Professional Documents
Culture Documents
MOUDA STPP-II (2X660MW) / SOLAPUR STPP (2X660MW) / NABINAGAR STPP (3X660MW) / MEJA TPP (2X660MW) / RAGHUNATHPUR TPP-II (2X660MW) STEAM TURBINE GENERATOR PACKAGE
CLAUSE NO.
1.00.00
DEAERATORS:
Chemical Analysis
Mech. Properties
Impact
Hardness
Flattening
Flaring
UT
RT
MPI
DPT
Eddy Current
SR
HT
Hydraulic
Pneumatic
Y(a)
Y(g)
Y(a) Y
Y(e) Y
QUALITY ASSURANCE
Fabrication/ Welding
a)
Dimensions
b)
Y Y
Y(d) Y
3 Y
Y(h)
Mock up Test
MOUDA STPP-II (2X660MW) / SOLAPUR STPP (2X660MW) / NABINAGAR STPP (3X660MW) / MEJA TPP (2X660MW) / RAGHUNATHPUR TPP-II (2X660MW) STEAM TURBINE GENERATOR PACKAGE
TESTS/CHECKS
COMPONENTS/ACTIVITY
PAGE 1 OF 3
CLAUSE NO.
2.00.00
HEATERS
TESTS/CHECKS
RT
MPI
DPT
Eddy Current
Hydraulic
Pneumatic
Dimensions
1 Y Y Y Y Y Y Y
(k)
Tube Sheet Y Y Y Y Y Y Y Y Y Y Y
Forging
Plates
Y(i) Y(j)
c Y Y(l) Y Y
Clading
QUALITY ASSURANCE
Shell Plates
Y(k)
Y(i)
Back Chipping
(i)
Butt
Y Y Y
(c)
Y Y Y Y Y Y Y Y
Y Y Y
Y Y Y
(ii)
Fillet
(iii)
Nozzle / Branch
(iv)
Mock up Test
MOUDA STPP-II (2X660MW) / SOLAPUR STPP (2X660MW) / NABINAGAR STPP (3X660MW) / MEJA TPP (2X660MW) / RAGHUNATHPUR TPP-II (2X660MW) STEAM TURBINE GENERATOR PACKAGE
COMPONENTS/ACTIVITY
PAGE 2 OF 3
CLAUSE NO.
TESTS/CHECKS
MOUDA STPP-II (2X660MW) / SOLAPUR STPP (2X660MW) / NABINAGAR STPP (3X660MW) / MEJA TPP (2X660MW) / RAGHUNATHPUR TPP-II (2X660MW) STEAM TURBINE GENERATOR PACKAGE
Chemical Analysis
Mech. Properties
Impact
Hardness
Flattening
Flaring
UT
RT
MPI
DPT
Eddy Current
SR
HT
Hydraulic
5 Y Y Y(q) Y(q) Y
)
Y(a) Y
Y(b) Y(b)
Tubes
Complete Heater
QUALITY ASSURANCE
3.00.00
(i) (j)
(e) (f)
(g) (h)
After forming of plates. For dished end and Hemi head. DPT may be used as an alternate to MPI. UT/RT to be decided according to configuration/accessibility. (i) For plates (ii) For welding (iii) For wall thickness Including wall thickness (i) 100% RT/UT shall be carried out on bodies, bonnets, nozzle and stem of valves of HP heater. (ii) 100% DPT/MPI on machined surfaces of valve body, bonnet, stem, disc & springs. Outer surface (Dished end Knuckle Portion) Seat leakage Including Relieving Capacity-popping test at set and blow down pressure
Note : (1) (2)
Include ovality of holes, surface finish and size of holes. For cladding bond and clading thickness during bond check and after drilling For feed nozzle (pipes) For forgings After bending also Dimension to include wall thinning Both tube and shell side. After Hydro test drying and nitrogen filling to be done. As per the code. For HP Heater & Gland steam coolers the staturoy requirments as per IBR to be ensured and to be certification original to be furnished as per IBR statutory requirements. Quantum of Checks Shall be 100% Unless Otherwise Specified. Chem./Mech. shall be One/ per heat or HT batch.
Pneumatic
Dimensions
Mock up Test
COMPONENTS/ACTIVITY
PAGE 3 OF 3