You are on page 1of 76

The Chief Estimator Software

Process Plant Bill of Quantities

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

10000

Description

Unit

Process Plant Direct Costs


Civil Work
Site Investigation
Soil Investigation,Boring
Monitoring Well, Depth=3.3m, with Cap & Post , Dia=150mm

Nos

10020

228,270.00

1.00

228,270.00

228,270.00

30.00

8,120.00

243,600.00

931.00

180.00

167,580.00

931.00

441.65

411,180.00

m3

3,000.00

95.00

285,000.00

m3

44,500.00

55.00

2,447,500.00

m3

3,000.00

11.00

33,000.00

m3

3,000.00

220.00

660,000.00

Sub Total Earthworks: m3

47,500.00

72.12

3,425,500.00

m3

14,697.00

42.00

617,274.00

m3

10,724.00

54.00

579,096.00

Piliing Works
Pile Driving, Sheet Pile, W 400 x W 400, 75 x 8t x 12m (with
waling and horizontal struts)
Pile Head Treatment,Misc. Special Piles,Bored-and-CIPwith_Casing
Dia=600mm

10050

Earthworks
Excavation,Normal Soil,Back Hoe
ncluding surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

10060

Crushed Stone Spreading with compaction,Machine

10040

Amount

76,090.00

m
Nos

Sub Total Piliing Works: ea

10030

Rate

3.00

Sub Total Site Investigation: LS

10010

Quantity

10090

Sewer/Drainage
Exavation & Backfill
Excavation,Normal Soil,Back Hoe
ncluding surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

2,055.68

11.00

22,612.48

10100

Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3

1,919.25

86.00

165,055.50

10110

Excavation,Normal Soil,Back Hoe


ncluding surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

14,676.09

65.00

953,945.85

m3

9,491.44

54.00

512,537.76

m3

4,635.13

11.00

50,986.43

10140

Crushed Stone Back-filling and Compaction,Machine,T=15cm m3


( Compacted )

41.00

86.00

3,526.00

10150

Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3

551.40

110.00

60,654.00

10160

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density

m3

2,030.51

66.00

134,013.66

m3

1,001.01

54.00

54,054.54

10070

10080

10120
10130

10170

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

10180

Disposal,Machine,0-10km ( Distance )

m3

1,029.50

11.00

11,324.50

10190

m3

4,138.13

97.00

401,398.61

m3

3,294.11

54.00

177,881.94

10210

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

845.98

11.00

9,305.78

10220

Crushed Stone Spreading with compaction,Machine

m3

14.00

86.00

1,204.00

Sub Total Exavation & Backfill: LS

1.00

3,754,871.05

3,754,871.05

10200

10230

Drainage & Sewer Pipe


Pipe Installation,Laying Hume Pipe,Socket Type,DIA 300

30.00

88.00

2,640.00

10240

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 400

50.00

120.00

6,000.00

10250

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 500

10.00

150.00

1,500.00

10260

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 700

10.00

210.00

2,100.00

10270

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 800

100.00

230.00

23,000.00

10280

Pipe Installation,Laying Hume Pipe,Socket Type,DIA 900

30.00

260.00

7,800.00

10290

Pipe Installation,PVC Pipe


dia.=150, for sanitary sewer, UPVC Class V 3inch Piping,
Flexible Coupling 41ea

100.00

86.00

8,600.00

Sub Total Drainage & Sewer Pipe: m

330.00

156.48

51,640.00

m2

10,273.38

81.00

832,143.78

m2

789.59

81.00

63,956.79

m2

3,525.08

81.00

285,531.48

Sub Total Formwork: m2

14,588.05

81.00

1,181,632.05

m3

2,202.19

610.00

1,343,335.90

m3

156.96

440.00

69,062.40

m3

754.64

610.00

460,330.40

10300
10310
10320

10330

10340

10350

Drainage Structures
Cast in Place Concrete Culverts
Formwork
Forming Work,Ply Wood,3 Times
- Structure 1
Forming Work,Ply Wood,3 Times
- Structure 2
Forming Work,Ply Wood,3 Times
- Structure 3

Concrete
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10360

10370

10380

10390

10400

10410

10420

10430

10440

10450

Description

Unit

Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm


Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45

Quantity

Rate

Amount

m3

26.40

440.00

11,616.00

m3

470.83

610.00

287,206.30

m3

25.53

440.00

11,233.20

Sub Total Concrete: m3

3,636.55

600.23

2,182,784.20

ton

32.30

6,770.00

218,671.00

ton

150.14

6,770.00

1,016,447.80

ton

15.14

6,770.00

102,497.80

ton

53.33

6,770.00

361,044.10

ton

0.38

6,770.00

2,572.60

ton

42.53

6,770.00

287,928.10

Sub Total Reinforcing Steel: ton

293.82

6,770.00

1,989,161.40

m2

2,300.00

62.00

142,600.00

Sub Total Wiremesh: LS

1.00

142,600.00

142,600.00

3,344.80

37.00

123,757.60

Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm

Wiremesh
Wire Mesh,F6x150x150
Epoxy Coated

10460

Concrete Accessories
Water Stop,B=200

10470

Mortar Grouting,Non Shrinkage

m3

3.60

7,040.00

25,351.04

10480

Mortar Grouting,Epoxy Grout,Water Proofing

m3

17.02

24,430.00

415,798.60

Sub Total Concrete Accessories: LS

1.00

564,907.24

564,907.24

Sub Total Cast in Place Concrete Culverts: m3

3,637.00

1,666.51

6,061,084.89

Structural Steel

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10490
10500
10510
10520
10530

10540
10550
10560
10570

10580
10590

10600
10610

10620
10630

10640
10650

10660

10670
10680
10690
10700

Description
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Insert Plate,Steel
with HDG
Steel Item 1,Misc.Steel Fabrication,Steel
with HDG
Steel Item 2,Misc.Steel Fabrication,Steel
with HDG
Steel Item 3,Misc.Steel Fabrication,Steel
with HDG

Unit

Quantity

Rate

Amount

ton

5.60

13,310.00

74,536.00

ton

24.13

13,310.00

321,170.30

ton

7.01

13,310.00

93,303.10

ton

0.02

13,310.00

266.20

ton

12.09

13,310.00

160,917.90

Sub Total Structural Steel: ton

48.85

13,310.00

650,193.50

m2

694.00

450.00

312,300.00

m2

59.00

820.00

48,380.00

m2

55.28

450.00

24,876.00

m2

700.00

820.00

574,000.00

Sub Total Steel Gratings: m2

1,508.28

636.19

959,556.00

Nos

109.00

1,690.00

184,210.00

EA

294.00

19.00

5,586.00

Sub Total Manhole Accessories: LS

1.00

189,796.00

189,796.00

m2

806.40

55.00

44,352.00

m2

10,595.00

55.00

582,725.00

m2

5,400.25

4.86

26,245.22

m2

2,337.50

53.00

123,887.50

m2

466.00

4.86

2,264.76

m2

514.00

55.00

28,270.00

m2

30.00

130.00

3,900.00

m2

30.00

54.00

1,620.00

m2

1,796.49

54.00

97,010.46

m2

555.52

4.65

2,583.17

m2

1,449.77

52.00

75,388.04

Steel Gratings
Grating,I-32
with HDG
Grating,I-50
with HDG
Grating,I-32
with HDG
Grating,I-50
with HDG

Manhole Accessories
Man Hole,Cover
Cast Iron Cover,D=600,Heavy Duty with Lock
Pipe Sleeve,Sleeeve Pipe,Installation Only

Waterproofinjg
Proofing,Epoxy Waterproofing
Coal Tar Epoxy Coating, THK=1000 Microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing
Coal Tar Epoxy Coating, THK=1000 Microns
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

Sub Total Waterproofinjg: LS

1.00

988,246.14

988,246.14

Sub Total Drainage Structures: LS

1.00

8,848,876.53

8,848,876.53

Sub Total Sewer/Drainage: LS

1.00

12,655,387.58

12,655,387.58

m3

4,300.00

40.00

172,000.00

m3

4,300.00

11.00

47,300.00

Sub Total Grading: m3

4,300.00

51.00

219,300.00

m2

61,400.00

0.06

3,684.00

Sub Total Subgrade Preparation: m2

61,400.00

0.06

3,684.00

m2

21,580.00

0.92

19,853.60

m2

21,580.00

9.89

213,426.20

10760

Base Course,Crused Stone ( Lower than 8 cm ),T=20CM


Well graded Aggregate, 97% compaction ratio, CBR>70%
Gravel Paving,Crused Stone ( Lower than 8 cm ),T=10CM

m2

22,426.00

34.00

762,484.00

10770

Subbase Course,Crused Stone ( Lower than 8 cm ),T=30CM

m2

17,690.90

34.00

601,490.60

Sub Total Granular Base Coarse: m2

83,276.90

19.18

1,597,254.40

m2

21,580.00

22.00

474,760.00

m2

21,580.00

22.00

474,760.00

m2

21,580.00

3.38

72,940.40

m2

21,580.00

3.38

72,940.40

m2

17,690.90

0.87

15,391.08

m2

636.00

100.00

63,600.00

Sub Total Asphalt Paving: m2

21,580.00

54.42

1,174,391.88

m2

218.92

73.00

15,981.16

10710

10720

10730

10740

10750

Road/Paving
Grading
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Disposal,Machine,0-10km ( Distance )

Subgrade Preparation
Surfacing and Compaction

Granular Base Coarse


Subbase Course,Crused Stone ( Lower than 150 mm
),T=80CM

10820

Asphalt Paving
Wearing Course,#78,T=5 CM
maximum aggregate size = 50 mm, detailed specification SES
C04-S02
Binder Course,#467,T=5CM
Maximum aggregate size = 3/4 inch, Detailed specification
SES C04-S02
Tack Coating
detailed specification SES C04-S02
Prime Coating
detailed specification SES C04-S02
Surfacing and Cleaning

10830

Lane Marking, Normal Temperature Type, Manual Type

10780

10790

10800
10810

10840

Concrete Flatwork
Forming Work,Ply Wood,3 Times

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
10850

10860
10870

10880

Description

Unit

2,437.89

510.00

1,243,323.90

m
m

7,480.09
3,552.62

17.00
47.00

127,161.53
166,973.14

Isolation Joint, Thk=12mm,Bituminous Joint Filler with Joint


Sealant

6,870.00

37.00

254,190.00

1.00

1,807,629.73

1,807,629.73

86.40

1,320.00

114,048.00

Sub Total Guiderail: m

86.40

1,320.00

114,048.00

m2

30,350.00

28.00

849,800.00

m2

17,690.90

8.67

153,380.10

m2
m2

108.00
100.00

180.00
170.00

19,440.00
17,000.00

Sub Total Paving Accessories: LS

1.00

1,039,620.10

1,039,620.10

50.00

2,260.00

113,000.00

Sub Total Signage: LS

1.00

113,000.00

113,000.00

Sub Total Road/Paving: m2

44,006.00

137.91

6,068,928.12

m3

1,258.25

150.00

188,737.50

m3

883.20

54.00

47,692.80

m3

375.06

11.00

4,125.66

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

218.00

270.00

58,860.00

m3

135.00

54.00

7,290.00

m3

84.00

11.00

924.00

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

8,696.00

56.00

486,976.00

m3

4,471.50

54.00

241,461.00

m3

2,815.00

11.00

30,965.00

Guiderail
Guard Rail Installation

10910
10920
10930

Acid Proofing Tile


Alkali Proofing Tile

10940

10950

10960
10970
10980

10990
11000
11010

11020
11030

Amount

m3

Paving Accessories
Wire Mesh,F6x150x150
Epoxy Coated
PE Film,T=0.25 mm

10900

Rate

Concrete Pouring,Remicon, D=25mm,Fc=300kg/cm2,Slump


12cm
Cement Type I with Minimum Cement Content 360kg/m3,
Max. W/C Ratio 0.40, pouring height=-3~+3meters
Contraction Joint, SES-C01-F01-03, with Sealant
Expansion Joint, SES-C01-F01-03, with Sealant and Dowel
Bar

Sub Total Concrete Flatwork: LS

10890

Quantity

Signage
Traffic Sign Work,Guide Sign Pole
Safety & Information Board, Height 2.8m, Board Size
600x600mm

Equipment Foundations
Structural Excavation & Backfill
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

Nos

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11040

Description

Unit

Quantity

Rate

Amount

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

2,526.00

56.00

141,456.00

m3

9,091.00

54.00

490,914.00

m3

498.00

11.00

5,478.00

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

435.56

140.00

60,978.40

m3

384.79

54.00

20,778.66

m3

50.77

11.00

558.47

m3

3,722.96

57.00

212,208.72

m3

1,969.81

54.00

106,369.74

11120

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

1,754.16

11.00

19,295.76

11130

Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3

1,431.54

110.00

157,469.40

11140

Oily Sand,Machine,T=10cm (Compacted), Asphalt Concrete m3


with Prime Coat
Gravel filling and Compaction,Machine,T=15cm ( Compacted m3
)

155.46

120.00

18,655.20

14.40

86.00

1,238.40

m3

2,098.20

65.00

136,383.00

m3

1,302.31

54.00

70,324.74

m3

793.90

11.00

8,732.90

Sub Total Structural Excavation & Backfill: LS

1.00

2,517,873.35

2,517,873.35

11050
11060
11070

11080
11090
11100

11110

11150

11160

11170
11180

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

11190

Cast in Situ Concrete


Formwork
Forming Work,Ply Wood,3 Times

m2

487.27

81.00

39,468.87

11200

Forming Work,Ply Wood,3 Times

m2

135.00

81.00

10,935.00

11210

Forming Work,Ply Wood,3 Times

m2

2,273.00

81.00

184,113.00

11220

Forming Work,Ply Wood,3 Times

m2

1,449.00

81.00

117,369.00

11230

Forming Work,Ply Wood,3 Times

m2

106.89

82.00

8,764.98

11240

Forming Work,Ply Wood,3 Times

m2

2,221.08

81.00

179,907.48

11250

Forming Work,Ply Wood,3 Times

m2

1,349.34

81.00

109,296.54

Sub Total Formwork: m2

8,021.58

81.01

649,854.87

Concrete

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11260

11270

11280

11290

11300

11310

11320

11330

11340

11350

11360

11370

11380

11390

Description

Unit

Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump


12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters

Reinforcing Steel

Quantity

Rate

Amount

m3

439.50

610.00

268,095.00

m3

47.37

440.00

20,842.80

m3

1,568.00

610.00

956,480.00

m3

101.00

610.00

61,610.00

m3

2.20

440.00

968.00

m3

15.66

440.00

6,890.40

m3

25.62

440.00

11,272.80

m3

609.10

610.00

371,551.00

m3

31.24

440.00

13,745.60

m3

51.24

610.00

31,256.40

m3

3.98

440.00

1,751.20

m3

1,837.12

610.00

1,120,643.20

m3

101.01

430.00

43,434.30

m3

848.52

610.00

517,597.20

Sub Total Concrete: m3

5,681.56

603.03

3,426,137.90

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11400

11410

11420

11430

11440

11450

11460

11470

11480

11490

11500

11510

11520

11530

11540

Description
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm

Unit

Quantity

Rate

Amount

ton

0.34

6,770.00

2,301.80

ton

2.02

6,770.00

13,675.40

ton

8.63

6,770.00

58,425.10

ton

4.04

6,770.00

27,350.80

ton

7.80

6,770.00

52,806.00

ton

0.40

6,770.00

2,708.00

ton

0.79

6,770.00

5,348.30

ton

73.70

6,770.00

498,949.00

ton

1.90

6,770.00

12,863.00

ton

9.40

6,770.00

63,638.00

ton

33.00

6,770.00

223,410.00

ton

42.63

6,770.00

288,605.10

ton

0.06

6,770.00

406.20

ton

0.45

6,770.00

3,046.50

ton

2.61

6,770.00

17,669.70

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11550

11560

11570

11580

11590

11600

11610

11620

11630

11640

11650

11660

11670
11680

Description
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm

Unit

Quantity

Rate

Amount

ton

0.26

6,770.00

1,760.20

ton

0.37

6,850.00

2,507.10

ton

1.68

6,790.00

11,380.04

ton

14.60

6,770.00

98,814.92

ton

53.63

6,770.00

363,075.10

ton

9.10

6,770.00

61,607.00

ton

53.00

6,770.00

358,810.00

ton

80.76

6,770.00

546,745.20

ton

4.90

6,770.00

33,173.00

ton

43.25

6,770.00

292,802.50

ton

7.86

6,770.00

53,212.20

ton

7.72

6,770.00

52,264.40

Sub Total Reinforcing Steel: ton

464.89

6,770.14

3,147,354.56

Sub Total Cast in Situ Concrete: m3

5,682.00

1,271.27

7,223,347.33

Nos

124.00

4.28

530.72

Nos

28.00

110.00

3,080.00

Structural Steel
Anchor Bolts
Anchor Bolt Installation,M24
Installation Only
Anchor Box Installation,150x150x450(WxLxD)(mm)

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11690

Description

Unit

Quantity

Rate

Amount

Nos

20.00

3.34

66.80

Nos

106.00

4.28

453.68

Nos

80.00

4.55

364.00

Nos

20.00

6.42

128.40

Nos

48.00

8.03

385.44

11740

Anchor Bolt Installation,M16


Installation Only
Anchor Bolt Installation,M24
Installation Only
Anchor Bolt Installation,M32
Installation Only
Anchor Bolt Installation,M42
Installation Only
Anchor Bolt Installation,M48
Installation Only
Anchor Box Installation,150x150x600(WxLxD)(mm)

Nos

16.00

130.00

2,080.00

11750

Anchor Box Installation,150x150x900(WxLxD)(mm)

Nos

20.00

1,150.00

23,000.00

11760

Anchor Box Installation,150x150x450(WxLxD)(mm)

Nos

70.00

110.00

7,700.00

11770

Nos

24.00

3.34

80.16

Nos

80.00

4.28

342.40

11790

Anchor Bolt Installation,M16


Installation Only
Anchor Bolt Installation,M24
Installation Only
Anchor Box Installation,150x150x450(WxLxD)(mm)

Nos

8.00

130.00

1,040.00

11800

Anchor Box Installation,150x150x900(WxLxD)(mm)

Nos

12.00

180.00

2,160.00

11810

Nos

44.00

4.28

188.32

Nos

36.00

4.55

163.80

11830

Anchor Bolt Installation,M24


Installation Only
Anchor Bolt Installation,M32
Installation Only
Anchor Box Installation,150x150x600(WxLxD)(mm)

Nos

244.00

130.00

31,720.00

11840

Anchor Box Installation,150x150x900(WxLxD)(mm)

Nos

294.00

160.00

47,040.00

11850

Nos

85.00

4.71

400.35

11860

Anchor Bolt Installation,M24


Installation Only
Anchor Box Installation,150x150x600(WxLxD)(mm)

Nos

16.00

130.00

2,080.00

11870

Anchor Box Installation,150x150x450(WxLxD)(mm)

Nos

418.00

110.00

45,980.00

Sub Total Anchor Bolts: Nos

1,793.00

94.25

168,984.07

ton

0.03

13,310.00

399.30

ton

0.64

13,310.00

8,518.40

ton

2.80

13,310.00

37,268.00

ton

0.40

13,310.00

5,324.00

ton

7.00

13,310.00

93,170.00

Sub Total Steel: LS

1.00

144,679.70

144,679.70

Sub Total Structural Steel: LS

1.00

313,663.77

313,663.77

11700
11710
11720
11730

11780

11820

11880
11890
11900
11910
11920

Steel
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Misc.Steel Fabrication,Steel
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Insert Plate,Steel
with HDG

Waterproofing

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
11930

11940
11950

11960

11970
11980

11990

12000
12010
12020

12030

12040
12050

12060
12070

12080
12090

12100
12110
12120

12130
12140

12150
12160

Description
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Protection Board
3.5 mm bitumen impregnated fibreboard or 12 mm thickness
bitumen impregnated soft board
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Protection Board
3.5 mm bitumen impregnated fibreboard or 12 mm thickness
bitumen impregnated soft board
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,HDPE Film
THK = 750 microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,HDPE Film
THK = 750 microns

Unit

Quantity

Rate

Amount

m2

758.68

54.00

40,968.72

m2

373.18

4.65

1,735.29

m2

162.44

52.00

8,446.88

m2

86.00

54.00

4,644.00

m2

24.00

4.65

111.60

m2

10.00

52.00

520.00

m2

163.24

30.00

4,897.20

m2

1,638.44

55.00

90,114.20

m2

1,266.00

4.86

6,152.76

m2

120.00

41.00

4,920.00

m2

289.78

52.00

15,068.56

m2

445.63

54.00

24,064.02

m2

1,604.20

55.00

88,231.00

m2

764.00

4.86

3,713.04

m2

335.00

53.00

17,755.00

m2

294.45

4.65

1,369.19

m2

88.43

52.00

4,598.36

m2

135.38

54.00

7,310.52

m2

63.12

4.65

293.51

m2

27.80

52.00

1,445.60

m2

520.00

35.00

18,200.00

m2

1,163.00

54.00

62,802.00

m2

862.00

4.65

4,008.30

m2

927.00

35.00

32,445.00

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
12170

Description

Unit

Rate

Amount

m2

211.00

52.00

10,972.00

Sub Total Waterproofing: m2

12,332.77

36.88

454,786.75

12180

Mortar Grouting
Mortar Grouting,Non Shrinkage

m3

5.38

7,040.00

37,875.20

12190

Mortar Grouting,Non Shrinkage

m3

26.50

6,820.00

180,730.00

12200

m3

3.10

24,440.00

75,764.00

12210

Mortar Grouting,Epoxy Grout


minimum compressive strength at 7 days = 96 MPa
Mortar Grouting,Non Shrinkage

m3

6.24

7,050.00

43,992.00

12220

Mortar Grouting,Non Shrinkage

m3

0.11

7,050.00

775.50

12230

Mortar Grouting,Non Shrinkage

m3

16.62

6,810.00

113,182.20

Sub Total Mortar Grouting: m3

57.95

7,805.33

452,318.90

Sub Total Equipment Foundations: m3

5,650.00

1,940.18

10,961,990.10

m3

5,466.71

180.00

984,007.80

m3

2,541.25

54.00

137,227.50

m3

2,926.06

11.00

32,186.66

m3

3,088.38

170.00

525,024.60

m3

1,645.81

54.00

88,873.74

m3

1,442.57

11.00

15,868.27

Sub Total Structural Excavation & Backfill: LS

1.00

1,783,188.57

1,783,188.57

12240

12250
12260
12270

12280
12290

Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)

Quantity

Pit/Dike/Cooling Tower
Structural Excavation & Backfill
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

12300

Cast in Situ Concrete


Formwork
Forming Work,Ply Wood,3 Times

m2

2,234.09

81.00

180,961.29

12310

Forming Work,Ply Wood,3 Times

m2

3,409.80

81.00

276,193.80

Sub Total Formwork: m2

5,643.89

81.00

457,155.09

973.37

590.00

574,288.30

12320

Concrete
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters

m3

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
12330

12340

12350

12360

12370

12380

12390

12400

12410

12420

12430

12440

Description

Unit

Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm


Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45

Quantity

Rate

Amount

m3

38.20

440.00

16,808.00

m3

1,160.16

610.00

707,697.60

m3

63.76

440.00

28,054.40

Sub Total Concrete: m3

2,235.49

593.54

1,326,848.30

ton

1.25

6,770.00

8,462.50

ton

1.22

6,770.00

8,259.40

ton

72.10

6,770.00

488,117.00

ton

15.95

6,770.00

107,981.50

ton

9.50

6,770.00

64,315.00

ton

6.30

6,770.00

42,651.00

ton

21.76

6,770.00

147,315.20

ton

58.49

6,770.00

395,977.30

ton

20.21

6,770.00

136,821.70

Sub Total Reinforcing Steel: ton

206.78

6,770.00

1,399,900.60

Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D10 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D22 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D25 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D19 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm

12450

Concrete Accessories
Water Stop,B=200

248.00

37.00

9,176.00

12460

Expansion Joint, Gelacreyl Superflex AR

115.00

42.00

4,830.00

Sub Total Concrete Accessories: m

363.00

38.58

14,006.00

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Cast in Situ Concrete: LS

12470
12480
12490

12500
12510

12520
12530

12540
12550

12560

12570

12580
12590

12600

Rate

Amount

1.00

3,197,909.99

3,197,909.99

ton

1.37

13,310.00

18,234.70

ton

2.73

13,310.00

36,336.30

ton

5.65

13,310.00

75,201.50

Sub Total Steel: ton

9.75

13,310.00

129,772.50

m2

22.11

450.00

9,949.50

201.00

15,750.00

3,165,750.00

Sub Total Misc Metal: LS

1.00

3,175,699.50

3,175,699.50

Sub Total Structural Steel: LS

1.00

3,305,472.00

3,305,472.00

m2

1,425.62

55.00

78,409.10

m2

1,304.69

55.00

71,757.95

m2

828.72

4.86

4,027.58

m2

155.30

53.00

8,230.90

m2

785.00

41.00

32,185.00

m2

3,959.20

55.00

217,756.00

m2

1,912.80

4.86

9,296.21

m2

1,044.60

53.00

55,363.80

Sub Total Waterproofing: m2

11,415.93

41.79

477,026.54

m3

1.43

6,820.00

9,752.60

Sub Total Mortar Grouting: LS

1.00

9,752.60

9,752.60

Sub Total Pit/Dike/Cooling Tower: m3

2,172.00

4,039.30

8,773,349.70

Structural Steel
Steel
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Insert Plate,Steel
with HDG
Steel Item,Checked Plate
with HDG

Misc Metal
Grating,I-32
with HDG
Hand Rail,Steel,H=1.2m
Hot-Dip-Galvanized
Pipe Type

Waterproofing
Proofing,Epoxy Waterproofing
Coal Tar Epoxy Coating, THK=1000 Microns
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
Proofing,Protection Board
3.5 mm bitumen impregnated fibreboard or 12 mm thickness
bitumen impregnated soft board
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)

Mortar Grouting
Mortar Grouting,Non Shrinkage

Cable Trench/Duct Bank

Quantity

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

12630

Structural Excavation & Backfill


Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

6,590.70

11.00

72,497.70

12640

Sand filling and Compaction,Machine,T=15cm ( Compacted ) m3

10,638.84

110.00

1,170,272.40

12650

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

2,544.00

150.00

381,600.00

m3

1,957.40

54.00

105,699.60

m3

588.10

11.00

6,469.10

m3

508.00

130.00

66,040.00

m3

382.00

54.00

20,628.00

12700

Excavation,Normal Soil,Back Hoe


including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )

m3

145.00

11.00

1,595.00

12710

Crushed Stone Spreading with compaction,Machine

m3

134.00

83.00

11,122.00

Sub Total Structural Excavation & Backfill: LS

1.00

3,427,520.72

3,427,520.72

8,607.40

0.00

0.00

4,701.00
237.00

48.00
48.00

225,648.00
11,376.00

12610

12620

12660
12670
12680

12690

12720

Conduit
Warning Tape

m3

21,313.57

50.00

1,065,678.50

m3

9,739.23

54.00

525,918.42

12730
12740

HI PVC Conduit, SCH. 40, Size : 6 Inches


HI PVC CONDUIT FOR CONCRETE DUCT BANK.
SCHEDULE 40

M
M

12750

PVC CONDUIT SPACER


SIZE : 8"
UNIT : EA

SET

475.00

34.00

16,150.00

12760

PVC CONDUIT SPACER


SIZE : 6"
UNIT : EA

SET

5,234.00

34.00

177,956.00

Sub Total Conduit: LS

1.00

431,130.00

431,130.00

12770

Cast in Situ Concrete


Formwork
Forming Work,Ply Wood,3 Times

m2

5,040.87

81.00

408,310.47

12780

Forming Work,Ply Wood,3 Times

m2

477.45

81.00

38,673.45

12790

Forming Work,Ply Wood,3 Times

m2

492.00

81.00

39,852.00

Sub Total Formwork: m2

6,010.32

81.00

486,835.92

Concrete

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
12800

12810

12820

12830

12840

12850

12860

12870

12880

12890

12900

12910

12920

Description

Unit

Concrete Pouring,Remicon, D=25mm,Fc=300kg/cm2,Slump


12cm
Cement Type I with Minimum Cement Content 360kg/m3,
Max. W/C Ratio 0.40, pouring height=-3~+3meters
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=170kg/cm2,Slump
12cm
Red Color Powder Added 1kg/100kg cement, Cement Type I
with Minimum Cement Content 354kg/m3, Max. W/C Ratio
0.40, pouring height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45

