PART 6 - PRODUCTS
6.01 GENERAL A. In order to achieve competitive bidding of products and enable the greatest number of vendors to participate in procurement opportunities, every attempt has been made to indicate multiple and comparable selections for all categories of products throughout the technical Specifications. The A/E shall ensure that no proprietary manufacturers are listed in the Projects final Specification documents unless approved via Owner or otherwise indicated herein. B. Changes in technologies, introduction of new products, phasing out of product lines, and changes in a manufacturers ownership can quickly render a Specification obsolete. While MD Anderson will endeavor to maintain the Master Construction Specifications current, critical
B. Typical Master Construction Specification Footer: Footers within Master Construction Specification Sections must not be edited. Footer Content: The University of Texas MD Anderson Cancer Center Owners Control Number Footer Example: The University of Texas MD Anderson Cancer Center MS010107
C. Typical A/E Generated Specification Footer: A/E shall not remove the Owners name or page numbering. A/E must delete Owners Control Number and include the applicable CSI Section Title and Number. Footer Content: The University of Texas MD Anderson Cancer Center MS###### Footer Example: The University of Texas MD Anderson Cancer Center The University of Texas MD Anderson Cancer Center ODG061113
Rev. 3
04-08-08
DOS
Rev. 4
03-02-10
SAK, DOS
Rev. 5
08-12-10
DOS
Rev. 6
03-31-11
SAK
Rev. 7
08-02-11
DOS
END OF ELEMENT 2010 The University of Texas MD Anderson Cancer Center ODG061113 INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 11 OF 11
The Project Architect/Engineer (A/E) shall organize the Project Manual in accordance with requirements described within this Attachment and as based on the following examples for project delivery types. For projects that require multiple bid packages, documents included in the Project Manual for each bid package, must be applicable to the scope of the bid package issue.
TABLE 1. JOB ORDER CONTRACTING (JOC) A Procurement And Contracting Requirements Group
Electronic File Name Include in Notes Project Manual? OWNERS BIDDING REQUIREMENTS AND CONTRACT FORMS Request for Proposal for a No Issued by Owner under separate cover for General Contractor contractor procurement. Respondents Pricing and No Delivery Proposal Draft Agreement between No Owner and Contractor including Performance and Payment Bond templates Rider 1 to the Agreement, No Joint Commission on Accreditation of Healthcare Organizations (JCAHO) Historically Underutilized No Business (HUB) Subcontracting Plan Rider 105, Contractors No Affirmations and Warranties Rider 106, Premises Rules No Rider 107, Travel Policy No RFI Request for No Information Form INTRODUCTORY INFORMATION Project Title Page Yes Table of Contents Yes Edit to suit Project. For phased release of bid packages, the Table of Contents must reference all documents with their associated issue date and issue description. Note documents previously issued as Issued under separate cover. Document Name
N/A
N/A
00 01 01 00 01 10
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 1 OF 8
ATTACHMENT A PROJECT MANUAL ORGANIZATION TABLE 1. JOB ORDER CONTRACTING (JOC) A Procurement And Contracting Requirements Group
Electronic File Name Include in Notes Project Manual? CONDITIONS OF THE CONTRACT 2010 Uniform General and No Issued Under Separate Cover. Supplementary General Conditions for Building Construction Contracts for The University of Texas System Owners Special Conditions Yes A/E and Owners Project Manager must edit for Project requirements. Attachment A: No Issued Under Separate Cover Minimum Wage Rate Determination Attachment B: Yes Facilities Planned Utility Outages Policy Attachment C: No Not Applicable to Job Order Contracts. Project Sign Layout Attachment D: See Notes Applicable to Bastrop Projects only. Bastrop Visitation and Tour Policy Statement and Medical Documentation Requirements Document Name
00 25 00 00 25 00 A
00 25 00 B
00 25 00 C 00 25 00 D
B Specifications Group
01 31 00 01 32 00 01 35 16 01 35 25 01 35 25 A 01 45 00 01 57 23 01 57 25 01 77 00 01 91 00 DIVISION 01 GENERAL REQUIREMENTS Project Administration No Issued Under Separate Cover. Project Planning and No Issued Under Separate Cover. Scheduling Alteration Project No Issued Under Separate Cover. Procedures Owner Safety No Issued Under Separate Cover. Requirements Attachment "A": No Issued Under Separate Cover. I.A.Q. Activities Policy Project Quality Control No Issued Under Separate Cover. Temporary Storm Water No Issued Under Separate Cover. Pollution Control Dust Control Plan No Issued Under Separate Cover. Project Closeout No Issued Under Separate Cover. Procedures General Commissioning No Issued Under Separate Cover. Requirements ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 2 OF 8
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION TABLE 1. JOB ORDER CONTRACTING (JOC) A Procurement And Contracting Requirements Group
Electronic File Name Document Name Include in Project Manual? Notes
B Specifications Group
File name is specification division number (typical). DIVISIONS 02 THROUGH 19 CONSTRUCTION SPECIFICATIONS Refer to Project Manual Yes A/E must edit to suit Project requirements; Index for complete listing of A/E shall furnish specification sections for Master Construction required products and components not Specifications. listed in the Project Manual Index.
