AASHTO/NSBA Steel Bridge Collaboration S10.

Steel Bridge Erection Guide Specification April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration Task Group 10, Erection

PREFACE
This document is a DRAFT standard developed by the AASHTO/NSBA Steel Bridge Collaboration. The primary goal of the Collaboration is to achieve steel bridges of the highest quality and value through standardization of the design, fabrication, and erection processes. Each standard represents the consensus of a diverse group of professionals As consensus documents, the Collaboration standards represent the best approach to the processes they cover. It is intended that Owners adopt and implement Collaboration standards in their entirety to facilitate the achievement of standardization, but it is understood that local statutes or preferences may prevent full adoption for some. In such cases Owners should adopt these documents with the exceptions they feel are necessary. This document establishes and defines the basic, minimum requirements for the transportation, handling and erection of steel bridge components to ensure safe and accurate steel erection as well as quality and value in the completed bridge structure.

Disclaimer
All data, specifications, suggested practices presented herein, are based on the best available information and delineated in accordance with recognized professional engineering principles and practices, and are published for general information only. Procedures and products, suggested or discussed, should not be used without first securing competent advice respecting their suitability for any given application. Publication of the material herein is not to be construed as a warranty on the part of the American Association of State Highway and Transportation Officials (AASHTO) or the National Steel Bridge Alliance (NSBA) - or that of any person named herein - that these data and suggested practices are suitable for any general or particular use, or of freedom from infringement on any patent or patents. Further, any use of these data or suggested practices can only be made with the understanding that neither AASHTO nor NSBA makes any warranty of any kind respecting such use and the user assumes all liability arising therefrom.

Steel Bridge Erection Guide Specification

TABLE OF CONTENTS
PART ONE - SPECIFICATION
Definitions Erector Qualifications Erection Procedures Transportation Material Storage Bearings and Anchorages Assembly Field Bolted Connections Field Welded Connections Inspection Repair Appendices

PART TWO - COMMENTARY PART THREE - SAMPLE PROCEDURES & CALCULATIONS


EP-1 EP-2 EP-3 CALC-1 CALC-2 Single Span Straight Steel Girder - to be developed Multi Span Straight Steel Girder - to be developed Multi Span Horizontally Curved Steel Girder - to be developed Calculation for Girder Stability - to be developed Calculation for Temporary Support - to be developed

PART FOUR - SAMPLE CHECKLISTS


CL-1 CL-2 Erection Procedure Checklist Pre-Erection Field Checklist - to be developed

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

page i

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

page ii

Steel Bridge Erection Guide Specification

1. Definition Steel bridge erection is the process of transporting, handling and assembling steel bridge components in a safe and efficient manner to result in a bridge structure that meets all the geometric and structural requirements of the contract documents. 2. Erector Qualifications Utilize an AISC Certified Steel Erector for all bridge construction which requires any of the following: a single lift over ten (10) tons in weight, any one lift using two or more cranes/derricks/poles, spans over water or active railroad/rapid transit tracks, erection from the water on floating equipment, phased construction requiring lane closures combined with active lanes, curved girders, main member field splices. 3. Erection Procedures The Contractor shall submit a detailed erection procedure to the Owner for each bridge structural unit. Prepare the procedure under the supervision of a qualified individual, experienced in steel erection. The procedure shall address all requirements for erection of the structural steel into the final designed configuration. The procedure shall satisfy all written Owner comments prior to the start of erection. Include in the procedure, as a minimum, the following information: a) Drawings i) plan of the work area showing support structures (piers and abutments), roads, railroad tracks, waterways, overhead and underground utilities and other information relative to erection. ii) erection sequence for main members and secondary members (crossframes, diaphragms, lateral bracing, etc.) noting any temporary support conditions, such as holding crane positions, temporary supports, falsework, etc. Member shipping marks shall be the same as used on shop detail drawings. iii) bolted splice assembly requirements per Section 7 & 8