Rate

Amount

m3

60.00

550.00

33,000.00

m3

1,174.44

590.00

692,919.60

m3

73.68

440.00

32,419.20

m3

395.22

440.00

173,896.80

m3

50.80

440.00

22,352.00

m3

149.00

590.00

87,910.00

m3

19.00

440.00

8,360.00

Sub Total Concrete: m3

1,922.14

546.71

1,050,857.60

ton

6.00

6,770.00

40,620.00

ton

117.45

6,770.00

795,136.50

ton

23.00

6,770.00

155,710.00

ton

0.48

6,770.00

3,249.60

ton

23.00

6,770.00

155,710.00

Sub Total Reinforcing Steel: ton

169.93

6,770.00

1,150,426.10

117.00

37.00

4,329.00

1.00

4,329.00

4,329.00

Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D13 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm

Concrete Accessories
Water Stop,B=200

Quantity

Sub Total Concrete Accessories: LS

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Cast in Situ Concrete: LS

12930
12940

12950
12960

12970

12980
12990

13000
13010
13020

13030
13040

Quantity

Rate

Amount

1.00

2,692,448.62

2,692,448.62

m2

1,808.92

4.86

8,791.35

m2

4,696.13

55.00

258,287.15

m2

1,061.25

4.86

5,157.68

m2

1,401.20

54.00

75,664.80

m2

389.00

54.00

21,006.00

m2

170.00

55.00

9,350.00

m2

104.00

66.00

6,864.00

Sub Total Waterproofing: m2

9,630.50

39.99

385,120.98

ton

0.06

13,310.00

798.60

ton

0.01

13,310.00

133.10

Nos

13.00

1,810.00

23,530.00

Sub Total Misc Metal: LS

1.00

24,461.70

24,461.70

m2

7,575.74

47.00

356,059.78

m2

56.97

3,830.00

218,195.10

Sub Total Brick Masonry: m2

7,632.71

75.24

574,254.88

Sub Total Cable Trench/Duct Bank: m3

748.00

10,073.45

7,534,936.90

m3

306.00

18.00

5,508.00

m3

270.00

54.00

14,580.00

m3

36.00

11.00

396.00

m3

24.00

18.00

432.00

m3

20.00

53.00

1,060.00

Waterproofing
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof (250 x 2 coats)

Misc Metal
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Steel Item,Misc.Steel Fabrication,Steel
with HDG
Man Hole,Cover
Cast Iron Cover

Brick Masonry
Laying Brick,Both Side
Red Concrete Tile, 305x305x50
Laying Brick,Both Side

Fence/Gate & Miscellaneous Works


Line item no. 1075 is a Subcontract Work by

13050

13060
13070
13080

13090

Structural Excavation & Backfill


Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density
Disposal,Machine,0-10km ( Distance )
Excavation,Normal Soil,Back Hoe
including surfacing and compaction 95 %, excavation
depth=0~-2meters
Back-filling and Compaction,Machine,T=15cm
compaction ratio 95% of maximum dry density

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

13100

Disposal,Machine,0-10km ( Distance )

m3

4.00

11.00

44.00

13110

EXCAVATION (GRAVEL & SOIL)


Including surfacing & compacyion 95%
BACKFILLING & COMPACTION
T=150
DISPOSAL (10KM)
Unfactored soil, Disposal area(10km far)
GRAVEL COMPACT.
Aggregate base course,THK=150mm

m3

30,535.78

18.00

549,644.04

m3

26,947.97

54.00

1,455,190.38

m3

3,527.79

11.00

38,805.69

m3

92.50

94.00

8,695.00

Sub Total Structural Excavation & Backfill: LS

1.00

2,074,355.11

2,074,355.11

13120
13130
13140

13150

Cast in Situ Concrete


Formwork
Forming Work,Ply Wood,3 Times

m2

270.00

81.00

21,870.00

13160

Forming Work,Ply Wood,3 Times

m2

20.00

86.00

1,720.00

13170

FORM (PLYWOOD)
for U/G concrete

m2

11,345.98

81.00

919,024.38

Sub Total Formwork: m2

11,635.98

81.01

942,614.38

m3

33.00

610.00

20,130.00

m3

3.90

440.00

1,716.00

m3

2.60

610.00

1,586.00

m3

0.30

440.00

132.00

m3

234.68

440.00

103,259.20

m3

2,878.91

620.00

1,784,924.20

m3

308.60

8,580.00

2,647,788.00

Sub Total Concrete: m3

3,461.99

1,317.03

4,559,535.40

7.20

6,770.00

48,744.00

13180

13190

13200

13210

13220

13230

13240

13250

Concrete
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
Concrete Pouring,Remicon, D=25mm,Fc=350kg/cm2,Slump
12cm
Cement Type I with Silica Fume 6% of Cement,Minimum
Cement Content 364kg/m3, Max W/C Ratio 0.4, pouring
height=-3~+3meters
Concrete,Man , D=25mm,Fc=170kg/cm2,Slump 12cm
Cement Type I,Minimum Cement Content 275kg/m3, Max
W/C Ratio 0.45
CONCRETE 1
For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE V
minimum Cement Content 275kg/cm3 Max W/C Ratio 0.45
CONCRETE 3
For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica
6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4,
Caicium Nitrite shall be added(min. 10 liters/m3 for 30%
solution)
CONCRETE ENCASEMENT
Included FORM & MISC. WORK & Material

Reinforcing Steel
Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy
Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm

ton

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
13260

13270

13280
13290
13300

13310

13320
13330
13340
13350

13360
13370
13380
13390

13400
13410

13420
13430

Description

Unit

Re-bar,Deformed Bar Normal Bending,SD40,D16 Epoxy


Coating
ASTM A615 Grade60,Epoxy Coating ASTM A775 min
0.15mm
RE-BAR 2
Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy
coating,thick.180~300micron

Quantity

Rate

Amount

ton

0.60

6,770.00

4,062.00

ton

326.56

6,770.00

2,210,811.20

Sub Total Reinforcing Steel: ton

334.36

6,770.00

2,263,617.20

Sub Total Cast in Situ Concrete: m3

3,462.00

2,243.14

7,765,766.98

Ton

13.00

13,310.00

173,030.00

EA

200.00

2.99

598.00

m2

57.02

53.00

3,022.06

Sub Total Misc Metal: LS

1.00

176,650.06

176,650.06

m2

216.00

54.00

11,664.00

m2

78.00

4.86

379.08

m2

16.80

54.00

907.20

m2

6.00

55.00

330.00

m2

16.80

53.00

890.40

m2

4,699.61

110.00

516,957.10

m2
m2
m2

537.35
630.02
12,070.75

63.00
66.00
52.00

33,853.05
41,581.32
627,679.00

Sub Total Waterproofing: m2

18,271.33

67.55

1,234,241.15

EA

2,492.00

98.00

244,216.00

EA

290.00

36.00

10,440.00

Sub Total Anchor Bolts: ea

2,782.00

91.54

254,656.00

400.00

480.00

192,000.00

1,599.00

460.00

735,540.00

1,999.00

464.00

927,540.00

Misc Metal
Metal Work/FAB. & Installation of MISC. Steel for Embeded
steel w/hot-dip-galvanized
Nut welding for Fireproofing (for fixing WWF)
ASTM A 563
w.w.f 50x50x2.5mm
including material and installation work

Waterproofing
Proofing,Epoxy Waterproofing, T=0.4 mm
Coal Tar Epoxy Coating, THK=400 Microns
(200 x 2 coats)
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Epoxy Waterproofing, T=0.5 mm
Coal Tar Epoxy Coating, THK=500 Microns
Proofing,PE Film
THK=0.25mm PE Membrane
Proofing,Polyurethane
Min. THK=500 microns, Water Proof
(250 x 2 coats)
LAYING PE FILM
FLOOR.(0.25MMX1PLIES)
Chemical resistant
One Pack Moisture cured, 500micr(250mic X 2Plys)
400micro(200micro X 2Plys)

Fence
Anchor Bolts
ANCHOR BOLT
M25~M35, Hot Dip Galvanized
ANCHOR BOLT
hot dip galvarnize

Fencing
Fence,Bared Wire Fence
m
Post Space=2m,H=1.55m,Gavanised
Installation and Disposal of Site Perimeter Fence (Temporary m
Purpose)
Sub Total Fencing: m

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

13440
13450

13460

13470
13480
13490

13500

13510

20000
20010

20020
20030
20040
20050

20060
20070

Description

Unit

Gates
Gate,Gate with Rail
W=8m,H=2.5m, Auto Sliding
Gate for temporary fence, 6 m width

Quantity

Rate

Amount

EA

2.00

103,040.00

206,080.00

EA

5.00

6,050.00

30,250.00

Sub Total Gates: ea

7.00

33,761.43

236,330.00

EA

1,070.00

70.00

74,900.00

Sub Total Piles: ea

1.00

74,900.00

74,900.00

D/I
D/I
D/I

414.00
1,220.00
1,996.00

460.00
1,270.00
2,210.00

190,440.00
1,549,400.00
4,411,160.00

Sub Total Sockets: DI

3,630.00

1,694.49

6,151,000.00

m3

10.30

6,560.00

67,568.00

Sub Total Grout: LS

1.00

67,568.00

67,568.00

Sub Total Fence: LS

1.00

7,711,994.00

7,711,994.00

m2

7,515.72

370.00

2,780,816.40

Sub Total Fendolite: LS

1.00

2,780,816.40

2,780,816.40

Sub Total Fence/Gate & Miscellaneous Works: m3

3,458.00

6,287.98

21,743,823.70

Sub Total Civil Work: LS

1.00

71,803,366.09

71,803,366.09

m3

7,868.73

63.00

495,729.99

m3

3,429.75

71.00

243,512.25

m3
m3

6,073.74
1,403.14

71.00
11.00

431,235.54
15,434.54

m3

784.39

120.00

94,126.80

m3

1,148.85

61.00

70,079.85

m2

6,907.93

3.85

26,595.53

m2

927.08

12.00

11,124.96

Piles
PILE HEAD TREATMENT
Dia.=600mm, L=14m & 18m

Sockets
Non Internal Lined. Non External Lined. Socket (Fillet)Joint
Non Internal Lined. Non External Lined. Socket (Fillet)Joint
Non Internal Lined. Non External Lined. Socket (Fillet)Joint

Grout
GROUT
Min.35MPa(7 days) : ASTM C1107

Fendolite
FENDOLITE
For 2 hrs fire resistance,including w.w.f 50x50x2.5mm and
required(stud)bolt@300 & final urethane coating

Building Work
Sitework
EXCAVATION (GRAVEL & SOIL)
Including surfacing & compacyion 95%
BACKFILLING & COMPACTION
w/imported soil, 50mm sieve 100% passing, #200 sieve
0~20% passing, LL=Max.35, PL=Max.12
BACKFILLING & COMPACTION
DISPOSAL (10KM)
Unfactored soil, Disposal area(10km far)
GRAVEL COMPACT.
Aggregate base course,THK=150mm
SAND POURING & COMPACTION
Imported sand for sand bedding(w/Soil compaction
underneath the bedding
LAYING PE FILM
FLOOR.(0.25MMX1PLIES)
GRAVEL PAVING
THK=100

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20080

20090
20100

20110

20120

20130

20140
20150

20160
20170

20180

20190

20200

Description

Unit

FENCE (P.V.C COATING)


Havy duty expanded metal mesh - Hot dip
galvanized(including Fence Door),removable, 8~12 gage
13mm Max.gap

Rate

Amount

923.95

730.00

674,483.50

Sub Total Sitework: LS

1.00

2,062,322.96

2,062,322.96

m2

12,326.21

110.00

1,355,883.10

m2

3,897.14

110.00

428,685.40

Sub Total Formwork: m2

16,223.35

110.00

1,784,568.50

m3

317.49

420.00

133,345.80

m3

1,703.25

690.00

1,175,242.50

m3

2,797.70

690.00

1,930,413.00

m3

1,703.25

31.00

52,800.75

m3

3,115.19

23.00

71,649.37

Sub Total Concrete: m3

9,636.88

349.02

3,363,451.42

ton

438.84

4,690.00

2,058,159.60

ton

153.24

6,470.00

991,462.80

ton

592.08

300.00

177,624.00

Sub Total Rebar: ton

1,184.16

2,725.35

3,227,246.40

Sub Total Reinforced Concrete: m3

9,637.00

869.07

8,375,266.32

m2

66.36

150.00

9,954.00

m2

647.52

180.00

116,553.60

Reinforced Concrete
Formwork
FORM (PLYWOOD)
above ground
FORM (PLYWOOD)
for U/G concrete

Concrete
CONCRETE 1
For U/G Plain Con'c.,ASTM 17MPa,ASTM C150 TYPE I
minimum Cement Content 275kg/cm3 Max W/C Ratio 0.45
CONCRETE 2
For A/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica
Fume 6% Minimum Cement Content 364kg/cm3 Max W/C
Ratio 0.4, Calcium Nitrite shall be added (min. 10 litres/m3 for
30% solution)
CONCRETE 3
For U/G RC,ASTM 35MPa,ASTM C150 TYPE I + Micro silica
6% Minimum Cement Content 364kg/cm3 Max W/C Ratio 0.4,
Caicium Nitrite shall be added(min. 10 liters/m3 for 30%
solution)
CON'C POURING ( PUMPCAR)
CON'C POURING (REMICON)
for U/G Concrete

Rebar
RE-BAR 1
Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated
RE-BAR 2
Dia.10~32,ASTM A615 Grade 60, Fusion bonded epoxy
coating,thick.180~300micron
RE-BAR MANUFACTURING AND FITTING

Masonry Work
CONCRETE BLOCK WORK
(ASTM C129,TYPE?),Including solid concrete fill,12mm
vertical reinforcement & tooled finish(Min. 2hr. fire rated)
including block mesh
CONCRETE BLOCK WORK
(ASTM C129,TYPE?),Including solid concrete fill,12mm
vertical reinforcement & tooled finish(Min. 2hr. fire rated)
including block mesh

Quantity

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20210

20220
20230
20240

20250
20260

20270
20280
20290

Description

Unit

CONCRETE BLOCK WORK


(ASTM C129,TYPE?),Including solid concrete fill,12mm
vertical reinforcement & tooled finish(Min. 2hr. fire rated)
including block mesh
LINTEL FAB.& INSTALL
PC Lintel, 250 x 300mm
RE-BAR
Dia.10~32mm,ASTM A615/A615M Grade 60, Uncoated
GRANITE
T=50(W=450)

Rate

Amount

1,800.00

220.00

396,000.00

11.50

170.00

1,955.00

ton

17.94

6,770.00

121,453.80

m2

96.88

1,350.00

130,788.00

Sub Total Masonry Work: m2

2,414.00

321.75

776,704.40

EA

276.00

260.00

71,760.00

EA

396.00

260.00

102,960.00

Sub Total Anchor Bolts: ea

672.00

260.00

174,720.00

ton

10.35

15,510.00

160,528.50

ton

42.80

10,900.00

466,520.00

ton

42.80

9,060.00

387,768.00

Sub Total Miscellaneous Metal: ton

95.95

10,576.51

1,014,816.50

Metal Work
Anchor Bolts
ANCHOR BOLT
M25~M35, Hot Dip Galvanized
ANCHOR BOLT
hot dip galvarnize

Miscellaneous Metal
INSERT PLATE
ASTM A36
MISC. STEEL
hot dip galvanized material
FAB. & INSTALL. OF MISC. STEEL

m2

Quantity

20300

Metal Trim
AL. MOULDING

464.58

190.00

88,270.20

20310

SETTING NON-SLIP

115.63

170.00

19,657.10

Sub Total Metal Trim: m

580.21

186.01

107,927.30

m3

8.26

5,210.00

43,034.60

Sub Total Grouting: LS

1.00

43,034.60

43,034.60

56.00

23,937.47

1,340,498.40

1,376.70

180.00

247,806.00

1,460.50

180.00

262,890.00

20320

Grouting
GROUT
Min.35MPa(7 days) : ASTM C1107

Sub Total Metal Work: t

20330

20340

Thermal & Mosture Protection


Waterproofing
Waterproofing
SHEET WATERPROOFING
m2
300*300*50thl. Cement Leight Weight Tiles or
Gravel(50mm)+Alyaf 140Gm/m2 Seperation layer+insulation :
Thk=50 Extruded polystyrene board+Thk.=0.2 P.E
Film+Waterproof membrane : Torchseal membrane 4mm
Thk.(2Layer)+Asphalt primer+Steel t
SHEET-APPLIED MEMBRANE WATERPROOFING
PU Waterproof Membrane

m2

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20350
20360
20370
20380

20390
20400
20410

20420

20430

20440

20450

20460

Description
WATERPROOF MORTAR
For wall,T=30
WATERPROOF MORTAR

Unit

Quantity

Rate

Amount

m2

257.92

81.00

20,891.52

m2

385.66

89.00

34,323.74

LIQUID WATERPROOFING
m2
For floor & Wall
WATERPROOF PROTECTION BOARD
m2
Waterproof gypsum board(For wall), Waterproof plywood 9t +
Waterproofed gypsumboard 9t

28.52

240.00

6,844.80

331.20

270.00

89,424.00

Sub Total Waterproofing: m2

3,840.50

172.42

662,180.06

700.00

51.00

35,700.00

255.30

60.00

15,318.00

40.25

130.00

5,232.50

Sub Total Joint Sealing: LS

1.00

56,250.50

56,250.50

Sub Total Waterproofing: m2

2,866.00

250.67

718,430.56

m2

1,926.25

23.00

44,303.75

Sub Total Insulation: LS

1.00

44,303.75

44,303.75

602.80

60.00

36,168.00

Sub Total Caulking & Sealing: LS

1.00

36,168.00

36,168.00

Sub Total Thermal & Mosture Protection: LS

1.00

798,902.31

798,902.31

9.00

3,980.00

35,820.00

27.00

5,420.00

146,340.00

7.00

5,960.00

41,720.00

Joint Sealing
CAULKING
Around Doors & Windows
CONTROL JOINT
WATER DRIP
Water stop

Insulation
ROCK WOOL
Wall (T=50)

Caulking & Sealing


EXPANSION JOINT/CAULKING

Doors & Windows


Steel Doors
STEEL DOOR
EA
(Size 0.8x2.1) Steel door on lightweight partition-Including
Alkyd painting/Accessories/Grouting for the frames(If
necessory), 10mmTHK.(ext.)/3mmTHK(int.) Cold rolled sheet
door leaf(Both sides) & 100x65x2 Door frame
STEEL DOOR
EA
(Size 1.0x2.2) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces
STEEL DOOR
EA
(Size 1.1x2.2) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

20470

STEEL DOOR
(Size 1.8x2.4)Including Alkyd painting/Accessories/Grouting
for the frames(if necessary),45mm thick,grade?,Heavy
duty,model2,seamless design 1.5mm thick cold rolled steel
sheet faces

EA

2.00

10,750.00

21,500.00

20480

STEEL DOOR
EA
(Size 2.2x2.6) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces
STEEL DOOR
EA
(Size 2.7x3.1) Including Alkyd painting/Accessories/Grouting
for the frames(if necessary). 45mm thick, grade2, heavy dyty,
model2, seamless design 1.5mm thick colorolled steel sheet
faces

2.00

14,200.00

28,400.00

2.00

20,720.00

41,440.00

Sub Total Steel Doors: ea

49.00

6,433.06

315,220.00

EA

1.00

16,330.00

16,330.00

EA

1.00

21,360.00

21,360.00

EA

2.00

21,250.00

42,500.00

Sub Total Glass Doors: ea

4.00

20,047.50

80,190.00

EA

3.00

35,320.00

105,960.00

EA

1.00

129,320.00

129,320.00

Sub Total Special Doors: ea

4.00

58,820.00

235,280.00

EA

61.00

1,650.00

100,650.00

EA

61.00

1,040.00

63,440.00

EA

61.00

110.00

6,710.00

EA

18.00

16,970.00

305,460.00

7.00
1.00

880.00
1,650.00

6,160.00
1,650.00

1.00

484,070.00

484,070.00

EA

2.00

6,970.00

13,940.00

EA

13.00

46,930.00

610,090.00

20490

20500
20510
20520

20530

20540

20550

20560
20570
20580
20590
20600

Glass Doors
TEMPERED GLASS DOOR
1.8*2.1 W/ACCESSORIES
TEMPERED GLASS DOOR
2.0 X 2.4 W/ACCESORRIES
TEMPERED GLASS DOOR
1.8 X 2.7 W/ACCESSORIES

Special Doors
BLAST RESISTANT DOOR
(Size 1.0x2.2) Resisting against 2ton/m2(suction),including
door accessories
BLAST RESISTANT DOOR
(Size 2.0x2.4) Resisting against 2ton/m2(suction),including
door accessories

Door Hardware
LOCK SET
3 keys for each door, 3 keys for each building, 3 keys for each
group, 3 keys for master
DOOR CLOSER
FOR GENERAL USE K-1630, for Heavy duty steel door"
DOOR STOP
FOR OPERATED FRICTION DOOR HOLDER
PANIC DEVICE
Stainless steel
PIVOT HINGE
DOOR KNOB

SET
EA

Sub Total Door Hardware: LS

20610

20620

Windows
AL. WINDOW/FRAME
(Size 0.9x1.8) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x12) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
20630

20640

20650

20660

20670

20680

20690

20700

20710
20720
20730
20740
20750

20760
20770
20780
20790

20800

Description

Unit

AL. WINDOW/FRAME
(Size 1.2x0.6) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x12) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 1.2x1.5) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 1.2x3.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 2.0x1.5) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x3.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 1.2x4.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5
AL. WINDOW/FRAME
(Size 0.9x6.0) Including accessories Extruded aluminum
complying with ASTM B221 alloy 6063-T5

Quantity

Rate

Amount

EA

1.00

3,160.00

3,160.00

EA

3.00

46,930.00

140,790.00

EA

3.00

7,730.00

23,190.00

EA

3.00

15,450.00

46,350.00

EA

2.00

13,000.00

26,000.00

EA

2.00

11,710.00

23,420.00

EA

3.00

20,610.00

61,830.00

EA

4.00

23,360.00

93,440.00

Sub Total Windows: ea

36.00

28,950.28

1,042,210.00

m2

223.97

1,550.00

347,153.50

m2

16.39

4,270.00

69,985.30

m2

3.04

2,080.00

6,323.20

m2

13.70

3,090.00

42,333.00

m2

8.19

880.00

7,207.20

Sub Total Glazing: m2

265.29

1,782.96

473,002.20

EA

1.00

14,790.00

14,790.00

EA

4.00

33,110.00

132,440.00

EA

1.00

33,110.00

33,110.00

EA

5.00

50,550.00

252,750.00

Sub Total Shutters: ea

11.00

39,371.82

433,090.00

EA

36.00

6,180.00

222,480.00

Sub Total Louvres: LS

1.00

222,480.00

222,480.00

Sub Total Doors & Windows: ea

140.00

23,468.16

3,285,542.20

Glazing
CLEAR GLASS
Type I,Class 1, Quality Q4
PAIR GLASS
Tempered Glass 6T + Air space 13T + Clear Glass 6T
WIRED GLASS
T=8
TEMPERED GLASS
DAMP PROOFING MIRROR
For toilet

Shutters
SHUTTER (ELECTRICAL)
(Size 1.8x2.5) Steel, Galv.
SHUTTER (ELECTRICAL)
3.0x3.5 (Steel Galvanized)
SHUTTER (ELECTRICAL)
3.0x3.5 (Steel Galvanized)
SHUTTER (ELECTRICAL)
(Size 4.0x4.0) Steel, Galv.

Louvres
LOUVER(AL)
(Size 1.2x1.2) Including accessories

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

20810
20820

20830

Description

Unit

Finishing
Flooring
CARPET TILE
Modular carpet tile
ACCESS FLOOR
Rubber tile finish(H=600) - Galvanized steel frame filled with
cement grout H=600mm,including accessories & anchor bolt
including the 2% of the spare material supply
BASE BOARD VINYL (H=100)

20850
20860

20870

20880
20890

20900
20910
20920
20930
20940
20950
20960
20970
20980

Rate

Amount

m2

43.70

90.00

3,933.00

m2

354.20

820.00

290,444.00

597.10

76.00

45,379.60

1.00

339,756.60

339,756.60

m2

2,196.50

96.00

210,864.00

m2

697.04

98.00

68,309.92

m2

3,686.50

88.00

324,412.00

m2

687.75

120.00

82,530.00

m2

360.87

100.00

36,087.00

m2

2,415.71

88.00

212,582.48

m2

24.15

75.00

1,811.25

m2

4,396.40

75.00

329,730.00

m2

279.45

77.00

21,517.65

m2

5,252.81

66.00

346,685.46

m2

769.43

81.00

62,323.83

m2

350.68

96.00

33,665.28

667.87

22.00

14,693.14

m
m

163.30
22.99

19.00
25.00

3,102.70
574.75

Sub Total Painting: m2

21,117.29

82.82

1,748,889.46

Sub Total Flooring: LS

20840

Quantity

Painting
ACRYLIC PAINT
On gypsum board - Fenomastic 04 flat emulsion
w/Fenomastic 20 semi Gloss emulsion finish coat Acrylic
emulsion Paint conforming to SASO SSA 470 for exterior
emulsion
ACRYLIC PAINT
DOOR & WINDOW, Polyamide, Oil Paint 2 Plies
ACRYLIC PAINT
Fenomastic 04 flat emulsion w/Fenomastic 20 semi Gloss
emulsion finish coat Acrylic emulsion Paint conforming to
SASO SSA 470 for exterior emulsion
ACRYLIC PAINT
On exposed Con'c celing - Fenomastic 04 flat emulsion 2
coats Acrylic emulsion Paint conforming to SASO SSA 470 for
exterior emulsion
ACRYLIC PAINT
Acrylic latex paint for exposed Conc.(WeatherProofing)
ACRYLIC PAINT
Block filler & Fenomastic 04 flat emulsion Acrylic emulsion
paint cinforming to SASO SSA 470 for Exterior emulsion
EPOXY COATING
T=0.2mm Dust-proofing
EPOXY COATING
T=0.2mm Dust-proofing
EPOXY COATING
T=0.2mm For dust-proofing, under access floor
Coaltar Epoxy,for U/G RC Surface,400micro (250mic.x 2plys)
URETHANE COATING
One Pack Moisture cured, 500micro 1 Ply
VINYL TILE
Resilient Vinyl Tile,300x300x3T,Homogenious type
BASE BOARD SELLAMIN PAINT
base board enamel paint(H=100)
ARCRLIC PAINT (H=100)
BASE BOARD EPOXY PAINT

20990

Tile
CERAMIC TILE (INT.- WALL)

m2

291.87

450.00

131,341.50

21000

CERAMIC TILE (FLOOR)

m2

91.38

390.00

35,638.20

21010

ACIDPROOF TILE

m2

26.45

650.00

17,192.50

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit
Sub Total Tile: m2

21020

21030
21040

Gypsum Board
SETTING GYPSUM BOARD
m2
16mm,for wall,including 22 gage steel stud frame(64) & runner
& bead & sealant on the other side of the steel framed metal
sheet wall cladding
GYPSUM BOARD
m2
GYPSUM PARTITION
m2
Sub Total Gypsum Board: m2

Quantity

Rate

Amount

409.70

449.53

184,172.20

2,196.50

160.00

351,440.00

41.90
7.04

180.00
170.00

7,542.00
1,196.80

2,245.44

160.40

360,178.80

187.22

1,080.00

202,197.60

21060

Plastering
METAL LATH
m2
Heavy duty expanded metal mesh - Hot dip
galvanized(excluding the steel frames),removable, 8~12 gage
13mm Max.gap
CEMENT MORTAR
m2

1,522.98

59.00

89,855.82

21070

CEMENT MORTAR

m2

4,408.77

30.00

132,263.10

21080

CEMENT MORTAR

m2

2,415.71

30.00

72,471.30

21090

LEVELLING MORTAR
For roof
STEEL TROWEL FINISH

m2

963.60

57.00

54,925.20

m2

1,944.42

10.00

19,444.20

HARDENER
Metallic,aggregate dry-shake floor hardener(including water
soluble inorganic silicate based compound finish)
MORTAR GROUTING AROUND WINDOW FRAME

m2

752.25

55.00

41,373.75

38.64

47.00

1,816.08

9,312.00

65.97

614,347.05

m2

888.95

130.00

115,563.50

m2

407.10

27.00

10,991.70

m2

481.85

36.00

17,346.60

Sub Total Ceilings: LS

1.00

143,901.80

143,901.80

Sub Total Finishing: LS

1.00

3,391,245.91

3,391,245.91

m2

6.73

3,460.00

23,285.80

EA

1.00

35,370.00

35,370.00

21050

21100
21110

21120

Sub Total Plastering : m2

21130

21140
21150

Ceilings
ACOUSTIC BOARD
15x600x600 - For ceiling,including paint including the 2% of
the spare material supply
CEILING SYSTEM 2
Lightweight ceiling frame - T bar
CEILING SYSTEM 2
Lightweight ceiling frame - M bar

21170

Accessories
TOILET PARTITION
Including partition door and accessories
FRP SEPTIC TANK

21180

FRP SEPTIC TANK

EA

2.00

35,370.00

70,740.00

21190

FRP SEPTIC TANK


50 PERSON

EA

1.00

52,280.00

52,280.00

Sub Total Accessories: LS

1.00

181,675.80

181,675.80

21160

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

21200

Description

Unit

Furniture
CURTAIN BOX

Quantity

Rate

Amount

m2

11.22

250.00

2,805.00

Sub Total Furniture: LS

1.00

2,805.00

2,805.00

Sub Total Building Work: LS

1.00

20,214,963.30

20,214,963.30

Ton

2,420.88

2,450.00

5,931,156.00

30010

CHK'D PLATE
Ton
Steel angle framed including painting works, HOT DIP GALV.

