Professional Documents
Culture Documents
Before the drum lifting was performed, several preparations were done to make
sure that the activity can proceed smoothly. First, the steel structure was
completed and checked for its structural stability. This is one of the essential
preparations to ensure that the steam drum is properly supported.
1
Steam Drum Lifting (con’t.)
After lifting the drum, pressure parts installation followed. These pressure
parts included water and steam headers and furnace water walls, among
others.
2
Coal Silo Shell Lifting of Boiler Unit No. 1
A fter the steam drum lifting, the coal silo shell lifting of Boiler Unit No. 1
followed last June 5, 2009.
The coal silo is one of components of the fuel feeding system. It provides
temporary storage of crushed coal for continuous operation. The coal silo is
composed of the top frame, shell, middle shell, cone and chute.
Of these components, the coal shell is the only part fabricated at the
construction site. The rest were fabricated at the contractor’s shops.
Meanwhile, the two coal silo shells were lifted and installed in the boiler
structure and then connected to the silo cone.
Before the shells were lifted, the shell plate dimensions, diameter, welded
connection and painting quality, among other parameters were inspected to
make sure that the specification was properly followed.
3
Coal Silo Shell Lifting (con’t.)
Several preparations were also made before the coal silo shell lifting was
conducted. The cone-chute-middle shell assembly was lifted first since it is
located below the shell. The top frame was also installed above the shell as
part of the fabrication plan.
Lifting the shell was not easy because the winds may cause the shell to
abruptly swing and trigger the collision of the steel structure and the shell. If
this happens, the shell and the steel structure may be damaged.
The other works related to the fuel handling system are now proceeding as
scheduled.
The coal silo before it was lifted and installed in the boiler
structure (June 5, 2009)
4
Shop Test for Steam Turbine
The inspection and test of Cebu Power Plant’s steam turbine was performed in
Japan where it is manufactured. This was done in the presence of the supplier,
representatives of Doosan and KSPC in accordance with the approved Shop
Inspection Test Plan and EPC Contract.
Prior to the activities, the Shop Test Procedures were submitted for KSPC’s
approval. This started last February 25, 2009 while the succeeding tests were
done after each test had been carried out and had satisfactorily passed the
criteria.
5
Successful Completion of the
Chimney Concrete Shell
6
Completion of the Chimney
Concrete Shell (con’t.)
After the successful erection of the reinforced concrete shell, the final works of
the main structure of the chimney will follow. This will include the
construction of its duct opening, the inner lining, stairs and platforms, among
others. Surely, the 110-meter high chimney will permanently change the
skyline of Naga and will standout as the landmark of KSPC’s Cebu Power Plant.
May 6, 2009
7
Project Progress
8
Project Progress
9
Project Progress
10
Project Progress
11
Project Information
Contact us
12