You are on page 1of 103

AP-T247-13

AUSTROADS TECHNICAL REPORT

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One Published September 2013

Austroads Ltd 2013 This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may be reproduced by any process without the prior written permission of Austroads.

ISBN 978-1-925037-20-3 Austroads Project No. TT1825 Austroads Publication No. AP-T247-13

Project Manager David Hazell Roads and Maritime Services NSW Prepared by Geoff Jameson ARRB Group

Published by Austroads Ltd Level 9, Robell House 287 Elizabeth Street Sydney NSW 2000 Australia Phone: +61 2 9264 7088 Fax: +61 2 9264 1657 Email: austroads@austroads.com.au www.austroads.com.au

Austroads believes this publication to be correct at the time of printing and does not accept responsibility for any consequences arising from the use of information herein. Readers should rely on their own skill and judgement to apply information to particular issues.

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Sydney 2013

About Austroads Austroads purpose is to: promote improved Australian and New Zealand transport outcomes provide expert technical input to national policy development on road and road transport issues promote improved practice and capability by road agencies. promote consistency in road and road agency operations.

Austroads membership comprises the six state and two territory road transport and traffic authorities, the Commonwealth Department of Infrastructure and Regional Development, the Australian Local Government Association, and NZ Transport Agency. Austroads is governed by a Board consisting of the chief executive officer (or an alternative senior executive officer) of each of its eleven member organisations:

Roads and Maritime Services New South Wales Roads Corporation Victoria Department of Transport and Main Roads Queensland Main Roads Western Australia Department of Planning, Transport and Infrastructure South Australia Department of Infrastructure, Energy and Resources Tasmania Department of Transport Northern Territory Territory and Municipal Services Directorate Australian Capital Territory Commonwealth Department of Infrastructure and Regional Development Australian Local Government Association New Zealand Transport Agency.

The success of Austroads is derived from the collaboration of member organisations and others in the road industry. It aims to be the Australasian leader in providing high quality information, advice and fostering research in the road transport sector.

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

SUMMARY
In July 2012 Austroads commissioned ARRB to conduct a four-year research project TT1825 Mix design and field evaluation of foamed bitumen stabilised pavements. The objectives of this project are to:
improve the Austroads procedures for the structural design of foamed bitumen stabilised

materials for new pavements and structural rehabilitation treatments


identify distress modes of bitumen stabilised pavements from a series of trial sites improve and harmonise national mix design procedures for bitumen stabilised materials.

This progress report summarises the test methods drafted to date and details the results of monitoring foamed bitumen stabilised pavement trial sites on:
the Calder Freeway at Woodend, Victoria which was constructed specifically for this project in

2013
Port Wakefield Road in Virginia, South Australia constructed in 2011 and which experienced

fatigue cracking within two years of opening to traffic


Kewdale Road in Canning, Western Australia constructed in 2011 and which experiences shear

stresses due to braking and acceleration of heavy vehicles


the Kwinana Freeway in Perth, Western Australia constructed in 2010, and the New England Highway south of Toowoomba, Queensland constructed in 2009.

The report also identifies the mix design and structural design project tasks for 201314.

Austroads 2013 i

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

CONTENTS
1 2 2.1 2.2 2.3 2.4 2.5 3 3.1 3.2 3.3 3.4 INTRODUCTION ................................................................................................................... 1 MIX DESIGN PROCEDURES ................................................................................................ 2 Introduction ............................................................................................................................ 2 Key Mix Design Characteristics.............................................................................................. 2 2.2.1 Review of Austroads Guide Part 4D Framework ........................................................... 2 Proposed Mix Design Framework .......................................................................................... 5 Progress on Test Method Development ................................................................................. 6 Verification of Mix Properties during Construction .................................................................. 7

CALDER FREEWAY WOODEND ......................................................................................... 8 Introduction ............................................................................................................................ 8 Site Investigation Prior to Stabilisation ................................................................................... 9 Properties of the Untreated Crushed Rock Base.................................................................... 9 Mix Design ........................................................................................................................... 10 3.4.1 Downer Infrastructure Testing ..................................................................................... 10 3.4.2 Department of Transport and Main Roads, Queensland Testing ................................. 11 3.4.3 Adopted Mix Design .................................................................................................... 12 3.5 Thickness Design ................................................................................................................ 12 3.6 Construction and Testing of the Foamed Bitumen Stabilised Trial Section........................... 13 3.6.1 Construction of the FBS Pavement ............................................................................. 13 3.6.2 Surface Prior to Sealing .............................................................................................. 14 3.6.3 Two-coat Primerseal ................................................................................................... 15 3.6.4 Field Density Testing .................................................................................................. 16 3.6.5 Laboratory Testing of Field Samples........................................................................... 17 3.7 Construction of Asphalt Section ........................................................................................... 17 3.8 Early-life Characteristics ...................................................................................................... 18 3.8.1 Surface Deflections..................................................................................................... 18 3.8.2 Field Core Moduli ........................................................................................................ 22 3.8.3 Rutting and Roughness .............................................................................................. 24 3.9 Effect of Temperature on Moduli .......................................................................................... 25 3.10 Effect of Laboratory Compaction Method on Modulus .......................................................... 27 3.11 Traffic Monitoring ................................................................................................................. 28 3.12 Performance Prediction ....................................................................................................... 29 4 4.1 4.2 4.3 4.4 4.5 PORT WAKEFIELD ROAD VIRGINIA................................................................................. 30 Introduction .......................................................................................................................... 30 Site Investigation Prior to Stabilisation ................................................................................. 31 Mix Design ........................................................................................................................... 31 Thickness Design ................................................................................................................ 32 Pavement Construction........................................................................................................ 33 4.5.1 Foamed Bitumen Stabilised Sections.......................................................................... 33 4.5.2 Asphalt Section ........................................................................................................... 34 4.6 Visual Condition Monitoring ................................................................................................. 35 4.7 Pavement Investigation........................................................................................................ 36 4.7.1 Asphalt Section ........................................................................................................... 36 4.7.2 FBS Sections .............................................................................................................. 39 4.8 Pavement Deflections .......................................................................................................... 44 4.9 Rutting and Roughness ....................................................................................................... 46 4.10 Traffic Monitoring ................................................................................................................. 48 4.11 Comparison of Observed and Predicted Performance ......................................................... 48

Austroads 2013 ii

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

5 5.1 5.2 5.3 5.4 5.5 5.6 5.7 5.8 6 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 7 7.1 7.2 7.3 7.4 7.5 7.6 7.7 7.8

KEWDALE ROAD WELSHPOOL ....................................................................................... 49 Introduction .......................................................................................................................... 49 Site Investigation Prior to Stabilisation ................................................................................. 50 Mix Design ........................................................................................................................... 51 Thickness Design ................................................................................................................ 52 Pavement Construction........................................................................................................ 54 Pavement Condition Monitoring ........................................................................................... 55 Traffic Monitoring ................................................................................................................. 57 Comparison of Observed and Predicted Performance ......................................................... 57 KWINANA FREEWAY PERTH ............................................................................................ 58 Introduction .......................................................................................................................... 58 Site Investigation Prior to Stabilisation ................................................................................. 59 Mix Design ........................................................................................................................... 59 Thickness Design ................................................................................................................ 60 Pavement Construction........................................................................................................ 61 Condition Monitoring ............................................................................................................ 61 Traffic Monitoring ................................................................................................................. 63 Performance Review............................................................................................................ 64

NEW ENGLAND HIGHWAY QUEENSLAND ...................................................................... 65 Brief Description .................................................................................................................. 65 Site Investigation Prior to Stabilisation ................................................................................. 66 Mix Design ........................................................................................................................... 66 Thickness Design ................................................................................................................ 67 Pavement Construction........................................................................................................ 67 Pavement Coring ................................................................................................................. 68 Pavement Maintenance ....................................................................................................... 69 Performance Monitoring ....................................................................................................... 71 7.8.1 Visual Inspections ....................................................................................................... 71 7.8.2 2012 Roughness and Rutting Data ............................................................................. 72 7.9 Traffic Monitoring ................................................................................................................. 74 7.10 Performance Prediction ....................................................................................................... 74 7.11 Comparison of Observed and Predicted Performance ......................................................... 75 8 8.1 8.2 PROPOSED 201314 RESEARCH ..................................................................................... 76 Introduction .......................................................................................................................... 76 Mix Design ........................................................................................................................... 76 8.2.1 Test Methods .............................................................................................................. 76 8.2.2 Laboratory Testing ...................................................................................................... 76 Structural Design ................................................................................................................. 77 8.3.1 Calder Freeway Woodend .......................................................................................... 77 8.3.2 Port Wakefield Road Virginia ...................................................................................... 77 8.3.3 Kewdale Road Welshpool ........................................................................................... 77 8.3.4 Kwinana Freeway Perth .............................................................................................. 77 8.3.5 New England Highway Queensland ............................................................................ 77 8.3.6 Review Other Monitoring Sites.................................................................................... 78 8.3.7 Additional Sites ........................................................................................................... 79 SUMMARY .......................................................................................................................... 80 Mix Design ........................................................................................................................... 80 Thickness Design ................................................................................................................ 80

8.3

9 9.1 9.2

REFERENCES ............................................................................................................................. 83 APPENDIX A FIELD PERFORMANCE MONITORING PROCEDURES FOR LTPP SITES ...... 85

Austroads 2013 iii

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

TABLES
Table 2.1: Table 2.2: Table 2.3: Table 2.4: Table 3.1: Table 3.2: Table 3.3: Table 3.4: Table 3.5: Table 3.6: Table 3.7: Table 3.8: Table 3.9: Table 4.1: Table 4.2: Table 4.3: Table 4.4: Table 4.5: Table 4.6: Table 4.7: Table 4.8: Table 5.1: Table 5.2: Table 5.3: Table 5.4: Table 5.5: Table 6.1: Table 6.2: Table 6.3: Table 6.4: Table 6.5: Table 6.6: Table 7.1: Table 7.2: Table 7.3: Table 7.4: Table 7.5: Table 8.1: Selecting mix components ....................................................................................... 5 Selecting compactive effort to relative to field density .............................................. 6 Determination of design bitumen content ................................................................. 6 Test methods under development ............................................................................ 7 Description of the Calder Freeway FBS pavement ................................................... 8 Downer Infrastructure mix design results................................................................ 11 TMR mix design testing .......................................................................................... 11 Data used to predict fatigue life of the Calder Freeway pavement .......................... 13 FBS field wet densities, moisture contents and dry densities.................................. 16 Modulus and density of early-life field cores ........................................................... 23 Effect of compaction method on modulus ............................................................... 28 Traffic volume for the Calder Freeway northbound carriageway ............................. 28 Results of average ESA per heavy vehicle Calder Freeway northbound carriageway ............................................................................................................ 29 Description of the Port Wakefield Road FBS pavements ........................................ 30 Data used to predict the FBS fatigue life of Port Wakefield Road sections ............. 32 Field dry densities and laboratory maximum dry densities ...................................... 34 Estimated in situ subgrade CBR ............................................................................. 37 Laboratory test results of Port Wakefield cores ...................................................... 38 Particle size distribution and bitumen content of field cores obtained in nominal 150 mm thick FBS section ........................................................................ 40 Particle size distribution and bitumen content of field cores obtained in nominal 200 mm thick FBS section ........................................................................ 42 Traffic data on Port Wakefield Road 1.7 km south of Angle Vale Road .................. 48 Description of Kewdale Road FBS pavement ......................................................... 49 Results of coring and DCP testing on Kewdale Road FBS pavement prior to stabilisation ................................................................................................ 50 Results of particle size distribution and PI for the untreated materials in Kewdale Road FBS pavement (prior to stabilisation) .............................................. 51 Data used to predict FBS fatigue lives of Kewdale Road FBS trial pavements ............................................................................................................. 53 Traffic data for Kewdale Road ................................................................................ 57 Description of Kwinana Freeway FBS pavement .................................................... 58 Particle size distribution of the host material Kwinana Freeway FBS pavement ............................................................................................................... 60 Data used to predict FBS life of the under-designed Kwinana Freeway pavement ............................................................................................................... 60 QA testing for pavement thickness and density after construction .......................... 61 Kwinana Freeway northbound carriageway daily heavy vehicle volumes ............... 63 Kwinana Freeway average ESA per heavy vehicle type ......................................... 63 Job description of New England Highway FBS pavement ...................................... 65 Results of New England Highway cores extracted April 2000................................. 68 New England Highway maintenance ...................................................................... 69 Estimated 2012 traffic loading ................................................................................ 74 Data for predicting allowable traffic loading of New England Highway FBS pavement ....................................................................................................... 75 Test methods under development .......................................................................... 76

Austroads 2013 iv

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

FIGURES
Figure 2.1: Figure 3.1: Figure 3.2: Figure 3.3: Figure 3.4: Figure 3.5: Figure 3.6: Figure 3.7: Figure 3.8: Figure 3.9: Figure 3.10: Figure 3.11: Figure 3.12: Figure 3.13: Figure 3.14: Figure 3.15: Figure 3.16: Figure 3.17: Figure 3.18: Figure 3.19: Figure 4.1: Figure 4.2: Figure 4.3: Figure 4.4: Figure 4.5: Figure 4.6: Figure 4.7: Figure 4.8: Figure 4.9: Figure 4.10: Figure 4.11: Figure 4.12: Figure 4.13: Figure 4.14: Figure 4.15: Figure 4.16: Figure 4.17: Figure 4.18: Figure 5.1: Figure 5.2: Figure 5.3: Figure 5.4: Figure 5.5: Suitable particle size distribution granular material stabilisation with bitumen binders (Zone A) ......................................................................................... 3 Calder Freeway FBS site during construction ........................................................... 9 Particle size distribution of the untreated crushed rock base .................................. 10 Calder Freeway pavement design .......................................................................... 12 Foamed bitumen stabilisation of the Calder Freeway, Woodend ............................ 14 Finished unsealed surface prior to trafficking overnight .......................................... 14 Condition after trafficking overnight ........................................................................ 15 Primersealing ......................................................................................................... 15 Nuclear gauge direct transmission field density measurements ............................. 16 Asphalt section of the Calder Freeway, Woodend .................................................. 18 Calder Freeway Woodend FBS early-life maximum deflections ............................. 19 Calder Freeway Woodend FBS early-life curvatures .............................................. 20 Calder Freeway Woodend asphalt section ............................................................. 21 FWD deflection testing and coring at Calder Freeway site eight days after construction.................................................................................................... 22 Variation in field core modulus with density ............................................................ 23 Effect of laboratory drying and soaking on one month field core moduli ................. 24 Rutting five weeks after construction of the FBS pavement .................................... 25 Modulus variation with temperature ........................................................................ 26 Correction of WMAPT to measured temperature ratios .......................................... 26 Modulus variation with compaction method ............................................................ 27 Port Wakefield Road FBS site before stabilisation .................................................. 31 Stabilisation equipment used at the Port Wakefield Road FBS site ........................ 33 Compaction equipment used at the Port Wakefield Road FBS site ........................ 33 100 mm thick dense graded asphalt inlay............................................................... 35 Rutting due to foamed bitumen stabilisation of an old asphalt patch....................... 35 Example of cracking observed in FBS section, after about 18 months of trafficking................................................................................................................ 36 Port Wakefield Road asphalt coring ....................................................................... 37 Cores obtained from the nominal 150 mm thick FBS section.................................. 39 Measured bitumen contents of nominal 150 mm FBS cores compared to design application rates.......................................................................................... 40 Variation in field core moduli with density ............................................................... 41 BH11 core, FBS of an asphalt patch together with underlying asphalt patching material .................................................................................................... 41 Relationship between indirect tensile strength and modulus................................... 42 Measured bitumen contents of nominal 200 mm FBS cores compared to design application rate ........................................................................................... 43 Cores extracted from the nominal 200 mm thick FBS section................................. 44 Port Wakefield Road measured surface deflections ............................................... 45 Pavement surface temperatures during FWD measurements ................................ 46 Port Wakefield Road rut depth measurements May 2013 ....................................... 47 Port Wakefield Road roughness measurements May 2013 .................................... 47 Kewdale Road looking towards intersection with Dowd Street................................ 50 Crushed granite base resheet of Section 2 before stabilisation .............................. 51 Particle size distribution of untreated materials in Kewdale Road FBS pavement ............................................................................................................... 52 Kewdale Road pavement structures ....................................................................... 53 Kewdale Road FBS site during stabilisation ........................................................... 54

Austroads 2013 v

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Figure 5.6: Figure 5.7: Figure 6.1: Figure 6.2: Figure 6.3: Figure 7.1: Figure 7.2: Figure 7.3: Figure 7.4: Figure 7.5: Figure 7.6: Figure 7.7: Figure 7.8:

Ravelling of Section 1 due to trafficking before the asphalt surfacing was placed .................................................................................................................... 55 Kewdale Road measured surface deflections ......................................................... 56 Kwinana Freeway FBS site .................................................................................... 58 FWD testing results for Kwinana Freeway FBS site ............................................... 62 Predicted cumulative traffic loading ........................................................................ 64 New England Highway FBS pavement, near Nobby Connection Road intersection (34.5 km) ............................................................................................. 65 Results of cured wet modulus for various FBS mixes for New England Highway FBS pavement ......................................................................................... 67 Cracking at chainage 47.5 km in November 2009, 12 months before geotextile seal was placed ..................................................................................... 70 Cracking at chainage 37.8 km in November 2009, 12 months before geotextile seal was placed ..................................................................................... 70 Flushed binder on the surface suggests transverse cracking under the PMB seal, chainage 46.7 km .................................................................................. 71 Transverse fatigue cracking in New England Highway FBS pavement, chainage 53.6 km ................................................................................................... 72 Severe cracking in southbound lane near chainage 54.8 km .................................. 72 2012 rutting and roughness for New England Highway FBS pavement .................. 73

Austroads 2013 vi

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

INTRODUCTION

The Guide to Pavement Technology Part 5 Pavement Evaluation and Treatment Design includes an interim procedure for the thickness design of foamed bitumen stabilised (FBS) pavements (Austroads 2011a). However, there has been a concern that the interim FBS design procedure is not as well founded as those for conventional treatments due to lack of performance data. The design method needs to be verified/modified with field performance to provide a more accurate performance prediction method for foamed bitumen stabilised pavements. In 2012 Austroads commissioned ARRB Group to undertake a research project TT1825 Mix design and field evaluation of foamed bitumen stabilised pavements. The objectives of this project are to:
improve the Austroads procedures for the design of foamed bitumen stabilised materials for new

pavements and structural rehabilitation treatments


identify distress modes of bitumen stabilised pavements from the trial sites improve and harmonise national mix design procedures for bitumen stabilised materials.

In the first year (201213) of the project, the following two issues were addressed regarding mix design procedures:
development of various draft test methods performance monitoring and analysis of foamed bitumen stabilised pavements.

This report is a progress report on the developments and findings to date. Section 2 summarises the test methods drafted to date and those planned for 201314. Section 3 describes the construction and early-life monitoring of the Calder Freeway Woodend trial section. Section 4 to Section 7 detail monitoring and testing of the other trial sections. Section 8 is the proposed scope of the research for 201314. To guide the project, a project Working Group (WG) has been formed with representative from road agencies, industry and ARRB, convened by Austroads Project Manager, David Hazell of Roads and Maritime Services.

Austroads 2013 1

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

2
2.1

MIX DESIGN PROCEDURES


Introduction

The Guide to Pavement Technology Part 4D Stabilised Materials (Austroads 2006) provides broad mix design guidance for foamed bitumen stabilised materials. The indirect tensile modulus values (initial, cured and soaked) are key characteristics in mix design. Leek and Jameson (Austroads 2011d) provide additional information on the mix design methods in use. Although Part 4D provides the framework for the mix design procedures, there is a need to harmonise mix design test methods which have been developed by road agencies in the absence of Austroads methods. Harmonisation will enable improved understanding of the characteristics of foamed bitumen stabilised materials by pooling national expertise. One key area where harmonisation would be of national benefit is the method used to compact FBS test cylinders for modulus testing. Part 4D describes two approaches:
gyratory compaction Marshall drop hammer.

Measured moduli have been found to vary markedly with the compaction method used (Section 3.4).

2.2
2.2.1

Key Mix Design Characteristics


Review of Austroads Guide Part 4D Framework

Properties of the untreated materials The Guide to Pavement Technology Part 4D Stabilised Materials provides guidance on the types of granular materials suitable for stabilisation with bitumen. Materials usually suitable for bitumen stabilisation have a plasticity index (PI) not exceeding 10, although materials with PI up to 20 have been used by pre-treating with lime. Figure 2.1 shows the recommended particle size distribution of materials suitable for bitumen stabilisation. It is not envisaged that the project will need to review this guidance on materials selection, other than to consider the inclusion of a grading envelope for size 20 material.

Austroads 2013 2

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Austroads (2006).