DIVISIONS 20 THROUGH 28, 32 & 43 CONSTRUCTION SPECIFICATIONS File name is Refer to Project Manual Yes A/E must edit to suit Project requirements; specification Table of Contents for A/E shall furnish specification sections for division number complete listing of Master required products and components not (typical). Construction Specifications. listed in the Project Manual Index.
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 3 OF 8
The Project Architect/Engineer (A/E) shall organize the Project Manual in accordance with requirements described within this Attachment and as based on the following examples for project delivery types. For projects that require multiple bid packages, documents included in the Project Manual for each bid package, must be applicable to the scope of the bid package issue.
TABLE 2. COMPETITIVE SEALED BIDDING AND COMPETITIVE SEALED PROPOSALS A Procurement And Contracting Requirements Group
Electronic File Name Include in Notes Project Manual? OWNERS BIDDING REQUIREMENTS AND CONTRACT FORMS Request for Proposal for a No Issued by Owner under separate cover for General Contractor contractor procurement. Respondents Pricing and No Delivery Proposal Draft Agreement between No Owner and Contractor including Performance and Payment Bond templates Rider 1 to the Agreement, No Joint Commission on Accreditation of Healthcare Organizations (JCAHO) Historically Underutilized No Business (HUB) Subcontracting Plan Rider 105, Contractors No Affirmations and Warranties Rider 106, Premises Rules No Rider 107, Travel Policy No RFI Request for No Information Form INTRODUCTORY INFORMATION Project Title Page Yes Table of Contents Yes Edit to suit Project. For phased release of bid packages, the Table of Contents must reference all documents with their associated issue date and issue description. Note documents previously issued as Issued under separate cover. Document Name
N/A
N/A
00 01 01 00 01 10
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 4 OF 8
ATTACHMENT A PROJECT MANUAL ORGANIZATION TABLE 2. COMPETITIVE SEALED BIDDING AND COMPETITIVE SEALED PROPOSALS A Procurement And Contracting Requirements Group
Electronic File Name Include in Notes Project Manual? CONDITIONS OF THE CONTRACT 2010 Uniform General and Yes Do not edit. Supplementary General Conditions for Building Construction Contracts for The University of Texas System Owners Special Conditions Yes A/E and Owners Project Manager must edit for Project requirements. Attachment A: Yes Do not edit. Minimum Wage Rate Determination Attachment B: Yes Do not edit. Facilities Planned Utility Outages Policy Attachment C: See Notes Do not edit. Include if applicable; confirm Project Sign Layout with Owners Project Manager. Attachment D: See Notes Applicable to Bastrop Projects only. Bastrop Visitation and Tour Policy Statement and Medical Documentation Requirements Project Insurance (OCIP.) See Notes Do not edit. Include if applicable; confirm with Owners Project Manager. Document Name
00 25 00 00 25 00 A
00 25 00 B
00 25 00 C 00 25 00 D
00 73 16
B Specifications Group
01 31 00 01 32 00 01 35 16 01 35 23 01 35 25 01 35 25 A 01 45 00 01 57 23 DIVISION 01 GENERAL REQUIREMENTS Project Administration Yes Do not edit. Project Planning and Yes Do not edit. Scheduling Alteration Project Yes Do not edit. Procedures Project Safety (OCIP) See Notes Do not edit. Include if applicable; confirm with Owners Project Manager. Owner Safety Yes Do not edit. Requirements Attachment "A": Yes Do not edit. I.A.Q. Activities Policy Project Quality Control Yes Do not edit. Temporary Storm Water See Notes Do not edit. Include if applicable; confirm Pollution Control with Owners Project Manager. ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 5 OF 8
ODG050713
TABLE 2. COMPETITIVE SEALED BIDDING AND COMPETITIVE SEALED PROPOSALS B Specifications Group
