DAILY SITE PROGRESS REVIEW MEETING HELD AT ONGC SITE OFFICE, ODALAREVU DATED 10th September 2013 AMONG

ONGC, DNV AND L&T REGARDING COMPLETION OF BALANCE WORKS FOR EARLY PRODUCTION (G1-11), ODALAREVU. Attendees: ONGC L&T DNV ETA Mr. R.Reddy Shashank Mr.T.K.Datta Mr. B.R.V.P.Prasad Mr. SK Haldar Mr. Pavan Mr.SHOAIB AHMED KHAN

Sno I.

Issue/Discipline Building Package Admin. Building-Ground floor (Civil)

Deliberation

Action by

Completion Schedule

Remarks

1 2 3 4 5 6 7 8 9 10 11

False ceiling False flooring Cleaning of ground floor Painting of Primer False flooring fixing Doors Shutters fixing Sanitary works RCC hume pipe Epoxy flooring in battery room Hand rails Final painting

Completed material received at site on 08/09/2013. Vacuum cleaning completed on 26.08.2013 primer & 1st coat paint completed in control room & ground floor of admin building.exrenal painting is in progress. To be done after the MCS Panel & Cable Termination In progress Sensor materials yet to receive To excavate & lay RCC hume pipes for Soak pit to Septic tank connection. Activity yet to start. Hold due to revised drawing required for UPS & battery location. Vendor visited (Sika India Product) site on 24-08-13. Materials will reach to site 10 days after placing order by L&T. Materials yet to receive at site Will be done at last ONGC asked L&T to procure 5000 L capacity Sintex tank compatible with structural arrangement. This is an additional item and to be procured on cost plus basis. L&T L&T L&T L&T L&T L&T L&T Technip/L&T L&T L&T 24-08-13 to 26-08-13 8/31/2013 20-08-13 to 31-08-13 26-08-13 to 31-08-13 26-08-13 to 31-08-13 5/9/2013 24-08-13 to 28-08-13 8/24/2013 8/25/2013 23-08-13 to 26-08-13

12

Overhead Tank

L&T/Technip

L&T to take action.

Admin. Building-First floor (Civil)


1 2 3 4 Gypsum partition Flase ceiling Wooden shutters Aluminum doors fixing Work in progress Tiles fixing is in progress,duct to be provided in revised conference room. In progress. Materials recived at site,manpower not available L&T L&T L&T L&T 31/08/2013 31/08/2013 24-08-13 to 31-08-13 01-09-13 to 05-09-13

ONGC

Page1of3 DNV

L&T

Sno
5 6 7 8

Issue/Discipline
Painting of Primer Plumbing & Sanitary External painting Vinyl flooring

Deliberation
Application of primer coat & 1st coat is completed Sensor materials yet to receive 1st coat painting is completed. To be done at the end

Action by
L&T L&T L&T L&T

Completion Schedule
9/10/2013 31/08/2013 5/9/2013 14/09/2013

Remarks

II.
1 2

Admin. Building (E&I)


Panel Erection Erection completed for all panels. L&T ONGC 31/08/2013 31/08/2013 After commissioning of HVAC

Deputation of Honey well ONGC to decide,as commissioning of 1 hvac unit is completed. representative for panel Termination Panel Cable Termination Smoke detectors at Ground floor Light fittings at first floor Methanol pumps Tray EJB-Umbilical area Mod bus Cable procurement Temporary Power supply Panel Cable termination is in progress. Fixing of smoke detectors at ground floor is completed. After the false ceiling work To be done Junction box identification & relocation to be done near Umbillical area L&T submitted proposal to ONGC regarding the procurement on 23-08-13 Power cable connection in DG building & Switch gear building for Temporary power arrangement for 750 KVA DG is in progress.

3 4 5 7 8 9 10

L&T L&T L&T L&T L&T L&T L&T

11/9/2013 26/08/2013 06-09-13 to 10-09-13 8/27/2013 In Progress In Progress

To be received from L&T's other site 31/08/2013

III. Mechanical Methanol Tank (TK-33)


1 2 3 4 Modifications of Methanol tank (TK33) Cutting & Grinding works completed welding & RT completed Leak detected during testing, Hydrotest preparation is in progress. Calibration, Strapping & dewatering-After hydrotesting of tank. L&T L&T L&T L&T 21-08-13 to 24-08-13 25-08-13 to 28-08-13 30/08/2013

Piping
1 2 TK-33 Connecting piping Methanol unloading pumps piping In progress, fitup completed,welding to be done.PVSV-8030 not available. Flame proof pump not available at site,connecting piping is in progress,detailed support drawing for piping is to be submitted by technip L&T L&T 27-08-13 to 06-09-13 pipe support padestial will be ready on 29/08/2013

ONGC

Page2of3 DNV

L&T

Sno
3 4

Issue/Discipline
PR-3 Piping Painting works In progress In progress

Deliberation

Action by
L&T L&T

Completion Schedule
7/9/2013 14/09/2013

Remarks

Civil
1 Methanol unloading pump foundation Completed on 23-08-13 Box Culvert near Methanol unloading Completed on 06/09/2013 pumps L&T 23/08/2013

L&T

15/09/2013

HVAC-Admin bldg Ground floor


1 2 3 4 5 Precision unit spares Precision unit power for Testing Return air grill Commissioning of precision unit number 2 ETA didnt confrim the date 1 number unit tested & commissioned on 31/08/2013 Material received on today 07/09/2013 emerson techician not reported to site since defective parts have not supplied by ETA. L&T ETA L&T 28/08/2013 11/9/2013 31/08/2013 28/08/2013 Testing of 1 unit is completed,trial run is going on, no document submitted by ETA/EMERSON Date to be confirm by ETA Temporary power arranged,testing is in progress.

Water line connection in HVAC room To be done

HVAC-Admin bldg First floor


1 2 3 Roof Top unit plenum erection Insulation of duct outside building Fixing of droppers Erection completed,connection yet to do yet to start.insulation manpower not available to site. Work in progress ETA ETA ETA 29/08/2013 4/9/2013 8/9/2013

ONGC

Page3of3 DNV

L&T