are made, 25% increase in slump from 80 mm to 100 mm could result in a reduction in strength of approximately1.5 MPa (approximately 7.5% in 20 MPa concrete) If no other adjustments to a mix are made, 50% increase in slump from 80 mm to 120 mm could result in a reduction in strength of approximately 25%. This chart shows that as increasing quantities of water are added, there is a resulting loss of strength.
Source: Readymix - The Effect of Excess Water in Concrete http://www.readymix.com.au/Toolbox/DIY/excessWater.shtml Similar information is available in: Beware of excess water, Cement Concrete & Aggregates Australia, March 2006: Copyright: Quasar Management Services Pty Ltd
A common footing design is 1000 x 1000 x 500 with 10 mm diameter reinforcement. In some cases the reinforcement diameter is too small and the dimensions of bent bars are incorrect.
The diameter, dimensions and position of reinforcement should be inspected before placing concrete.
Do not put too much reinforcement in the footings and ground beams. It is just a waste of money.
Footings and ground beams should have enough, but not too much reinforcement
Often concrete slabs-on-ground are only 50 mm thick and do not contain any steel reinforcement. This can lead to cracking and moisture penetration.
The thickness of slabs-on-ground (that are bigger than 3.0 m x 3.0 m) should be at least 70 mm thick with at least SL42 steel reinforcement mesh (3.8 diameter at 200 mm centres) over compacted fill. If the thickness is increased, so should the reinforcement be increased. Australia The thickness of slabs-on-ground should be 100 mm thick with at least SL72 steel reinforcement over compacted fill.
When permanent steel sheet formwork is used, preformed metal edge forms can also be screwed to the sheeting by short metal straps.
Copyright: Quasar Management Services Pty Ltd
The lapping of welded fabric reinforcement in the top face of a slab will significantly increase the thickness of reinforcement and reduce the cover.
Copyright: Quasar Management Services Pty Ltd
Mechanical vibration is recommended for all concrete members. Although AS 2870 does not make mechanical vibration of residential footings and slab-on-ground construction mandatory, it is strongly recommended.
However, if the concrete has not achieved sufficient hardness, the mechanical trowel (helicopter) may dig into the surface.
Photo: Wacker
Excessive trowelling will lead to a concentration of bleed water at the surface and eventual dusting and/or abrasion of the surface.
Copyright: Quasar Management Services Pty Ltd
Source: AS 3661.1
To prevent termite penetration, AS 3661.1-2000 Termite management Part 1 New building work places a limit of 1 mm on the permissible width of cracks. Copyright: Quasar Management Services Pty Ltd
Specifications
This module provides typical specifications, summarised from the Electronic Blueprint. More comprehensive editable building specifications may be downloaded from: www.electronicblueprint.com
Copyright: Quasar Management Services Pty Ltd
Bar and Fabric Reinforcement Reinforcement shall comply with AS 4671, AS 2870. Unless stated otherwise, properties shall be not less than: Deformed bars - 500 MPa, normal ductility (N) Square fabric, rectangular fabric and trench mesh - 500 MPa, low (L) or normal (N) ductility ribbed wires Fitments -500 MPa, low (L) or normal (N) ductility ribbed wires Round bar (e.g. R250 N10 for dowels) - 250 MPa round. Fibre Reinforcement Fibre reinforcement used for enhancing toughness and impact resistance of concrete shall comply with the relevant Standard (ASTM A820 Type 1 for steel fibres). Unless stated otherwise, fibre reinforcement shall be polypropylene or steel fibres capable of being mixed uniformly throughout the concrete.
Copyright: Quasar Management Services Pty Ltd
In slabs, bar chairs shall be placed at one metre centres both ways. Unless specified otherwise in the Drawings or Standard, bar chairs shall provide cover not less than the following:
This sample inspection schedule defines a minimum level of control that should be exercised by a builder during construction. It is not intended for use by licensed tradesmen, installers or authority inspectors, who would need to apply more rigorous inspections.
Copyright: Quasar Management Services Pty Ltd
Construction Checklist Builder: Site: Activity: Cast in-situ Concrete Piers Item or Product Drawings & specifications Pier location Pier diameter Founding material Pier depth Casing (if required) Reinforcement grade Reinforcement diameter Reinforcement spacing Reinforcement laps Reinforcement ligatures spacing Concrete strength Inspection Required Inspect controlled docs Check grid Check hole position Check auger diameter Visual inspection Measure depth or monitor volume Measure diameter Spot check markings Spot check diameter Spot check Spot check Spot check Spot check dockets Accept Criteria Latest issue on site +,- 50mm +,- 50mm As specified As specified +,- 20% + 20mm ,- 10mm As specified As specified +,- 10% +,- 10% +,- 10% As specified Hold Witness Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Witness Date Inspector Comment
Construction Checklist Builder: Site: Activity: Concrete Footings, Ground Beams, Slab-On-Ground Item or Product Drawings & specifications Footing width Footing length Reinforcement cover Edge forms Level on sand bed Membrane and tape Reinforcement grade Reinforcement diameter Reinforcement spacing Reinforcement laps Reinforcement ligature spacing Plumbing roughed-in Concrete strength Curing Inspection Required Inspect controlled docs Spot check Spot check Check chair size Check all edges Spot check levels Spot check taping Spot check markings Spot check diameter Spot check Spot check Spot check Check all positions Delivery dockets Spot check Accept Criteria Latest issue on site + 10%,- 2% + 10%,- 2% As specified +,- 20 mm + 10 mm, -30mm As specified As specified As specified +,- 10% +,- 10% +,- 10% +,- 50 mm As specified As specified Hold Witness Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Witness Witness Date Inspector Comment
Construction Checklist Builder: Site: Activity: Concrete Superstructures Item or Product Drawings & specifications Beam & column width Beam & column depth Slab and stair depth Reinforcement cover Reinforcement grade Reinforcement diameter Reinforcement spacing Reinforcement laps Reinforcement ligature spacing Plumbing & electrical roughed-in Concrete strength Curing Inspection Required Inspect controlled docs Spot check forms Spot check forms Spot check forms Check chair size Spot check markings Spot check diameter Spot check Spot check Spot check Check all positions Delivery dockets Spot check Accept Criteria Latest issue on site + 10%,- 2% + 10%,- 2% + 10%,- 2% As specified As specified As specified +,- 10% +,- 10% +,- 10% +,- 50 mm As specified As specified Hold Witness Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Hold Witness Witness Date Inspector Comment