Figure 2.1: Suitable particle size distribution granular material stabilisation with bitumen binders (Zone A)

Maximum dry density and optimum moisture content Part 4D describes the need to determine the maximum dry density (MDD) and optimum moisture content (OMC) of the host material to be stabilised in order to:
provide guidance on the mixing moisture content and density of laboratory test specimens provide a reference density to assess achieved field densities against specified relative density

values. The project WG has confirmed the need to determine MDD and OMC and that improved guidance is required on how to select the mixing moisture content for preparation of test specimens from the laboratory compaction curve. Note that Section 6.2.1 of Part 4D mentions MDD determination using gyratory compaction (80 cycles) and Marshall drop hammer compaction. Such MDD would only be useful to assess field relative density if the reference MDD relate to these laboratory compaction methods. Currently, reference MDD values are determined using either Standard or Modified drop hammer compaction test methods rather than gyratory compaction or Marshall hammer. Bitumen foaming characteristics Part 4D describes the use of laboratory foaming apparatus to determine the foaming characteristics of bitumen. The expansion ratio (increase in volume due to foaming) and the half-life (time for the expanded volume to collapse to half the maximum expansion volume) are the

Austroads 2013 3

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

currently measured characteristics. It is not envisaged that the project will need to review the suitability of these characteristics, however there is a need to develop an Austroads test method. Preparation of modulus test specimens Part 4D mentions that for materials stabilised with bitumen binders, gyratory compaction (80 cycles) or Marshall drop hammer (50 blows per end) is generally adopted. Where the untreated materials include those over 20 mm in size, it is recommended that a 150 mm diameter mould and, by implication, an associated modified compaction foot be used. There are two key issues of concern with this practice:
the known variation in the modulus values measured on specimens being compacted using

these two compaction methods


the relationship between the modulus test specimen density and the specified field densities

(commonly expressed in terms of standard or modified MDD) is not apparent. There would be benefit in the project addressing these concerns. TMR experience is that laboratory cured samples compacted using 50 blow Marshall hammer achieve similar modulus values to the upper half of field cores after 1224 months field curing (Austroads 2011d). Modulus test specimens The Part 4D design procedure provides the following indirect tensile modulus testing based in part on Main Roads Queensland practice in 2006:
initial modulus testing (uncured, unsoaked) the specimens are dried for three days at 60 C and the dry modulus determined the specimens are then either soaked for 24 hours or soaked in a vacuum chamber for

10 minutes at 95 kPa and the wet modulus determined. The uncured modulus should exceed 500700 MPa, depending traffic loading, as a measure of the pavements ability to withstand trafficking when opened to traffic on the day of construction. The design bitumen content is that which results in the optimum modulus. Leek and Jameson (Austroads 2011d) describe more recent details of the Transport and Main Roads (TMR) Queensland method:
initial modulus testing is conducted after three hours curing at 25 C specimens are dried for three days at 40 C and the dry cured modulus measured specimens are then soaked in water in a vacuum chamber at a pressure not exceeding 95 kPa

for 10 minutes and the wet cured modulus measured. TMR also considers the ratio of the wet to dry cured moduli in selecting the bitumen content. The change in curing temperature from 60 C to 40 C was implemented due to concerns that it 60 C was above the softening point of the bituminous binder which allows its mobilisation and possible absorption into the aggregate. This was seen as a fundamental change to the materials property and therefore not representative.

Austroads 2013 4

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

2.3

Proposed Mix Design Framework

Key anticipated outcomes of the project are:


revised guidance for mix design for inclusion in Part 4D the associated test methods.

As mentioned above no changes are proposed in relation to the material properties suitable for foamed bitumen stabilisation or the evaluation of the bitumen foaming characteristics, other than providing the test method. In relation to performance-related tests, the first meeting of the project WG held in September 2012 confirmed that modulus should continue to be used in the Austroads mix design process based on the TMR experience over the last 1015 years. At this stage it is proposed that the following key properties used to select the bitumen content follow the TMR practice:
the initial modulus cured dry modulus cured wet modulus ratio of wet to dry moduli.

At the second meeting of the WG the issue of whether for heavily trafficked roads the modulus testing needed to be supplemented by deformation testing using the small wheel-tracking test (Austroads 2006) was discussed. It was agreed that this was not necessary at this stage. The principal performance test related to early-life rut-resistance would be initial modulus, with optional use of the wheel-tracking test method. The steps in the proposed mix design procedure are described in Table 2.1 to Table 2.3. The process assumes that:
reference density used to assess field densities will continue to be based on maximum dry

density measured in Standard or Modified drop hammer tests of the stabilised material
modulus test specimens will continue to be compacted using either Marshall drop hammer or

gyratory (Servopac) compaction. As such there is a need to establish the link between the density of the specimens tested for modulus and the field densities as described in Table 2.2.
Table 2.1: Selecting mix components
Step 1 2 3 4 5 6 Activity Obtain a representative sample of the untreated material to be stabilised, including any recycled surfacings materials. Measure particle size distribution and assess whether it is necessary to improve the gradings by adding other granular materials. Measure liquid limit, plastic limit and plasticity index and assess whether the material needs to be pre-treated. Obtain a representative sample of Class 170 bitumen and determine the expansion ratio and half-life on samples with 2%, 3% and 4% water content. Compare measured expansion ratio and half-life against limits. If the limits cannot be achieved at any moisture, assess whether a foaming agent or another bitumen is needed and repeat step 4. Otherwise select the moisture content for foaming and proceed to step 6. Select whether the secondary binder is lime or cement and obtain a representative sample and check for compliance.

Austroads 2013 5

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 2.2: Selecting compactive effort to relative to field density


Step 7 8 9 10 11 12 13 14 Activity From the specification for construction, determine the whether Standard or Modified maximum dry density (MDD) will be used in assessing field compaction and determine the minimum acceptable percentage of the MDD used in the works. Select the mostly likely design bitumen content and secondary binder content. Mix the granular materials, foamed bitumen and secondary binders over a range of moisture contents, including the likely field moisture content at which the material will be stabilised. Determine Standard or Modified laboratory compaction curve as appropriate. Using steps 7 and 10, determine the minimum acceptable field dry density. Select whether the modulus test specimens will be compacted using gyratory compaction (Servopac) or Marshall hammer. Mix the granular materials, foamed bitumen and secondary binders using the likely field moisture content (e.g. 6080% Standard or Modified optimum moisture content). Compact the mixture and assess the compactive effect to achieve the minimum acceptable field dry density (step 12). In the case of the Servopac, the compactive effort is the number of cycles and for the Marshall hammer the number of blows per face.

Table 2.3: Determination of design bitumen content


Step 15 16 17 18 19 20 21 Activity Mix the granular materials, foamed bitumen and secondary binders using the step 13 moisture content. Initially the binder contents in step 8 shall be used. Compact the three cylinders of the mixture using the compactive effort from step 14. Cure the specimens for three hours at 25 C and measure the initial indirect tensile modulus Mi. Dry the specimens for three days at 40 C and measure the dry indirect tensile modulus Md. Soak the specimens in a vacuum chamber for 10 minutes at 95 kPa and measure the wet indirect tensile modulus Mw. Calculate the ratio of the wet to dry modulus. Compare the measured results of steps 1720 with the specified values. If the results are below requirements, increase the bitumen content and/or secondary binder and repeat steps 1520. If the results are above requirements, decrease the bitumen content and repeat steps 1520. Plot the moduli and modulus ratio against bitumen content and select the design bitumen content. The specified bitumen content may need to be adjusted for construction tolerance. If the mix design is significantly different from that used in step 10, it may be necessary to repeat step 10 to provide appropriate values for field compaction assessment.

22 23

2.4

Progress on Test Method Development

Table 2.4 lists the test methods that have been identified for drafting. The initial draft of test methods T301, T305, T310 and T311 have been revised in light of WG comments and utilising the following TMR test methods:
Q138 Preparation and Testing of Foamed Bitumen Materials, draft October 2012 Q139 Resilient Modulus of Stabilised Materials (indirect tensile method), draft October 2012.

It is anticipated these methods may need to be revised in 201314 following trial use and feedback from users.

Austroads 2013 6

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 2.4: Test methods under development


Number T301 T305 T310 T311 T313 T320 T321 T330 T340 Determination of Foaming Properties of Bitumen Mixing of Foamed Bitumen Stabilised Materials (includes method of establishing mixing moisture content) Compaction of Test Cylinders of Foamed Bitumen Stabilised Mixtures: Part 1 Dynamic Compaction Using Marshall Drop Hammer Compaction of Test Cylinders of Foamed Bitumen Stabilised Mixtures: Part 2 Gyratory Compaction Compaction of Test Slabs of Foamed Bitumen Stabilised Mixtures Curing of Test Cylinders of Foamed Bitumen Stabilised Mixtures Curing of Test Slabs of Foamed Bitumen Stabilised Mixtures Resilient Modulus of Foamed Bitumen Stabilised Mixtures Deformation Resistance of Foamed Bitumen Stabilised Mixtures by the Wheel-tracking Test Title Status Drafted Drafted Drafted Drafted To be drafted in 201314 To be drafted in 201314 To be drafted in 201314 To be drafted in 201314 To be drafted in 201314

2.5

Verification of Mix Properties during Construction

In addition to the laboratory mix design process, WG members have raised the need to provide a process to compact modulus specimens of uncompacted stabilised materials sampled from the roadbed during construction. This testing is required to verify the mix properties during construction. Accordingly, it is anticipated that during the four-year project, testing will be undertaken to assess the suitability of various field compaction and curing test methods.

Austroads 2013 7

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

3
3.1

CALDER FREEWAY WOODEND


Introduction

One of the key objectives of this project is to improve the Austroads interim procedures for the structural design of foamed bitumen stabilised materials for new pavements and structural rehabilitation treatments (Austroads 2011a). To address this need the performances of a number of pavements are being monitored. In March 2013, VicRoads and the stabilisation industry agreed to support the Austroads project by constructing an under-designed FBS pavement on the existing Calder Freeway, Woodend, Victoria. That is, the section was designed with a reasonable likelihood of distress within the period of the research project. Details of locality and job statistics (job size, FBS specification and construction method) of the Calder Freeway FBS pavement are given in Table 3.1.
Table 3.1: Description of the Calder Freeway FBS pavement
Location Job size Calder Freeway bypass of Woodend 69.3 to 69.5 km Length Number of lanes Lane width Total area Stabilisation depth Wearing course Foamed stabilisation specification Mix design Host materials Supplementary binder Bitumen Foaming agent Construction method Work specifications and QA testing Construction date 100 m 1 4.8 m (3.5 m slow lane and 1.3 m shoulder) 480 m2 Nominal 150 mm FBS base Size 14/7 primerseal, includes 10 parts rubber Undertaken by Downer Infrastructure and Department of Transport and Main Roads Queensland VicRoads Class 1 crushed rock (size 20 mm), plasticity index 2 to 6 1.5% quick lime 3.5% class 170 bitumen 0.6% Terec 311 VicRoads specifications Foamed bitumen stabilisation, 4 March 2013 Two-coat primerseal of FBS, 5 March 2013 Asphalt section, 21 March 2013

Figure 3.1 shows a view of the trial site. Prior to stabilisation the pavement was a granular pavement with a sprayed seal surface, originally constructed in 2001 as part of the bypass of Woodend. Recently increasing pothole patching within the top 100 mm of the base has been required in the outer wheelpath. This patching material and the existing seal were mixed with the crushed rock base during the foamed bitumen stabilisation.

Austroads 2013 8

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Photograph taken by VicRoads staff (2013).

Figure 3.1: Calder Freeway FBS site during construction

3.2

Site Investigation Prior to Stabilisation

The Calder Freeway bypass of Woodend was designed and constructed using a design traffic loading of 1.1 x 107 ESA over a 30 year period. The bypass was opened to traffic in December 2001. The pavement structure prior to stabilisation comprised:
a prime and double/double size 14/7 seal 200 mm Class 1 (size 20 mm crushed rock) base 150 mm Class 3 (size 20 mm crushed rock) upper subbase 150 mm Class 4 (size 40 mm crushed rock) lower subbase 300 mm Type A capping layer subgrade clay (laboratory soaked design CBR 2%).

3.3

Properties of the Untreated Crushed Rock Base

The crushed rock base was a nominal VicRoads Class 1 crushed rock base of low plasticity and a particle size distribution as given in Figure 3.2. The sample taken from the road bed in March 2013, was taken after the mixing pass and before addition of the lime and bitumen.

Austroads 2013 9

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

100 90 80 70 60 Percentage 50 passing 40 30 20 10 0 0.01 0.1 Sieve size (mm) 1 10 Lower limit Zone A Austroads 2006 Upper limit Zone A, Austroads 2006 Feb 2012 sample from road bed, tested by Downer Oct 2012 sample from road bed, tested by TMR March 2013 sample from road bed during construction

Figure 3.2: Particle size distribution of the untreated crushed rock base

3.4

Mix Design

Prior to construction, samples of the crushed rock base were obtained from the pavement for the mix design. The designs were undertaken by two experienced laboratories: Downer Infrastructure (contractor for the Calder Freeway trial) and the Department of Transport and Main Roads (TMR) Queensland. 3.4.1 Downer Infrastructure Testing

In FebruaryApril 2012, mix design testing was undertaken by Downer Infrastructure at the request of ARRB. The untreated crushed rock base was non-plastic (unexpected as specified to have a plasticity index in the range 24) with a particle size distribution shown in Figure 3.2. The Modified compaction maximum dry density of the untreated material was 2.25 t/m3 and the optimum moisture content (OMC) was 4.8%. By comparison, in subsequent testing of stabilised materials retrieved during construction the maximum dry density was 2.17 t/m3 and the optimum moisture content was 4.5% (Section 3.6.5). To prepare the test specimens, the untreated base was mixed at the bitumen, quicklime and moisture contents shown in Table 3.2. The mixing moisture content was about 85% of Modified OMC of the untreated material and about 92% of the Modified OMC of the stabilised material. Modulus test specimens (150 mm diameter) were then compacted using a Servopac gyratory compactor and then tested for indirect tensile modulus. The results are given in Table 3.2.

Austroads 2013 10

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 3.2: Downer Infrastructure mix design results


Bitumen content (%) 3.0 3.5 4.0
1 2 3

Quicklime content (%) 1 1 1

Moisture content (%) 3.9 4.2 4.3

Mean dry density (t/m3) 2.14 2.19 2.19

Mean indirect tensile modulus (MPa) at 25 C Initial Cured dry Cured wet modulus(1) modulus(2) modulus(3) 463 411 522 2220 2680 4530 1180 1030 1970

% wet/dry modulus 53 37 44

Cured unsealed for three hours at 25 C. Cured unsealed for three days at 40 C. Soaked in water under vacuum of 95 kPa for 10 minutes at 25 C.

3.4.2

Department of Transport and Main Roads, Queensland Testing

In December 2012 prior to construction, another sample of the crushed rock base was excavated from the pavement to enable mix design testing by the Department of Transport and Main Roads (TMR). Following TMR practice, the modulus test specimens were compacted using a modified Marshall hammer in a 150 mm diameter mould by applying 50 hammer blows to each end of the specimen. The particle size distribution of this sample had significantly less fines than the material used in the Downer testing (Figure 3.2). In addition, a plasticity index of 45 was measured by TMR whereas the earlier Downer material was measured to be non-plastic. Downer advise a possible reason for this difference in plasticity index as follows:
This may be due to allowance in the AS method in line with most international methods to classify material not able to be rolled to an initial 3 mm thread as non-plastic. The TMR test method varies from this and states that at any point if it cannot be rolled to a 3 mm thread that should be taken as its plastic limit. This needs reviewing as it will affect classifications on marginal materials.

For the TMR mix the Standard compaction curve was measured: the Standard maximum dry density was 2.22 t /m3 and OMC was 6.6%. The FBS mixes were all mixed at a target moisture content of 70% Standard OMC of the untreated material, that is 4.6%. As the Modified OMC of the stabilised material recovered from the roadbed (Section 3.6.5) was 4.5%, the TMR mix design moisture contents were close to the Modified OMC of the stabilised material. The modulus, bitumen, hydrated lime and moisture contents are shown in Table 3.3. Note that the densities of the test specimens were not measured.
Table 3.3: TMR mix design testing
Bitumen content (%) 2 3 4
1 2 3

Hydrated lime content (%) 2 2 2

Moisture content (%) 4.6 4.5 4.6

Mean indirect tensile modulus (MPa) at 25 C Initial Cured dry Cured wet modulus(1) modulus(2) modulus(3) 1 400 1 460 1 380 700 12 980 10 050 7 600 4 000 5 970 5 510 4 780 2 000

% wet/dry modulus 46 55 63 50

TMR minimum requirements for base with > 1000 ESA/day


Cured unsealed for three hours at 25 C. Cured unsealed for three days at 40 C. Soaked in water under vacuum of 95 kPa for 10 minutes at 25 C.

Source: Personal communication TMR (2012).

Note that the TMR moduli are significantly higher than the Downer values (Table 3.2). Later testing of material retrieved from the roadbed (Section 3.10) suggested that this is in part due to use of different methods used to compact the test specimens.
Austroads 2013 11

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

3.4.3

Adopted Mix Design

As shown in Table 3.3, TMR testing indicated that the crushed rock base stabilised with 3% bitumen and 2% hydrated lime met all TMR minimum mix design requirements for basecourses on heavily trafficked roads. Given that most FBS in Australia to date have been constructed using design bitumen contents in excess of 3%, it was decided to adopt the following design binder contents:
3.5% bitumen 1.5% quicklime (equivalent to about 2% hydrated lime).

3.5

Thickness Design

The objective of the project is to obtain pavement performance data with up to three years of trafficking. Accordingly, the Calder Freeway pavement was designed with a reasonable likelihood of distress occurring within the project period. A nominal FBS thickness of 150 mm was agreed (Figure 3.3), this being the minimum practical thickness based on industry advice.
Sprayed bituminous seal 150 mm foamed bitumen stabilised crushed rock base 50 mm Class 2 crushed rock base 150 mm Class 3 crushed rock subbase 150 mm Class 4 crushed rock subbase 300 mm capping layer Subgrade design CBR = 2%

Figure 3.3: Calder Freeway pavement design

Using the interim thickness design method, a preliminary estimate has been made of the predicted life of the nominal 150 mm thickness stabilisation treatment. In the interim method, the FBS design modulus is determined from indirect tensile moduli measured on laboratory-manufactured specimens cured for three days at 40 C and then soaked in water under vacuum of 95 kPa for 10 minutes. This method was based on TMR comparison of cured wet indirect tensile moduli with in situ values back-calculated from surface deflections on pavements stabilised to depths of 250 mm to 300 mm. However, from Calder Freeway trial cured wet moduli are overly conservative moduli compared to the field cores (Section 3.8.2). Consequently, at this stage in the project, it is suggested the FBS design moduli be determined from the cured dry moduli of laboratory-manufactured specimens compacted using the gyratory method. This will be investigated further as part of the project. Using the gyratory compacted specimens, the mean cured dry modulus was 2680 MPa, at a temperature of 25 C, a dry density of 2.19 t/m3. The average density of the field cores extracted to date is 2.08 t/m3, about 5% lower than the density of the mix design specimens. Currently the interim process does not provide a procedure to adjust modulus for variation in density. Based on the data in Figure 3.14 it is estimated that a reduction in density of 5% leads to a reduction in modulus of about 30%. Correcting the cured dry modulus to the in situ density, a Weighted Mean Annual Pavement Temperature (WMAPT) of 24 C and a design traffic speed of 80 km/h, a FBS design modulus of 1800 MPa was calculated. The fatigue life of the FBS layer was predicted using the Austroads interim design method and the input data given in Table 3.4.

Austroads 2013 12

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 3.4: Data used to predict fatigue life of the Calder Freeway pavement
Pavement component Subgrade Subbase FBS base Design parameter Subgrade type Design modulus Subbase thickness Design modulus FBS thickness Design modulus FBS volume of binder Wearing course Thickness Design modulus Available data clay 20 MPa 350 mm 390 MPa (top layer) 130 mm 1800 MPa 7% n.a. n.a. Assume high standard base material from Table 6.5 of GPT Part 2 (Austroads 2012) Design 150 mm design thickness less 20 mm construction tolerance Derived from the mix design measured dry cured moduli (Section 3.4) Assumed 14/7 mm double primerseal Technical basis for data selection Presumptive laboratory soaked CBR of 2% for basaltic clay

Using the interim design method, the 150 mm thick FBS pavement the predicted FBS fatigue life is 6.6 x 105 ESA at 50% design reliability. As discussed in Section 3.10 the estimated annual traffic loading is about 9 x 105 ESA. Consequently, the design model predicts there is a 50% chance of observing FBS fatigue cracking within 12 months.

3.6
3.6.1

Construction and Testing of the Foamed Bitumen Stabilised Trial Section


Construction of the FBS Pavement

The FBS pavement was constructed on 4 March 2013 and the unsealed surface was opened to traffic the same day. The following day the surface was sealed using a size 14/7 primerseal and opened to traffic again. The project was undertaken by VicRoads, Downer Infrastructure Pty Ltd and Stabilised Pavements Australia Pty Ltd as a contribution to this national research project. The pavement section was 100 m in length and 4.8 m in width covering the slow lane and part of the sealed shoulder. The fast lane was not treated. The construction sequence was as follows (Figure 3.4):
First mixing pass with Wirtgen Stabiliser WR2400 in two 2.4 m widths, this mixed the sprayed

seal through crushed rock base to a nominal depth of 150 mm.


