PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Excavate and Remove Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay Load Spoil to Barge, capacity 2,000m3 Load Spoil to Barge, capacity 1,500m3 Load Spoil to Barge, capacity 1,000m3 Spoil conveyor, 600mm belt, 150m/min m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours 14.50 15.20 12.30 11.20 25.40 25.60 22.50 18.90 20.00 20.40 18.50 16.90 30.30 31.30 27.80 24.40 8.00 6.50 5.50 260.00 25.60 25.60 23.20 21.30 35.70 37.00 33.30 30.30 0.0690 0.0658 0.0813 0.0893 0.0394 0.0391 0.0444 0.0529 0.0500 0.0490 0.0541 0.0592 0.0330 0.0319 0.0360 0.0410 0.1250 0.1538 0.1818 0.0038 0.0391 0.0391 0.0431 0.0469 0.0280 0.0270 0.0300 0.0330 -

Concrete Road surfacing Concrete Road surfacing, Kerbs or Side Haunches Concrete Road surfacing, 150mm thick Concrete Road surfacing, 200mm thick Concrete Road surfacing, 300mm thick m3 m2 m2 m2 hours hours hours hours 0.40 12.50 7.70 6.70 2.5000 0.0800 0.1299 0.1493 -

Basecourse Production Rates Urban environment: Spread & Compact Production = 30m3/hr Trimming Production = 250m2/hr Rural environment: Spread & Compact Production = 50m3/hr Trimming Production = 350m2/hr m3 m2 hours hours 50.00 350.00 0.0200 0.0029 m3 m2 hours hours 30.00 250.00 0.0333 0.0040 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Working Platforms Metal KwikStage, 5 Boards with 2m lifts Metal KwikStage, 5 Boards with 3m lifts Metal KwikStage, House Scaffold with 3 lifts Metal Tube and Fittings, 5-6 Boards wide Tube and Fitting Platforms, 50-250m3 Tube and Fitting Platforms, 250-1000m3 Tube and Fitting Platforms, over 1000m3 Tube and Fitting Platforms, striking m run m run m run m run m3 m3 m3 % x erect hours hours hours hours hours hours hours 11.10 9.10 2.80 3.20 10.60 18.50 24.50 11.90 10.00 3.20 3.70 12.50 22.50 30.00 200.00 12.50 10.50 3.80 4.60 18.50 24.50 33.50 0.0901 0.1099 0.3571 0.3125 0.0943 0.0541 0.0408 0.0840 0.1000 0.3125 0.2703 0.0800 0.0444 0.0333 200.00 0.0800 0.0952 0.2632 0.2174 0.0541 0.0408 0.0299 -

Waterproofing Asphalt coatings, horizontal surfaces Asphalt coatings, vertical surfaces Bituminous Brushed application, 2 coats Bituminous Brushed application, 3 coats Bituminous Sheets, horizontal surfaces Bituminous Sheets, vertical surfaces Polythene Sheets, horizontal surfaces Bentonite Sheets, horizontal surfaces Bentonite Sheets, vertical surfaces Epoxy Based application, 1 coat Epoxy Based application, 2 coat m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours 18.70 11.20 3.50 1.20 4.80 3.30 3.80 3.30 4.20 1.70 5.00 3.50 4.00 3.50 20.00 25.00 15.00 75.00 38.00 31.30 17.30 5.80 2.20 6.30 4.40 4.80 4.20 0.2857 0.8333 0.2083 0.3030 0.2632 0.3030 0.0535 0.0893 0.2381 0.5882 0.2000 0.2857 0.2500 0.2857 0.0500 0.0400 0.0667 0.0133 0.0263 0.1724 0.4545 0.1587 0.2273 0.2083 0.2381 0.0319 0.0578 -

Wallpapering Strip Existing Wallpaper (3 layers) & Prepare Walls Fix Wallpaper and lining paper Fix Vinyl and Washable paper m2 m2 m2 hours hours hours 5.00 5.00 4.20 0.2000 0.2000 0.2381 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Fix Ceiling Lining Paper

UNIT FOR QUANTITY


m2

UNIT FOR TIME


hours

PRODUCTION RATES (Qty per Time) Slow Average 4.00 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.2500 Fast -

Wall Finishes Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, Window Cills, setout and level Clay, quarry Tiles, Window Cills, fix, grout and clean Ceramic Tiles 150x150mm, Ledges/Upstands Ceramic Tiles 150x150mm, Areas under 1.5m2 per room Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 150x150mm, Areas over 2.5m2 per room Ceramic Tiles 150x150mm, Extra Over for Cutting Ceramic Tiles 108x108mm, Ledges/Upstands Ceramic Tiles 108x108mm, Areas under 1.5m2 per room Ceramic Tiles 108x108mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 108x108mm, Areas over 2.5m2 per room Ceramic Tiles 108x108mm, Extra Over for Cutting Ceramic Tiles, Grouting Works no m m2 no m2 m2 m2 no no m2 m2 m2 no m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours 1.00 1.60 1.70 2.20 20.40 0.90 1.40 1.50 1.10 55.50 1.50 27.10 1.00 1.60 1.70 41.60 62.50 1.30 1.80 1.90 125.00 2.50 1.50 2.10 2.20 2.60 32.00 1.20 1.90 2.10 1.50 0.0490 1.1111 0.7143 0.6667 1.0000 0.6250 0.5882 0.4545 0.9091 0.0180 0.6667 0.0369 1.0000 0.6250 0.5882 0.0240 0.0160 0.7692 0.5556 0.5263 0.0080 0.4000 0.6667 0.0313 0.8333 0.5263 0.4762 0.6667 0.4762 0.4545 0.3846

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Underpinning Concrete Pinning, 4th or 5th pin cycles Brickwork Pinning, 1.0 brick thick Brickwork Pinning, 1.5 brick thick Brickwork Pinning, 2.0 brick thick Wedge and Pin Method, 102mm wall Wedge and Pin Method, 215mm wall Wedge and Pin Method, 317mm wall m m2 m2 m2 m m m day hours hours hours hours hours hours 0.10 1.20 0.40 0.30 0.20 0.80 0.70 0.50 2.20 0.70 10.0000 0.8333 2.5000 3.3333 5.0000 1.2500 1.4286 2.0000 0.4545 1.4286 -

Trench Excavation Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Hard Ground Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 5.60 4.80 4.80 9.70 20.50 18.20 18.20 17.00 26.00 26.30 26.30 22.70 3.30 3.00 2.70 6.60 6.20 5.80 7.10 6.10 6.10 5.40 25.00 22.20 22.20 20.00 28.60 28.60 28.60 25.00 4.50 4.20 4.00 7.10 6.70 6.20 8.20 7.30 7.10 6.40 29.20 26.00 26.00 23.40 33.10 33.20 33.20 28.80 6.80 6.50 6.00 8.80 9.20 10.50 0.1786 0.2083 0.2083 0.1031 0.0488 0.0549 0.0549 0.0588 0.0385 0.0380 0.0380 0.0441 0.3030 0.3333 0.3704 0.1515 0.1613 0.1724 0.1408 0.1639 0.1639 0.1852 0.0400 0.0450 0.0450 0.0500 0.0350 0.0350 0.0350 0.0400 0.2222 0.2381 0.2500 0.1408 0.1493 0.1613 0.1220 0.1370 0.1408 0.1563 0.0342 0.0385 0.0385 0.0427 0.0302 0.0301 0.0301 0.0347 0.1471 0.1538 0.1667 0.1136 0.1087 0.0952

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Trackwork FST Floating Track Slab, side restraints FST Floating Track Slab, resin pads FST Floating Track Slab, slab units PCBT - Pre-cast Concrete Block Track, in Bored Tunnels PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels PCBT - Pre-cast Concrete Block Track, in Station Tunnels IST - Isolated Slab Track, in Bored Tunnels IST - Isolated Slab Track, in Cut and Cover Tunnels IST - Isolated Slab Track, in Station FST - Floating Slab Track, in Station Ballasted Track, in Mainline Ballasted Track, in Depot Non-Ballasted Track, in Depot Embedded / Paved Track, in Depot Heavy Maintenance / Train Wash Track, in Depot Maintenance Pit, in Depot Siding Trackwork, in Depot m m m m m m m m m m m m m m m m m days days days days days days days days days days days days days days days days days 8.50 3.60 57.00 9.60 10.20 10.60 17.10 41.00 35.00 35.00 20.00 34.00 29.00 4.60 71.00 28.00 12.80 71.00 29.00 52.00 38.00 17.40 5.70 115.00 0.1042 0.0980 0.0943 0.0585 0.2778 0.0175 0.1176 0.0244 0.0286 0.0286 0.0500 0.0294 0.0345 0.2174 0.0141 0.0357 0.0781 0.0141 0.0345 0.0192 0.0263 0.1754 0.0087 0.0575 -

Tower Cranes Erect and Setup 50m gib Dismantle 50m gib Lifting, Reinforcement Bins and Cages, 1st 15m lift Lifting, Reinforcement Bins and Cages, above 1st 15m lift Lifting, Crane Tracking Time lift 15m m days days mins mins seconds 11.00 10.00 3.20 0.50 3.30 7.50

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Timber Frames Roof Trusses Wall Plates Roof Rafters Ceiling Joists Roof Carcass, Common Rafters, under 3m Roof Carcass, Common Rafters, 3-6mm Roof Carcass, Common Rafters, over 6m Roof Carcass, Jack Rafters, under 3m Roof Carcass, Jack Rafters, 3-6mm Roof Carcass, Purlins, under 3m Roof Carcass, Purlins, 3-6mm Roof Carcass, Purlins, over 6m Roof Carcass, Binders, under 3m Roof Carcass, Binders, 3-6mm Roof Carcass, Binders, over 6m Roof Carcass, Hangers, under 3m Roof Carcass, Collars under 3m Roof Carcass, Collars 3-m Roof Carcass, Ridge Boards under 3m Roof Carcass, Cut Rafter Feet to line Roof Soffits, Softwood, nailed Roof Soffits, Softwood, screwed Roof Soffits Asbestos, under 300mm nailed Roof Soffits Asbestos, under 300mm screwed Roof Soffits, Asbestos, over 300mm nailed Roof Soffits, Asbestos, over 300mm screwed Roof Facia Panels, Softwood Roof Facia Panels, Asbestos Roof Facia Panel Studding, nailed Roof Facia Panel Studding, screwed no m m m no no no no no no no no no no no no no no no no m m m m m m m m m m hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 5.10 1.30 7.30 4.60 18.20 13.30 14.10 18.80 10.40 5.10 4.30 3.50 5.70 2.10 1.30 8.20 7.60 6.50 12.00 142.00 1.30 2.70 1.20 32.10 20.00 16.60 15.60 20.10 16.10 5.40 4.80 4.30 6.60 2.30 1.50 9.00 8.00 7.40 13.10 166.00 9.20 3.90 9.10 3.80 3.50 1.30 7.20 2.50 8.10 5.20 9.30 3.90 9.00 5.80 21.70 18.20 16.10 21.70 16.60 5.80 5.10 4.60 7.60 2.50 1.60 9.60 9.10 8.30 15.30 175.00 0.0549 0.0752 0.0709 0.0532 0.0962 0.1961 0.2326 0.2857 0.1754 0.4762 0.7692 0.1220 0.1316 0.1538 0.0833 0.0070 0.1961 0.7692 0.1370 0.2174 0.7692 0.3704 0.8333 0.0312 0.0500 0.0602 0.0641 0.0498 0.0621 0.1852 0.2083 0.2326 0.1515 0.4348 0.6667 0.1111 0.1250 0.1351 0.0763 0.0060 0.1087 0.2564 0.1099 0.2632 0.2857 0.7692 0.1389 0.4000 0.1235 0.1923 0.0461 0.0549 0.0621 0.0461 0.0602 0.1724 0.1961 0.2174 0.1316 0.4000 0.6250 0.1042 0.1099 0.1205 0.0654 0.0057 0.1075 0.2564 0.1111 0.1724

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Roof Facia Panel Studding, bolted to beams Roof Works, Fix Herringbone Strutting Roof Works, Fix Firing Strips Roof Works, Fix Drip/Tilt Filleting

UNIT FOR QUANTITY


m m m m

UNIT FOR TIME


hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 5.40 Average 5.90 5.10 25.00 20.50 Fast 6.60

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1852 Average 0.1695 0.1961 0.0400 0.0488 Fast 0.1515 -

Structural Steelwork Simple Universal Beam Steel Bridge, erect support steel H frames Simple Universal Beam Steel Bridge, erect 15m truss no m days days 0.8333 3.30 1.2000 0.3030 -

Stonework Fix 0.5m2 Stones to Metal Support Frame Fix 0.5-0.75m2 Stones to Metal Support Frame Fix 0.75-1.0m2 Stones to Metal Support Frame Fix Complex Stonework to Metal Support Frame Fix Curved Stone Cladding Fix Stone Edge Beams/Window Reveals Fix Stone Soffits Stone Floors Granite Wall Panels, First Fix Granite Wall Panels, Second Fix m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 days days days days days days days days hours hours 6.90 6.90 5.60 7.20 6.90 7.00 9.00 8.70 1.80 8.00 2.30 4.00 10.40 1.30 1.10 12.20 9.20 3.20 7.80 10.10 9.70 0.1786 0.1389 0.1449 0.1449 0.1449 0.1429 0.1111 0.1149 0.5556 0.1250 0.4348 0.2500 0.0962 0.7692 0.9091 0.1282 0.0990 0.1031 0.1087 0.3125 0.0820 -

Steel Strutting Horizontal heavy duty strutting no days 0.5000 2.00 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Diagonal heavy duty strutting

UNIT FOR QUANTITY


no

UNIT FOR TIME


days

PRODUCTION RATES (Qty per Time) Slow Average 0.1667 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 6.00 Fast -

Steel Frames Steel Frame and Roof Members Wall Frame, Bow String Truss and Frame Roof Frame, Curved Truss and Frame Wall Frame, Glazed Frame and Atrium Tons Tons Tons Tons days days days days 3.40 1.60 5.20 0.30 4.60 0.2941 0.6250 0.1923 3.3333 0.2174 -

Spread and Level Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 13.90 7.60 14.20 7.60 12.70 6.90 11.60 6.30 23.80 16.70 25.00 17.20 21.70 15.10 19.60 13.70 18.60 20.40 9.50 20.40 10.20 18.40 8.90 16.90 8.20 28.50 18.50 32.00 19.30 27.50 16.90 24.50 15.90 28.50 25.00 12.60 25.60 12.80 23.20 11.60 21.30 10.40 35.70 20.40 37.00 21.20 33.30 18.80 30.30 17.50 38.50 0.0719 0.1316 0.0704 0.1316 0.0787 0.1449 0.0862 0.1587 0.0420 0.0599 0.0400 0.0581 0.0461 0.0662 0.0510 0.0730 0.0538 0.0490 0.1053 0.0490 0.0980 0.0543 0.1124 0.0592 0.1220 0.0351 0.0541 0.0313 0.0518 0.0364 0.0592 0.0408 0.0629 0.0351 0.0400 0.0794 0.0391 0.0781 0.0431 0.0862 0.0469 0.0962 0.0280 0.0490 0.0270 0.0472 0.0300 0.0532 0.0330 0.0571 0.0260

Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile m3 Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile m3 m3 m3 m3 m3 m3 m3

Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile m3 Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil m3

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay

UNIT FOR QUANTITY


m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 24.40 18.90 24.20 15.80 19.20 17.20 22.20 43.50 55.50 43.80 55.50 37.10 47.60 43.80 55.60 Average 37.20 28.60 37.20 23.50 29.60 26.40 33.80 48.00 61.10 48.30 61.10 40.30 51.60 45.70 59.10 Fast 50.00 38.40 50.00 31.20 40.00 35.70 45.40 52.60 66.70 52.90 66.70 43.50 55.60 47.60 62.50

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.0410 0.0529 0.0413 0.0633 0.0521 0.0581 0.0450 0.0230 0.0180 0.0228 0.0180 0.0270 0.0210 0.0228 0.0180 Average 0.0269 0.0350 0.0269 0.0426 0.0338 0.0379 0.0296 0.0208 0.0164 0.0207 0.0164 0.0248 0.0194 0.0219 0.0169 Fast 0.0200 0.0260 0.0200 0.0321 0.0250 0.0280 0.0220 0.0190 0.0150 0.0189 0.0150 0.0230 0.0180 0.0210 0.0160

Soil Mix Walls Three Auger Drill, cement and cure m days 3.80 4.50 6.40 0.2632 0.2222 0.1563

Small or Deep Excavation Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Gravel Beds m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours 6.70 3.20 3.30 3.30 8.20 7.10 8.40 4.50 4.10 4.10 10.00 8.70 9.90 5.00 5.20 5.20 11.70 10.20 0.1493 0.3125 0.3030 0.3030 0.1220 0.1408 0.1190 0.2222 0.2439 0.2439 0.1000 0.1149 0.1010 0.2000 0.1923 0.1923 0.0855 0.0980

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Hard Ground

UNIT FOR QUANTITY


m3 m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 6.50 6.30 12.20 10.20 9.70 6.10 Average 8.30 7.70 13.30 11.10 10.50 6.70 Fast 9.40 9.10 15.40 12.90 12.10 7.70

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1538 0.1587 0.0820 0.0980 0.1031 0.1639 Average 0.1205 0.1299 0.0752 0.0901 0.0952 0.1493 Fast 0.1064 0.1099 0.0649 0.0775 0.0826 0.1299

Slurry Mix Walls Crane grab, cement/bentonite and sheet piles m days 1.80 2.50 3.40 0.5556 0.4000 0.2941

Slates and Tiling Slate Roofs, Welsh Slate 3-5mm Slate Roofs, Cumbrian Slate 8-11mm Slate Roofs, Asbestos Slates Tiled Roofs, Concrete Tiles Tiled Roofs, Clay Pan Tiles m2 m2 m2 m2 m2 days days days days days 18.00 8.50 36.00 52.00 26.00 0.0556 0.1176 0.0278 0.0192 0.0385 -