5.18

6,690.00

34,654.20

30020

Fabrication and Erection of Access Platform for Operation and Ton


Maintenance Purpose

50.00

18,410.00

920,500.00

Sub Total Structural Steel: ton

2,476.06

2,781.16

6,886,310.20

m2

5,657.25

260.00

1,470,885.00

m2

540.00

110.00

59,400.00

Sub Total Grating & Deck Plate: m2

6,197.25

246.93

1,530,285.00

3,015.41

300.00

904,623.00

11.50

320.00

3,680.00

7.25

260.00

1,885.00

477.86

390.00

186,365.40

412.14

1,150.00

473,961.00

Sub Total Handrail, Ladders & Stairs: m

3,924.16

400.22

1,570,514.40

EA

850.00

21.00

17,850.00

EA

102.00

41.00

4,182.00

Sub Total Anchor Bolts: ea

952.00

23.14

22,032.00

m2

2,661.84

31.00

82,516.89

Sub Total Field Painting: LS

1.00

82,516.89

82,516.89

30000

30030
30040

30050

30060

30070
30080
30090

30100
30110

30120

Structural Steel Work


Structural Steel
Structural Steel
STEEL ERECTION

Grating & Deck Plate


GRATING (SERRATED)
F-32 (HOT DIP GALV. )
DECK PLATE

Handrail, Ladders & Stairs


HANDRAIL (SECL STANDARD)
m
Including Hot dip galvanizing(25kg/m)+POLYURETHANE
COATING 50 MIC. H=1.1(Post&Top/Middle Rail Pipe)
HANDRAIL (SECL STANDARD)
m
Removable Type, Including Hot dip galvanized H=1.1(Post &
Top/Middle Rail Pipe)
STEEL LADDER WITHOUT CAGE
m
STEEL LADDER WITH CAGE
Hop Dip Galvanizing
STEEL STAIR(SECL STD'D)
w/ HANDRAIL (Hop Dip Galvanized) W=800~900
FL:GRTG.F-32

Anchor Bolts
SET ANCHOR BOLT
Expansion stud anchor
SET ANCHOR BOLT
Expansion Stud anchor

Field Painting
TOUCH UP PAINT

Grouting

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
30130

Description

Unit

NON-SHRINK GROUT

Quantity

Rate

Amount

m3

11.54

5,210.00

60,123.40

Sub Total Grouting: LS

1.00

60,123.40

60,123.40

Sub Total Structural Steel: ton

2,847.00

3,565.78

10,151,781.89

30140

Roofing & Siding Work


Roofing & Siding
F.M SHEET (V-115) : FOR ROOFING

m2

1,807.45

380.00

686,831.00

30150

F.M SHEET (V-115) : FOR SIDING

m2

1,937.70

360.00

697,572.00

30160

S/W PANEL (GLASS WOOL) : FOR ROOFING


Roof : C/S(0.6)+75+C/S(0.7)
S/W PANEL (GLASS WOOL) : FOR SIDING
Wall : C/S(0.6)+50+C/S(0.7)

m2

37.98

27.00

1,025.46

m2

113.40

27.00

3,061.80

Sub Total Roofing & Siding: LS

1.00

1,388,490.26

1,388,490.26

469.52

170.00

79,818.40

364.30

280.00

102,004.00

360.41

450.00

162,184.50

Sub Total Flashing: m

1,194.23

288.06

344,006.90

408.98

100.00

40,898.00

246.73

370.00

91,290.10

Sub Total Gutter: m

655.71

201.60

132,188.10

30170

30180
30190
30200

30210
30220

Flashing
FLASHING (COLOR SHEET)
Factory painted galvanized steel
FLASHING (COLOR SHEET)
Factory painted galvanized steel
FLASHING (COLOR SHEET)
Factory painted galvanized steel

Gutter
STEEL DOWNSPOUT
Galvanized alkyd painted
GUTTER
Gal.2.3t+Epoxy coating 2plys

30230

Drains
ROOF DRAIN

EA

19.00

830.00

15,770.00

30240

ROOF DRAIN

EA

50.00

790.00

39,500.00

30250

FLOOR DRAIN
Dia.250, Stainless steel
SPLASH BLOCK

EA

10.00

1,030.00

10,300.00

EA

50.00

2,090.00

104,500.00

LEADER HEAD
t=0.7 Factory painted galvanized steel

EA

50.00

2,440.00

122,000.00

Sub Total Drains: LS

1.00

292,070.00

292,070.00

Sub Total Roofing & Siding Work: m2

3,614.00

596.78

2,156,755.26

Sub Total Structural Steel Work: LS

1.00

12,308,537.15

12,308,537.15

30260
30270

Process Piping Work


Underground Piping Installation
Pipe

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
40000
40010
40020
40030
40040
40050

40060

40070
40080

41140
41150

40090
40100
40110
40120
40130
40140
40150
40160
40170
40180
40190
40200
40210
40220
40230
40240
40250
40260
40270
40280

Description

Unit

Flange to Flange connection, Installation of In-line


components such as PIV etc.
3" ~ 6" (STD) FBE Coated Steel Pipes (3-Layer (FBE+PP)
Coated)
8" ~ 10" (STD) FBE Coated Steel Pipes (3-Layer (FBE+PP)
Coated)
12" ~ 24" (Over 7.93 ~ 9.53T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated)
26" ~ 48" (Over 7.93 ~ 9.53T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated)
26" ~ 48" (Over 9.53 ~ 12.70T) FBE Coated Steel Pipes (3Layer (FBE+PP) Coated)

Quantity

Rate

Amount

D/I

781.50

25.00

19,537.50

D/I

1,560.00

120.00

187,200.00

D/I

98.00

68.00

6,664.00

D/I

7,608.00

98.00

745,584.00

D/I

2,982.00

120.00

357,840.00

D/I

356.00

130.00

46,280.00

Sub Total Pipe: D/I

13,385.50

101.83

1,363,105.50

m2

76.00

2,200.00

167,200.00

Sub Total Wrapping: LS

1.00

167,200.00

167,200.00

774.00
78.00

470.00
310.00

363,780.00
24,180.00

Sub Total Testing: LS

1.00

387,960.00

387,960.00

Sub Total Underground Piping Installation: DI

13,386.00

143.30

1,918,265.50

m3
m3

12.00
6.00

580.00
6,670.00

6,960.00
40,020.00

Sub Total Piping Civil Work: LS

1.00

46,980.00

46,980.00

DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI

2.00
31,937.30
3.00
25.00
21,647.40
23,029.25
4.00
5,652.00
7,562.00
26.00
1,124.00
5,851.50
4.00
22.00
23,029.25
4.00
5,652.00
7,562.00
26.00
1,124.00

73.00
68.00
75.00
75.00
110.00
110.00
110.00
90.00
66.00
96.00
95.00
120.00
120.00
120.00
110.00
130.00
64.00
70.00
100.00
100.00

146.00
2,171,736.40
225.00
1,875.00
2,381,214.00
2,533,217.50
440.00
508,680.00
499,092.00
2,496.00
106,780.00
702,180.00
480.00
2,640.00
2,533,217.50
520.00
361,728.00
529,340.00
2,600.00
112,400.00

Sub Total Carbon Steel Pipe: DI

134,286.70

92.72

12,451,007.40

Wrapping
Wrapping/Coating For Welding Joint ALL Size (Included
wrapping material)

Testing
NDT/PMI/Thick Test Shop NDT Radiographic Test
NDT/PMI/Thick Test Shop NDT Liquid Penetration Test

Above Ground Piping


Piping Civil Work
Local Foundation Installation Con'c only
Local Foundation Installation Grouting only

Piping Installation
Carbon Steel Pipe
Up to 2.1/2" Carbon Steel
Up to 2.1/2" Carbon Steel Class 3000 & Below
Up to 2.1/2" Carbon Steel Class 6000 & Over
Up to 2.1/2" Carbon Steel Class 3000 ~ 9000
Up to 2.1/2" Carbon Steel STD
3" ~ 6" Carbon Steel STD
3" ~ 6" Carbon Steel SCH XS
8" ~ 10" Carbon Steel STD
12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T
12" ~ 24" Carbon Steel Over 12.70T ~ 15.88T
12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T
Up to 2.1/2" Carbon Steel SCH XS
Up to 2.1/2" Carbon Steel SCH XXS
Up to 2.1/2" Carbon Steel SCH160
3" ~ 6" Carbon Steel STD
3" ~ 6" Carbon Steel SCH XS
8" ~ 10" Carbon Steel STD
12" ~ 24" Carbon Steel Over 7.93 ~ 9.53T
12" ~ 24" Carbon Steel Over 12.70T ~ 15.88T
26" ~ 48" Carbon Steel Over 7.93 ~ 9.53T

SHT
Point

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

40290
40300
40310
40320
40330
40340
40350
40360
40370
40380
40390
40400
40410
40420
40430
40440
40450
40460
40470
40480
40490
40500
40510
40520
40530
40540

40550
40560
40570
40580
40590
40600

40610

40620
40630
40640
40650
40660
40670
40680
40690
40700

Description

Unit

Stainless Steel Pipe


Up to 2.1/2" Stainless Steel SCH10S
Up to 2.1/2" Stainless Steel SCH40S
Up to 2.1/2" Stainless Steel SCH80S
Up to 2.1/2" Stainless Steel SCH40S
Up to 2.1/2" Stainless Steel SCH80S
Up to 2.1/2" Stainless Steel Class 3000 & Below
3" ~ 6" Stainless Steel SCH10S
3" ~ 6" Stainless Steel SCH40S
3" ~ 6" Stainless Steel SCH80S
3" ~ 6" Stainless Steel SCH80S
3" ~ 6" Stainless Steel SCH10S
3" ~ 6" Stainless Steel SCH40S
8" ~ 10" Stainless Steel Below than SCH 40
8" ~ 10" Stainless Steel SCH10S
8" ~ 10" Stainless Steel SCH80S
8" ~ 10" Stainless Steel Below than SCH 40
8" ~ 10" Stainless Steel SCH10S
8" ~ 10" Stainless Steel SCH80S
12" ~ 24" Stainless Steel Up to 7.93T
12" ~ 24" Stainless Steel Over 7.93 ~ 9.53T
12" ~ 24" Stainless Steel Over 9.53T ~ 12.70T
12" ~ 24" Stainless Steel Up to 7.93T
12" ~ 24" Stainless Steel Over 7.93 ~ 9.53T
12" ~ 24" Stainless Steel Over 9.53T ~ 12.70T
26" ~ 48" Stainless Steel Over 7.93 ~ 9.53T
26" ~ 48" Stainless Steel Over 7.93 ~ 9.53T

Quantity

Rate

Amount

DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI
DI

18,058.50
1,473.30
480.50
2,044.00
125.50
12,606.60
28,109.75
91.50
179.00
179.00
28,109.75
91.50
1,406.00
1,342.00
243.00
1,406.00
1,342.00
243.00
1,637.00
397.00
106.00
1,637.00
397.00
106.00
140.00
140.00

90.00
94.00
110.00
40.00
49.00
51.00
160.00
160.00
220.00
99.00
85.00
85.00
130.00
140.00
170.00
59.00
58.00
77.00
150.00
160.00
230.00
84.00
100.00
150.00
240.00
170.00

1,625,265.00
138,490.20
52,855.00
81,760.00
6,149.50
642,936.60
4,497,560.00
14,640.00
39,380.00
17,721.00
2,389,328.75
7,777.50
182,780.00
187,880.00
41,310.00
82,954.00
77,836.00
18,711.00
245,550.00
63,520.00
24,380.00
137,508.00
39,700.00
15,900.00
33,600.00
23,800.00

Sub Total Stainless Steel Pipe: DI

102,090.90

104.70

10,689,292.55

DI
DI
DI
DI
DI
DI

3,314.60
4,458.70
2,726.50
2,736.50
697.00
2,458.50

9.85
15.00
11.00
11.00
11.00
11.00

32,648.81
66,880.50
29,991.50
30,101.50
7,667.00
27,043.50

Sub Total Screw Joint Pipe: DI

16,391.80

11.86

194,332.81

DI

210.00

8.46

1,776.60

Sub Total PVC Pipe: DI

210.00

8.46

1,776.60

1,178.00

48.00

56,544.00

EA
DI

5.00
24.00

190.00
260.00

950.00
6,240.00

DI
DI

30.00
2.00

15.00
56.00

450.00
112.00

DI
DI

11.00
16.00

26.00
380.00

286.00
6,080.00

DI
DI

1,411.00
598.00

25.00
25.00

35,275.00
14,950.00

Screw Joint Pipe


Screw Joint
Screw Joint Cast Iron
Screw Joint Carbon Steel
Screw Joint Carbon Steel
Screw Joint Cooper
Screw Joint Stainless Steel

PVC Pipe
Glass Fiber/PVC

Appurtenances
Appurtenaces Installation Multi Side Mounting Hose/Tube(W/
Connection)
Apputenaces installation Multi Side Mounting Sight Glass
Appurtenaces Installation Multi Side Mounting Safety(Eye)
Shower
Appurtenaces Installation Single Side Mounting pot
Appurtenaces Installation Single Side Mounting Injection
Nozzle
Appurtenaces Installation Single Side Mounting Silencer
Appurtenaces Installation Single Side Mounting Sampling
System
Appurtenaces Installation Single Side Mounting Strainer
Appurtenaces Installation Single Side Mounting Steam Trap

DI

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

40710
40720
40730
40740

40830
40840
40850

Description

Unit

40890
40900
40910
40920

40930
40940
40950

40960
40970
40980
40990

41000
41010
41020
41030

Rate

Amount

Sub Total Appurtenances: DI

3,275.00

36.91

120,887.00

DI
DI
DI
DI

19,007.40
220.80
252.00
7,333.00

25.00
23.00
25.00
38.00

475,185.00
5,078.40
6,300.00
278,654.00

Sub Total Bolt Up All Material: DI

26,813.20

28.54

765,217.40

Sub Total Piping Installation: DI

283,067.60

85.57

24,222,513.76

5.40
122.20

15,030.00
13,850.00

81,162.00
1,692,470.00

3.30

8,910.00

29,403.00

130.90

13,774.14

1,803,035.00

EA
EA
EA

31.00
12.00
18.00

140.00
140.00
1,640.00

4,340.00
1,680.00
29,520.00

Sub Total Fire Hydrant: ea

61.00

582.62

35,540.00

EA
EA
EA
EA

12.00
200.00
200.00
200.00

55.00
37.00
37.00
37.00

660.00
7,400.00
7,400.00
7,400.00

Sub Total Sprinkers: ea

612.00

37.35

22,860.00

EA
EA
EA

4.00
2.00
2.00

170.00
140.00
94.00

680.00
280.00
188.00

Sub Total Deluge Valves: ea

8.00

143.50

1,148.00

EA
EA
EA
EA

1.00
1.00
2.00
2.00

230.00
170.00
140.00
94.00

230.00
170.00
280.00
188.00

Sub Total Strainer Baskets: ea

6.00

144.67

868.00

EA
EA
EA
EA

120.00
12.00
40.00
6.00

120.00
240.00
120.00
240.00

14,400.00
2,880.00
4,800.00
1,440.00

Sub Total Extinguishers: ea

178.00

132.13

23,520.00

Bolt Up All Material


Bolting Up for Flange All Material
Bolting Up for Flange All Material
Bolting Up All Material
Bolting Up for Valve All Material

Pipe Supports
Spring hanger/Support Installation ALL Size
M/T
Fabrication & Installation of Piping Support - Carbon Steel with M/T
H.D.G (including U-bolts and clamps)
Fabrication & Installation of Piping Support - Stainless Steel
M/T
(including U-bolts and clamps)
Sub Total Pipe Supports: M/T

40860
40870
40880

Quantity

Fire Accessories
Fire Hydrant
FIRE HYDRANT (4 WAY)
FIRE HYDRANT WITH MONITOR (5 WAY)
FIRE HOSE RACK

Sprinkers
NOZZLE FOR MONITOR
WATER SPRAY NOZZLE
SPRINKLER PILOT HEAD
SPRINKLER HEAD(CLOSED TYPE)

Deluge Valves
DELUGE VALVE ASSEMBLY
DELUGE VALVE ASSEMBLY
DELUGE VALVE ASSEMBLY

Strainer Baskets
STRAINER(BASKET TYPE)
STRAINER(BASKET TYPE)
STRAINER(BASKET TYPE)
STRAINER(BASKET TYPE)

Extinguishers
PORTABLE DRY CHEMCIAL EXTINGUISHER (7.7 kg)
WHEELED DRY CHEMICAL EXTINGUISHER (56.7 kg)
PORTABLE CO2 EXTINGUISHER (6.9 kg)
WHEELED CO2 EXTINGUISHER (45.3 kg)

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Fire Accessories: LS

41040
41050

41060
41070

41080
41090
41100
41110
41120
41130

41160
41170
41180
41190
41200
41210
41220
41230
41240

41250

40750
40760
40770
40780
40790
40800
40810
40820

Quantity

Rate

Amount

1.00

83,936.00

83,936.00

EA
EA

65.00
65.00

58.00
58.00

3,770.00
3,770.00

Sub Total Steam Manifolds: ea

130.00

58.00

7,540.00

5,942.00
3,512.00

30.00
36.00

178,260.00
126,432.00

Sub Total Steam Tracing: LS

1.00

304,692.00

304,692.00

Sub Total Steam Accessories: LS

1.00

312,232.00

312,232.00

EA
EA
EA
EA
EA
EA

158.00
13.00
2.00
158.00
13.00
2.00

58.00
85.00
280.00
1,210.00
1,580.00
1,940.00

9,164.00
1,105.00
560.00
191,180.00
20,540.00
3,880.00

Sub Total PSV: LS

1.00

226,429.00

226,429.00

1,728.00
17,500.00
1,728.00
17,307.00
1,412.00
14,319.00
1,412.00
14,158.00
1,074.40

300.00
360.00
300.00
470.00
300.00
360.00
300.00
470.00
270.00

518,400.00
6,300,000.00
518,400.00
8,134,290.00
423,600.00
5,154,840.00
423,600.00
6,654,260.00
290,088.00

Sub Total Testing: LS

1.00

28,417,478.00

28,417,478.00

DI

5,103.10

130.00

663,403.00

Sub Total In Line Instruments: LS

1.00

663,403.00

663,403.00

5,060.00
35.00
12.00
2.00
3.00
7.00
50.00

18.00
300.00
140.00
458,370.00
1,710.00
1,130.00
34,400.00

91,080.00
10,500.00
1,680.00
916,740.00
5,130.00
7,910.00
1,720,000.00

300.00

160.00

48,000.00

Steam Accessories
Steam Manifolds
Installation of Steam Manifold, CM 8, 2"x1500 long
Installation of Steam Manifold, SM 8, 2"x1500 long

Steam Tracing
Steam tracing, 1/2", Tube, A269 GR. TP316/316L
Steam tracing, 1/2", Pre-insulated tube, A269 GR.
TP316/316L

PSV
PSV PSV Installation Up to ND2.1/2"
PSV PSV Installation ND5" ~ ND6"
PSV PSV Installation ND5" ~ ND6"
PSV PSV Popping Test Up to ND2.1/2"
PSV PSV Popping Test ND3" ~ ND4"
PSV PSV Popping Test ND5" ~ ND6"

Testing
NDT/PMI/Thick Test Field NDT Magnetic Test
NDT/PMI/Thick Test Field NDT PMI Test
NDT/PMI/Thick Test Field NDT Liquid Penetration Test
NDT/PMI/Thick Test Field NDT Radiographic Test
NDT/PMI/Thick Test Shop NDT Magnetic Test
NDT/PMI/Thick Test Shop NDT PMI Test
NDT/PMI/Thick Test Shop NDT Liquid Penetration Test
NDT/PMI/Thick Test Shop NDT Radiographic Test
Post Weld Heat Treatment (Included hardness test)

In Line Instruments
In-Line Instrument

Miscellaneous
Earth Bonding Lug Fabrication & Installation ALL Size
Post Indicator Valve
MONITOR
Fabrication & Installation of Temporary Silencer
Fabrication & Installation of Funnel
Fabrication & Installation of Bird Screen
Temp. piping for flushing, CW Passivation, Chemical cleaning
(including pipes, fittings, valves, supports, etc.)
Opening on grating for pipe and support Under 8" Refer to
information "Standard Drawing for Bldg & Strl Grating Detail.

M
M

Points
Points
Points
SHT
Points
Points
Points
SHT
DI

EA
EA
EA
EA
EA
EA
M/T
Points

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

50460
50470
50480
50490
50500
50510
50520
50530
50540
50550
50560
50570
50580
50590
50600
50610
50620
50630
50640
50650

50660
50670
50680
50690
50700
50710
50720
50730
50740

50750
50760
50770

Description

Unit

Quantity

Rate

Amount

Sub Total Miscellaneous: LS

1.00

2,801,040.00

2,801,040.00

Sub Total Above Ground Piping: LS

1.00

58,577,046.76

58,577,046.76

Sub Total Process Piping Work: LS

1.00

60,495,312.26

60,495,312.26

Ton
Ton
Ton
M3
M3
M3
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
M3
M3
Ton

35.00
26.00
28.00
55.00
17.60
16.50
2.50
0.04
6.00
0.04
6.00
0.02
2.49
56.00
54.00
0.13
0.54
48.00
37.00
0.15

3,110.00
3,240.00
3,150.00
2,040.00
2,040.00
2,040.00
3,560.00
28,080.00
2,380.00
28,110.00
2,380.00
50,990.00
4,420.00
5,340.00
4,860.00
6,400.00
3,850.00
2,040.00
2,040.00
9,390.00

108,850.00
84,240.00
88,200.00
112,200.00
35,904.00
33,660.00
8,900.00
1,123.20
14,280.00
1,124.40
14,280.00
1,019.80
11,005.80
299,040.00
262,440.00
832.00
2,079.00
97,920.00
75,480.00
1,399.11

Sub Total Columns: Ton

391.01

3,207.03

1,253,977.31

Ton

1.00

7,860.00

7,860.00

Ton

1.00

9,390.00

9,390.00

Ton

4.50

4,640.00

20,880.00

Ton

6.50

3,950.00

25,675.00

Ton

25.40

4,240.00

107,696.00

Ton

5.00

4,020.00

20,100.00

Ton

3.00

4,080.00

12,240.00

Ton

8.00

3,610.00

28,880.00

Ton

6.00

3,950.00

23,700.00

Sub Total Vacuum System: Ton

60.40

4,245.38

256,421.00

67.00
82.00
11.80

12,040.00
11,870.00
1,740.00

806,680.00
973,340.00
20,532.00

Mechanical Erection
Process Equipment Installation
Heating Cooling Drying Equipment
Columns
DRYING COLUMN
MEA COLUMN
DEA SPLITTER COLUMN
DRYING COLUMN
MEA COLUMN
DEA SPLITTER COLUMN
DEA SPLITTER COLUMN
DEA COLUMN
DEA COLUMN
TEA COLUMN
TEA COLUMN
MEA COLUMN
MEA COLUMN
DEA COLUMN
TEA COLUMN
DRYING COLUMN
DRYING COLUMN
DEA COLUMN
TEA COLUMN
DEA SPLITTER COLUMN

Vacuum System
DRYING COLUMN VACUUM SYSTEM
(Refer to informative document attached)
MEA COLUMN VACUUM SYSTEM
(Refer to informative document attached)
DEA SPLITTER VACUUM SYSTEM
(Refer to informative document attached)
DEA COLUMN VACUUM SYSTEM
(Refer to informative document attached)
TEA COLUMN VACUUM SYSTEM
(Refer to informative document attached)
REACTOR 120 VACUUM SYSTEM
(Refer to informative document attached)
POST TREATMENT VACUUM SYSTEM
(Refer to informative document attached)
REACTOR 220 VACUUM SYSTEM
(Refer to informative document attached)
REACTOR 320 VACUUM SYSTEM
(Refer to informative document attached)

Condenser
DEA COLUMN CONDENSER
TEA COLUMN CONDENSER
AMMONIA STRIPPER MAIN CONDENSER

Ton
Ton
Ton

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
50780
50790
50800
50810
50820
50830
50840
50850
50860
50870
50880

50000
50010
50020
50030
50040
50050
50060
50070
50080
50090
50100
50110
50120
50130
50140
50150

50160
50170
50180
50190
50200
50210
50220
50230
50240
50250
50260
50270
50280
50290
50300
50310
50320
50330
50340
50350
50360
50370
50380
50390

