Professional Documents
Culture Documents
DOCUMENT NO:
LS-TSZD-- QJ 005
UEEPL
Utility Energytech and Engineers Pvt. Ltd. Ground Floor, H-146/147 Sector-63 Noida 201 307 Uttar Pradesh DEVELOPMENT CONSULTANTS PRIVATE LIMITED CONSULTING ENGINEERS 24B, PARK STREET, KOLKATA - 700 016, INDIA TPSC (INDIA) PRIVATE LIMITED A-1 Module, D-Quadrant, 2nd Floor Cyber Towers, Hi-Tec City, Hyderabad-81 Shanghai Electric Group Co. Ltd. No. 8 , Xingyi Road. Shanghai China - 200336 Tianjin Electric Power Construction Company The 26th floor, Harbor Centre ,No. 240 Zhangzizhong Road, Heping district, Tianjin P.R.China p.c:300041
PROJECT
CLIENT
DOCUMENT TITLE
DOCUMENT
NO.
LS-TSZD-- QJ005
REV. NO.
ENDORSEMENTS
Rev No
Date
Description
Initials
Sgn.
Initials
Sgn.
Reviewed by
Approved by
DOCUMENT NO.
LS-TSZD-- QJ005
Page 1 of 23
Trained person
DOCUMENT NO.
LS-TSZD-- QJ005
Page 2 of 23
Contents
1. Project overview and work quantity ...........................................................................................4 1.1 Project overview ............................................................................................................................4 1.2 Commissioning schedule ...............................................................................................................7 2 .System function introduction...........................................................................................................7 3. Compiling basis ...............................................................................................................................7 4. Required conditions before turbine bypass system commissioning ................................................8 4.1 Organization and division of work ................................................................................................8 4.2 Required conditions before system commissioning ......................................................................8 4.3 Commissioning person deployment and qualification.................................................................10 4.4 Equipment and instruments for commissioning.......................................................................10 5. Commissioning procedure and method......................................................................................10 5. Flow chart...................................................................................................................................10 5.2 Commissioning procedure and methods ..................................................................................12 6. Commissioning quality checking standard ................................................................................17 6.1 key control point setting...........................................................................................................17 6.2 Quality standard .......................................................................................................................18 6.3 Recording content ....................................................................................................................18 7. Safety requirement and environment condition during commissioning ....................................18 7.1 Danger factors identification and control.................................................................................18 7.2 Commissioning environment condition ...................................................................................19 8. Appendix ....................................................................................................................................19
DOCUMENT NO.
LS-TSZD-- QJ005
Page 3 of 23
This document is only for technical direction, is not the site construction and commissioning execution document.
DOCUMENT NO.
LS-TSZD-- QJ005
Page 4 of 23
M a in s te a m
H P b y p a ss
C o ld s e c tio n o f re h e a te r
R e h e a te r
C o n d e n se r
L P b y p a ss
H e a t s e c tio n o f re h e a te r
Bypass system hydraulic oil station is made up by 2 nos oil pump and the corresponding system that supply the high pressure oil to the system as the power resource for hydraulic parts. Meanwhile, there has a accumulator installed on the oil supply pipe to stabilize the system work pressure. This bypass hydraulic control system includes the oil supply device, HP bypass actuator, LP bypass actuator, HP accumulator parts, LP accumulator parts and pipe fittings. The working medium for the bypass hydraulic system is adopted the phosphate burning resistance oil which has the good burning resistance and stability. And the oil is supplied by the single oil supply device. The system work pressure range is 15-13.5 MPa. And the oil temperature range is 40-55 deg C. While operation, the cleanness of the work medium shall reach NAS 6 Class or higher Class. Oil supply device has been set the regeneration device, circulation cooling device; main pump, standby pump is designed as redundancy. This is supplying the power resource for the actuator of the valve. The valve actuator has two types, one is regulation type, and the other is switch type, the HP & LP desuperheating valve actuator, HP & LP bypass spray governing valve actuator is regulation type, and the HP bypass spray valve actuator is switch type. There are two control methods for the regulation type valve, viz. normal regulating control and fast control, this two methods are parallel, while the operation, this two control methods are interlocked, and controlled by DCS. In order to open or close the valve quickly, there is set the 40L HP accumulator and 40L LP accumulator for the HP bypass valve and LP bypass valve actuator respectively to guarantee the valve can active quickly and guarantee the oil device supply oil or discharge oil in time.