Site Investigation Pre Drilling, Rercussive or Rotary, soft deposits Pre Drilling, Wash Boring, grade V/IV rock Pre Drilling, Triple Tube Sampling, grade V/IV rock Pre Drilling, Rotary, grade III/II rock Pre Drilling, Triple Tube Sampling, grade III/II rock m m m m m hours hours hours hours hours 8.00 2.50 0.40 0.20 0.10 10.00 3.20 0.80 0.50 0.40 14.00 3.90 0.90 0.70 0.70 0.1250 0.4000 2.5000 5.0000 10.0000 0.1000 0.3125 1.2500 2.0000 2.5000 0.0714 0.2564 1.1111 1.4286 1.4286

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Site Clearance Shrubs and Bushes, dig up and removal Turf, lifting and removal Trees, small sizes and shrubs Trees and Shrubs, 500mm - 900mm girth Trees and Shrubs, 900mm - 1200mm girth Trees and Shrubs, 1200mm - 1500mm girth Hedges and Roots, 0.5-1.0m high Hedges and Roots, 1.0-1.5m high Hedges and Roots, 1.5-2.0m high m2 m2 m2 no no no m m m hours hours hours hours hours hours hours hours hours 25.00 2.90 14.00 0.0556 0.0455 0.0385 0.90 0.80 0.60 38.00 0.0400 0.3448 0.0714 18.00 22.00 26.00 1.1111 1.2500 1.6667 0.0263 -

Sheeted Roofs PVC Sheeted Roofs, large areas PVC Sheeted Roofs, small areas Plastic Profiled Sheet Systems m2 m2 m2 days days days 50.00 40.00 54.00 0.0200 0.0250 0.0185 -

Sheet Piling Vibro/Drop Hammer, 10m deep Sand Vibro/Drop Hammer, 35m deep Sand m m days days 3.50 55.00 32.00 60.00 10.50 0.2857 0.0182 0.0313 0.0167 0.0952

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Secant Piling Construct 30m dia cofferdam, 255 piles/concrete base weeks 12.00 -

Screeding Sand/Cement Floor Screed, 15-20mm thick Sand/Cement Floor Screed, 20-30mm thick Sand/Cement Floor Screed, 30-40mm thick Sand/Cement Floor Screed, 40-50mm thick Sand/Cement Floor Screed, 50-65mm thick Sand/Cement Floor Screed, 65-100mm thick Fix/Setout Screed Battens m2 m2 m2 m2 m2 m2 m hours hours hours hours hours hours hours 3.20 2.00 4.80 4.60 4.20 3.80 3.30 3.00 10.00 5.70 5.50 5.30 5.20 3.90 3.60 0.3125 0.5000 0.2083 0.2174 0.2381 0.2632 0.3030 0.3333 0.1000 0.1754 0.1818 0.1887 0.1923 0.2564 0.2778 -

Rule of Thumb Site Investigation Pre Drilling Ground Excavation, Hydraulic Backhoe Bored Piling, 25-70m deep Formwork Fixing Reinforcement Fixing Concrete Placement Scaffold Erection, Steel Falsework Blockwork Laying Plastering and Rendering Blockwork Laying Stonework Cladding Window Glazing no. m3 no. m2 Tonnes m3 m3 m2 m2 m2 m2 m2 days days days days days days days days days days days hours 7.00 0.1000 0.2000 0.2500 50.00 0.1250 12.00 0.70 16.00 140.00 7.00 12.00 12.00 5.10 1.50 17.50 0.1667 0.3333 5.00 10.00 0.1429 4.00 0.0200 8.00 0.0833 1.4286 0.0625 0.0071 0.1429 0.0833 0.0833 0.1961 0.6667 3.00 6.00 0.0571 -

PRODUCTION RATES

ITEM NO.
Granolithic Flooring Floor Screeding Floor Screeding Ceramic Wall Tiling

DESCRIPTION

UNIT FOR QUANTITY


m2 m2 m2 m2

UNIT FOR TIME


hours hours days hours

PRODUCTION RATES (Qty per Time) Slow Average 4.50 4.50 60.00 1.50 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.2222 0.2222 0.0167 0.6667 Fast -

Rock Tunnels Excavation, non explosive chemical method, cycle time Excavation, non explosive chemical method, Class I Granite Excavation, non explosive chemical method, Class II Granite Excavation, non explosive chemical method, Class III Granite m3 m3 m3 mins cycle cycle cycle 0.30 2.00 1.20 0.90 2.60 1.40 1.20 2.90 1.80 8.00 3.3333 0.5000 0.8333 6.00 1.1111 0.3846 0.7143 5.50 0.8333 0.3448 0.5556

Restoration Works Faade Cleaning, Water Jetting Faade Cleaning, Acid Etching Faade Cleaning, Grit Blasting Cladding Restoration, Brickwork Cladding Restoration, Stonework courses m2 m2 m2 m2 m days days days days days 25.00 9.00 12.00 6.50 20.00 0.0400 0.1111 0.0833 0.1538 0.0500 -

Rendering Large Wall Areas, applied in 2 coats Small Wall Areas, applied in 2 coats Narrow Widths, applied in 2 coats Columns and Beams, applied in 2 coats Staircase and Soffits, applied in 2 coats m2 m2 m2 m2 m2 hours hours hours hours hours 2.20 1.50 1.20 1.50 1.40 2.70 1.70 1.40 1.70 0.4545 0.6667 0.8333 0.6667 0.7143 0.3704 0.5882 0.7143 0.5882 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Removable Anchors Drill 30m shaft Install strands/setup anchor Grout in strands hours hours hours 7.00 6.00 2.00 -

Reinforcement Ratios Pile Cap, Concrete m3 x Ratio = Rebar Tonnes Base Slab, Concrete m3 x Ratio = Rebar Tonnes Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes Platform Slab, Concrete m3 x Ratio = Rebar Tonnes Columns, Concrete m3 x Ratio = Rebar Tonnes Walls, Concrete m3 x Ratio = Rebar Tonnes % ratio % ratio % ratio % ratio % ratio % ratio 15.80 14.70 14.80 13.20 20.60 15.60 18.70 15.00 28.70 14.10 25.60 -

Reinforcement Slabs/Foundations, steelfixing, 6mm Slabs/Foundations, steelfixing, 8mm Slabs/Foundations, steelfixing, 10mm Slabs/Foundations, steelfixing, 12mm Slabs/Foundations, steelfixing, 16mm Slabs/Foundations, steelfixing, 20mm Slabs/Foundations, steelfixing, 25mm Slabs/Foundations, steelfixing, 32mm Slabs/Foundations, steelfixing, 40mm Slabs/Foundations, steelfixing, 50mm Beams/Columns, steelfixing, 6mm Beams/Columns, steelfixing, 8mm tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne hours hours hours hours hours hours hours hours hours hours hours hours 0.0248 0.0355 0.0444 0.0592 0.0833 0.1087 0.1449 0.1754 0.1887 0.1923 0.0181 0.0258 0.0260 0.0372 0.0485 0.0613 0.0870 0.1163 0.1493 0.1818 0.1961 0.2041 0.0189 0.0270 0.0274 0.0388 0.0498 0.0649 0.0917 0.1220 0.1538 0.1923 0.2041 0.2174 0.0198 0.0285 40.30 28.20 22.50 16.90 12.00 9.20 6.90 5.70 5.30 5.20 55.40 38.80 38.40 26.90 20.60 16.30 11.50 8.60 6.70 5.50 5.10 4.90 52.80 37.00 36.50 25.80 20.10 15.40 10.90 8.20 6.50 5.20 4.90 4.60 50.60 35.10

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Beams/Columns, steelfixing, 10mm Beams/Columns, steelfixing, 12mm Beams/Columns, steelfixing, 16mm Beams/Columns, steelfixing, 20mm Beams/Columns, steelfixing, 25mm Beams/Columns, steelfixing, 32mm Beams/Columns, steelfixing, 40mm Beams/Columns, steelfixing, 50mm Walls, steelfixing, 6mm Walls, steelfixing, 8mm Walls, steelfixing, 10mm Walls, steelfixing, 12mm Walls, steelfixing, 16mm Walls, steelfixing, 20mm Walls, steelfixing, 25mm Walls, steelfixing, 32mm Walls, steelfixing, 40mm Walls, steelfixing, 50mm Staircases, steelfixing, 6mm Staircases, steelfixing, 8mm Staircases, steelfixing, 10mm Staircases, steelfixing, 12mm Staircases, steelfixing, 16mm Staircases, steelfixing, 20mm Staircases, steelfixing, 25mm

UNIT FOR QUANTITY


tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.0339 0.0427 0.0602 0.0806 0.1010 0.1471 0.1639 0.1639 0.0243 0.0342 0.0441 0.0568 0.0806 0.1064 0.1351 0.1429 0.1563 0.1887 0.0204 0.0291 0.0376 0.0478 0.0685 0.0885 0.1163 Average #VALUE! 0.0446 0.0633 0.0840 0.1087 0.1515 0.1695 0.1695 0.0245 0.0350 0.0455 0.0578 0.0820 0.1087 0.1389 0.1471 0.1639 0.1961 0.0208 0.0298 0.0388 0.0490 0.0694 0.0926 0.1190 Fast 0.0372 0.0457 0.0662 0.0885 0.1149 0.1613 0.1786 0.1786 0.0256 0.0365 0.0472 0.0592 0.0847 0.1149 0.1429 0.1563 0.1695 0.2083 0.0220 0.0313 0.0412 0.0513 0.0725 0.0952 0.1220

PRODUCTION RATES (Time per Quantity) REMARKS Slow 29.50 23.40 16.60 12.40 9.90 6.80 6.10 6.10 41.20 29.20 22.70 17.60 12.40 9.40 7.40 7.00 6.40 5.30 48.90 34.40 26.60 20.90 14.60 11.30 8.60 Average 28.4 22.40 15.80 11.90 9.20 6.60 5.90 5.90 40.80 28.60 22.00 17.30 12.20 9.20 7.20 6.80 6.10 5.10 48.00 33.60 25.80 20.40 14.40 10.80 8.40 Fast 26.90 21.90 15.10 11.30 8.70 6.20 5.60 5.60 39.10 27.40 21.20 16.90 11.80 8.70 7.00 6.40 5.90 4.80 45.50 31.90 24.30 19.50 13.80 10.50 8.20

Rainwater Works UPVC Downpipes, 75mm UPVC Guttering, 75mm UPVC RWP Fittings, 75mm m m no hours hours hours 3.30 3.10 3.10 0.3030 0.3226 0.3226 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Cast Iron Downpipes, 75mm Cast Iron Guttering, 75mm Cast Iron RWP Fittings, 75mm Aluminium Downpipes, 72mm Aluminium Guttering, 72mm Aluminium RWP Fittings, 72mm

UNIT FOR QUANTITY


m m no m m no

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 2.10 2.50 2.20 2.50 2.90 1.90 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.4762 0.4000 0.4545 0.4000 0.3448 0.5263 Fast -

Power Supply AC Install 2 no Service transformers, 6 men AC Install 2 no Switchgear, 7 men AC Install Associated Trays and ladders, 3 men AC Cable Terminations in Tx and SWG Rooms, 3 men DC Install Insulated Flooring in DC Room, 1 men DC Install 1 set Rectifier Transformer and Rectifier, 7 men DC Install Switchgear, 7 men DC Primary Cable Terminations and Busduct, 18 men DC Secondary Cable Terminations and Connections, 9 men Trackside Cabling 33kV/Pilot Cables, 10 men Trackside Cabling Terminations, 6 men m run days days days days days days days days days days days 2,100.00 12.0 12.0 0.0005 11.00 12.00 12.00 12.00 5.00 6.00 5.00 1.00 10.00 9.00 6.00 1.0 -

Post Tensioning Lag for Initial Stress Tensioning after 1st bay cast Lag for Final Stress Tensioning after Initial Stress hrs hrs 48.00 120.00 -

Plastering Browning (undercoat), Internal Walls under 2.5m high m2 hours 2.20 2.80 3.10 0.4545 0.3571 0.3226

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Browning (undercoat), Internal Walls over 2.5m high Browning (undercoat), Reveals and Columns less than 100mm wide Browning (undercoat), Reveals and Columns 100-200mm wide Browning (undercoat), Reveals and Columns 200-300mm wide Covings Skimming (topcoat), Internal Walls under 2.5m high Skimming (topcoat), Internal Walls over 2.5m high Skimming (topcoat), Reveals and Columns less than 100mm wide Skimming (topcoat), Reveals and Columns 100-200mm wide Skimming (topcoat), Reveals and Columns 200-300mm wide Plaster Board to Ceilings Plastering Ceilings, 1 Bonding, 1 Skimming Plastering Ceilings, Topcoat Skimming

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 2.10 9.90 5.20 3.30 6.10 5.50 12.60 7.70 4.50 3.20 1.10 2.70 Average 2.60 10.00 5.40 3.60 5.00 6.70 6.10 13.80 8.30 5.00 4.50 1.70 3.20 7.30 6.70 15.40 9.80 5.50 5.50 2.40 5.40 Fast 2.80 10.10 6.40 3.90

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.4762 0.1010 0.1923 0.3030 0.1639 0.1818 0.0794 0.1299 0.2222 0.3125 0.9091 0.3704 Average 0.3846 0.1000 0.1852 0.2778 0.2000 0.1493 0.1639 0.0725 0.1205 0.2000 0.2222 0.5882 0.3125 Fast 0.3571 0.0990 0.1563 0.2564 0.1370 0.1493 0.0649 0.1020 0.1818 0.1818 0.4167 0.1852

Plasterboard Boarding to Plaster dabs Boarding to Stud-work/Metal Lathes Boarding 12mm nailed to studding Boarding 19mm nailed to studding Tape, Jointing and Sanding m2 m2 m2 m2 m hours hours hours hours hours 3.60 4.00 4.00 5.00 12.50 16.50 10.00 5.50 6.70 0.2778 0.2500 0.2500 0.2000 0.0800 0.0606 0.10 0.1818 0.1493 -

Partitioning Timber Studding Metalwork System (MF) Studding Tape, Joint Sand and Top Coat Plasterboard Skimming to Plasterboards 5mm Hardboard Paneling, excluding studding time 100mm Pine Paneling, excluding studding time m m2 m2 m2 m2 m2 hours hours hours hours hours hours 0.80 5.90 1.60 1.10 5.50 6.20 2.00 1.50 6.10 3.20 1.10 6.80 2.50 2.10 6.70 3.60 1.40 0.1695 0.6250 0.9091 0.1818 1.2500 0.1613 0.5000 0.6667 0.1639 0.3125 0.9091 0.1471 0.4000 0.4762 0.1493 0.2778 0.7143

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Quality Hardwood Paneling, excluding studding time Fix 50mm Rocksil Insulation to cavities Fix Timber Studding and Paramount Partitions Fix Timber Studding and Demountable Partitions Fix Timber Studding and Hills Duraboard Partitions Fix Timber Studding and Gyproc Laminated Partitions Stud Partitions, Butt Jointed, nailed Stud Partitions, Butt Jointed, screwed Stud Partitions, T&G Jointed, nailed Stud Partitions, T&G Jointed, screwed Stud Partitions, Fix Sole Plates Stud Partitions, Fix Noggins Stud Partitions, Drill 25-40mm Holes Fix Toilet Partition System, Separation panels Fix Toilet Partition System, Wall Front Panels Fix Toilet Partition System, Separation Front Panels Fix Toilet Partition System, End Front Panels Fix Toilet Partition System, Hang Door to Panel Fix Toilet Partition System, Hand Door plugged to wall Fix Toilet Partition System, Fix Head Rails

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m m m m m m no no no no no no no no

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.30 2.60 0.80 3.00 2.20 5.90 3.50 2.90 2.10 Average 0.50 17.80 3.00 1.10 3.50 2.60 7.30 4.60 3.60 2.80 11.10 16.60 28.50 1.25 1.43 1.67 1.67 2.50 1.67 10.00 Fast 0.60 20.20 3.40 1.60 3.90 2.90 9.10 5.80 4.80 3.70

PRODUCTION RATES (Time per Quantity) REMARKS Slow 3.3333 0.3846 1.2500 0.3333 0.4545 0.1695 0.2857 0.3448 0.4762 Average 2.0000 0.0562 0.3333 0.9091 0.2857 0.3846 0.1370 0.2174 0.2778 0.3571 0.0901 0.0602 0.0351 0.80 0.70 0.60 0.60 0.40 0.60 0.10 Fast 1.6667 0.0495 0.2941 0.6250 0.2564 0.3448 0.1099 0.1724 0.2083 0.2703 -

Painting Prepare Walls Prepare Doors Prepare Door Frames Burn Off / Heat Strip Paintwork Internal Timber, 1 coat primer before fixing, generally Internal Timber, 1 coat primer before fixing, timber lengths Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss Internal Timber, touchup primer, 1 undercoat, 1 coat gloss m2 m2 m m2 m2 m m2 m2 hours hours hours hours hours hours hours hours 14.20 12.50 25.00 1.10 6.70 20.00 1.70 3.10 2.10 3.80 0.0704 0.0800 0.0400 0.9091 0.1493 0.0500 0.5882 0.3226 0.4762 0.2632