Description

Unit

AMMONIA STRIPPER AUXILIARY CONDENSER


DRYING COLUMN CONDENSER
MEA COLUMN CONDENSER
DEA SPLITTER COLUMN CONDENSER
ATMOSPHERIC STEAM CONDENSER
REACTOR 120 CONDENSER
POST TREATMENT CONDENSER
REACTOR 220 CONDENSER
REACTOR 320 CONDENSER
ATM STEAM CONDENSER
EFFLUENT CONDENSER

Quantity

Rate

Amount

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

15.00
20.80
23.00
28.00
4.50
1.50
1.40
1.40
1.10
1.20
1.30

2,350.00
3,710.00
3,520.00
2,380.00
2,340.00
3,850.00
3,450.00
3,450.00
3,940.00
3,940.00
3,450.00

35,250.00
77,168.00
80,960.00
66,640.00
10,530.00
5,775.00
4,830.00
4,830.00
4,334.00
4,728.00
4,485.00

Sub Total Condenser: Ton

260.00

8,077.24

2,100,082.00

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

0.20
0.20
0.20
0.20
4.00
0.20
0.60
0.60
2.10
0.20
0.60
0.60
2.00
0.20
1.90
0.50

18,750.00
18,750.00
18,750.00
18,750.00
2,340.00
8,950.00
3,370.00
3,370.00
3,220.00
11,260.00
4,200.00
4,200.00
1,130.00
7,670.00
3,220.00
5,650.00

3,750.00
3,750.00
3,750.00
3,750.00
9,360.00
1,790.00
2,022.00
2,022.00
6,762.00
2,252.00
2,520.00
2,520.00
2,260.00
1,534.00
6,118.00
2,825.00

Sub Total Heater: Ton

14.30

3,984.97

56,985.00

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

4.10
4.10
4.10
4.10
4.10
2.70
0.20
1.00
1.00
1.40
1.60
0.50
0.10
5.90
1.80
1.50
5.90
1.40
1.20
0.20
2.80
0.80
0.20
0.20

2,340.00
2,340.00
2,340.00
2,340.00
2,460.00
3,450.00
10,480.00
3,940.00
3,940.00
3,450.00
3,430.00
5,400.00
19,140.00
2,320.00
3,120.00
1,260.00
5,900.00
3,450.00
3,450.00
7,670.00
2,890.00
3,180.00
2,930.00
6,400.00

9,594.00
9,594.00
9,594.00
9,594.00
10,086.00
9,315.00
2,096.00
3,940.00
3,940.00
4,830.00
5,488.00
2,700.00
1,914.00
13,688.00
5,616.00
1,890.00
34,810.00
4,830.00
4,140.00
1,534.00
8,092.00
2,544.00
586.00
1,280.00

Sub Total Cooler: Ton

50.90

3,176.72

161,695.00

Heater
Utility Station Steam Desuperheater
MS DESUPERHEATER
MS DESUPERHEATER
LS DESUPERHEATER
AMMONIA STRIPPER PRE-HEATER
WASTE WATER HEATER
NP PREHEATER
FA PREHEATER
WATER CIRCULATION HEATER I
TEMPERED WATER HEATER I
DEG PREHEATER
SMO PREHEATER
WATER CIRCULATION HEATER II
TEMPERED WATER HEATER II
WATER CIRCULATION HEATER III
TEMPERED WATER HEATER III

Cooler
FIRST REACTOR INTERCOOLER
SECOND REACTOR INTERCOOLER
THIRD REACTOR INTERCOOLER
FOUTH REACTOR INTERCOOLER
FIFTH REACTOR INTERCOOLER
AMMONIA SOLUTION COOLER
RECYCLE WATER COOLER
MEA PRODUCT COOLER
AMINES RECYCLE COOLER
DEA PRODUCT COOLER
TEA PRODUCT COOLER
HEAVY AMINES COOLER
LEAN WATER COOLER
WATER CIRCULATION COOLER I
POST TREATMENT CIRCULATION COOLER
PRODUCT COOLER I
WATER CIRCULATION COOLER II
POLYSORBATE COOLER
PEGs COOLER
PEG 600 I COOLER
WATER CIRCULATION COOLER III
PRODUCT COOLER III
C-67920 COOLER
EFFLUENT COOLER

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

50400
50410
50420
50430
50440
50450

Description

Unit

Reboiler
AMMONIA STRIPPER REBOILER
DRYING COLUMN REBOILER
MEA COLUMN REBOILER
DEA SPLITTER COLUMN REBOILER
DEA COLUMN REBOILER
TEA COLUMN REBOILER

50920
50930
50940
50950
50960
50970

50980
50990
51000
51010
51020

51030
51040
51050

51060

51070

Rate

Amount

Ton
Ton
Ton
Ton
Ton
Ton

16.00
20.50
8.30
17.20
23.50
22.50

2,350.00
3,730.00
1,900.00
2,440.00
3,570.00
3,630.00

37,600.00
76,465.00
15,770.00
41,968.00
83,895.00
81,675.00

Sub Total Reboiler: Ton

108.00

3,123.82

337,373.00

1.00

4,166,533.31

4,166,533.31

Ton
Ton
Ton

6.10
6.00
2.50

2,320.00
5,900.00
2,890.00

14,152.00
35,400.00
7,225.00

Sub Total Exchanger: Ton

14.60

3,888.84

56,777.00

Ton
Ton
Ton
Ton
Ton
Ton

0.30
0.50
0.30
0.50
0.30
0.50

6,280.00
3,670.00
5,590.00
4,200.00
5,590.00
4,200.00

1,884.00
1,835.00
1,677.00
2,100.00
1,677.00
2,100.00

Sub Total Filter: Ton

2.40

4,697.08

11,273.00

Ton
Ton
Ton
Ton
Ton

0.10
0.10
0.10
0.10
0.10

23,430.00
23,430.00
23,430.00
23,430.00
23,430.00

2,343.00
2,343.00
2,343.00
2,343.00
2,343.00

Sub Total Eductor: Ton

0.50

23,430.00

11,715.00

Ton

11.00

127,390.00

1,401,290.00

Ton
Ton

0.10
0.10

23,430.00
23,430.00

2,343.00
2,343.00

Sub Total Compressor: Ton

11.20

125,533.57

1,405,976.00

Ton

9.40

1,820.00

17,108.00

Sub Total Receiver: Ton

9.40

1,820.00

17,108.00

Ton

15.00

9,610.00

144,150.00

1.00

144,150.00

144,150.00

Sub Total Heating Cooling Drying Equipment: LS

50890
50900
50910

Quantity

Gas & Liquid Handling Equipment


Gas Handling Equipment
Exchanger
REACTOR 120 EXCHANGER
REATOR 220 EXCHANGER
REACTOR 320 EXCHANGER

Filter
BASKET FILTER I
CARTRIDGE FILTER I
BASKET FILTER II
CARTRIDGE FILTER II
BASKET FILTER III
CARTRIDGE FILTER III

Eductor
STEAM EDUCTOR
STEAM EDUCTOR
STEAM EDUCTOR
STEAM EDUCTOR
STEAM EDUCTOR

Compressor
HP Nitrogen Compressor Package
(Refer to informative document attached)
5 Ton Geared Trolley with Chain Block
2 Ton Manual Geared Trolley Chain Hoist

Receiver
HP Nitrogen Compressor Discharge Receiver

Evaporator
EVAPORATOR
(Refer to informative document attached)

Sub Total Evaporator: LS

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

51080
51090
51100
51110

Description

Unit

Reactor
ETHANOLAMINES REACTORS
ETHOXYLATION I REACTOR
ETHOXYLATION II REACTOR
ETHOXYLATION III REACTOR

Rate

Amount

Ton
Ton
Ton
Ton

80.00
23.70
23.70
10.30

1,990.00
2,730.00
2,730.00
1,830.00

159,200.00
64,701.00
64,701.00
18,849.00

Sub Total Reactor: Ton

137.70

2,232.76

307,451.00

1.00

1,954,450.00

1,954,450.00

0.20
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
1.60
0.60
0.60
1.20
0.80
1.60
0.10
1.80
0.06
3.00
1.00
1.08
1.60
1.60
1.80
0.30
0.60
0.30
0.60
1.00
3.00
1.00
9.00
2.60
4.40
1.40
0.40
0.40
4.60
0.80
2.40
1.60
1.20
1.80
0.24

15,960.00
15,960.00
15,960.00
15,940.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00
6,400.00
9,080.00
9,080.00
9,590.00
9,590.00
4,260.00
15,960.00
3,630.00
22,330.00
6,400.00
10,600.00
9,590.00
9,590.00
9,590.00
15,960.00
23,430.00
23,430.00
23,430.00
23,430.00
14,070.00
9,390.00
15,560.00
9,390.00
13,680.00
9,390.00
13,680.00
22,210.00
23,430.00
9,390.00
15,560.00
14,070.00
14,070.00
13,300.00
14,070.00
23,430.00

3,192.00
4,788.00
4,788.00
4,782.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
4,788.00
10,240.00
5,448.00
5,448.00
11,508.00
7,672.00
6,816.00
1,596.00
6,534.00
1,339.80
19,200.00
10,600.00
10,357.20
15,344.00
15,344.00
28,728.00
7,029.00
14,058.00
7,029.00
14,058.00
14,070.00
28,170.00
15,560.00
84,510.00
35,568.00
41,316.00
19,152.00
8,884.00
9,372.00
43,194.00
12,448.00
33,768.00
22,512.00
15,960.00
25,326.00
5,623.20

Sub Total Gas Handling Equipment: LS

51120
51130
51140
51150
51160
51170
51180
51190
51200
51210
51220
51230
51240
51250
51260
51270
51280
51290
51300
51310
51320
51330
51340
51350
51360
51370
51380
51390
51400
51410
51420
51430
51440
51450
51460
51470
51480
51490
51500
51510
51520
51530
51540
51550
51560
51570
51580
51590

Quantity

Liquid Handling Equipment


Pumps
NP PROCESS FEED PUMP II
AE3EO TRANSFER PUMP
AE7EO TRANSFER PUMP
AE9EO TRANSFER PUMP
AE12EO TRANSFER PUMP
NP3EO TRANSFER PUMP
NP7EO TRANSFER PUMP
NP9EO TRANSFER PUMP
NP15EO/NP20EO TRANSFER PUMP
NP25EO/NP30EO TRANSFER PUMP
PEG 200 TRANSFER PUMP
PEG 400/ PEG 600 TRANSFER PUMP
PEG 1200/ PEG 1500 TRANSFER PUMP
CONDENSATE RETURN PUMP
CATALYST PUMP
NEUTRALIZER PUMP
SCRUBBER RECIRCULATION PUMP
ORGANIC BLOW DOWN PUMP
AQUEOUS EFFLUENT TRANSFER PUMP
20% NaOH Feed Pump
TK-67930 RECIRCULATION PUMP
ACID PUMP I
DELUGE WATER PUMP
Amines Storage Area PCS Sump Pump
MEA Loading Pumps
DEA Loading Pumps
TEA 99 Loading Pump
SANITARY PUMP (Including Startup Panel)
ETHOXYLATE DRUMMING PUMP
FA UNLOADING PUMP
NP UNLOADING PUMP
Eye Wash/Safety Shower Water Supply Pump
Ammonia Transfer Pumps
Deluge Water Pump - 1
Potentially Contaminated Surface Water Sump Pump - 1
EO FEED PUMPS
AMMONIA SOLUTION CIRCULATION PUMPS
AMMONIA SOLUTION FEED PUMPS
AMINES RERUN PUMP
RICH WATER HOT WELL PUMPS
LEAN WATER HOT WELL PUMPS
DRYING COLUMN BOTTOM PUMPS
CYCLE WATER PUMPS
MEA COLUMN BOTTOM PUMPS
MEA PRODUCT PUMPS
MEA TRANSFER PUMPS
DEA SPLITTER BOTTOM PUMPS
AMINES RECYCLE PUMPS

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
51600
51610
51620
51630
51640
51650
51660
51670
51680
51690
51700
51710
51720
51730
51740
51750
51760
51770
51780
51790
51800
51810
51820
51830
51840
51850
51860
51870
51880
51890
51900
51910
51920
51930
51940
51950
51960
51970

51980
51990

52000
52010
52020
52030
52040
52050
52060
52070
52080
52090

Description

Unit

DEA COLUMN BOTTOM PUMPS


DEA PRODUCT PUMPS
DEA TRANSFER PUMPS
TEA COLUMN BOTTOM PUMPS
TEA PRODUCT PUMPS
TEA TRANSFER PUMPS
TEA TOP COLUMN PURGE PUMP
HEAVIES TRANSFER PUMP
CONDENSATE RETURN PUMPS
COLD COOLING WATER BOOSTER PUMPS
WASTE WATER PUMPS
DELUGE WATER PUMP
BLOW DOWN DRUM PUMP
REACTOR 120 RECIRCULATION PUMP
WATER CIRCULATION PUMP I
POST TREATMENT CIRCULATION PUMP
EFFLUENT TRANSFER PUMP I
HOLDING VESSEL I TRANSFER PUMP
TEMPERED WATER RECIRCULATION PUMP I
REACTOR 220 RECIRCULATION PUMP
WATER CIRCULATION PUMP II
EFFLUENT TRANSFER PUMP II
POLYSORBATE TRANSFER PUMP
PEGS TRANSFER PUMP
PEG 600 I TRANSFER PUMP
TEMPERED WATER RECIRCULATION PUMP II
REACTOR 320 RECIRCULATION PUMP
WATER CIRCULATION PUMP III
HOLDING VESSEL III TRANSFER PUMP
TA UNLOADING PUMP
SMO UNLOADING PUMP
CAO UNLOADING PUMP
RAW MATERIAL BLOW DOWN PUMP
FA PROCESS FEED PUMP I
FA PROCESS FEED PUMP II
FA PROCESS FEED PUMP III
FA PROCESS FEED PUMP IV
NP PROCESS FEED PUMP I

Quantity

Rate

Amount

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

2.80
1.20
1.40
3.20
1.20
1.40
0.07
0.90
2.20
9.90
1.00
0.20
0.70
2.30
1.50
2.90
0.20
0.70
0.20
2.40
0.50
0.20
0.30
0.40
0.20
0.20
1.90
1.40
0.30
0.20
0.30
0.20
0.70
0.20
0.20
0.20
0.20
0.30

13,680.00
13,300.00
12,850.00
9,390.00
13,320.00
12,850.00
19,140.00
9,590.00
9,590.00
6,400.00
10,600.00
15,960.00
8,760.00
6,400.00
9,330.00
6,400.00
15,960.00
8,760.00
15,960.00
6,400.00
10,600.00
15,960.00
15,960.00
10,600.00
19,140.00
19,140.00
6,400.00
9,330.00
15,960.00
15,960.00
15,960.00
15,960.00
8,760.00
15,960.00
15,960.00
15,960.00
15,960.00
15,960.00

38,304.00
15,960.00
17,990.00
30,048.00
15,984.00
17,990.00
1,339.80
8,631.00
21,098.00
63,360.00
10,600.00
3,192.00
6,132.00
14,720.00
13,995.00
18,560.00
3,192.00
6,132.00
3,192.00
15,360.00
5,300.00
3,192.00
4,788.00
4,240.00
3,828.00
3,828.00
12,160.00
13,062.00
4,788.00
3,192.00
4,788.00
3,192.00
6,132.00
3,192.00
3,192.00
3,192.00
3,192.00
4,788.00

Sub Total Pumps: Ton

104.15

10,468.07

1,090,250.00

Ton
Ton

46.18
32.30

410.00
330.00

18,933.80
10,659.00

Sub Total Chemical Handling Equipment: Ton

78.48

377.07

29,592.80

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

0.10
0.10
0.10
0.10
0.10
0.10
1.00
0.10
0.20
0.20

28,110.00
28,110.00
28,110.00
28,110.00
28,110.00
28,110.00
9,390.00
23,430.00
27,530.00
18,750.00

2,811.00
2,811.00
2,811.00
2,811.00
2,811.00
2,811.00
9,390.00
2,343.00
5,506.00
3,750.00

Sub Total Mixer: Ton

2.10

18,026.19

37,855.00

Chemical Handling Equipment


Catalyst Initial Loading (to TK-67911)
Chemical Initial Filling (to TK-67912)

Mixer
STATIC MIXER
STATIC MIXER
STATIC MIXER
STATIC MIXER
STATIC MIXER
STATIC MIXER
REACTOR 120 STATIC MIXER
POST TREATMENT VESSEL STATIC MIXER
REACTOR 220 STATIC MIXER
REACTOR 320 STATIC MIXER

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Liquid Handling Equipment: LS

52100
52110
52120
52130
52140
52150
52160
52170
52180
52190
52200
52210
52220

52230
52240
52250
52260
52270
52280
52290
52300
52310
52320
52330
52340
52350

52360
52370
52380

52390
52400

52410
52420
52430
52440
52450
52460
52470
52480

Quantity

Rate

Amount

1.00

1,157,697.80

1,157,697.80

Ton

40.00

6,150.00

246,000.00

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
M3
M3

3.30
2.90
27.00
6.60
7.40
3.10
3.30
8.00
3.30
13.60
3.00
0.50

2,380.00
3,450.00
2,660.00
1,990.00
1,990.00
2,380.00
2,380.00
2,120.00
2,380.00
2,210.00
2,040.00
2,040.00

7,854.00
10,005.00
71,820.00
13,134.00
14,726.00
7,378.00
7,854.00
16,960.00
7,854.00
30,056.00
6,120.00
1,020.00

Sub Total Drum: Ton

122.00

3,612.96

440,781.00

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

2.00
7.10
12.00
0.80
2.00
12.00
12.00
12.00
0.70
1.60
8.40
13.40
4.50

3,450.00
1,990.00
1,810.00
4,710.00
3,450.00
1,970.00
1,970.00
1,970.00
5,900.00
3,850.00
1,820.00
2,210.00
2,370.00

6,900.00
14,129.00
21,720.00
3,768.00
6,900.00
23,640.00
23,640.00
23,640.00
4,130.00
6,160.00
15,288.00
29,614.00
10,665.00

Sub Total Vessels: Ton

88.50

2,149.08

190,194.00

Ton
Ton
Ton

2.30
2.20
1.80

3,450.00
3,450.00
3,850.00

7,935.00
7,590.00
6,930.00

Sub Total Hotwell: Ton

6.30

3,564.29

22,455.00

M3
M3

3.00
1.50

7,830.00
7,830.00

23,490.00
11,745.00

Sub Total Disposal System: LS

1.00

35,235.00

35,235.00

5.50
14.60
14.60
14.60
4.80
5.70
5.70
3.40

2,020.00
2,320.00
2,140.00
2,140.00
2,370.00
2,020.00
2,020.00
920.00

11,110.00
33,872.00
31,244.00
31,244.00
11,376.00
11,514.00
11,514.00
3,128.00

Gas Liquid Storage


Drum
DRUM FILLING PACKAGE FACILITY
(Refer to informative document attached)
ORGANIC DRAIN DRUM
EO SURGE DRUM
AMMONIA SOLUTION SURGE DRUM
LOW PRESSURE CONDENSATE FLASH DRUM
ATMOSPHERIC CONDENSATE FLASH DRUM
BLOWDOWN DRUM
RAW MATERIAL BLOW DOWN DRUM
DRUM FOR C-67920
ORGANIC BLOW DOWN DRUM
AQUEOUS EFLUENT BLOW DOWN DRUM
LOW PRESSURE CONDENSATE FLASH DRUM
ATMOSPHERIC CONDENSATE FLASH DRUM

Vessels
WATER EXPANSION VESSEL I
POST TREATMENT VESSEL
HOLDING VESSEL I
KNOCK DOWN VESSEL II
WATER EXPANSION VESSEL II
POLYSORBATE HOLDING VESSEL
PEGS HOLDING VESSEL
PEG 600 I HOLDING VESSEL
KNOCK DOWN VESSEL III
WATER EXPANSION VESSEL III
HOLDING VESSEL III
ATM FLASH
VESSEL
HIGH PRESSURE NITROGEN VESSEL

Hotwell
HOT WELL I
HOT WELL II
EJECTORS HOT WELL

Disposal System
Lube Oil Charge & Flushing & Disposal
Seal Oil Charge & Flushing & Disposal

Tanks
RECYCLE WATER TANK
MEA DAY TANKS
DEA DAY TANKS
TEA DAY TANKS
HEAVIES DAY TANK
CATALYST TANK
NEUTRALIZER TANK
Eye Wash/Safety Shower Water Storage Tank

Ton
Ton
Ton
Ton
Ton
Ton
Ton
Ton

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
52490
52500

52510
52520
52530
52540
52550
52560
52570

Description

Unit

AQUEOUS EFFLUENT NEUTRALIZATION TANK


ACID TANK

3,430.00
5,640.00

7,546.00
1,974.00

Sub Total Tanks: Ton

71.45

2,162.66

154,522.00

Sub Total Gas Liquid Storage: LS

1.00

843,187.00

843,187.00

Sub Total Gas & Liquid Handling Equipment: LS

1.00

3,955,334.80

3,955,334.80

4.30
2.90
0.01
0.04
0.04
1.00
2.70

2,280.00
2,370.00
90,790.00
19,140.00
19,140.00
2,040.00
2,040.00

9,804.00
6,873.00
726.32
765.60
765.60
2,040.00
5,508.00

1.00

26,482.52

26,482.52

4.30
4.00
0.54

2,340.00
2,040.00
3,850.00

10,062.00
8,160.00
2,079.00

1.00

20,301.00

20,301.00

Ton
Ton
Ton

20.00
1.50
0.18

3,770.00
9,500.00
9,380.00

75,400.00
14,231.00
1,688.40

Sub Total Stripper: Ton

21.68

4,212.54

91,319.40

1.00

138,102.92

138,102.92

Ton
Ton
Ton
Ton
Ton

0.10
0.10
0.10
1.10
0.10

23,430.00
23,430.00
23,430.00
4,710.00
23,430.00

2,343.00
2,343.00
2,343.00
5,181.00
2,343.00

Sub Total Pot: Ton

1.50

9,702.00

14,553.00

Ton

1.00

9,390.00

9,390.00

1.00

9,390.00

9,390.00

Ton

25.00

1,910.00

47,750.00

Ton

3.40

300.00

1,020.00

Pollution Control Equipment


Scrubber
EO SCRUBBER
EO CAUSTIC SCRUBBER
EO SCRUBBER
EO CAUSTIC SCRUBBER
EO CAUSTIC SCRUBBER
EO SCRUBBER
EO CAUSTIC SCRUBBER

Ton
Ton
Ton
Ton
Ton
M3
M3

Absorber
AMMONIA ABSORBER
AMMONIA ABSORBER
AMMONIA ABSORBER

Ton
M3
Ton

Stripper
AMMONIA STRIPPER
AMMONIA STRIPPER
AMMONIA STRIPPER

Sub Total Pollution Control Equipment: LS

52700
52710
52720
52730
52740

52640

Other Equipment
Pot
CORROSION INHIBITOR POT
CORROSION INHIBITOR POT
CORROSION INHIBITOR POT
KNOCK OUT POT
SEAL POT FOR TK-66911

Ejector
EJECTOR

Sub Total Ejector: LS

52650
52660

Amount

2.20
0.35

Sub Total Absorber: LS

52610
52620
52630

Rate

Ton
Ton

Sub Total Scrubber: LS

52580
52590
52600

Quantity

Other
WEIGHING BRIDGES
(Refer to informative document attached)
Eye Wash/Safety Shower Chiller Package
(Refer to informative document attached)

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
52670
52680
52690

52750

52760
52770

52780

60000
60010
60020
60030
60040
60050

60060
60070
60080
60090
60100
60110
60120
60130
60140

Description

Unit

Ammonia Vapour Recovery Package


(Refer to informative document attached)
Safety valve poping test for rotating and package item at the
site
UV STERILIZER

Rate

Amount

Ton

16.00

6,620.00

105,920.00

EA

51.00

940.00

47,940.00

Ton

0.20

9,390.00

1,878.00

Sub Total Other : LS

1.00

204,508.00

204,508.00

Sub Total Other Equipment: LS

1.00

228,451.00

228,451.00

120.00

6,270.00

752,400.00

Sub Total Miscellaneous Metal: LS

1.00

752,400.00

752,400.00

M3
M3

42.00
2.00

2,230.00
2,680.00

93,660.00
5,360.00

Sub Total Grouting: m3

44.00

2,250.45

99,020.00

Sub Total Process Equipment Installation: ton

1,800.00

5,188.80

9,339,842.03

LS

1.00

2,110,050.00

2,110,050.00

Sub Total HVAC & Plumbing: LS

1.00

2,110,050.00

2,110,050.00

Sub Total Mechanical Erection: LS

1.00

11,449,892.03

11,449,892.03

EA
EA
EA
EA
EA
EA

320.00
120.00
180.00
91.00
10.00
37.00

150.00
170.00
730.00
710.00
700.00
1,410.00

48,000.00
20,400.00
131,400.00
64,610.00
7,000.00
52,170.00

Sub Total Lighting Fixtures: ea

758.00

426.89

323,580.00

4.00
8.00
10.00
2.00
5.00
1.00
1.00
3.00
7.00

240.00
240.00
200.00
680.00
680.00
680.00
570.00
570.00
680.00

960.00
1,920.00
2,000.00
1,360.00
3,400.00
680.00
570.00
1,710.00
4,760.00

41.00

423.41

17,360.00

438.00

49.00

21,462.00

Miscellaneous Metal
PLATFORM & LADDER

Ton

Grouting
Non-Shrink Grout
Epoxy Grout

HVAC & Plumbing


HVAC & PLUMBING WORKS

Electrical Systems
Lighting System
Lighting Fixtures
LIGHTING FIXTURE
EMER/STAND-BY LIGHTING FIXTURE
LIGHTING FIXTURE2/36W
LIGHTING FIXTURE4/36W
LIGHTING FIXTURE13W
EXIT LIGHT10W

Lighting Panels
PANEL BOARD( 30 )CKT
PANEL BOARD( 24 )CKT
PANEL BOARD( 24 )CKT
LIGHTING PANELBOARD ( 30 )CKT
RECEPTACLE PANEL ( 30 )CKT
LIGHTING PANELBOARD ( 30 )CKT
RECEPTACLE PANEL BOARD( 12 )CKT
RECEPTACLE PANEL ( 12 )CKT
LIGHTING PANELBOARD ( 30 )CKT

SET
SET
SET
SET
SET
SET
SET
SET
SET

Sub Total Lighting Panels: Set

60150

Quantity

Lighting Junction Boxes


JUNCTION BOX WITH COVER AND GASKETCAST
IRON3/4"

EA

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

60160

JUNCTION BOX WITH COVER AND GASKETCAST IRON1" EA

101.00

52.00

5,252.00

60170
60180
60190
60200
60210

JUNCTION BOX WITH COVER AND GASKET3/4"


JUNCTION BOX WITH COVER AND GASKET1"
4" SQUARE BOXZINC ELECTRO PLATE
3"X2" SQUARE BOXFOR OUTLET ZINC ELECTRO PLATE
3"X2" SQUARE BOX FOR SWITCHZINC ELECTRO
PLATE1 GANG
4" SQUARE BOX FOR SWITCHZINC ELECTRO PLATE
BUSHING & LOCK NUT FOR SQUARE BOX3/4"

