In a collective order, planned orders or production orders are linked to one another over several production levels. Each order in the collective order has its own order number. If subassemblies are produced directly for superior orders within a production process, without physically entering the warehouse, it is useful to have a representation via collective orders. The components for which separate production orders are created in the collective order are called directly produced components (see Creating Collective Orders)

Prerequisites
A collective order cannot be created for components that have one of the following indicators set: Co-product By-product Alternative item with strategy 2 Alternative item with usage probability 0 Discontinued Follow-up material Intra material

Features
Collective orders offer the following advantages: Integrated view of a production process Collective orders make it possible to represent different levels of the production process together in the system. The production process can be viewed as an integrated whole. Separate order number for every order Every level in a collective order represents a separate production order/planned order. Every production order/planned order has its own order number. This enables you to process the entire collective order, a subtree in the collective order or an individual order. No placements in storage or removals from storage between production levels

Within a collective order stock movements only take place for the leading order (that is, the order that is at the highest production level) and not for directly produced components. This makes it easier to maintain the collective order in comparison with several individual orders. A further advantage is a more realistic representation of the costs of the production process, since subordinate orders can be directly assigned and settled to superior orders. Business functions simultaneously for several orders Certain business transactions can be carried out simultaneously for several orders. Releasing an order that belongs to a collective order has the effect that all the hierarchically subordinate orders are released simultaneously. Automatic change to dependent orders Changes to an order automatically affect dependent orders / components affecting orders. For example, if you change the order quantity in an order then the relevant quantity changes are automatically made to dependent orders the requirements quantity of the directly produced component is automatically changed.

In the collective order, you also have the option of manufacturing directly produced material in a different plant to the planning plant. Set status in leading order If you make changes in subordinate orders that have an affect on the status, then the system sets the corresponding status in the order header of the leading order in the collective order as follows: CFCO Confirmation in collective order GMCO Goods movements in collective order RLNE Release taken place in network In this way you are informed about changes in the whole collective order. Reading master data You can copy the routing data and BOM data to the order again. You can find more information in Read master data.

Example You want to produce a pump. The BOM for the pump contains a pressure regulating valve and a spiral casing. You want to enter these two components in separate production orders, but you do not want them to be posted to stock. You set the special procurement type to direct production in the material master record for the pressure regulating valve and the spiral casing, so that production occurs using a collective order. When you create a production order for the pump, a collective order is automatically created, which contains subordinate production orders for the pressure regulating valve and the spiral casing.

ntroduction:

This White paper explains briefly on the scenario of direct production or collective order concept. Basically, collective order is the technical term used for the Direct Production scenario.

Main objective of the document is to explain the basic concept of collective order with Business examples as well as sap Process flow. Best attempt has been made to explain key settings, advantages, Disadvantages & Limitations of collective order. I would also update versions based on feedback and comments of SDN experts and consultants on this topic accordingly in future.

Collective order or direct Production can be carried out for Discrete Manufacturing or PP-PI. However this document limits to Discrete Manufacturing only.

Applies to: ECC 6.0, Sap R/3 4.6

Need for Direct production or Collective order:

If subassemblies are produced directly for superior orders within a production process, without physically entering the warehouse, then it is useful to have direct production via collective orders. Example: 1. 2. Joining of Left door & Right door assembly in a car Fitting of Front & rear wheel assembly in cycle or Bike

Direct Production:
Direct production is the special type of production where components are directly produced for the higher-level assembly, without Stocked @ warehouse as normal and no goods receipt or goods issue postings are made for components that are produced directly. The system flags a direct production segment for the components to be produced directly in the MRP list and the stock/requirements list. When the planned order for the finished product is converted into a production order, the system also converts all planned orders for lower-level components to be produced directly into production orders. The system adapts planned orders for direct production to changes in date and quantity in the higher-level assembly, even if they are firmed, so that the collective order remains consistent.

Collective order:
Collective order is a network where planned orders or production orders are linked to each another over several production levels. Each order in the collective order has its own order number. The components for which separate production orders are created in the collective order are called directly produced components.

Business scenario:
Let us understand Business scenarios where collective order or Direct Production scenario is used before briefing the sap process flow. In Our professional life, we used to get below items from our Company or in any events a) Ball pen or Mug or Bottle embedded with Company name

b) c)

Wrist watch or wall clock with company logo & name Wallet or Bag or Sun glass embedded with Company or sponsor

If the manufacturer uses exclusive components for producing above finished product where he wants to control production with linkage of header & child orders with no intermediate stock transfer to warehouse, then Collective order process will be helpful. Above examples are just for explanation purpose of collective order in a better way but it is not limited .You can use Collective order concept in general where components has to be issued only to Superior orders instead of warehouse as unrestricted stock . Sap Process Flow of Collective order: A. A. Configuration: B. A.1 Order Type Setting:
IMG path: Production --> Shop Floor control --> Master data --> order Tcode: OPJH --> Define order Types

If this indicator is set , then it means there are automatic goods movements between the production orders in a collective order. When the goods movement is posted,costs are credited from the subordinate order& costs are debited to the superior order.

