Professional Documents
Culture Documents
Salient Features
The mode of operation is “Base Load”. Natural Gas is used as main fuel.
Naphtha is used as alternate fuel. Average gas requirement is two million cubic
meters per day. Gas Authority of India Ltd. supplies Natural Gas to the plant
through their H.B.J. Gas pipeline. The electricity generated is supplied to the
state of Haryana.
3
MAIN PLANT:
NTPC-Faridabad is a Gas based Combined Cycle Power Plant. It has two gas
turbines of 138 MW each. Natural Gas, when fired in combustion chamber, runs
gas turbine. Exhaust gases from gas turbines go to two Heat Recovery Steam
Generator of 277 t/hr each. Superheated steam generated in these generators is
used to run steam turbine coupled with Power Generator to get 156 MW. In
addition to these, we have various other auxiliaries; mentioned hereunder.
DM PLANT:
COOLING TOWER:
Induced Draft Cooling Tower of 29000-m3/hr capacity has been built to cool the
hot water coming out of condenser of steam turbine. It is capable to reduce
water temperature by 110C.
STORAGE RESERVOIR:
Raw water drawn from Rampur Distributory of Gurgaon Canal is stored in two
reservoirs of 45000 m3 each.
Raw Water Softening Plant of capacity 630 m3/hr has been provided. The raw
water received is treated in clarifier, then passed through sand filter and stilling
chamber. The pH value of soft water is maintained throughout. The water from
cooling water-softening system is fed into basin of cooling tower.
As a part of integrated fire fighting system, firewater pump house has also been
built which houses following equipment:
A] Hydrant System:
Motor driven pumps = 03 Nos.
Diesel driven pumps = 02 Nos.
B] Spray System:
Motor driven pumps = 02 Nos.
Diesel driven pumps = 02 Nos.
4
C] Jockey pumps: Motor driven = 02 Nos. (common for Hydrant
& Spray system)
D] Compressors: Motor driven = 02 Nos. (for hydro-pneumatic
tank)
This pump house remains operational round-the-clock.
To handle and treat all effluents, an Effluent Treatment Plant has been designed
to treat following liquid effluents.
After treatment water is taken to the Central Monitoring Basin. The treated
effluents meet the parameters of Water (Prevention and Control of Pollution) Act
1974. Then they are discharged to the canal.
This system has two tanks of 8000 m3 each. This system involves unloading
from tankers and then transportation to storage tanks. It has all in-built system
for transfer of naphtha from tanks to gas turbines, also leak detection system
and protection against fire.
SAFETY:
FIRE FIGHTING:
Fire Fighting activities are being controlled by Central Industrial Security Force
(CISF). They have trained manpower for this job. They conduct mock drills from
time-to-time to test soundness of their system in coordination with NTPC
operation & safety Department.
HUMAN RESOURCE:
Human Resource is the main strength of this medium industry. General Manager
is the head of the Unit. Predominantly; executives manning Operation,
Maintenance, Erection, and other technical sections are engineers. Executives
looking after Human Resource, Finance is professionals. Supervisors and
workmen are qualified personnel. Skill is further sharpened through training from
time-to-time.
6
CONTRACTS & MATERIALS:
This department is responsible for arranging/ storing all raw materials, spares
and consumables required for generation of electricity.
MEDICAL CENTRE:
There is a Medical Centre located inside NTPC- Township where the injured and
sick persons are treated. It is under the charge of Chief Medical Officer (CMO).
Also one Asst. Chief Medical Officer is available on General duty. Also one nurse
is available during the day time and one compo under is on duty during night.
Further, an ambulance with driver is kept ready all the time. All other Medical
facilities are out sourced to Escorts- Faridabad.
We also use small quantity of Chlorine, Acid and Alkali for treating the water and
water purification purposes.
3 Sulphuric Acid 40 Kl
7 HSD 500KL
7
RISK ASSESSMENT AND HAZARD IDENTIFICATION
Considering the power generation process at Faridabad Gas Power Project, the
following are the major plant sections :
• Main plant including gas and steam turbo-generators and their auxiliaries
• Waste heat recovery boilers and their auxiliaries.
• Central and local control rooms.
• LT and HT switch gear rooms.
• Cable galleries .
• PT & DM plants and chlorination units
• Gas receiving station and gas distribution piping network.
• Unit gas skids.
• Naphtha storage and distribution piping network.
• Black start DG set
The major emergencies or disasters usually take place from one or any
combination of the following:
• Fast spreading fires
• Explosions
• Bursting of pipe lines or vessels
• Uncontrolled release of toxic / corrosive / flammable liquid
• Uncontrolled release of toxic / flammable gas .