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Internal Timber, polyurethane varnish, 2 coats Internal Timber, polyurethane varnish, 3 coats Internal Timber, linseed oil to hardwood, 2 coats External Timber, windows and frames External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss, External Timber, touchup primer, 2 undercoats, 1 coat gloss, External Timber, 2 coats wood preservative External Timber, 3 coats polyurethane varnish Internal Walls, 2 coats emulsion to plaster Internal Walls, 2 coats emulsion to brick/blockwork Internal Walls, 1 mist, 2 coats emulsion to plaster Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster Internal Walls, undercoat to door frame Internal Walls, gloss to door frame Internal Walls, undercoat to door Internal Walls, gloss to door External Walls, 2 coats sandtex to render/concrete External Walls, 2 coats sandtex to brick/blockwork External Walls, 1 sealer, 2 emulsion to render/concrete External Walls, 1 sealer, 2 emulsion to brick/blockwork Floors, epoxy paint Ceilings, emulsion paint, 2 coats Ceilings, emulsion paint, 3 coats Ceilings, textured paint Ceilings, artex finish Internal Steelwork, 1 primer, 1 undercoat, 1 gloss External Steelwork, 1 primer, 2 undercoats, 1 gloss Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 1.30 0.90 Average 3.30 2.20 3.60 2.40 1.50 2.00 4.00 2.00 8.00 6.00 6.00 4.50 2.30 20.00 16.50 7.10 6.20 2.50 2.00 2.00 1.70 2.90 6.10 5.00 4.20 4.10 2.40 1.70 2.50 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.7692 1.1111 Average 0.3030 0.4545 0.2778 0.4167 0.6667 0.5000 0.2500 0.5000 0.1250 0.1667 0.1667 0.2222 0.4348 0.0500 0.0606 0.1408 0.1613 0.4000 0.5000 0.5000 0.5882 0.3448 0.1639 0.2000 0.2381 0.2439 0.4167 0.5882 0.4000 Fast -

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

NATM Tunnels Standard Advance Method, used on tunnels with max diameter Half Face Advance Method, used on tunnels with max diameter Double side Drift Advance Method, used on tunnels with diameter over Double side Drift Advance Method, used on tunnels with diameter over Excavation, London Clay, internal diameter under 7.0m Excavation, London Clay, internal diameter 7.0-10.0m Excavation, London Clay, internal diameter over 10.0m Excavation, Woolwich/Reading Beds, internal diameter 2.0-7.0m Excavation, Woolwich/Reading Beds, internal diameter 7.0-10.0m Excavation, Woolwich/Reading Beds, internal diameter over 10.0m Excavation, London Clay, Inclined Tunnels, diameter 2.0-7.0m Excavation, London Clay, Inclined Tunnels, diameter 7.0-10.0m Excavation, London Clay, Vertical Shafts, diameter 2.0-9.0m Excavation, London Clay, Vertical Shafts, diameter 9.0-15.0m Excavation, London Clay, Circulation Halls Excavation, London Clay, Junction Excavation Mucking Capacity, 1 access with 2 crews Mucking Capacity, 1 access with 4 crews Mucking Capacity, 2 access with 4 crews Sprayed Secondary Lining, Tunnels, diameter under 6.5m Sprayed Secondary Lining, Tunnels, diameter over 6.5m Sprayed Secondary Lining, Inclined Tunnels, diameter under 6.5m Sprayed Secondary Lining, Inclined Tunnels, diameter over 6.5m Sprayed Secondary Lining, Vertical Shafts, diameter under 6.5m Sprayed Secondary Lining, Vertical Shafts, diameter over 6.5m Sprayed Secondary Lining, Circulation Halls, diameter under 11.0m Sprayed Secondary Lining, Intermediate Landing Tunnels with columns m m m m m m m m m m m m m m m of circumf m m3 m3 m3 m m m m m m m m days days days days days days days days days days days days days days days days days days days days days days days days days days 1.70 1.60 190.00 255.00 382.00 2.10 1.50 1.50 1.00 1.80 2.20 1.50 0.50 1.00 0.50 0.80 2.50 1.50 1.00 1.50 7.00 10.00 10.00 10.00 2.90 2.00 1.30 1.80 1.50 1.00 2.00 1.00 1.50 1.00 1.00 0.20 225.00 300.00 450.00 2.50 2.00 2.00 1.50 2.00 2.50 2.00 2.00 2.10 0.20 8.40 1.5 2.0 1.5 3.2 2.2 2.2 2.6 1.2 279.0 366.0 549.0 2.8 2.4 2.3 1.9 2.5 3.1 2.3 2.1 2.3 0.3 12.0 3.20 2.50 0.4000 0.6667 1.0000 0.6667 0.6667 2.0000 1.0000 2.0000 1.2500 0.0053 0.0039 0.0026 0.4762 0.6667 0.6667 1.0000 0.5556 0.4545 0.5882 0.6250 0.3448 0.5000 0.7692 0.5556 0.6667 1.0000 0.5000 1.0000 0.6667 1.0000 1.0000 5.0000 0.0044 0.0033 0.0022 0.4000 0.5000 0.5000 0.6667 0.5000 0.4000 0.5000 0.5000 0.4762 5.0000 0.1190 0.3125 0.4000 -

Sprayed Secondary Lining, Intermediate Landing Tunnels without columns m Sprayed Secondary Lining, Tunnel Junctions m

Insitu Permanent Lining, 12m bays, 350-400mm reinforced with PCV backingm

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average 25.00 3.20 3.30 2.20 1.20 4.00 3.90 2.50 1.50 Fast 4.9 4.2 2.7 1.7

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.3125 0.3030 0.4545 0.8333 Average 0.2500 0.2564 0.4000 0.6667 Fast -

Insitu Permanent Lining, extra over excavate/lining time to allow for permanent % lining Excavate and Line Cycle Time , Running Tunnels Excavate and Line Cycle Time, Station Access Adits Excavate and Line Cycle Time, Concourse Tunnels Excavate and Line Cycle Time, Escalator Tunnels m m m m days days days days

Metal Decking Metal Decking, large areas Metal Decking, small or complicated Titanium Sheeted Roofs Copper Roofs, flat work Copper Roofs, sloping work Zinc Roofs, flat work Zinc Roofs, sloping work Aluminium Roofs, flat work Aluminium Roofs, sloping work Lead Roofs, flat work Lead Roofs, sloping work Lead Roofs, dormer cheeks Lead Roofs, flat gutters Lead Roofs, flat copings Lead Roofs, stepped gutters Lead Roofs, shaped copings Lead Roofs, cover step flashings Lead Roofs, rooflight flashings Lead Roofs, domed roof coverings m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m m m no m2 days days days days days days days days days days days days days days days days days days days 70.00 28.00 9.50 3.00 2.70 2.40 2.10 2.80 1.90 2.50 2.10 1.30 88.00 76.00 3.50 3.30 3.20 0.80 0.70 0.0143 0.0357 0.1053 0.3333 0.3704 0.4167 0.4762 0.3571 0.5263 0.4000 0.4762 0.7692 0.0114 0.0132 0.2857 0.3030 0.3125 1.2500 1.4286 -

Manholes and Gulleys

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm Brickwork Manhole, 1.0 brick engineering Brickwork Manhole, 1.5 brick engineering Brickwork Manhole, 2.0 brick engineering Benching to Manhole, under 0.5m2 Benching to Manhole, 0.5-0.75m2 Benching to Manhole, 0.75-1.0m2 Brickwork Manhole, build in pipes, under 150mm dia Brickwork Manhole, build in pipes, 150-225mm dia Brickwork Manhole, build in pipes, over 225mm dia Brickwork Manhole, build in cast iron covers Yard Gulleys, 75-150mm dia pipes, bed and level Yard Gulleys, 150-225mm dia pipes, bed and level Yard Gulleys, 225-300mm dia pipes, bed and level Road Gulleys, 600mm deep, bed and level Road Gulleys, 750mm deep, bed and level Road Gulleys, 900mm deep, bed and level Road Gulleys, 1,200mm deep, bed and level Road Gulleys, install gratings PVC Manhole

UNIT FOR QUANTITY


no no m2 m2 m2 no no no no no no no no no no no no no no no no

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours minutes

PRODUCTION RATES (Qty per Time) Slow 3.33 Average 0.8333 0.6250 0.30 0.20 0.20 1.1111 0.8333 0.5556 10.0000 5.0000 3.3333 1.6667 2.20 1.80 1.50 1.20 0.80 0.40 0.30 5.00 0.0667 Fast 0.83

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.30 Average 1.20 1.60 3.3333 5.0000 5.0000 0.90 1.20 1.80 0.10 0.20 0.30 0.60 0.4545 0.5556 0.6667 0.8333 1.2500 2.5000 3.3333 0.2000 15.00 Fast 1.20 -

Lift Installation Hydraulic Lift, Install 2 to 3 storeys Hydraulic Lift, Install 4 storeys and above Hydraulic Lift, Testing allow 2 wks plus Standard Lift, Manufacture, test and deliver Non-Standard Lift, Manufacture, test and deliver floor floor floor weeks weeks days weeks weeks 0.3333 0.5000 1.0000 75.00 3.00 2.00 1.00 12.00 65.00 52.00

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Landscaping Top Soil, spread, level and prepare for turf or seeding Top Soil, rake in fertilizer for seeding Planting, Shrubs and Hedges, under 750mm high Planting, Shrubs and Hedges, over 750mm high Planting, Saplings, under 3.0m high Turfing, including for minor preparations m2 m2 no no no m2 hours hours hours hours hours hours 2.50 25.00 4.00 1.50 1.70 16.80 0.4000 0.0400 0.2500 0.6667 0.5882 0.0595 -

Land Drains Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run m m m m m m m m m hours hours hours hours hours hours hours hours hours 11.60 14.10 18.80 8.40 10.20 11.90 5.40 6.50 7.90 0.0862 0.0709 0.0532 0.1190 0.0980 0.0840 0.1852 0.1538 0.1266 -

Kerbs & Paving Concrete Slabs, laid on bedding, to slight falls Concrete Slabs, laid on bedding, to steep falls Concrete Slabs, laid in mortar, to slight falls Concrete Slabs, laid in mortar, to steep falls Concrete Slabs, laid on sand, to slight falls Concrete Slabs, laid on sand, to steep falls Cobble Stones, laid in mortar, no patterns m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours 2.70 2.30 1.50 1.10 1.70 1.60 0.30 4.20 2.70 2.30 1.50 2.80 1.90 0.3704 0.4348 0.6667 0.9091 0.5882 0.6250 3.3333 0.2381 0.3704 0.4348 0.6667 0.3571 0.5263 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Cobble Stones, laid in mortar, with patterns Artificial Stone, laid on sand, with patterns Brick Paviors, in mortar, straight joints Brick Paviors, in mortar, herringbone pattern Gravel Paths, including preparation of sub-base Concrete Paths, 100mm thick, including preparation of sub-base Concrete Kerbs or Channels, laid straight Concrete Kerbs or Channels, laid to 5m radius Concrete Kerbs or Channels, laid to 10m radius Concrete Kerbs or Channels, laid to 20m radius Stone/Granite Kerbs or Channels, laid straight Concrete Edging, laid straight Concrete Edging, laid to 5m radius Concrete Edging, laid to 10m radius Concrete Edging, laid to 20m radius Cutting and Fitting Ends, Concrete Kerbs Cutting and Fitting Ends, Channels Cutting and Fitting Ends, Concrete Edging

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m m m m m m m m m no no no

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.90 Average 0.20 2.50 1.30 1.00 10.50 2.50 6.20 4.50 5.00 5.50 3.50 7.70 5.80 6.20 7.10 6.60 5.80 8.30 Fast 1.90 1.20

PRODUCTION RATES (Time per Quantity) REMARKS Slow 1.1111 Average 5.0000 0.4000 0.7692 1.0000 0.0952 0.4000 0.1613 0.2222 0.2000 0.1818 0.2857 0.1299 0.1724 0.1613 0.1408 0.1515 0.1724 0.1205 Fast 0.5263 0.8333 -

Ground Compaction Deep Vibroflot, 3m centres Vibro-Roller, Sand Vibro-Roller, Soil Vibro-Roller, Clay Vibro-Roller, Hardcore Vibro-Roller, Ash m3 m2 m2 m2 m2 m2 hours hours hours hours hours hours 330.00 28.50 380.00 31.20 58.80 55.60 38.40 57.80 465.00 45.20 0.0030 0.0351 0.0026 0.0321 0.0170 0.0180 0.0260 0.0173 0.0022 0.0221 -

Formwork

PRODUCTION RATES

ITEM NO.
Pilecaps, < 0.7m2 Pilecaps, 0.7-2.5m2 Pilecaps, 2.5-3.0m2 Pilecaps, > 3.0m2

DESCRIPTION

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 no no m2 m2 m2 m2 m2 m2

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.90 1.60 2.00 2.30 1.10 1.70 1.80 2.50 0.60 0.90 1.00 1.20 1.50 1.40 5.30 0.90 1.00 1.20 1.00 1.90 2.30 3.20 3.80 1.00 3.20 1.20 1.30 1.80 2.00 7.90 6.90 8.50 Average 1.60 2.00 2.30 2.50 1.70 1.80 2.50 2.60 0.80 1.00 1.10 1.30 1.60 1.50 7.10 1.80 2.20 2.50 1.40 2.30 2.80 4.50 4.80 1.50 4.10 2.80 1.60 2.10 2.30 9.50 7.50 10.20 Fast 2.00 2.30 2.50 3.10 1.80 2.50 2.60 3.50 1.20 1.10 1.30 1.50 1.80 1.70 10.00 1.90 2.50 2.90 2.00 3.30 3.50 4.00 5.40 1.80 5.40 3.20 1.80 2.40 2.50 10.30 8.30 12.00

PRODUCTION RATES (Time per Quantity) REMARKS Slow 1.1111 0.6250 0.5000 0.4348 0.9091 0.5882 0.5556 0.4000 1.6667 1.1111 1.0000 0.8333 0.6667 0.7143 0.1887 1.1111 1.0000 0.8333 1.0000 0.5263 0.4348 0.3125 0.2632 1.0000 0.3125 0.8333 0.7692 0.5556 0.5000 0.1266 0.1449 0.1176 Average 0.6250 0.5000 0.4348 0.4000 0.5882 0.5556 0.4000 0.3846 1.2500 1.0000 0.9091 0.7692 0.6250 0.6667 0.1408 0.5556 0.4545 0.4000 0.7143 0.4348 0.3571 0.2222 0.2083 0.6667 0.2439 0.3571 0.6250 0.4762 0.4348 0.1053 0.1333 0.0980 Fast 0.5000 0.4348 0.4000 0.3226 0.5556 0.4000 0.3846 0.2857 0.8333 0.9091 0.7692 0.6667 0.5556 0.5882 0.1000 0.5263 0.4000 0.3448 0.5000 0.3030 0.2857 0.2500 0.1852 0.5556 0.1852 0.3125 0.5556 0.4167 0.4000 0.0971 0.1205 0.0833

Ground Beams, < 0.7m2 Ground Beams, 0.7-1.5m2 Ground Beams, 1.5-3.0m2 Ground Beams, 3.0-5.0m2 Elevated Plain Slab Soffit Beams, on erected falsework, width 100-200mm Beams, on erected falsework, width 200-300mm Beams, on erected falsework, width 300-500mm Beams, on erected falsework, width 500-750mm Beams, on erected falsework, width over 750mm Walls, Construct Kickers Walls, Fully Framed Formwork/Struts, 1.0-2.0m2 Walls, Fully Framed Formwork/Struts, 2.0-5.0m2 Walls, Fully Framed Formwork/Struts, over 5.0m2 Walls, StoriForm Shutters, 1.0-3.0m2 Walls, StoriForm Shutters, 3.0-5.0m2 Walls, StoriForm Shutters, 5.0-10.0m2 Walls, StoriForm Shutters, 10.0-15.0m2 Walls, StoriForm Shutters, over 15.0m2 Ground Slabs Columns, Construct Kickers, direct to slab Columns, Construct Kickers, suspended from soffit slab Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2 Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2 Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2 Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia Columns, Round Sides, Steel Mould, 3.0-4.0m dia Columns, Sloping Column Heads, extra over rate Staircases, Stair Soffit, Sloping Staircases, Stair Soffit, Flat Landing Staircases, Wall Strings Staircases, Open Strings Staircases, Riser Boards fixed to strings Staircases, Risers fixed to Strings Waffle Flooring, 2.4m grid Shaft Slip Forming Table Form, Aluminum System, 400m2 bays Table Form, H-Frame Steel Falsework, 400m2 bays Tunnel Forms, Wall and Slab poured as one Hollorib Decking, lay deck Hollorib Decking, shear connecting studs Stop Ends, no perforations Stop Ends, minor perforations Stop Ends, dense perforations Box Outs, 0.01-0.05m2 Box Outs, over 0.05m2 Dummy Frames, under 3.0m2 Dummy Frames, over 3.0m2

UNIT FOR QUANTITY


m2 m2 no m2 m2 m2 m2 m2 m2 m2 mm m2 m2 m2 m2 m2 m2 m2 m2 no no no no

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 3.50 5.20 0.70 0.80 0.40 0.70 1.10 2.10 1.90 2.80 1.20 0.90 7.60 3.10 4.50 3.10 Average 4.50 6.50 0.40 0.80 0.90 0.60 0.80 2.50 2.30 1.40 300.00 3.20 3.00 15.60 43.50 29.30 3.50 1.50 1.10 8.20 3.90 6.20 3.70 2.80 2.60 1.80 500.00 3.80 3.50 17.50 47.50 31.20 4.20 1.90 1.40 9.10 4.50 7.10 4.50 Fast 6.00 7.50 0.29 1.00 1.20

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.2857 0.1923 1.4286 1.2500 2.5000 1.4286 0.9091 0.4762 0.5263 0.3571 0.8333 1.1111 0.1316 0.3226 0.2222 0.3226 Average 0.2222 0.1538 2.50 1.2500 1.1111 1.6667 1.2500 0.4000 0.4348 0.7143 0.0033 0.3125 0.3333 0.0641 0.0230 0.0341 0.2857 0.6667 0.9091 0.1220 0.2564 0.1613 0.2703 Fast 0.1667 0.1333 3.50 1.0000 0.8333 0.3571 0.3846 0.5556 0.0020 0.2632 0.2857 0.0571 0.0211 0.0321 0.2381 0.5263 0.7143 0.1099 0.2222 0.1408 0.2222