The mixed material was then reshaped with the grader. Quicklime was then spread at an average rate of 4.49 kg/m , about 10% less than the target of
2

4.8 kg/m (assuming mean compaction to 98% Modified maximum dry density). The lime was then slaked.
The slaked lime was mixed through crushed rock base to a nominal depth of 150 mm. The surface was then shaped and lightly compacted with a 12 t vibrating smooth drum roller. The lime reacted with the crushed rock base for about two hours while the bitumen heated to

170 C in the tanker.


The foaming agent (0.6% Terec 311, about 70 litres) was added to the bitumen in the tanker

and then connected to the stabiliser.


With the tanker and the stabiliser connected, the foamed bitumen was then mixed through the

lime-treated crushed rock base. The average bitumen application rate was 11.65 kg/m2. This equates to about 3.6% bitumen content, close to the target of 3.5%.

Austroads 2013 13

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

The FBS crushed rock base was then shaped with a grader and compacted using (a) a

12 tonne vibrating smooth drum roller and (b) a 16 tonne multi-tyre roller (Figure 3.4).

Source: Photographs taken by ARRB and VicRoads staff.

Figure 3.4: Foamed bitumen stabilisation of the Calder Freeway, Woodend

Figure 3.5 shows the compacted unsealed surface prior to opening to traffic the same day.

Figure 3.5: Finished unsealed surface prior to trafficking overnight

3.6.2

Surface Prior to Sealing

Prior to construction there was discussion between VicRoads and the contractor as to whether the stabilised pavement should be cured overnight and sealed the next day before opening to highway traffic. On this heavily trafficked road, VicRoads required the road be opened to traffic immediately following construction.
Austroads 2013 14

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

When the unsealed pavement was inspected the day after construction, the unsealed surface had ravelled under the heavy traffic loading as shown in Figure 3.6. In addition, there was a significant amount of deformation of the FBS layer, also shown in Figure 3.6 (refer to Section 3.8.3). The rutting over about a 10 m length at the start of the works was excessive; this area was subsequently milled and patched with a 100 mm thickness of asphalt during the construction of the asphalt control section (Section 3.7).

Widespread ravelling overnight of the unsealed surface

Deformation of the FBS material near start of the trial section

Figure 3.6: Condition after trafficking overnight

3.6.3

Two-coat Primerseal

A size 14/7 primerseal was placed on 5 March 2013, the day following the FBS construction. The total binder application rate was 1.8 l/m2 (1.2 l/m2 and 0.6 l/m2). The sprayed binder includes 8 parts cutter and 10 parts rubber; the addition of the rubber was not planned but occurred due to the sealing contractor using this binder for another VicRoads job in the area that day.

Figure 3.7: Primersealing

Austroads 2013 15

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

3.6.4

Field Density Testing

The field densities were measured at six sites in the slow lane after the completion of initial rolling (Figure 3.8). At each test site a sample of FBS material was excavated for determination of oven-dried moisture content. The wet density, moisture contents and dry densities are given in Table 3.5. The mean field moisture content was 3.9% and the mean dry density 2.13 t/m3. As described in Section 3.6.5, the Modified maximum dry density (MDD) of the foamed stabilised base was 2.17 t/m3. Accordingly, the mean field density equated to 98% Modified MDD. The measured mean field moisture content of 3.9% was about 87% of the Modified OMC (Section 3.6.5).

Figure 3.8: Nuclear gauge direct transmission field density measurements Table 3.5: FBS field wet densities, moisture contents and dry densities
Project chainage 10 20 30 40 50 60 Mean Wet density (t/m3) 2.18 2.22 2.22 2.22 2.21 2.24 2.22 Moisture content (%) 3.8 3.9 3.6 4.1 3.8 4.2 3.9 Dry density (t/m3) 2.10 2.13 2.14 2.13 2.13 2.15 2.13 Relative density (%) 96.8 98.2 98.6 98.2 98.2 99.1 98.2

Following these field density measurements, the surface was reworked to provide a tighter surface by lightly watering and re-rolling. A repeat series of measurements indicated no significant change in the mean wet densities following this rework.

Austroads 2013 16

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

3.6.5

Laboratory Testing of Field Samples

Materials were sampled from the roadbed during construction for laboratory testing. The untreated crushed rock was tested for particle size distribution (Figure 3.2). The material varied from the TMR mix design material but was similar to the Downer mix design material. The material was non-plastic again consistent with the Downer mix design material but different from the plasticity index of 45 measured by TMR in its mix design (Section 1). The untreated crushed rock was compacted in a150 mm mould to determine the Modified compaction curve. The Modified maximum dry density (MDD) was 2.25 t/m3 and the optimum moisture content (OMC) was 5.3%. These values are similar to those measured by Downer during the mix design (Section 3.4.1). Samples of the lime-treated crushed rock were obtained from the roadbed and tested for lime content and active lime content (CaO) in accordance with test method ASTM D25C-2006. The quicklime contents were 1.8% and 1.2% compared to the design value of 1.5%. The active lime contents were 1.07% and 0.71%. Note that the design value of 1.5% quicklime results in 4.8 kg/m2 for a 150 mm depth. The contractor advised the actual spread rate was 4.5 kg/m2, slightly less than the design value. Uncompacted lime-treated and foamed bitumen stabilised material was sampled from the roadbed during construction to determine the Modified compaction curve. The MDD was 2.17 t/m3 and the OMC was 4.5%. The 3.5% design bitumen content equated to an application rate of 11.2 kg/m2 for 150 mm stabilisation depth. The contractor advised the actual application rate was greater, 11.65 kg/m2. Samples of the loose foamed stabilised crushed rock from the roadbed during construction were tested using the Austroads ignition furnace method, AS 2891.3.3 pressure filter solvent washing method and the TMR solvent extraction method. The measured binder contents were 3.4%, 3.7% and 2.9% respectively. In addition, a bitumen content of 3.4% was obtained by ignition oven testing of a field core taken eight days after construction. Note that these measured bitumen contents included asphalt pot hole patching material and the pulverised bituminous sprayed seal surfacing.

3.7

Construction of Asphalt Section

On 21 March 2013, a 100 mm thick inlay of size 20 mm dense graded asphalt was placed over 100 m section abutting the northern end of the FBS section to compare performance with the 150 mm thick FBS section. The existing seal and top 100 mm of crushed rock base were milled from the pavement, the milled surface broomed, a bitumen emulsion tack coat was applied to the edges and then the asphalt was placed and compacted in a single layer (Figure 3.9). The underlying crushed rock base was very firm and tight and did not require compaction prior to asphalt placement. As discussed in Section 3.6.2, a 10 m section at the southern end of the FBS pavement was milled and inlaid with asphalt as part of the works as it rutted in the first 24 hours of trafficking.

Austroads 2013 17

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Figure 3.9: Asphalt section of the Calder Freeway, Woodend

3.8
3.8.1

Early-life Characteristics
Surface Deflections

Falling weight deflectometer (FWD) deflection testing of the FBS crushed rock base was undertaken eight days and one month after construction. Measurements were taken:
on the edge line in the outer wheelpath between the wheelpaths.

The measured maximum deflections (D0) and curvatures (D0D200) were normalised to a plate contact stress of 566 kPa. The maximum deflections and curvature were corrected from the pavement temperature at the time of measurement to the Weighted Mean Annual Pavement Temperature (WMAPT) of 24 C using the interim deflection-temperature method developed in Section 3.9. The maximum deflections and curvatures are shown Figure 3.10 and Figure 3.11.

Austroads 2013 18

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Calder Freeway Woodend foamed bitumen stabilised material 8 days post-construction corrected from measurement temperature of 29C to WMAPT =24C
0.50

0.40

Outer wheelpath Maximum deflection at 566 kPa (mm) 0.30 Between wheelpaths

0.20

0.10

0.00 0 10 20 30 40 50 Chainage (m) 60 70 80 90 100

0.50

Calder Freeway Woodend foamed bitumen stabilised material 1 month post-construction corrected from measurement temperature of 12C to WMAPT of 24C

0.40

0.30 Maximum deflection at 566 kPa (mm) Outer wheelpath Between wheelpaths 0.20

0.10

0.00 0 10 20 30 40 50 Chainage (m) 60 70 80 90 100

Figure 3.10: Calder Freeway Woodend FBS early-life maximum deflections

Austroads 2013 19

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

0.10 0.09 0.08 0.07 0.06 Curvatures (D0-D200) 0.05 at 566 kPa (mm) 0.04 0.03 0.02 0.01 0.00 0

Calder Freeway Woodend foamed bitumen stabilised material 8 days post-construction corrected from measurement temperature of 29C to WMAPT = 24C

Outer wheelpath Between wheelpaths

10

20

30

40

50 Chainage (m)

60

70

80

90

100

0.10 0.09 0.08 0.07 0.06 Curvatures (D0-D200) 0.05 at 566 kPa (mm) 0.04 0.03 0.02 0.01 0.00 0

Calder Freeway Woodend foamed bitumen stabilised materials 1 month post-construction corrected from measurement temperature of 12C to WMAPT =24C

Outer wheelpath Between wheelpaths

10

20

30

40

50 Chainage (m)

60

70

80

90

100

Figure 3.11: Calder Freeway Woodend FBS early-life curvatures

Surface deflections were also measured on the 100 mm thick asphalt section two weeks after construction. The maximum deflections and curvatures normalised to 566 kPa and adjusted from the pavement temperature during measurement to the WMAPT of 24 C are shown Figure 3.12.

Austroads 2013 20

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

FBS cores taken along the edge line (Figure 3.13) indicated an FBS layer thickness of 200 mm or more. In future monitoring, in situ layer moduli will be estimated by back-calculation of the measured bowls using FBS layer thicknesses estimated from cores in the trafficked area.
Calder Freeway Woodend dense graded asphalt 2 weeks post-construction corrected from measurement temperature of 18C to WMAPT =24C

0.60

0.50

0.40 Maximum deflection 0.30 at 566 kPa (mm) 0.20

Outer wheelpath Between wheelpaths

0.10

0.00 100 110 120 130 140 150 Chainage (m) 160 170 180 190 200

0.10 0.09 0.08 0.07 0.06 Curvatures (D0-D200) 0.05 at 566 kPa (mm) 0.04 0.03 0.02 0.01 0.00 100

Calder Freeway Woodend dense graded asphalt 2 weeks post-construction corrected from measurement temperature of 18C to WMAPT =24C

Outer wheelpath Between wheelpaths

110

120

130

140

150 Chainage (m)

160

170

180

190

200

Figure 3.12: Calder Freeway Woodend asphalt section

Austroads 2013 21

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

3.8.2

Field Core Moduli

As a contribution to this national research project, Stabilised Pavements of Australia Pty Ltd took cores of FBS material eight days and one month after construction along the edge line at chainages identified by ARRB. Surface deflections were measured at these locations prior to coring. At eight days some of the cores could not be fully extracted as the upper and lower portions sheared apart in the coring process. However, all four cores were extracted intact one month after construction. Figure 3.13 shows an example taken on the edge line at chainage 40 m. The cores were transported to Downer Infrastructures laboratory in Somerton, Victoria for testing. Each core was sawn into upper and lower portions and the bulk dry density and resilient modulus measured. The results are summarised in Table 3.6.

200 mm

Figure 3.13: FWD deflection testing and coring at Calder Freeway site eight days after construction

The density of the bottom portion of the field cores was 36% lower than the upper portion. This was a significant factor in the modulus decrease with depth. Figure 3.16 shows the variation in modulus with density and time. The moduli of cores obtained at eight days and one month were reasonably similar for a given density. The next pavement coring is planned 12 months after construction (March 2014). Note that the modulus of cores tested as received from the field appears in closer agreement to the Downer mix design cured dry moduli (Table 3.2) than the TMR values (Table 3.3). As shown in Figure 3.15, the moduli of the one month old field cores roughly doubled after drying for three days at 40 C and then reduced roughly by half after soaking in water. Note that all the full-length cores obtained to date along the outer edge line indicate an FBS thickness in excess of the 150 mm design thickness (Figure 3.13). There is a need for additional coring in the traffic lane to confirm the constructed thickness.

Austroads 2013 22

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 3.6: Modulus and density of early-life field cores


Date of coring Chainage Offset Upper or lower portion Bulk dry density (t/m3) Indirect tensile modulus (MPa) at 25 C As received from roadbed 2540 1910 3690 1700 3170 4470 1750 4190 2540 1910 3690 1700 3170 4470 1750 Cured dry modulus(1) Cured wet modulus(2) % wet/dry modulus

12 March 2013 Eight days after construction

15 15 35 35 55 75 75 95

Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line Outer edge line

Upper Lower Upper Lower Upper Lower Upper Upper Upper Lower Upper Lower Upper Lower Upper Lower

2.15 2.04 2.06 1.99 2.15 2.16 2.03 2.22 2.13 1.99 2.11 2.01 2.13 2.02 2.06 1.98

4920 4060 6510 3670 6930 7540 4060 9360 5980 4130 8520 2920 5300 1830 3530 1790

3470 2540 4560 2130 1960 3940 1900 3490 4300 2820 4310 2620 2770 1890 2590 1700

70 63 70 58 28 52 47 37 72 68 51 90 52 103 73 95

3 April 2013 One month after construction

20 20 40 40 60 60 80 80

1 2

Dried for three days at 40 C before modulus testing at 25 C. After drying for three days at 40 C, cores were soaked in water for 10 minutes under vacuum of 95 kPa then tested for modulus at 25 C.

5000 4500 4000 3500 3000

Field cores 8 days field core 1 month Downer mix design - initial

TMR mix design (density unknown) cured: 8800 MPa soaked: 5100 MPa

Indirect tensile 2500 modulus (MPa)


2000 1500 1000 500 0 1.98

Servopac compacted lab specimen cured 3 days at 40C

Servopac compacted lab specimen cured 3 days at 40C then soaked

2.00

2.02

2.04

2.06

2.08

2.10

2.12

2.14

2.16

2.18

2.20

2.22

2.24

Dry density (t/m3)

Figure 3.14: Variation in field core modulus with density

Austroads 2013 23

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

10000 After 3 days curing at 40C, dry modulus 9000 8000 7000 After 3 days curing at 40C then soaking, wet modulus y = 2.267x - 513

10000 9000 8000 7000 6000 5000 4000 3000 2000 1000 5000

Modulus 6000 after curing (MPa) 5000


4000 3000 2000 1000 1000 y = 0.655 + 1625

1500

2000

2500

3000

3500

4000

4500

Modulus as received from field (MPa)

Figure 3.15: Effect of laboratory drying and soaking on one month field core moduli

3.8.3

Rutting and Roughness

On 10 April 2013, about five weeks after construction of the FBS crushed rock base, the rutting and roughness of the two sections were measured with a laser profiler. The rutting results are shown in Figure 3.16. As mentioned in Section 3.6.1, the pavement ravelled and rutted when trafficked overnight prior to sealing. Note particularly the high rutting of the inner wheelpath. During construction, considerable effort was applied to the inner wheelpath to achieve a tight FBS base surface suitable for bituminous sealing. This reworking of the base may have led to an excess of fines on the surface or higher moisture contents resulting in early-life ravelling and rutting. By comparison, the area in the vicinity of the outer wheelpath did not require the same effort to prepare and showed significantly lower ravelling and rutting. Note this rutting occurred despite the mix design indicating the initial modulus of Marshall compacted specimens (Table 3.7) achieving the minimum 700 MPa required by the TMR mix design method. TMR have advised this is contrary to their experience. The roughness results were as follows:
FBS section: lane IRI of 2.1 m/km asphalt section: lane IRI of 3.6 m/km.

Note, however, the roughness results only apply to short (< 100 m) sections, are influenced by construction joints and as such are not a reliable indicator of performance.

Austroads 2013 24

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

22 20 18 16 14 Rut depth 12 (mm) 10 8 6 4 2 0 0

Foamed bitumen stabilised crushed rock base

Dense graded asphalt

Inner wheel path Outer wheel path

20

40

60

80

100 120 Chainage (m)

140

160

180

200

Figure 3.16: Rutting five weeks after construction of the FBS pavement

3.9

Effect of Temperature on Moduli

In the research project, surface deflections are being monitored on various projects to evaluate the extent to which the modulus changes with time and traffic loading. As the FBS material can differ in temperature between deflection measurements, a procedure is required to adjust the measured deflections from the pavement temperature at the time of deflection measurement to the WMAPT. A procedure similar to the adjustments currently in use for asphalt (Austroads 2011a) would be appropriate. To assist in this regard, after three days drying at 40 C, the one month field cores were tested for indirect tensile modulus over a range of temperatures. The results are plotted in Figure 3.17. The modulus variation is consistent with the FBS modulus variation given in the Guide to Pavement Technology Part 5 Pavement Evaluation and Treatment Design (Austroads 2011a). The variation of modulus with temperature appears to be about 1/3rd the asphalt modulus variation provided in the Guide to Pavement Technology Part 2 Pavement Structural Design (Austroads 2012). As an interim measure pending further research, it is proposed that the asphalt deflection and curvature adjustment factor in Part 5 (Austroads 2011a) be used for FBS pavements but with the ratio of WMAPT to the measured temperature (Tmeas) adjusted to reflect the lower temperature dependency. The adjusted WMAPT/Tmeas ratios are shown in Figure 3.18. In the case of pavements with asphalt surfacing on the FBS layer, the adjustment varies according to the ratio of FBS layer thickness to the total thickness of the asphalt and FBS layers. In using the charts in Part 5, the total thickness of asphalt and FBS layers is used with the adjusted WMAPT/Tmeas ratio.

Austroads 2013 25

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

12000
20m top portion 20 m bottom portion 40 m top portion 40 m bottom portion 60 m top portion 60 m bottom portion

10000

8000 Indirect tensile 6000 modulus (MPa) 4000

80 m top portion 80 m bottom portion Mean

2000

0 10 12 14 16 18 20 22 Temperature (C) 24 26 28 30

Figure 3.17: Modulus variation with temperature

1.8 1.7 1.6 1.5 1.4 1.3

FBS with sprayed seal surface FBS thickness 90% of total thickness FBS thickness 80% of total thickness FBS thickness 70% of total thickness FBS thickness 60% of total thickness

WMAPT/Tmeas 1.2 for use in deflection/curvature 1.1 adjustment


1.0 0.9 0.8 0.7 0.6 0.5 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 2.2 2.4 2.6

WMAPT/Tmeas at time of deflection measurements

Figure 3.18: Correction of WMAPT to measured temperature ratios

Austroads 2013 26

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

3.10

Effect of Laboratory Compaction Method on Modulus

As described in Section 3.4, two experienced laboratories measured very different moduli in the mix designs prior to construction. It was of interest to evaluate the extent to which this was due to the specimen compaction method, namely:
Downer Infrastructure mix design specimens were compacted using gyratory (Servopac)

compaction in 150 mm diameter moulds.


TMR mix design specimens were compacted in 150 mm diameter moulds using a 9.9 kg

Marshall hammer with a modified compaction foot. Samples of the foamed stabilised crushed rock base were obtained from the roadbed prior to field compaction. They were quickly transported to Downers laboratory and the following specimens prepared:
four specimens compacted in a 100 mm diameter mould using 50 blows of a 4.5 kg Marshall

hammer each end


four specimens compacted in a 100 mm diameter mould using gyratory (Servopac) compaction

to a target wet density of 2.26 t/m3


six specimens compacted in a 150 mm diameter mould using gyratory (Servopac) compaction

to a target wet density of 2.26 t/m3. The measured initial, cured dry and cured wet moduli are given in Table 3.7. The cured dry moduli are plotted in Figure 3.19. Clearly, most of the difference in mix design moduli between the two laboratories appears to be due to the method of compacting test specimens. This reinforces the need to harmonise test methods nationally.
8000 101 mm mould, Marshall hammer 7000 100 mm mould, Servopac 150 mm mould, Servopac 6000

Indirect tensile modulus (MPa)

5000

4000

3000

2000

1000 2.14 2.15 2.16 2.17 2.18 2.19 2.2 2.21 2.22 2.23 2.24 2.25 2.26 2.27

Dry density (t/m3)

Figure 3.19: Modulus variation with compaction method

Austroads 2013 27

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 3.7: Effect of compaction method on modulus


Compaction method Sample number M1 M2 M3 M4 100 mm diameter mould, gyratory compaction to a target wet density S1 S2 S3 S4 150 mm diameter mould, gyratory compaction to a target wet density 1 2 3 4 5 6
1 2 3 Cured unsealed for three hours at 25 C. Cured unsealed for three days at 40 C. Soaked in water under vacuum of 95 kPa for 10 minutes at 25 C.

Bulk dry density (t/m3) 2.15 2.16 2.18 2.15 2.17 2.19 2.19 2.20 2.26 2.23 2.23 2.23 2.23 2.23

Indirect tensile modulus (MPa) at 25 C Initial modulus(1) 1090 1070 700 510 700 640 610 Cured dry modulus(2) 6410 6800 6980 6900 3260 2360 2660 2770 5900 5740 5710 5620 5380 5290 Cured wet modulus(3) 2740 2780 3160 3280 1660 1230 1670 1730 3240 3040 2930 3130 2920 2910 % wet/dry modulus 43 41 45 48 51 52 63 62 55 53 51 56 54 55

100 mm diameter mould, Marshall hammer

3.11

Traffic Monitoring

VicRoads provided the current design values of AADT and %HV for the Woodend section of Calder Freeway as given in Table 3.8.
Table 3.8: Traffic volume for the Calder Freeway northbound carriageway
Year 2011 2012
1

Total heavy vehicles(1) 3.5 x 105 3.8 x 105

Number of survey days 343 343

Estimated annual number of heavy vehicles 3.7 x 105 4.0 x 105

Annual ESA 8.3 x 105 9.0 x 105

Total heavy vehicles assumes all rejected and unknown vehicles are heavy vehicles.

