You are on page 1of 2

MINE OF THE MONTH – LIHIR, PAPUA NEW GUINEA

The Papua
performer
Despite a production setback in late 2005, Papua New
Guinea’s Lihir Gold is going from strength to strength
after separation from long-term partner, Rio Tinto

F
OLLOWING its final break from Rio Tinto had been gradually winding down in the few years pipe rupture meant that processing had to be
last November, the remote Lihir Island gold before the move. suspended for a month, and, ultimately, cost about
mine in Papua New Guinea off New Ireland At the time of the sale, Rio Tinto’s chief executive, 100,000 oz of production for the year, which stood at
has ramped up to record production levels, Leigh Clifford, said: “Rio Tinto generally does not hold 596,000 oz. Lihir had originally aimed for a 2005 figure
with a March-quarter production figure of long-term minority positions in other listed compa- of 700,000 oz.
184,000 oz, leaving owner Lihir Gold Ltd on track for nies. Following our relinquishment of management
a full-year record total of 670,000 oz. This figure is set rights announced on September 16, 2005, we have PROCESSING
to increase further to over 800,000 oz next year after taken advantage of the current favourable market Run-of-mine stockpiling and primary crushing
the addition of a flotation circuit. conditions to sell our holding in Lihir.” facilities, incorporating a gyratory crusher, are in the
Speaking at the company’s annual general meet- Lihir Gold told Mining Magazine: “It is a major step Ladolam Creek area, about 500 m east of the orebod-
ing in Port Moresby on April 24, managing director in the development in the company. In the past, Lihir ies. The main processing plant lies in an area known
Arthur Hood said of the figures: “Mining performance was run essentially as a semi-autonomous operat- as Putput, at the mouth of Luise Harbour.
has improved markedly, costs remain under control ing division of Rio Tinto. The CEO was based on the Lihir ore is refractory, meaning that conventional
and good progress has been made in development island, and was very operationally focused, as a mine extraction of gold by cyanidation is not viable without
projects … this is the fifth-best quarterly production manager might be in a multi-mine company like Rio pre-treatment. The Lihir process plant incorporates
achieved at Lihir since mining commenced in 1996.” … we are now transforming into a mature corporate a pressure oxidation pre-treatment step using auto-
On the back of rising gold prices, revenues for the identity, with a management team singularly focused claves to release the gold. This, in turn, is followed by
March quarter topped US$100 million for the first on the growth and profitability of this company.” conventional cyanidation.
time, while operating cashflow for the three months Lihir sees the sale as having marked the transition The plant’s facilities first crush the ore and convert
reached US$46 million. One of Lihir’s main strengths from a long period of development, during which it into a slurry suitable for pressure oxidation. A small
is the size of its reserves, which stood at over 20 Moz time the very large, but also geologically- and techni- flotation plant is sometimes used to concentrate
at the end of 2005, from a resource of about 40 Moz. cally-challenging orebody, entered a new era of ex- a portion of the slurry as required. The ore is then
panded production and reduced costs. The markets subjected to pressure oxidation, counter-current
GOING IT ALONE have recognised Lihir’s future potential: the company decantation (CCD), neutralisation, carbon-in-leach
The separation from Rio Tinto represented a major stock value increased by 88% last year, making Lihir (CIL) and tailings disposal. Gold is recovered from
milestone for Lihir, reflecting the fact that it had Gold one of last year’s ten best-performing stocks in the CIL process through carbon stripping, electro-
matured into a US$1.5 billion company, with a the ASX 200. winning and smelting.
well-established operation and sound financial It has not all been plain sailing. The improved The processing plant was initially designed to
base. Mr Hood described Lihir in 2005 as being production figures for early 2006 come after a major treat 375 t/h of ore at a design sulphur grade of
“big enough and strong enough to stand on its setback for the mine on October 9, 2005, when a 7.2%. A design autoclave operating time of 89% of
own two feet”. landslide on a hillside north of the mine killed two total time was used resulting in a plant capacity of
From 1995, when the mine opened, until the workers, ruptured the water supply to the process- 2.9 Mt/y. The processing plant was upgraded in 1999
decision to sell its 14.46% shareholding in late 2005, ing plant, and cut off an access road from the main to include a second oxygen plant and a small flotation
Rio Tinto had managed Lihir Gold, but its influence worker township of Londolovit and the mine. The plant. Three autoclave heat recovery vessels, used