Floor Finishes Granolithic Flooring Terrazzo Flooring, in-situ Terrazzo Flooring, pre-cast Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, small areas, much cutting m2 m2 m2 m2 m2 hours hours hours hours hours 3.10 3.60 4.60 1.50 0.80 5.10 2.20 1.10 0.3226 0.2778 0.2174 0.6667 1.2500 0.1961 0.4545 0.9091

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Clay, quarry Tiles, large areas, little cutting Raised Floor System Linolium/Thermo-Plastic Flooring Thermo-Plastic Floor Tiles Wood Block Flooring, lay blocks Wood Block Flooring, sand and polish Carpeting, Underlay & Gripper Carpeting, Adhesive Fixing Carpeting, Fully Fitted Hardboard Sheeting Coverings, small areas Hardboard Sheeting Coverings, large areas Floor Sheeting Coverings, Lay Lino

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 2.20 2.60 3.10 3.30 1.50 3.10 5.60 3.50 2.00 3.70 6.60 9.50 6.10 4.20 2.80 4.10 7.20 10.50 5.00 5.60 2.10 Fast 2.80

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.4545 0.3846 0.3226 0.3030 0.6667 0.3226 0.1786 0.2857 0.5000 0.2703 0.1515 0.1053 Fast 0.3571 0.2000 0.1786 0.4762 0.1639 0.2381 0.3571 0.2439 0.1389 0.0952

Flat and Layered Roofs Asphalt Roof in layers Asbestos Sheets in layers Felt Roofs, large areas Felt Roofs, small or complicated Felt Roofs, Gravel roof chippings m2 m2 m2 m2 Tons days days days days days 45.00 39.00 52.00 35.00 1.40 0.0222 0.0256 0.0192 0.0286 0.7143 -

Fencing Works Site Hoarding, timber posts, plywood nailed to horizontal rails Post Erection, Timber / Metal, dig, erect, fix Post Erection, Concrete, dig, erect, fix Fence Erection, Chainlink, posts at 1.5m Fence Erection, Chainlink, posts at 2.0m Fence Erection, Chainlink, posts at 3.0m Fence Erection, Chestnut Pailings, posts at 1.5m m no no m m m m hours hours hours hours hours hours hours 1.00 3.30 3.20 1.20 4.50 4.00 4.20 4.40 5.50 23.80 1.0000 0.3030 0.3125 0.8333 0.2222 0.2500 0.2381 0.2273 0.1818 0.0420 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Fence Erection, Chestnut Pailings, posts at 2.0m Fence Erection, Chestnut Pailings, posts at 3.0m Fence Erection, Barbed Wire, posts at 1.5m Fence Erection, Barbed Wire, posts at 2.0m Fence Erection, Barbed Wire, posts at 3.0m Gate Erection, Chainlink on frame

UNIT FOR QUANTITY


m m m m m no

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 33.30 41.60 71.40 100.00 125.00 4.10 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.0300 0.0240 0.0140 0.0100 0.0080 0.2439 Fast -

Escalators Truss type, Overall Installation (excl arch finishes) Truss type, Manufacture, test and deliver Truss type, Phase A assemble truss , position/level Truss type, Stop-Work for surrounding finishes Truss type, Phase B decking and glazing etc Truss type, Phase C performance testing Truss type, Phase D full load testing Truss type, Phase E final test and inspection wks wks wks wks wks wks wks wks 8.00 14.00 12.00 60.00 1.00 6.00 5.00 2.00 2.00 2.00 4.00 11.00 48.00

Electrical System Railway Station 1st Fix Railway Station 2nd Fix Railway Station T&C Cable Installation, 1 cable laid in trench and protect Cable Installation, 2 cable laid in trench and protect Cable Installation, 5 cable laid in trench and protect Cable Installation, 7 cable laid in trench and protect Cable Installation, 8 cable laid in trench and protect Cable Installation, 2 cable laid in trench and protect, 100mm dia Cable Installation, 2 cable laid in trench and protect, 135mm dia m m m m m m m wks wks wks hours hours hours hours hours hours hours 6.20 5.60 4.30 3.70 3.50 1.80 1.60 38.0 16.0 8.0 0.1613 0.1786 0.2326 0.2703 0.2857 0.5556 0.6250 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Cable Installation, 3 cable laid in trench and protect, 100mm dia Cable Installation, 6 cable laid in trench and protect, 100mm dia Cable Installation, 4 cable laid in trench and protect, 150mm dia Cable Installation, 36 cable laid in trench and protect, 100mm dia Cable Installation, 10 cable laid in trench and protect, 100mm dia Cable Installation, 1 cable laid in trench and protect, 300mm dia

UNIT FOR QUANTITY


m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.70 Average 1.00 0.70 1.20 0.20 0.50 1.30 Fast 1.50 1.20 3.10

PRODUCTION RATES (Time per Quantity) REMARKS Slow 1.4286 Average 1.0000 1.4286 0.8333 5.0000 2.0000 0.7692 Fast 0.6667 0.8333 0.3226 -

Drainage PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run PVC Drainage, 1m pipes, 100-150mm dia, over 30m run PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run PVC Drainage, 3m pipes, 100-150mm dia, over 30m run PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run PVC Drainage, 6m pipes, 100-150mm dia, over 30m run PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run PVC Drainage, 3m pipes, 150-200mm dia, over 30m run PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run PVC Drainage, 6m pipes, 150-200mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run m m m m m m m m m m m m m m m m m m m m m m hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 5.70 8.10 9.50 12.20 15.20 18.20 22.20 27.70 33.30 10.60 12.80 21.20 25.60 4.70 5.50 6.60 4.40 5.00 6.20 3.20 3.80 4.50 0.1754 0.1235 0.1053 0.0820 0.0658 0.0549 0.0450 0.0361 0.0300 0.0943 0.0781 0.0472 0.0391 0.2128 0.1818 0.1515 0.2273 0.2000 0.1613 0.3125 0.2632 0.2222 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run

UNIT FOR QUANTITY


m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours minutes hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 2.10 2.60 3.10 1.40 1.70 2.40 1.10 1.30 1.60 8.30 10.00 12.50 7.70 9.10 10.00 5.20 6.20 7.70 2.70 3.30 4.00 1.70 2.10 2.50 1.40 1.60 2.10 0.4167 9.10 16.60 20.00 9.10 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.4762 0.3846 0.3226 0.7143 0.5882 0.4167 0.9091 0.7692 0.6250 0.1205 0.1000 0.0800 0.1299 0.1099 0.1000 0.1923 0.1613 0.1299 0.3704 0.3030 0.2500 0.5882 0.4762 0.4000 0.7143 0.6250 0.4762 2.40 0.1099 0.0602 0.0500 0.1099 Fast -

Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run

Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run m Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run PVC, Stoneware, Pitch Fibre & Concrete Joints Pitch Fibre Pipes, 75mm dia, 0-5m run Pitch Fibre Pipes, 75mm dia, 5-30m run Pitch Fibre Pipes, 75mm dia, over 30m run Pitch Fibre Pipes, 100mm dia, 0-5m run m m m m m m m m m m m m m m m m m m no m m m m

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Pitch Fibre Pipes, 100mm dia, 5-30m run Pitch Fibre Pipes, 100mm dia, over 30m run Pitch Fibre Pipes, 150mm dia, 0-5m run Pitch Fibre Pipes, 150mm dia, 5-30m run Pitch Fibre Pipes, 150mm dia, over 30m run Pitch Fibre Pipes, 200mm dia, 0-5m run Pitch Fibre Pipes, 200mm dia, 5-30m run Pitch Fibre Pipes, 200mm dia, over 30m run Pitch Fibre Pipes, 225mm dia, 0-5m run Pitch Fibre Pipes, 225mm dia, 5-30m run Pitch Fibre Pipes, 225mm dia, over 30m run Hepsleve Rubber Joint System, 75mm dia, 0-5m run Hepsleve Rubber Joint System, 75mm dia, 5-30m run Hepsleve Rubber Joint System, 75mm dia, over 30m run Hepsleve Rubber Joint System, 100mm dia, 0-5m run Hepsleve Rubber Joint System, 100mm dia, 5-30m run Hepsleve Rubber Joint System, 100mm dia, over 30m run Hepsleve Rubber Joint System, 150mm dia, 0-5m run Hepsleve Rubber Joint System, 150mm dia, 5-30m run Hepsleve Rubber Joint System, 150mm dia, over 30m run Hepsleve Rubber Joint System, 225mm dia, 0-5m run Hepsleve Rubber Joint System, 225mm dia, 5-30m run Hepsleve Rubber Joint System, 225mm dia, over 30m run Hepsleve Rubber Joint System, 300mm dia, 0-5m run Hepsleve Rubber Joint System, 300mm dia, 5-30m run Hepsleve Rubber Joint System, 300mm dia, over 30m run Hepsleve Rubber Joint System, over 375mm dia, 0-5m run Hepsleve Rubber Joint System, over 375mm dia, 5-30m run Hepsleve Rubber Joint System, over 375mm dia, over 30m run Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run

UNIT FOR QUANTITY


m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 11.20 8.30 Average 16.60 20.00 6.60 12.50 14.30 6.20 11.10 12.50 5.80 10.00 12.10 12.50 14.30 16.60 10.00 12.50 14.30 7.10 9.10 10.00 6.80 4.50 5.50 2.50 2.90 3.70 1.90 2.30 2.70 2.80 3.40 3.80 13.80 Fast 30.10

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.0893 0.1205 Average 0.0602 0.0500 0.1515 0.0800 0.0699 0.1613 0.0901 0.0800 0.1724 0.1000 0.0826 0.0800 0.0699 0.0602 0.1000 0.0800 0.0699 0.1408 0.1099 0.1000 0.1471 0.2222 0.1818 0.4000 0.3448 0.2703 0.5263 0.4348 0.3704 0.3571 0.2941 0.2632 Fast 0.0332 0.0725 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run Concrete Pipes, 1.5m pipes, 1,050mm dia Concrete Pipes, 1.5m pipes, 1,500mm dia Concrete Pipes, 1.5m pipes, 1,800mm dia Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run

UNIT FOR QUANTITY


m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours days days days hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 2.70 3.20 3.60 2.50 2.90 3.40 2.40 2.70 3.30 2.20 2.60 2.90 1.10 2.40 2.50 2.90 2.50 2.10 3.60 4.30 5.00 3.40 4.10 4.50 3.30 3.80 4.10 3.00 3.50 4.00 2.80 3.30 9.00 8.00 Fast 4.20 3.80 2.60

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.3704 0.3125 0.2778 0.4000 0.3448 0.2941 0.4167 0.3704 0.3030 0.4545 0.3846 0.3448 0.9091 0.4167 0.4000 0.3448 0.4000 0.4762 0.2778 0.2326 0.2000 0.2941 0.2439 0.2222 0.3030 0.2632 0.2439 0.3333 0.2857 0.2500 0.3571 0.3030 Fast 0.2381 0.2632 0.3846 0.1250 0.1111 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run Lay Shingle Around Pipework, under 150mm dia Lay Shingle Around Pipework, over 150mm dia

UNIT FOR QUANTITY


m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 4.00 Average 3.70 2.60 3.10 3.60 7.00 5.50 Fast 9.00

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.2500 Average 0.2703 0.3846 0.3226 0.2778 0.1429 0.1818 Fast 0.1111

Doors and Windows Mastic Pointing to Frames Fix Metal and Timber Windows After Wall Complete Window Glazing Window Glazing, Single Glazed Units Window Glazing, Double Glazed Units m m2 m2 m2 m2 hours hours hours hours hours 9.50 2.00 1.30 2.00 1.30 0.1053 0.5000 0.7692 0.5000 0.7692 -

Blockwork Thermalite Blockwork, under 100mm thick Thermalite Blockwork, under 100-150mm thick Thermalite Blockwork, over 150mm thick Lightweight Concrete Blockwork, under 100mm thick Lightweight Concrete Blockwork, under 100-150mm thick Lightweight Concrete Blockwork, over 150mm thick Heavyweight Concrete Blockwork, under 100mm thick Heavyweight Concrete Blockwork, under 100-150mm thick Heavyweight Concrete Blockwork, over 150mm thick Face Finish, Raked Out Face Finish, Bag Rubbed Face Finish, Flush Pointing m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours 1.80 1.40 1.20 1.50 1.40 1.20 1.40 1.20 1.10 2.50 1.90 1.60 2.20 1.90 1.60 2.10 1.60 1.40 71.40 29.40 17.60 3.20 2.50 2.10 2.90 2.10 2.00 2.90 2.10 1.80 0.5556 0.7143 0.8333 0.6667 0.7143 0.8333 0.7143 0.8333 0.9091 0.4000 0.5263 0.6250 0.4545 0.5263 0.6250 0.4762 0.6250 0.7143 0.0140 0.0340 0.0568 0.3125 0.4000 0.4762 0.3448 0.4762 0.5000 0.3448 0.4762 0.5556 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Dewatering Setup small 2 hole system Setup large 15 hole system Calculate system times per pump Setup Recharge System pump pump days days days days 0.4000 0.2857 10.00 8.00 21.00 2.50 3.50 6.00

Demolition Weight, Structural Steel Remove & Cart away, Ceramic Wall Tiles Remove & Cart away, Wallpaper, 1 layer Remove & Cart away, Wallpaper, 2 layers Remove & Cart away, Wallpaper, 3 layers Remove & Cart away, Lathe and Plaster Ceilings Remove & Cart away, Plaster to Walls Remove & Cart away, External Render Remove & Cart away, Floor Screed Remove & Cart away, Concrete Paving Remove & Cart away, Brickwork Walls, 1.0 brick thick Remove & Cart away, Brickwork Walls, 0.5 brick thick Remove & Cart away, Brickwork Walls, Sand/Lime Mortar Remove & Cart away, Fireplace and Hearth Remove & Cart away, Floor Boards Remove & Cart away, Skirting, Architrave, Dado rail etc Remove & Cart away, Staircase Remove & Cart away, Windows, 0-1m2 Remove & Cart away, Windows 1-2m2 Remove & Cart away, Windows 2-3m2 Remove & Cart away, Doors Tonnes m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 100 no m2 m no no no no no m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 3.20 2.10 2.00 2.50 2.50 8.70 7.10 5.70 4.60 3.10 3.90 3.20 4.00 1.30 2.60 0.5556 0.5263 6.20 16.50 0.1370 1.6667 1.2500 1.1111 3.3333 5.00 5.90 3.40 0.5000 0.3125 0.4762 0.4000 0.4000 0.1149 0.1408 0.1754 0.2174 0.3226 0.2564 0.3125 0.2500 0.7692 0.3846 1.80 1.90 0.1613 0.0606 7.30 0.60 0.80 0.90 0.30 0.2941 0.2000 0.1695 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Remove & Cart away, Door Frame Remove & Cart away, Floor and Ceiling Joists Remove & Cart away, Wall Plates Remove & Cart away, Iron Bath Remove & Cart away, Wash Basin/Sink Remove & Cart away, Pipework including brackets etc

UNIT FOR QUANTITY


no m m no no m

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 10.0000 0.9091 0.2564 0.7143 1.2500 6.10 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.10 1.10 3.90 1.40 0.80 0.1639 Fast -

Decking Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover m days 7.10 0.1408 -

Cutting Switchboxes Cutting in Concrete, small box Cutting in Concrete, large box Cutting in Brickwork, small box Cutting in Brickwork, large box Cutting in Lightweight Blockwork, small box Cutting in Lightweight Blockwork, large box Cutting in Heavyweight Blockwork, small box Cutting in Heavyweight Blockwork, large box no no no no no no no no hours hours hours hours hours hours hours hours 7.10 3.60 6.60 4.20 20.00 10.00 7.70 3.80 9.50 4.50 9.50 5.30 23.00 12.50 10.00 4.80 12.50 5.60 12.50 6.30 25.00 14.30 12.50 5.90 0.1408 0.2778 0.1515 0.2381 0.0500 0.1000 0.1299 0.2632 0.1053 0.2222 0.1053 0.1887 0.0435 0.0800 0.1000 0.2083 0.0800 0.1786 0.0800 0.1587 0.0400 0.0699 0.0800 0.1695

Cutting Chases Concrete, cutting by hand, < 25mm wide Concrete, cutting by hand, 25-50mm wide Concrete, cutting by hand, 50-75mm wide Concrete, cutting by hand, 75-100mm wide Concrete, cutting by machine, < 25mm wide m m m m m hours hours hours hours hours 1.50 1.20 1.00 0.90 3.10 2.10 1.60 1.40 1.20 4.00 3.10 2.50 2.10 1.80 5.80 0.6667 0.8333 1.0000 1.1111 0.3226 0.4762 0.6250 0.7143 0.8333 0.2500 0.3226 0.4000 0.4762 0.5556 0.1724

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Concrete, cutting by machine, 25-50mm wide Concrete, cutting by machine, 50-75mm wide Concrete, cutting by machine, 75-100mm wide Brickwork, cutting by hand, < 25mm wide Brickwork, cutting by hand, 25-50mm wide Brickwork, cutting by hand, 50-75mm wide Brickwork, cutting by hand, 75-100mm wide Brickwork, cutting by machine, < 25mm wide Brickwork, cutting by machine, 25-50mm wide Brickwork, cutting by machine, 50-75mm wide Brickwork, cutting by machine, 75-100mm wide Light Blockwork, cutting by hand, < 25mm wide Light Blockwork, cutting by hand, 25-50mm wide Light Blockwork, cutting by hand, 50-75mm wide Light Blockwork, cutting by hand, 75-100mm wide Light Blockwork, cutting by machine, < 25mm wide Light Blockwork, cutting by machine, 25-50mm wide Light Blockwork, cutting by machine, 50-75mm wide Light Blockwork, cutting by machine, 75-100mm wide Heavy Blockwork, cutting by hand, < 25mm wide Heavy Blockwork, cutting by hand, 25-50mm wide Heavy Blockwork, cutting by hand, 50-75mm wide Heavy Blockwork, cutting by hand, 75-100mm wide Heavy Blockwork, cutting by machine, < 25mm wide Heavy Blockwork, cutting by machine, 25-50mm wide Heavy Blockwork, cutting by machine, 50-75mm wide Heavy Blockwork, cutting by machine, 75-100mm wide