Source: Gisborne Culway site data supplied by VicRoads.

Table 3.9 lists the average Equivalent Standard Axles (ESA) per heavy vehicle derived from the weigh-in-motion (WIM) site on Calder Freeway northbound carriageway near Gisborne (which is 14 km from the Woodend trial section). Based on this data, an average of 2.5 ESA per heavy vehicle was assumed. Assuming 90% of the heavy vehicles travel in the slow lane, the estimated annual traffic loading is 9.0 x 105 ESA.

Austroads 2013 28

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 3.9: Results of average ESA per heavy vehicle Calder Freeway northbound carriageway
Survey period July 2012December 2012 January 2012June 2012 July 2011December 2011 January 2011June 2011
Source: Gisborne Culway site data supplied by VicRoads.

Average ESA per HV 2.52 2.38 2.44 2.48

3.12

Performance Prediction

A key objective of the project is to improve the Austroads interim thickness design procedure (Austroads 2011a). As described in Section 3.5, a preliminary prediction has been made of the allowable traffic loading using the interim method: for a 150 mm thick FBS the predicted fatigue life of the FBS is 6.6 x 105 ESA at 50% design reliability. As discussed in Section 3.10, the estimated annual traffic loading is about 9 x 105 ESA. Consequently, the design model predicts there is a 50% chance of observing FBS fatigue cracking within 12 months. Note that cores taken along the outer edge line indicated FBS thicknesses of 200 mm or more, well above the 150 mm design thickness. If the FBS fatigue life is predicted for 200 mm thickness of FBS and the in situ subgrade modulus of 50 MPa rather than 20 MPa, the predicted fatigue life increases to 2.3 x 106 ESA at 50% design reliability. In this case the design model predicts there is a 50% chance of observing FBS fatigue cracking after about 23 years of trafficking. Clearly before the end of the project the constructed FBS thickness in the wheelpaths will need to be measured to provide feedback on the structural design method. To provide a better understanding of an appropriate design modulus for the subgrade, in the future layer moduli will be back-calculated from FWD surface deflections. It is planned to monitor this pavement section over the next three years to provide detailed data on pavement performance (surface defects, cracking, rutting, roughness, deflection). In March 2014, 12 months after construction, FWD testing and coring between the wheelpaths will also be undertaken to evaluate FBS thickness and modulus development. Coring in the wheelpaths will be delayed until 201415 to limit the influence of coring on the pavement performance.

Austroads 2013 29

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

4
4.1

PORT WAKEFIELD ROAD VIRGINIA


Introduction

About 1 km length of the northbound carriageway slow lane of Port Wakefield Road, Virginia, South Australia was foamed bitumen stabilised in April 2011. The project comprises the following three pavement sections:
a control asphalt section (75 m long between chainages 075 m) comprising 100 mm dense

graded asphalt on granular base and subbase


an under-designed sub-section (75 m long between chainages 75150 m) comprising 150 mm

thick FBS base with a two-coat seal surfacing


a main section (900 m long between chainages 1501067 m) constructed with 200 mm thick

FBS base with a two-coat seal surfacing. Details of locality and job statistics (job size, FBS specification and construction method) for the Port Wakefield Road FBS pavement sections are given in Table 4.1.
Table 4.1: Description of the Port Wakefield Road FBS pavements
Location Job size Port Wakefield Road, Virginia, South Australia, between Angle Vale Road and Park Road Length Number of lanes Lane width Stabilisation depth Wearing course Foamed stabilisation specification Mix design Host materials Foamed bitumen Supplementary binder Foaming agent Construction method Work specifications and QA testing Construction date Nominal 150 mm thickness FBS: chainages 75150 m Nominal 200 mm thickness FBS: chainages 1501067 m 1 (northbound outer lane) 3.5 m (stabilisation width 3.9 m) Nominal 150 mm and 200 mm FBS base 16/7 mm double seal Empirically-based method Calcrete limestone crushed rock PM1/PM2 3.0% class 170 bitumen 1% hydrated lime Not recorded DPTI Specification: Part 224 Foamed Bitumen Pavement (January 2007) April 2011

Figure 4.1 shows the test site prior to stabilisation. Only the outer lane was stabilised with hydrated lime and foamed bitumen.

Austroads 2013 30

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Personal communication Crosley (2012).

Figure 4.1: Port Wakefield Road FBS site before stabilisation

4.2

Site Investigation Prior to Stabilisation

Prior to stabilisation, coring and sampling of the pavement and subgrade materials was undertaken at two locations (chainages 100 m and 125 m, and 1.75 m from the outer edge line) and dynamic cone penetrometer (DCP) testing of the subgrade was also performed. The results indicated that the unbound granular pavement was uniform and had a total pavement thickness in the range of 480500 mm, which included:
14 mm/7 mm sprayed seal 160 mm calcrete limestone crushed rock base 190 mm size 60 mm quartzite sandstone rubble subbase 150 mm size 75 mm calcrete limestone rubble subbase subgrade clay, estimated in situ CBR in the range 920% (Table 4.4).

4.3

Mix Design

The material collected from the roadbed was identified as crushed calcrete limestone, with a particle size distribution complying with DPTI requirements for crushed rock base and PI less than 6%. Accordingly, the material was suitable for foamed bitumen stabilisation. For this job, DPTI specified a 3.0% residual bitumen and 1.0% hydrated lime in the FBS process based on previous experience. The material has been sent to ARRB for laboratory testing to determine FBS design modulus later in the project.

Austroads 2013 31

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

4.4

Thickness Design

The 200 mm thickness of FBS was used for the main section (900 m long between chainages 1501067 m), whilst a nominal 150 mm thickness of FBS was used for the 75 m long under-designed section to increase the probability of pavement distress within the next three years. Table 4.2 shows the pavement structures of the two sections (nominal FBS thicknesses of 150 mm and 200 mm) and the selected design modulus values used to predict the allowable loading using the interim FBS thickness design procedure (Austroads 2011a). In the interim method, the FBS design modulus is determined from indirect tensile moduli measured on laboratory-manufactured specimens cured for three days at 40 C and then soaked in water under vacuum of 95 kPa for 10 minutes. These cured wet moduli are overly conservative moduli compared to the field cores as illustrated from the Calder Freeway (Section 3.8.2). For the Port Wakefield Road project a mix design was not undertaken, so cured dry moduli were not available. It is noted from the Calder Freeway project, that for a given density the cured dry moduli were about half the field core moduli. For the 200 mm thick FBS section, the mean field core modulus was about 5000 MPa at a temperature of 25 C. Hence the cured dry modulus of laboratory specimens at the field density was estimated to be 2500 MPa at 25 C. Adjusting this cured dry modulus to a WMAPT of 27 C and for a design traffic speed of 80 km/h, an FBS design modulus of 2200 MPa was calculated for the 200 mm FBS section. For the 150 mm FBS, a design modulus of 3100 MPa was calculated in the same manner. Later in the project, a mix design will be undertaken to provide a more accurate estimate of the FBS design moduli. Based on this data set, the following FBS fatigue lives were predicted:
nominal 150 mm thickness: 2.3 x 10 ESA at 50% design reliability nominal 200 mm thickness: 3.5 x 10 ESA at 50% design reliability. Table 4.2: Data used to predict the FBS fatigue life of Port Wakefield Road sections
Pavement component Subgrade Subbase Design parameter Type Design modulus Thickness Design modulus of top sublayer FBS base Thickness Design modulus 90 MPa Nominal 150 mm FBS: 350 mm Nominal 200 mm FBS: 300 mm Nominal 150 mm FBS: 240 MPa Nominal 200 mm FBS: 185 MPa Nominal 150 mm FBS: 130 mm Nominal 200 mm FBS: 170 mm Nominal 150 mm FBS: 3100 MPa Nominal 200 mm FBS: 2200 MPa Nominal 150 mm FBS: Vb = 9% Nominal 200 mm FBS: Vb = 7% n.a. n.a. Normal granular base/subbase as per original design Austroads Guide to Pavement Technology Part 2 Table 6.4 (Austroads 2012) Field cores (Table 4.5) From Calder Freeway results, assumed that dry modulus of laboratory compacted specimens is half the modulus of field cores at the same density Based on the measured bitumen content of cores (Table 4.6 and Table 4.7) Double spray seal Available data Clay, in situ CBR 9% Technical basis for data selection In situ DCP testing Table 4.4
6 6

Volume of binder Wearing course Thickness Design modulus

Austroads 2013 32

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

4.5
4.5.1

Pavement Construction
Foamed Bitumen Stabilised Sections

The pavements were constructed between 1115 April 2011 in accordance with the DPTI specification (DPTI 2007). The details of stabilisation and compaction equipment and construction tolerances are as follows:
The Wirtgen WR2000 stabiliser (Figure 4.2) was used and the construction tolerance for the

application rate for the binder and supplementary binder was 10% of the specified values.
The depth of stabilisation was measured to the nearest 5 mm for conformation against the

requirements of the DPTI specification (2007). These measurements were taken along the construction joint between the slow and fast lane. As discussed later, this process did not reflect the lower stabilisation thickness subsequently obtained from coring the pavement.

Source: Personal communication Crosley (2012).

Figure 4.2: Stabilisation equipment used at the Port Wakefield Road FBS site

Compaction equipment included (a) a vibrating padfoot roller of a mass of 12 t; (b) a vibrating smooth drum roller with a mass of 12 t; and (c) a multi-tyre roller with a mass of 15 t (Figure 4.3). The stabilised pavement layers were compacted uniformly to the full depth and over the full width and to the relative density of not less than 98% Modified maximum dry density (MDD) (Table 4.3).

Source: Personal communication Crosley (2012).

Figure 4.3: Compaction equipment used at the Port Wakefield Road FBS site

Austroads 2013 33

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Stabilisation of the nominal 150 mm thick FBS section (chainage 75150 m) commenced 11 April 2011, the sprayed seal was mixed through the crushed rock base, the hydrated lime was added and then the foamed bitumen. The pavement was subsequently sealed four days later, 15 April 2011. In terms of the 200 mm thick FBS section between chainage 1501067 m, the stabiliser could only pulverise, wet mix and lime treat a 425 m long section on 11 April 2011 due to the presence of a pavement patch of what was considered at the time cement treated crushed rock between chainage 509573 m. This was subsequently found to be an asphalt patch (Section 4.6) and caused excessive wear to the milling teeth. The following day, 12 April 2011, the remaining length (5751067 m) was pulverised, wet mixed and lime treated, and an asphalt patch was encountered between chainage 780845 m which again hindered progress. The hydrated lime spread rate was measured during construction as 2.6 kg/m2 for the nominal 150 mm section compared to the design value of 3.0 kg/m2. For the nominal 200 mm thick FBS section the measured spread rate was 4.0 kg/m2 compared to the design value of 4.1 kg/m2. On 13 April 2011, the nominal 200 mm thick FBS between chainages 1501067 m was foamed bitumen stabilised. It is not known whether the delay between lime stabilisation and foamed bitumen stabilisation affected the subsequent performance. Due to rain on 14 April 2011, the application of the two-coat sprayed seal surface was delayed until 15 April 2011. After the FBS was compacted, the in situ densities were measured to a depth of 150 mm and material excavated at selected test sites to determine the Modified maximum dry density (MDD) and optimum moisture content (OMC) (Table 4.3). The relative density at each site was calculated by dividing the in situ dry density by the Modified MDD.
Table 4.3: Field dry densities and laboratory maximum dry densities
Chainage (m) 122 196 352 431 487 591 711 838 1007 Field dry density (t/m3) 2.04 1.98 1.98 2.01 2.06 2.02 2.02 1.98 2.05 Modified MDD (t/m3) 2.03 1.98 1.95 1.93 2.01 2.01 1.99 2.02 2.02 Modified OMC (%) 7.0 9.0 9.0 9.0 6.0 8.0 8.0 7.0 7.5 Relative density (%) 100.0 100.0 102.0 104.0 102.5 100.5 101.0 98.5 101.0

4.5.2

Asphalt Section

To benchmark the FBS performance, it was decided to construct a 100 mm thick asphalt inlay of a short length of Port Wakefield Road adjacent to the 150 mm thick FBS section. The 100 mm thick asphalt section was constructed by milling the existing pavement to a depth of 100 mm, spraying a tack coat and placing the asphalt in two layers (40 mm wearing course, 60 mm thick intermediate course) (Figure 4.4). Following common local practice, a tack coat was not placed between the two asphalt layers as both layers were placed on a single day.
Austroads 2013 34

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Personal communication Crosley (2012).

Figure 4.4: 100 mm thick dense graded asphalt inlay

4.6

Visual Condition Monitoring

DPTI has inspected the pavement about every two months since construction. In January 2012, the first summer after construction, flushing was observed over a 30 m length of the 200 mm FBS section length, chainage 510 to 575 m. By March 2013 after the second summer and about two years of trafficking, the rutting was up to about 50 mm deep in some areas (Figure 4.5). Coring of the pavement showed that this area of the pavement was an asphalt patch prior to stabilisation. This was thought to be a cement stabilised patch during construction. Foamed bitumen stabilisation of this asphalt patch resulted in a mix with inadequate rut resistance.

Figure 4.5: Rutting due to foamed bitumen stabilisation of an old asphalt patch

On 23 August 2012, fatigue cracking was observed for the first time. Two months later, October 2012, a detailed inspection of the asphalt section, the nominal 150 mm FBS and 200 mm thick FBS sections was undertaken. Fatigue cracking was observed in all three sections. The cracking of the FBS section starts as fine transverse cracks in the wheel patch and develops into block cracking (Figure 4.6). Fine transverse cracking was also observed in the 100 mm thick asphalt section (Figure 4.6).

Austroads 2013 35

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Example of fine transverse cracking of nominal 150 mm FBS

Example of crocodile cracking of nominal 200 mm FBS

Figure 4.6: Example of cracking observed in FBS section, after about 18 months of trafficking

4.7

Pavement Investigation

As a result of the premature pavement distress, in October 2012 FBS cores were extracted from the pavement and dynamic cone penetrometer testing of the subgrade was undertaken to estimate in situ Californian Bearing Ratio (CBR) using the Austroads (2012) method. Dynamic cone penetrometer testing was also undertaken during construction in April 2011. 4.7.1 Asphalt Section

The asphalt section was cored at chainage 62.6 m in the outer wheelpath and between wheelpaths in an area with fine fatigue cracking (Figure 4.7). While the core from the unloaded area between wheelpaths was extracted with the upper and lower asphalt layers bonded together, in the outer wheelpath the 40 mm thick wearing course was debonded from the underlying asphalt (Figure 4.7). As the cracking appeared to be confined to the wearing course, the cracking may have been due to inadequate bonding between asphalt layers. The two asphalt layers were placed on the same day and without trafficking of the intermediate course. Following normal local practice, a tack coat was not applied to the surface of the intermediate course prior to the placement of the overlying wearing course. As shown in Table 4.5 and as expected, the cracked wearing course asphalt from the outer wheelpath was significantly lower in modulus than sound asphalt from the unloaded area between wheelpaths. As shown in Table 4.4, the subgrade has high strength with an estimated in situ subgrade CBR exceeding 10%.

Austroads 2013 36

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Lower portion of delaminated outer wheelpath core

Core between wheelpaths, bonding between asphalt layers

Figure 4.7: Port Wakefield Road asphalt coring Table 4.4: Estimated in situ subgrade CBR
Section Description Chainage (m) Offset Date Estimated CBR (%) at depths below top of subgrade 0100 mm Asphalt FBS nominal 150 mm thick BH (during construction) BH1 BH (during construction) BH2 BH (during construction) BH4 BH6 FBS nominal 200 mm thick BH8 BH11 BH12 37.5 62.6 100 101 125 122 144.5 420 820 950 BWP OWP BWP BWP BWP BWP BWP April 2011 October 2012 April 2011 October 2012 April 2011 October 2012 October 2012 October 2012 October 2012 October 2012 6 > 30 6 11 18 > 30 13 11 11 7 100200 mm 5 11 11 18 25 > 30 30 11 11 12 200300 mm 5 13 14 28 6 15 > 30 15 15 15 300400 mm 8 15 14 30 7 11 n.a n.a n.a n.a

Austroads 2013 37

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 4.5: Laboratory test results of Port Wakefield cores


Section Description Chainage (m) 62.6 62.6 62.6 62.6 101 112 122 131 144.5 200 420 420 660 750 750 820 820 950 950 Offset Thickness (mm) FBS OWP OWP BWP BWP BWP BWP BWP BWP OWP BWP BWP BWP BWP BWP BWP BWP BWP BWP BWP 140 130 140 130 110 150 180 160 180 175 190 Asphalt 90 90 90 90 Underlying asphalt patch No No No No No No No No No No No No No Yes Yes Yes Yes No No Core diameter (mm) 99 99 99 99 142 142 142 142 142 142 142 142 142 142 142 142 142 142 142 Core length (mm) 40 40 37 35 78 76 76 77 70 74 60 68 83 74 64 78 77 73 78 Bulk density (t/m3) 2.23 2.24 2.21 2.25 2.10 2.06 2.09 2.07 2.09 2.02 1.97 1.88 2.04 2.04 1.94 2.11 2.40 2.09 1.99 IT strength (kPa) 1 990 1 570 1 830 2 070 770 760 920 770 720 430 590 350 980 930 390 810 1 300 450 230 IT modulus (MPa) 1 980 7 750 9 000 9 160 7 550 6 890 7 520 6 250 5 290 2 760 5 190 2 220 7 880 11 430 3 250 6 430 9 750 5 560 1 070

Asphalt

BH1, asphalt wearing course BH1, asphalt intermediate course BH1A, asphalt wearing course BH1A, asphalt intermediate course

FBS nominal 150 mm thick

BH2, top layer BH3 BH4 BH5 BH6

FBS nominal 200 mm thick

BH7 BH8, top layer BH8, bottom layer BH9 BH10, top layer BH10, bottom layer BH11, top layer BH11, bottom layer BH12, top layer BH12, bottom layer

Austroads 2013 38

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

4.7.2

FBS Sections

Nominal 150 mm thick FBS Four FBS cores were taken from the untrafficked area between wheelpaths and one core was taken in the outer wheelpath. The average FBS thickness was 130 mm, less than the 150 mm design thickness. The cores were transported to ARRBs laboratory in Vermont South for testing. About 30 mm was sawn from the top and bottom of each core and the remaining 7078 mm length was tested from indirect tensile modulus and strength. The moduli were high, the average of the indirect tensile moduli in Table 4.2 was 6700 MPa. Figure 4.8 shows three of the five cores obtained and the pavement condition at time of coring.

BH 3 chainage 111 m

BH4 chainage 121 m

BH6 chainage 144.5 m

Figure 4.8: Cores obtained from the nominal 150 mm thick FBS section

Following modulus and strength testing, the particle size distribution and the recovered bitumen content of the cores were measured. The bitumen contents were measured using the pressure filter method (AS 2891.3.3) with Solvex MT solvent. The results are given in Table 4.6. The design bitumen content of 3.0% equates to application rates of 9.1 kg/m2 and 12.2 kg/m2 for stabilisation depths of 150 mm and 200 mm respectively, assuming an in situ dry density of 2.03 t/m3. The average measured bitumen content was 5.1% considerably higher than the design content of 3.0%. The high bitumen contents may have been due to:
the use of the bitumen application calculated for nominal 200 mm FBS depth on the shorter

section where the depth was reduced to a nominal 150 mm


the stabilisation depths being below the 150 mm design thickness the inclusion of the old double seal in the recycled pavement.