A.2. Special Procurement Key:


IMG path: Production --> Material requirement planning --> Master data --> Define special procurement type

Case study:

Let us take manufacturing of Ball Pen, a simple example for the scenario of collective order processing.

Product structure:

1 Ball Pen (Finished Product)

1.1 Pen casing ( Halb) 1.1.1 Refill for Pen casing (ROH)

1.2 Pen Cap (Halb) 1.2.1 Slug for Pen cap (ROH)

Master Data:

1. Multi level BOM for Ball Pen & Routing

TCODE: CS12

2. Material Master:

2.1 Header Material MRP views: TCODE: MM02

2.2 Child Material MRP views: TCODE: MM03

Production planning & Control Cycle :

Collective order can be created by below 3 methods

1. Directly Production order with Header Material using Tcode : CO01

2. Create Planned order ( Tcode : MD11) for Header & Convert into Production order (Tcode :CO40) 3. PIR -------> MRP -----> Planned order to Production order.

Let us illustrate by Method 3 with Full cycle of Material Planning & Shop Floor Execution.

Material Planning:

i. creation of Planned Independent requirement (MD61 ):

ii. MRP RUN (MD02) :

I.

iii Stock Requirement List (MD04) :

A.

Stock requirement list for Header Material & child material :

Planned order for Header material & child material are created for the balance required qty (17)

*** You can notice Description Direct Production & Dep req for Header material .

I.

iv .Order Report:

If we execute order report, we can see linkage of planned order as a network in below screen shot.

I.

v. Planned order : Here is the advantage of collective order concept. Subordinate planned orders are linked to superior header order which can be seen in assignment tab of below screen shot of child planned orders. TCODE: MD13

I.

vi. Conversion of planned order to production order :

Refer stock requirement list below once planned order of header material is converted

Shop Floor Execution:

Real Benefits of collective order concept starts here. Mark *** highlights its advantage

I. Creation of collective production order (CO03)

When we click read collective order button, system will display collective order network @ created stage as below.

Note : Collective orders represent different levels of the production process together as an integrated whole network. Each level represents a prod order. *** Refer assignment linkage of subordinate order to Leading /superior order below

I.

ii. Scheduling

of collective production order (CO02) :

***If we schedule header superior order, it automatically schedule total network of collective order.

iii. Releasing

of collective production order (CO02) :

*** Releasing the superior order results in release of all child orders in network. Header order receives RLNE status Release in Network.

I.

iv. Changing collective production order (CO02) :

*** We can change header order Quantity or Scheduling Date or both which will gets drilldown to entire network below. Read PP master data function for header order is allowed. Note: Below case, we have changed order qty from 17 to 15 which got drilled down.

I.

v.Confirmation of CO11n) :

collective production order (CO15 or

Confirmation of child order @ order level or operation level will result in direct Good issue to header order. Stock of subordinate order will not be available in warehouse .Instead; child component is directly produced for Header order.

Note that leading order will get below status when there is confirmation or goods movement in network. 1.1. 1.2. CFCO Confirmation in collective order GMCO Goods movements in collective order

*** Check warehouse stock for the direct components which is nil. TCODE: MB52

*** Check Material document for the direct components which shows GI for order (261) --TCODE: MB51

vi.Final confirmation of leading order :

I.

vii. GR of

collective production order (MB31) :

Refer FInal material document & Stock overview

This concludes the complete cycle of direct production via collective order

Limitations:
We have limitation to create collective order if components are belongs to below set

Co Product or By product Alternative item of strategy 2 or usage probability 0 Either Discontinued or Follow up or Intra Material

Moreover, Collective order cannot be created Via SAP APO.

Exception settings:

If you want to restrict direct production for a particular BOM, then you enter this in the respective BOM item. This entry overwrites the entry in the material master. or

You can use the indicator "No direct production" in the explosion key to switch off the direct production for individual BOMs.

TCODE: CS02

Conclusion:
In general , Direct production is aimed at doing Major sap business functions such as Creation ,Release ,scheduling ,costing for Finished product ,assembly & components within a BOM structure jointly or collectively. Even though direct production or collective order has its unique benefits, it has a negative impact of Material flow & stock inventory indirectly. Collective order will not consider below points

Plant warehouse stock of direct components. Anonymous Dependent requirements are not considered.

i would be happy to include feedback and improvement points from SDN PP experts in subsequent Versions for the benefit of Members .

Reference:

1.

1. http://help.sap.com/erp2005_ehp_06/helpdata/en/b1/c0500c439a11d189410000e829fbbd/content.htm? frameset=/en/a5/63198843a211d189410000e829fbbd/frameset.htm 2. http://scn.sap.com/message/7241069

2.

1.

I.

You might also like