Include in Notes Project Manual? DIVISIONS 02 THROUGH 19 CONSTRUCTION SPECIFICATIONS File name is Refer to Project Manual Yes A/E must edit to suit Project requirements; specification Index for complete listing of A/E shall furnish specification sections for division number Master Construction required products and components not (typical). Specifications. listed in the Project Manual Index. DIVISIONS 20 THROUGH 28, 32 & 43 CONSTRUCTION SPECIFICATIONS File name is Refer to Project Manual Yes A/E must edit to suit Project requirements; specification Table of Contents for A/E shall furnish specification sections for division number complete listing of Master required products and components not (typical). Construction Specifications. listed in the Project Manual Index. Electronic File Name Document Name
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 6 OF 8
ATTACHMENT A PROJECT MANUAL ORGANIZATION TABLE 3. CONSTRUCTION MANAGER-AT-RISK (CM-R) AND DESIGN/BUILD (DB) A Procurement And Contracting Requirements Group
Electronic File Name Include in Notes Project Manual? INTRODUCTORY INFORMATION Project Title Page Yes Table of Contents Yes Edit to suit Project. For phased release of bid packages, the Table of Contents must reference all documents with their associated issue date and issue description. Note documents previously issued as Issued Under Separate Cover. CONDITIONS OF THE CONTRACT 2010 Uniform General Yes Include original document as executed in and Supplementary the Agreement between CM-R or DB Firm General Conditions for and Owner. Building Construction Contracts for The University of Texas System Owners Special Yes A/E and Owners Project Manager must Conditions edit for Project requirements. Attachment A: Yes Do not edit. Minimum Wage Rate Determination Attachment B: Yes Do not edit. Facilities Planned Utility Outages Policy Attachment C: Yes Do not edit. Project Sign Layout Attachment D: See Notes Applicable to Bastrop Projects only. Bastrop Visitation and Tour Policy Statement and Medical Documentation Requirements Project Insurance (OCIP) Yes Include original document as executed in the Agreement between CM-R or DB Firm and Owner. DIVISION 01 GENERAL REQUIREMENTS Project Administration Yes Include original document as executed in the Agreement between CM-R or DB Firm Project Planning and Yes and Owner. (Typical Division 01 Scheduling documents). Alteration Project Yes Procedures Project Safety (OCIP) Yes ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 7 OF 8 Document Name
00 01 01 00 01 10
00 25 00 00 25 00 A
00 25 00 B
00 25 00 C 00 25 00 D
00 73 16
B Specifications Group
01 31 00 01 32 00 01 35 16 01 35 23
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION TABLE 3. CONSTRUCTION MANAGER-AT-RISK (CM-R) AND DESIGN/BUILD (DB) B Specifications Group
Electronic File Name 01 35 25 Document Name Include in Project Manual? Yes Notes
Owner Safety Include original document as executed in Requirements the Agreement between CM-R or DB Firm and Owner. (Typical Division 01 01 35 25 A Attachment "A": Yes documents). I.A.Q. Activities Policy 01 45 00 Project Quality Control Yes 01 57 23 Temporary Storm Water Yes Pollution Control 01 57 25 Dust Control Plan Yes 01 77 00 Project Closeout Yes Procedures 01 91 00 General Commissioning Yes Requirements DIVISIONS 02 THROUGH 19 CONSTRUCTION SPECIFICATIONS File name is A/E shall edit A/Es own See Notes Use Master Construction Specifications specification Specifications. only for redevelopment / renovation Projects within existing Owner facilities. division number EXCEPTIONS: Include Division 10 & 14 (typical). Master Construction Specification Sections listed below when applicable within Project Scope. 10 14 16 Cast Bronze Dedicatory Yes Confirm application with Owners Project Building Plaque Manager. 10 14 16 A Attachment A: Yes Building Plaque Drawing 10 44 00 Fire Extinguisher Cabinets Yes Required only when fire extinguisher and Accessories cabinets are included within Project Scope. 14 21 00 Electric Traction Elevators Yes Required only when traction elevators are included within Project Scope. DIVISIONS 20 THROUGH 28, 32 & 43 CONSTRUCTION SPECIFICATIONS File name is Refer to Project Manual Yes A/E must edit to suit Project requirements; specification Table of Contents for A/E shall furnish specification sections for division number complete listing of Master required products and components not (typical). Construction Specifications. listed in the Project Manual Index.
ODG050713
ATTACHMENT A PROJECT MANUAL ORGANIZATION INSTRUCTIONS FOR THE PREPARATION OF PROJECT MANUALS 2010 8 OF 8