DOCUMENT NO. : LS-TSZD-- QJ005 Page 5 of 23
Technical parameter of bypass system rating work condition Valve name Model Inlet Rating flux (t/h) Inlet working parameter 16.67 MPa/538 Discharge working parameter 3.663 MPa/318.5
HP bypass valve HP bypass desuperheating spray valve HP bypass desuperheating isolation valve LP bypass valve LP bypass desuperheating spray valve
C7z61Y-P5519.2V
615
Tp7z63Y-32.01
C7z61Y-P554.6V
716.3
0.598MPa/160
Tp7z64Y-4.01
bypass valve regulating factor Valve name HP Bypass valve HP bypass desuperheating spray valve HP bypass desuperheating isolating valve LP bypass 1 1 2 Qty. Driving method Hydraulic driven Hydraulic driven Hydraulic driven Hydraulic Actuator Switch on/off time Switch off 3s BP-300 quickly, 3s quick Switch off 3s LBP-300 quickly, 3s quick Switch off 3s BPE-300 BD-300 quickly, 3s quick Switch off 3s 70%BMCR 60%BMCR Design capability
DOCUMENT NO.
LS-TSZD-- QJ005
Page 6 of 23
driven
Hydraulic driven
3. Compiling basis
3.1 3.2 3.3 3.4 3.5 Indian ROSA 2 x 300MW unit commissioning outline Indian ROSA project equipment erection instruction Indian ROSA project China-Indian general contract The relevant drawings from GEDI Equipment instruction, drawings, and data documents for Indian ROSA project
DOCUMENT NO.
LS-TSZD-- QJ005
Page 7 of 23
4. Required conditions before turbine bypass system commissioning 4.1 Organization and division of work
NO. Organization and division of work Under organized and directed by sub-system commissioning 4.1.1 group, the person in charge of commissioning should carry out commissioning of system and make out commissioning measures of such system. Commissioning person should be responsible for transmission 4.1.2 of related valve, C&I signal and interlock in the system. Before the trial, shall give the technical and safety training, Meanwhile, measure and record necessary data. Operation person is in charge of the operating and operation 4.1.3 monitoring, making the safety isolation for the trial run equipments. Construction 4.1.4 unit should be responsible for finishing commissioning of related individual units in the system and maintaining, overhauling and eliminating the defects in commissioning of system. Organize and coordinate safety, fire fighting and safeguard works on commissioning site The commissioning direction unit shall be in charge of 4.1.5 compiling the commission measure and directing the site commissioning. And shall make the technical training before trial run. Supervision unit shall be in charge of coordinating and attending the system acceptance, coordinating the equipment 4.1.6 and system storage problem, and coordinating the problems disposal which happened in the commissioning. Quality supervising and checking before/ after trial run. Confirmation
DOCUMENT NO.
LS-TSZD-- QJ005
Page 8 of 23
NO.
Required conditions before commissioning Site is flat without debris, the scaffolding shall be removed, the handrail of stairways shall be installed completely, and adequate light is prepared. Fire fighting device is ready. There shall have the clear dividing line around the trial run site. The warning board or enclosure shall be set around the danger area Covers of ditch and holes are complete; ladders, paths, handrails are available for platform. Enough firefighting facilities are available at site; Adequate light is ready for using at the trail run site. And the emergency light can operate automatically. Good ventilation establishment Good communication system. Equipments, pipes, valves shall be hanged the nameplate Equipment and system are installed as per the requirement and accepted. The installation recording is complete. And the relevant equipment individual trial run is finished. The instrument calibration is accepted, and the warning and showing is correct. The person deployment is clear, and the commissioning work training is finished. Equipment and system are installed as per the requirement and accepted. The installation recording is complete. And the relevant equipment individual trial run is finished. And the unit is ready for starting. The entire pipes and equipment in the bypass system shall be installed complete. The oil circu8lation is finished, oil quality is accepted, the oil pressure test for hydraulic pipe is accepted, the bypass oil station commissioning is accepted. The pressure filling to accumulator is finished.
: LS-TSZD-- QJ005
Confirmation
4.2.1
4.2.9 4.2.10
4.2.11
4.2.12
4.2.13
DOCUMENT NO.
Page 9 of 23
Calibration, erection and wire connection for C & I and 4.2.14 electrical equipment is finished, and the bypass system C & I commissioning is finished and accepted. The steam blowing for HP bypass system is accepted, and the 4.2.15 cleaning for LP bypass system is accepted, flushing for HP, LP bypass desuperheating piping is accepted. Commissioning instrument is ready, the calibration for the 4.2.16 instrument is accepted, and the precision of the test instrument meets the requirement.
DOCUMENT NO.