Austroads 2013 39

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

The variation in measured bitumen content with stabilisation depth is illustrated in Figure 4.9. Also shown are the bitumen contents for the design bitumen application rate of 9.1 kg/m2 and for 12.2 kg/m2. Considering the old double seal added an additional 1.5 to 2.0 kg/m2 of bitumen, the measured bitumen contents are consistent with use of an application rate of 12.2 kg/m2 for the nominal 150 mm stabilisation depth. That is, the results suggest the use of the 200 mm thick FBS bitumen application rate on the 150 mm thick FBS section. The high bitumen content may have contributed to the higher densities for the nominal 150 mm FBS section and hence the higher moduli as shown in Figure 4.10. Even though these high bitumen contents are high, generally the rutting is not yet excessive (Figure 4.17).
Table 4.6: Particle size distribution and bitumen content of field cores obtained in nominal 150 mm thick FBS section
Sieve size BH2 19.0 mm 13.2 mm 9.5 mm 6.7 mm 4.75 mm 2.36 mm 1.18 mm 600 m 300 m 150 m 75 m Recovered bitumen content Stabilisation depth (mm) Chainage (m)
6.0

% passing sieve BH3 100 96 85 75 62 46 35 27 21 15 10 4.4% 130 112 BH4 97 95 84 72 60 45 34 26 20 15 9 5.7% 140 122 BH5 98 95 83 73 60 45 34 27 22 17 12 4.8% 130 131 BH6 100 89 74 61 49 35 28 23 19 15 11 5.7% 110 144.5 100 97 87 74 62 46 35 28 22 16 11 5.1% 140 101

5.5 Application rate 9.1 kg/m2 5.0 Application rate of 12.2 kg/m2 Measured

4.5 Bitumen content 4.0 (% by mass) 3.5

3.0

2.5

2.0 100 110 120 130 140 150 160 Depth of FBS stabilisation (mm) 170 180 190 200

Figure 4.9: Measured bitumen contents of nominal 150 mm FBS cores compared to design application rates

Austroads 2013 40

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Nominal 200 mm thick FBS Six FBS cores were taken from the untrafficked area between wheelpaths. The average thickness was 179 mm, below the 200 mm design thickness. The cores were transported to the ARRB laboratory in Vermont South, Melbourne for testing. For cores less than 160 mm in length (BH7, BH9) about 30 mm was sawn from the top and bottom of each core and the remaining 7384 mm length was tested for indirect tensile modulus and strength testing. Cores from the other sites were cut into top and bottom halves prior to testing for density, modulus and strength testing. As shown in Figure 4.10, the moduli tended to increase with density and the FBS layer tended to have lower density and moduli in the bottom portion compared with the top portion, consistent with the Calder Freeway findings (Figure 3.14).

12000

10000

8000

150 mm FBS 200 mm FBS bottom 200 mm FBS top

Indirect tensile 6000 modulus (MPa)


4000

2000

0 1.86 1.88 1.90 1.92 1.94 1.96 1.98 2.00 2.02 2.04 2.06 2.08 2.10

Density (t/m3)

Figure 4.10: Variation in field core moduli with density

The very high modulus of cores from BH11 appears to be due to the host material being an old asphalt patch. Note that at BH11, the FBS material was well supported by the underlying old asphalt patching material (Figure 4.11). Due to this support, the density and modulus of the bottom half of the layer was higher than other locations.

Figure 4.11: BH11 core, FBS of an asphalt patch together with underlying asphalt patching material

Austroads 2013 41

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

For this material, the measured relationship between indirect tensile modulus of field cores from indirect tensile strength is shown in Figure 4.12. The strength and modulus results were highly correlated.
12000 y = 8.59x R = 0.80 10000

8000

Indirect tensile 6000 modulus (MPa)


4000

2000

0 0 200 400 600 800 1,000 1,200 1,400

Indirect tensile strength (kPa)

Figure 4.12: Relationship between indirect tensile strength and modulus

Following modulus and strength testing, the particle size distribution and the recovered bitumen content of the cores were measured. The results are given in Table 4.7.
Table 4.7: Particle size distribution and bitumen content of field cores obtained in nominal 200 mm thick FBS section
Sieve size BH7 19.0 mm 13.2 mm 9.5 mm 6.7 mm 4.75 mm 2.36 mm 1.18 mm 600 m 300 m 150 m 75 m Recovered bitumen content Stabilisation depth (mm) Chainage (m) 95 86 67 57 48 36 29 24 20 16 12 4.4% 150 200 BH8 top 95 93 84 73 62 46 36 29 24 18 12 5.5% 180 420 BH8 bottom 100 93 80 69 56 46 38 32 27 21 14 6.6% BH9 99 93 81 67 55 40 30 24 18 13 8 5.3% 160 660 % passing sieve BH10 top 99 93 81 67 54 37 26 20 14 10 5 3.1% 180 750 BH10 bottom 96 92 81 69 60 45 34 27 21 15 9 4.3% BH11 top 100 99 93 84 72 55 43 34 25 16 10 8.1% 175 820 BH11 bottom 89 78 68 62 49 38 30 24 16 8 5 3.8% BH12 top 93 84 71 61 50 37 29 23 19 14 9 3.4% 190 950 BH12 bottom 100 91 78 67 57 44 32 24 17 12 7 2.8%

Austroads 2013 42

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

The average measured binder content was 5.4%, well above the 3% design content. The recovered binder contents were not highly correlated with the length of the field cores (Figure 4.13). The high bitumen content of core BH11 was due to the stabilisation of an old asphalt patch (Figure 4.11). As the sprayed seal surfacing of the original unbound granular pavements was included in the FBS material, this may also have contributed about an additional 0.5% to the measured bitumen contents. However, the very high bitumen contents at BH8 and BH9 cannot be explained, other than these again being FBS stabilisation of old asphalt patches.
6.5

6.0

BH8
BH11 - asphalt patch

5.5 BH9 5.0 Bitumen content 4.5 (% by mass) 4.0 BH10 3.5 Application rate of 12.2 kg/m2 Application rate of 12.2 kg/m2 plus old seal (1.8 kg/m2) 3.0 Measured BH12

BH7

2.5 100 110 120 130 140 150 160 Depth of FBS stabilisation (mm) 170 180 190 200

Figure 4.13: Measured bitumen contents of nominal 200 mm FBS cores compared to design application rate

Figure 4.14 shows the very different appearance of the BH8 material from the material at BH12 consistent with the difference in measured bitumen contents. Also shown are the severities of surface cracking at the time of coring. Given that BH10 and BH12 had bitumen contents close to the design value yet had very different severities of cracking, it cannot be concluded that there is a close link between the cracking and the bitumen content being well above the design value.

Austroads 2013 43

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

BH8 chainage 420 m

BH10 chainage 750 m

BH12 chainage 950 m

Figure 4.14: Cores extracted from the nominal 200 mm thick FBS section

4.8

Pavement Deflections

Surface deflections were measured using a Falling weight deflectometer (FWD) at the following times:
1 March 2012, about 11 months after construction 27 September 2012, about 17 months construction.

The deflection bowls were measured using a contact stress in the range 550580 kPa then normalised to a stress of 566 kPa. The maximum deflections (D0) and curvatures (D0D200) normalised to a stress of 566 kPa are plotted in Figure 4.15.

Austroads 2013 44

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

1.0 0.9 0.8 0.7 0.6

Maximum deflection 0.5 at 566 kPa (mm) 0.4


0.3 0.2 0.1 0.0 0 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 100010501100 Asphalt control March 12 150 mm FBS March 12 200 mm FBS March 12 Asphalt control Sept 12 150 mm FBS Sept 12 200 mm FBS Sept 12
Previous asphalt patch Previous asphalt patch

Chainage

0.28 0.26 0.24 0.22 0.20 0.18


Previous asphalt patch

Previous asphalt patch

Curvature 0.16 at 0.14 566 kPa (mm) 0.12


0.10 0.08 0.06 0.04 0.02 0.00 0 Asphalt March 12 150 mm FBS March 12 200 mm FBS March 12 Asphalt control Sept 12 150 mm FBS Sept 12 200 mm FBS Sept 12 50 100 150 200 250 300 350 400 450 500 550 600 650 700 750 800 850 900 950 100010501100

Chainage

Figure 4.15: Port Wakefield Road measured surface deflections

Although the pavement surface temperatures were measured (Figure 4.16), the temperatures at depth are required to correct the deflection measured on FBS from the testing temperature to a representative in-service temperature. Note that the surface temperature increase with chainage measured in September 2012 reflected the surface heating during the morning of testing. Given this variability it was not possible to accurately estimate the mid-layer pavement temperatures from surface temperatures. Accordingly, the process developed in Section 3.9 to correct deflections to the WMAPT was not used.

Austroads 2013 45

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

45

40

35

Surface temperature (C)

30 Mar-12 Sep-12

25

20

15

10 0 100 200 300 400 500 600 700 800 900 1000 1100

Chainage (m)

Figure 4.16: Pavement surface temperatures during FWD measurements

In March 2012, no cracking was observed by DPTI staff driving over the site, but six months later distress was apparent in all sections. As seen from Figure 4.15, the deflections and curvatures of the nominal 200 mm thick FBS section generally increased during this six month period, consistent with the onset of cracking. Despite the high strength subgrade and thickness of underlying granular subbase, the curvatures 12 months after construction were high (> 0.1 mm) compared to other sites being monitored. A possible reason for this is fatigue damage to the FBS layers in the first 12 months of trafficking, despite surface cracking not being observed. However, not known is the extent to which the increase in surface temperature between the March and September 2012 deflection measurements resulted in the observed increases in deflections and curvatures. As part of the 201314 project work, consideration will be given to measuring both the pavement temperatures and the surface deflections to evaluate the layer moduli if a section with more commonly used bitumen contents (34%) can be identified by pavement coring.

4.9

Rutting and Roughness

In May 2013, the rutting and the roughness of the project were measured. The 1.2 m straight edge rut depths are given in Figure 4.17. The high rutting in the vicinity of chainage 550 m was due the stabilisation of an old asphalt patch (Figure 4.5). The lane IRI roughness values are plotted in Figure 4.18.

Austroads 2013 46

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

35

30

Outer wheel path Inner wheel path

25

Rut depth (mm)

20

15

10 asphalt 150 mm FBS

0 0.0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0 1.1

Chainage (km)

Figure 4.17: Port Wakefield Road rut depth measurements May 2013
4.2 4.0 3.8 3.6 3.4 3.2

Lane 3.0 IRI (m/km) 2.8


2.6 2.4 2.2 2.0 1.8 1.6 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1 1.1

Chainage (km)

Figure 4.18: Port Wakefield Road roughness measurements May 2013

Austroads 2013 47

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

4.10

Traffic Monitoring

DPTI provided 7-day vehicle classification count data (two-way) for the Port Wakefield Road (at a traffic count site located 1.7 km south of the Angle Vale Road) for two periods in July 2006 and August 2011 (DPTI 2011). Table 4.8 provides a summary of the daily number of heavy vehicles.
Table 4.8: Traffic data on Port Wakefield Road 1.7 km south of Angle Vale Road
Year 2006 2011 Northbound average daily heavy vehicles 745 1240 Annual ESA 9.8 x 105 1.6 x 106

Weigh-in-motion (WIM) axle load data is not available at this site to estimate the number of ESA per heavy vehicle and hence the cumulative traffic loading. However, DPTI suggested an estimated value of the average number of ESA per heavy vehicle of 3.6 for the outer lane of the Port Wakefield Road based on WIM data collected on similar road sites (personal communication Crosley 2012). Hence the current estimated annual traffic loading is 1.6 x 106 ESA assuming all heavy vehicles travel in the slow lane. Over the 16 month period between construction in April 2011 and the first observation of fatigue cracking (August 2012), the cumulative traffic loading is estimated to be 2.1 x 106 ESA.

4.11

Comparison of Observed and Predicted Performance


6 6

As noted in Section 4.4, the predicted FBS fatigue lives are:


nominal 150 mm thickness: 2.3 x 10 ESA at 50% design reliability nominal 200 mm thickness: 3.5 x 10 ESA at 50% design reliability.

Therefore the interim design process predicts it would take approximately 18 months of cumulative traffic loading for the 150 mm thick FBS section to fatigue crack and about two years for the 200 mm thick FBS section. Hence the predicted fatigue life is reasonably consistent with the observed cracking of both sections after a traffic loading of 2.1 x 106 ESA. However, given the high bitumen contents of field cores of the nominal 150 mm thick FBS section there is considerable doubt about the applicability of the findings to more commonly used binder contents. Moreover, for the nominal 200 mm thick FBS about half of the field cores had unexpectedly high measured bitumen contents, possibly due to the inclusion of old asphalt patches in the recycled pavement. Of most use to the project is the performance of pavement areas with more typical binder contents. Further pavement coring is required to clearly identify these areas.

Austroads 2013 48

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

5
5.1

KEWDALE ROAD WELSHPOOL


Introduction

In November 2011, the City of Canning, Western Australia constructed FBS pavement sections on Kewdale Road, Welshpool. Three pavement sections were constructed:
a main section (100 m long and 4 m wide) constructed with 320 mm FBS thickness under-designed Section 1: 50 m length with 150 mm FBS thickness under-designed Section 2: 50 m length with 100 mm FBS thickness.

Only the two under-designed sections were selected for performance review in this project as the 320 mm thick section is unlikely to be distressed during the project period. Details of locality and job statistics (job size, FBS specification and construction method) for the Kewdale Road FBS pavement are given in Table 5.1.
Table 5.1: Description of Kewdale Road FBS pavement
Location Job size Kewdale Road Welshpool, Western Australia (southbound close to Dowd Street intersection) Length Number of lanes Lane width Total area Stabilisation depth Wearing course Foamed stabilisation specification Mix design Host materials Supplementary binder Bitumen Foaming agent Construction method Work specifications and QA testing Construction date Under supervision of City of Canning 13 November 2011 2 sections, each 50 m in length 1 (slow lane) 4m 400 m2 Section 1: nominal 150 mm FBS Section 2: nominal 100 mm FBS 30 mm dense graded asphalt Empirically-based method 30% recycled asphalt and 70% crushed granite base 0.8% hydrated lime 3.5% class 170 bitumen

Source: Personal communication Leek (2012).

Figure 5.1 shows Kewdale Road prior to stabilisation; Section 1 is located 50100 m from the intersection with Dowd Street and Section 2 is located 050 m from the intersection. As such, both sections experience shear stresses due to braking and acceleration of heavy vehicles.

Austroads 2013 49

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Personal communication Leek (2012).

Figure 5.1: Kewdale Road looking towards intersection with Dowd Street

5.2

Site Investigation Prior to Stabilisation

Coring and sampling of the pavement materials was undertaken at eight locations and dynamic cone penetrometer (DCP) testing of the subgrade was also performed prior to stabilisation. The results (Table 5.2) indicated that the existing pavement structure prior to rehabilitation comprised:
4560 mm dense graded asphalt 140275 mm thickness of size 20 mm crushed granite base 120230 mm thickness of size 40 mm gravel or crushed limestone subbase subgrade sand with in situ CBRs in the range of 1550%. Table 5.2: Results of coring and DCP testing on Kewdale Road FBS pavement prior to stabilisation
Chainage (m) 80 Offset (m) Asphalt thickness (mm) Crushed rock base thickness (mm) Crushed limestone/gravel subbase thickness (mm) Total pavement depth (mm) Subgrade CBR (%)
1 2

Section 1 110 1.0 50 140 210 400 35 120 1.5 45 185 230 460 15 120 2.0 55 175 150 380 25 20 1.5 50 220(1) 165 435 30 2.0 50 150 220 420 NR(2)

Section 2 20 2.0 50 275(1) 185 510 30 50 1.5 60 260(1) 130 450 50 70 1.5 50 220(1) 165 435 15

Crushed rock base thickness after 50 mm granular resheet. Not recorded.

Source: Personal communication Leek (2012).

There were also some areas of asphalt patching in both sections.

Austroads 2013 50

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Prior to stabilisation, a 45 mm granular resheet of size 20 mm crushed granite base was placed on Section 2 to raise its pavement profile (Figure 5.2). This allowed the construction of the 100 mm thick FBS layer by firstly stabilising the overlaid pavement to a depth of 150 mm, then trimming the surface by 45 mm to the height of the adjacent traffic lane.

Source: Personal communication Leek (2012).

Figure 5.2: Crushed granite base resheet of Section 2 before stabilisation

5.3

Mix Design

Samples of materials in Section 1 and Section 2 were collected from the roadbed after pulverising the top 150 mm layer with the stabiliser (Leek 2012). Results of particle size distribution and plasticity index (PI) of these materials are summarised in Table 5.3 and Figure 5.3. The host material lacked fines (for grain size < 0.15 mm) as compared to the Zone A particle size distribution (Austroads 2006).
Table 5.3: Results of particle size distribution and PI for the untreated materials in Kewdale Road FBS pavement (prior to stabilisation)
Size (mm) Section 1 Section 2 Austroads (2006) Percentage passing 19 100 100 73100 16 99 98 13.2 97 91 9.5 90 75 4475 6.7 80 62 4.75 71 52 2955 2.36 56 38 2345 1.18 41 28 1838 0.6 28 20 1431 0.425 21 16 0.3 15 12 1027 0.15 7 6 824 0.075 3 2 520 PI (%) 8 4

Source: Personal communication Leek (2012).

A mix design was not undertaken prior to the works. Based on previous experience in the City of Canning, the host material was stabilised with a target 3.5% residual bitumen and 0.8% hydrated lime. Laboratory testing to determine FBS design modulus is planned for 201314.

Austroads 2013 51

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

100 90 80 70 60 Percentage 50 passing 40 30 20 10 0 0.01 0.1 Sieve size (mm) 1 10 Section 1 Section 2 Lower limit Zone A Austroads 2006 Upper limit Zone A, Austroads 2006

Figure 5.3: Particle size distribution of untreated materials in Kewdale Road FBS pavement

5.4

Thickness Design

The structural designs of the two under-designed test sections are shown in Figure 5.4. The FBS thicknesses were selected as follows to increase the probability of observing fatigue cracking during the research project:
Section 1 has a nominal 150 mm thickness of FBS, which is the minimum allowable FBS

thickness (150 mm) when using the normal construction method.


Section 2 has a nominal 100 mm thickness of FBS, which required a special construction

method (Section 5.5). The 100 mm depth was achieved by firstly stabilising to a depth of 150 mm layer was then trimming back to the design 100 mm thickness before compaction. Table 5.4 shows the pavement structures and the selected design moduli used in the Austroads interim FBS thickness design procedure to predict the FBS fatigue lives. Given that there was no laboratory data yet to determine the FBS design modulus, a typical FBS design modulus value of 2500 MPa was assumed. The following FBS fatigue lives were predicted:
Section 1 (150 mm FBS base): 3.7 x 10 ESA (50% design reliability). Section 2 (100 mm FBS base): 1.1 x 10 ESA (50% design reliability).
6 6

The high moduli of the underlying granular subbase and sand subgrades increase the predicted FBS fatigue lives on Kewdale Road.

Austroads 2013 52

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Section 1

Section 2

30 mm asphalt wearing course 100 mm FBS 150 mm FBS 200 mm crushed granite base

50 mm crushed granite base

200 mm crushed limestone/gravel subbase 150 mm crushed limestone/gravel subbase


Sand subgrade Figure 5.4: Kewdale Road pavement structures

Table 5.4: Data used to predict FBS fatigue lives of Kewdale Road FBS trial pavements
Pavement component Subgrade Design parameter Subgrade type Subgrade design modulus Subbase Subbase thickness Design modulus of subbase FBS base FBS thickness Section 1 CBR 12% 120 MPa 270 mm Table 6.4 of Austroads (2012) 130 mm Section 2 CBR 12% 120 MPa 370 mm Table 6.4 of Austroads (2012) 80 mm Technical basis for data selection Presumptive design value for subgrade sand in WA. Mixture of crushed granite base and gravel subbase. Design thickness of 150 mm (Section 1) and 100 mm (Section 2) less 20 mm construction tolerance. Assumed, will be determined later in the project from laboratory mix design testing. For typical dense graded asphalt (size 10 mm, Class 320) assuming a design speed of 50 km/h and the Weighted Mean Annual Pavement Temperature (WMAPT) of 29 C for an urban road in Perth.

FBS design modulus Wearing course Thickness Design modulus

2500 MPa 30 mm 2600 MPa

2500 MPa 30 mm 2600 MPa

Austroads 2013 53

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

5.5

Pavement Construction

The sections were stabilised on 13 November 2011 and opened to traffic the same day. The preliminary construction report (personal communication Leek 2012) indicated that:
A Wirtgen WR 2500 SK stabiliser was used and the construction tolerance for the application

rate for the binder and supplementary binder was 10% of the specified values. The minimum stabilisation depth of 150 mm was initially constructed for both Section 1 and Section 2. The 150 mm layer in Section 2 was then cut back to the design 100 mm thickness during the compaction and shaping operation.
Compaction equipment included (a) an 18 tonne vibrating padfoot roller (b) a 12 tonne vibrating

smooth drum roller; and (c) a 20 tonne multi-tyre roller. The specified minimum field compaction was 98% Modified Maximum Dry Density.

Source: Personal communication Leek (2012).

Figure 5.5: Kewdale Road FBS site during stabilisation

The sections were opened to traffic prior to the placement of the 30 mm thick dense graded asphalt surfacing several days later. The unsealed foamed bitumen stabilised surface ravelled under initial trafficking (Figure 5.6) as observed during the Calder Freeway construction (Section 3.6.2).

Austroads 2013 54

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Personal communication Leek (2012).

Figure 5.6: Ravelling of Section 1 due to trafficking before the asphalt surfacing was placed

5.6

Pavement Condition Monitoring

Since construction in November 2011 Curtin University has monitored the pavement condition. In February 2013, about 15 months after construction the test pavements were inspected and rutting was measured. Rut depths were measured on the 30 mm thick asphalt surfacing every 5 m along the two sections. There was minimal rutting with all measurements less than 3 mm depth. There was also no cracking in either section and they were in sound condition. Surface deflections were measured using a falling weight deflectometer (FWD) at the following times:
14 November 2011, the day after construction and prior to placement of the asphalt surfacing 5 January 2012, about seven weeks after stabilisation and after placement of the asphalt

surfacing
6 December 2012, 13 months after stabilisation.

