INSPECTION AND TEST PLAN

For

Structural Concrete

Project Name Contract No. Client ITP No.

: : : :

BTIP- Onshore Facilities / Offshore Pipelines E-09335 Shell Petroleum Development Company of Nigeria Limited ITP-C-005

EPIC CONTRACTOR Rev Date Description Prepared by 0 Jan.17. 2003. 1 Feb.07 2003 Re-issued for Review/Comment J.W.KIM G.W.KIM K.S.CHUNG For Review/Comment J.W.KIM Reviewed by G.W.KIM Approved by K.S.CHUNG Date

SPDC Reviewed by Approved by

1, Cheonha-Dong, Dong-Ku, Ulsan, Korea, 682-792, http//:www.hhi.co.kr Tel: 82-52-230-5461/2, Fax: 82-52-230-3549, E-mail: btipdcc@hhi.co.kr

Client : SPDC Item : Structural Concrete Discipline : Civil

INSPECTION & TEST PLAN

ITP No. : Page :

C-005 1 of 2

Rev. 1

BTIP-Onshore Facilities / Offshore Pipelines Contract No. : E-09335 No. Activity Description 1 Pre-pour inspection of forms, rebar embeds etc. Release for concrete order by construction and request to pour. Each work Frequency Procedure / Spec. ITP-C-004 Verify ITP-C-004 (blinding concrete) complete Rebar installed as per drawings. Embedded items installed as per drawing. Verify structural concrete surfaces scabbled, primed as applicable. Verify placement of concrete as per spec. rqmnt. Concrete receival & placement inspection. Verify correct concrete design mix used. Method / Acceptance Criteria Reporting Format HSFP-CE-08 Survey Report Inspection By S/C HHI R SPDC W Remarks

Each work

SCS sec.12.4.2 SCS sec.12.4.3

Delivery Ticket

S/W

S/W

Concrete field testing and sampling carried out.

Each work

SCS sec.12.4.8

Verify slump. Verify max. concrete temp. as per spec rqmnts. Verify max ambient temp. as per spec. rqmnts. Verify entrained air as per spec. rqmnts.

HSFP-CE-08

S/W

S/W

Form striking, surface inspection & completed repair, if required.

Each work

SCS sec.12.2.18

Verify major repairs (if required) carried out immediately after form removal. R : Review Point, M : Monitoring,

N.C.R. (If required)

* Legend : S/W : Spot Witness,

W : Witness Point,

H : Hold Point,

I : Random Inspection,

SCS : Standard Construction Specifications Client : SPDC Item : Structural Concrete Discipline : Civil

INSPECTION & TEST PLAN


BTIP-Onshore Facilities / Offshore Pipelines Contract No. : E-09335 Method / Acceptance Criteria

ITP No. : Page :

C-005 2 of 2

Rev. 1

No.

Activity Description Curing and protection of concrete.

Frequency

Procedure / Spec.

Reporting Format

Inspection BY S/C HHI S/W SPDC S/W

Remarks

Each work

SCS sec.12.4.19

Wet curing minimum 7 days, Hydraulic concrete min. 14 days as per spec. rqmnt.

Placement of pre-cast items

Each work

SCS sec.12.4.17 ITP-C-003

Verify pre-cast item has been released, prior to placement. See ITP-C-003.

R/W

Conformance of compressive strength results

Each work

SCS sec.12.4.21

Verify minimum compressive strength result as per spec. rqmnts. All inspection and tests complete and conformant. Release for additional courses, coating or loading (as applicable)

HSFP-CE-10 HSFP-CE-11 HSFP-CE-12 N.C.R.