You are on page 1of 40

USER MANUAL

VESTDAVIT TYPE TDB-3602

VESTVINSJ TYPE C - 356 - 1

Customer Vestdavit project no. Date of delivery

: : :

Neptune Offshore 8050 July 2009

Prepared by H.Laupsa

Approved by P.C.Mgster

Doc. No. VDT-UMT-8050

Rev.No. 0

Date 31.05.10

Page 1 of 41

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 2 of 40

TABLE OF CONTENTS
List of illustration ...................................................................................................................................................................3 Part I INTRODUCTION ..............................................................................................................................................4 Part II MAIN DATA........................................................................................................................................................5 2.1 Conditions of guarantee..............................................................................................................................................5 2.2 Technical data ............................................................................................................................................................5 2.3 Restrictions in use.......................................................................................................................................................6 2.4 Main connections and requirements for connected systems .......................................................................................6 2.5 Weight and outline dimensions...................................................................................................................................6 PART III TECHNICAL DESCRIPTION...........................................................................................................................7 3.1 Davit functions ...........................................................................................................................................................7 3.2 Winch .........................................................................................................................................................................7 3.3 Hydraulic system ........................................................................................................................................................8 PART IV INSTALLATION AND PREPARATION ....................................................................................................9 4.1 General .......................................................................................................................................................................9 4.2 Storage........................................................................................................................................................................9 4.3 Float chart installation ..............................................................................................................................................10 4.4 Welding to deck........................................................................................................................................................11 4.5 Maneuvering equipment location .............................................................................................................................11 4.6 Maneuvering valve connections ...............................................................................................................................12 4.7 Hydraulic system on ship..........................................................................................................................................13 4.8 Filling of hydraulic oil..............................................................................................................................................17 4.9 Starting the system....................................................................................................................................................18 4.11 Threading of wire ................................................................................................................................................19 4.12 Maintenance of piston rods on the hydraulic cylinders on the TDB-Davit..........................................................20 4.13| Lubrication oil and drain connections for winch .................................................................................................22 4.14 Instruction for activating shockabsorber..............................................................................................................23 4.15 Instructions for refilling nitrogen on shock absorber accumulator.......................................................................24 4.15 Test Procedures ...................................................................................................................................................25 Part V OPERATING AND CONTROL ......................................................................................................................26 5.1 Checking before start................................................................................................................................................26 5.2 Starting .....................................................................................................................................................................26 5.3 Special notes regarding the winch ............................................................................................................................26 5.4 Lowering operation ..................................................................................................................................................27 5.5 Hoisting operation ....................................................................................................................................................27 5.6 Emergency push out and lowering operation............................................................................................................28 5.7 Emergency hoisting operation (see Hydraulic diagram).........................................................................................29 5.6 Charging of accumulator ..........................................................................................................................................30 Part VI INSPECTION AND MAINTENANCE ...........................................................................................................31 6.1 General .....................................................................................................................................................................31 6.2 Inspection routines....................................................................................................................................................31 6.3 Disturbance of operations.........................................................................................................................................34 6.4 Long term stop and new start....................................................................................................................................37 PART VII SPARE PARTS ..................................................................................................................................................38 APPENDIX A - DRAWINGS ..............................................................................................................................................39 APPENDIX B - CERTIFICATES .......................................................................................................................................40

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 2 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 3 of 40

List of illustration
Figure 1 Float chart installation ..............................................................................................................................................10 Figure 2 Maneuvering valve connections ...............................................................................................................................12 Figure 3 Piping exanple ..........................................................................................................................................................16 Figure 4 Threading of wire .....................................................................................................................................................19 Figure 5 Piston rod on cylinder...............................................................................................................................................20 Figure 6 Cylinder ....................................................................................................................................................................21 Figur 7 Guiding cylinder.........................................................................................................................................................21 Figur 8 Winch lubrications points...........................................................................................................................................22 Figure 9 Activating shockabsorber .........................................................................................................................................23 Figure 10 Charging of accumulator ........................................................................................................................................30

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 3 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 4 of 40

Part I

INTRODUCTION

This manual contains description of all necessary details needed for installation, operation and maintenance of the davit. The manual consist of the following parts: PART I PART II PART III PART IV PART V PART VI PART VII Introduction Main data Technical description Installation and Preparation Operation and Control Inspection and maintenance Spare parts

APPENDIX A APPENDIX B

Drawings Certificates

Any questions regarding the manual or the davit should be directed to: Vestdavit A/S Damsgrdsveien 143 5162 Laksevg, Norway Telephone: 47 55 54 92 00 Telefax : 47 85 02 85 29 E-mail: post@vestdavit.no

