Rough Cost estimate of box type Storm watwer drain size 3.0 m X 2.

5 m , along NH-71-B & NH-8 upto Barrage on Sahibi River, starting from Alwar road T- Point
All quantities are tentative Length 1.0 M 1. E/Work Excavation by mechanical Means/Manual Means including disposal. Of surplus earth up to 50 m, leveled & dressed complete in all respect.

Average width of excavation Average depth of excavation

= =

6.0 m 4.0 m

1 X 6 X 4 =24 cum@ 12/cum=2688/-

2. P.CC :- M-10 grade nominal mix(1:3:6) with 40 mm size stone aggregate 1 X 4.20 X 0.15 2774/cum = 1748/= 0.63 Cum @

3. Prody & layingM- 20 nominal mix. in RCC structure up to plinth level i/c Curing, compaction, finishing, rendering with cement sand mortar 1:3 making good joints excluding centering, Shuttering & reinforcement

(1 X 3.60 X 3.10 1 X 3.0 X 2.50) = 11.16 7.50 = 3.66 Cum@X 4025/cum = 14732/-

4. Centering & shuttering with steel sheets i/c shuttering propping, bracing both ways & removal etc.for foundation, footing raft etc. 2 X 1 X 0.15 = 3.00 2 X 1 X 3.10 = 6.20 2 X 1 X 2.8 1 X 3.0 = 5.60 = 3.00 17.80 Sgm @ 118/sqm = 2100/-

5. Reinforcement for RCC work i/c straitening, cutting, bending, binding& placing in position i/c cost of binding wire complete in all respect. @ 100 kg /M3 = 3.66 X 100 = 366 KG @ 64/kg = 23424/-

6. Miscellaneous ( Manholes covers, culverts, shifting of sewers) repair, rebuilt construction of off take structures etc. (L/S) =Rs 1000/m Total cost = Rs. 45692/mtr Say=Rs. 46000/mtr

DIMENTLING:7. Dismantling of manually or mechanically i/c stacking of serviceable material & disposal of un serviceable material as per direction of E.I.C a. W.B.M road ( avg. Th. 250 mm) = 1.8 + 1.2 = 3.0 km b. Bituminous road ( avg. TH. 300 mm) =1.8 + 1.2 = 3.0 km 3000 X 6.0 = 18000 sqm@ 33/sqm = 594000/3000 x 6.0 = 18000 sqm @ 64/sqm = 1152000/-

8. Dismantling of C.C road manually or mechanically i/c stacking of serviceable material and disposal of unserviceable material as per direction of E.I.C

C.C Road (a) PCC 1 : 3 : 6 =1.2 Km

(b)

C.C 1 : 1 :3 = 1.2 km

1200 X 6.0 X 0.20 = 1440 cum 1200 X 6.0 X 0.30 = 2160 cum 3600 cum @353/cum= 1270800/Tota cost of dismantling roads = 3016800/Say 30 lacs

9. Road cut charges to be deposited with NHA / HUDA or other authorities available. Bituminous road = 18000 m2 @ ------Concrete Road = 7200 m2 @ -------Abstract of cost 1. Cost of construction of RCC Box type drain along NH-71 B & NH-8 from Alwar road Tee-point to Barrage at Sahibi River. Length = 6500 mtr @ 46000 / mtr = 299000000 Say = 3000 lacs 2. Dismantling of C.C / Bituminous road = 30.0 lac 3. Road cut charges. = --------