BUILDING:
In Progress
1
Progress in Construction
of the Administration Building
In early October, the concrete for the 1st lift of basement floor was placed.
The works like rebar and form installation for the 2nd lift of basement and 1st
floor and water curing of the placed concrete were the major activities
during the middle of October.
Next month’s major activity will be the rebar, form and staging works for the
1st floor of the superstructure of the Administration Building.
2
Boiler and Turbine Bldg Foundation Progress
In the month of September 2008, the bored piling works for Boiler No. 1 has
been finished. Excavation works around the bored pile have proceeded
during October. After the piles have been exposed, cutting or removing the
concrete material of that exposed portion will be done. Soil backfilling
compaction is done to make the excavated ground uniform.
For Boiler Unit No. 2, bored piling works are still on-going and is projected
to be finished by the end of October 2008.
For the Turbine Building, pile works for building foundation are still on
going. PC piles are used to bear the load of the turbine building. For the
turbine generator, pedestal bored piles are used and the works has been
started in October, 2008.
3
Signing of MOA for MMT, EMF and EGF
Signing of MOA for the creation of MMT, EMF and EGF at the
City Hall of Naga, Cebu (September 22, 2008)
4
Project Progress
5
Project Progress
6
Project Progress
7
Project Progress
8
Project Information
TARGET COMPLETION : Unit #1: February 2011; Unit #2: May 2011