The deflection bowls were measured using a contact stress in the range 600700 kPa then normalised to a 566 kPa. The surface temperatures during the FWD measurements were with 3 C of the Weighted Mean Annual Pavement Temperature (WMAPT) of 29 C. As the pavement temperature at mid-depth was not measured, the deflections cannot be reliably temperature corrected. The maximum deflections (D0) and curvatures (D0D200) normalised to a stress of 566 kPa are plotted in Figure 5.7. Note that the deflections measured on 14 November 2011 (the day after stabilisation) were measured without the 30 mm thick asphalt surfacing. Had the surfacing been in place it is estimated the maximum deflections would have been about 10% lower and the curvatures about 20% lower.

Austroads 2013 55

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

0.8

Section 1 150 mm

Section 2 100 mm

0.7

0.6

0.5

Maximum deflection at 566 kPa (mm)

0.4

0.3

0.2

14-Nov-11, 1 day 5-Jan-12, 7 weeks 6-Dec-12, 13 months

0.1

0.0 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125

Chainage

0.30

Section 1 150 mm
0.25

Section 2 100 mm

14-Nov-11, 1 day
0.20

5-Jan-12, 7 weeks 6-Dec-12, 13 months

Curvatures at 566 kPa 0.15 (mm)

0.10

0.05

0.00 0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100 105 110 115 120 125

Chainage

Figure 5.7: Kewdale Road measured surface deflections

The results to date suggest that seven weeks after stabilisation the pavements had cured. There is no indication yet that the FBS material is deteriorating structurally in either section.

Austroads 2013 56

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

5.7

Traffic Monitoring
Table 5.5: Traffic data for Kewdale Road
Road name Lane Date AADT (slow lane) 6000 7300 Percentage heavy vehicles (slow lane) 26 28 Annual daily heavy vehicles 1590 2050 Annual ESA 8.7 x 105 1.1 x 106

Annual average daily traffic (AADT) and percentage heavy vehicles data as given in Table 5.5.

Kewdale Road, Welshpool

Southbound

May 2010 July 2012

Source: Personal communication Leek (2012).

The MRWA Engineering Road Note 9 (MRWA 2013) provides a presumptive ESA per heavy vehicle value of 1.5. Using this value the annual ESA of loadings in Table 5.5 were estimated.

5.8

Comparison of Observed and Predicted Performance


6 6

As discussed in Section 5.4, the predicted FBS fatigue lives are:


Section 1 (150 mm FBS base): 3.7 x 10 ESA (50% design reliability) Section 2 (100 mm FBS base): 1.1 x 10 ESA (50% design reliability).

Based on the traffic data in Table 5.5, the estimated annual cumulative traffic loading would be about 106 ESA. Consequently:
Section 1 (150 mm FBS base): it would take approximately three years of cumulative traffic

loading to reach the predicted fatigue life of 3.7 x 106 ESA (50% design reliability).
Section 2 (100 mm FBS base): it would take approximately one year of cumulative traffic

loading to reach the predicted fatigue life of 1.1 x 106 ESA (50% design reliability). As described in Section 5.6, there are no observable pavement defects after 16 months of cumulative traffic loading since construction in November 2011. In addition, there is no clear evidence at this stage that the foamed bitumen stabilised material is reducing in modulus due to traffic loading. It is planned to monitor these two FBS pavement sections over the next two years to provide detailed data on pavement performance (surface defects, cracking, rutting, roughness, deflection) for the validation of the Austroads interim FBS thickness design procedure.

Austroads 2013 57

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

6
6.1

KWINANA FREEWAY PERTH


Introduction

In 2010, trial sections of FBS pavements were constructed for Main Roads Western Australia (MRWA) on the Kwinana Freeway Perth. Three pavement sections, each 100 m long and 3.8 m wide, were constructed with different FBS thicknesses (namely 150 mm, 240 mm and 290 mm) and resurfaced with 30 mm dense graded asphalt (DGA) and 30 mm open graded asphalt (OGA). Figure 6.1 shows a view of the test site during construction. Only the under-designed pavement section with the minimum FBS thickness of 150 mm is considered suitable for inclusion in this project.

Source: Personal communication Kenworthy-Groen (2012).

Figure 6.1: Kwinana Freeway FBS site

Details of locality and job statistics (job size, FBS specification and construction method) for the Kwinana Freeway under-designed FBS pavement section are given in Table 6.1. Detailed data on mix design, pavement design and construction for this pavement supplied by MRWA (personal communication Kenworthy-Groen 2012) is briefly described below.
Table 6.1: Description of Kwinana Freeway FBS pavement
Location Job size Kwinana Freeway (north of the Mundijong Road between 37.7237.82 SLK) northbound Length Number of lanes Lane width Stabilisation depth Wearing course Foamed stabilisation specification Mix design by Host materials Supplementary binder Bitumen Foaming agent Construction method Work specifications and QA testing Construction date MRWA 2010 Construction Specification Foamed Bitumen Stabilisation Pavement February 2010 100 m 1 (outer lane) 3.8 m 150 mm FBS base 30 mm OGA+ geofabric + 30 mm DGA MRWA (empirically-based method) Mixture of HCTCRB (85%) and crushed limestone subbase (15%) 0.8% lime 3.5% class 170 bitumen

Source: Personal communication Kenworthy-Groen (2012).

Austroads 2013 58

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

6.2

Site Investigation Prior to Stabilisation

Site investigation prior to stabilisation showed that the existing pavement had the following composition:
30 mm open graded asphalt 30 mm dense graded asphalt 10 mm sprayed seal 125 mm hydrated cement treated crushed rock base (HCTCRB) 225 mm crushed limestone subbase sand subgrade.

HCTCRB is crushed rock base that has been mixed with water and 2% of cement and then allowed to hydrate in stockpile for extended period of time before wet mixing again, placing and compacting in the road-bed. Rutting, loss of texture in wheel-tracks and minor shape problems were observed. Subsequently, it was decided to trial the use of FBS as a rehabilitation treatment.

6.3

Mix Design

A large bulk sample of each pavement layer was excavated using a 1 m wide profiler from the pavement at the south end of the pavement section at SLK 38.015 prior to stabilisation. The OGA and DGA asphalt layers were removed by the profiler. Laboratory particle size distribution test results for these materials are summarised in Table 6.2. Table 6.2 also includes the particle size distribution of a sample collected behind the stabiliser after pulverising and mixing. As explained in Section 6.5, as the pavement was initially stabilised to a nominal depth of 210 mm, the host material comprised:
30 mm open graded asphalt 30 mm dense graded asphalt 125 mm HCTCRB 25 mm crushed limestone subbase.

For this under-designed pavement section, MRWA specified a 3.5% residual bitumen and 0.8% hydrated lime in the FBS process. The binder contents were empirically based rather than established through a mix design process. It is proposed that a mix design be undertaken as part of this research project, provided sufficient amounts of materials recovered from the roadbed are still available.

Austroads 2013 59

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Table 6.2: Particle size distribution of the host material Kwinana Freeway FBS pavement
Sieve size (mm) 75 26.5 19 13.2 9.5 4.75 2.36 1.18 0.600 0.425 0.300 0.150 0.075
Source: Personal communication Kenworthy-Groen (2012).

Percentage passing 100 99 99 94 85 62 44 34 26 21 17 11 7

6.4

Thickness Design

The 150 mm FBS thickness was selected to increase the likelihood of observing FBS fatigue in accordance with the project objective. Table 6.3 shows the final pavement structure and the selected design modulus values used in the Austroads interim FBS thickness design procedure to calculate the allowable traffic loading of the under-designed pavement. Given that laboratory measured moduli are currently not available to determine FBS design modulus, a typical FBS design modulus value of 2500 MPa was assumed. Based on this data set, the predicted FBS fatigue life is 1.7 x 107 ESA at 50% design reliability.
Table 6.3: Data used to predict FBS life of the under-designed Kwinana Freeway pavement
Pavement component Subgrade Subbase FBS base Design parameter Subgrade type Subgrade design modulus Subbase thickness Design modulus of subbase FBS thickness FBS design modulus Wearing course Thickness Design modulus Available data CBR 12% 120 MPa 200 mm Table 6.4 of Austroads (2012) 135 mm 2500 MPa 70 mm 3600 MPa Mean thickness of 160 mm and construction tolerance of 20 mm For typical dense FBS base (assuming a design speed of 80 km/h and the WMAPT of 29 C for a freeway in Perth) 30 mm OGA + geofabric + 30 mm DGA Normal crushed rock base/subbase as per original design Technical basis for data selection Presumptive design value for subgrade sand in WA

Austroads 2013 60

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

6.5

Pavement Construction

The pavement was constructed in February 2010 in accordance with the MRWA Construction Specification Foamed Bitumen Stabilised Trial Kwinana Freeway (MRWA 2010). In planning Kwinana Freeway trial sections it was proposed to open the unsealed FBS base to traffic to observe the early-life ravelling and rutting prior to reshaping and placement of the asphalt surfacing. Consequently, the initial plan was to prepare the unsealed FBS to the level of the adjacent traffic lane, open it to traffic and several days later to mill the top 60 mm of the FBS to provide for the 60 mm asphalt surfacing. Although this early-life performance evaluation was not implemented, the sequence of the works program aligned with the initial plan:
The 30 mm thick open graded asphalt, 30 mm dense graded asphalt, 125 mm HCTCRB and

25 mm was pulverised, mixed and compacted to provide 210 mm thickness of FBS base. Note that due to concerns about the breakdown of the crushed limestone subbase due to the stabiliser, the lime and bitumen were incorporated into the pavement in the first pass of the stabiliser to minimise the number of mixing passes. Nevertheless a second mixing pass was required due to inadequate depth of mixing in the first pass.
Several days later the top 60 mm of FBS base layer was removed by milling and brooming. The asphalt surfacing was placed consisting of 30 mm thick open graded asphalt on 30 mm

dense graded asphalt. Detailed specifications of stabiliser and compaction equipment and construction tolerances are given below.
A Wirtgen WR 2000 stabiliser was used and the construction tolerance for the application rate

for the binder and supplementary binder was 10% of the specified values.
Compaction equipment used comprised (a) a vibrating padfoot roller of a minimum mass of 18 t;

(b) a vibrating smooth drum roller with a minimum mass of 12 t; and (c) a multi-tyre roller with a minimum mass of 15 t. The stabilised pavement layers were compacted uniformly to the full depth and over the full width and compacted to a characteristic dry density ratio (Rc) of 98% or greater. QA testing for layer thickness and density was carried out at three locations (chainages 225 m, 250 m, 275 m) and the results of layer thickness and density are given in Table 6.4. The results confirmed that the minimum compaction standard was achieved.
Table 6.4: QA testing for pavement thickness and density after construction
Test location SLK (km) 37.750 37.775 38.000 Average
1

Thickness (mm) Wearing course and FBS base 210 240 220 223 Limestone subbase 210 170 220 200

Nuclear density meter testing on the FBS base Dry density ratios (%)(1) 105.7 103.3 105.3 104.8 Moisture ratio (%)(1) 55 53 51 53

Based on Modified MDD = 2.081 t/m3 and Modified OMC = 8.2%.

6.6

Condition Monitoring

Since construction, MRWA has regularly inspected the pavement and has reported no surface defects to date.

Austroads 2013 61

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

MRWA also conducted four FWD surveys about four months, 14 months, 26 months, 33 months and 39 months after construction). The FWD testing results (as shown in Figure 6.2) indicated that pavement deflections significantly reduced in the first 12 months and have become more stable since. To date there is no evidence that the FBS is deteriorating structurally under traffic loading.

0.50 0.45 0.40 0.35 0.30

Normalised maximum 0.25 deflection (mm)


0.20 0.15 0.10 0.05 0.00 37.725 Deflection Jun 2010 Deflection April 2011 Deflection April 2012 Deflection Nov 2012 Deflection May 2013

37.735

37.745

37.755

37.765

37.775

37.785

37.795

37.805

37.815

Kwinana Freeway northbound outer lane SLK

0.14

0.12

0.10

Normalised curvature (mm)

0.08

0.06 Curvature Jun 2010 Curvature April 2011 Curvature April 2012 Curvature Nov 2012 Curvature May 2013

0.04

0.02

0.00 37.725

37.735

37.745

37.755

37.765

37.775

37.785

37.795

37.805

37.815

Kwinana Freeway northbound outer lane SLK

Figure 6.2: FWD testing results for Kwinana Freeway FBS site

Austroads 2013 62

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

6.7

Traffic Monitoring

Weekly traffic data for Kwinana Freeway provided traffic classification counts on the northbound lane of Kwinana Freeway just south of the Mundijong Rd Bridge for the period 200611 as given in Table 6.5.
Table 6.5: Kwinana Freeway northbound carriageway daily heavy vehicle volumes
Survey date 3 07 July13 July 2006 23 June 20102 July 2010 10 August 201117 August 2011 414 1105 1541 4 113 142 182 5 59 27 27 Austroads vehicle classification 6 25 37 82 7 183 58 84 8 40 52 152 9 200 356 259 10 27 94 88 11 38 140 143 12 20 2 5

Source: Personal communication Kenworthy-Groen (2012).

Table 12 of Main Roads Engineering Road Note 9 (MRWA 2013) provides the average ESA of pavement loading for each Austroads vehicle class. Table 6.6 lists the values recommended for use for this project.
Table 6.6: Kwinana Freeway average ESA per heavy vehicle type
Austroads vehicle classification 3 0.49 4 2.63 5 2.8 6 0.68 7 1.49 8 3.73 9 4.69 10 6.79 11 8.88 12 11.54

Source: MRWA (2013), Table 12 Kwinana Freeway (H015) SLK56.84, Mandurah.

The annual ESA of loading were calculated based on:


annual heavy vehicle volumes in the slow lane calculated from the average daily values

(Table 6.5) and assumed 70% of heavy vehicles travel in the slow lane
the ESA of damage per heavy vehicle type (Table 6.6).

The calculated annual ESA of loading for 2006, 2010 and 2011 were 7.1 x 105 ESA, 1.2 x 106 ESA and 1.3 x 106 ESA. Based on this data, Figure 6.3 shows the predicted cumulative traffic loading over the 10 year period from pavement construction in 2010 assuming an annual ESA of loading increase of 1.2 x 106 ESA.

Austroads 2013 63

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

1.9E+07

1.7E+07

1.5E+07

1.3E+07

Cumulative 1.1E+07 traffic loading 9.0E+06 (ESA)


7.0E+06

5.0E+06

3.0E+06

1.0E+06 2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

Year

Figure 6.3: Predicted cumulative traffic loading

6.8

Performance Review

Based on the traffic data in Section 6.7 it would take about 10 years of cumulative traffic loading to reach the predicted fatigue life of 1.7 x 107 ESA (50% design reliability). Currently, there is no pavement distress after 3.3 years of cumulative traffic loading. It is planned to monitor the pavement over the next three years to provide detailed data on pavement performance (surface defects, cracking, rutting, roughness, deflection) for the validation of the Austroads interim FBS thickness design procedure. As it is unlikely that cracking will be observed by the completion of the project (June 2015), reliance will be placed on the change in measured surfaced deflections as an indicator of structural deterioration.

Austroads 2013 64

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

7
7.1

NEW ENGLAND HIGHWAY QUEENSLAND


Brief Description

In March to May 1999, two separate sections (with a total 16.74 km road length) on New England Highway (between Toowoomba Road-Warwick Road) in Queensland were rehabilitated using FBS to correct shape loss and improve strength. The first section was between 34.4548.25 km (between Toowoomba-Warwick Road) and the second section between 52.7555.69 km (north of Warwick). Details of locality and job statistics (job size, FBS specification and construction method) for the New England Highway FBS pavement are given in Table 7.1.
Table 7.1: Job description of New England Highway FBS pavement
Location Job size New England Highway (22B) (ToowoombaWarwick Road) between 34.4548.25 km and 52.7555.69 km Length Number of lanes Lane width FBS thickness Foamed stabilisation specification Mix design Host material Quicklime Foamed bitumen Foaming agent Construction method Work specifications and QA testing Construction date 16.74 km 2 4m 200 mm (IWP) and 250 mm (OWP) Empirically-based method and new TMR FBS mix design Existing granular base materials (20 mm well graded clayey gravel complied with MRS11.05 C grading) 2 % hydrated lime 3.5% Class 170 bitumen 0.5% TMR construction specifications MRS 11.07 23 March28 May 1999

Figure 7.1 shows a view of the pavement.

Figure 7.1: New England Highway FBS pavement, near Nobby Connection Road intersection (34.5 km)

The pavements were designed and constructed to TMR standards (Kendall et al. 2001, Ramanujam & Jones 2000, Ramanujam et al. 2009).

Austroads 2013 65

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Data on site investigation, mix design, pavement design, construction, maintenance and traffic and field performance for this road gathered from various TMR reports is briefly described below.

7.2

Site Investigation Prior to Stabilisation

Prior to stabilisation the pavement was a sprayed seal unbound granular pavement. By 1999 the pavement had a significant amount of rutting of the well graded clayey gravel base over the low strength black soil subgrade. There were also a number of sections of the pavement which had been rehabilitated by cement stabilisation. Consequently TMR decided to rehabilitate the pavement using FBS to correct shape loss and improve strength. Prior to construction, dynamic cone penetration testing was conducted. This testing confirmed that the subgrade was of CBR 5% or greater (Ramanujam et al. 2009).

7.3

Mix Design

The bitumen and lime contents for the works were selected based on TMR experience obtained from previous FBS trials in Queensland and the FBS mix design method under development by TMR at that time (Ramanujam & Jones 2000, Kendall et al. 2001). For the mix design, samples from the original well graded clayey gravel base were collected in accordance with TMR standard materials sampling procedures. Preliminary assessment testing of the base material was conducted to confirm that the materials met the TMR specifications for stabilisation (in terms of particle size distribution, Atterberg limits and moisture density relationship). It was reported to comply with the MRS11.05 C particle size distribution envelopes and had a fines content between 5% and 15% passing the 0.075 mm sieve. The measured Atterberg limits were not reported. TMR performed a number of laboratory tests to optimise the binder contents and foamed water content. Class 170 bitumen was preferred for foamed bitumen stabilisation. Tests indicated the desirable foaming properties were usually achieved with a water content of 2.5%. A foaming agent (0.5% by mass of the bitumen) was also added to the bitumen to enhance the bitumen foaming properties. The optimum bitumen content of the FBS mix was also selected on the basis of laboratory modulus and rut resistance. Based on the results of cured wet indirect tensile test (IDT) resilient moduli of mixes with bitumen contents in the range of 24% and 1.5% quicklime (Figure 7.2), a mix with 3.5% bitumen and 1.5 % quicklime was selected: this mix had the highest indirect tensile modulus of about 2100 MPa. This mix also met the TMR minimum guidelines for IDT modulus. Test slabs of the selected mix design were prepared in the laboratory and tested using the wheel-tracker test for rut resistance. It was reported that the rut resistance also met the TMR minimum guidelines for rut resistance.

Austroads 2013 66

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

2200

2000

Modulus (MPa)

1800

1600

1400

1200 2 2.5 3 Bitumen Content (%) 3.5 4

Source: Kendall et al. (2001).

Figure 7.2: Results of cured wet modulus for various FBS mixes for New England Highway FBS pavement

7.4

Thickness Design

Kendall et al. (2001) reported that the FBS pavement was designed and constructed to have a design life of 20 years. Although there were large variations in pavement thicknesses and subgrade support along the 17 km pavement length of this road section, the selected treatment was as follows:
FBS was carried out to a width of 8 m (i.e. traffic lanes plus 0.5 metre of each shoulder) rather

than full width


the FBS depth was 200 mm for the inner wheelpath (IWP) and 250 mm for the outer wheelpath

(OWP)
a primer seal was initially applied on the FBS base.

Note that Kendall et al. (2001) advised that the thickness design anticipated that a 75 mm thick asphalt overlay would be required on most sections to achieve the 20 year life. Based on deflection testing after construction it was concluded that this structural overlay was not required. As discussed in Section 7.10, the Austroads interim thickness design method predicts a fatigue life significantly less than 20 years.

7.5

Pavement Construction

The pavement was constructed between March and May 1999 using a new specification developed for the project. This project specification was later modified to produce the Main Roads Standard Specifications MRS 11.07 Specification for In situ Stabilisation. The project specification provided detailed specifications of stabiliser and compaction equipment and construction tolerances as given below:
A 30 t Wirtgen WR 2500 stabiliser was used and the construction tolerance for the application

rate for the binder and supplementary binder was 10% of the specified values. The depths of stabilisation had a construction tolerance of 15 mm.

Austroads 2013 67

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Compaction equipment included (a) an 18 t vibrating padfoot roller; (b) a 12 t vibrating smooth

drum roller; and (c) a 15 t multi-tyre roller. The stabilised pavement layers were required to be compacted to a dry density ratio of not less than 100% Standard Maximum Dry Density. It was reported (Kendall et al. 2001) that:
most of the recorded lime spread rates and bitumen pumping speeds were within the tolerance

of 5% of the specified lime-spread rate and bitumen-pumping speed


the design FBS depth (200 mm at IWP and 250 mm at OWP) were achieved with a tolerance of

15 mm
most of the recorded field density results were in the range of 100110% Standard Maximum

Dry Density
compaction moistures of the FBS layers varied over the large range (48%) due to different

initial in situ moisture contents at different locations. In a number of locations the granular pavement had been previously rehabilitated using cement stabilisation. These cement stabilised materials were not removed but incorporated in the FBS pavement (Kendall et al. 2001).