EA
EA
EA
EA
EA

438.00
101.00
669.00
72.00
16.00

49.00
52.00
49.00
38.00
38.00

21,462.00
5,252.00
32,781.00
2,736.00
608.00

EA
EA

45.00
833.00

49.00
15.00

2,205.00
12,495.00

Sub Total Lighting Junction Boxes: ea

2,713.00

38.43

104,253.00

m
m
m
m

836.00
26,493.00
2,946.00
164.00

13.00
16.00
13.00
13.00

10,868.00
423,888.00
38,298.00
2,132.00

Sub Total Lighting Cable: m

30,439.00

15.61

475,186.00

EA
EA
EA
EA

1,633.00
126.00
1,302.00
81.00

5.07
5.07
5.07
5.07

8,279.31
638.82
6,601.14
410.67

Sub Total Cable Gland: ea

3,142.00

5.07

15,929.94

16,597.00

180.00

2,987,460.00

Sub Total Lighting Wire: m

16,597.00

180.00

2,987,460.00

1.00

3,478,575.94

3,478,575.94

2,724.00

34.00

92,616.00

m
m

3,433.00
256.00

43.00
54.00

147,619.00
13,824.00

342.00

63.00

21,546.00

Sub Total Rigid Steel Conduit: m

6,755.00

40.80

275,605.00

60370
60380

PVC Conduit
PVC CONDUITSCHEDULE 40 WITH RED CONCRETE3/4" m
PVC CONDUITSCHEDULE 40 WITH RED CONCRETE1-1/4" m

1,928.00
12,836.00

0.00
22.00

0.00
282,392.00

60390

PVC CONDUITSCHEDULE 40 WITH RED CONCRETE2-1/2" m

299.00

42.00

12,558.00

Sub Total PVC Conduit: m

15,063.00

19.58

294,950.00

134.00

490.00

65,660.00

60220
60230

60240
60250
60260
60270

60280
60290
60300
60310

60320

Lighting Cabling
Lighting Cable
LIGHTING CABLE5/C * 6mm2
LIGHTING CABLE3/C * 6mm2
LIGHTING CABLE5/C * 10mm2
LIGHTING CABLE4/C * 6mm2

Cable Gland
CABLE GLANDWEATHER PROOF TYPE3/4"
CABLE GLANDWEATHER PROOF TYPE1"
CABLE GLANDEXPLOSION PROOF TYPE3/4"
CABLE GLANDEXPLOSION PROOF TYPE1"

Lighting Wire
LIGHTING WIRE4mm2

Sub Total Lighting Cabling: LS

60330
60340
60350
60360

60400

Lighting Conduit
Rigid Steel Conduit
RIGID STEEL CONDUIT HOT DIP GALVANIZED3/4" (22mm) m
RIGID STEEL CONDUIT HOT DIP GALVANIZED1" (28mm)
RIGID STEEL CONDUIT HOT DIP GALVANIZED1-1/4"
(36mm)
RIGID STEEL CONDUIT HOT DIP GALVANIZED1-1/2"

Conduit Fittings
FLEXIBLE CONDUITLIQUID TIGHT 3/4"

EA

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Conduit Fittings: LS

60410
60420
60430
60440
60450
60460
60470
60480
60490
60500
60510
60520

60530
60540
60550
60560

60570

60580
60590
60600
60610
60620
60630
60640
60650

60660
60670
60680
60690
60700
60710
60720
60730
60740

Quantity

Rate

Amount

1.00

65,660.00

65,660.00

EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA

206.00
1,354.00
186.00
922.00
1,905.00
2.00
2.00
197.00
1,905.00
2.00
2.00
197.00

26.00
29.00
35.00
38.00
84.00
94.00
100.00
110.00
8.76
8.76
8.76
8.76

5,356.00
39,266.00
6,510.00
35,036.00
160,020.00
188.00
200.00
21,670.00
16,687.80
17.52
17.52
1,725.72

Sub Total Conduit Clamps: ea

6,880.00

41.67

286,694.56

Sub Total Lighting Conduit: LS

1.00

922,909.56

922,909.56

m
m
m
m

4,957.00
966.00
2,479.00
483.00

19.00
20.00
19.00
90.00

94,183.00
19,320.00
47,101.00
43,470.00

Sub Total Lighting Cable Tray: m

8,885.00

22.97

204,074.00

200.00

31.00

6,200.00

Sub Total Lighting Raceway: m

200.00

31.00

6,200.00

EA
EA
EA
EA
EA
EA
EA
EA

1,735.00
412.00
158.00
2,479.00
483.00
1,735.00
412.00
158.00

68.00
71.00
73.00
6.70
6.70
17.00
17.00
17.00

117,980.00
29,252.00
11,534.00
16,609.30
3,236.10
29,495.00
7,004.00
2,686.00

Sub Total Cover Clamps: ea

7,572.00

28.76

217,796.40

Sub Total Lighting Cable Tray: LS

1.00

428,070.40

428,070.40

564.00

75.00

42,300.00

EA
m3
SET
SET
SET
SET
SET
SET

0.00
829.00
42.00
0.00
42.00
0.00
74.00
0.00

0.00
67.00
190.00
0.00
160.00
0.00
79.00
0.00

0.00
55,543.00
7,980.00
0.00
6,720.00
0.00
5,846.00
0.00

Conduit Clamps
CONDUIT CLAMP UNISTRUT TYPE3/4"
CONDUIT CLAMP UNISTRUT TYPE 1"
CONDUIT CLAMP UNISTRUT TYPE 1-1/4"
CONDUIT CLAMP UNISTRUT TYPE 1-1/2"
CONDUIT CLAMPUNISTRUT TYPE3/4"
CONDUIT CLAMPUNISTRUT TYPE1"
CONDUIT CLAMPUNISTRUT TYPE1-1/4"
CONDUIT CLAMPUNISTRUT TYPE1-1/2"
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1-1/4"
CONDUIT CLAMP 1-1/2"

Lighting Cable Tray


Lighting Cable Tray
PERFORATED CABLE TRAY50 X 50
PERFORATED CABLE TRAY100 X 50
PERFORATED CABLE TRAY50mm
PERFORATED CABLE TRAY100mm

Lighting Raceway
RACE WAY100x50x2.6t

Cover Clamps
COVER CLAMP FOR PERFORATED CABLE TRAY50mm
COVER CLAMP FOR PERFORATED CABLE TRAY100mm
COVER CLAMP FOR PERFORATED CABLE TRAY150mm
COVER CLAMP FOR PERFORATED CABLE TRAY50mm
COVER CLAMP FOR PERFORATED CABLE TRAY100mm
COVER CLAMP 50mm
COVER CLAMP 100mm
COVER CLAMP 150mm

Lighting Support
UNISTRUT CHANNELHOT DIP GALVANIZED STEEL 41 x
41 x 2.6t
SUPPORT FOR JUNCTION BOX
EXCAVATION & BACK FILL WORK
SUPPORT FOR LIGHTING TRANSFORMER
SUPPORT FOR LIGHTING TRANSFORMER
SUPPORT FOR LIGHTING/RECEPTACLE PANEL
SUPPORT FOR LIGHTING/RECEPTACLE PANEL
SUPPORT FOR RECEPTACLE
SUPPORT FOR RECEPTACLE

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
60750
60760
60770
60780
60790
60800
60810
60820
60830
60840
60850
60860
60870

Description

Unit

LIGHTING FIXTURE SUPPORT


LIGHTING FIXTURE SUPPORT
SUPPORT FOR JUNCTION BOX
PERFORATED TRAY SUPPORT
ANCHOR BOLT STAINLESS STEEL
MISCELLANEOUS FOR LIGHTING SYSTEM
SHANK BOLT AND NUT FOR PERFORATED CABLE
TRAYSTAINLESS STEEL
STAINLESS SHANK BOLT & NUT
HANGER FITTING FOR RACE WAY110x85x2.6t
THREAD STILL ROD FOR HANGER FITTING3/8"
STRONG ANCHOR NON DRILLING, STAINLESS
STEEL3/8"
UNISTRUT CHANNEL FOR RACE WAY SUPPORT41 X 41 X
2.6t
SHANK BOLT

60920
60930
60940
60950

60960
60970
60980
60990

61000
61010
61020
61030

Rate

Amount

SET
SET
EA
SET
EA
LOT
SET

570.00
0.00
633.00
2,962.00
240.00
1.00
13,777.00

110.00
0.00
87.00
230.00
37.00
122,210.00
17.00

62,700.00
0.00
55,071.00
681,260.00
8,880.00
122,210.00
234,209.00

EA
M
EA
EA

17,769.00
40.00
200.00
200.00

1.52
33.00
38.00
59.00

27,008.88
1,320.00
7,600.00
11,800.00

EA

200.00

70.00

14,000.00

13,777.00

8.76

120,686.52

1.00

1,465,134.40

1,465,134.40

EA
EA
EA
EA

62.00
20.00
34.00
40.00

57.00
55.00
31.00
31.00

3,534.00
1,100.00
1,054.00
1,240.00

Sub Total Lighting Receptacles: ea

156.00

44.41

6,928.00

EA
EA
EA
EA

81.00
20.00
50.00
54.00

0.00
77.00
30.00
29.00

0.00
1,540.00
1,500.00
1,566.00

Sub Total Light Switches: ea

205.00

22.47

4,606.00

Sub Total Lighting Devices: LS

1.00

11,534.00

11,534.00

EA
EA
EA
EA

37.00
1.00
222.00
153.00

6,180.00
5,950.00
2,240.00
1,790.00

228,660.00
5,950.00
497,280.00
273,870.00

Sub Total Light Poles: ea

413.00

2,435.25

1,005,760.00

Sub Total Lighting System: LS

1.00

7,757,177.30

7,757,177.30

EA
EA
EA
EA

14.00
20.00
77.00
23.00

48.00
39.00
48.00
48.00

672.00
780.00
3,696.00
1,104.00

Sub Total Control Switches: ea

134.00

46.66

6,252.00

SET

Sub Total Lighting Support: LS

60880
60890
60900
60910

Quantity

Lighting Devices
Lighting Receptacles
CONVENIENCE RECEPTACLE
CONVENIENCE RECEPTACLE
CONVENIENCE RECEPTACLEOUTDOOR
CONVENIENCE RECEPTACLEOUTDOOR

Light Switches
TUMBLER SWITCHGENERAL PURPOSE
TUMBLER SWITCHGENERAL
TUMBLER SWITCHINDUSTRIAL
TUMBLER SWITCHOUTDOOR

Light Poles
LIGHTING POLE FOR STREET LIGHTING
LIGHTING POLE FOR FLOOD LIGHTING
LIGHTING POLE FOR STANCHION MTD FIXTURE
LIGHTING POLE FOR STANCHION MTD FIXTURE

Power Generation System


Power Generatioin Equipment
Switches
Control Switches
Control SwitchON - OFF W/SEL. SW
Control SwitchON - OFF W/SEL. SW, AMMETER
Control SwitchON - OFF W/SEL. SW
CONTROL SWITCH STATION ON - OFF W/SEL. SW,
AMMETER

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

61040
61050
61060
61070
61080

61090
61100

61110
61120
61130
61140
61150

Description

Unit

Safety Switches
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 16AF
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 32AF
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 100AF
SAFETY SWITCH 3 PH, ( 480 )V, (60)HZ, SIZE : 500AF
SAFETY SWITCH3 PH, ( 480 )V, (60)HZ, SIZE : 150AF

61220
61230
61240
61250

61270
61280

Amount

63.00
4.00
7.00
2.00
1.00

93.00
93.00
93.00
190.00
370.00

5,859.00
372.00
651.00
380.00
370.00

Sub Total Safety Switches: ea

77.00

99.12

7,632.00

Sub Total Switches: LS

1.00

13,884.00

13,884.00

EA

12.00

74.00

888.00

EA

5.00

180.00

900.00

Sub Total Welding Receptacle: ea

17.00

105.18

1,788.00

2.00
2.00
2.00
2.00
1.00

940.00
940.00
940.00
940.00
940.00

1,880.00
1,880.00
1,880.00
1,880.00
940.00

9.00

940.00

8,460.00

1.00
1.00
1.00
1.00
1.00
1.00

430.00
460.00
170.00
170.00
260.00
260.00

430.00
460.00
170.00
170.00
260.00
260.00

Sub Total Dry Type Transformer: Set

6.00

291.67

1,750.00

Sub Total Transformers: LS

1.00

10,210.00

10,210.00

2.00
2.00
2.00
1.00

680.00
590.00
590.00
1,270.00

1,360.00
1,180.00
1,180.00
1,270.00

7.00

712.86

4,990.00

PNL

18.00

1,370.00

24,660.00

PNL

18.00

1,370.00

24,660.00

PNL

11.00

1,480.00

16,280.00

Welding Receptacle
WELDING RECEPTACLE3 PH, ( 480 )V, (60)HZ, 3P + 1E.
WEATHER PROOF
WELDING RECEPTACLE3 PH, ( 480 )V, (60)HZ, 3P + 1E.
CLASS I,ZONE 2 IIC T4

Transformers
Power Transformer
Power Transformer 2000/2300kVA
Power Transformer2000/2300kVA
Power Transformer2000/2300kVA
Power Transformer2000/2300kVA
Power Transformer2000/2300kVA

SET
SET
SET
SET
SET

Dry Type Transformer


Dry Type Transformer90KVA
Dry Type Transformer100KVA
Dry Type Transformer30KVA
Dry Type Transformer: 30KVA
Dry Type Transformer50KVA
Dry Type Transformer50KVA

SET
SET
SET
SET
SET
SET

Power Systems
Power Capacitor
Power Capacitor225 KVA
Power Capacitor 180KVAR
Power Capacitor300KVAR
Power Capacitor( 600 )KVAR

SET
SET
SET
SET
Sub Total Power Capacitor: Set

61260

Rate

EA
EA
EA
EA
EA

Sub Total Power Transformer: ea

61160
61170
61180
61190
61200
61210

Quantity

Switchgear & MCC


L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC
L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC
L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80
)kA/(1)SEC

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
61290

61300

Description

Unit

L.V. SwitchGear & MCC3 PH,( 0.48 )V,(60)HZ, ( 80


)kA/(1)SEC

61340

1,270.00

16,510.00

Sub Total Switchgear & MCC: PNL

60.00

1,368.50

82,110.00

SET

1.00

1,040.00

1,040.00

1.00

1,040.00

1,040.00

1.00
1.00
1.00

1,220.00
1,220.00
1,220.00

1,220.00
1,220.00
1,220.00

Sub Total UPS & Battery : Set

3.00

1,220.00

3,660.00

Sub Total Power Systems: LS

1.00

91,800.00

91,800.00

3.00

86.00

258.00

1.00

258.00

258.00

1.00

220.00

220.00

1.00

220.00

220.00

PNL

2.00

430.00

860.00

PNL

1.00

430.00

430.00

PNL

1.00

430.00

430.00

PNL

2.00

430.00

860.00

PNL

2.00

430.00

860.00

PNL

1.00

430.00

430.00

Sub Total L.V. Main Distribution Panel: PNL

9.00

430.00

3,870.00

1.00
1.00
1.00

10,230.00
2,870.00
3,750.00

10,230.00
2,870.00
3,750.00

3.00

5,616.67

16,850.00

1.00

300.00

300.00

1.00

300.00

300.00

Battery Charger & Battery


Battery Charger & Battery

UPS & Battery


UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (10)KVA
UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (80)KVA
UPS & BATTERY( 1)PH, AC( 120)V, (60)HZ, (100)KVA

Panels
Interposing Relay Panel
INTERPOSING RELAY AND MARSHALLING PANELSIZE :
800W X 800D X 2350H X 3PNLS

SET
SET
SET

SET

Signal Concentrator Panel


SIGNAL CONCENTRATOR PANELW1600 x D600 x H1800 x SET
1PNL
Sub Total Signal Concentrator Panel: LS

61360
61370
61380
61390
61400
61410

61420
61430
61440

L.V. Main Distribution Panel


L.V. Main Distribution Panel3 PH,( 4 )W, ( 208-120 )V,60HZ,(
20 )kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 4 )W, ( 480-277 )V,60HZ,(
80 )kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80
)kA, ( 1)SEC
L.V. Main Distribution Panel 3 PH,( 3 )W, ( 480 )V,60HZ,( 80
)kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 3 )W, ( 480 )V,60HZ,( 80
)kA, ( 1)SEC
L.V. Main Distribution Panel3 PH,( 3 )W,
( 480 )V,60HZ,( 80 )kA, ( 1)SEC

VSD Panel
VSD Panel 3 PH, ( 0.48 )KV, 60HZ,
VSD Panel 3 PH, ( 0.48 )KV, 60HZ,
VSD Panel 3 PH, ( 0.48 )KV, 60HZ,

SET
SET
SET
Sub Total VSD Panel: Set

61450

Amount

13.00

Sub Total Interposing Relay Panel: LS

61350

Rate

PNL

Sub Total Battery Charger & Battery: LS

61310
61320
61330

Quantity

Annunciator Panel
ANNUNCIATOR PANEL BOARDSIZE : W800 x D800 x
H2100 x 1PNL

SET

Sub Total Annunciator Panel: LS

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Panels: LS

61460
61470
61480
61490
61500
61510

61520
61530
61540
61550
61560
61570
61580
61590

61600
61610
61620
61630
61640
61650
61660
61670
61680
61690
61700
61710
61720
61730
61740
61750
61760
61770
61780

Rate

Amount

1.00

21,498.00

21,498.00

11.00
5.00
1.00
1.00
3.00
4.00

69.00
69.00
69.00
69.00
69.00
69.00

759.00
345.00
69.00
69.00
207.00
276.00

Sub Total Power Junction Box: Set

25.00

69.00

1,725.00

Sub Total Power Generatioin Equipment: LS

1.00

140,905.00

140,905.00

EA
EA
EA
EA
EA
EA
EA
EA

2.00
31.00
56.00
79.00
102.00
17.00
17.00
81.00

8.45
8.45
8.45
8.45
8.45
8.45
8.45
8.45

16.90
261.95
473.20
667.55
861.90
143.65
143.65
684.45

Sub Total Multi Cable Transit: ea

385.00

8.45

3,253.25

366.00
42.00
74.00
106.00
72.00
36.00
36.00
92.00
70.00
26.00
30.00
90.00
10.00
80.00
10.00
12.00
10.00
326.00
50.00

310.00
310.00
310.00
310.00
500.00
500.00
2,600.00
2,600.00
2,560.00
2,560.00
2,560.00
2,560.00
390.00
390.00
390.00
2,620.00
3,290.00
7.86
19.00

113,460.00
13,020.00
22,940.00
32,860.00
36,000.00
18,000.00
93,600.00
239,200.00
179,200.00
66,560.00
76,800.00
230,400.00
3,900.00
31,200.00
3,900.00
31,440.00
32,900.00
2,562.36
950.00

1,538.00

799.02

1,228,892.36

140.00
116.00
64.00
28.00
10.00
26.00

7.78
8.69
9.38
7.59
91.00
7.59

1,089.20
1,008.04
600.32
212.52
910.00
197.34

Power Junction Box


POWER JUNCTION BOX610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
POWER JUNCTION BOX610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D
POWER JUNCTION BOX 610W X 610H X 203D

Power Generation Cabling


Multi Cable Transit
MULTI CABLE TRANSIT RM 90
MULTI CABLE TRANSIT RM 60
MULTI CABLE TRANSIT RM 40
MULTI CABLE TRANSIT RM 30
MULTI CABLE TRANSIT RM 20
MULTI CABLE TRANSIT ROX SF SINGLE FRAME SF-6x1
MULTI CABLE TRANSIT ROX WEDGE 120 mm
MULTI CABLE TRANSIT

LV Power Termination Point


POWER TERMINATION POINT
LV POWER TERMINATION POINT 3/C 4mm2
LV POWER TERMINATION POINT 3/C 6mm2
LV POWER TERMINATION POINT 3/C 10mm2
LV POWER TERMINATION POINT 3/C 16mm2
LV POWER TERMINATION POINT 3/C 25mm2
LV POWER TERMINATION POINT 3/C 35mm2
LV POWER TERMINATION POINT 3/C 50mm2
LV POWER TERMINATION POINT 3/C 70mm2
LV POWER TERMINATION POINT 3/C 95mm2
LV POWER TERMINATION POINT 3/C 120mm2
LV POWER TERMINATION POINT 3/C 150mm2
LV POWER TERMINATION POINT 3/C 185mm2
LV POWER TERMINATION POINT 4/C 6mm2
LV POWER TERMINATION POINT 4/C 10mm2
LV POWER TERMINATION POINT 4/C 16mm2
LV POWER TERMINATION POINT 4/C 50+25mm2
LV POWER TERMINATION POINT 4/C 150+70mm2
LV POWER TERMINATION POINT 12/C 2.5mm2
LV POWER TERMINATION POINT 19/C 2.5mm2

SET
SET
SET
SET
SET
SET

SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET

Sub Total POWER TERMINATION POINT: Set

61790
61800
61810
61820
61830
61840

Quantity

CONTROL TERMINATION POINT


LV CONTROL TERMINATION POINT 3/C 2.5mm2
LV CONTROL TERMINATION POINT 5/C 2.5mm2
LV CONTROL TERMINATION POINT 7/C 2.5mm2
LV CONTROL TERMINATION POINT 2P 0.75mm2
LV CONTROL TERMINATION POINT 24/P 1.00mm2
LV CONTROL TERMINATION POINT 2T 1.0mm2

SET
SET
SET
SET
SET
SET

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
61850
61860
61870
61880
61890
61900
61910
61920
61930
61940
61950
61960

61970
61980
61990
62000

62010
62020
62030
62040
62050
62060
62070
62080
62090
62100
62110
62120
62130
62140
62150

62160
62170
62180
62190
62200
62210
62220
62230
62240
62250
62260
62270
62280
62290

Description
LV CONTROL TERMINATION POINT 1/C 35mm2
LV CONTROL TERMINATION POINT 1/C 70mm2
LV CONTROL TERMINATION POINT 1/C 95mm2
LV CONTROL TERMINATION POINT 1/C 120mm2
LV CONTROL TERMINATION POINT 2/C 4mm2
LV CONTROL TERMINATION POINT 2/C 6mm2
LV CONTROL TERMINATION POINT 2/C 10mm2
LV CONTROL TERMINATION POINT 2/C 16mm2
LV CONTROL TERMINATION POINT 2/C 25mm2
LV CONTROL TERMINATION POINT 8P 1.0mm2
LV CONTROL TERMINATION POINT 9/C 2.5mm2
LV CONTROL TERMINATION POINT 4/C 4mm2

Unit

Rate

Amount

4.00
16.00
4.00
18.00
138.00
40.00
42.00
20.00
8.00
28.00
6.00
4.00

21.00
27.00
35.00
61.00
4.02
5.71
7.52
11.00
190.00
30.00
11.00
8.29

84.00
432.00
140.00
1,098.00
554.76
228.40
315.84
220.00
1,520.00
840.00
66.00
33.16

Sub Total CONTROL TERMINATION POINT: Set

712.00

13.41

9,549.58

Sub Total LV Power Termination Point: Set

2,250.00

550.42

1,238,441.94

EA
EA
EA
EA

25.00
91.00
36.00
5.00

310.00
370.00
2,560.00
4,270.00

7,750.00
33,670.00
92,160.00
21,350.00

Sub Total Motor Connections kit: ea

157.00

986.82

154,930.00

EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA

118.00
1,139.00
5,759.00
1,460.00
259.00
658.00
435.00
261.00
129.00
143.00
322.00
234.00
118.00
110.00
271.00

1.71
1.71
1.71
2.21
3.23
5.68
7.80
7.80
16.00
18.00
21.00
26.00
32.00
37.00
46.00

201.78
1,947.69
9,847.89
3,226.60
836.57
3,737.44
3,393.00
2,035.80
2,064.00
2,574.00
6,762.00
6,084.00
3,776.00
4,070.00
12,466.00

Sub Total Pressure Terminal: ea

11,416.00

5.52

63,022.77

750.00
1,884.00
408.00
46.00
292.00
2,698.00
5,255.00
559.00
849.00
2,932.00
7,746.00
11,494.00
9,464.00
2,776.00

2.87
4.53
3.35
1.47
1.28
0.77
0.86
0.92
1.03
0.86
0.86
0.86
1.03
1.21

2,152.50
8,534.52
1,366.80
67.62
373.76
2,077.46
4,519.30
514.28
874.47
2,521.52
6,661.56
9,884.84
9,747.92
3,358.96

Motor Connections kit


MOTOR CONNECTION KITS 2.5 ~ 6mm
MOTOR CONNECTION KITS 4 ~ 25mm
MOTOR CONNECTION KITS 35 ~ 120mm
MOTOR CONNECTION KITS 150 ~ 300mm

Pressure Terminal
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL
PRESSURE TERMINAL

0.75mm
1mm
2.5mm
4mm
6mm
10mm
16mm
25mm
35mm
50mm
70mm
95mm
120mm
150mm
185mm

Cable
Power Cable
POWER CABLE, ELECTRIC (MV).1/C * 240mm2
POWER CABLE, ELECTRIC (MV).1/C * 630mm2
POWER CABLE, ELECTRIC (MV).3/C * 240mm2
POWER CABLE, ELECTRIC (LV).1/C * 95mm2
POWER CABLE, ELECTRIC (LV).1/C * 120mm2
POWER CABLE, ELECTRIC (LV).2/C * 4mm2
POWER CABLE, ELECTRIC (LV).2/C * 10mm2
POWER CABLE, ELECTRIC (LV).2/C * 16mm2
POWER CABLE, ELECTRIC (LV).2/C * 25mm2
POWER CABLE, ELECTRIC (LV).2/C * 6mm2
POWER CABLE, ELECTRIC (LV).3/C * 10mm2
POWER CABLE, ELECTRIC (LV).3/C * 16mm2
POWER CABLE, ELECTRIC (LV).3/C * 25mm2
POWER CABLE, ELECTRIC (LV).3/C * 50mm2

SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET
SET

Quantity

m
m
m
m
m
m
m
m
m
m
m
m
m
m

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
62300
62310
62320
62330
62340
62350
62360
62370
62380
62390
62400
62410
62420
62430
62440
62450
62460

62470
62480
62490
62500
62510
62520
62530
62540
62550
62560
62570
62580

62590
62600
62610
62620
62630
62640
62650
62660
62670
62680
62690
62700
62710
62720
62730

62740
62750
62760

Description

Unit

POWER CABLE, ELECTRIC (LV).3/C * 70mm2


POWER CABLE, ELECTRIC (LV).3/C * 95mm2
POWER CABLE, ELECTRIC (LV).3/C * 120mm2
POWER CABLE, ELECTRIC (LV).3/C * 150mm2
POWER CABLE, ELECTRIC (LV).3/C * 185mm2
POWER CABLE, ELECTRIC (LV).1/C * 35mm2
POWER CABLE, ELECTRIC (LV).1/C * 70mm2
POWER CABLE, ELECTRIC (LV).3/C * 6mm2
POWER CABLE, ELECTRIC (LV).3/C * 35mm2
POWER CABLE, ELECTRIC (LV).4/C * 4mm2
POWER CABLE, ELECTRIC (LV).3.5/C * 150mm2
POWER CABLE, ELECTRIC (LV).4/C * 16mm2
POWER CABLE, ELECTRIC (LV).4/C * 6mm2
POWER CABLE, ELECTRIC (LV).4/C * 10mm2
POWER CABLE, ELECTRIC (LV).3.5/C * 50mm2
POWER CABLE, ELECTRIC (LV).3/C * 4mm2
POWER CABLE, ELECTRIC (LV).4/C * 10mm2

Quantity

Rate

Amount

m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m
m

4,692.00
5,534.00
413.00
1,129.00
4,662.00
40.00
332.00
1,941.00
4,387.00
278.00
114.00
582.00
1,089.00
1,016.00
258.00
9,368.00
464.00

1.30
1.47
1.60
1.79
1.94
0.77
0.86
0.77
1.03
0.77
1.82
0.86
0.86
0.86
1.21
0.77
0.86

6,099.60
8,134.98
660.80
2,020.91
9,044.28
30.80
285.52
1,494.57
4,518.61
214.06
207.48
500.52
936.54
873.76
312.18
7,213.36
399.04