UNIT FOR QUANTITY


m m m m m m m m m m m m m m m m m m m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 2.50 2.10 1.80 2.10 1.60 1.40 1.20 4.20 3.30 3.30 2.50 3.80 3.20 2.60 2.30 7.70 5.90 5.20 4.70 1.90 1.60 1.30 1.20 3.80 3.20 2.70 2.30 Average 3.30 2.90 2.40 2.70 2.30 1.90 1.60 5.50 4.50 4.50 3.30 5.00 4.20 3.40 3.10 10.00 7.70 7.20 6.30 2.60 2.10 1.80 1.50 5.00 4.20 3.60 3.10 Fast 5.00 4.20 3.70 4.10 3.50 2.80 2.50 11.10 6.70 6.70 5.00 7.70 6.30 5.30 4.50 14.20 11.10 10.00 9.10 3.80 3.20 2.70 2.30 7.70 6.20 5.20 4.50

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.4000 0.4762 0.5556 0.4762 0.6250 0.7143 0.8333 0.2381 0.3030 0.3030 0.4000 0.2632 0.3125 0.3846 0.4348 0.1299 0.1695 0.1923 0.2128 0.5263 0.6250 0.7692 0.8333 0.2632 0.3125 0.3704 0.4348 Average 0.3030 0.3448 0.4167 0.3704 0.4348 0.5263 0.6250 0.1818 0.2222 0.2222 0.3030 0.2000 0.2381 0.2941 0.3226 0.1000 0.1299 0.1389 0.1587 0.3846 0.4762 0.5556 0.6667 0.2000 0.2381 0.2778 0.3226 Fast 0.2000 0.2381 0.2703 0.2439 0.2857 0.3571 0.4000 0.0901 0.1493 0.1493 0.2000 0.1299 0.1587 0.1887 0.2222 0.0704 0.0901 0.1000 0.1099 0.2632 0.3125 0.3704 0.4348 0.1299 0.1613 0.1923 0.2222

Cutting Back Concrete Pile Caps, 50-300mm deep and 0.6m dia no hours 1.6667 3.3333 0.60 0.30

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Concrete Pile Caps, 300-750mm deep and 0.6m dia Concrete Pile Caps, > 750mm deep and 0.6m dia Concrete Pile Caps, 50-300mm deep and 1.1m dia Concrete Pile Caps, 300-750mm deep and 1.1m dia Concrete Pile Caps, > 750mm deep and 1.1m dia Concrete Pile Caps, 50-300mm deep and 2.5m dia Concrete Pile Caps, 300-750mm deep and 2.5m dia Concrete Pile Caps, > 750mm deep and 2.5m dia Concrete, Cutting Slabs, 5-25m deep Concrete, Cutting Slabs, 25-50m deep Concrete, Cutting Slabs, 50-75m deep Concrete, Cutting Holes, coring machine Concrete, Cutting Back to expose couplers 0.7m slab

UNIT FOR QUANTITY


no no no no no no no no m m m m3 m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours days

PRODUCTION RATES (Qty per Time) Slow 0.6667 0.5556 0.5263 0.4000 0.2381 0.1087 0.0990 0.0870 Average 15.20 11.50 6.70 0.20 2.50 Fast 2.5000 1.2500 1.2500 0.9091 0.4348 0.1220 0.1053 0.0980

PRODUCTION RATES (Time per Quantity) REMARKS Slow 1.50 1.80 1.90 2.50 4.20 9.20 10.10 11.50 Average 0.0658 0.0870 0.1493 5.0000 0.4000 Fast 0.40 0.80 0.80 1.10 2.30 8.20 9.50 10.20 -

Curtain Walling Vertical Glazed Lights, 6m x 2.5m Vertical Glazed Walls, large scale Clerestory Frame/Glazing, 3m x 4m Oriel Window Frame/Glazing, 4m x 2m Glazed Curtain Wall, First Fix Glazed Curtain Wall, Second Fix High Quality Glazed Curtain Walling m2 m2 m2 m2 m2 m2 m2 days days days days hours hours days 14.50 70.00 28.00 35.00 1.20 1.10 25.00 0.0690 0.0143 0.0357 0.0286 0.8333 0.9091 0.0400 -

Concrete Placement Placing concrete, lorry based pump Hollorib Decking, concrete topping Hollorib Decking, concrete topping, incl PowerFloat Placing Concrete, By Wheelbarrow over 1-10m m3 m2 m2 m3 hours hours hours hours 30.00 85.00 40.00 2.10 40.00 100.00 50.00 2.30 50.00 120.00 70.00 2.50 0.0333 0.0118 0.0250 0.4762 0.0250 0.0100 0.0200 0.4348 0.0200 0.0083 0.0143 0.4000

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Placing Concrete, By Wheelbarrow over 10-20m Placing Concrete, By Wheelbarrow over 20-50m Placing Direct From Readymix Lorry, Mass Fill Placing Direct From Readymix Lorry, 50mm Blinding Placing Direct From Readymix Lorry, Ground Beams Placing Direct From Readymix Lorry, Pile Caps Placing Direct From Readymix Lorry, Duct Walls Placing Direct From Readymix Lorry, Stub Columns Placing Direct From Readymix Lorry, Ground Slab Placing Direct From Readymix Lorry,Drains Bed and Cover Placing From Tower Crane, Pile Caps Placing From Tower Crane, Mass Fill Placing From Tower Crane, Slabs under 150mm thick Placing From Tower Crane, Slabs over 150mm thick Placing From Tower Crane, Trough/Coffered Slabs Placing From Tower Crane, Stairs and Landings Placing From Tower Crane, Blinding Placing From Tower Crane, Beams under 150mm thick Placing From Tower Crane, Beams over 150mm thick Placing From Tower Crane, Walls Placing From Tower Crane, Columns

UNIT FOR QUANTITY


m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 1.50 0.80 2.80 1.50 1.00 2.10 1.20 4.00 0.90 1.20 0.90 0.60 0.80 0.50 0.60 0.60 0.40 Average 1.80 1.10 3.10 1.30 1.50 0.80 0.40 2.30 0.90 1.40 4.50 1.30 1.50 1.10 0.70 1.00 0.60 0.80 1.10 0.50 Fast 2.10 1.50 3.30 1.60 1.70 2.30 1.10 0.60 2.60 1.00 1.60 5.50 1.70 1.80 1.20 0.90 1.10 0.80 1.00 1.50 0.60

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.6667 1.2500 0.3571 0.6667 1.0000 0.4762 0.8333 0.2500 1.1111 0.8333 1.1111 1.6667 1.2500 2.0000 1.6667 1.6667 2.5000 Average 0.5556 0.9091 0.3226 0.7692 0.6667 1.2500 2.5000 0.4348 1.1111 0.7143 0.2222 0.7692 0.6667 0.9091 1.4286 1.0000 1.6667 1.2500 0.9091 2.0000 Fast 0.4762 0.6667 0.3030 0.6250 0.5882 0.4348 0.9091 1.6667 0.3846 1.0000 0.6250 0.1818 0.5882 0.5556 0.8333 1.1111 0.9091 1.2500 1.0000 0.6667 1.6667

Concrete Mixing Concrete Weight, 1m3 Readymix Lorry, Length Readymix Lorry, Width Readymix Lorry, Height Readymix Lorry, Length Readymix Lorry, Turning Circle Readymix Lorry, Allowable Access Ramp Gradient Tonnes m m m Tonnes m degrees 2.40 8.30 2.50 3.70 24.40 16.40 17.00 20.00 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Mixing Concrete, By Hand Mixing Concrete, Single Drum Paddle Mixer Mixing Concrete, Double Drum Paddle Mixer Mixing Concrete, Single Drum Plant Pan Mixer Mixing Concrete, Dry Mix Plant

UNIT FOR QUANTITY


m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 158.00 315.00 Average 0.30 180.00 370.00 120.00 90.00 Fast 210.00 420.00

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.0063 0.0032 Average 3.3333 0.0056 0.0027 0.0083 0.0111 Fast 0.0048 0.0024 -

Concrete Finishing Surface Finishing, Steel Float By Hand Surface Finishing, Wood Float By Hand Surface Finishing, Power Float Surface Finishing, Light Brush on Trowel Surface Finishing, Brush on Trowel Margin Surface Finishing, Sprayed By Pump, expose aggregate Surface Finishing, Wire Brush, expose aggregate Making Good Walls, prepare, shutter, pour Making Good Columns, prepare, shutter, pour Making Good Sides of Beams, prepare, shutter, pour Making Good Slab Soffits, prepare, shutter, pour Making Good Bolt Holes, prepare, shutter, pour Making Good Rubdown Precast Concrete, prepare, shutter, pour Making Good Scabble 3 head brush hammer, prepare, shutter, pour m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 no/hr m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours 30.70 14.80 9.20 11.70 13.90 55.80 28.80 65.00 15.00 13.90 17.20 20.80 90.10 48.50 95.00 25.00 5.50 2.80 2.80 4.20 16.80 18.00 59.50 73.80 25.00 29.40 37.00 170.00 85.00 145.00 30.00 8.60 6.90 7.00 5.50 25.80 0.1087 0.0855 0.0719 0.0179 0.0347 0.0154 0.0667 0.0676 0.0326 0.0719 0.0581 0.0481 0.0111 0.0206 0.0105 0.0400 0.1818 0.3571 0.3571 0.2381 0.0595 0.0556 0.0168 0.0400 0.0340 0.0270 0.0059 0.0118 0.0069 0.0333 0.1163 0.1449 0.1429 0.1818 0.0388 0.0136

Commercial Kitchen Overall Installation for 100 persons or 50m2 Overall Installation for 500 persons or 150m2 Overall Installation for 1000 persons or 250m2 Install Ovens, friers and large mixers etc Install Sinks, bain maries and washers etc wks wks wks mandays mandays 3.00 5.00 8.00 1.00 2.00 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Ceiling Finishes Suspended Ceilings, office situations Suspended Ceilings, First Fix Suspended Ceilings, Second Fix m2 m2 m2 hours hours hours 2.60 0.70 1.20 3.50 0.3846 1.4286 0.8333 0.2857 -

Carpentry Final Fixing Windows, Softwood, 3.0-7.0m2 Windows, Softwood, 7.0-10.0m2 Windows, Hardwood, 1.0-3.0m2 Windows, Hardwood, 3.0-7.0m2 Windows, Hardwood, 7.0-10.0m2 Windows, Aluminum, 1.0-3.0m2 Windows, Aluminum, 3.0-7.0m2 Windows, Aluminum, 7.0-10.0m2 Windows, Steel, 1.0-3.0m2 Windows, Steel, 3.0-7.0m2 Windows, Steel, 7.0-10.0m2 Window Boards, nailed Window Boards, screwed Mouldings, Softwood, Nailed Mouldings, Softwood, Screwed Mouldings, Softwood, Gun Nailed Mouldings, Hardwood, Nailed Mouldings, Hardwood, Screwed Mouldings, Hardwood, Gun Nailed Skirting, Aluminum, Screwed 150-300mm centres Skirting, Aluminum, Screwed 300-450mm centres no no no no no no no no no no no m m m m m m m m m m hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 1.6667 0.7692 2.5000 1.4286 0.6250 5.0000 2.0000 0.8333 2.5000 0.8333 0.7143 2.5000 1.1111 3.3333 2.0000 0.8333 3.3333 2.5000 1.2500 3.3333 1.6667 0.8333 3.3333 2.5000 6.30 4.60 8.20 3.30 2.40 8.50 7.60 4.50 3.3333 1.6667 2.5000 1.4286 3.3333 2.0000 5.0000 2.0000 1.0000 5.0000 3.3333 8.50 5.60 11.10 5.50 3.70 11.30 0.60 1.30 0.40 0.70 1.60 0.20 0.50 1.20 0.40 1.20 1.40 0.40 0.90 0.30 0.50 1.20 0.30 0.40 0.80 0.30 0.60 1.20 0.30 0.40 0.1587 0.2174 0.1220 0.3030 0.4167 0.1176 0.1316 0.2222 0.30 0.50 0.20 0.50 1.00 0.20 0.30 0.1176 0.1786 0.0901 0.1818 0.2703 0.0885 0.40 0.70 0.30 0.60

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Skirting, Plastic, Adhesive Fixing Architrave Mouldings Architrave, Fix to Doors Door Stop Mouldings Glazed Bead Mouldings Hanging Doors, Softwood, Single Pair Butts Hanging Doors, Hardwood, Single Pair Butts Cut Mortice to Receive Lock, Softwood Cut Mortice to Receive Lock, Hardwood Cut & Fix Formica Bath Panel Kitchen Cupboards, Floor Units Kitchen Cupboards, Wall Units Kitchen Cupboards, Shelf Units Staircase, pre-made, simple, straight flight Staircase, pre-made, 2 straight flights, 1 landing Staircase, pre-made, 2 straight flights, 2 landings Staircase, Balustrades/Handrails, fix horizontal Staircase, Balustrades/Handrails, fix raking Staircase, Cut and Fix Newel to Walls Windows, Softwood, 1.0-3.0m2 Raised Flooring, metal system

UNIT FOR QUANTITY


m m door m m no no no no no no no no no no no no no no no m2

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 9.50 10.10 15.50 0.7692 0.5263 0.5263 0.2703 0.8333 1.1111 1.1111 3.3333 Average 8.60 12.20 0.8333 16.90 18.60 1.1111 0.8333 5.0000 1.6667 2.5000 1.2500 1.4286 0.6667 0.3448 0.1587 1.6667 2.0000 5.0000 0.50 25.00 20.40 1.6667 1.1111 1.6667 2.0000 1.4286 0.9091 0.3846 10.0000 3.3333 5.0000 Fast 18.20

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1053 0.0990 0.0645 1.30 1.90 Average 0.1163 0.0820 1.20 0.0592 0.0538 0.90 1.20 0.20 0.60 0.40 0.80 0.70 0.8 1.90 3.70 1.50 2.90 6.30 1.20 0.90 0.90 0.30 0.60 0.50 0.20 2.0000 0.10 0.30 0.20 0.60 0.50 0.70 1.10 2.60 Fast 0.0549 0.0400 0.0490 0.60 0.90

Carpentry Carcassing Windows, Timber Frames for Bricklaying Windows, Drill, Screw & Plug extra over Door Frames, Softwood, 1.0-3.0m2 Door Frames, Softwood, 3.0-7.0m2 Door Frames, Softwood, 7.0-10.0m2 Door Frames, Hardwood, 1.0-3.0m2 Door Frames, Hardwood, 3.0-7.0m2 no no no no no no no hours hours hours hours hours hours hours 0.9091 3.3333 2.0000 0.8333 1.6667 2.0000 10.0000 5.0000 2.5000 1.2500 3.3333 3.3333 10.0000 0.60 0.50 1.20 1.10 0.30 0.50 0.10 0.20 0.40 0.80 0.30 0.30 0.10

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Door Frames, Hardwood, 7.0-10.0m2 Erect Water Tank Platform Fix Studding For Bath Cut Access Hatch Floor Joists, under 3m Floor Joists, 3.0-4.5m Floor Joists, 4.5-6.0m Ceiling Joists, under 3m Ceiling Joists, 3.0-4.5m Ceiling Joists, 4.5-6.0m Ceiling Joists, Notch to Beams Ceiling Joists, Pack Joist Ends Ceiling Joists, Nailing Joists together Ceiling Joists, Bolting Joists Together Floor Boards, Butt Jointed Floor Boards, T&G Boards, under 75mm wide Floor Boards, T&G Boards, 75-100mm wide Floor Boards, T&G Boards, 100-125mm wide Floor Boards, T&G Boards, 125-150mm wide Plywood Sheeting, Butt Jointed, nailed Plywood Sheeting, Butt Jointed, screwed Plywood Sheeting, T&G Jointed, nailed Plywood Sheeting, T&G Jointed, screwed Chipboard Sheeting, Butt Jointed, nailed Chipboard Sheeting, Butt Jointed, screwed Chipboard Sheeting, T&G Jointed, nailed Chipboard Sheeting, T&G Jointed, screwed

UNIT FOR QUANTITY


no no m no no no no no no no no no m m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.7143 9.00 6.80 5.50 12.80 10.80 9.60 20.00 20.10 Average 1.0000 2.30 10.00 0.30 9.60 7.20 5.80 14.00 12.10 10.80 25.00 23.80 23.00 12.60 1.70 3.40 3.80 4.20 5.50 9.10 4.10 8.30 4.00 10.00 5.10 9.30 5.50 10.20 4.80 9.10 4.60 11.50 5.80 9.10 5.90 11.60 9.70 7.30 14.70 12.60 11.10 28.50 26.30 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow 1.40 Average 1.00 0.4348 0.10 3.3333 0.1111 0.1471 0.1818 0.0781 0.0926 0.1042 0.0500 0.0498 0.1042 0.1389 0.1724 0.0714 0.0826 0.0926 0.0400 0.0420 0.0435 0.0794 0.5882 0.2941 0.2632 0.2381 0.1818 0.1099 0.2439 0.1205 0.2500 0.1000 0.1961 0.1075 0.1818 Fast 0.0862 0.1031 0.1370 0.0680 0.0794 0.0901 0.0351 0.0380 0.0980 0.2083 0.1099 0.2174 0.0870 0.1724 0.1099 0.1695

Carpentry & Joinery Formwork to Soffit of Manhole m2 hours 1.80 0.5556 -

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Formwork to Walls of Manhole Formwork to Road Edges, straight Formwork to Road Edges, curves

UNIT FOR QUANTITY


m2 m m

UNIT FOR TIME


hours hours hours

PRODUCTION RATES (Qty per Time) Slow 11.20 Average 14.20 7.70 6.20 Fast 20.20

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.0893 Average 0.0704 0.1299 0.1613 Fast 0.0495 -

Bulk Excavation Excavation Bulking Factor, Sand/Soil Excavation Bulking Factor, Gravel Excavation Bulking Factor, Clay/Chalk Excavation Bulking Factor, Boulder Clay Excavation Bulking Factor, Rock Spoil Weight, Rock Spoil Weight, Concrete Spoil Weight, Landfill/CDG Spoil Weight, Sand Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Hard Ground % % % % % Tonnes/m3 Tonnes/m3 Tonnes/m3 Tonnes/m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 30.00 25.00 34.00 6.90 23.40 45.50 5.60 20.50 36.80 5.60 20.50 37.00 4.50 17.90 25.70 15.00 33.00 40.00 45.00 60.00 2.50 2.40 1.90 1.80 48.00 33.00 42.00 8.70 28.60 50.00 7.10 25.00 40.00 7.10 25.00 40.00 6.10 22.20 28.60 59.00 41.00 52.00 10.20 33.40 58.00 8.20 29.00 46.00 8.30 28.70 46.00 7.20 25.00 32.90 20.00 0.0333 0.0400 0.0294 0.1449 0.0427 0.0220 0.1786 0.0488 0.0272 0.1786 0.0488 0.0270 0.2222 0.0559 0.0389 0.0208 0.0303 0.0238 0.1149 0.0350 0.0200 0.1408 0.0400 0.0250 0.1408 0.0400 0.0250 0.1639 0.0450 0.0350 0.0169 0.0244 0.0192 0.0980 0.0299 0.0172 0.1220 0.0345 0.0217 0.1205 0.0348 0.0217 0.1389 0.0400 0.0304

PRODUCTION RATES

ITEM NO.