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 4 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 5 of 40

Part II
2.1

MAIN DATA

Conditions of guarantee 24 months provided commissioning supplied by Vestdavit AS. Technical data
DAVIT: Davit type Max. load ,SWL : Test load in work shop Wire Hydraulic cylinder davit Shock Absorber Accumulator for shock absorber WINCH: Winch type Max. wire pull 2. Layer Drum dim. Max. Hoisting speed Max lowering speed Oil pressure Required oil flow Hydraulic motor, type Gear, type Gear reduction MANOEUVRE EQUIPMENT: Maneuvering valve Valve Block HYDRAULIC POWER UNIT: Electric motor, Oil tank volume Oil flow Oil type Operation temperature Bevi-motor, 54kw, 440V, 60Hz 350 L 145 L/Min at 200 bar Shell Tellus T32 or similar Max. 55 C HPV-O-77M190-41C80 Linde 94

2.2

Vestdavit TDB-3602 3600 kg 7920 kg 18mm, L=29 m HMT2-V-D-100/90x70/40x3700-S-R-SP CP4BG 80 x 400 10L, loaded 120 bar N2

Vestvinsj C-356-1 3600 kg 356 mm 50 m/min 50 m/min 220 bar 110 l/min F12-110-MS Brevini ED 2090/ FL 450MN 1:30,3

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 5 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 6 of 40

2.3

Restrictions in use 1 2 3 The davit is only to be used in lowering/hoisting operation with boat connected to hook. The davit is not to be used as a crane, i. e. cargo net is not allowed. The davit shall not exceed SWL for the davit arrangement.

Any violation to these restrictions will invalidate the guarantee conditions.

2.4

Main connections and requirements for connected systems If the davit hydraulic system is connected to external hydraulic supply, i.e. constant pressure system, load-sensing etc., hook up valve arrangements should be stated in hydraulic diagram. If not, contact Vestdavit A/S.

2.5

Weight and outline dimensions Davit weight Davit outline dimensions App. 2250 [kg] App. 400 x 150 x 120 [cm]

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 6 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 7 of 40

PART III

TECHNICAL DESCRIPTION

3.1

Davit functions TDB -davit is a hydraulic operated single point davit designed for effective safe launching of Man Overboard Boats or Work boat. All operations of the davit are hydraulic driven which benefits control of the boat position at all stages during the operation and, in contrast to a gravity davit, gives the opportunity to bring the boat back onboard in any position required at any time. In stowed position the boat is resting on supports and secured by lashings. Embarkation of the boat can take place in parked position or in a position on ship's side in deck level. The davit is operated by one person from the operators console and should have a clear view to the boat when launching. Launching of the boat is done by pushing the cylinder from its parked position to a position where it is free of the ship's side and then lowered by means of the winch. This two-step operation makes it possible to move the davit backwards after lowering the boat below deck level, allowing it to rest along the ship's side and prevent it from excessive movements in rough weather conditions, or to park the boat along the ship's side for embarkation. The Shock absorber is a fully automatic/passive hydraulic device, that ensure smooth lowering and hoisting operation of the boat.

3.2

Winch The winch consists of five main elements: Frame with wire drum Wire drum is connected directly to the gear shaft. The winch frame is mounted to the davit by 4 bolts. Gear The reduction gear is a planetary gear flanged directly to frame. Mechanical brake Between gear and motor there is a automatic spring-loaded disc brake functioning as parking brake and a mechanical brake. The brake is released by hydraulic pressure. Hydraulic motor The motor is an axial piston motor connected to a hydraulic pump in open circuit.
Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 7 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 8 of 40

Hydraulic control unit The hydraulic control unit controls the hydraulic brake at dynamic stop of the winch. It functions as an automatic controller of the disc brake, hydraulic brake and the maximum speed. 3.3 Hydraulic system

The winch system consists of hydraulic motor, valve block flanged to motor and hydraulic operated brake. Hydraulic double acting cylinders for swing out / in, with throttle-check valves. Hydraulic shock absorber for smooth lowering and hoisting. The Maneuvering unit is a lever operated directional valve. Spring centered 2 spools valve. First bank closed center for operating cylinder, second bank open center for winch motor. The hydraulic power unit consist of a closed reservoir and following equipment: An electric motor which drives a gear pump through a flexible coupling. A hydraulic return filter for oils flowing from davit. An air breather filter for preventing dirt and dust to enter the tank and vapors to leave. An oil level gauge. A temperature indicator.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 8 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 9 of 40