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 1

Steel Bridge Erection Guide Specification

iv) capacity chart for each crane configuration and boom length used in the work v) center of gravity locations for main members vi) detail, weight and arrangement of all rigging for main member picks vii) lifting weight of each member viii) location of each crane for each pick, showing radius, crane support (barges, mats, etc) ix) main member delivery location and orientation b) Calculations i) design calculations indicating the load capacity and stability of temporary supports for structure and crane ii) calculations to substantiate structural integrity and stability of erected girders prior to completion of bridge assembly iii) calculations to provide capacity of Contractor fabricated rigging such as lift beams, spreader beams, beam clamps, etc. Submit manufacturers' certification or catalog cuts for preengineered devices c) Coordination Items i) review/approval by other agencies as required, eg, railroads, Coast Guard, etc.

ii) follow on construction activities which occur prior to completion of steel erection, such as concrete deck pours. 4. Transportation 4.1 The Contractor is responsible for coordinating delivery from the fabricator to the jobsite and for providing adequate site access.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 2

Steel Bridge Erection Guide Specification

4.2 The Contractor is responsible to submit a shipping plan to the Owner indicating support and tiedown points for main members during transportation to the job site. Ship main members upright, unless otherwise approved by owner. Load, support, and unload main members in a manner that will not damage, excessively stress, or deform the steel, nor subject it to repeated stress reversals. 4.3 Ship fasteners in sealed, watertight containers. 5. Material Storage 5.1 Place material to be stored on blocking above the ground. Properly drain the ground and keep material clean. Store girders and beams upright and shored. Support all members to prevent damage. 5.2 Store fasteners, welding consumables, and machine finished parts inside covered structures or otherwise protected from the weather. Fasteners removed from storage should be installed by the end of the work shift. Return unused fasteners to storage at the end of the work shift. 5.3 Store and handle welding consumables in accordance with the AASHTO/AWS D1.5 Bridge Welding Code. 5.4 Report any damaged material to the Engineer. 6. Bearings and Anchorages 6.1 Document all substructure locations (lateral and longitudinal), existing anchor bolt locations, bearing seat elevations, and other pertinent information in a Contractor survey, conducted prior to start of erection. Provide the Owner with notification prior to this survey, so that he may participate. Document and report to the Owner any discrepancies between the survey findings and the Contract plans. 6.2 Place bearing devices on properly finished bridge seat bearing areas. Notify the Owner if seats are out of level or at incorrect elevations, and determine corrective actions to be taken.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 3

Steel Bridge Erection Guide Specification

6.3 When setting bearings, make corrections for ambient temperature and anticipated rotation due to dead load deflection of the member attached to the bearing. Position bearings such that the first position, including corrections for temperature and dead load rotation, is within manufacturers specification. Notify the Owner if anchor bolt locations do not permit proper positioning, and determine corrective actions to be taken. 6.4 In addition to the dimensional tolerances in AWS D1.5 for steel bearing contact areas, members shall seat on bearing devices with no final gaps exceeding 1/16. 7. Assembly 7.1 Erect and assemble all members in accordance with the procedures satisfying Section 3. The proposed crane location(s) and member delivery location(s) may require modification in the field to suit changing jobsite conditions. However, cranes and material to be lifted must be located such that the lift is safe and within the crane's certified capacity for all required positions. 7.2 Curved girders and long span straight girders shall be stabilized with falsework, temporary bracing, or holding cranes until a sufficient number of adjacent girders are erected with diaphragms and crossframes connected to provide the necessary lateral stability. 7.3 All trusses shall be erected on falsework unless approved by the Owner. When erecting trusses, the falsework shall remain in place until all connections are completed. 7.4 Falsework and temporary supports shall be detailed in a manner to insure that the temporary elevation of supported steel accommodates the deflections that will occur as the structure is completed. 7.5 Drift pins will normally be required to align holes for field splices. Field reaming will only be allowed to facilitate fit-up with the Owner's prior approval. Any abnormal distortion of the member or damage to the holes during the alignment process shall be immediately reported to the Owner.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 4