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Breaking Out Concrete Slabs, unreinforced 50-150mm Concrete Slabs, unreinforced 150-300mm Concrete Slabs, reinforced 50-150mm Concrete Slabs, reinforced 150-300mm Concrete Walls, unreinforced Concrete Walls, reinforced Concrete Foundations, unreinforced Concrete Foundations, reinforced Concrete Beams Concrete Columns Tarmac paving 20-50mm thick Tarmac paving 50-100mm thick Tarmac paving 100-150mm thick Tarmac roadway 150mm thick Brickwork, walls and columns Brickwork, foundations m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 0.3125 0.1818 0.1923 0.1099 0.2128 0.1786 0.2778 0.1852 0.1333 0.1087 0.5263 0.4762 0.4762 0.4167 0.3704 0.2439 0.1613 0.2564 0.2128 0.3030 0.1961 0.1538 0.1220 0.5882 0.2778 0.5556 0.4762 0.5263 0.2703 0.2564 0.2128 0.3226 0.2564 0.3333 0.2083 0.1786 0.1370 0.6667 0.6250 0.5882 0.7692 0.6667 2.40 2.70 3.20 5.50 5.20 9.10 4.70 5.60 3.60 5.40 7.50 9.20 1.90 2.10 2.10 4.10 6.20 3.90 4.70 3.30 5.10 6.50 8.20 1.70 3.60 1.80 2.10 1.30 1.50 1.90 3.70 3.90 4.70 3.10 3.90 3.00 4.80 5.60 7.30 1.50 1.60 1.70

Barrette Piles Rule of Thumb, overall rate by Mill Fabricate reinforcement cages Concreting barrette panels Trimming top of barrette panels Concrete Testing, Coring Test Concrete Testing, Sonic Logging Test no cage m3 no no no hours hours hours days days days 2.0000 40.00 0.2500 0.9091 0.2500 50.00 0.4167 0.2857 1.4286 0.8333 55.00 0.5000 4.00 0.0250 0.50 1.10 4.00 0.0200 2.40 3.50 0.70 2.00 0.0182 1.20

PRODUCTION RATES

ITEM NO.
Basement Excavation

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works

m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3

hours hours hours hours hours hours hours hours hours hours hours hours

6.40 5.50 5.20 4.70 12.60 11.70 10.90 9.70 18.20 16.50 15.40 13.30

8.00 6.90 6.50 5.90 15.40 14.30 13.30 11.80 20.00 18.10 16.70 15.40

9.40 8.10 7.90 8.20 18.90 16.70 15.60 14.00 23.00 20.00 19.30 17.70

0.1563 0.1818 0.1923 0.2128 0.0794 0.0855 0.0917 0.1031 0.0549 0.0606 0.0649 0.0752

0.1250 0.1449 0.1538 0.1695 0.0649 0.0699 0.0752 0.0847 0.0500 0.0552 0.0599 0.0649

0.1064 0.1235 0.1266 0.1220 0.0529 0.0599 0.0641 0.0714 0.0435 0.0500 0.0518 0.0565

Bell Ground Anchors Uncased Anchors, 10m long Top Cased Anchors, 15m long Anchors stressing no no no days days days 2.00 1.00 2.20 0.5000 1.0000 0.4545 -

Bored Piling Cycle Time, 5-20m deep Cycle Time, 20-40m deep Cycle Time, 40-70m deep Cycle Time, 70-90m deep Cycle Time, 90-135m deep Move piling setup to next location Excave shaft by grab, general fill/uppr levels Excave shaft by grab, sand/minor rubble m m no no no no no days days days days days hours hours hours 3.50 2.10 0.1250 0.1000 0.0400 0.0222 0.0167 0.2500 0.1250 0.1000 0.0400 0.0222 0.2500 8.00 10.00 25.00 45.00 60.00 4.00 8.00 10.00 25.00 45.00 2.00 0.2857 0.4762 4.00

PRODUCTION RATES

ITEM NO.

DESCRIPTION
Excave shaft by grab, marinve/aluvium Excave shaft by grab/RCD, CDT Excave shaft by grab/RCD, CDG <150 Excave shaft by RCD, CDG 150-200 Excave shaft by RCD, CDG >200/gravel Excave shaft by RCD/Chisel, corestones Excave Rock Socket by RCD, grade IV/V rock Excave Rock Socket by RCD, grade II/III rock Excave Rock Socket by RCD, tendering rate Add/remove RCD plant Add/remove RCD drill string/drill bit Remove Obstruction, above water hand hammers Remove Obstruction, below water heavy chisel Concrete Plug, RCD off/tremmie/concrete/cure/RCD on Install air lift tremmie tube Fabricate reinforcement cages Install reinforcement cages Shaft cleaning, air lifting after excavation Shaft cleaning, air lifting after cage installed Shaft concreting/extract casing 5-70m deep Shaft concreting/extract casing 70-95m deep Shaft concreting/extract casing 95-135m deep Concrete curing prior to remove telescopic casing Concrete Testing, Coring Test Concrete Testing, Sonic Logging Test Concrete Testing, Vibration Test

UNIT FOR QUANTITY


m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 2.50 0.50 1.50 1.00 0.50 0.50 0.20 0.10 0.10 0.80 0.50 0.4000 0.5000 3.20 0.4000 0.1538 2.20 Fast 0.30 0.20

PRODUCTION RATES (Time per Quantity) REMARKS Slow 60.00 Average 0.4000 2.0000 0.6667 1.0000 2.0000 2.0000 5.0000 10.0000 10.0000 2.00 5.00 1.2500 2.0000 53.00 5.00 2.50 2.00 8.0 2.0 12.0 14.0 48.0 72.0 0.3125 2.50 6.50 0.4545 Fast 3.3333 5.0000 50.00

m m

hours hours hours hours

cage no

hours hours hours hours hours hours hours hours

m no no

hours hours hours

Introduction to Costing

1.1 Introduction
Cost is important to all industry. Costs can be divided into two general classes; absolute costs and relative costs. Absolute cost measures the loss in value of assets. Relative cost involves a comparison between the chosen course of action and the course of action that was rejected. This cost of the alternative action - the action not taken - is often

The accountant is primarily concerned with the absolute cost. However, the forest engineer, the planner, the manager needs to be concerned with the alternative cost - the cost of the lost opportunity. Management has to be able to make comparisons between the policy that should be chosen and the policy that should be rejected. Such

Cost data are, of course, essential to the technique of cost prediction. However, the form in which much cost data are recorded limits accurate cost prediction to the field of comparable situations only. This limitation of accurate cost prediction may not be serious in industries where the production environment changes little from month to month or

1.2 Basic Classification of Costs


Costs are divided into two types: variable costs, and fixed costs. Variable costs vary per unit of production. For example, they may be the cost per cubic meter of wood yarded, per cubic meter of dirt excavated, etc. Fixed costs, on the other hand, are incurred only once and as additional units of production are produced, the unit costs fall.

1.3 Total Cost and Unit-Cost Formulas


As harvesting operations become more complicated and involve both fixed and variable costs, there usually is more than one way to accomplish a given task. It may be possible to change the quantity of one or both types of cost, and thus to arrive at a minimum total cost. Mathematically, the relationship existing between volume of production and

Total cost = fixed cost + variable cost output

In symbols using the first letters of the cost elements and N for the output or number of units of production, these simple formulas are C = F + NV

UC = F/N + V

1.4 Breakeven Analysis

A breakeven analysis determines the point at which one method becomes superior to another method of accomplishing some task or objective. Breakeven analysis is a common and important part of cost control.

One illustration of a breakeven analysis would be to compare two methods of road construction for a road that involves a limited amount of cut-and-fill earthwork. It would be possible to do the earthwork by hand or by bulldozer. If the manual method were adopted, the fixed costs would be low or non-existent. Payment would be done on a daily

Figure 1.1 Breakeven Example for Excavation.

If, on a set of coordinates, cost in dollars is plotted on the vertical axis and units of production on the horizontal axis, we can indicate fixed cost for any process by a horizontal line parallel to the x-axis. If variable cost per unit output is constant, then the total cost for any number of units of production will be the sum of the fixed cost and the variable

1.5 Minimum Cost Analyses

A similar, but different problem is the determination of the point of minimum total cost. Instead of balancing two methods with different fixed and variable costs, the aim is to bring the sum of two costs to a minimum. We will assume a clearing crew of 20 men is clearing road right-of-way and the following facts are available:

1. Men are paid at the rate of $0.40 per hour.

2. Time is measured from the time of leaving camp to the time of return.

3. Total walking time per man is increasing at the rate of 15 minutes per day.

4. The cost to move the camp is $50.

If the camp is moved each day, no time is lost walking, but the camp cost is $50 per day. If the camp is not moved, on the second day 15 crew-minutes are lost or $2.00. On the third day, the total walking time has increased 30 minutes, the fourth day, 45 minutes, and so on. How often should the camp be moved assuming all other things are

TABLE 1.1 Average daily total camp cost as the sum of the cost of walking time plus the cost of moving camp.

Days camp remained in location

Average daily Average daily Average total cost of cost of camp cost walking time moving camp 0 50 50

25

26

16.67

18.67

12.5

15.5

10

14

8.33

13.33

7.14

13.14

6.25

13.25

5.56

13.56

10

14

We see the average daily cost of walking time increasing linearly and the average cost of moving camp decreasing as the number of days the camp remains in one location increases. The minimum cost is obtained for leaving the camp in location 7 days (Figure 1.2). This minimum cost point should only be used as a guideline as all other things are

Figure 1.2 Costs for Camp Location Example.

PRODUCTION RATES
ITEM NO. DESCRIPTION UNIT FOR QUANTITY UNIT FOR TIME
PRODUCTION RATES (Qty per Time) Slow Average Fast PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Excavate and Remove Excavate Spoil Heaps to Transport, 0.6m3 bucket, Sand/Soil Excavate Spoil Heaps to Transport, 0.6m3 bucket, Gravel Beds Excavate Spoil Heaps to Transport, 0.6m3 bucket, Clay/Chalk Excavate Spoil Heaps to Transport, 0.6m3 bucket, Boulder Clay Excavate Spoil Heaps to Transport, 1.1m3 bucket, Sand/Soil Excavate Spoil Heaps to Transport, 1.1m3 bucket, Gravel Beds Excavate Spoil Heaps to Transport, 1.1m3 bucket, Clay/Chalk Excavate Spoil Heaps to Transport, 1.1m3 bucket, Boulder Clay Load Spoil to Barge, capacity 2,000m3 Load Spoil to Barge, capacity 1,500m3 Load Spoil to Barge, capacity 1,000m3 Spoil conveyor, 600mm belt, 150m/min m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours 14.50 15.20 12.30 11.20 25.40 25.60 22.50 18.90 20.00 20.40 18.50 16.90 30.30 31.30 27.80 24.40 260.00 25.60 25.60 23.20 21.30 35.70 37.00 33.30 30.30 0.0690 0.0658 0.0813 0.0893 0.0394 0.0391 0.0444 0.0529 0.0500 0.0490 0.0541 0.0592 0.0330 0.0319 0.0360 0.0410 8.00 6.50 5.50 0.0038 0.0391 0.0391 0.0431 0.0469 0.0280 0.0270 0.0300 0.0330

Trench Excavation Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Hard Ground Excavate and Board Trench, 0.5-1.5m deep, < 2.0m wide Excavate and Board Trench, 1.5-3.0m deep, < 2.0m wide Excavate and Board Trench, 3.0-4.5m deep, < 2.0m wide Excavate and Board Trench, 0.5-1.5m deep, > 2.0m wide Excavate and Board Trench, 1.5-3.0m deep, > 2.0m wide Excavate and Board Trench, 3.0-4.5m deep, > 2.0m wide m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 5.60 4.80 4.80 9.70 20.50 18.20 18.20 17.00 26.00 26.30 26.30 22.70 3.30 3.00 2.70 6.60 6.20 5.80 7.10 6.10 6.10 5.40 25.00 22.20 22.20 20.00 28.60 28.60 28.60 25.00 4.50 4.20 4.00 7.10 6.70 6.20 8.20 7.30 7.10 6.40 29.20 26.00 26.00 23.40 33.10 33.20 33.20 28.80 6.80 6.50 6.00 8.80 9.20 10.50 0.1786 0.2083 0.2083 0.1031 0.0488 0.0549 0.0549 0.0588 0.0385 0.0380 0.0380 0.0441 0.3030 0.3333 0.3704 0.1515 0.1613 0.1724 0.1408 0.1639 0.1639 0.1852 0.0400 0.0450 0.0450 0.0500 0.0350 0.0350 0.0350 0.0400 0.2222 0.2381 0.2500 0.1408 0.1493 0.1613 0.1220 0.1370 0.1408 0.1563 0.0342 0.0385 0.0385 0.0427 0.0302 0.0301 0.0301 0.0347 0.1471 0.1538 0.1667 0.1136 0.1087 0.0952

Spread and Level Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 5-50m to stockpile Crawler Shovel, 0.8m3 bucket, Clay/Chalk, pushed 50-120m to stockpile Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 5-50m to stockpile m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 55 13.90 7.60 14.20 7.60 12.70 6.90 11.60 6.30 23.80 16.70 25.00 17.20 21.70 15.10 19.60 13.70 18.60 24.40 20.40 9.50 20.40 10.20 18.40 8.90 16.90 8.20 28.50 18.50 32.00 19.30 27.50 16.90 24.50 15.90 28.50 37.20 25.00 12.60 25.60 12.80 23.20 11.60 21.30 10.40 35.70 20.40 37.00 21.20 33.30 18.80 30.30 17.50 38.50 50.00 0.0719 0.1316 0.0704 0.1316 0.0787 0.1449 0.0862 0.1587 0.0420 0.0599 0.0400 0.0581 0.0461 0.0662 0.0510 0.0730 0.0538 0.0410 0.0490 0.1053 0.0490 0.0980 0.0543 0.1124 0.0592 0.1220 0.0351 0.0541 0.0313 0.0518 0.0364 0.0592 0.0408 0.0629 0.0351 0.0269 0.0400 0.0794 0.0391 0.0781 0.0431 0.0862 0.0469 0.0962 0.0280 0.0490 0.0270 0.0472 0.0300 0.0532 0.0330 0.0571 0.0260 0.0200

Crawler Shovel, 0.8m3 bucket, Boulder Clay, pushed 50-120m to stockpile m3 Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Sand/Soil, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Gravel, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Gravel, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 5-50m to stockpile Crawler Shovel, 1.2m3 bucket, Clay/Chalk, pushed 50-120m to stockpile Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 5-50m to stockpile m3 m3 m3 m3 m3 m3 m3

Crawler Shovel, 1.2m3 bucket, Boulder Clay, pushed 50-120m to stockpile m3 Crawler Shovel, 0.6m3 bucket, 50-200m2, Sand/Soil Crawler Shovel, 0.6m3 bucket, over 200m2, Sand/Soil m3 m3

PRODUCTION RATES
ITEM NO. DESCRIPTION
Crawler Shovel, 0.6m3 bucket, 50-200m2, Gravel Crawler Shovel, 0.6m3 bucket, over 200m2, Gravel Crawler Shovel, 0.6m3 bucket, 50-200m2, Hardcore Crawler Shovel, 0.6m3 bucket, over 200m2, Hardcore Crawler Shovel, 0.6m3 bucket, 50-200m2, Boulder Clay Crawler Shovel, 0.6m3 bucket, over 200m2, Boulder Clay Crawler Shovel, 1.2m3 bucket, 50-200m2, Sand/Soil Crawler Shovel, 1.2m3 bucket, over 200m2, Sand/Soil Crawler Shovel, 1.2m3 bucket, 50-200m2, Gravel Crawler Shovel, 1.2m3 bucket, over 200m2, Gravel Crawler Shovel, 1.2m3 bucket, 50-200m2, Hardcore Crawler Shovel, 1.2m3 bucket, over 200m2, Hardcore Crawler Shovel, 1.2m3 bucket, 50-200m2, Boulder Clay Crawler Shovel, 1.2m3 bucket, over 200m2, Boulder Clay