PART IV

INSTALLATION AND PREPARATION

4.1

General Correct installation is a prerequisite for safe operation. If any questions arise during the installation, contact the Vestdavit supervisor at site or contact a Vestdavit engineer by telephone or telefax. The davit has been tested and all the components are controlled prior to shipment. Before starting the installation, check that no part of the system or any components have been damaged under transportation. If any damages have occurred, contact immediately Vestdavit for replacements. The davit is complete for installation on board. The davit system consists of the following components: Three square tubes. One outer to be fixed to the ship structure and two inner tubes. Winch Maneuvering console. Hydraulic cylinders. Shock absorber. Hydraulic Wire hauler Hydraulic Power Unit Hydraulic piping on ships deck (Yard delivery)

4.2

Storage Davit steel structure Outdoors unprotected normally 3 months. Normal position is two legs and davit head to ground. Power unit Submerged Stainless Steel Tank, no preservation, time unlimited. Hydraulic components Indoors, dry conditions.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 9 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 10 of 40

4.3

Float chart installation

Installation of davit

Installation of man. consol/hand pump

Airing of system

Hydraulic piping on deck Flushing of system Filling of System oil

Threading of wire

Installation of

wedge lock

Function tests

Charging of Accumulators

Load tests

Starting of system

Installation completed

Figure 1 Float chart installation

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 10 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 11 of 40

4.4

Welding to deck The davit is delivered with brackets for welding under ships deck. Correct position for the brackets are given in the davit arrangement drawing. NOTE! Check that the brackets are correctly levered and that they do not twist during welding.

4.5

Maneuvering equipment location Maneuvering valve should be located in a position in view to the MOB boat during launching. A spring-loaded control valve to be installed in the return line as close as possible to the maneuvering valve. Opening pressures 2-3 Bar. Valve is to prevent loss of oil and is for that reason very important. Check valve in pressure line close as well.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 11 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 12 of 40

4.6

Maneuvering valve connections

Brevini valve central


HPV

Lever movement (from picture position) gives oil to port: Port A Pull lever Port B Push lever

Plug for P

Port A

Port P

Port B

Port T Pressure adjustment valve


Figure 2 Maneuvering valve connections

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 12 of 40

User Manual TDB-3602


4.7 Hydraulic system on ship.

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 13 of 40

General Keep all pipe connections from winch, pump, cylinders etc. plugged until final system connecting is complete. Only plastic plugs or covers must be used. Do not use paper plugs or cotton waste. The system is designed for minimum pressure loss. Pipe sizes as shown on system drawings are based on short distance between hydraulic users. Max. 10m pipe distance between davit and maneuvering valve. Idle pressure measured at maneuvering valve shall not exceed 5 bar. Choice of pipes On long distance pipelines the velocity must be reduced by increasing the diameter. Pressure head loss and oil velocities must be kept to a minimum in pipelines for leakage oil from pumps and motors. These pipelines should go direct to the tank and not be connected to the return line. Forming the pipelines, bends must be achieved by cold bending without sand- or lead filling. If welding cannot be avoided, the joints should be placed so that they are easy accessible for maintenance. Fittings In hydraulic installations, un-welded couplings are preferable. For external diameters up to 42 mm, cutring-couplings may be used. First condition of a tight joint is pipe cutting at correct angle, using a jig. External and internal grades must be removed. Debris must be thoroughly removed using white spirit, compressed air or clean textile cloths. (Do not use paper or waste cotton). Cutring are to be assembled according to the manufacture specification. The pipes must be properly adjusted/fitted prior to installation. The conring armature cannot pull together pipes that are too short or straighten distorted bends. When the system has been used for a period, the couplings should be re -tightened. The flange couplings must consist of one male and one female part with O-ring. Threaded connections Threaded connections do not give complete sealing, therefore sealant is required. Teflon tape is not recommended, especially for cast iron. Furthermore, surplus Teflon can enter the system and create functional problems. Loctite should be used rather than thread tape.
Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 13 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 14 of 40

Cleaning of pipes NB! All pipes must be cleaned when the assembly is finished. This is very important. Arrangement of pipes The distance between pump, valves and motors should be kept to a minimum. It is preferable using formed pipes rather than elbows due to loss of efficiency. Clamping The clamps shall prevent the pipes from vibrating and at the same time allow longitudinal movements. The clamps should be lined with plastic or rubber to prevent wearing of the pipes and reduce the noise level. Normal distance between clamps is 25-50 time outerdiameter. Longitudinal expansion Pipe bends or hoses can be used for compensation of thermal expansion. Noise Noise may occur in high-pressure hydraulic systems, but correct installation can reduce this substantially: - The pump must have adequate supply of oil. - Flexible suction line can be an advantage. - The suction line must be absolute tight to prevent air entering into the oil. In some cases it can be necessary to install an accumulator on the compression side. - Hoses can be used in the system functioning as shock absorbers and elongation compensators. - No metallic contact between pipes and clamps.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 14 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 15 of 40