Steel Bridge Erection Guide Specification

7.6 For splice connections of main members, as well as diaphragm or cross-frame connections for curved girders; fill at least 50% of the holes with erection bolts in a snug tight condition or full size erection pins, with at least half (25% of all holes) being bolts, prior to release. Uniformly distribute the filled holes throughout the connection, except install pins at or near the corners of main member connections. Permanent bolts may be used as erection bolts, provided they are installed in accordance with Section 8.4. For complex structures (arches, trusses, etc.), fill holes in accordance with erection procedures. 7.7 Any abnormal member deformation or brace deflection after crane release shall be immediately reported to the Owner 8. Field Bolted Connections 8.1 Use bolts meeting the requirements of ASTM A325, ASTM A490, or ASTM F1852 8.2 Fully tension all bolts in the completed bridge prior to completion of steel erection, unless otherwise noted. 8.3 No loose mill scale, dirt, or other foreign material that would preclude solid seating of the parts is allowed on faying surfaces of bolted connections. 8.4 Verify bolt installation method prior to bolt installation, in accordance with Section 7 of the RCSC Bolt Specification for Structural Connections Using ASTM A325 of A490 Bolts, dated June 23, 2000 (referred hereafter as the Bolt Specification and currently available at http://www.boltcouncil.org/download RCSC Specification.htm ). Additionally, perform fastener assembly Rotational Capacity test per Appendix 1 or 1A. 8.5 Install and tighten bolts using any of the methods allowed per the Bolt Specification, paragraph 8.2. Tighten bolts to the minimum tension shown in the Bolt Specification, Table 8.1. Fully tension bolts before exposure to the elements affects their torque characteristics.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 5

Steel Bridge Erection Guide Specification

9. Field Welded Connections 9.1 Field welding and nondestructive testing shall be performed according to the current AASHTO/AWS D1.5, Bridge Welding Code or other code (s) as specified in the contract documents. Field welding is not allowed unless shown on the plans or approved by the Engineer. 9.2 All structural field welding shall be done by the Shielded Metal Arc Welding (SMAW) process. Flux Cored Arc Welding (FCAW) and Submerged Arc Welding (SAW) may also be allowed for field welding when approved by the Engineer. Gas Metal Arc Welding (GMAW) and other gas shielded welding processes are prohibited. 9.3 Qualification 9.3.a Welder Qualification. Test welders according to Section 5, Part B of AWS D1.5 in the same position required for field welding as determined by the Engineer. Field Welder qualification shall remain in effect indefinitely unless the welder is not engaged in welding for a period of three months or more, or unless there is some specific reason to question the welder's ability. 9.3.b Procedure Qualification. No field welding shall be performed until acceptable welding procedures have been written and established by test. The weld procedure tests shall be done in the same position and joint configuration required for the field welding (e.g., 3F and 4F for fillet welding and 3G and 4G for groove welding). The written welding procedures shall be qualified after testing of the welds is completed. These tests shall be according to Section 5 of AWS D1.5 or as specified in the Contract Special Provisions. Tests shall be performed on steel plate material the same type as that to be welded, with mill certification provided. 9.4 Welding Requirements

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 6

Steel Bridge Erection Guide Specification

9.4.a Make available a written copy of the approved welding procedure to the field welders. 9.4.b The contact surfaces and joints to be field welded and the surrounding area shall be blast cleaned or ground prior to welding. Loose mill scale, coatings, galvanizing, grease, oil, rust, moisture, or other contaminates shall be removed from the base metal prior to welding. Joints to be field welded shall be ground to remove pitting and irregularities. Joints to be welded shall be prepared and any foreign material removed according to Section 3 of AWS D1.5. 9.4.c The parts to be joined shall be brought into as close contact as practicable according to Section 3.3.2.1 of AWS D1.5. 9.4.d Field welding shall not be allowed when the ambient air temperature is below 0o F or during periods of precipitation unless the area to be welded is heated and housed in a manner approved by the Engineer. See Section 3.1.3 of AWS D1.5. 9.4.e Electrodes shall be purchased in hermetically sealed containers and/or dried in an oven according Section 4.5.2 of AWS D1.5. Electrodes shall be redried no more than one time. Electrodes that have been wet shall not be used. 9.4.f All surfaces to be welded shall be preheated 3 inches in all directions from the weld. Minimum preheat shall be 250o F for plate thicknesses less than or equal to 11/2 inches, 300oF for plate thickness exceeding 11/2 inches up to 21/2 inches and 350oF for plate thicknesses over 21/2 inches. Preheating methods shall not cause damage to adjacent coated surfaces, neoprene bearings and other heat sensitive components.