Sub Total Power Cable: m

83,452.00

1.15

95,602.52

m
m
m
m
m
m
m
m
m
m
m
m

1,457.00
5,857.00
2,255.00
1,444.00
36,593.00
464.00
3,780.00
1,533.00
816.00
400.00
840.00
376.00

1.82
0.64
0.72
0.79
0.04
1.08
1.08
0.64
0.79
1.08
1.89
1.89

2,651.74
3,748.48
1,623.60
1,140.76
1,463.72
501.12
4,082.40
981.12
644.64
432.00
1,587.60
710.64

Sub Total Control Cable: m

55,815.00

0.35

19,567.82

EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA

35.00
124.00
144.00
21.00
26.00
16.00
5.00
1,061.00
436.00
148.00
62.00
116.00
131.00
26.00
5.00

2.54
2.54
2.54
2.54
3.42
3.42
2.54
2.54
2.54
2.54
2.54
3.42
3.42
3.80
3.80

88.90
314.96
365.76
53.34
88.92
54.72
12.70
2,694.94
1,107.44
375.92
157.48
396.72
448.02
98.80
19.00

Sub Total Cable Glands: ea

2,356.00

2.66

6,277.62

12.00
4.00
2.00

61.00
81.00
99.00

732.00
324.00
198.00

18.00

69.67

1,254.00

Control Cable
CONTROL CABLE 2.5mm2
CONTROL CABLE 3/C * 2.5mm2
CONTROL CABLE 5/C * 2.5mm2
CONTROL CABLE 7/C * 2.5mm2
CONTROL CABLE 12/C * 2.5mm2
CONTROL CABLE 12/C * 2.5mm2
CONTROL CABLE 2P
CONTROL CABLE 2T 1.00MM2
CONTROL CABLE 8P/1.00MM2
CONTROL CABLE 24P/1.00MM2
CONTROL CABLE, ELECTRIC 7/C * 2.5mm2
CONTROL CABLE, ELECTRIC 19/C * 2.5mm2

Cable Glands
CABLE GLAND 1-1/2" (42mm)
CABLE GLAND 3/4" (22mm)
CABLE GLAND 1" (28mm)
CABLE GLAND 1-1/4" (36mm)
CABLE GLAND 2" (54mm)
CABLE GLAND 2-1/2" (70mm)
CABLE GLAND 1/2"
CABLE GLAND 3/4"
CABLE GLAND 1"
CABLE GLAND 1-1/4"
CABLE GLAND 1-1/2"
CABLE GLAND 2"
CABLE GLAND 2-1/2"
CABLE GLAND 3"
CABLE GLAND 4"

Cable Termination Kits


CABLE TERMINATION KIT.1/C * 240mm2
CABLE TERMINATION KIT.1/C * 630mm2
CABLE TERMINATION KIT.3/C * 240mm2

SET
SET
SET

Sub Total Cable Termination Kits: Set

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

62770
62780
62790
62800
62810
62820

62830
62840
62850
62860
62870
62880
62890
62900
62910
62920
62930
62940
62950
62960
62970

62980

62990

Description

Unit

Variable Speed Drive Cable


VARIABLE SPEED DRIVE CABLE3/C * 150mm2
VARIABLE SPEED DRIVE CABLE3/C * 185mm2
VARIABLE SPEED DRIVE CABLE3/C * 4mm2
VARIABLE SPEED DRIVE CABLE3/C * 10mm2
VARIABLE SPEED DRIVE CABLE3/C * 95mm2
VARIABLE SPEED DRIVE CABLE3/C * 70mm2

Quantity

Rate

Amount

m
m
m
m
m
m

20.00
1,244.00
2,081.00
525.00
666.00
722.00

1.78
1.99
0.77
0.77
1.47
1.30

35.60
2,475.56
1,602.37
404.25
979.02
938.60

Sub Total Variable Speed Drive Cable: m

5,258.00

1.22

6,435.40

Sub Total Cable: LS

1.00

129,137.36

129,137.36

Sub Total Power Generation Cabling: LS

1.00

1,588,785.32

1,588,785.32

m
m
m
m
m
m
m
m
m
M
M
M
m
M
M

1,015.00
231.00
126.00
552.00
95.00
81.00
2,420.00
32.00
89.00
4,826.00
5,127.00
1,192.00
214.00
228.00
21.00

4.22
7.95
10.00
16.00
21.00
3.66
7.82
30.00
55.00
55.00
17.00
17.00
35.00
17.00
17.00

4,283.30
1,836.45
1,260.00
8,832.00
1,995.00
296.46
18,924.40
960.00
4,895.00
265,430.00
87,159.00
20,264.00
7,490.00
3,876.00
357.00

Sub Total PVC Conduit: m

16,249.00

26.33

427,858.61

EA

1,394.00

31.00

43,214.00

EA

68.00

36.00

2,448.00

Sub Total PVC Plugs: ea

1,462.00

31.23

45,662.00

Sub Total PVC Conduit: LS

1.00

473,520.61

473,520.61

427.00
1,432.00

92.00
120.00

39,284.00
171,840.00

Power Generation Conduit


PVC Conduit
PVC Conduit
HI PVC CONDUIT 1" (28mm)
HI PVC CONDUIT 1-1/2" (42mm)
HI PVC CONDUIT 2" (54mm)
HI PVC CONDUIT 2-1/2" (70mm)
HI PVC CONDUIT 3" (82mm)
HI PVC CONDUIT 3/4" (22mm)
HI PVC CONDUIT 1-1/4" (36mm)
HI PVC CONDUIT 3-1/2"
HI PVC CONDUIT 6" (150MM)
PVC CONDUIT 6"
PVC CONDUIT 6"
PVC CONDUIT 6"
PVC CONDUIT 200mm
PVC CONDUIT 200mm
PVC CONDUIT 200mm

PVC Plugs
PVC CONDUIT PLUG
SIZE : 6"
PVC CONDUIT PLUG
SIZE : 8"

Rigid Steel Conduit


Rigid Steel Conduit Straight
SPECIFICATION :
RIGID STEEL CONDUIT HOT DIP GALVANIZED, METRIC
THREADED BOTH ENDS WITH 1-COUPLING, SIZE:
3600mmL X 1" NPT
SUPPLIED By Sub-Con.
63000
63010

RIGID STEEL CONDUIT3/4" (22mm)


RIGID STEEL CONDUIT1" (28mm)

m
m

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
63020
63030
63040
63050
63060
63070
63080

Description
RIGID STEEL CONDUIT1-1/4" (36mm)
RIGID STEEL CONDUIT1-1/2" (42mm)
RIGID STEEL CONDUIT2-1/2" (70mm)
RIGID STEEL CONDUIT3" (82mm)
RIGID STEEL CONDUIT3-1/2" (92mm)
RIGID STEEL CONDUIT 2"
RIGID STEEL CONDUIT 6"

Unit

Quantity

Rate

Amount

m
m
m
m
m
m
m

1,223.00
95.00
570.00
86.00
5.00
13.00
21.00

190.00
200.00
370.00
510.00
630.00
260.00
1,000.00

232,370.00
19,000.00
210,900.00
43,860.00
3,150.00
3,380.00
21,000.00

Sub Total Rigid Steel Conduit Straight: m

3,872.00

192.35

744,784.00

EA
EA
EA
EA
EA
EA
EA
EA
EA

116.00
73.00
9.00
55.00
426.00
394.00
45.00
30.00
13.00

110.00
140.00
200.00
14.00
20.00
38.00
43.00
59.00
990.00

12,760.00
10,220.00
1,800.00
770.00
8,520.00
14,972.00
1,935.00
1,770.00
12,870.00

Sub Total Rigid Steel Elbow: ea

1,161.00

56.52

65,617.00

EA
EA
EA
EA
EA
EA
EA
EA
EA
EA

186.00
623.00
532.00
41.00
6.00
248.00
37.00
2.00
9.00
18.00

14.00
21.00
35.00
47.00
34.00
34.00
34.00
34.00
34.00
34.00

2,604.00
13,083.00
18,620.00
1,927.00
204.00
8,432.00
1,258.00
68.00
306.00
612.00

Sub Total Rigid Steel Conduit Clamps: ea

1,702.00

27.68

47,114.00

Sub Total Rigid Steel Conduit: m

3,872.00

221.47

857,515.00

Sub Total Power Generation Conduit: LS

1.00

1,331,035.61

1,331,035.61

63280
63290

Power Generation Cable Tray


Cable Tray Elbow
CABLE TRAY VERT. ELBOW(90 DEGREE-IN) * 600mmW
EA
CABLE TRAY VERT. ELBOW(90 DEGREE-OUT) * 600mmW EA

2.00
2.00

33.00
33.00

66.00
66.00

63300
63310
63320
63330

CABLE TRAY TEE * 900mmW


CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 900mmW
CABLE TRAY VERT. ELBOW(90 DEGREE-IN) * 450mmW
CABLE TRAYVERT. ELBOW(90 DEGREE-OUT) * 300mmW

EA
EA
EA
EA

5.00
4.00
2.00
3.00

38.00
38.00
33.00
32.00

190.00
152.00
66.00
96.00

63340

CABLE TRAYVERT. ELBOW(90 DEGREE-OUT) * 450mmW EA

2.00

33.00

66.00

63350
63360

CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * 300mmW


EA
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREE-IN) * ea
300mmW

2.00
2.00

32.00
32.00

64.00
64.00

63090
63100
63110
63120
63130
63140
63150
63160
63170

Rigid Steel Elbow


RIGID STEEL ELBOW2-1/2" (70mm)
RIGID STEEL ELBOW3" (82mm)
RIGID STEEL ELBOW3-1/2" (92mm)
RIGID STEEL ELBOW3/4" (22mm)
RIGID STEEL ELBOW1" (28mm)
RIGID STEEL ELBOW1-1/4" (36mm)
RIGID STEEL ELBOW 1-1/2" (42mm)
RIGID STEEL ELBOW 2"
RIGID STEEL ELBOW 6"

Rigid Steel Conduit Clamps


I STOP HERE, TO BE CONTINUED ON
SATURDAY..................
63180
63190
63200
63210
63220
63230
63240
63250
63260
63270

CONDUIT CLAMP 3/4"


CONDUIT CLAMP 1"
CONDUIT CLAMP 1-1/4"
CONDUIT CLAMP 1-1/2"
CONDUIT CLAMP 2"
CONDUIT CLAMP 2-1/2"
CONDUIT CLAMP 3"
CONDUIT CLAMP 3-1/2"
CONDUIT CLAMP 4"
CONDUIT CLAMP 1-1/4"

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
63370
63380
63390
63400
63410
63420
63430
63440
63450

63460
63470
63480
63490
63500
63510
63520
63530
63540
63550
63560
63570
63580

63590
63600
63610
63620
63630
63640
63650

Description
COVER FOR CABLE TRAYHORIZ. ELBOW(90 DEGREE) *
300mmW
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREE-IN) *
450mmW
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREEOUT) * 300mmW
COVER FOR CABLE TRAYVERT. ELBOW(90 DEGREEOUT) * 450mmW
CABLE TRAY TEE * 600mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 300mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 450mmW
CABLE TRAY HORIZ. ELBOW(90 DEGREE) * 600mmW
COVER FOR CABLE TRAY HORIZ. ELBOW(90 DEGREE) *
450mmW

Unit

Rate

Amount

ea

6.00

32.00

192.00

ea

2.00

33.00

66.00

ea

3.00

32.00

96.00

ea

2.00

33.00

66.00

EA
EA
EA
EA
m

1.00
6.00
2.00
2.00
2.00

33.00
32.00
33.00
33.00
33.00

33.00
192.00
66.00
66.00
66.00

Sub Total Cable Tray Elbow: ea

50.00

33.46

1,673.00

EA
EA
EA
EA
EA

2.00
5.00
1.00
24.00
69.00

2.54
1.78
1.78
3.17
1.27

5.08
8.90
1.78
76.08
87.63

EA

10.00

1.27

12.70

EA
EA
EA
EA
EA
EA
EA

1,078.00
104.00
132.00
14.00
40.00
40.00
304.00

0.25
0.25
0.25
0.25
0.38
0.38
0.38

269.50
26.00
33.00
3.50
15.20
15.20
115.52

Sub Total Cable Tray Fittings: ea

1,823.00

0.37

670.09

m
m
m
m
m
m
m

96.00
240.00
72.00
108.00
12.00
72.00
108.00

33.00
38.00
41.00
33.00
33.00
33.00
33.00

3,168.00
9,120.00
2,952.00
3,564.00
396.00
2,376.00
3,564.00

Sub Total Cable Tray Straight: m

708.00

35.51

25,140.00

1.00

27,483.09

27,483.09

m3
m3
m3
m3
EA

20,273.00
12,159.00
7,652.26
930.00
52,912.00

1.90
69.00
44.00
1.90
3.16

38,518.70
838,971.00
336,699.40
1,767.00
167,201.92

Sub Total Power Generation Civil Works: LS

1.00

1,383,158.02

1,383,158.02

Cable Tray Fittings


BLIND END PLATEEND BLIND PLATE * 600mmW
BLIND END PLATEEND BLIND PLATE * 300mmW
BLIND END PLATEEND BLIND PLATE * 450mmW
BLIND END PLATEEND BLIND PLATE * 900mmW
SEPERATOR FOR CABLE TRAY150 mmH *
STRAIGHT(3000MML)
SEPERATOR FOR CABLE TRAY150 mmH * VERT.
ELBOW(600)
CABLE TRAY HOLE DOWN CLAMPS
CABLE TRAY COVER CLAMPS W: 300mm
CABLE TRAY COVER CLAMPS W: 450mm
CABLE TRAY COVER CLAMPS W: 600mm
ADJUSTABLE RISER CONNECTOR VERTICAL TYPE
ADJUSTABLE RISER CONNECTOR HORIZONTAL TYPE
JOINT CONNECTOR THICKNESS : 2.6t(8 HOLES)

Cable Tray Straight


CABLE TRAY STRAIGHT * 600mmW
CABLE TRAY STRAIGHT * 900mmW
CABLE TRAYSTRAIGHT * 300mmW
CABLE TRAYSTRAIGHT * 450mmW
COVER FOR CABLE TRAYSTRAIGHT * 600mmW
COVER FOR CABLE TRAYSTRAIGHT * 300mmW
COVER FOR CABLE TRAYSTRAIGHT * 450mmW

Sub Total Power Generation Cable Tray: LS

63660
63670
63680
63690
63700

Quantity

Power Generation Civil Works


EXCAVATION WORK
BACK FILLING AND COMPACTION
SAND FILLING AND COMPACTION
EXCAVATION & BACK FILL WORK
RED CONCRETE

Power Generation Bus


Bus Duct

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
63710
63720
63730
63740
63750
63760
63770
63780
63790

Description

Unit

BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA


BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA
BUS DUCT(0.635)KV, 60HZ, (4000)A, 3PH, (3)W, (80)KA

SET
SET
SET
SET
SET
SET
SET
SET
SET

63810
63820
63830
63840
63850

63860
63870
63880
63890
63900
63910
63920
63930

780.00
780.00
780.00
780.00
500.00
780.00
720.00
500.00
780.00

9.00

711.11

6,400.00

1,200.00

1.88

2,256.00

Sub Total Modular Bus: LS

1.00

2,256.00

2,256.00

Sub Total Power Generation Bus: LS

1.00

8,656.00

8,656.00

m
m
m
m
m

869.00
86.00
86.00
86.00
86.00

65.00
150.00
160.00
180.00
190.00

56,485.00
12,900.00
13,760.00
15,480.00
16,340.00

Sub Total Steel Angle: m

1,213.00

94.78

114,965.00

m
SET
EA

333.00
53.00
212.00

73.00
96.00
55.00

24,309.00
5,088.00
11,660.00

SET
SET
SET
SET
SET

211.00
25.00
17.00
30.00
9.00

520.00
520.00
97.00
1,100.00
1,100.00

109,720.00
13,000.00
1,649.00
33,000.00
9,900.00

1.00

208,326.00

208,326.00

2,176.00
6,488.00
30.00
55.00
143.00
40.00
1,166.00
949.00
111.00
474.00
157.00
3.00
91.00
58.00

24.00
17.00
69.00
71.00
75.00
73.00
24.00
26.00
29.00
36.00
44.00
50.00
16.00
91.00

52,224.00
110,296.00
2,070.00
3,905.00
10,725.00
2,920.00
27,984.00
24,674.00
3,219.00
17,064.00
6,908.00
150.00
1,456.00
5,278.00

Modular Bus
RSS485(MODBUS)SHIELDED TWIST PAIR CABLE

Power Generation Support


Steel Angle
STEEL ANGLE 50 x 50 x 6t
STEEL ANGLE 200 x 2.6t
STEEL ANGLE 300 x 2.6t
STEEL ANGLE 500 x 2.6t
STEEL ANGLE 800 x 2.6t

Support
CABLE TRAY SUPPORT 100 * 50 * 5T
CABLE TRAY SUPPORT STEEL(0.75M/SET)
BASE STEEL PLATE FOR CABLE TRAY SUPPORT 260 x
160 x 12t
CONTROL STATION SUPPORT
POWER JUNCTION BOX SUPPORT
WELDING RECEPTACLE SUPPORT
SUPPORT FOR BUS DUCT
SUPPORT FOR BUS DUCT

Clamps
HOLD DOWN CLAMP
SHANK BOLT AND NUT
COVER CLAMPBAND TYPE
COVER CLAMPBAND TYPE
COVER CLAMPBAND TYPE
COVER CLAMPBAND TYPE
UNISTRUT CLAMP1" (28mm)
UNISTRUT CLAMP1-1/4" (36mm)
UNISTRUT CLAMP1-1/2" (42mm)
UNISTRUT CLAMP2-1/2" (70mm)
UNISTRUT CLAMP3" (82mm)
UNISTRUT CLAMP3-1/2" (92mm)
UNISTRUT CLAMP3/4" (22mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY
1" (28mm)

Amount
780.00
780.00
780.00
780.00
500.00
780.00
720.00
500.00
780.00

Sub Total Support: LS

63940
63950
63960
63970
63980
63990
64000
64010
64020
64030
64040
64050
64060
64070

Rate

1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

Sub Total Bus Duct: Set

63800

Quantity

EA
SET
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

64080

CONDUIT CLAMP FOR OUTSIDE RAIL TRAY

EA

213.00

100.00

21,300.00

64090

1-1/4" (36mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY

EA

5.00

170.00

850.00

64100

2-1/2" (70mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY

EA

24.00

180.00

4,320.00

64110

3" (82mm)
CONDUIT CLAMP FOR OUTSIDE RAIL TRAY

EA

6.00

82.00

492.00

Sub Total Clamps: LS

1.00

295,835.00

295,835.00

EA
EA
EA

508.00
55.00
44.00

110.00
140.00
95.00

55,880.00
7,700.00
4,180.00

EA

44.00

120.00

5,280.00

Sub Total Connectors: ea

651.00

112.20

73,040.00

2,358.00

28.00

66,024.00

3/4" (22mm)

64120
64130
64140
64150

Connectors
JOINT CONNECTOR150mmH
EXPANSION CONNECTOR
ADJUSTABLE CONNECTOR 150mmH * HORIZONTAL
TYPE
ADJUSTABLE CONNECTOR 150mmH * VERTICAL TYPE

64160

Other
EXPANSION ANCHOR FOR TRAY SUPPORT STAINLESS
STEEL (4EA /SET)

EA

64170

WARNING TAPE 3" wide x 305m length x 2.5mm th'k

Roll

483.00

430.00

207,690.00

64180
64190

CABLE ROUTE MARKER


GROUNDING BONDING JUMPER WITH TERMINAL
LUG35mm2
UNISTRUT CHANNELSTRAIGHT(3000mmL)
MISCELLANEOUS FOR POWER SYSTEM
STRONG ANCHOR BOLT M12xL75
NUT M12xL50
ANCHOR BOL M20xL500
WARNING SIGN
SCREWS BOLT 1/4"
CABLE ROUTE MARKER
EXPANSION ANCHOR 1/2"- 30
SHANK BOLT STEEL 8 mm DIA /19mmL
EXPANSION CONNECTOR THICKNESS : 2.6t(8 HOLES)

EA
EA

239.00
192.00

270.00
0.46

64,530.00
88.32

EA
LOT
EA

57.00
1.00
188.00

180.00
551,850.00
4.14

10,260.00
551,850.00
778.32

EA
EA
EA
EA
EA
EA
EA

52.00
11.00
6,880.00
1,659.00
938.00
3,883.00
33.00

4.99
9.22
2.66
250.00
220.00
5.24
85.00

259.48
101.42
18,300.80
414,750.00
206,360.00
20,346.92
2,805.00

Sub Total Other: LS

1.00

1,564,144.26

1,564,144.26

Sub Total Power Generation Support: LS

1.00

2,256,310.26

2,256,310.26

M/D
M/D

540.00
270.00

160.00
190.00

86,400.00
51,300.00

Sub Total Power Generation Commissioning: M/D

810.00

170.00

137,700.00

1.00

6,874,033.30

6,874,033.30

64200
64210
64220
64230
64240
64250
64260
64270
64280
64290

64300
64310

Power Generation Commissioning


Commissioning & Start-up Assist (LABOR)
Commissioning & Start-up Assist (TECHNICIANS)

Sub Total Power Generation System: LS


Cathodic Protection System
Cathodic Protection Anodes

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

64320
64330
64340

64350
64360

64370

64380
64390

64400
64410

64420
64430

64440
64450
64460
64470
64480
64490
64500
64510
64520
64530
64540
64550
64560
64570

Description
Standard Anode
IMPRESSED CURRENT ANODE MMO(MIXED METAL
OXIDE)
SACRIFICIAL ANODE TEMPORARY CATHODIC
PROTECTION
SACRIFICIAL ANODE TEMPORARY CATHODIC
PROTECTION

Unit

Quantity

Rate

Amount

EA

116.00

43,860.00

5,087,760.00

EA

116.00

4,690.00

544,040.00

EA

44.00

47,770.00

2,101,880.00

Sub Total Standard Anode: ea

276.00

28,020.58

7,733,680.00

M
M

1,200.00
1,200.00

13.00
96.00

15,600.00
115,200.00

Sub Total Ribbon Anode: m

2,400.00

54.50

130,800.00

EA

104.00

4,350.00

452,400.00

Sub Total Reference Electrodes: LS

1.00

452,400.00

452,400.00

EA

10.00

200.00

2,000.00

EA

10.00

120.00

1,200.00

Sub Total Anode Power Feed Connectors: ea

20.00

160.00

3,200.00

Sub Total Cathodic Protection Anodes: ea

1.00

8,320,080.00

8,320,080.00

EA
EA

518.00
518.00

25.00
430.00

12,950.00
222,740.00

Sub Total Cathodic Protection CADWelding: ea

1,036.00

227.50

235,690.00

M
M

700.00
700.00

36.00
250.00

25,200.00
175,000.00

Sub Total Cathodic Protection Conductor Bar: m

1,400.00

143.00

200,200.00

M
M
M
M
M
M
M
M
M
M
M
M
M
M

800.00
1,600.00
1,550.00
375.00
400.00
4,500.00
375.00
800.00
1,600.00
1,550.00
375.00
400.00
4,500.00
375.00

48.00
250.00
250.00
59.00
81.00
81.00
58.00
17.00
42.00
42.00
72.00
100.00
51.00
72.00

38,400.00
400,000.00
387,500.00
22,125.00
32,400.00
364,500.00
21,750.00
13,600.00
67,200.00
65,100.00
27,000.00
40,000.00
229,500.00
27,000.00

Sub Total Cathodic Protection Cabling: m

19,200.00

90.42

1,736,075.00

Ribbon Anode
MMO RIBBON ANODE 6.4MM X 0.64T
MMO RIBBON ANODE 6.4MM X 0.64T

Reference Electrodes
REFERFNCE ELECTRODE PERMANENT TYPE

Anode Power Feed Connectors


ANODE POWER FEEDER CONNECTOR 3MM Ti ROD X
25M/ROLL
ANODE POWER FEEDER CONNECTOR 3MM Ti ROD X
25M/ROLL

Cathodic Protection CADWelding


CAD WELD WIRE TO STEEL SURFACE TYPE
CAD WELD

Cathodic Protection Conductor Bar


CONDUCTOR BAR, 12.7MM X 0.89T
CONDUCTOR BAR, 12.7MM X 0.89T

Cathodic Protection Cabling


TEST LEAD CABLE HMWPE CABLE 1C 10MM2
MONITORING CABLE HMWPE CABLE 1C 16MM2
ANOD LEAD CABLE HMWPE CABLE 16MM2 1C
NEGATIVE CABLE HMWPE CABLE 1C 35MM2
NEGATIVE CABLE HMWPE CABLE 1C 50MM2
POSITIVE CABLE HMWPE-CV-IC-25MM2
POSITIVE CABLE HMWPE-CV-1C-35MM2
TEST LEAD CABLE 1C 10MM2
MONITORING CABLE 1C 16MM2
ANOD LEAD CABLE 16MM2 1C
NEGATIVE CABLE 1C 35MM2
NEGATIVE CABLE 1C 50MM2
POSITIVE CABLE 25MM2
POSITIVE CABLE 35MM2

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

64580

Description

Unit

Cathodic Protection Conduit


Conduit
RIGID STEEL CONDUITHOT DIP GALVANIZED, NPT
THREADED BOTH ENDSWITH 1-COUPLING, 4"
RIGID STEEL CONDUIT 4"

Quantity

Rate

Amount

2,500.00

63.00

157,500.00

2,500.00

230.00

575,000.00

Sub Total Conduit: m

5,000.00

146.50

732,500.00

69.00

57.00

3,933.00

EA

104.00

130.00

13,520.00

EA

104.00

31.00

3,224.00

EA

65.00

34.00

2,210.00

m
EA
EA
EA

69.00
104.00
104.00
65.00

280.00
510.00
17.00
29.00

19,320.00
53,040.00
1,768.00
1,885.00

Sub Total Fittings: LS

1.00

98,900.00

98,900.00

1.00

831,400.00

831,400.00

22.00
22.00
25.00
81.00

5,050.00
4,660.00
3,740.00
1,340.00

111,100.00
102,520.00
93,500.00
108,540.00

150.00

2,771.07

415,660.00

SET

9.00

47,770.00

429,930.00

EA

1.00

47,770.00

47,770.00

EA

3.00

47,770.00

143,310.00

EA

1.00

47,770.00

47,770.00

Sub Total Cathodic Protection Equipment: Set

14.00

47,770.00

668,780.00

EA
EA
EA
EA

244.00
202.00
244.00
202.00

770.00
770.00
840.00
540.00

187,880.00
155,540.00
204,960.00
109,080.00

Sub Total Cathodic Protection Markers: ea

892.00

737.06

657,460.00

64800

Cathodic Protection Miscellaneous


MISCELLANEOUS FOR CATHODIC PROTECTION SYSTEM EA

1.00

144,570.00

144,570.00

64810

DESK FOR COMPUTER OPERATION

1.00

2,600.00

2,600.00

64590

64600
64610
64620
64630
64640
64650
64660
64670

Fittings
CONDUIT ELBOW 90' HOT DIP GALVANIZED, NPT
THREADED BOTH ENDS WITH 2-COULING 1"
SEALING FITTINGFLAME EXPLOSION PROOF TYPE,
UNIVERSAL
CONDUIT CLAMP WITH 304SS BOLT & NUT UNISTRUT
TYPE STAINLESS STEEL(304SS), 41 X 41 X 2.6t
3M LONG 2" DEA. SLOTTED PVC PIPE INSERTED IN GEOTEXTILE SOCK
CONDUIT ELBOW 90' 1"
SEALING FITTING
CONDUIT CLAMP 4" (104mm)
PVC PIPE 3M LONG 2" DEA.

