Professional Documents
Culture Documents
v. vi.
Measurement and Payment shall be made on the basis in the Specification. If the Drawings do not contain particular materials and works which are obviously necessary for the proper completion of the works, all such materials and works shall be deemed to be included in the unit price stated in the Bill of Quantities for the appropriate items of the buildings construction works.
vii.
The Subcontractor shall provide all temporary building including site office. The space for all temporary building will be provided by the Main Contractor. But the reinstatement of these shall be done by the Subcontractor.
viii. ix.
The Subcontractor shall responsible for all claims including civil appeals related to Architectural & Metal work The Subcontractor shall provide generators for his own use because no electric power supply from PLSs existing distribution line is available at the Site for construction use.
All consumable materials related Architectural & Metal work. Architectural & Metal work Intake Control House Intake Guard House Headpond Control House Work Tunnel for Powerhouse Arch Heading Powerhouse Outdoor Switchyard Service Building All consumable materials related Architectural & Metal Works. The Subcontractor shall cooperate with other Contractors below on interfacing matters. Lot II : Metal Works Contractors Lot III : Electromechanical Works Contractors Lot IV : Transmission Line Contractors Lot V : Telemetering and Flood Warning System Access Roads and Base Camp Contractors 20KV Distribution Lines Contractors
4.
Insurance
i.
The subcontractor shall insure all insurance against such risks as are specified therein that the subcontractor first enters upon the site for the purpose of executing the work. That is to say the subcontractor shall effects insurance as bellow; Third party insurance Labor insurance Medical(health) insurance Vehicle insurance Equipment insurance National pension
5. Indonesian Taxes, Duties, Permits and Licenses i. The off and on-shore portion of the Contract will be exempted from Indonesian taxes and levies, except for personal income tax(es), levies, duties related to personal items ii. VAT(Value Added Tax) shall be paid by the Contractor.
Duties, taxes and other levies indicated below shall be exempted; iii. iv. Import Duties of the Plant and Materials Import Duties of the Contractor s Equipment in case they are re-exported after completion of the Works 6. The others i. ii. iii. Performance bond : 10% of contract amount Advance Payment : to be discussed later Defect Liability Period : 12 months
7. Submission i. ii. iii. iv. v. vi. Quotation Company profile Method of general construction details (Powerhouses, Intake Control houses and others) Area (m2) required for temporary office Area (m2) required for equipment and material stock yard. Subcontractor s Equipment and Labour Forces Schedule. Subcontractor shall
enter details of requisites items in enclosed format Schedule T-4 Contractor s Equipment, and Schedule T-6 Labour Forces. vii. Organization Chart and Manning Schedule Site Organization Chart One organization chart shall be provided for the proposed structure, staff members and positions necessary to adequately manage and control the Works. Manning Schedule shall be provided in bar chart format, covering the contract period in monthly horizontally and listing the key personnel vertically. The key personnel are site management and senior supervisory personnel that Subcontractor considers necessary for the Works.