LS-TSZD-- QJ005
Page 10 of 23
DOCUMENT NO.
LS-TSZD-- QJ005
Page 11 of 23
Result
Time
Remarks
System blowing
System tightness
DOCUMENT NO.
Function group test 7 Static state regulation test System operation Control system factor test Regulation function simulation test Operation at any condition Bypass system operation Operation characteristic checking Parameter optimizing setting Dynamic characteristic inspection on the load rejection condition and other working condition
System commissioning items Inspect the complete bypass system. Transmission test, switch on/off test shall be done for the valve to check whether it is flexible and reliable. DAS measurement point and local instrument checking Interlock protection and C & I signal test Bypass system, static state function test Main commissioning procedure bypass system static state commissioning Bypass valve static state characteristic test HP & LP bypass governing valve switch feedback calibration, fast switch on/ off time measurement HP bypass spray governing valve switch feedback calibration, fast switch on/off time measurement LP bypass spray governing valve switch feedback calibration, fast switch on/off time measurement Bypass system control function and interlock protection test HP bypass protection test
HP bypass protection function, the HP bypass is forced to close in the following status
DOCUMENT NO.
LS-TSZD-- QJ005
Page 13 of 23
a) manual HP valve close quickly b) HP spray valve pressure is lower c) reheater pressure is higher The HP bypass desuperheating water control: HP bypass desuperheating water control subsystem to control HP bypass outlet temperature in the suitable temperature around the setting value. HP decompression control: the HP bypass decompression control subsystem to control the main steam pressure as per the pressure setting value. Before the HP cylinder starting to stably the main steam pressure till the unit parameter reaches to the turbine rolling parameter, and then the HP bypass valve is switch to the heating standby status. While the HP cylinder starting, in order to avoid affecting the reheater pressure and HP cylinder steam discharge stop valve action caused by HP bypass switch on/off quickly, the auto control of the bypass shall be changed into manual control. In addition, while the unit operated as load rejection model, the HP bypass can be operation in time. 2 LP bypass control function
LP bypass protection function, the LP bypass is forced to close as the following status: a) condenser vacuum pressure is low b) condenser temperature is high c) LP desuperheating spray water pressure is low d) three-class desuperheating water pressure is low e) condenser water level is high The LP bypass is open as the following status: a) reheating steam pressure is high b) open the LP bypass by manual method LP bypass desuperheating water control: LP bypass desuperheating water control subsystem to control the LP bypass outlet temperature in the suitable value around the setting value. . LP bypass keeps closed while the HP cylinder starting. Before the turbine rolling, the LP bypass valve switch to heat standby status, in addition, while the unit is operated as the load rejection model, the LP bypass can operate immediately.
DOCUMENT NO.
LS-TSZD-- QJ005
Page 14 of 23
3 Reheating steam over-pressure protection While the unit operation, if the deviation between reheating steam pressure and the setting value is more than___ MPa (refer to the setting value from GEDI) or the reheating steam pressure exceeds ___ MPa (refer to the setting value from GEDI), the LP bypass open immediately, and the LP desuperheating valve is also open. 4 condenser protection test While the condenser vacuum is lower, and the condenser water level or the high temperature protection at the downstream of the LP are active, LP decompression valve shall be close, meanwhile, the LP desuperheating valve is also close, 5.2.3.2 A bypass control system dynamic commissioning Regulate the dynamic control parameter of each control subsystem at the different load, and setting the corresponding PID parameter. After the bypass control system operation and the control parameter regulated, B the setting valve dynamic perturbation test for this control system shall be done to precisely regulate the control parameter and improve the regulation quality of control system while the controlled heating power system is operated stably. 5.2.3.3 A 1 2 3 B 1 bypass system operation operation condition Bypass system static state commissioning work is finished. water discharge system commissioning for main steam, reheating steam is finished, and this system is ready for operation The staring preparation work of the main unit is finished. system operation Open the water discharge valve of the bypass system, HP & LP bypass are operated automatically. After the boiler lighting and the pressure generation, HP bypass is switch to the minimum opening, and the LP bypass is opening gradually, go along with the 2 main steam parameter rising, warm the HP & LP bypass piping. Control the temperature rising speed to 2 deg C per min. While the main steam pressure rising to the setting value, control the HP bypass valve to maintenance the main
DOCUMENT NO.