UNIT FOR QUANTITY


m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 18.90 24.20 15.80 19.20 17.20 22.20 43.50 55.50 43.80 55.50 37.10 47.60 43.80 55.60 Average 28.60 37.20 23.50 29.60 26.40 33.80 48.00 61.10 48.30 61.10 40.30 51.60 45.70 59.10 Fast 38.40 50.00 31.20 40.00 35.70 45.40 52.60 66.70 52.90 66.70 43.50 55.60 47.60 62.50

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.0529 0.0413 0.0633 0.0521 0.0581 0.0450 0.0230 0.0180 0.0228 0.0180 0.0270 0.0210 0.0228 0.0180 Average 0.0350 0.0269 0.0426 0.0338 0.0379 0.0296 0.0208 0.0164 0.0207 0.0164 0.0248 0.0194 0.0219 0.0169 Fast 0.0260 0.0200 0.0321 0.0250 0.0280 0.0220 0.0190 0.0150 0.0189 0.0150 0.0230 0.0180 0.0210 0.0160

Small or Deep Excavation Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Hard Ground m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours 6.70 3.20 3.30 3.30 8.20 7.10 6.50 6.30 12.20 10.20 9.70 6.10 8.40 4.50 4.10 4.10 10.00 8.70 8.30 7.70 13.30 11.10 10.50 6.70 9.90 5.00 5.20 5.20 11.70 10.20 9.40 9.10 15.40 12.90 12.10 7.70 0.1493 0.3125 0.3030 0.3030 0.1220 0.1408 0.1538 0.1587 0.0820 0.0980 0.1031 0.1639 0.1190 0.2222 0.2439 0.2439 0.1000 0.1149 0.1205 0.1299 0.0752 0.0901 0.0952 0.1493 0.1010 0.2000 0.1923 0.1923 0.0855 0.0980 0.1064 0.1099 0.0649 0.0775 0.0826 0.1299

Rock Tunnels Excavation, non explosive chemical method, cycle time Excavation, non explosive chemical method, Class I Granite Excavation, non explosive chemical method, Class II Granite Excavation, non explosive chemical method, Class III Granite m3 m3 m3 mins cycle cycle cycle 0.30 2.00 1.20 0.90 2.60 1.40 1.20 2.90 1.80 8.00 3.3333 0.5000 0.8333 6.00 1.1111 0.3846 0.7143 5.50 0.8333 0.3448 0.5556

Bulk Excavation Excavation Bulking Factor, Sand/Soil Excavation Bulking Factor, Gravel Excavation Bulking Factor, Clay/Chalk Excavation Bulking Factor, Boulder Clay Excavation Bulking Factor, Rock Spoil Weight, Rock Spoil Weight, Concrete Spoil Weight, Landfill/CDG Spoil Weight, Sand Rail Mounted Grab, 2.0m3 bucket 2.4min lift cycle Crane Mounted Clamshell Grab, 2.0m3 bucket 2.9min lift cycle Crane Mounted Clamshell Grab, 2.5m3 bucket 2.9min lift cycle Hydraulic Excavator, 0.3m3 bucket, Sand/Soil Hydraulic Excavator, 0.4m3 bucket, Sand/Soil Hydraulic Excavator, 0.5m3 bucket, Sand/Soil % % % % % Tonnes/m3 Tonnes/m3 Tonnes/m3 Tonnes/m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours 56 30.00 25.00 34.00 6.90 23.40 45.50 15.00 33.00 40.00 45.00 60.00 2.50 2.40 1.90 1.80 48.00 33.00 42.00 8.70 28.60 50.00 59.00 41.00 52.00 10.20 33.40 58.00 20.00 0.0333 0.0400 0.0294 0.1449 0.0427 0.0220 0.0208 0.0303 0.0238 0.1149 0.0350 0.0200 0.0169 0.0244 0.0192 0.0980 0.0299 0.0172

PRODUCTION RATES
ITEM NO. DESCRIPTION
Hydraulic Excavator, 0.3m3 bucket, Gravel Beds Hydraulic Excavator, 0.4m3 bucket, Gravel Beds Hydraulic Excavator, 0.5m3 bucket, Gravel Beds Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk Hydraulic Excavator, 0.3m3 bucket, Hard Ground Hydraulic Excavator, 0.4m3 bucket, Hard Ground Hydraulic Excavator, 0.5m3 bucket, Hard Ground

UNIT FOR QUANTITY


m3 m3 m3 m3 m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 5.60 20.50 36.80 5.60 20.50 37.00 4.50 17.90 25.70 Average 7.10 25.00 40.00 7.10 25.00 40.00 6.10 22.20 28.60 Fast 8.20 29.00 46.00 8.30 28.70 46.00 7.20 25.00 32.90

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1786 0.0488 0.0272 0.1786 0.0488 0.0270 0.2222 0.0559 0.0389 Average 0.1408 0.0400 0.0250 0.1408 0.0400 0.0250 0.1639 0.0450 0.0350 Fast 0.1220 0.0345 0.0217 0.1205 0.0348 0.0217 0.1389 0.0400 0.0304

Basement Excavation Hydraulic Excavator, 0.3m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.3m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.3m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.3m3 bucket, Hard Ground - Basement Works Hydraulic Excavator, 0.4m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.4m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.4m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.4m3 bucket, Hard Ground - Basement Works Hydraulic Excavator, 0.5m3 bucket, Sand/Soil - Basement Works Hydraulic Excavator, 0.5m3 bucket, Gravel Beds - Basement Works Hydraulic Excavator, 0.5m3 bucket, Clay/Chalk - Basement Works Hydraulic Excavator, 0.5m3 bucket, Hard Ground - Basement Works m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours 6.40 5.50 5.20 4.70 12.60 11.70 10.90 9.70 18.20 16.50 15.40 13.30 8.00 6.90 6.50 5.90 15.40 14.30 13.30 11.80 20.00 18.10 16.70 15.40 9.40 8.10 7.90 8.20 18.90 16.70 15.60 14.00 23.00 20.00 19.30 17.70 0.1563 0.1818 0.1923 0.2128 0.0794 0.0855 0.0917 0.1031 0.0549 0.0606 0.0649 0.0752 0.1250 0.1449 0.1538 0.1695 0.0649 0.0699 0.0752 0.0847 0.0500 0.0552 0.0599 0.0649 0.1064 0.1235 0.1266 0.1220 0.0529 0.0599 0.0641 0.0714 0.0435 0.0500 0.0518 0.0565

Working Platforms Metal KwikStage, 5 Boards with 2m lifts Metal KwikStage, 5 Boards with 3m lifts Metal KwikStage, House Scaffold with 3 lifts Metal Tube and Fittings, 5-6 Boards wide Tube and Fitting Platforms, 50-250m3 Tube and Fitting Platforms, 250-1000m3 Tube and Fitting Platforms, over 1000m3 Tube and Fitting Platforms, striking m run m run m run m run m3 m3 m3 % x erect hours hours hours hours hours hours hours 11.10 9.10 2.80 3.20 10.60 18.50 24.50 11.90 10.00 3.20 3.70 12.50 22.50 30.00 200.00 12.50 10.50 3.80 4.60 18.50 24.50 33.50 0.0901 0.1099 0.3571 0.3125 0.0943 0.0541 0.0408 0.0840 0.1000 0.3125 0.2703 0.0800 0.0444 0.0333 200.00 0.0800 0.0952 0.2632 0.2174 0.0541 0.0408 0.0299 -

Underpinning Concrete Pinning, 4th or 5th pin cycles Brickwork Pinning, 1.0 brick thick Brickwork Pinning, 1.5 brick thick Brickwork Pinning, 2.0 brick thick Wedge and Pin Method, 102mm wall Wedge and Pin Method, 215mm wall Wedge and Pin Method, 317mm wall m m2 m2 m2 m m m day hours hours hours hours hours hours 0.10 1.20 0.40 0.30 0.20 0.80 0.70 0.50 2.20 0.70 10.0000 0.8333 2.5000 3.3333 5.0000 1.2500 1.4286 2.0000 0.4545 1.4286 -

Tower Cranes Erect and Setup 50m gib Dismantle 50m gib Lifting, Reinforcement Bins and Cages, 1st 15m lift Lifting, Reinforcement Bins and Cages, above 1st 15m lift Lifting, Crane Tracking Time lift 15m m days days mins mins seconds 57 11.00 10.00 3.20 0.50 3.30 7.50

PRODUCTION RATES
ITEM NO. DESCRIPTION UNIT FOR QUANTITY UNIT FOR TIME
PRODUCTION RATES (Qty per Time) Slow Average Fast PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Soil Mix Walls Three Auger Drill, cement and cure m days 3.80 4.50 6.40 0.2632 0.2222 0.1563

Slurry Mix Walls Crane grab, cement/bentonite and sheet piles m days 1.80 2.50 3.40 0.5556 0.4000 0.2941

Site Clearance Shrubs and Bushes, dig up and removal Turf, lifting and removal Trees, small sizes and shrubs Trees and Shrubs, 500mm - 900mm girth Trees and Shrubs, 900mm - 1200mm girth Trees and Shrubs, 1200mm - 1500mm girth Hedges and Roots, 0.5-1.0m high Hedges and Roots, 1.0-1.5m high Hedges and Roots, 1.5-2.0m high m2 m2 m2 no no no m m m hours hours hours hours hours hours hours hours hours 25.00 2.90 14.00 0.0556 0.0455 0.0385 0.90 0.80 0.60 38.00 0.0400 0.3448 0.0714 18.00 22.00 26.00 1.1111 1.2500 1.6667 0.0263 -

Sheet Piling Vibro/Drop Hammer, 10m deep Sand Vibro/Drop Hammer, 35m deep Sand m m days days 3.50 55.00 32.00 60.00 10.50 0.2857 0.0182 0.0313 0.0167 0.0952

Secant Piling Construct 30m dia cofferdam, 255 piles/concrete base weeks 12.00 -

Rule of Thumb Site Investigation Pre Drilling Ground Excavation, Hydraulic Backhoe Bored Piling, 25-70m deep Formwork Fixing Reinforcement Fixing Concrete Placement Scaffold Erection, Steel Falsework Blockwork Laying Plastering and Rendering Blockwork Laying Stonework Cladding Window Glazing Granolithic Flooring Floor Screeding Floor Screeding no. m3 no. m2 Tonnes m3 m3 m2 m2 m2 m2 m2 m2 m2 m2 days days days days days days days days days days days hours hours hours days 58 7.00 0.1000 0.2000 0.2500 50.00 0.1250 12.00 0.70 16.00 140.00 7.00 12.00 12.00 5.10 1.50 4.50 4.50 60.00 17.50 0.1667 0.3333 5.00 10.00 0.1429 4.00 0.0200 8.00 0.0833 1.4286 0.0625 0.0071 0.1429 0.0833 0.0833 0.1961 0.6667 0.2222 0.2222 0.0167 3.00 6.00 0.0571 -

PRODUCTION RATES
ITEM NO.
Ceramic Wall Tiling

DESCRIPTION

UNIT FOR QUANTITY


m2

UNIT FOR TIME


hours

PRODUCTION RATES (Qty per Time) Slow Average 1.50 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.6667 Fast -

Removable Anchors Drill 30m shaft Install strands/setup anchor Grout in strands hours hours hours 7.00 6.00 2.00 -

NATM Tunnels Standard Advance Method, used on tunnels with max diameter Half Face Advance Method, used on tunnels with max diameter Double side Drift Advance Method, used on tunnels with diameter over Double side Drift Advance Method, used on tunnels with diameter over Excavation, London Clay, internal diameter under 7.0m Excavation, London Clay, internal diameter 7.0-10.0m Excavation, London Clay, internal diameter over 10.0m Excavation, Woolwich/Reading Beds, internal diameter 2.0-7.0m Excavation, Woolwich/Reading Beds, internal diameter 7.0-10.0m Excavation, Woolwich/Reading Beds, internal diameter over 10.0m Excavation, London Clay, Inclined Tunnels, diameter 2.0-7.0m Excavation, London Clay, Inclined Tunnels, diameter 7.0-10.0m Excavation, London Clay, Vertical Shafts, diameter 2.0-9.0m Excavation, London Clay, Vertical Shafts, diameter 9.0-15.0m Excavation, London Clay, Circulation Halls Excavation, London Clay, Junction Excavation Mucking Capacity, 1 access with 2 crews Mucking Capacity, 1 access with 4 crews Mucking Capacity, 2 access with 4 crews Sprayed Secondary Lining, Tunnels, diameter under 6.5m Sprayed Secondary Lining, Tunnels, diameter over 6.5m Sprayed Secondary Lining, Inclined Tunnels, diameter under 6.5m Sprayed Secondary Lining, Inclined Tunnels, diameter over 6.5m Sprayed Secondary Lining, Vertical Shafts, diameter under 6.5m Sprayed Secondary Lining, Vertical Shafts, diameter over 6.5m Sprayed Secondary Lining, Circulation Halls, diameter under 11.0m Sprayed Secondary Lining, Intermediate Landing Tunnels with columns m m m m m m m m m m m m m m m of circumf m m3 m3 m3 m m m m m m m m days days days days days days days days days days days days days days days days days days days days days days days days days days days days days days 3.20 3.30 2.20 1.20 1.70 1.60 190.00 255.00 382.00 2.10 1.50 1.50 1.00 1.80 2.20 1.50 0.50 1.00 0.50 0.80 2.50 1.50 1.00 1.50 7.00 10.00 10.00 10.00 2.90 2.00 1.30 1.80 1.50 1.00 2.00 1.00 1.50 1.00 1.00 0.20 225.00 300.00 450.00 2.50 2.00 2.00 1.50 2.00 2.50 2.00 2.00 2.10 0.20 8.40 25.00 4.00 3.90 2.50 1.50 1.5 2.0 1.5 3.2 2.2 2.2 2.6 1.2 279.0 366.0 549.0 2.8 2.4 2.3 1.9 2.5 3.1 2.3 2.1 2.3 0.3 12.0 4.9 4.2 2.7 1.7 3.20 2.50 0.4000 0.6667 1.0000 0.6667 0.6667 2.0000 1.0000 2.0000 1.2500 0.0053 0.0039 0.0026 0.4762 0.6667 0.6667 1.0000 0.5556 0.4545 0.5882 0.6250 0.3125 0.3030 0.4545 0.8333 0.3448 0.5000 0.7692 0.5556 0.6667 1.0000 0.5000 1.0000 0.6667 1.0000 1.0000 5.0000 0.0044 0.0033 0.0022 0.4000 0.5000 0.5000 0.6667 0.5000 0.4000 0.5000 0.5000 0.4762 5.0000 0.1190 0.2500 0.2564 0.4000 0.6667 0.3125 0.4000 -

Sprayed Secondary Lining, Intermediate Landing Tunnels without columns m Sprayed Secondary Lining, Tunnel Junctions m

Insitu Permanent Lining, 12m bays, 350-400mm reinforced with PCV backingm Insitu Permanent Lining, extra over excavate/lining time to allow for permanent %lining Excavate and Line Cycle Time , Running Tunnels Excavate and Line Cycle Time, Station Access Adits Excavate and Line Cycle Time, Concourse Tunnels Excavate and Line Cycle Time, Escalator Tunnels m m m m

Fencing Works Site Hoarding, timber posts, plywood nailed to horizontal rails Post Erection, Timber / Metal, dig, erect, fix Post Erection, Concrete, dig, erect, fix Fence Erection, Chainlink, posts at 1.5m Fence Erection, Chainlink, posts at 2.0m Fence Erection, Chainlink, posts at 3.0m Fence Erection, Chestnut Pailings, posts at 1.5m m no no m m m m hours hours hours hours hours hours hours 59 1.00 3.30 3.20 1.20 4.50 4.00 4.20 4.40 5.50 23.80 1.0000 0.3030 0.3125 0.8333 0.2222 0.2500 0.2381 0.2273 0.1818 0.0420 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
Fence Erection, Chestnut Pailings, posts at 2.0m Fence Erection, Chestnut Pailings, posts at 3.0m Fence Erection, Barbed Wire, posts at 1.5m Fence Erection, Barbed Wire, posts at 2.0m Fence Erection, Barbed Wire, posts at 3.0m Gate Erection, Chainlink on frame

UNIT FOR QUANTITY


m m m m m no

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 33.30 41.60 71.40 100.00 125.00 4.10 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.0300 0.0240 0.0140 0.0100 0.0080 0.2439 Fast -

Dewatering Setup small 2 hole system Setup large 15 hole system Calculate system times per pump Setup Recharge System pump pump days days days days 0.4000 0.2857 10.00 8.00 21.00 2.50 3.50 6.00

Demolition Weight, Structural Steel Remove & Cart away, Ceramic Wall Tiles Remove & Cart away, Wallpaper, 1 layer Remove & Cart away, Wallpaper, 2 layers Remove & Cart away, Wallpaper, 3 layers Remove & Cart away, Lathe and Plaster Ceilings Remove & Cart away, Plaster to Walls Remove & Cart away, External Render Remove & Cart away, Floor Screed Remove & Cart away, Concrete Paving Remove & Cart away, Brickwork Walls, 1.0 brick thick Remove & Cart away, Brickwork Walls, 0.5 brick thick Remove & Cart away, Brickwork Walls, Sand/Lime Mortar Remove & Cart away, Fireplace and Hearth Remove & Cart away, Floor Boards Remove & Cart away, Skirting, Architrave, Dado rail etc Remove & Cart away, Staircase Remove & Cart away, Windows, 0-1m2 Remove & Cart away, Windows 1-2m2 Remove & Cart away, Windows 2-3m2 Remove & Cart away, Doors Remove & Cart away, Door Frame Remove & Cart away, Floor and Ceiling Joists Remove & Cart away, Wall Plates Remove & Cart away, Iron Bath Remove & Cart away, Wash Basin/Sink Remove & Cart away, Pipework including brackets etc Tonnes m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 100 no m2 m no no no no no no m m no no m m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 3.20 2.10 2.00 2.50 2.50 8.70 7.10 5.70 4.60 3.10 3.90 3.20 4.00 1.30 2.60 0.5556 0.5263 6.20 16.50 0.1370 1.6667 1.2500 1.1111 3.3333 10.0000 0.9091 0.2564 0.7143 1.2500 6.10 5.00 5.90 3.40 0.5000 0.3125 0.4762 0.4000 0.4000 0.1149 0.1408 0.1754 0.2174 0.3226 0.2564 0.3125 0.2500 0.7692 0.3846 1.80 1.90 0.1613 0.0606 7.30 0.60 0.80 0.90 0.30 0.10 1.10 3.90 1.40 0.80 0.1639 0.2941 0.2000 0.1695 -