10. Inspection 10.1 The alignment, profile and fastening of the erected steel shall be subject to inspection by the Owner. 10.1.a Tolerances 10.1.a.1 Deviation from theoretical horizontal alignment shall not exceed the following:
Draft - April 9, 2004 AASHTO/NSBA Steel Bridge Collaboration Page 7

Steel Bridge Erection Guide Specification

+- 1/8 inch x (total length, in feet, between supports)/10 Deviation shall be measured at the top and bottom flanges, with the larger deviation being the control. If the top and bottom flanges are on opposite sides of the theoretical horizontal alignment, the total deviation (top flange plus bottom flange) shall not exceed the value computed above. Theoretical horizontal alignment is to be provided by the Engineer and calculated under steel dead load conditions only. 10.1.a.2 Deviation from theoretical erected web position +- 3/32 inch x (web depth, in feet) Deviation is the horizontal displacement between the top and bottom of the web. Required theoretical erected web position is to be provided by the Engineer and calculated under steel dead load conditions only. 10.1.a.3 Deviation from theoretical vertical alignment - 0, + 1/4 inch x (total length, in feet, from nearest support)/10 Deviation shall not exceed 3 /4 in cantilever sections or 1 1/2 between supports. Theoretical vertical alignment is to be provided by the Engineer and calculated under steel dead load conditions only. 10.2 It is the Contractors responsibility to survey steel profile and alignment during and after completion of steel erection, with verification by the Owner. 10.3 Bolt tension shall conform to the requirements of the Bolt Specification. 10.4 Visual inspection and nondestructive testing shall be performed on 100 percent of all field welds. Welds shall be accepted according to Section 3.6 and 6.26 of AWS D1.5. 10.4.a Welds shall be free of rust, scale, coatings, and other foreign material prior to conducting nondestructive testing (NDT). NDT shall include liquid dye penetrant (PT), magnetic particle testing (MT), ultrasonic testing (UT) or radiograph testing (RT). Liquid dye penetrant or magnetic particle testing shall be used for all fillet and partial penetration butt

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 8

Steel Bridge Erection Guide Specification

welds. Ultrasonic testing or radiograph testing shall be used for all complete penetration butt welds, plug welds and slot welds.

10.4.b Nondestructive testing methods shall be according to AWS D1.5. The Engineer shall
determine the frequency, location and type of NDT performed by the Contractor prior to accepting the work. Personnel qualified as NDT Level II or Level III according to the American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNTTC-1A shall perform all tests. The NDT personnel shall provide proper certifications to the Engineer prior to doing the work. The Engineer shall witness all nondestructive testing. Welds that are cracked or determined to be unacceptable by the Engineer shall be rejected and repaired at the Contractor's expense. 10.5 Inspect and test repaired welds in accordance with Section10.

11. Repair 11.1 The Contractor is responsible for documenting damage and proposing the method of repair and submitting same to Owner. 11.2 Correct misaligned steel so that alignment tolerances specified in the Contract Documents are achieved. The Contractor is responsible for proposing the method of realignment and submitting same to Owner for approval. 11.3 Submit repair procedures for damaged or misaligned steel in the form of sketches and/or written procedures as applicable. Submit information in sufficient detail for the Owner to adequately review the repair application. 11.4 Repair welds in accordance with Section 3.7 of AWS D1.5.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 9

Steel Bridge Erection Guide Specification

Appendix 1 ROTATIONAL CAPACITY TEST (Long Bolts in Tension Calibrator)