• Structure collapse due to Natural disasters like earth quake, storm etc
• Sabotage and Terrorist attacks on installations
• Destructive trade union activities, strikes and mob violence etc
Depending upon the nature, scale, velocity and impact on environment, each of
these may constitute an emergency.
• Fire hazard :
a) Cable galleries and cables trays
b) Diesel oil tank, Transformer oil
c) Naphtha storage area
d) Gas handling station at GAIL terminal
e) Gas skids
f) Turbine hall.
g)
9
• Explosion hazard :
• Release of gases :
• Release of liquid:
• Natural disasters
• The probability of sabotage and terrorist attacks and also the possibilities
of destruction by union activities / strikes and mob violence is very less as
the plant is protected by a boundary wall and watch towers are
constructed at four corners of the boundary wall. These are manned
round the clock by CISF personnel. CISF personnel are also deployed at
vulnerable locations of the plant. Visitors are screened by CISF personnel
and photo passes are issued to them.
11
• All the pipes carrying steam, oil , water, gas are identified by different
colors.
Steam – insulated with aluminum sheet cover.
Water – green
Oil- brown
Compressed air- blue
Fire hydrant – red
• Permit to work system is strictly followed with lock out boxes as per CEGB
pattern of U.K
• Safety audit of station is done very year by other project representatives
of NTPC.
• All the break down / periodic maintenance are done under the strict
supervision of qualified officers. The job quality is checked by field quality
assurance department after thorough checking and testing.
• Personal protective equipment like – safety shoes, gum boot & safety
helmet are given to every employee every year.
• Plastic overhaul suit with face mask, rubber hand gloves , dust mask, ear
plugs, safety goggles, safety belt, Breathing apparatus set etc. are also
used by employees when required.
• Installation is certified under ISO – 9001. The systems being followed are
as per this standard
12
• FGPP is also certified under ISO – 14001. Environment management
systems confirm to this standard.
• Certification under Occupational Health and Safety Management System
(OHSAS – 18001 ) is also done.
5 Inspection procedure
• Daily visual inspection of all the equipment and meter readings are
recorded by area operators daily in each shift.
• Shutdown maintenance inspection is done vigorously.
• Electrical testing is done after every shut down, break down and routine
maintenance.
• After every shut down maintenance all area and equipments are
thoroughly checked by maintenance personnel.
• Testing of pressure vessels are done by competent mechanical
maintenance engineer group.
• Pressure pipes are tested by mechanical engineers in the presence of
Chief inspector of boiler or his representative and take the certificate of
safe condition.
• At the time of commissioning, all the interlocks and protections, tripping
circuit, safety alarm circuit are tested and records are kept.
• All the lifting tools & tackles, hoists tested every year after preventive
maintenance.
• All the fire fighting and alarm system are on auto and during mock
demonstration these are checked.
• Smoke detection systems are checked by maintenance and operation
group.
• Fixed fire fighting systems are checked jointly by operation, safety and fire
groups.
• Chlorination system healthiness is checked monthly by operation, safety
and fire groups
6. Safeguard of DM plant.
• In acid, alkali tanks area all safety measures have been taken to avoid
disaster.
• Contents of the tanks are marked clearly.
• Said areas are carpeted with acid/alkali proof bricks and separate soaking
pits around the tanks are also provided to hold the total volume of acid /
alkali in case of total drain of acid / alkali, to avoid spreading.
• Drains are provided to drain the spilled acid / alkali to neutralization pits
which have capacity of more than total capacity of acid / alkali tanks.
14
• Shower both platform and eye wash basins are provided in the vicinity of
tanks.
• Acid fumes extraction fans are provided to remove the fumes from
working area.
• Safety instructions are displayed what to do in case of emergency.
• Chlorine leak detectors are provided for sensing and giving alarm in case
of chlorine leakage from toners or manifold.
• Neutralization pit with lime solution is provided for neutralization of leaking
gas
• Ventilation fans are provided at low level
• An automatic functioning scrubber system is provided to neutralize any
chlorine leak from the connected toner and the manifold.
• Chlorination plant is open from all sides and covered by roof only
• Breathing apparatus and emergency leak sealing kit is provided for
emergency use.
• Employees are trained to use breathing apparatus and sealing kit.
• Monthly checking of detection, protection and control system is carried out
jointly by Safety, fire and O&M groups
• Safety instructions do’s and don’ts are displayed prominently in the area.
• Disaster Management Plan is prepared and mock drills are conducted
once in six months
• Leak detectors are provided for natural gas at gas receiving station, unit
gas skids and combustion chambers of gas turbines.
• Naphtha leak detectors are installed for naphtha handling and storage
areas
• Chlorine gas leak detectors are installed in chlorination plants.