Flushing of the system Prior to assembly of the main components it is recommended that the pipe system is flushed. The main components may be by-passed when flushing. The flushing power pack should give an oil flow not less than the capacity of the hydraulic system. The flushing should go on for 4-8 hours, depending of the number of joints and pipe lengths. During the flushing operation the filter must be checked regularly and replaced if required. The filter grade must be at least equal to the system filter. NAS-class 7 to be achieved. The oil used for flushing shall be of the same type as that used under operation. Pressure testing Pressure testing of the pipes must be achieved prior to starting operation of the system. According to The Norwegian Maritime Directorate regulations a normal testing pressure equals 1,5 x operation pressure. NB! Only the pipe system must be tested. Pumps, motors, cylinders and valves are not normally tested. Nitrogen to be used as test gas.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 15 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 16 of 40

PIPING EXAMPLE

Flexible hoses should be installed according to specifications on the diagram. The hoses can not stand sharp bends or torsion. The bending radius must be checked to make sure that it is sufficient and that the hose is long enough to be moved freely.

Right

Wrong

Hose to short and turned Use a big bend The hose must not be turned in bending

Remember smallest bending radius

Make the hose long enough Never use sharp bendings Use hose connections giving the hose right direction
Figure 3 Piping exanple

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 16 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 17 of 40

4.8

Filling of hydraulic oil Tank, pumps and motors must be filled with correct type of oil according to manufacture specifications. Oil types For emergency systems of this type it is important that the hydraulic oil has a correct viscosity at all times and at all temperature conditions. A hydraulic oil of good quality and high viscosity index is recommended. Oil with viscosity grade 22-68 cSt at 40 C, running 13-54 cSt, will assure a good result under normal temperature conditions.

The following table indicates the temperature extremes between which the viscosity grades can be used to remain within start-up and running viscosity range recommendations. Viscosity 22 is recommended with ambient temperature from +5 to -10 C. ____________________________________________________________________ Viscosity Grade Start up Start up Start up Running Running @ 40 C 860 cSt 220 cSt 110 cSt 54 cSt Max. 13 cSt Min 22 cSt -22 C -5 C 8 C 18 C 55 C 32 cSt -12 C 6 C 14 C 27 C 62 C 46 cSt -6 C 12 C 22 C 34 C 71 C 68 cSt 0 C 19 C 29 C 42 C 81 C In special Arctic condition the use of synthetic oil is recommended. Shell Tellarctic Oil or equal. The gearbox should use gear oil EP 80W/90 or equal. Operation temperature For continuous operation the temperature should not exceed 65 C anywhere in the system. Normally the best results are achieved at 55 C.
Lubricant chart NIPPLE LUBRIC. (Also davit arm and cylinder) ALVANIA EP BEALON EP2 MOVILLUX EP LM GREASE MARSON

BRAND SHELL ESSO/EXXON MOBIL CASTROL FINA ELF

HYDRAULIC OIL BRAKE TELLUS T-32 UNIVIS N 32 MOBIL DTE 13 M HYSPIN AWH 32 HYDRAN HV

GEAR OIL OMALA OIL 150 SPARTAN EP 150 MOBILGEAR 629 ALPHA SP 150 GIRAN REDUCTELF SP150

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 17 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 18 of 40

4.9

Starting the system Preparation before starting After mounting, flushing and oil filling, the following 7 points have to be controlled:

1. 2. 3. 4. 5. 6 7

The oil level in tanks. Circuit- and steering voltage. Turning direction of pump and motor. Over-pressure valves, throttle valves and mass control valves have to be completely open. Valves in the suction line have to be open. All pipe couplings have to be securely tightened. The accumulator on chock absorber must be charged.

Starting

The test run can start when all above 7 points are controlled and found in order. The system shall be run at low pressure and aired carefully. Airing should start close to the pump and end at the driving gea. (Winch, cylinder). The different components to be tested at low pressure. Cylinders and motor shall be run several times in both directions. If everything is satisfactory, the system to be slowly brought up to normal operating pressure. The pressure is increased by keeping the maneuvering valve for cylinder in POs in and at the same time tighten the safety valve (at the inlet side of the maneuvering valve). When the operating pressure has been reached, the pipeline must be checked for tightness. When all connections are found tight, all valves shall be set at correct pressure and oil level. See hydraulic diagram. During starting period, the filter inner parts should be replaced after 10 hours of operation.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 18 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 19 of 40

4.11 1. 2. 3. 4.