per FHWA Report No. FHWA-SA-91-031, dated May 1991, Appendix A1 Procedure for Performing Rotational Capacity Test, Long Bolts in Tension Calibrator EQUIPMENT REQUIRED: 1. Calibrated bolt tension measuring device of size required for bolts to be tested. Mark off a vertical line and line 1/3 of a turn, 120 degrees; and 2/3 of a turn, 240 degrees, from vertical in a clockwise direction on the face plate of the calibrator. 2. Calibrated torque wrench. 3. Spacers and/or washers with hole size no larger than 1/16 in. greater than bolt to be tested. 4. Steel section to mount calibrator. Flange of girder or cross frame accessible from the ground is satisfactory. PROCEDURE: 1. Install nut on bolt and measure stick out of bolt when 3 to 5 full threads of the bolt are located between the bearing face of the nut and bolt head. Measure the bolt length, the distance from the end of the threaded shank to the underside of the bolt head. 2. Install the bolt into the tension calibrator and install the required number of shim plates and/or washer (one washer under the nut must always be used) to produce the thread stickout measure in Step 1. 3. Tighten bolt using a hand wrench to the snug tensions listed below 0 kips, +2 kips
Bolt Dia. (in.) Snug Tension (kips)

1/2 1

5/8 2

3/4 3

7/8 4

1 5

1-1/8 6

1-1/4 7

1-3/8 9

1-1/2 10

4. Match mark the nut to the vertical stripe on the face plate of the bolt calibrator. 5. Using the calibrated manual torque wrench, tighten the bolt to at least the tension listed below and record the torque required to reach the tension and the value of the bolt tension. Torque must be measured with the nut in motion.
Bolt Dia. (in.) Tension (kips)

1/2 12

5/8 19

3/4 28

7/8 39

1 51

1-1/8 56

1-1/4 71

1-3/8 85

1-1/2 103

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 10

Steel Bridge Erection Guide Specification

6. Further tighten the bolt to the rotation listed below. The rotation is measured from the initial marking in Step 4. Record the bolt tension. Assemblies which fail prior to this rotation either by stripping or fracture fail the test. Bolt Length (measured in Step 1) Required Rotation 4 x bolt dia. or less 2/3 Greater than 4 but no more than 8 x bolt dia. 1 Greater than 8 x bolt dia. 1-1/3

7. The bolt tension measured in Step 6 after the required rotation must equal or exceed the values in the table shown below. Assemblies which do not meet this tension have failed the test.
Bolt Dia. (in.) Tension (kips)

1/2 14

5/8 22

3/4 32

7/8 45

1 59

1-1/8 64

1-1/4 82

1-3/8 98

1-1/2 118

8. Loosen and remove nut, and examine the threads on the nut and bolt. No signs of thread shear failure, stripping, or torsional failure of the bolt should be evident. Assemblies which have evidence of stripping have failed the test. 9. Calculate and record the value of 0.25x the tension (pounds = kips x 1000) measured in Step 5 x the bolt diameter in feet. The torque measured and recorded in Step 5 must be equal to or less than this calculated value. Assemblies with torque values exceeding this calculated value failed the test.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 11

Steel Bridge Erection Guide Specification

Appendix 1A ROTATIONAL CAPACITY TEST (Bolts Too Short to Fit In Tension Calibrator)
per FHWA Report No. FHWA-SA-91-031, dated May 1991, Appendix A1 Procedure for Performing Rotational Capacity Test, Bolts Too Short to Fit Tension Calibrator EQUIPMENT REQUIRED: 1. Calibrated torque wrench and a spud wrench or equivalent 2. Spacers and/or washers with hole size no larger than 1/16 in. greater than bolt to be tested. 3. Steel section with normal size hole to install bolt. Any available splice hole can be used with a plate thickness that will provide the number of threads under the nut required in Step 1 below. Mark off a vertical hole and lines 1/3 of a turn, 120 degrees; 1/2 of a turn, 180 degrees; and 2/3 of a turn, 240 degrees, from vertical in a clockwise direction on the plate. PROCEDURE: 1. Install nut on bolt and measure stick out of bolt when 3 to 5 full threads of the bolt are located between the bearing face of the nut and bolt head. Measure the bolt length, the distance from the end of the threaded shank to the underside of the bolt head. 2. Install the bolt into the hole and install the required number of shim plates and/or washer (one washer under the nut must always be used) to produce the thread stickout measure in Step 1. 3. Snug the bolt using a hand wrench. The snug condition should be the normal effort applied to a 12 inch long wrench. The applies torque should not exceed 20% of the torque determined in Step 5. 4. Match mark the nut to the vertical stripe on the plate. 5. Tighten the bolt by turning the nut using the torque wrench to the rotation listed below. A second wrench must be used to prevent rotation of the bolt head during tightening. Record the torque to reach this rotation. Torque must be measured with the nut in motion. Bolt Length (measured in Step 1) Required Rotation 4 x bolt dia. or less 1/3 Greater than 4 but no more than 8 x bolt dia. 1/2 Greater than 8 x bolt dia. 2/3