Sub Total Cathodic Protection Conduit: m

64680
64690
64700
64710

Cathodic Protection Junction Boxes


ANODE JUNCTIION BOX EXPLOSION PROOF TYPE
NEGATIVE JUNCTION BOX WEATHER PROOF
BONDIN BOX WEATHER PROOF TYPE
TEST BOX FOR CATHODIC PROTECTION EXPLOSION
PROOF TYPE

EA
EA
ea
SET

Sub Total Cathodic Protection Junction Boxes: ea

64720
64730
64740
64750

64760
64770
64780
64790

Cathodic Protection Equipment


TRANSFORMER RECTIFIER FOR CATHODIC
PROTECTION WEATHER PROOF TYPE
TRANSFORMER RECTIFIER FOR CATHODIC
PROTECTION WEATHER PROOF TYPE
TRANSFOMER RECTIFIER FOR CATHODIC PROTECTION
WEATHER PROOF TYPE
TRANSFOMER RECTIFIER FOR CATHODIC PROTECTION
WEATHER PROOF TYPE

Cathodic Protection Markers


ANODE MARKER
CABLE MARKER
ANODE MARKER
CABLE MARKER

EA

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
64820
64830

64840
64850
64860

64870
64880
64890

Description

Unit

PERSONAL COMPUTER AND MONITOR FOR CP SYSTEM EA


MONITORING
DIRECT BURIAL CABLE TRENCH FOR ANODE CATHODE M
REFERENCE ELECTRODE CABLES 600mmW X 715mmD

64940
64950

64960
64970

64980
64990
65000

Rate

Amount

1.00

57.00

57.00

7,000.00

48.00

336,000.00

CATHODIC PROTECTION
EA
DESK FOR COMPUTER OPERATION
EA
PERSONAL COMPUTER AND MONITOR FOR CP SYSTEM EA
MONITORING

1.00
1.00
1.00

92,320.00
17,090.00
17,090.00

92,320.00
17,090.00
17,090.00

Sub Total Cathodic Protection Miscellaneous: ea

7,006.00

87.03

609,727.00

Sub Total Cathodic Protection System: LS

1.00

13,675,072.00

13,675,072.00

SET

2.00

2,870.00

5,740.00

SET
SET

8.00
8.00

2,930.00
460.00

23,440.00
3,680.00

18.00

1,825.56

32,860.00

m
m
m
m

2,227.00
2,169.00
210.00
80.00

15.00
12.00
12.00
12.00

33,405.00
26,028.00
2,520.00
960.00

Sub Total Cable: m

4,686.00

13.43

62,913.00

EA
EA

12.00
36.00

6.34
6.34

76.08
228.24

Sub Total Cable Gland: ea

48.00

6.34

304.32

Sub Total CCTV Cabling: LS

1.00

63,217.32

63,217.32

m
m

129.00
269.00

34.00
22.00

4,386.00
5,918.00

Sub Total Conduit: m

398.00

25.89

10,304.00

m
EA
EA

65.00
80.00
80.00

25.00
16.00
8.76

1,625.00
1,280.00
700.80

Sub Total Clamp: LS

1.00

3,605.80

3,605.80

Sub Total CCTV Conduit: LS

1.00

13,909.80

13,909.80

CCTV System
CCTV Equipment
CCTV SYSTEM EQUIPMENT19" 42U EQUIPMENT
CABINETINDOOR
COLOR CAMERA SONY'S MODEL FCB-EX SERIES
WASHER TANK FOR COLOR CAMERA

Sub Total CCTV Equipment: Set

64900
64910
64920
64930

Quantity

CCTV Cabling
Cable
POWER CABLE, ELECTRIC 3/C * 4mm2
FIBER OPTIC CABLE4C SINGLE MODE
FIBER OPTIC ABLE4C SINGLE MODE
COMPOSITE CABLE FOR CCTV CAMERA

Cable Gland
CABLE GLANDEXPLOSION PROOF TYPE3/4"
CABLE GLANDWEATHER PROOF3/4"

CCTV Conduit
Conduit
RIGID STEEL CONDUIT 3/4"
PVC CONDUITSCHEDULE 40

Clamp
CONDUIT CLAMP 3/4"
CONDUIT CLAMPUNISTRUT TYPE 3/4"
CONDUIT CLAMP

CCTV Cable Tray


Tray

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
65010
65020

Description

Unit

PERFORATED CABLE TRAYSTRAIGHT


PERFORATED CABLE TRAY SUPPORT

m
SET

65070

65080
65090

65140
65150
65160

4,407.00
9,890.00

1.00

14,297.00

14,297.00

EA
EA
EA
EA

170.00
170.00
204.00
204.00

10.00
6.70
69.00
17.00

1,700.00
1,139.00
14,076.00
3,468.00

Sub Total Clamps: LS

1.00

20,383.00

20,383.00

Sub Total CCTV Cable Tray: LS

1.00

34,680.00

34,680.00

EA

8.00

100.00

800.00

Sub Total CCTV Junction Boxes: LS

1.00

800.00

800.00

1.00
1.00

1,180.00
1,400.00

1,180.00
1,400.00

1.00

2,580.00

2,580.00

EA
EA
m
m

8.00
1,019.00
16.00
20.00

1,700.00
17.00
70.00
75.00

13,600.00
17,323.00
1,120.00
1,500.00

EA

8.00

78.00

624.00

1,219.00
1,219.00

17.00
8.76

20,723.00
10,678.44

1.00

65,568.44

65,568.44

1.00

86,900.00

86,900.00

Sub Total CCTV Miscellaneous: LS

1.00

86,900.00

86,900.00

Sub Total CCTV System: LS

1.00

300,515.56

300,515.56

m3
EA
EA

456.00
12.00
11.00

67.00
420.00
420.00

30,552.00
5,040.00
4,620.00

Sub Total Fire Alarm Civil Work: LS

1.00

40,212.00

40,212.00

400.00
2,382.00

11.00
11.00

4,400.00
26,202.00

Clamps
JOINT CONNECTOR
COVER CLAMP FOR PERFORATED CT
COVER CLAMP FOR PERFORATED CABLE TRAY50MM
COVER CLAMP

CCTV Junction Boxes


JUNCTION BOX WITH COVER AND GASKET

CCTV Computer Equipment


24 PORT LAN SWITCH, CISCO, WS-C3750E
WORK STATION WITH KEYBOARD

SET
SET

CCTV Support
POLE FOR CCTV CAMERA SET
STAINLESS SHANK BOLT & NUT
STEEL ANGLE HOT DIP GALVANIZED STEEL
UNISTRUT CHANNELHOT DIP GALVANIZED STEEL41 X
41 X 2.6t
STEEL PLATE HOT DIP GALVANIZED STEEL 500 X 300 X
6t
SHANK BOLT AND NUT
SHANK BOLT

SET
SET

Sub Total CCTV Support: LS

65170

65180
65190
65200

65210
65220

Amount
13.00
230.00

Sub Total CCTV Computer Equipment: LS

65100
65110
65120
65130

Rate

339.00
43.00

Sub Total Tray: LS

65030
65040
65050
65060

Quantity

CCTV Miscellaneous
MISCELLANEOUS FOR CCTV SYSTEM

Fire Alarm System


Fire Alarm Civil Work
EXCAVATION & BACK FILL WORK
FOUNDATION FOR MPS POLEW305 x D305 x H914
FOUNDATION FOR MPS POLEW305 x D305 x H510

Fire Alarm Cabling


Cable
LINEAR HEAT DETECTOR CABLE
FIRE ALARM CABLE, ELECTRIC.
1P-1.5mm2

LOT

m
m

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
65230
65240
65250
65260
65270
65280
65290
65300
65310

65320
65330
65340
65350
65360
65370
65380

65390
65400
65410
65420

Description

Unit

FIRE ALARM CABLE, ELECTRIC.


6C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
2C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
3C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
4C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
12C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
19C-2.5mm2
FIRE ALARM CABLE, ELECTRIC.
30C-2.5mm2
CABLE FOR GAS DETECTOR1P-1.0mm2
FIRE ALARM CABLE, ELECTRIC.
10C-2.5mm2

65440
65450

Rate

Amount

95.00

11.00

1,045.00

7,743.00

11.00

85,173.00

285.00

11.00

3,135.00

520.00

11.00

5,720.00

1,330.00

11.00

14,630.00

4,233.00

11.00

46,563.00

505.00

11.00

5,555.00

m
m

42.00
24.00

11.00
11.00

462.00
264.00

Sub Total Cable: m

17,559.00

11.00

193,149.00

EA

258.00

16.00

4,128.00

EA

2.00

20.00

40.00

EA

6.00

22.00

132.00

EA

1.00

26.00

26.00

EA

140.00

16.00

2,240.00

EA

4.00

20.00

80.00

EA

13.00

22.00

286.00

Sub Total Cable Gland: ea

424.00

16.35

6,932.00

Sub Total Fire Alarm Cabling: LS

1.00

200,081.00

200,081.00

5,368.00

42.00

225,456.00

565.00

56.00

31,640.00

317.00

27.00

8,559.00

35.00

76.00

2,660.00

1.00

268,315.00

268,315.00

1,642.00

24.00

39,408.00

45.00

26.00

1,170.00

568.00

28.00

15,904.00

Cable Gland
CABLE GLAND
3/4"
CABLE GLAND
1"
CABLE GLAND
1-1/2"
CABLE GLAND
2"
CABLE GLAND
3/4"
CABLE GLAND
1"
CABLE GLAND
1-1/2"

Fire Alarm Conduit


Rigid Steel Conduit
RIGID STEEL CONDUIT
HOT DIP GALVANIZED, NPT THREADED BOTH ENDS1"
RIGID STEEL CONDUIT
1-1/4"
RIGID STEEL CONDUIT
1-1/2"
RIGID STEEL CONDUIT
2"

Sub Total Rigid Steel Conduit: LS

65430

Quantity

PVC Conduit
PVC CONDUIT (SCHEDULE 40)
1"
PVC CONDUIT (SCHEDULE 40)
1-1/4"
PVC CONDUIT (SCHEDULE 40)
1-1/2"

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
65460

65470

65480
65490
65500
65510
65520
65530
65540
65550
65560

65570
65580

65590

Description

Unit

PVC CONDUIT (SCHEDULE 40)


2"

Quantity

Rate

Amount

23.00

38.00

874.00

Sub Total PVC Conduit: m

2,278.00

25.18

57,356.00

38.00

110.00

4,180.00

Sub Total Flexible Metal Conduit: m

38.00

110.00

4,180.00

EA
EA
EA
EA
EA
EA
EA
EA
EA

1,398.00
90.00
149.00
2,000.00
3,957.00
754.00
2,000.00
3,957.00
754.00

29.00
35.00
38.00
25.00
29.00
35.00
97.00
130.00
160.00

40,542.00
3,150.00
5,662.00
50,000.00
114,753.00
26,390.00
194,000.00
514,410.00
120,640.00

Sub Total Conduit Clamp: ea

15,059.00

71.02

1,069,547.00

Sub Total Fire Alarm Conduit: LS

1.00

1,399,398.00

1,399,398.00

M
M

60.00
30.00

20.00
59.00

1,200.00
1,770.00

Sub Total Tray: m

90.00

33.00

2,970.00

EA

30.00

6.70

201.00

Sub Total Clamps: ea

30.00

6.70

201.00

Sub Total Fire Alarm Cable Tray: LS

1.00

3,171.00

3,171.00

Flexible Metal Conduit


FLEXIBLE METALLIC CONDUIT
3/4"

Conduit Clamp
CONDUIT CLAMP1"
CONDUIT CLAMP1-1/4"
CONDUIT CLAMP1-1/2"
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1 1/4"
CONDUIT CLAMP 3/4"
CONDUIT CLAMP 1"
CONDUIT CLAMP 1-1/4"

Fire Alarm Cable Tray


Tray
PERFORATED CABLE TRAY100 X 50
PERFORATED CABLE TRAY100MM

Clamps
COVER CLAMP100MM

65600

Fire Alarm Devices


Fire Alarm Stations
FIRE ALARM MANUAL STATION

EA

30.00

150.00

4,500.00

65610

FIRE ALARM MANUAL STATION

EA

18.00

140.00

2,520.00

65620

FIRE ALARM MANUAL STATION

EA

14.00

120.00

1,680.00

65630

CO2 DISCHARGE MANUAL STATION

EA

1.00

140.00

140.00

Sub Total Fire Alarm Stations: ea

63.00

140.32

8,840.00

65640

Warning Devices
FIRE ALARM SIREN (MEDC DB3 RANGE)

SET

38.00

190.00

7,220.00

65650

FIRE ALARM SIREN (MEDC DB3 RANGE)

SET

44.00

190.00

8,360.00

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

65660

FIRE ALARM HORN/STROBE

EA

12.00

340.00

4,080.00

65670

FIRE ALARM HORN/STROBE

EA

6.00

340.00

2,040.00

65680

FLASH LIGHT FOR FIRE ALARM(BEACON)

EA

8.00

250.00

2,000.00

65690

FLASH LIGHT FOR FIRE ALARM(BEACON)

EA

8.00

250.00

2,000.00

65700

CO2 DISCHARGE WARNING LIGHT (LAMP)

EA

1.00

250.00

250.00

65710

CO2 DISCHARGE WARNING SIREN

EA

1.00

320.00

320.00

Sub Total Warning Devices: LS

1.00

26,270.00

26,270.00

65720

Fire Alarm Detectors


FIRE DETECTOR

EA

41.00

320.00

13,120.00

65730

DUCT SMOKE DETECTOR

EA

12.00

320.00

3,840.00

65740

FIRE DETECTOR

EA

1.00

110.00

110.00

65750

FIRE DETECTOR

EA

62.00

110.00

6,820.00

65760

BEAM DETECTOR

EA

5.00

110.00

550.00

Sub Total Fire Alarm Detectors: ea

121.00

201.98

24,440.00

EA

1.00

140.00

140.00

Sub Total Fire Alarm Switches: ea

1.00

140.00

140.00

Sub Total Fire Alarm Devices: LS

1.00

59,690.00

59,690.00

532.00

75.00

39,900.00

35.00

140.00

4,900.00

1,641.00
180.00
6.00

22.00
17.00
230.00

36,102.00
3,060.00
1,380.00

1.00

85,342.00

85,342.00

EA

1.00

450.00

450.00

EA

15.00

380.00

5,700.00

EA

16.00

380.00

6,080.00

EA

1.00

310.00

310.00

Sub Total Termination Boxes: ea

33.00

380.00

12,540.00

65770

65780
65790
65800
65810
65820

Fire Alarm Switches


CO2 DISCHARGE ABORT SWITCH

Fire Alarm Support


UNISTRUT CHANNEL HOT DIP GALVANIZED STEEL41 X
41 X 2.6t
STEEL CHANNEL HOT DIP GALVANIZED STEEL100 x 50 x
5t
EXPANSION ANCHOR3/8"
STAINLESS SHANK BOLT & NUT
PERFORATED CABLE TRAY SUPPORT

EA
EA
SET

Sub Total Fire Alarm Support: LS

65830
65840
65850
65860

Fire Alarm Panels & Boxes


Termination Boxes
TERMINAL BOX FOR FIRE ALARM
40TB
TERMINAL BOX FOR FIRE ALARM
20TB
TERMINAL BOX FOR FIRE ALARM
20TB
TERMINAL BOX FOR FIRE ALARM
5TB

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Quantity

Rate

Amount

65870

Junction Boxes
4" SQUARE BOX

EA

45.00

49.00

2,205.00

65880

4" SQUARE BOX

EA

77.00

49.00

3,773.00

65890
65900

BUSHING & LOCK NUT FOR SQUARE BOX 1"


BUSHING & LOCK NUT FOR SQUARE BOX 1-1/4"

EA
EA

220.00
24.00

15.00
16.00

3,300.00
384.00

Sub Total Junction Boxes: ea

366.00

26.40

9,662.00

3.00

2,740.00

8,220.00

3.00

2,740.00

8,220.00

4.00

2,740.00

10,960.00

Sub Total Fire Alarm Cabinets: LS

1.00

10,960.00

10,960.00

Sub Total Fire Alarm Panels & Boxes: LS

1.00

41,382.00

41,382.00

65910

Fire Alarm Panels


ADDRESSABLE FIRE ALARM PANEL

SET

Sub Total Fire Alarm Panels: Set

65920

Fire Alarm Cabinets


EDIO CABINET WITH 4 EDIO MODULES(400)W X (150)D X SET
(405)H

65930

Fire Alarm Miscellaneous


LINEAR HEAT DETECTOR WITH INTERFACE MODULE

SET

1.00

2,740.00

2,740.00

65940

MISCELLANEOUS FOR FIRE ALRAM SYSTEM

LOT

1.00

136,870.00

136,870.00

Sub Total Fire Alarm Miscellaneous: LS

1.00

139,610.00

139,610.00

Sub Total Fire Alarm System: LS

1.00

1,968,886.00

1,968,886.00

EA
EA

11.00
11.00

120.00
73.00

1,320.00
803.00

Sub Total Grounding Reels: ea

22.00

96.50

2,123.00

161.00

180.00

28,980.00

161.00

180.00

28,980.00

m
m
m
m

5,258.00
8,844.00
2,089.00
435.00

38.00
81.00
38.00
96.00

199,804.00
716,364.00
79,382.00
41,760.00

Sub Total Ground Wire: m

16,626.00

62.39

1,037,310.00

65950
65960

65970

Grounding System
Grounding Reels
GROUND REEL(EXPLOSION PROOF15m LONG
STEEL PLATE FOR GROUND REEL203 x 203 x 13t

Ground Conductors
Ground Rods
GROUNDING ROD WITH CONNECTOR38mmDIA *
1520mmL

SET

Sub Total Ground Rods: Set

65980
65990
66000
66010

Ground Wire
GROUNDING WIRE, ELECTRIC35mm2
GROUNDING WIRE, ELECTRIC.70mm2
GROUNDING WIRE, ELECTRIC.35mm2
GROUNDING WIRE, ELECTRIC.120mm2

Bus Bar

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
66020

66030
66040
66050
66060
66070
66080
66090

66100
66110
66120
66130
66140
66150
66160

66170

Description

Unit

TINNED COPPER GROUNDING BUS BAR6mmT X 50mmW SET


X 356mmL

Quantity

Rate

Amount

67.00

520.00

34,840.00

Sub Total Bus Bar: LS

1.00

34,840.00

34,840.00

Sub Total Ground Conductors: LS

1.00

1,101,130.00

1,101,130.00

EA

59.00

630.00

37,170.00

EA

21.00

630.00

13,230.00

EA

1.00

630.00

630.00

EA

6.00

640.00

3,840.00

EA
EA
EA

2.00
2.00
1.00

630.00
630.00
630.00

1,260.00
1,260.00
630.00

Sub Total Thermal Moulds: ea

92.00

630.65

58,020.00

EA

1,395.00

42.00

58,590.00

EA

344.00

45.00

15,480.00

EA

7.00

53.00

371.00

EA

104.00

56.00

5,824.00

EA
EA
EA

24.00
19.00
4.00

56.00
61.00
56.00

1,344.00
1,159.00
224.00

Sub Total Thermal Welding Powder: ea

1,897.00

43.75

82,992.00

Sub Total Grounding Thermal Welds: LS

1.00

141,012.00

141,012.00

3,515.00

28.00

98,420.00

Sub Total Conduit: m

3,515.00

28.00

98,420.00

866.00
1,130.00
1,130.00

26.00
25.00
8.76

22,516.00
28,250.00
9,898.80

Sub Total Clamps: LS

1.00

60,664.80

60,664.80

Sub Total Grounding System Conduit: LS

1.00

159,084.80

159,084.80

Grounding Thermal Welds


Thermal Moulds
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 70mm2 * TAP: 35mm2
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 70mm2 * TAP: 70mm2
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 120mm2 * TAP: 70mm2
MOLD WITH FRAME FOR GROUND WIRE
CONNECTIONMAIN: 240mm2 * TAP: 240mm2
MOLD WITH FRAMEMAIN: 240mm2 * TAP: 70mm2
MOLD WITH FRAMEMAIN: 240mm2 * TAP: 240mm2
MOLD WITH FRAME MAIN: 70mm2 * TAP: 70mm2

Thermal Welding Powder


THERMAL WELDING POWDER FOR GROUND WIRE
CONNECTION # 45
THERMAL WELDING POWDERFOR GROUND WIRE
CONNECTION# 115
THERMAL WELDING POWDER FOR GROUND WIRE
CONNECTION# 150
THERMAL WELDING POWDER FOR GROUND WIRE
CONNECTION# 150
THERMAL WELDING POWDER# 150
THERMAL WELDING POWDER# 500
THERMAL WELDING POWDER# 150

Grounding System Conduit


Conduit
PVC CONDUIT SCHEDULE 40 PVC
3/4" (22mm)

66180
66190
66200

Clamps
CONDUIT CLAMP ONE HOLE
CONDUIT CLAMP
CONDUIT CLAMP 3/4"

Grounding Support

EA
SET
SET

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
66210
66220
66230
66240

Description

Unit

UNISTRUT CHANNEL
UNISTRUT CHANNEL
STEEL CHANNEL FOR GROUND REEL100 * 50 * 5T
UNISTRUT CLAMP3/4" (22mm)

75.00
75.00
81.00
16.00

13,500.00
675.00
2,187.00
22,336.00

Sub Total Grounding Support: LS

1.00

38,698.00

38,698.00

2,385.00

67.00

159,795.00

11.00
7.00

88.00
270.00

968.00
1,890.00

1.00

162,653.00

162,653.00

58.00

850.00

49,300.00

1.00

49,300.00

49,300.00

2.00

840.00

1,680.00

Sub Total Bonding Boxes: LS

1.00

1,680.00

1,680.00

Sub Total Grounding Boxes: LS

1.00

50,980.00

50,980.00

EA
EA

1,365.00
335.00

46.00
54.00

62,790.00
18,090.00

EA

18.00

46.00

828.00

Sub Total Servit Posts: ea

1,718.00

47.56

81,708.00

EA
EA

58.00
12.00

120.00
93.00

6,960.00
1,116.00

Sub Total Fence Post Grounding Connector: ea

70.00

115.37

8,076.00

EA

12.00

730.00

8,760.00

Sub Total Copper Braid: ea

12.00

730.00

8,760.00

Sub Total Grounding Connectors: LS

1.00

98,544.00

98,544.00

SET

198.00

320.00

63,360.00

SET

2,089.00

54.00

112,806.00

EA
SET

145.00
44.00

51.00
25.00

7,395.00
1,100.00

m3

66260
66270

BASE CONCRETE FOR GROUND REEL305 x 305 x 5t


GROUNDING CABLE ROUTE MARKERSHEET

EA
SET

Sub Total Grounding System Civil Work: LS


Grounding Boxes
Concrete Boxes
GROUND WELLCONCRETE BOX TYPE267mm 438mm
305mm (EA)

SET

Sub Total Concrete Boxes: LS

66300
66310
66320

66330
66340

66350

66360
66370
66380
66390

Amount

180.00
9.00
27.00
1,396.00

Grounding System Civil Work


EXCAVATION & BACK FILL WORK

66290

Rate

EA
EA
m
EA

66250

66280

Quantity

Bonding Boxes
GROUND BONDING BOX

SET

Grounding Connectors
Servit Posts
CONNECTION SERVIT POST
CONNECTION SERVIT POST 25-70 mm1/2"-13 x 3/4"
STUD
CONNECTION SERVIT POST FOR TRANSFORMER

Fence Post Grounding Connector


FENCE POST GROUNDING CONECTOR2"
FENCE POST GROUNDING CONECTOR1-1/2"

Copper Braid
COPPER BRAID FOR FENCE GATE GROUND1"W x 12"L

Grounding Accessories
AIR TERMINALCOPPER WITH NICKEL 5/8"(DIA) 1'(LONG)
(EA)
SUPPORT FOR LIGHTNING CONDUCTOR CLIP TYPE 35
mm2
GROUND LUG (WITH/15mm HOLE)128 x 50 x 6t
HEX HEAD BOLT, SPRING NUT AND LOCK WASHER1/4" x
20mm

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
66400
66410
66420
66430
66440
66450
66460
66470
66480
66490
66500
66510
66520
66530
66540
66550
66560
66570
66580

66590
66600
66610
66620
66630
66640
66650
66660

Description

Unit

MOUNTING BASE250 x 250 x 6T


WARINING SIGN STEEL PLATE 76 x 76 x 6t
MISCELLANEOUS FOR GROUNDING SYSTEM
EXPANSION ANCHOR,1/2" - 30
STANDOFF INSULATOR FOR GROUNDING BUS BAR
ALL THREAD ROD1/2"-13 x 4"L
EXPANSION ANCKOR,1/2"-20
1/2" MACHINE BOLT1/2"-20
1/2" NUT, HEX1/2"-13
1/2" LOCKWASHER
1/2" LOCKWASHER
PARALLEC CLAMP FOR LIGHTNING DOWN
CONDUCTOR35 mm
SUPPORT FOR AIR TERMINAL(OUTSIDE)
MACHINE BOLT1/2" x 20mm
ANCHOR BOLT
ANCHOR BOLT
MACHINE BOLT 1/2" x 20mm
ANCHOR BOLT 1/2" x 30mm
ANCHOR BOLT 1/2" x 30mm

66710
66720

66730
66740
66750

Rate

Amount

EA
EA
LOT
EA
EA
EA
EA
EA
EA
EA
EA
EA

198.00
11.00
1.00
44.00
84.00
84.00
134.00
134.00
335.00
413.00
80.00
48.00

230.00
57.00
41,760.00
24.00
63.00
18.00
17.00
9.72
9.72
8.96
8.96
51.00

45,540.00
627.00
41,760.00
1,056.00
5,292.00
1,512.00
2,278.00
1,302.48
3,256.20
3,700.48
716.80
2,448.00

SET
SET
EA
EA
SET
EA
EA

8.00
96.00
33.00
59.00
96.00
33.00
59.00

510.00
9.72
37.00
37.00
8.76
8.76
8.76

4,080.00
933.12
1,221.00
2,183.00
840.96
289.08
516.84

Sub Total Grounding Accessories: LS

1.00

304,213.96

304,213.96

Sub Total Grounding System: LS

1.00

2,058,438.76

2,058,438.76

1.00
1.00
2.00
2.00
4.00
20.00
69.00
4.00

2,180.00
2,180.00
2,180.00
2,180.00
190.00
92.00
300.00
300.00

2,180.00
2,180.00
4,360.00
4,360.00
760.00
1,840.00
20,700.00
1,200.00

1.00

37,580.00

37,580.00

m
m
m
m

129.00
352.00
261.00
3,028.00

29.00
20.00
20.00
14.00

3,741.00
7,040.00
5,220.00
42,392.00

Sub Total Telephone System Cabling: m

3,770.00

15.49

58,393.00

m
m

1,550.00
146.00

34.00
28.00

52,700.00
4,088.00

Sub Total Conduit: m

1,696.00

33.48

56,788.00

EA
EA
EA

74.00
776.00
74.00

8.76
16.00
17.00

648.24
12,416.00
1,258.00

Sub Total Clamps: ea

924.00

15.50

14,322.24

Communications System
Telephone System
Telephone System Equipment
19" EQPT CABINET
19" EQPT CABINET
19" EQPT CABINET
19" EQUT CABINET
TELEPHONE HANDSET ASSEMBLY
INDOOR TELEPHONE HANDSET
STATION TERMINAL OUTLET4 PORT TYPE, RJ45
TELEPHONE OUTLETINDOOR 4 PORT