Threading of wire Lead the wire through the inner wire sheave (item 1), then below the next wire sheave(item 2). Run the wire through the shock absorber wire sheave(item 3), and then back to the winch(item 4). Run the wire around the winch and into the winch wedge socket. Fasten wire rope in wedge socket firmly.

Figure 4 Threading of wire

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 19 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 20 of 40

4.12

Maintenance of piston rods on the hydraulic cylinders on the TDB-Davit

Piston rod on cylinder is made of chrome plated stainless steel. It is very important to keep the piston rod clean to avoid seal damage. Piston rods exposed to salt and marine environment may cause failure on the chrome layers on the piston rods. If the chrome layer get pitting/cratering the sealings inside the cylinder will fail, and a leakage may occur. All cylinders have projection of the piston rod. (See pictures) This area is to be cleaned once a week. This area will always be exposed to salt and marine environment.

Figure 5 Piston rod on cylinder.

Projection (Exposed all time) To prevent damage on the chrome layer the davit must be in parked position when its not in use. This means all cylinders on the davit all in. If some of the cylinders must be in out position for some days, the piston rod must be cleaned also then once a week.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 20 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 21 of 40

Figure 6 Cylinder

Rod to be cleaned once a week. Guiding cylinders (if included): The guiding cylinder rod is exposed to the salt and marine environment . To prevent damage on the chrome layer on rod the rod must be cleaned once a week.

Figur 7 Guiding cylinder

Rod to be cleaned

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 21 of 40

User Manual TDB-3602


4.13| Lubrication oil and drain connections for winch

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 22 of 40

VESTWINCH

Figur 8 Winch lubrications points

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 22 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 23 of 40

4.14 Item 1. 2. 3. 4.

Instruction for activating shockabsorber Description - Filling connection - Ball valve - Accumulator - Cylinder

Figure 9 Activating shockabsorber

DESCRIPTION The damping element consists mainly of a one-acting cylinder which is connected to a preloaded accumulator.
ACTIVATING

1. 2. 3.

Start the system, idle running. Loosen fitting at filling connection. Make sure that the wire is unloaded. Open the ball valve slowly until the cylinder is in out position and oil is flowing out of the fitting. Then shut the ball valve, and tighten the fitting. It may also be useful to air at the breather on the accumulator. Repeat the operation until the system is de-aired. The damping element is now ready for use. The accumulator is charged with nitrogen. The pressure is calculated according to the weight to be suspended in the davit. With no load on the hook, the pressure should be checked twice a year. Draining the system: Stop the system, and open the ball valve. The oil will flow back to the tank when the cylinder is compressed.
Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

4.

Page 23 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 24 of 40

ACCUMULATOR FILLING UP If the N2 pressure in the accumulator is too low, it can be filled by use of a special t tool. 4.15 Instructions for refilling nitrogen on shock absorber accumulator.

For refilling nitrogen on shock absorber accumulator we recommend using a Filling- and checking equipment. This equipment can be obtained from Vestdavit AS . Operational weight is boat weight + 3 crew members.

PRESSURE-LOAD GRAPH 80 SHOCKABSORBER


PRELOADING ACCUMULATOR IN BAR/ TON

250

216 bar 200

150

151,5

100 86

50 1 2 3 4 5 6 7

ton

STATIC LOAD
Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 24 of 40

User Manual TDB-3602


4.15 Test Procedures

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 25 of 40

DELIVERY TEST PROCEDURES FOR THE FIRST INSTALLATION ONBOARD.

General The Davit to be installed according to Vestdavits General Arrangement drawing and hydraulic diagram. Accumulator to be pre charged to recommended pressure, hydraulic system pressure tested, function tested and wire spooled on winch drum. Representative from classification societies or other authorities may be present. The tests normally to be carried out by the yards staff.