The measured torque should not exceed the values listed below. Assemblies which exceed the listed torque have failed the test.
Bolt Dia. (in.) Torque (ft-lbs)

1/2 150

5/8 290

3/4 500

7/8 820

1 1230

1-1/8 1500

1-1/4 1500

1-3/8 2810

1-1/2 3690

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 12

Steel Bridge Erection Guide Specification

6. Tighten the bolt further to the rotation listed below. The rotation is measured from the initial marking in Step 4. Assemblies which fail prior to this rotation either by stripping or fracture fail the test. Bolt Length (measured in Step 1) Required Rotation 4 x bolt dia. or less 2/3 Greater than 4 but no more than 8 x bolt dia. 1 Greater than 8 x bolt dia. 1-1/3

7. Loosen and remove nut, and examine the threads on the nut and bolt. No signs of thread shear failure, stripping, or torsional failure of the bolt should be evident. Assemblies which have evidence of stripping have failed the test.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 13

Steel Bridge Erection Guide Specification

COMMENTARY
3. A qualified individual is one who, by possession of a recognized degree, certificate of professional standing, or who by extensive knowledge, training and experience, has successfully demonstrated the ability to solve or resolve problems related to steel bridge erection. The Owner may require that the individual preparing the erection procedure be a licensed Professional Engineer. Complex structures (tied arch, moveable truss) should have specific erection requirements noted in the Contract. The erection procedure should be submitted as soon as possible after contract award. The erector is encouraged to attend a prebid and preconstruction meeting. Projects that involve complex erection or multi-agency review can be expected to require additional time for review of submitted erection procedure. 3.a.i Other parameters may also need to be shown on the plan of the work area, such as Right of Way. 3.a.viii For operations on navigable waterways, the configuration of the barge(s), loading sequence, stability provisions (tie downs, piles, etc) and calculations, safety measures (emergency boat, notification plans), coordination plan for regulatory agencies and other water traffic, and the details and anticipated schedules of obstructing the navigable channel should be required. 3.b Design criteria to be established or approved by the Owner. 3.b.ii Complex erection projects may require input from the structural designer in addition to the original design calculations such that the contractor can confirm constructability of the structure during various erection stages. The Owner should ensure that the structural designer is available to consult with the Contractor in these cases. 3.c The Contractor should coordinate activities with the Owner/Engineer, Fabricator, and Erector. Special coordination requirements may be included in the Contract. Examples would be Corp of Engineers,

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 14

Steel Bridge Erection Guide Specification

Railroads, Coast Guard, maintenance and protection of traffic control, school bus routes, and emergency vehicle routes. 4.2 Care should be exercised to avoid coatings damage from slings, chokers, clamps, etc. Also, limiting the length of members overhanging the rear wheels of a trailer may reduce the range of stress reversals and potential damage from ground strikes. 6.1 Bearing seat elevations must allow for sufficient clearance under bearings for proper installation of grouting 7. Jobsite conditions vary on a daily basis and are often not as they were anticipated to be when the erection procedure was conceived and submitted to the owner. Consequently, the need to deviate from the submitted erection procedure may arise during the course of a bridge project. It is the Contractors responsibility to erect the steel in a safe and efficient manner. The Owner's review and disposition of erection procedure changes to suit jobsite conditions should be handled in an expeditious fashion and avoid delaying the work. 7.5 Examples of an abnormal hole would be one that is non-cylindrical, not perpendicular to the faying surface, or out of round by more than 1/16". 8.4 It is required that connections be brought to the snug condition prior to fully tensioning bolts. It may be difficult to achieve the snug tight condition for large main member connections, which utilize many bolts and/or plies of thick material. The engineer may require a minimum of ten percent of each connection be filled with fully tensioned temporary bolts prior to installing permanent bolts. Permanent bolts can then be installed in the remaining holes in accordance with the Bolt Specification. Finally, remove the temporary bolts and install permanent bolts at each location of temporary bolts. 9.1 Specific parts of AWS D1.5 have been referenced in this section as opposed to the entire code. AWS D1.5 was written mostly for the use of shop fabricating structural steel members. Field welding
Draft - April 9, 2004 Page 15