7.6

Pavement Coring

In April 2000 prior to the application of the final seal, four FBS cores were extracted from the pavement to compare in situ properties with design values (Ramanujam & Jones 2007). They were cored in a staggered pattern 250 m apart (chainages have not been reported). The results are given in Table 7.2. Although the cured wet moduli were clearly high, the measured bitumen contents of three of the four cores were well below the design values of 3.5%.
Table 7.2: Results of New England Highway cores extracted April 2000
Core Sample Cured dry modulus (MPa) 6 725 5 761 3 180 2 533 10 907 8 468 7 330 7 200 5 743 2 428 6 000 7 831 2 744 Cured wet modulus (MPa) 4 139 3 749 3 406 1 290 9 329 11 270 5 852 6 275 5 220 2 072 5 308 5 911 1 842 Bitumen content (%) 2.05 2.10 2.10 2.40 2.55 2.50 2.85 3.20 2.55 3.20 4.10 3.40 3.75 Compacted density (t/m3) 2.265 2.234 2.137 2.076 2.326 2.303 2.225 2.173 2.174 2.107 2.232 2.295 2.213 Air voids (%) 14.0 15.2 19.9 21.5 6.8 7.1 11.1 7.2 9.2 13.4 8.5 5.8 10.8

Outer wheelpath

Top Middle 1 Middle 2 Bottom

Inner wheelpath

Top Middle Bottom Top Middle Bottom Top Middle Bottom

Outer wheelpath

Inner wheelpath

Austroads 2013 68

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

7.7

Pavement Maintenance

The TMR network survey provides maintenance history recorded over the full length of the project since construction in 1999, as summarised in Table 7.3.
Table 7.3: New England Highway maintenance
Section 1 Date April 2000 June 2000 November 2002 November 2010 November 2010 November 2011 November 2011 November 2011 November 2011 2 April 2000 November 2011 Chainage (km) 34.4548.25 47.2847.68 36.8143.61 37.6038.80 46.8747.28 34.4536.43 36.4338.8 38.846.89 46.8948.28 52.7555.69 52.7555.69 Length (km) 13.8 (full length) 0.40 6.80 1.20 0.41 1.98 2.37 8.09 1.39 2.94 (full length) 2.94 (full length) Treatment Final seal over the primerseal placed at construction a year after FBS construction 80 mm asphalt overlay Geotextile reinforced seal 30 mm dense graded asphalt overlay 30 mm dense graded asphalt overlay Double application PMB seal Geotextile reinforced seal Single application PMB seal Geotextile reinforced seal Final seal over the primerseal placed at construction Single PMB seal

Of particular note was the geotextile reinforced seal placed over about a third of the project length in November 2002 after about three years trafficking. A section of this (36.4338.8 km) needed to be re-treated with a geotextile seal in November 2011. By November 2011 about half (8.19 km) of the project length had received a geotextile reinforced seal. Note that 12 months before the geotextile seal was placed, a 30 mm corrector course of asphalt was required at some locations due to the loss of shape after cracking. Advice from TMR regional staff is that geotextile seals were required because of extensive cracking in the wheelpaths. The cracking was generally longitudinal in the wheelpaths as shown in Figure 7.3. However between chainages 36.43 to 38.8 km in addition to the longitudinal cracking there are some limited areas of severe crocodile fatigue cracking (Figure 7.4).

Austroads 2013 69

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Source: Google maps (2013).

Figure 7.3: Cracking at chainage 47.5 km in November 2009, 12 months before geotextile seal was placed

Source: Google maps (2013).

Figure 7.4: Cracking at chainage 37.8 km in November 2009, 12 months before geotextile seal was placed

Austroads 2013 70

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

7.8
7.8.1

Performance Monitoring
Visual Inspections

In May 2013 the pavement was visually inspected. Generally, the southbound lane was in worse condition than the northbound, perhaps due to the southbound vehicles heading from Toowoomba being more heavily laden. As described in Section 7.7, geotextile seals have been placed over a substantial portion of Section 1 (34.4548.25 km) which presumably hides much of the cracking. The cracking in these areas is longitudinal cracking both in the loaded areas of the pavements (wheelpaths) and unloaded areas. As such, the longitudinal cracking is unlikely to be related to the fatigue of the FBS base. The most likely source of the longitudinal cracking is changes in moisture content of highly plastic black soil subgrade. Clearly, such cracking has a major influence on the fatigue performance of the FBS material. In addition, TMR advice is the re-stabilisation of previously cement stabilised patches may have contributed to the cracking. TMR advise that re-stabilisation is now not encouraged and replacement of the patch with granular material prior to stabilisation is recommended. These factors limit the usefulness of the site for the Austroads project. Figure 7.5 shows the pavement condition in the north of the Spring Creek Road intersection, an area that has not been treated with a geotextile seal. Like a number of other areas along the project, the surface condition suggests transverse cracking in the wheelpaths indicative of fatigue cracking. For the New England Highway performance data to be of use in evaluating the structural design method, pavement sections without longitudinal cracking will need to be identified.

Figure 7.5: Flushed binder on the surface suggests transverse cracking under the PMB seal, chainage 46.7 km

At the time of inspection geotextile seals had not been placed in Section 2 (52.7555.69 km) and this allowed a better appreciation of the extent of fatigue cracking. Figure 7.6 illustrates the development of transverse fatigue cracking along the inner wheelpath.

Austroads 2013 71

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Figure 7.6: Transverse fatigue cracking in New England Highway FBS pavement, chainage 53.6 km

In the vicinity of chainage 54.8 km, there is currently extensive block cracking and rutting as shown in Figure 7.7.

Figure 7.7: Severe cracking in southbound lane near chainage 54.8 km

In 201314, pavement investigations will be undertaken at various locations in Section 2 (52.7555.69 km) to measure pavement deflections, layer thickness and in situ subgrade CBR in areas that have fatigue cracked but do not exhibit longitudinal cracking. A thermal imaging camera may be useful to identify cracks below the geotextile seals. 7.8.2 2012 Roughness and Rutting Data

Figure 7.8 shows the data on rutting and roughness for the full length of the New England Highway (22B) as of February 2012.

Austroads 2013 72

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

It is apparent that despite the fatigue cracking that has occurred, the maintenance treatments (Section 7.7) have resulted in rut depths generally not exceeding 10 mm and the roughness below the level where intervention may be required (IRI = 3.5 m/km). There are however some shorter sections (e.g. 54.6554.85 km) that require treatment due to extensive cracking and associated rutting.
20 18 16 14 12

OWP IWP

Rut depth 10 (mm)


8 6 4 2 0 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

Chainage (km)

3.5

Roughness IRI 2.5 (m/km)


2

1.5

1 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56

Chainage (km)

Figure 7.8: 2012 rutting and roughness for New England Highway FBS pavement

Austroads 2013 73

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

7.9

Traffic Monitoring

Table 7.4 shows the measured truck traffic counts in 2012 provided by TMR from which the 2012 ESA of loading were calculated, based on an assumed average 3 ESA of damage per heavy vehicle from weigh-in-motion data on Gore Highway and Warrego Highway near Toowoomba (Austroads 2012). Assuming a 4% traffic growth rate, the cumulative traffic loadings after 14 years of trafficking (May 2013) were estimated as shown in Table 7.4.
Table 7.4: Estimated 2012 traffic loading
Chainage (km) 34.4543.73 43.7356.91 2012 daily heavy vehicles (one-way) 226 269 2012 annual heavy vehicles (one-way) 8.2 x 104 9.8 x 104 2012 annual ESA 3.3 x 105 3.9 x 105 Cumulative ESA at May 2013 2.6 x 106 3.1 x 106

7.10

Performance Prediction

A key objective of the project is to improve the Austroads interim thickness design procedure. It is apparent from the above that the New England Highway will provide valuable information in this regard, provided areas can be identified where FBS fatigue cracking is not affected by the longitudinal cracking of the black soil subgrade. In the interim method, the FBS design modulus is determined from indirect tensile moduli measured on laboratory-manufactured specimens cured for three days at 40 C and then soaked in water under vacuum of 95 kPa for 10 minutes. These cured wet moduli are overly conservative moduli compared to the field cores as illustrated from the Calder Freeway trial data (Section 3.8.2). Consequently, at this stage in the project, it is suggested the FBS design moduli be determined from the cured dry moduli of laboratory-manufactured specimens. In the New England Highway mix design, a soaked indirect tensile modulus of 2100 MPa was reported (Figure 7.2) for a 3.5% bitumen content. However, limited core data (Table 7.2) suggests the mean bitumen content in situ is about 3%. The soaked modulus at this bitumen content is about 1900 MPa. Cured dry moduli of laboratory-manufactured specimens have not been reported. It is noted the dry moduli of the field cores were about 20% higher than the cured wet moduli (Table 7.2). Using this factor, the dry modulus of laboratory-manufactured specimens at 3% bitumen is estimated to be 2300 MPa at a temperature of 25 C. Adjusting this dry cured modulus to a WMAPT of 27 C (Toowoomba) and for a design traffic speed of 80 km/h, a FBS design modulus of 2000 MPa was calculated. Table 7.5 provides a summary of the currently available data to predict the FBS fatigue life. Referring to Table 7.5:
A subgrade design CBR of 4% was adopted consistent with Ramanujam et al. (2009). Note

that most of the pavement lies on the highly plastic black soils of Darling Downs.
The thickness of granular subbase after stabilisation in the 2011 TMR Network Survey is

uncertain. However, for pavement with this traffic loading and subgrade design CBR it is considered that the total granular thickness would have been at least 400 mm prior to stabilisation. The remaining granular subbase thicknesses used in the calculation were based on an assumed 400 mm total thickness.

Austroads 2013 74

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

An analysis was undertaken using the data set as given in Table 7.5. This analysis produced a predicted allowable loading to fatigue of 6.2 x 105 ESA (for the IWP) to 2.4 x 106 ESA (for the OWP) at 50 % design reliability.
Table 7.5: Data for predicting allowable traffic loading of New England Highway FBS pavement
Pavement component Subgrade Design parameter Subgrade support Subgrade design modulus Granular subbase FBS base Thickness Design modulus Thickness Design modulus Selected data CBR 4% 40 MPa 225 mm IWP 175 mm OWP 5 sub-layers 175 mm (IWP) 225 mm (OWP) 2000 MPa Technical basis for data selection Ramanujam et al. (2009) reported a minimum subgrade support of 4% in fatigued areas. Based on the relationship of subgrade modulus = 10 CBR (Austroads 2012). Assumed 400 mm thick granular pavement prior to stabilisation. Based on Table 6.4 of Austroads (2012). Mean thickness of 250 mm (OWP) and 200 mm (IWP) and construction tolerance of 15 mm as per TMR construction specifications. Laboratory dry modulus was taken as half the modulus of field cores based on Calder Freeway results. Dry modulus was then adjusted for temperature and loading rate using a Weighted Mean Annual Pavement Temperature = 27 C and a heavy vehicle design speed = 80 km/h. Assumed based on bitumen content 3%. Double spray seal is not considered as a structural component (Austroads 2012).

Volume of binder Surfacing Thickness Design modulus

7% n.a. n.a.

7.11

Comparison of Observed and Predicted Performance

As the cumulative traffic loading to date exceeds these predicted lives, the Austroads interim design method predicts there is a 50% probability of observing fatigue cracking. As discussed in Section 7.8.1, there has been widespread longitudinal cracking along New England Highway for a number of years. Although the longitudinal cracking is commonly in the wheelpaths there is some doubt about the cause of this cracking. It may relate to the use of different stabilisation depths in the outer and inner wheelpaths or to reactive subgrade soils. In addition crocodile fatigue cracking has occurred in some areas and these areas are considered as more reliable sources of data to calibrate the design model. Of particular interest is the performance of Section 2 (52.7555.69 km). To enable more accurate prediction of allowable loading, it is proposed to obtain the following data by coring/trenching at several sites along the project (subject to TMR approval):
thicknesses of FBS base and underlying granular subbase in situ subgrade CBR as estimated from dynamic cone penetrometer measurements binder content of the FBS material.

Nevertheless, the accuracy of the performance prediction will be limited due to the absence of measured cured dry modulus of laboratory-manufactured specimens. The other complication in utilising the performance data from this site is the unusual pavement design in which the FBS thickness in the outer wheelpath was 50 mm greater than the inner wheelpath. It is not known whether this discontinuity has influenced the FBS fatigue characteristics. In addition, there is a need to discount the influence of longitudinal cracking due to moisture changes in the highly plastic black soil subgrade as mentioned above.

Austroads 2013 75

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

8
8.1

PROPOSED 201314 RESEARCH


Introduction

This section describes the proposed scope of research to be undertaken in 201314 in consultation with the project Working Group.

8.2

Mix Design

Section 2 describes progress in developing the test methods for use in the Austroads mix design procedure. 8.2.1 Test Methods

Table 8.1 lists the test methods that have been identified for drafting. The initial drafts of test methods T301, T305, T310 and T311 have been revised in light of the Working Group comments. It is anticipated these methods may need to be revised in 201314 following trial use and feedback from users. In addition, the remaining test methods will be drafted.
Table 8.1: Test methods under development
Number T301 T305 T310 T311 T313 T320 T321 T330 T340 Determination of Foaming Properties of Bitumen Mixing of Foamed Bitumen Stabilised Materials (includes method of establishing mixing moisture content) Compaction of Test Cylinders of Foamed Bitumen Stabilised Mixtures: Part 1 Dynamic Compaction Using Marshall Drop Hammer Compaction of Test Cylinders of Foamed Bitumen Stabilised Mixtures: Part 2 Gyratory Compaction Compaction of Test Slabs of Foamed Bitumen Stabilised Mixtures Curing of Test Cylinders of Foamed Bitumen Stabilised Mixtures Curing of Test Slabs of Foamed Bitumen Stabilised Mixtures Resilient Modulus of Foamed Bitumen Stabilised Mixtures Deformation Resistance of Foamed Bitumen Stabilised Mixtures by the Wheel-tracking Test Title Status Drafted Drafted Drafted Drafted To be drafted in 201314 To be drafted in 201314 To be drafted in 201314 To be drafted in 201314 To be drafted in 201314

8.2.2

Laboratory Testing

It is proposed to undertake laboratory testing with the objectives of:


providing improved guidance on how to select the mixing moisture content for preparation of

test specimens for modulus testing


quantifying the influence of the laboratory compaction method (100 mm mould Marshall,

150 mm mould Marshall, gyratory and Modified/Standard hammer) on indirect tensile modulus.

Austroads 2013 76

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

8.3
8.3.1

Structural Design
Calder Freeway Woodend

In 201314 the following testing is proposed in March 2014, 12 months after construction:
visual inspection FWD deflection testing to assess whether the FBS modulus has increased or decreased in

trafficked and untrafficked areas


coring of the FBS layer between wheelpaths to determine stabilisation depth and

laboratory-measured indirect tensile modulus. In situ layer moduli will be back-calculated from the FWD deflections and layer thicknesses. Appendix A lists the pavement inspection and testing procedures. 8.3.2 Port Wakefield Road Virginia

The pavement is currently distressed and may be resurfaced during 201314. This may impact on the proposed testing and monitoring. The testing to date indicates most of the pavement has very high bitumen contents. A critical issue is to obtain more bitumen content data to possibly identify a section with a more commonly used bitumen content (< 4%). At this stage it is proposed to visually inspect the pavement and undertake additional coring of the FBS layer to determine thickness, moduli, particle size distributions and bitumen contents. If a section with more commonly used bitumen content (< 4%) is identified, FWD deflections in and between wheelpaths together with measurements of pavement temperature will be also taken. 8.3.3 Kewdale Road Welshpool

To refine the pavement performance predictions, the indirect tensile modulus of laboratory manufactured specimens will be undertaken. In addition the following will be undertaken:
visual inspection FWD deflection testing to assess whether the FBS modulus has increased or decreased in

trafficked and untrafficked areas


coring of the FBS layer in the outer wheelpath and between wheelpaths to determine

stabilisation depth and in situ moduli. 8.3.4 Kwinana Freeway Perth

The testing will be limited to:


visual inspection FWD deflection testing to assess whether the FBS modulus has increased or decreased in

trafficked and untrafficked areas. 8.3.5 New England Highway Queensland

As reported in Section 7, over half of this 17 km long project has now been treated with a geotextile seal, principally to address longitudinal cracking likely to be due to moisture changes in the highly plastic black soil subgrade.

Austroads 2013 77

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

A detailed investigation of New England Highway is proposed to identify areas that have fatigue cracked without being influenced by this longitudinal cracking. Another complication in using the data from this site is the variation in FBS thickness occurring across the pavement. 8.3.6 Review Other Monitoring Sites

In addition to the monitoring data for five sites reported in Section 3 to Section 7, Austroads project TT1663 (Vuong 2012) recommended some limited monitoring of the following four sites:
Somerton Road, Campbellfield, Victoria State Highway 26, Kurere Stream, New Zealand State Highway 1, Cherry Lane, New Zealand State Highway 3, Te Kuiti, Waikato, New Zealand.

In this progress report it is suggested that these four sites be no longer monitored in the project as the data will not assist in refining the interim thickness design method. Somerton Road was constructed in 1993 about 20 years ago. As reported by Vuong a substantial length of the project has since been rehabilitated and he concluded:
Only the pavement section on the westbound left lane between chainages 320-1420 m, which had a reseal (with 10 mm spray seal) in 1995 and appeared to show fatigue cracking in 2006, is suitable for the performance review.

A 50 mm asphalt overlay has been applied to this area since 2006, which makes it difficult to assess the extent and timing of the FBS cracking. In addition and most importantly, the pavement was stabilised with 3% cement works flue dust and 3% bitumen. The use of 3% cement works flue dust is likely to have resulted in a more fatigue-susceptible material than is current stabilisation practice. In addition, it will be difficult to estimate the design modulus of the material a critical parameter in the thickness design method. Given the above, it is considered no further evaluation of Somerton Road pavement is warranted in this project. At the outset of the Austroads research of foamed bitumen stabilisation commencing with Austroads project TT1663, it was considered desirable to include performance monitoring of New Zealand pavements given the different mix types and FBS thickness used. The above three New Zealand pavements were suggested for inclusion in the Austroads research. As reported by Vuong (2012) two (Cherry Lane and Te Kuiti) of the three pavements had at least 100 mm granular resheet of size 65 mm granular base (GAP 65 grading) to correct shape. Given the FBS thickness is 175 mm to 200 mm, about half of the host material is size 65 mm granular base. The modulus of FBS materials is a critical input in the Austroads interim thickness design method. In the interim method the design modulus is estimated from the laboratory indirect tensile modulus testing of laboratory manufactured mixes. This characterisation method is applicable to materials with a maximum size of 40 mm. As such, the design modulus of the Cherry Lane and Te Kuiti materials will not be able to be measured. As this significantly impacts on the ability to design the pavements with the Austroads interim method, it is considered no further evaluation of these two pavements is warranted in this project. It is proposed that State Highway 26 Kurere Stream be retained for evaluation but due to its variable composition including sections with very high contents of recycled asphalt, the evaluation in 201314 be limited to a visual condition survey.

Austroads 2013 78

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

8.3.7

Additional Sites

Preliminary discussions have been held with Roads and Maritime Services New South Wales in relation to construction of an under-designed FBS pavement as part of rehabilitation works being undertaken on the heavily trafficked Newell Highway. The above-mentioned 201314 project tasks may need to be adjusted if this valuable additional site can be included in the project.

Austroads 2013 79

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

SUMMARY

Improvements are required to the current Austroads interim mix design and structural design methods for foamed bitumen stabilised pavements. This report details progress to address this need under Austroads project TT1825 Mix design and field evaluation of foamed bitumen stabilised pavements.

9.1

Mix Design

Under the guidance of a project Working Group the mix design framework has been agreed. It has been decided to build on the experience of Department of Transport and Main Roads Queensland and use the indirect tensile modulus as the principal pavement performance measure in the mix design process. To date the following draft test methods have been developed:
T301 Determination of foaming properties of bitumen T305 Mixing of foamed bitumen stabilised materials T310 Compaction of test cylinders of foamed bitumen stabilised mixtures: Part 1 Dynamic

compaction using Marshall drop hammer


T311 Compaction of test cylinders of foamed bitumen stabilised mixtures: Part 2 Gyratory

compaction. During 201314 these draft test methods will finalised based on use and feedback from the Working Group. To assist in this regard, testing will be undertaken to assess the significance of mixing moisture content on measured modulus and also the differences in modulus results between Marshall and gyratory compacted test cylinders. In addition, the following test methods will be drafted:
T313 Compaction of test slabs of foamed bitumen stabilised mixtures T320 Curing of test cylinders of foamed bitumen stabilised mixtures T321 Curing of test slabs of foamed bitumen stabilised mixtures T330 Resilient modulus of foamed bitumen stabilised mixtures T340 Deformation resistance of foamed bitumen stabilised mixtures by the wheel-tracking test.