Load Tests Load tests are done with Dummies in the hook. Do not use the boat. 1 LOWERING TEST (Brake test) Load = SWL x 1.1 = 3600 x 1,1 = 3960 kg The load to be lowered, with the hydraulic power unit running, and stopped three times by the brake during one lowering sequence. 2 HOISTING Load = SWL Minimum hoisting speed = 50 m/min (+/- 10%) 3 LIGHT LOWERING TEST Load: Boat with normal equipment. The Hydraulic power unit to be running. The load placed in stored position. Swing out the load and lower it. Minimum lowering speed = 50m/min. (+/- 10%)

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 25 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 26 of 40

Part V
5.1

OPERATING AND CONTROL


Checking before start Installation and oil filling is completed. System vented. The following must be checked: Oil level in tank. Relief valves, throttle valves and control valves to be open according to hydraulic diagram. All valves in the suction line must be open. Accumulator on shock absorber must be charged with Nitrogen.

5.2

Starting Start the Hydraulic Power Unit and circulate the oil for several minutes. Release lashings. Do a visual check of the equipment before operating a maneuvering handle. Observe the sound from the hydraulic power unit and the winch when operating the davit.

5.3

Special notes regarding the winch Maneuvering handle in hoisting position: If the oil pressure in the steering line exceeds the release pressure the automatic brake opens. The oil flows from aggregate, maneuvering valve, straight through steering valve, winch and back to the tank. Winch will hoist with desired speed. Maneuvering handle in stop (0-position). When there is a main power pack, the return line in the maneuvering valve is plugged, and there is no oil-flow through the valve in stop position. The oil pressure from the power pack does not influence the pressure of the circuit in the winch.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 26 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 27 of 40

5.4

Lowering operation

1. 2. 3.

Start power unit. Release slip hook and lashings. Check that sea painter line is connected to the Work boat. Push the davit outwards far enough to give the work boat the best position for launching. A throttle valve may adjust the speed. No people onboard during the initial push out. Launch the boat by means of the winch. When the boat is afloat, release first the hook and then the painter line.

4. 5.

5.5

Hoisting operation 1. 2. 3. 4. 5. Push the davit outwards far enough to give the boat the best position when hoisting. Lower the hook in position for the boat. Fasten the Sea painter line first, then the hook. Hoist the boat by means of the winch and stop at deck level so the people can disembark Move the davit inwards to parking position when the boat has passed deck level. Fasten lashings.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 27 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 28 of 40

5.6

Emergency push out and lowering operation General When an emergency situation has occurred, the davit arm may be moved out by means of stored energy. Oil pressure from the preloaded accumulator connected to hydraulic cylinder circuit, is used for the purpose. The system is designed so that the accumulator is automatically loaded when the maneuvering lever is held in cylinder in position. To obtain full pressure in the accumulator, make sure that cylinder is completely inwards. Then keep the maneuvering lever in the cylinder in position until you observe full system pressure indication on the gauge located on the maneuvering valve. Procedure for emergency push out: (The HPU to should be turned off) 1. 2. 3. 4. Release lashings. Open the ball valve marked 2. Move maneuvering lever to position cylinder out. Keep cylinder out until boat is clear of deck side.

IMPORTANT! The lever must not be placed in position cylinder in, because all oil from the accumulator will flow directly to tank.

Procedure for emergency lowering: 5. 6. Lower boat to embarking position. Lower boat to sea level

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 28 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 29 of 40

5.7

Emergency hoisting operation (see Hydraulic diagram) In a dead ship situation using the emergency hand pump can lift the boat. The accumulator is pressurized by using the emergency hand pump. The operation will require 2 men. Charging of accumulator. The davit in outer position. The valves marked 2 must be closed. Push the maneuvering handle to "Cyl. out" position and hold. Operate the hand pump until max. pressure is obtained in the accumulators. The accumulator pressure can now be used for lifting the boat. Lifting the boat (The accumulators loaded) One person operates maneuvering valve to winch hoist position, and then the ball valve marked 2 is opened. The boat will be lifted. When the winch has stopped, close the ball valve and put the handle in neutral position. Load the accumulator once more and repeat until the boat is hoisted. Recovery of davit arm (The accumulator loaded) One person operates maneuvering valve to CYL. IN position and then the ball valve marked 2 can be opened, and the boat will move in.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 29 of 40

User Manual TDB-3602


5.6 Charging of accumulator

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 30 of 40

Instructions for filling / checking of Nitrogen pressure

Figure 10 Charging of accumulator

1 2

Ensure that accumulator is shut off from the circuit and decompressed on the liquid side. Valve E to be unscrewed. Valve B to be closed. Attach the charging valve with its appropriate connector on the accumulator using the knurled nut F. Then tighten it fully after positioning the pressure gauge in the required position. Turn clockwise the adjustment knob E carefully. Check the pressure in the pressure gauge. If the charging pressure is too high, slowly open the general bleed valve B until the required pressure is obtained. To increase the pressure, connect the hose to the nitrogen supply and feed in slowly the pressurized gas. ATTENTION: In all cases, wait until the thermal exchange caused by the changes of pressure has stabilized before checking / adjusting the charge. DISMANTLING:

3. 4. 5.