AASHTO/NSBA Steel Bridge Collaboration

Steel Bridge Erection Guide Specification

structural steel members presents environmental and geometric conditions that exceed those in the shop. Rain, humidity, and wind are examples of conditions that can not be controlled in the field but can be controlled in the shop. Difficultly in steel fit-up, access to the joint by the welder and welding position are geometric constraints that can adversely affect the quality of the weld. The owner must specify in the contract documents what welding code is to be used. Codes other than AWS D1.5 will not have the same referred sections as that of AWS D1.5 and sections specified herein. The owner must coordinate code sections other than AWS D1.5 with sections in these documents. 9.2 It is recommended that E7018 or E7016 electrodes be used for field welding. These are low hydrogen electrodes and produce good quality welds when stored according to Section 4.5.2 of AWS D1.5. Flux Core Arc Welding (FCAW) may be used without gas shielding. Submerged Arc Welding (SAW) can be used providing it is used exclusively for welding butt welds in the flat position and fillet welding in the flat and horizontal position. When wind speeds exceed 20 mph, the granular flux required for SAW may blow away if precautions are not taken to block strong winds. Welding with gas shielding processes have been prohibited because of potential loss of shielding gases by drafts from nearby moving objects or when wind speeds exceed 5 mph. 9.3 Unlike shop welding, workers welding in the field for contractors move from project to project and keeping track of welders that are qualified can be difficult. It is recommend that field welders be qualified according to Section 5 of AWS D1.5 in the position, using the process, and material (grade of steel) to be used in the production welding. It is also recommended that field welders qualify indefinitely unless the welder is not engaged in welding for a period of three months, or unless there is some reason to question the welders ability. Many times field welders are labors, iron workers, carpenters, machinist, foremen, etc. These contractor employees will move from project to project and from company to company. Keeping track of who is qualified and who is not can be a difficult task. Therefore, it is recommended that an inventory of qualified field welders be kept so that project personnel can keep track of which contractor personnel are qualified to do field welding. Therefore, a
Draft - April 9, 2004 Page 16

AASHTO/NSBA Steel Bridge Collaboration

Steel Bridge Erection Guide Specification

work record or database of qualified field welders should be maintained by the owner. A frequency as short as two years between each qualification test for each welder may be used if tracking of both welders (project to project and company to company moves) and proper documentation of qualified welders becomes clumsy or difficult to maintain. 9.3.b Parameters (amperage, volts, travel speed, etc.) used by the welder for qualification and/or joint configuration mock-up (if necessary) should be used to write the Welding Procedure Specification (WPS). AWS D1.5, Annex III-2 Sample Welding Procedure Specification form can be used to write the WPS. 9.4.c When the ambient air temperature is below 0o F or during periods of precipitation when environmental conditions meet the requirements of Section 3.1.3 of AWS D1.5 and/or the welders ability to make sound welds are a concern, heating and housing should be used. See AWS D1.5 Commentary C3.1.3 for a detail explanation of cause and effect of weld quality due to ambient air temperature, moisture or precipitation, and wind speed. 9.4.d It is required that electrodes be keep dry at all times. Electrodes will absorb moisture if not properly stored according to the requirements of AWS D1.5. If electrodes are not stored according to the requirements of AWS D1.5 they will absorb moisture and produce poor quality welds during production welding. Electrode drying ovens should be at the project site located near the welders work station at all times. Once the electrode container is opened, electrodes should be place in the ovens and stored at temperatures according to AWS D1.5. 9.4.e Preheating the weld joint just prior to welding is extremely important in the field to achieve high quality welds. NCHRP Report 321 provides recommended preheats for field welding applications. These are the preheats used in most field welding applications. These elevated preheats (as compared to those required for shop welding) provide the following advantages for good sound weld quality: dries out the surface removing moisture, expands the base metal reducing residual stresses, diffuses
Draft - April 9, 2004 Page 17