LS-TSZD-- QJ005
Page 15 of 23
steam valve at the setting value. 3 4 5.2.3.4 Control the LP bypass opening as per the main steam pressure changing to maintenance the main steam setting valve. During operation, monitor the desuperheating water governing valve following status, checking the pipe expansion, and discharge is normal. test after bypass system operation
The test after bypass system operation shall be finished before the turbine rolling. Because the HP cylinder is operating, before the turbine rolling, first, secondary class bypass system shall be removed. 1 A 1 2 B 1 2 3 4 5 C 1 bypass system characteristic test test goal Measure the relationship between HP & LP bypass governing valve pressure and flux characteristic Check the spray desuperheating system working characteristic Test condition Unit bypass is operation, and the main body is in the barring gear status Bypass operation is normal Boiler operation is normal Condenser vacuum is normal Circulation water system is operation test procedure HP bypass characteristic test
a) Under the different opening of the governing valve, change the boiler working rate, doing the test till the bypass system valve is full open and the main steam parameter reaches to the rating valve b) During test, the LP bypass is in the following model, the HP bypass desuperheating water is operated automatically. c) Record the relative data d) Calculate the characteristic relationship 2 LP bypass characteristic test
: LS-TSZD-- QJ005 Page 16 of 23
DOCUMENT NO.
a) Under the different opening of the governing valve, change the boiler working rate and the HP bypass opening, doing the test till the LP bypass governing valve is full open and the main steam parameter reaches to the rating valve b) During test, the LP desuperheating water can operate automatically, and the HP bypass can be operated by manual method. c) Record the relative data d) Calculate the characteristic relationship 2 dynamic characteristic test Before the load rejection operation model, the warming and water discharge shall be done for the bypass system, while the unit load rejection operation starting, the HP & LP bypass valve open immediately, in order to estimate the HP & LP spray desuperheating water refection characteristic, record the valve open time, steam pressure, temperature stability valve, peak value and its time.
DOCUMENT NO.
LS-TSZD-- QJ005
Page 17 of 23
Ssupervise
HP & LP bypass system valve transmission recording list HP & LP bypass system subsection trial run recording list HP & LP bypass system logical transmission recording list
7. Safety requirement and environment condition during commissioning 7.1 Danger factors identification and control
Danger factors identification and control list Executive Sn. Description Control and strategy Operation person and erection person to check the equipment operation status periodically Operation person and 2 Injured by the system leakage erection person to check the equipment operation status periodically Operation person and 3 Leakage in the steam valve erection person monitor the pressure and temperature on the downstream of bypass
DOCUMENT NO. : LS-TSZD-- QJ005
person in charge Operation person, erection person Operation person, erection person Operation person, erection person
Signature person Commissioning person in charge Commissioning person in charge Commissioning person in charge
Page 18 of 23
valve periodically, and dispose the leakage once the leakage appeared. LP bypass desuperheating water pressure is 4 lower, the LP bypass will be open by interlocked Maintenance the CEP normal operation to avoid the low pressure at the CEP outlet Operation person, erection person Commissioning person in charge
8. Appendix
NO. 1 2 3 4 Content HP & LP bypass system subsection trial run recording list HP & LP bypass system logical transmission recording list HP & LP bypass system valve transmission recording list HP & LP bypass system subsection trial run acceptance and signature card
DOCUMENT NO.
LS-TSZD-- QJ005
Page 19 of 23
DOCUMENT NO.
LS-TSZD-- QJ005
Page 20 of 23
Number Specialty
Sn.
Unit subsystem commissioning recording list Turbine HP & LP bypass system logical transmission recording
Items Result Signature
DOCUMENT NO.
LS-TSZD-- QJ005
Page 21 of 23
Number Specialty
Valve name
DOCUMENT NO.
LS-TSZD-- QJ005
Page 22 of 23
Inspection Content System interlock protection and signal item complete, and action is correct System C & I instrument is complete, and the show is correct System pressure, temperature parameter is conformed to the design regulation System trial run, each valve is flexible, and can be operated normally Piping is tightness without leakage
Acceptance Non-acceptance
Evaluation: The subsection trial run of this equipment/system has been completed between _____ (Day) _____ (Month), _____ (Year) and _____ (Day) _____ (Month), _____ (Year). Through acceptance inspection according to the Criteria for Acceptance Inspection and Assessment of Adjustment Commissioning Quality of Thermal Power Projects by former Ministry of Electric Power, this equipment/system is rated as qualified ( ) / good ( )
and has achieved conditions required for operation. We hereby agree to enter the whole-set startup stage. Construction unit signature : Commissioning unit signature Commissioning direction unit signature Production unit signature Development unit signature Supervision unit signature Date: Date: Date: Date: Date: Date:
DOCUMENT NO.
LS-TSZD-- QJ005
Page 23 of 23