1. 2. 3.

Unscrew the knob E completely. Bleed off with bleed valve B. Undo the nut F, and screw home the protection cap(s).
Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 30 of 40

User Manual TDB-3602 Part VI


6.1

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 31 of 40

INSPECTION AND MAINTENANCE

General Inspections shall take place according to relevant Authorities Regulations. Observe if the following should occur: - Increase in noise level - Vibration in winch - Functional faults If faults should occur, repair action must be taken immediately. Contact VESTDAVIT if necessary. The inspection and maintenance guide below is the manufacturer recommendation. However, the operation conditions for the davit, or the Authorities, may require more frequently or extended routines.

6.2

Inspection routines Monthly

1. 2. 3. 4

Hinge bolts for cylinders and sheaves shall be lubricated with grease. Check that maneuvering valve is moving freely and grease if necessary. Check oil pressure on accumulator, ref. manometer. The davit wire must be checked for splinters. The wire should be greased with special oil. The hydraulic oil level must be checked and the tank filled up if necessary. Oil identical to the oil in the tank must be used. Change of oil may be necessary after 1500 hours of operation or annually. Check oil level in gear and fill up if necessary. Check oil level in brake and fill up if necessary. Return filter element on oil tank must be checked and replaced if required. Normal interval for replacement: 500 hours of operation. Min. once a year. The piston rods for hydraulic cylinders must be kept clean and oiled to avoid seal damages.

5. 6. 7.

8.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 31 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 32 of 40

The Nitrogen pressure in accumulators to be checked each 6 months.

YEARLY INSPECTIONS Ref. relevant requirements from authorities. 1. 2. 3. 4. Change of oil in the systems should normally be done after 1500 hours of operation or annually. Gear oil to be renewed if necessary. Brake oil to be renewed if necessary. Return filter on oil tank to be replaced as required. Normal interval for replacement: 500 hours of operation. Min. once a year. Once a year perform a visual inspection of the cylinder and seals. Drive the davit out and check the cylinder rod for pitting and the seals for leakage. Replace if necessary.

5.

After two years 1. Replace seals according to service interval described in the technical manual . If pitting on the rod is evident, replace rod when replacing seals.. After ten years 1. Replace cylinder. If the davit arrangement when in use is exposed to a worst case scenario with 20deg inward heel and 10deg trim, replacement of the cylinder is needed. The used cylinder will then be sent to the manufacture for service and refurbishing given that the cylinder has not been in service for more than 10 years.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 32 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 33 of 40

WARNING
Do not loosen or tighten any hydraulic fitting while system is energized. Hydraulic fluid under pressure is a risk to personnel and equipment. Ensure hydraulic pressure is bleed from hydraulic accumulators before breaking hydraulic fittings.

Greasing of wire The lubrication new wire ropes receive during manufacture is adequate for initial storage and the early stages of the ropes working life. It must however be supplemented at regular intervals. The frequency of this re-lubrication depends on the frequency of usage. When the wire appears dry, it needs re-lubrication. Proper lubrication is important to the service life of the rope. The lubrication serves both as protection against corrosion and as a factor to reduce the friction between wires and strands in the rope. Lubricants should be free from acid and with no pernicious influence either on the wires or on the core. The lubricant must have a consistency that enables it to penetrate into the rope. The rope must be clean before the lubricant is applied.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 33 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 34 of 40

6.3

Disturbance of operations.
POSSIBLE CAUSE REMEDIAL ACTION

DEFECT

A. The winch will not hoist/lower.

1. Safety valve opens too early.

Measure the pressure with the drum locked. If the pressure is too low, the safety valve should be adjusted until the pressure gauge shows correct pressure. Check the valve.

2. Throttle valve on hoist line is closed. 3. The safety valve can be partly open due to particles between seat and valve. The winch will run slower than normal due to reduced oil supply to winch motor. 4. Insufficient amount of oil in the hydraulic oil tank. Suction line can be obstructed or have an air leakage. The pump will then give a squealing sound. 5. Having checked the above points and found the winch pressure to be as specified without achieving the specified pulling force, the fault might be in the winch.

Clean safety valve.

Check oil level on hydraulic oil tank. Check pump suction line.

Contact VESTDAVIT.

B. Substantial speed reduction.

1. Ref. A.2.

Ref. A.2

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 34 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 35 of 40

DEFECT

POSSIBLE CAUSE

REMEDIAL ACTION

B Substantial speed reduction.