9.2

Thickness Design

In terms of the structural (thickness) design of FBS pavements, an under-designed FBS pavement was constructed on the Calder Freeway, Woodend, Victoria in March 2013. The trial involved the collaboration of VicRoads, industry and ARRB. The trial section was nominally 150 mm thickness of FBS, stabilised with 3.5% bitumen and 1.5% quicklime with a sprayed seal surfacing. The report describes the mix design, the construction process, testing during construction and the early-life performance monitoring. The findings to date are:
the very different project mix design results produced by two experienced laboratories

highlighted the need for this Austroads project


when the FBS pavement was opened to traffic without the sprayed seal surface it ravelled and

rutted in the first 24 hours but thereafter achieved a sound, stable basecourse of high modulus and high rut-resistance
eight days after construction, the FBS had cured such that cores were able to be taken from the

pavement

Austroads 2013 80

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

surface deflections taken at eight days and one month after construction were reasonably

similar consistent with the view the FBS has quickly cured in the high temperatures in the first week after construction. It is planned to monitor the performance of this pavement over the next three years. In March 2011 an under-designed FBS pavement was constructed on Port Wakefield Road, Virginia South Australia. It consisted of a 100 m long section of nominal 150 mm thick FBS and about 900 m length of nominal 200 mm thick FBS. The existing calcrete limestone base was stabilised with nominal 3% bitumen and 1% hydrated lime. The pavement has a sprayed seal surfacing. About 18 months after construction fatigue cracking was observed, reasonably consistent with the predictions of the Austroads interim structural design method. However, cores recovered from the nominal 150 mm thick section had very high bitumen contents (mean > 5%) possibly due to use of an inappropriate bitumen application rate. Consequently, there is doubt about the usefulness of the performance data of this material. In addition, about half of the cores taken from the nominal 200 mm thick FBS section had measured bitumen contents in excess of 5%, possibly due to the inclusion of asphalt patching materials and old sprayed seals. Again, there is doubt about the usefulness of the performance data at these sites. Further testing is required to clearly identify the pavement areas more typical bitumen contents which can be used to provide feedback on the structural design process. In November 2011, the City of Canning in Perth, Western Australia constructed two short underdesigned FBS sections, with nominal thicknesses of 150 mm (Section 1) and 100 mm (Section 2) on Kewdale Road, Welshpool. The host material was a mixture of crushed granite base and recycled asphalt, with a small quantity of crushed limestone subbase. The material was stabilised with nominal 3.5% bitumen and 0.8% hydrated lime and surfaced with 30 mm of dense graded asphalt. Like the Calder Freeway trial, the Kewdale Road trial sections ravelled when the unsealed FBS base was opened to traffic on the day of construction. The asphalt surfacing has since covered this ravelling. After 18 months trafficking, the pavement is in good condition, with minimal rutting and no cracking. Surface deflections measured periodically since construction are consistent with that expected of high modulus FBS base. As the deflections measured seven weeks and 13 months after stabilisation were similar, the pavements appear to have fully cured within seven weeks of construction. There is no evidence yet that the FBS layers are deteriorating structurally due to trafficking. In 201314, cores will be taken from the pavement to confirm mix properties and layer thicknesses and deflection measurements repeated. Consideration will also be given to undertaking a mix design with the trial materials using the draft test methods. In February 2010, Main Roads Western Australia constructed an under-designed pavement on Kwinana Freeway, Perth. The nominal 150 mm FBS layer was constructed by stabilising predominately hydrated cement treated crushed rock base (HCTCRB) with 3% bitumen and 0.8% hydrated lime. The surfacing over the FBS base comprised 30 mm open graded asphalt, geotextile reinforced seal and 30 mm dense graded asphalt. As this surfacing will inhibit fatigue cracking of the FBS layer reflecting through the surface, changes in measured surface deflections are being used to assess structural deterioration of the FBS layer.

Austroads 2013 81

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

After three years of trafficking, the Kwinana Freeway pavement is in sound condition. The deflections indicate the FBS layer has not deteriorated structurally. As the pavement is constructed on a sand subgrade, the Austroads interim design method predicts a fatigue life of about 10 years, that is in 2020. As such, the pavement may not deteriorate structurally by the end of the research project in 2016. In 201314, the surface deflection measurements will be repeated. The longest pavement section being monitored is a 17 km length of New England Highway, Allora, Queensland which was constructed in 1999. It is unusual in that the stabilisation depth was 250 mm in the outer wheelpath and 200 mm in the inner wheelpath. The cumulative traffic loading over the last 14 years has been about 23 x 106 ESA. There has been extensive longitudinal cracking along the project that has necessitated the placement of geotextile seals over about half the pavement length. This cracking does not appear to be fatigue cracking, rather cracking due to moisture changes in the highly plastic black soil subgrade. In addition to this longitudinal cracking, there are increasing areas of crocodile fatigue cracking consistent with performance predictions. Pavement coring/trenching and associated materials testing is required to improve the usefulness of the New England Highway data for performance prediction. Three New Zealand sites were initially included in the monitoring program. Two of these pavements included FBS materials with a maximum particle size of 65 mm. Consequently, it is not possible to prepare laboratory-manufactured mixes to measure indirect tensile modulus and hence determine the FBS design modulus. Accordingly, it is proposed to discontinue monitoring these sites. Similarly it is proposed to discontinue monitoring Somerton Road, Campbellfield, Victoria. This pavement was constructed in 1993 and has since been partially reconstructed. It also was stabilised with 3% cement works flue dust, not consistent with current practice. During 201314, discussions will be held with road agencies and industry seeking opportunities to include additional under-designed pavement sections in the monitoring program.

Austroads 2013 82

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

REFERENCES
Austroads 2006, Guide to pavement technology: part 4D: stabilised materials, AGPT04D/06, Austroads, Sydney, NSW. Austroads 2011a, Guide to pavement technology: part 5: pavement evaluation and treatment design, AGPT05-11, Austroads, Sydney, NSW. Austroads 2011b, Pavement roughness measurement with an inertial laser profilometer, test method AGAM/T001, Austroads, Sydney, NSW. Austroads 2011c, Pavement rutting measurement with a multi-laser profilometer, test method AGAM/T009, Austroads, Sydney, NSW. Austroads 2011d, Review of foamed bitumen stabilisation mix design methods, APT178/11, Austroads, Sydney, NSW. Austroads 2011e, Review of structural design procedures for foamed bitumen pavements, APT188/11, Austroads, Sydney, NSW. Austroads 2012, Guide to pavement technology: part 2: pavement structural design, AGPT02-12, Austroads, Sydney, NSW. Clayton, B 2000, Guidelines for site establishment and data collection for new long-term pavement performance site, unpublished contract report, ARRB Transport Research, Vermont South, Vic. Department of Planning, Transport and Infrastructure 2007, Construction of foamed bitumen stabilised pavement, specification part 224, DPTI, Adelaide, SA. Department of Planning, Transport and Infrastructure 2011, Traffic counts for Port Augusta: Port Wakefield/Port Wakefield Rd Site 6037 location 1.7 km south of RN 5000 (Angle Vale Rd), Spatial Intelligence and Road Assets Section, DPTI, Adelaide, SA. Kendall, M, Baker, B, Evans, P & Ramanujam, J 2001, Foamed bitumen stabilisation: the Queensland experience, ARRB Transport Research conference, 20th, 2001, Melbourne, Victoria, ARRB Transport Research Ltd, Vermont South, Vic, 57 pp. Main Roads Western Australia 2010, Construction specification foamed bitumen stabilised trial Kwinana freeway, MRWA, Perth, WA. Main Roads Western Australia 2013, Procedure for the design of road pavements, engineering road note no. 9, MRWA, Perth, WA. Ramanujam, J & Jones, J 2000, Characterisation of foam bitumen stabilisation, Road System and Engineering Technology Forum, 2000, Brisbane, Australia, Queensland Department of Main Roads, Brisbane, Queensland, 23 pp. Ramanujam, J, Jones, J 2007, Characterisation of foamed-bitumen stabilisation., International Journal of Pavement Engineering, 8:2, pp111-122. Ramanujam, J, Jones, J & Janosevic, M 2009, Design, construction and performance of insitu foamed bitumen stabilised pavements, Queensland Roads, no.7, pp. 5669. Standards Australia 1997, Methods of sampling and testing asphalt: bitumen content and aggregate grading: pressure filter method, AS/NZS 2891.3.3:1997, Standards Australia, North Sydney, NSW.

Austroads 2013 83

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Strategic Highway Research Program 1989, SHRP LTPP manual for FWD testing: operational field guidelines, version 1, operational guide no. SHRP-LTPP-OG-002, SHRP, Washington DC, USA.

Austroads 2013 84

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

APPENDIX A
A.1
A.1.1

FIELD PERFORMANCE MONITORING PROCEDURES FOR LTPP SITES

Visual Inspection Procedure


General

The objective of the visual inspection of the LTPP and LTPPM sites was to record pavement surface defects that are not collected through pavement monitoring activities such as deflection testing, transverse (rutting) and longitudinal profile (roughness) measurements. The primary focus of this inspection is to collect cracking information while paying reasonable attention to other defects such as potholes, ravelling, shoving, flushing and patching, etc. The quality of the data collected is limited by the site conditions such as whether the site has traffic control arrangements in place. In most cases, traffic control arrangements are made during deflection testing activities which allow the inspector to walk on the test site and record the defects in detail. A.1.2 Detailed Procedure

With traffic control arrangements Walk on the pavement and examine if there is any defect. Measure the parameters listed (Table A 1) according to the defect type and draw the defect on the LTPPM survey form. Where appropriate, record joint/crack width and number of potholes beside the sketch. Photographs of defects are also taken and a table recording pavement characteristics is collated. In the event of inadequate light such as at night, visual inspection should still be carried out with the help of lights. However, safety shall not be compromised in any situation. Without traffic control arrangements Wear a safety vest and walk along the left shoulder while maintaining safe distances from the traffic (safety shall not be compromised in any situation) and look for pavement defects on the pavement test sections. Estimate/measure the defect parameters (Table A 1) and draw the defect on the LTPP/M survey form. Record the number of potholes and estimated joint/crack width (if appropriate) beside the sketch. Photographs of defects are also taken and a table recording pavement characteristics is collated.
Table A 1:
Defect type Area (m2) Cracking: Crocodile Block Crescent Longitudinal Transverse Diagonal Meandering Corner

Defect type and parameters to measure


Parameters to measure Length (m) Joint/crack width (mm) Number Sketch on the survey form

Austroads 2013 85

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Defect type Area (m2) Other defects:


Notes:

Parameters to measure Length (m) Joint/crack width (mm) Number

Sketch on the survey form

Potholes Ravelling Shoving Flushing Patching Joint seal defects Spalling

LTPPM survey form shall be used to record pavement surface defects. Summary of defects shall be reported in the LTPP/M Visual inspection summary form.

Table A 2:
Study type: LTPP Site ID State Survey date Defect type Cracking: Crocodile (area, m2) Block (area, m2) Crescent (area, m2) LTPPM

LTPP and LTPPM visual inspection (surface condition) summary


Road name Location Weather Defect condition

Longitudinal (length, m and crack width, mm) Transverse (length, m and crack width, mm) Diagonal (length, m and crack width, mm) Meandering (length, m and crack width, mm) Corner (area, m2) Potholes (number and area, m2) Ravelling (area, m2) Shoving (area, m2) Flushing (area, m2) Patching (area, m2) Joint seal defects (length, m and crack width, mm) Spalling (length, m and crack width, mm) Texture

Other defects:

Austroads 2013 86

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Figure A 1: LTPP and LTPPM visual inspection survey form

Austroads 2013 87

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

A.2
A.2.1

Rutting and Roughness Testing Procedures


General

In the Austroads LTPP study, pavement roughness (longitudinal profile) and rutting (transverse profile) are measured using the ARRB multi-laser profiler (MLP). The MLP is a fully integrated vehicle that uses thirteen laser units, two accelerometers and a high accuracy distance transducer to collect both longitudinal profile and transverse profile at highway speeds. The laser units which are mounted on a special assembly across the front of the vehicle are used to monitor several points across the width of the lane. Other lasers point out to the edges of the traffic lane, enabling data to be captured across a wide path. It also provides software to perform the calculation of roughness and rut depth from the measured longitudinal profile and transverse profile and report the test results. ARRB provides general guidelines on MLP testing for LTPP sites (Clayton 2000). ARRB MLP test methods for measuring lane roughness and rut depth of the individual test sites in this Austroads project are briefly described below. A.2.2 Roughness

Roughness is measured with the MLP using the Austroads Test Method AG:AM/T001: Pavement Roughness Measurement with an Inertial Laser Profilometer (Austroads 2011b). The measured roughness is expressed in terms of the International Roughness Index (IRI) and can be reported in different ways, as follows:
single track IRI: The IRI based on a quarter car model run over a single wheelpath of

longitudinal profile
lLane IRI: This is a composite IRI value representing the roughness of a road lane section. It is

determined by averaging two individual single track IRI values obtained separately in each wheel-path of a lane (at 0.75 metres either side of the lane mid-track). Readings of single track IRI and lane IRI are taken for each 10 m sub-section along the two wheelpaths of each pavement section. A.2.3 Rutting

Rutting is measured with the MLP using the Austroads Test Method AG:AM/T009: Pavement Rutting Measurement with a Multi-laser Profilometer (Austroads 2011c). It is calculated using the taut wire method (also known as the stringline method) an imaginary wire is stretched across the transverse profile enveloping the high points and fixed at either end. Rutting is defined as the maximum gap under the string line in each wheelpath. It can be reported in different ways, as follows:
Wheelpath rutting: the maximum rut depth across the transverse profile of each wheelpath Lane rutting: the maximum rut depth across the entire transverse profile of the lane.

Readings of wheelpath rutting and lane rutting are taken nominally at 10 m intervals along the two wheelpaths of each pavement section.

Austroads 2013 88

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

A.2.4

Site Establishment

For each test site, GPS should be established for the start and end locations of each 100 m test section and these locations should also be marked with road nails for future measurements. Furthermore, it is suggested that each 10 m interval be marked with sprayed paint or survey nails to assist with the acquisition of the monitoring data. A marker post at the site would also assist in site identification. A site diagram should be prepared to show the following locations:
marker post at the site for identification start of Section 1 (i.e. at 0 m chainage and 0 m offset) end of Section 1 or the start of Section 2 (i.e. at 100 m chainage and 0 m offset) end of Section 2 (i.e. at 200 m chainage and 0 m offset) MLP test locations for reporting the measured roughness and rutting data.

A.2.5

MLP Testing

MLP operators must properly record the GPS of the permanently marked road nails (start and end reference stations of each test section) for future measurements of distances of the MLP test locations (for reporting the measured roughness and rutting data for each section). All MLP testing is done in the driving lane of the test section by following the marked wheel-path tracks. All testing uses the distance reference at the start reference station of the test section so all MLP test point locations can be located for future reporting. When finished with a particular pass, the MLP returns to the beginning of the section to start another pass. Five passes through the test section are made to collect five sets of MLP data. The ARRB MLP data collection software will be used to select the three most consistent sets of data for further analysis of mean values of wheelpath rutting, lane rutting, single track IRI and lane IRI for each MLP test location. A.2.6 Reporting Data

The ARRB MLP data collection software will be used to record surface profiles from all 13 laser sensors. Binary MLP data files shall be provided for verification purposes. For each MLP survey, mean values (from three MLP runs) of wheelpath rutting, lane rutting, single track IRI and lane IRI for each test point (ID, GPS location) shall be reported in ASCII format or Excel spreadsheet for display and verification purposes.

A.3
A.3.1

Falling Weight Deflectometer Testing Procedures


General

In the Austroads LTPP study, the falling weight deflectometer (FWD) was used to measure the surface deflection of the pavement test sections under a series of applied loads. All testing nominally adhered to the SHRP-LTPP Protocol (SHRP 1989). This protocol is now administered by the Long-Term Pavement Performance (LTPP) Division in the U.S. Department of Transportation Federal Highway Administration (see LTPP Manual for Falling Weight Deflectometer Measurements Operational Field Guidelines Version 3.1 August 2000). Different FWD testing protocols may be assigned to different LTPP pavement test sections in the LTPP program, depending on experiment categories, pavement types and pavement conditions. This appendix provides guidelines and information specific to FWD testing at individual test sites.
Austroads 2013 89

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

A.3.2 1 2 3 4

Detailed Test Plan Lane for each FWD pass at two transverse locations: outer wheelpath (OWP) at 0.76 m 0.08 m and mid-lane (ML) at 1.8 m 0.15 m for nominal 3.7 m wide lane. Test interval (longitudinal location): begin at station 0 m chainage and continue to station 100 m at 10 m intervals. Deflection sensor spacing: nine deflection sensors placed at radial offsets from the centre of the load plate to define the shape of the deflection basin. Drop sequence (load levels/number of drops): three drop heights are to be used with the target loads of 30 kN, 40 kN and 50 kN. The drop sequence consists of three seating drops of 40 kN and four repeat measurements at each of the specified target loads. Test point ID: tests at ML use the lane name F1 and tests in the OWP using the lane name F3.

The following FWD test plan will be used for the test pavement of 100 m long x 3.8 m wide:

The test plan includes 10 FWD tests on each pass down the test section for both the ML and the OWP. Each section has 20 test points. The FWD testing will take about one hour. Note that two types of deflectometers, namely falling weight deflectometer (FWD) and heavy weight deflectometer (HWD), have been used in the LTPP program. The FWD devices were used until the 1997 data collection and beyond that the HWD device was used. Deflection results are plotted assuming both devices would provide the same values. Currently deflection measurements are conducted primarily using the HWD with the smoothing function on, so that the deflections are similar to those measured with the FWD. A.3.3 FWD Testing

FWD operators must properly record longitudinal distances with the distance measuring instrument relative to the 0+00 station reference for each section, and follow the guidelines for lateral offset for the OWP and ML passes, so all FWD testing can be repeated in the same general location. All FWD testing is done in the driving lane at two lateral offsets. The two lateral offsets are the ML and OWP. For a given lateral offset, a single pass through the test section is made to collect a particular type of deflection data. When finished with a particular pass, the FWD returns to the beginning of the section to start another pass. All testing uses station 0 m chainage of the test section as the distance reference so FWD test point locations can be located for future testing. A.3.4 Temperature Gradient Measurements

The thermal gradient (temperature versus depth) through the bound pavement surface layer is important for the analysis of deflection data. The automatic temperature sensors on the FWD record air temperature and pavement surface temperature. To provide a direct measure of the temperature gradient through the surface, FWD operators shall measure the temperature of oil placed in holes, drilled to different depths, during deflection testing. The basic procedure consists of drilling three holes into the bound surface layer, filling each hole with approximately 25 mm of oil, and using a hand-held temperature probe to measure the temperature of the oil at one hour intervals during the conduct of deflection testing. Temperature measurements are obtained at only one location for each test section. The FWD operator should assess variations in sun exposure and wind conditions to select the most representative location adjacent to the section limits for temperature measurements.

Austroads 2013 90

Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One

Temperature readings are obtained at 20 minute intervals, with the first readings prior to starting FWD testing on the section and the last readings after completion of FWD testing at the section. A.3.5 Crack Widths

No crack opening measurements are made; however, FWD operators must record pavement distress at test point locations as described in guidelines for GPS testing using the Comment key. A.3.6 Calibration

As a minimum, any FWD collecting data for the LTPP study is required to undergo a full calibration (including both reference and relative calibration) at least once per year. The calibration of the FWD must strictly follow the SHRP/LTPP FWD Calibration Protocol (March 1994). A.3.7 Reporting Data

The Dynatest FWD data collection software will be used to record deflections from all nine sensors. Deflection data files shall be provided for verification purposes. Detailed results of the FWD testing (including test point ID, location, FWD load, results of deflections from all nine sensors of the final drop of each target load, air temperature, pavement temperature, date and time) shall be reported in ASCII format or Excel spreadsheet for display and verification purposes. The last FWD reference calibration results should be given for verification purposes.

Austroads 2013 91

INFORMATION RETRIEVAL
Austroads, 2013, Design and Performance of Foamed Bitumen Stabilised Pavements: Progress Report One, Sydney, A4, pp. 98. AP-T247-13. Keywords: Pavement design, rehabilitation, foamed bitumen, stabilisation, recycling, mix design, construction, field performance, validation. Abstract: This report is the first progress report of a four year project which aims to improve the Austroads procedures for the mix and structural design of foamed bitumen stabilised materials. The report summarises the test methods drafted to date and details the results of monitoring foamed bitumen stabilised pavement trial sites on:
the Calder Freeway at Woodend, Victoria which was constructed specifically

for this project in 2013


Port Wakefield Road in Virginia, South Australia constructed in 2011 and

which experienced fatigue cracking within two years of opening to traffic


Kewdale Road in Canning, Western Australia constructed in 2011 and which

experiences shear stresses due to braking and acceleration of heavy vehicles


the Kwinana Freeway in Perth, Western Australia constructed in 2010, and the New England Highway south of Toowoomba, Queensland constructed in

2009. The report also identifies the mix design and structural design project tasks for 201314.

You might also like