AASHTO/NSBA Steel Bridge Collaboration

Steel Bridge Erection Guide Specification

hydrogen preventing cracking in the weld metal, slows the cooling rate, and permits gases to escape preventing porosity. 10.1.a.2 The location the measurement for deviation from theoretical web position will vary depending on bridge type. For straight or skewed girders, measure adjacent to bearing stiffeners. For curved girders, measure adjacent to bearing stiffeners and also at midspan. For other bridge types, measurement locations are to be provided by the Engineer. 10.1.a.3 Tolerance in the negative direction, i.e. vertical alignment lower than theoretical, has not been permitted to ensure that the distance between top of flange and top of deck can be maintained, thereby avoiding thickening the haunch (or deck) to suit. Installed location lower than theoretical may be acceptable upon review by the Engineer. For a typical girder bridge, some agencies may choose to control only the elevation of the girder splices and accept vertical alignment between splices (within the tolerance on shop camber). Also note, some of the tolerance on vertical alignment may be 'consumed' by the tolerance on shop camber of the fabricated girder. 10.4 All field welding should be inspected visually by a Certified Welding Inspector (CWI). In addition, field welds should be evaluated non-destructively by personnel qualified as NDT Level II or III according to the American Society for Nondestructive Testing (ASNT), Recommended Practice No. SNT-TC-1A. The NDT personnel should provide proper certifications to the Engineer prior to doing the work. Welds should be cleaned prior to conducting nondestructive testing (NDT). The Engineer should determine the frequency, location and type of NDT performed by the Contractor prior to accepting the work. NDT includes liquid dye penetrant (PT), magnetic particle testing (MT), ultrasonic testing (UT) or radiograph testing (RT). PT or MT is used for fillet and partial penetration butt welds. UT or RT is used for complete penetration welds, plug welds and slot welds.

Draft - April 9, 2004

AASHTO/NSBA Steel Bridge Collaboration

Page 18

AASHTO / NSBA STEEL BRIDGE COLLABORATION

ERECTION PROCEDURE CHECKLIST


PART 1 ERECTION PROCEDURE DRAWING
PLAN:
To scale plan of work area showing supporting structures, roads, railroads, waterways, overhead & underground utilities, adjacent structures, etc.; and framing plan with member shipping marks <match those used on shop drawings> and indicate field splice locations if applicable Location of temporary supports, falsework, holding cranes Location of crane positions on plan showing pick radii Elevation view of crane and member Crane Support Method: barges, mats Member delivery location and orientation Included Included Not Applicable Not Applicable

DETAILS:

Detail and arrangement of member rigging: show sizes, capacities, and location of center of gravity of each pick Falsework and temporary support details: show sizes and capacities Crane capacity chart indicating crane type, lifting capacity at given radius and orientation, counterweight requirements, and boom length Pick weight chart indicating weight of member, plus rigging and any attachments Written procedure indicating erection sequence for main and secondary members (crossframes, diaphragms, lateral bracing, etc.), including the following: method of tie down of individual pieces, time and method of connections of diaphragms and lateral bracing and field splices;

PART 2 CALCULATIONS
Calculations for load capacity and stability of temporary supports for structure: falsework, tie downs, lifting beams, spreader beams, etc. Calculations indicating capacity of temporary crane supports: Included Not Applicable

Calculations to substantiate structural integrity and stability of members prior to completion of bridge assembly Calculations indicating structural integrity of any partially bolted main splice after release of external support system Calculations to substantiate structural integrity of abutments and retaining walls affected by surcharge from crane

PART 3 ASSOCIATED DATA


Manufacturers cut sheets for rigging devices: beam clamps, slings, wire rope, shackles, turnbuckles, chains, straps, etc., and pre-engineered falsework, if applicable Statement as to status of coordination with parallel entities requiring review: railroads, Coast Guard, Corps. Of Engineers, etc. PROJECT DESCRIPTION __________________________________________________________________________ COMPLETED BY _________________________________________________________________________________ <ERECTOR COMPANY NAME> <QUALIFIED INDIVIDUAL NAME>