2. Ref. A.3. 3. Ref. A.4. 4. If the speed reduction has developed gradually, the cause might be worn hydraulic pump or winch motor.

Ref. A.3. Ref. A.4 Check hydraulic pump. If the pump is in order, the motor in the winch must be overhauled or replaced. INVESTIGATE FIRST IF REPLACEMENT UNIT CAN BE DELIVERED.

C. Lowering speed is slower than hoisting speed

1. The control valve can reduce slide movement.

Check that coil movement in the control valve is equal in both directions. Ref. A Ref. A

2. Ref. A.1. 3. Ref. A.2. 4. The oil might be too thick and cause the safety valve to open. 5. Gasket in the winch might be defect.

Can be controlled by checking the amount of oil from the driver side.

D The brake releases when the control handle is returned to neutral after hoisting with load.

1. Wrong type of control valve. Correct valve shall have all gates to tank open when the handle is in neutral position.

Remove hoses or pipes from control valve. With handle in neutral position it shall be possible to blow air from gate "A" and "B" to tank gate. If not, a correct valve type must be provided.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 35 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 36 of 40

DEFECT

POSSIBLE CAUSE

REMEDIAL ACTION

2. Too high back pressure in the winch reverse the gate. Too high pressure on return line. Too small pipe dimensions or obstructions.

Check the pressure close behind the winch. Run the pump with maximum number of revolutions and read the pressure when the handle is in the neutral position. If the pressure is higher than 0,4kg/cm2 the return line should be investigated for possible obstructions, or be re-placed to greater dimensions. Replace the valve. Check the valve. Check, clean or replace the valve. Replace filter element. Ref. D1/D2. Measure the pressure with locked drum. If the pressure is higher than the specified maximum for the winch, it must be reduced.

3. Throttle valve on brake line is too tight. 4. Load control valve defect. 5. Dirt in change valve. 6. Dirt in return filter.

E. The brakes do not work at lowering operation.

1. Ref. D1, D2, D3, D4 and D5. 2. The winch may be over loaded.

3. After the above points have been checked and found satisfactory, the Contact VESTDAVIT. error is probably located in the winch.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 36 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 37 of 40

6.4

Long term stop and new start For long term stop in operation the oil tank must be completely filled to underside of tank (if separate power unit). This is to prevent condensation and internal corrosion. For the same reason it is recommended to run the system at regular intervals in order to lubricate all the moving parts. New restart should be performed in the same manner as the first starting operation. Additionally, do the following:

1. 2. 3. 4.

Drain oil from the tank bottom and check that the oil is free from water and dirt. If necessary, filtrate or replace oil before starting the pump. Check oil level. Check filter, clean all parts or replace if necessary. Check that maneuvering valve is moving freely and grease if necessary.

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 37 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 38 of 40

PART VII

SPARE PARTS

Item no. 1

Item name

Filter cartridge

Recom. qty. per davit 1

Vestdavit part no. 11242

Prime manuf. id.

Del. time 1 week

TTF230 TXW-5-10

Item 1 is recommended to store onboard.


2 3 4 5 Seal kit for maneuvering valve Seal kit for hydraulic cylinder. Seal kit for shock absorber Wire 18mm 1 1 1 29m 10810 11309 11359 10674 HPV-O-77M19041C80
HMT2-V-D100/90x70/40x370

2 weeks 2 weeks 2 weeks 1 week

CP4G 80 x 400 35x7 W/Spelter soc.

Item 2 5 are spare parts recommended for the first 5 years.


6 Hydraulic Cylinder 1 11200 HMT2-V-D100/90x70/40x3 700-S-R-SP 4 weeks

How to order When ordering spare parts to davit, please provide the following information: Davit type Davit serial no. Vestdavit Project No. : : : TDB - 3602 8050 8050

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 38 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 39 of 40

APPENDIX A - DRAWINGS
A-14539 A-32137 A-14585 13540-1A 20613 612-33A Davit arrangement Hydraulic diagram Hydraulic Winch Hydraulic Power Unit Starter Shock absorber

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 39 of 40

User Manual TDB-3602

No.: Rev.: Date: Page:

VDT-UMT-8050 00 0-JUL-09 40 of 40

APPENDIX B - CERTIFICATES
Davit Winch Wire Ring Electric Motor Hoses

Damsgrdsvn. 143, 5160 Laksevg, NORWAY Tel.: +47 55 54 92 00 E-mail: post@vestdavit.no http://www.vestdavit.no

Page 40 of 40