O&K RH 200 hydraulic excavators


loading Caterpillar 785 trucks at Lihir
Photo: Lihir Gold

12 Mining Magazine August 2006

12-13MM0608.indd 12 26/7/06 17:41:58


to pre-heat autoclave feed were installed in 2001 NEW GUINEA GOLD MINES* (NEW GUINEA ISLAND IS DIVIDED BETWEEN PAPUA NEW GUINEA
along with a 12th power generator. In 2002, a pebble AND IRIAN JAYA OR WEST PAPUA, PART OF INDONESIA)
crushing circuit was installed in the grinding area to Operation Type Location Operator 2005 attributable Year production
raise grinding capacity, and three extra autoclave feed (% share) gold production (oz) began
pumps were installed in 2003. In 2004, a new carbon Kainantu U/G Eastern Highlands Highlands Pacific 115,000 (expected 2006 2005
regeneration kiln was installed to increase gold Province, PNG Ltd (95%) figure, production began
recovery from the CIL circuit. December quarter 2005)
Lihir O/P Lihir island, off Lihir Gold Ltd 596,000 1997
NEW HORIZONS New Ireland, PNG
A new flotation circuit, under construction for about Ok Tedi O/P Mount Fubilan, Ok Tedi Mining Ltd 574,694 1984
US$162 million, is due for commissioning in the Western Province,
March quarter of 2007. This will increase the capacity PNG
of the plant to over 800,000 oz/y, although the Porgera U/G Enga Province, Placer Dome/ 635,348 1990
company regards a production rate of 1 Mt/y as an and O/P PNG Barrick (75%)
achievable medium-term target: a goal which is seen Tolukuma U/G Goilala District, Emperor Mines Ltd 68,370 1990
as likely to be “well advanced” by the end of 2008. and O/P Central Province,
Aver Kvaerner has been selected as the engineer- PNG
ing, procurement, construction and management Grasberg O/P Irian Jaya Freeport McMoran 2,789,400 1988
(EPCM) contractor for the flotation plant project, (Indonesia) Copper and Gold
which incorporates Outokumpu cells and the Outo- (60%)
kumpu FrothMaster, which is the first instrument and *Operations do not include Indonesia, with the exception of Grasberg

control package that converts froth image analysis to


useful plant measurements and controls, enhancing original, now largely-depleted Minifie pit, where min-
the performance of flotation cells. Outokumpu also ing began in 1997, to the new Lienetz pit was also
supplied new ball and SAG mills for a processing completed in 2005. Lienetz is a rich orebody, deeper
plant upgrade that was completed in the March than Minifie, but higher in grade. It will be the main
quarter of this year. source of ore for many years. Mining
The expansion should have a
major impact on the overall “One of the in Lienetz is due to continue until
2015, when the focus will shift to a
economics of the operation,
because the additional operating
main cost third pit: Kapit.
Overall mining in 2005 totalled
costs associated with the circuit are factors at Lihir about 42 Mt of ore, which was well mine, but also the whole island.
relatively low. Work began on the
bulk earthworks for the mill and
was petroleum- below the stated target of 54 Mt,
partly due to the landslide, which
This has since been ramped up by adding a 20 MW
power plant commissioned in July 2005. Capacity
flotation areas in the March quarter derived power in reduced productivity by requir- is now being expanded from 36 MW to 56 MW, due
and installation of the water supply
pipeline and the critical tie-ins to the face of rising ing employees to be moved into
and out of the mine by boat. The
for completion before the end of the year. Steelwork
for the powerhouse building is 80% complete and
the existing plant were completed
during a maintenance shutdown.
oil prices” availability of equipment availability
also had a major impact. A total of
concrete foundations for the cooling tower in place.

3.5 Mt of high-grade ore was mined THE TAILINGS ISSUE


FLEET ADDITIONS in the year, down from 5 Mt in 2004, due to the stage Lihir Gold uses submarine tailings disposal, and is
In terms of mining equipment, there have been of development of the pits. Some 5.9 Mt of economic now the region’s only mine to use this method, after
additions on an annual basis, with five new trucks grade ore was mined, down from 6.6 Mt in the prior the closure of Placer Dome’s Misima mine in 2004.
and one new shovel added in both 2005 and 2006. year. The company said it was disappointed with the Treated neutralised tailings are released by
Two O&K shovels were also added during this period. total mining cash cost for the year (US$234/t). How- pipeline at a depth of 128 m, below the surface zones
The overall equipment tally at Lihir is now impressive: ever, this is expected to fall for the full 2006 year, with which are most ecologically active, and then settle
79 mining units in total, consisting of five RH200 higher productivity and improved availabilities. some 2 km below sea level. The company says it does
O&K shovels, 34 Caterpillar 785 haul trucks (both C Ore grades improved steadily over the full year not undertake any riverine tailings disposal. A Lihir
and earlier models), six drill rigs, five barges and five as the richer segments of the Lienetz orebody were representative told Mining Magazine: “This process
Caterpillar 777D haul trucks along with graders, doz- reached. For the year, the gold grade was 5.98 g/t, is very carefully managed to ensure that the impact
ers and excavators. Two more Caterpillar 785s are set and reached a record 8.54 g/t in the December on the environment is minimised. In an area like Lihir,
to be bought next year. quarter. In addition, a new US$5 million gravity where there is some residual geothermal activity,
The transition of mining operations from the circuit supplied by Australia’s ConSep Pty Ltd was and where flat, arable land is a scarce resource, land-
commissioned in September 2005 to capture free based tailings dams are simply not an option. We
gold being encountered in the Lienetz ore. This have very strict controls in place and we constantly
should lead to improved recoveries in future. The measure the impacts on sea-life.”
circuit utilises two KC-XD-48 Knelson concentrators, The idea is that the tailings continue to descend
while the concentrates are treated with a ConSep rapidly beyond the pipeline. Waste rock is discarded
CS3000 intensive cyanidation fluidised bed reactor. by barges in designated disposal zones that are
100 m-plus deep. These zones lie above steep sub-
GOING GEOTHERMAL marine canyons, down which the rock descends. The
One of the main cost factors at Lihir was petroleum- waste rock mixes with the tailings and settles on the
derived power in the face of rising oil prices. In April ocean floor.
2003, the company started to address this by com- The counter-argument is that many species of fish
missioning a 6 MW geothermal power station: the descend to these depths to feed anyway, and that
first in Papua New Guinea to use natural geothermal the ocean ends up with a blanket of waste rock that
energy for generating electricity, not only for the smothers it and forces marine life to move elsewhere.

August 2006 Mining Magazine 13

12-13MM0608.indd 13 26/7/06 17:42:00

You might also like