SET
SET
SET
SET
EA
EA
EA
EA

Sub Total Telephone System Equipment: LS

66670
66680
66690
66700

Quantity

Telephone System Cabling


TELEPHONE CABLE, ELECTRIC50P-0.75mm2
TELEPHONE CABLE, ELECTRIC10P-0.75mm2
TELEPHONE CABLE, ELECTRIC4P-0.75mm2
UTPCAT NO.6, 4 PAIRS, UNARMORED

Telephone System Conduit


Conduit
RIGID STEEL CONDUITHOT DIP GALVANIZED3/4"
PVC CONDUIT SCHEDULE 40WITH3/4"

Clamps
UNISTRUT CLAMP 3/4"
UNISTRUT CLAMP HOT DIP GALVANIZED3/4"
UNISTRUT CLAMP

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Telephone System Conduit: LS

66760

66770

66790

66800

66810
66820
66830
66840
66850
66860

66870
66880

66890
66900

66910

Rate

Amount

1.00

71,110.24

71,110.24

m3

589.00

67.00

39,463.00

Sub Total Telephone System Civil Work: LS

1.00

39,463.00

39,463.00

73.00

49.00

3,577.00

73.00

49.00

3,577.00

79.00

75.00

5,925.00

EA

405.00

37.00

14,985.00

Sub Total Telephone System Support: LS

1.00

20,910.00

20,910.00

1.00

65,920.00

65,920.00

Sub Total Telephone System Miscellaneous: LS

1.00

65,920.00

65,920.00

Sub Total Telephone System: LS

1.00

296,953.24

296,953.24

SET
SET
SET

4.00
4.00
4.00

2,870.00
2,870.00
1,990.00

11,480.00
11,480.00
7,960.00

SET
SET

5.00
1.00

1,990.00
1,990.00

9,950.00
1,990.00

EA

1.00

350.00

350.00

Sub Total Computer Equipment: LS

1.00

43,210.00

43,210.00

m
m

897.00
299.00

11.00
23.00

9,867.00
6,877.00

Sub Total Computer Cabling: m

1,196.00

14.00

16,744.00

Computer Panels
FIBER OPTIC PATCH PANELW800 X D630 X H2000
EA
FIBER OPTIC PATCH PANELINDOOR USEFOPP MODULE EA

1.00
12.00

2,870.00
1,990.00

2,870.00
23,880.00

Sub Total Computer Panels: LS

1.00

26,750.00

26,750.00

1.00

61,620.00

61,620.00

1.00

61,620.00

61,620.00

Telephone System Civil Work


EXCAVATION & BACK FILL WORK

Telephone System Junction Boxes


4" SQUARE BOXZINC ELECTRO PLATE

SET

Sub Total Telephone System Junction Boxes: Set

66780

Quantity

Telephone System Support


UNISTRUT CHANNELHOT DIP GALVANIZED STEEL41 X
41 X 2.6t
EXPANSION ANCHOR3/8"

Telephone System Miscellaneous


MISCELLANEOUS FOR TELEPHONE SYSTEM

Computer System
Computer Equipment
LAN/IP SYSTEM COMPONENTINDOOR
LAN/IP SYSTEM COMPONENT48PORT ACCESS SWITCH
LAN/IP SYSTEM COMPONENT24PORT UTP PATCH
PANEL
LAN/IP SYSTEM COMPONENTUPS MODULEADELMO
LAN/IP SYSTEM COMPONENTANALOGUE PHONE
GATEWAYCISCO
PERSONAL COMPUTERFOR WEATHER MONITRING
SYSTEM

Computer Cabling
FIBER OPTIC CABLESINGLE MODE4C
FIBER OPTIC CABLESINGLE MODE, PVC INSULATED,
STEEL WIRE ARMOURED48C

Computer Miscellaneous
MISCELLANEOUS FOR LAN SYSTEM

LOT

LOT

Sub Total Computer Miscellaneous: LS

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

Description

Unit

Sub Total Computer System: LS

66920
66930
66940
66950
66960
66970
66980
66990
67000
67010
67020

67060
67070

67080
67090
67100

67110
67120
67130

Amount

148,324.00

148,324.00

SET

1.00

8,980.00

8,980.00

SET

1.00

8,390.00

8,390.00

EA
EA
EA

1.00
2.00
17.00

3,040.00
2,150.00
380.00

3,040.00
4,300.00
6,460.00

EA

33.00

340.00

11,220.00

EA
EA
SET
SET
SET

47.00
1.00
10.00
2.00
2.00

340.00
200.00
170.00
2,650.00
1,700.00

15,980.00
200.00
1,700.00
5,300.00
3,400.00

1.00

68,970.00

68,970.00

m
m
m

6,655.00
228.00
285.00

16.00
40.00
47.00

106,480.00
9,120.00
13,395.00

Sub Total Cable: m

7,168.00

18.00

128,995.00

EA
EA

45.00
45.00

6.34
6.34

285.30
285.30

Sub Total Cable Gland: ea

90.00

6.34

570.60

Sub Total Paging System Cabling: LS

1.00

129,565.60

129,565.60

m
m
EA

1,785.00
703.00
36.00

34.00
28.00
0.00

60,690.00
19,684.00
0.00

Sub Total Conduit: LS

1.00

80,374.00

80,374.00

m
EA
EA

893.00
1,207.00
1,207.00

16.00
17.00
8.76

14,288.00
20,519.00
10,573.32

Sub Total Clamps: LS

1.00

45,380.32

45,380.32

Sub Total Paging System Conduit: LS

1.00

125,754.32

125,754.32

Paging System
Paging System Equipment
CENTRAL PAGING EQUIPMENTTYCO MODEL NO.ACE
100INDOOR
REMOTE PAGING EQUIPMENTTYCO MODEL NO.ACE
100RAINDOOR
EE872 DIGITAL HAND SET MASTER STATION
HAND SET STATION EXPLOSION PROOF
CONE SPEAKER ASSEMBLY (FOR PAGING)INDOOR
USE6W
CONE SPEAKER ASSEMBLY (FOR PAGING)INDOOR
USE6W
HORN SPEAKER ASSEMBLY15W
BEACON LAMP
HAND HELD RADIOOUTDOOR USE
MOBILE RADIOVEHICLES USETRANSMITTER
BATTERY CHARGER FOR RADIO SYSTEMINDOOR

Paging System Cabling


Cable
COMMUNICATION CABLE, ELECTRIC1P-2.5mm2
COMMUNICATION CABLE, ELECTRIC 2C - 2.5mm2
COMMUNICATION CABLE, ELECTRIC2P- 1.5mm2

Cable Gland
CABLE GLAND, NICKEL PLATEWEATHER PROOF3/4"
CABLE GLAND, NICKEL PLATEEXPLOSION PROOF3/4"

Paging System Conduit


Conduit
RIGID STEEL CONDUIT HOT DIP GALVANIZED3/4"
PVC CONDUITSCHEDULE 40 3/4"
FLEXIBLE METALLIC CONDUIT INDOOR 3/4"

Clamps
UNISTRUT CLAMP HOT DIP GALVANIZED 3/4"
UNISTRUT CLAMP HOT DIP GALVANIZED STEEL
CLAMP 3/4"

Paging System Support

Rate

1.00

Sub Total Paging System Equipment: LS

67030
67040
67050

Quantity

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
67140
67150
67160

67170

67180

Description

Unit

UNISTRUT CHANNEL HOT DIP GALVANIZED STEEL41 X


41 X 2.6t
HANDSET SUPPORT
SPEAKER SUPPORTWITH

67200
67210
67220
67230

67240
67250
67260

67270
67280
67290

Amount
75.00

17,475.00

2.00
4.00

530.00
250.00

1,060.00
1,000.00

Sub Total Paging System Support: LS

1.00

19,535.00

19,535.00

Paging System Civil Work


EXCAVATION & BACK FILL WORK FOR PAGING SYSTEM m3

130.00

67.00

8,710.00

Sub Total Paging System Civil Work: LS

1.00

8,710.00

8,710.00

82.00

49.00

4,018.00

1.00

4,018.00

4,018.00

1.00

73,980.00

73,980.00

Sub Total Paging System Miscellaneous: LS

1.00

73,980.00

73,980.00

Sub Total Paging System: LS

1.00

430,532.92

430,532.92

Sub Total Communications System: LS

1.00

875,810.16

875,810.16

9.00

970.00

8,730.00

EA
EA
EA

854.00
848.00
58.00

44.00
12.00
12.00

37,576.00
10,176.00
696.00

Sub Total Heat Tracing Equipment: LS

1.00

57,178.00

57,178.00

m
m

19,120.00
167.00

12.00
12.00

229,440.00
2,004.00

37,820.00

35.00

1,323,700.00

Sub Total Cable: m

57,107.00

27.23

1,555,144.00

6.00
70.00
4,800.00

44.00
22.00
7.37

264.00
1,540.00
35,376.00

Sub Total Cable Accessories: LS

1.00

37,180.00

37,180.00

Sub Total Heat Tracing Cabling: LS

1.00

1,592,324.00

1,592,324.00

SET
SET

SET

Sub Total Paging System Junction Boxes: LS

67190

Rate

233.00

Paging System Junction Boxes


4" SQUARE BOXZINC ELECTRO PLATE

Quantity

Paging System Miscellaneous


MISCELLANEOUS FOR PA SYSTEM

LOT

Heat Tracing System


Heat Tracing Equipment
TRANSFORMER ( ELECTRICAL HAET TRACING
SYSTEM)DRY TYPE
THERMOSTAT SENSOR
CIRCUIT FABRICATION KIT
POWER TERMINATION KITOUTDOOR

Heat Tracing Cabling


Cable
SELF REGULATING HEATING CABLE
MINERAL INSULATED CABLE THERMON CAT NO. MIQ
SERIES
POWER CABLE, ELECTRIC 3/C * 4mm2

Cable Accessories
COLD & HOT LEAD FOR MI CABLE
ALUMINUM TAPE THERMON
CAUTION LABELTHERMON

Heat Tracing Cable Tray


Cable Tray

SET

EA
ROLL
EA

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
67300

67310
67320
67330
67340
67350
67360
67370
67380
67390
67400

67410

67420

Description

Unit

PERFORATED CABLE TRAYPUNCHED TYPE100mmW X


50mmH X

67480
67490
67500

Amount

12,810.00

32.00

409,920.00

Sub Total Cable Tray: m

12,810.00

32.00

409,920.00

EA
EA

35.00
70.00

57.00
12.00

1,995.00
840.00

EA

13.00

18.00

234.00

EA

4.00

18.00

72.00

EA

4.00

18.00

72.00

EA

13.00

12.00

156.00

EA

4.00

12.00

48.00

EA
EA
EA

4.00
252.00
286.00

12.00
8.54
22.00

48.00
2,152.08
6,292.00

Sub Total Cable Tray Accessories: LS

1.00

11,909.08

11,909.08

Sub Total Heat Tracing Cable Tray: LS

1.00

421,829.08

421,829.08

M3

10.00

5,210.00

52,100.00

Sub Total Heat Tracing Civil Work: LS

1.00

52,100.00

52,100.00

9.00

750.00

6,750.00

1.00

6,750.00

6,750.00

35.00
600.00
144.00

520.00
230.00
37.00

18,200.00
138,000.00
5,328.00

1.00

161,528.00

161,528.00

EA
EA

244.00
4.00

100.00
44.00

24,400.00
176.00

Sub Total Heat Tracing Junction Boxes: LS

1.00

24,576.00

24,576.00

95.00
1,300.00
1.00

11.00
12.00
42,110.00

1,045.00
15,600.00
42,110.00

1.00

58,755.00

58,755.00

Cable Tray Accessories


CABLE TRAYSTRAIGHT600mmW
TRAY COVER (FOR STRAIGHT) VENTILATED
TYPE600mmW
VERTICAL ELBOW (90),(R = 600 mm),(OUTSIDE
TYPE)600mmW
VERTICAL ELBOW (90),(R = 600 mm),(IN SIDE
TYPE)600mmW
HORIZONTAL ELBOW (90),(R = 600 mm)
TRAY COVER (FOR VERTICAL ELBOW OUTSIDE TYPE)
600mmW
TRAY COVER (FOR VERTICAL ELBOW INSIDE
TYPE)600mmW
TRAY COVER (FOR HORIZONTAL ELBOW)600mmW
CABLE TRAY COVER CLAMPS
CABLE TRAY HOLE DOWN CLAMPS

Heat Tracing Civil Work


NON-SHRINK GROUT

Heat Tracing Panels


ELECTRICAL HEAT TRACING CONTROL PANEL( 36 )CKT SET

Heat Tracing Support


CABLE TRAY SUPPORT
PERFORATED CABLE TRAY SUPPORT
ANCHOR BOLT STAINLESS STEEL, M12, 600mmL

SET
SET
EA

Sub Total Heat Tracing Support: LS

67460
67470

Rate

Sub Total Heat Tracing Panels: LS

67430
67440
67450

Quantity

Heat Tracing Junction Boxes


JUNCTION BOX EXPLOSION PROOF
BLIND END PLATES600mmW

Heat Tracing Miscellaneous


METALLIC TEE CONNECTION KITOUTDOOR
POLYESTER FIBER TAPE THERMON
MISCELLANEOUS FOR ELECTRICAL HAET TRACING
SYSTEM

EA
ROLL
LOT

Sub Total Heat Tracing Miscellaneous: LS

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

70000
70010
70020
70030
70040
70050
70060
70070
70080

70090
70100
70110
70120
70130
70140
70150
70160
70170
70180
70190
70200
70210
70220
70230
70240
70250
70260
70270

70280
70290
70300

70310
70320
70330
70340
70350
70360

Description

Unit

Amount

1.00

2,375,040.08

2,375,040.08

Sub Total Electrical Systems: LS

1.00

35,884,973.16

35,884,973.16

EA
EA
EA
EA
EA
EA
EA
EA
EA

3.00
3.00
3.00
1.00
1.00
80.00
20.00
3.00
10.00

1,370.00
980.00
1,060.00
1,060.00
1,060.00
160.00
160.00
160.00
1,370.00

4,110.00
2,940.00
3,180.00
1,060.00
1,060.00
12,800.00
3,200.00
480.00
13,700.00

Sub Total Analyzer: ea

124.00

342.98

42,530.00

EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA
EA

105.00
107.00
12.00
4.00
53.00
5.00
108.00
5.00
32.00
19.00
97.00
213.00
179.00
188.00
54.00
54.00
225.00
475.00
17.00

210.00
120.00
220.00
230.00
230.00
230.00
210.00
360.00
360.00
400.00
210.00
140.00
210.00
210.00
75.00
67.00
260.00
260.00
260.00

22,050.00
12,840.00
2,640.00
920.00
12,190.00
1,150.00
22,680.00
1,800.00
11,520.00
7,600.00
20,370.00
29,820.00
37,590.00
39,480.00
4,050.00
3,618.00
58,500.00
123,500.00
4,420.00

Sub Total Field Instruments: ea

1,952.00

213.49

416,738.00

87.00
50.00
2.00

1,040.00
490.00
490.00

90,480.00
24,500.00
980.00

Sub Total Computer System: LS

1.00

115,960.00

115,960.00

Sub Total Instrument Equipment: LS

1.00

575,228.00

575,228.00

52,500.00
7,500.00
7,500.00
15,000.00
34,000.00
2,800.00

1.62
1.62
1.62
22.00
24.00
11.00

85,050.00
12,150.00
12,150.00
330,000.00
816,000.00
30,800.00

Field Instruments
ORIFICE PLATE & ASSEMBLY
ORIFICE PLATE ONLY
INTEGRAL ORIFICE
PITOT TUBE, ANNUBAR
FLOWMETER
VARIABLE AREA METER
PRESSURE & D/P TRANSMITTER
CAPACITANCE TYPE LEVEL
LEVEL GAUGE
RADAR TYPE LEVEL
PRESSURE & D/P TRANSMITTER
PRESSURE GAUGE
PRESSURE & D/P TRANSMITTER
TEMPERATURE INSTRUMENT
BIMETALLIC THERMOMETER
TEST THERMOWELL
CONTROL VALVE
ON-OFF VALVE
PRESSURE REGULATING

Instrument Cable
Cable
SIGNAL CABLES
SIGNAL CABLES
SIGNAL CABLES
MULTI CABLE
MULTI CABLE
FIBER OPTICAL

Rate

Sub Total Heat Tracing System: LS

Instrumentation Work
Instrument Equipment
Analyzer
ANALYZER
ELECTROCHEMICAL ANALYZER
CONDUCTIVITY ANALYZER
OXYGEN ANALYZER
DENSITY ANALYZER
GAS DETECTOR
FLAME DETECTOR
INDICATOR
MISCELLANEOUS FOR RECEIVER INST.

Computer System
COMPUTER SYSTEM
LOCAL CONTROL BOX
MMS, PDC

Quantity

set
EA
SET

m
m
m
m
m
m

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
70370
70380
70390
70400
70410
70420
70430
70440
70450
70460
70470
70480
70490

70500
70510
70520
70530
70540
70550

70560
70570

Description
MULTI CABLE
MULTI CABLE
MULTI CABLE
MULTI CABLE
MULTI CABLE
MULTI CORE
MULTI CORE
MULTI CORE
MULTI CORE
SINGLE CORE
SINGLE CORE
MULTI CORE
MULTI CORE

Unit
m
m
m
m
m
m
m
m
m
m
m
m
m

70600
70610
70620
70630

70640
70650
70660
70670
70680
70690

Amount
21.00
5.66
21.00
9.61
10.00
2.59
7.30
11.00
17.00
3.33
3.36
4.65
4.65

147,000.00
186,780.00
147,000.00
19,220.00
40,000.00
97,125.00
36,500.00
55,000.00
136,000.00
14,985.00
5,040.00
125,550.00
6,975.00

Sub Total Cable: LS

262,300.00

8.78

2,303,325.00

EA
EA
EA
EA
EA
EA

4,449.00
1,438.00
94.00
86.00
118.00
55.00

23.00
26.00
29.00
31.00
48.00
56.00

102,327.00
37,388.00
2,726.00
2,666.00
5,664.00
3,080.00

Sub Total Cable Gland: ea

6,240.00

24.66

153,851.00

Sub Total Instrument Cable: LS

1.00

2,457,176.00

2,457,176.00

610.00
580.00

29.00
85.00

17,690.00
49,300.00

1.00

66,990.00

66,990.00

m
m

5.00
279.00

17.00
24.00

85.00
6,696.00

Sub Total Pipe Straight: m

284.00

23.88

6,781.00

EA
EA
EA
EA

42.00
68.00
62.00
211.00

580.00
670.00
40.00
40.00

24,360.00
45,560.00
2,480.00
8,440.00

Sub Total Pipe Fittings: LS

1.00

80,840.00

80,840.00

Sub Total Pipe: LS

1.00

87,621.00

87,621.00

4,712.00
36.00
102.00
1,464.00
16,872.00
760.00

24.00
20.00
26.00
16.00
24.00
25.00

113,088.00
720.00
2,652.00
23,424.00
404,928.00
19,000.00

Cable Gland
CABLE GLAND, 1/2"
CABLE GLAND, 3/4"
CABLE GLAND, 1-1/4"
CABLE GLAND, 1-1/2"
CABLE GLAND, 2"
CABLE GLAND, 2-1/2"

Instrument Conduit & Tubing


Conduit
PVC CONDUIT
PVC CONDUIT

Pipe
Pipe Straight
PIPE, 1/2"
PIPE, 1"

Pipe Fittings
AIR MANIFOLD HEADER, 8 POLE
AIR MANIFOLD HEADER, 12 POLE
SEAL POT
DRIP POT

Tubing
TUBE, 1/2"
TUBE, 1/4"
TUBE, 3/4"
TUBE, 3/8"
TUBE, 1/2"
TUBE, PRE-INSULATED, 3/8"

Rate

7,000.00
33,000.00
7,000.00
2,000.00
4,000.00
37,500.00
5,000.00
5,000.00
8,000.00
4,500.00
1,500.00
27,000.00
1,500.00

PCS
m
Sub Total Conduit: LS

70580
70590

Quantity

m
m
m
m
m
m

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
70700

Description
TUBE, PRE-INSULATED, 3/8"

Unit

70940
70950
70960
70970
70980
70990

71000
71010
71020
71030
71040

Amount

260.00

25.00

6,500.00

Sub Total Tubing: m

24,206.00

23.56

570,312.00

1.00

724,923.00

724,923.00

110.00
15.00
90.00
52.00
224.00
127.00
440.00
3,903.00
3,191.00
1,890.00
1,417.00
1,980.00

70.00
70.00
70.00
70.00
70.00
70.00
70.00
36.00
39.00
41.00
44.00
46.00

7,700.00
1,050.00
6,300.00
3,640.00
15,680.00
8,890.00
30,800.00
140,508.00
124,449.00
77,490.00
62,348.00
91,080.00

1.00

569,935.00

569,935.00

EA

3.00
4.00
1.00
4.00
11.00
12.00
102.00
804.00
240.00
261.00
151.00

350.00
380.00
450.00
500.00
550.00
590.00
67.00
67.00
67.00
67.00
67.00

1,050.00
1,520.00
450.00
2,000.00
6,050.00
7,080.00
6,834.00
53,868.00
16,080.00
17,487.00
10,117.00

Sub Total Cable Transit: LS

1.00

122,536.00

122,536.00

EA
EA
EA
EA
EA
EA

13.00
68.00
5.00
32.00
36.00
102.00

170.00
230.00
300.00
370.00
430.00
500.00

2,210.00
15,640.00
1,500.00
11,840.00
15,480.00
51,000.00

Sub Total Junction Box: ea

256.00

381.52

97,670.00

EA
EA
EA
EA
EA

1.00
6.00
4.00
9.00
26.00

270.00
380.00
610.00
730.00
840.00

270.00
2,280.00
2,440.00
6,570.00
21,840.00

Sub Total Enclosures: ea

46.00

726.09

33,400.00

Sub Total Junction Box & Enclosures: LS

1.00

131,070.00

131,070.00

Cable Tray & Fitting


CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY, LADDER TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE
CABLE TRAY,PERFORATED TYPE

PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS
PCS

Sub Total Cable Tray & Fitting: LS

70830
70840
70850
70860
70870
70880
70890
70900
70910
70920
70930

Rate

Sub Total Instrument Conduit & Tubing: LS

70710
70720
70730
70740
70750
70760
70770
70780
70790
70800
70810
70820

Quantity

Cable Transit
CABLE TRANSIT, SF-6
CABLE TRANSIT, SF-6x2
CABLE TRANSIT, SF-6x3
CABLE TRANSIT, SF-6x4
CABLE TRANSIT, SF-6+6x5
CABLE TRANSIT, SF-6+6x6
MCT BLOCK, 20Wx20HX60D
MCT BLOCK, 30Wx30HX60D
MCT BLOCK, 40Wx40HX60D
MCT BLOCK, 60Wx60HX60D
MCT BLOCK, 90Wx90HX60D

Junction Box & Enclosures


Junction Box
JUNCTION BOX, 16P
JUNCTION BOX, 28P
JUNCTION BOX, 36P
JUNCTION BOX, 40P
JUNCTION BOX, 54P
JUNCTION BOX, 80P

Enclosures
FIRE PROOFING ENCLOSURE, 16P
FIRE PROOFING ENCLOSURE, 28P
FIRE PROOFING ENCLOSURE, 40P
FIRE PROOFING ENCLOSURE, 54P
FIRE PROOFING ENCLOSURE, 80P

EA
LOT
EA
EA
EA
EA
EA
EA
EA

Bill Of Quantities
Process Plant Project Bill of Quantities
Item

71050
71060
71070
71080
71090
71100
71110
71120
71130
71140
71150
71160
71170
71180

Description

Unit

Support & Hardware


STANCHION, 2" PIPE, HDG
STANCHION, 2" PIPE, HDG
ANGLE, STEEL FOR TRAY
ANGLE, STEEL FOR PIPE, TUBE
ANGLE, STEEL FOR JB
CHANNEL, STEEL
SUNSHADE
SUPPORTING MISCELLANEOUS
NON SHRINK GROUT
EXCAVATION & BACKFILLING WORK
SANDFILLING & COMPACTION WORK
RED CONCRETE PROTECTIVE COVER
WARNING TAPE
SUPPORTING MISCELLANEOUS

EA
EA
m
m
m
m
EA
EA
M3
M3
M3
EA
SET
LOT

80000

90000

Rate

Amount

976.00
70.00
10,212.00
1,162.00
2,640.00
22,265.00
1,010.00
5,000.00
10.00
2,552.00
850.25
7,362.20
48.30
1.00

1,180.00
900.00
200.00
200.00
200.00
310.00
750.00
85.00
10,570.00
13.00
47.00
7.39
8.76
1,557,850.00

1,151,680.00
63,000.00
2,042,400.00
232,400.00
528,000.00
6,902,150.00
757,500.00
425,000.00
105,700.00
33,176.00
39,961.75
54,406.66
423.11
1,557,850.00

1.00

13,893,647.52

13,893,647.52

4,882.00

230.00

1,122,860.00

Sub Total Loop Test : LS

1.00

1,122,860.00

1,122,860.00

Sub Total Instrumentation Work: LS

1.00

19,597,375.52

19,597,375.52

LS

1.00

31,534,920.00

31,534,920.00

Sub Total Insulation Work: LS

1.00

31,534,920.00

31,534,920.00

m2

13,395.50

15.00

200,932.50

Sub Total Cleaning: m2

13,395.50

15.00

200,932.50

Sub Total Support & Hardware: LS

71190

Quantity

Loop Test
LOOP TEST

Loop

Insulation Work
SUBCONTRACT INSULATIOM WORKS

Painting Work
Cleaning
Solvent cleaning

90010
90020
90030
90040
90050
90060
90070
90080
90090
90100

Painting
Sa 2 1/2 Painting
SP, Surface tolerant, Epoxy Mastic, self priming, high solid
Acrylic Polyurethane-Gloss
Epoxy High Build Polyamide with Micaecous Iron Oxide
Acylic Polyurethane-Gloss
HT one pack Silicone coating
Sa 3 Painting
SP/HS Epoxy Phenolic
Inorganic Zinc Silicate(IZS) primer
SP, Surface tolerant, Epoxy Mastic, self priming, high solids

m2
m2
m2
m2
m2
m2
m2
m2
m2
m2

19,500.00
1,031.70
1,031.70
3,611.00
3,611.00
958.00
2,549.90
8,400.00
13,200.00
13,395.50

71.00
19.00
8.39
19.00
8.39
7.64
74.00
15.00
13.00
19.00

1,384,500.00
19,602.30
8,655.96
68,609.00
30,296.29
7,319.12
188,692.60
126,000.00
171,600.00
254,514.50

90110
90120

Acrylic Polyurethane-Gloss
All Systems Paint

m2
m2

13,395.50
3,325.00

8.39
18.00

112,388.25
59,850.00

Sub Total Painting: m2

84,009.30

28.95

2,432,028.02

36.00

6,810.00

245,160.00

1.00

245,160.00

245,160.00

90130

Galvanizing
HDG after shop fabrication, Galvanizing

Ton
Sub Total Galvanizing: LS

Line Marking

Bill Of Quantities
Process Plant Project Bill of Quantities
Item
90140

Description

Unit

[Line marking, Identification & Lettering for piping,


Equipment(including insulation items)

Quantity

Rate

Amount

Lot

1.00

227,770.00

227,770.00

Sub Total Line Marking: LS

1.00

227,770.00

227,770.00

Sub Total Painting Work: LS

1.00

3,105,890.52

3,105,890.52

Sub Total Process Plant Direct Costs: LS

1.00

266,395,230.02

266,395,230.02

Grand Total: LS

1.00

266,395,230.02

266,395,230.02

You might also like