Breaking Out Concrete Slabs, unreinforced 50-150mm Concrete Slabs, unreinforced 150-300mm Concrete Slabs, reinforced 50-150mm Concrete Slabs, reinforced 150-300mm Concrete Walls, unreinforced Concrete Walls, reinforced Concrete Foundations, unreinforced Concrete Foundations, reinforced Concrete Beams Concrete Columns m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours 60 0.3125 0.1818 0.1923 0.1099 0.2128 0.1786 0.2778 0.1852 0.1333 0.1087 0.2439 0.1613 0.2564 0.2128 0.3030 0.1961 0.1538 0.1220 0.5263 0.2703 0.2564 0.2128 0.3226 0.2564 0.3333 0.2083 0.1786 0.1370 3.20 5.50 5.20 9.10 4.70 5.60 3.60 5.40 7.50 9.20 4.10 6.20 3.90 4.70 3.30 5.10 6.50 8.20 1.90 3.70 3.90 4.70 3.10 3.90 3.00 4.80 5.60 7.30

PRODUCTION RATES
ITEM NO. DESCRIPTION
Tarmac paving 20-50mm thick Tarmac paving 50-100mm thick Tarmac paving 100-150mm thick Tarmac roadway 150mm thick Brickwork, walls and columns Brickwork, foundations

UNIT FOR QUANTITY


m3 m3 m3 m3 m3 m3

UNIT FOR TIME


hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 0.5263 0.4762 0.4762 0.4167 0.3704 Average 0.5882 0.2778 0.5556 0.4762 Fast 0.6667 0.6250 0.5882 0.7692 0.6667

PRODUCTION RATES (Time per Quantity) REMARKS Slow 1.90 2.10 2.10 2.40 2.70 Average 1.70 3.60 1.80 2.10 1.30 1.50 Fast 1.50 1.60 1.70

Site Investigation Pre Drilling, Rercussive or Rotary, soft deposits Pre Drilling, Wash Boring, grade V/IV rock Pre Drilling, Triple Tube Sampling, grade V/IV rock Pre Drilling, Rotary, grade III/II rock Pre Drilling, Triple Tube Sampling, grade III/II rock m m m m m hours hours hours hours hours 8.00 2.50 0.40 0.20 0.10 10.00 3.20 0.80 0.50 0.40 14.00 3.90 0.90 0.70 0.70 0.1250 0.4000 2.5000 5.0000 10.0000 0.1000 0.3125 1.2500 2.0000 2.5000 0.0714 0.2564 1.1111 1.4286 1.4286

Waterproofing Asphalt coatings, horizontal surfaces Asphalt coatings, vertical surfaces Bituminous Brushed application, 2 coats Bituminous Brushed application, 3 coats Bituminous Sheets, horizontal surfaces Bituminous Sheets, vertical surfaces Polythene Sheets, horizontal surfaces Bentonite Sheets, horizontal surfaces Bentonite Sheets, vertical surfaces Epoxy Based application, 1 coat Epoxy Based application, 2 coat m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours 18.70 11.20 3.50 1.20 4.80 3.30 3.80 3.30 4.20 1.70 5.00 3.50 4.00 3.50 20.00 25.00 15.00 75.00 38.00 31.30 17.30 5.80 2.20 6.30 4.40 4.80 4.20 0.2857 0.8333 0.2083 0.3030 0.2632 0.3030 0.0535 0.0893 0.2381 0.5882 0.2000 0.2857 0.2500 0.2857 0.0500 0.0400 0.0667 0.0133 0.0263 0.1724 0.4545 0.1587 0.2273 0.2083 0.2381 0.0319 0.0578 -

Trackwork FST Floating Track Slab, side restraints FST Floating Track Slab, resin pads FST Floating Track Slab, slab units PCBT - Pre-cast Concrete Block Track, in Bored Tunnels PCBT - Pre-cast Concrete Block Track, in Cut and Cover Tunnels PCBT - Pre-cast Concrete Block Track, in Station Tunnels IST - Isolated Slab Track, in Bored Tunnels IST - Isolated Slab Track, in Cut and Cover Tunnels IST - Isolated Slab Track, in Station FST - Floating Slab Track, in Station Ballasted Track, in Mainline Ballasted Track, in Depot Non-Ballasted Track, in Depot Embedded / Paved Track, in Depot Heavy Maintenance / Train Wash Track, in Depot Maintenance Pit, in Depot Siding Trackwork, in Depot m m m m m m m m m m m m m m m m m days days days days days days days days days days days days days days days days days 8.50 3.60 57.00 9.60 10.20 10.60 17.10 41.00 35.00 35.00 20.00 34.00 29.00 4.60 71.00 28.00 12.80 71.00 29.00 52.00 38.00 17.40 5.70 115.00 0.1042 0.0980 0.0943 0.0585 0.2778 0.0175 0.1176 0.0244 0.0286 0.0286 0.0500 0.0294 0.0345 0.2174 0.0141 0.0357 0.0781 0.0141 0.0345 0.0192 0.0263 0.1754 0.0087 0.0575 -

Structural Steelwork Simple Universal Beam Steel Bridge, erect support steel H frames no days 61 0.8333 1.2000 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
Simple Universal Beam Steel Bridge, erect 15m truss

UNIT FOR QUANTITY


m

UNIT FOR TIME


days

PRODUCTION RATES (Qty per Time) Slow Average 3.30 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.3030 Fast -

Steel Strutting Horizontal heavy duty strutting Diagonal heavy duty strutting no no days days 0.5000 0.1667 2.00 6.00 -

Reinforcement Ratios Pile Cap, Concrete m3 x Ratio = Rebar Tonnes Base Slab, Concrete m3 x Ratio = Rebar Tonnes Suspended Slab, Concrete m3 x Ratio = Rebar Tonnes Platform Slab, Concrete m3 x Ratio = Rebar Tonnes Columns, Concrete m3 x Ratio = Rebar Tonnes Walls, Concrete m3 x Ratio = Rebar Tonnes % ratio % ratio % ratio % ratio % ratio % ratio 15.80 14.70 14.80 13.20 20.60 15.60 18.70 15.00 28.70 14.10 25.60 -

Reinforcement Slabs/Foundations, steelfixing, 6mm Slabs/Foundations, steelfixing, 8mm Slabs/Foundations, steelfixing, 10mm Slabs/Foundations, steelfixing, 12mm Slabs/Foundations, steelfixing, 16mm Slabs/Foundations, steelfixing, 20mm Slabs/Foundations, steelfixing, 25mm Slabs/Foundations, steelfixing, 32mm Slabs/Foundations, steelfixing, 40mm Slabs/Foundations, steelfixing, 50mm Beams/Columns, steelfixing, 6mm Beams/Columns, steelfixing, 8mm Beams/Columns, steelfixing, 10mm Beams/Columns, steelfixing, 12mm Beams/Columns, steelfixing, 16mm Beams/Columns, steelfixing, 20mm Beams/Columns, steelfixing, 25mm Beams/Columns, steelfixing, 32mm Beams/Columns, steelfixing, 40mm Beams/Columns, steelfixing, 50mm Walls, steelfixing, 6mm Walls, steelfixing, 8mm Walls, steelfixing, 10mm Walls, steelfixing, 12mm Walls, steelfixing, 16mm Walls, steelfixing, 20mm Walls, steelfixing, 25mm Walls, steelfixing, 32mm Walls, steelfixing, 40mm Walls, steelfixing, 50mm Staircases, steelfixing, 6mm Staircases, steelfixing, 8mm Staircases, steelfixing, 10mm Staircases, steelfixing, 12mm Staircases, steelfixing, 16mm tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne tonne hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 62 0.0248 0.0355 0.0444 0.0592 0.0833 0.1087 0.1449 0.1754 0.1887 0.1923 0.0181 0.0258 0.0339 0.0427 0.0602 0.0806 0.1010 0.1471 0.1639 0.1639 0.0243 0.0342 0.0441 0.0568 0.0806 0.1064 0.1351 0.1429 0.1563 0.1887 0.0204 0.0291 0.0376 0.0478 0.0685 0.0260 0.0372 0.0485 0.0613 0.0870 0.1163 0.1493 0.1818 0.1961 0.2041 0.0189 0.0270 #VALUE! 0.0446 0.0633 0.0840 0.1087 0.1515 0.1695 0.1695 0.0245 0.0350 0.0455 0.0578 0.0820 0.1087 0.1389 0.1471 0.1639 0.1961 0.0208 0.0298 0.0388 0.0490 0.0694 0.0274 0.0388 0.0498 0.0649 0.0917 0.1220 0.1538 0.1923 0.2041 0.2174 0.0198 0.0285 0.0372 0.0457 0.0662 0.0885 0.1149 0.1613 0.1786 0.1786 0.0256 0.0365 0.0472 0.0592 0.0847 0.1149 0.1429 0.1563 0.1695 0.2083 0.0220 0.0313 0.0412 0.0513 0.0725 40.30 28.20 22.50 16.90 12.00 9.20 6.90 5.70 5.30 5.20 55.40 38.80 29.50 23.40 16.60 12.40 9.90 6.80 6.10 6.10 41.20 29.20 22.70 17.60 12.40 9.40 7.40 7.00 6.40 5.30 48.90 34.40 26.60 20.90 14.60 38.40 26.90 20.60 16.30 11.50 8.60 6.70 5.50 5.10 4.90 52.80 37.00 28.4 22.40 15.80 11.90 9.20 6.60 5.90 5.90 40.80 28.60 22.00 17.30 12.20 9.20 7.20 6.80 6.10 5.10 48.00 33.60 25.80 20.40 14.40 36.50 25.80 20.10 15.40 10.90 8.20 6.50 5.20 4.90 4.60 50.60 35.10 26.90 21.90 15.10 11.30 8.70 6.20 5.60 5.60 39.10 27.40 21.20 16.90 11.80 8.70 7.00 6.40 5.90 4.80 45.50 31.90 24.30 19.50 13.80

PRODUCTION RATES
ITEM NO. DESCRIPTION
Staircases, steelfixing, 20mm Staircases, steelfixing, 25mm

UNIT FOR QUANTITY


tonne tonne

UNIT FOR TIME


hours hours

PRODUCTION RATES (Qty per Time) Slow 0.0885 0.1163 Average 0.0926 0.1190 Fast 0.0952 0.1220

PRODUCTION RATES (Time per Quantity) REMARKS Slow 11.30 8.60 Average 10.80 8.40 Fast 10.50 8.20

Post Tensioning Lag for Initial Stress Tensioning after 1st bay cast Lag for Final Stress Tensioning after Initial Stress hrs hrs 48.00 120.00 -

Metal Decking Metal Decking, large areas Metal Decking, small or complicated Titanium Sheeted Roofs Copper Roofs, flat work Copper Roofs, sloping work Zinc Roofs, flat work Zinc Roofs, sloping work Aluminium Roofs, flat work Aluminium Roofs, sloping work Lead Roofs, flat work Lead Roofs, sloping work Lead Roofs, dormer cheeks Lead Roofs, flat gutters Lead Roofs, flat copings Lead Roofs, stepped gutters Lead Roofs, shaped copings Lead Roofs, cover step flashings Lead Roofs, rooflight flashings Lead Roofs, domed roof coverings m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m m m no m2 days days days days days days days days days days days days days days days days days days days 70.00 28.00 9.50 3.00 2.70 2.40 2.10 2.80 1.90 2.50 2.10 1.30 88.00 76.00 3.50 3.30 3.20 0.80 0.70 0.0143 0.0357 0.1053 0.3333 0.3704 0.4167 0.4762 0.3571 0.5263 0.4000 0.4762 0.7692 0.0114 0.0132 0.2857 0.3030 0.3125 1.2500 1.4286 -

Land Drains Land Drains, Concrete, butt jointed, under 150mm dia, 0-5m run Land Drains, Concrete, butt jointed, under 150mm dia, 5-30m run Land Drains, Concrete, butt jointed, under 150mm dia, over 30m run Land Drains, Concrete, butt jointed, 150-225mm dia, 0-5m run Land Drains, Concrete, butt jointed, 150-225mm dia, 5-30m run Land Drains, Concrete, butt jointed, 150-225mm dia, over 30m run Land Drains, Concrete, butt jointed, 225-300mm dia, 0-5m run Land Drains, Concrete, butt jointed, 225-300mm dia, 5-30m run Land Drains, Concrete, butt jointed, 225-300mm dia, over 30m run m m m m m m m m m hours hours hours hours hours hours hours hours hours 11.60 14.10 18.80 8.40 10.20 11.90 5.40 6.50 7.90 0.0862 0.0709 0.0532 0.1190 0.0980 0.0840 0.1852 0.1538 0.1266 -

Formwork Pilecaps, < 0.7m2 Pilecaps, 0.7-2.5m2 Pilecaps, 2.5-3.0m2 Pilecaps, > 3.0m2 Ground Beams, < 0.7m2 Ground Beams, 0.7-1.5m2 Ground Beams, 1.5-3.0m2 Ground Beams, 3.0-5.0m2 Elevated Plain Slab Soffit Beams, on erected falsework, width 100-200mm Beams, on erected falsework, width 200-300mm m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours 63 0.90 1.60 2.00 2.30 1.10 1.70 1.80 2.50 0.60 0.90 1.00 1.60 2.00 2.30 2.50 1.70 1.80 2.50 2.60 0.80 1.00 1.10 2.00 2.30 2.50 3.10 1.80 2.50 2.60 3.50 1.20 1.10 1.30 1.1111 0.6250 0.5000 0.4348 0.9091 0.5882 0.5556 0.4000 1.6667 1.1111 1.0000 0.6250 0.5000 0.4348 0.4000 0.5882 0.5556 0.4000 0.3846 1.2500 1.0000 0.9091 0.5000 0.4348 0.4000 0.3226 0.5556 0.4000 0.3846 0.2857 0.8333 0.9091 0.7692

PRODUCTION RATES
ITEM NO. DESCRIPTION
Beams, on erected falsework, width 300-500mm Beams, on erected falsework, width 500-750mm Beams, on erected falsework, width over 750mm Walls, Construct Kickers Walls, Fully Framed Formwork/Struts, 1.0-2.0m2 Walls, Fully Framed Formwork/Struts, 2.0-5.0m2 Walls, Fully Framed Formwork/Struts, over 5.0m2 Walls, StoriForm Shutters, 1.0-3.0m2 Walls, StoriForm Shutters, 3.0-5.0m2 Walls, StoriForm Shutters, 5.0-10.0m2 Walls, StoriForm Shutters, 10.0-15.0m2 Walls, StoriForm Shutters, over 15.0m2 Ground Slabs Columns, Construct Kickers, direct to slab Columns, Construct Kickers, suspended from soffit slab Columns, Square Sides, Timber Clamp/Prop, csa < 0.1m2 Columns, Square Sides, Timber Clamp/Prop, csa 0.1-0.4m2 Columns, Square Sides, Timber Clamp/Prop, csa over 0.4m2 Columns, Square Sides, Steel Forms, 1.5 x 1.5 x 9.0m high Columns, Square Sides, Steel Forms, 2.0 x 2.0 x 9.0m high Columns, Square Sides, Steel Forms, 2.0 x 4.0 x 9.0m high Columns, Round Sides, Sacrificial Plastic Mould, 3.0-4.0m dia Columns, Round Sides, Steel Mould, 3.0-4.0m dia Columns, Sloping Column Heads, extra over rate Staircases, Stair Soffit, Sloping Staircases, Stair Soffit, Flat Landing Staircases, Wall Strings Staircases, Open Strings Staircases, Riser Boards fixed to strings Staircases, Risers fixed to Strings Waffle Flooring, 2.4m grid Shaft Slip Forming Table Form, Aluminum System, 400m2 bays Table Form, H-Frame Steel Falsework, 400m2 bays Tunnel Forms, Wall and Slab poured as one Hollorib Decking, lay deck Hollorib Decking, shear connecting studs Stop Ends, no perforations Stop Ends, minor perforations Stop Ends, dense perforations Box Outs, 0.01-0.05m2 Box Outs, over 0.05m2 Dummy Frames, under 3.0m2 Dummy Frames, over 3.0m2

UNIT FOR QUANTITY


m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 no no m2 m2 m2 m2 m2 m2 m2 m2 no m2 m2 m2 m2 m2 m2 m2 mm m2 m2 m2 m2 m2 m2 m2 m2 no no no no

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 1.20 1.50 1.40 5.30 0.90 1.00 1.20 1.00 1.90 2.30 3.20 3.80 1.00 3.20 1.20 1.30 1.80 2.00 7.90 6.90 8.50 3.50 5.20 0.70 0.80 0.40 0.70 1.10 2.10 1.90 2.80 1.20 0.90 7.60 3.10 4.50 3.10 Average 1.30 1.60 1.50 7.10 1.80 2.20 2.50 1.40 2.30 2.80 4.50 4.80 1.50 4.10 2.80 1.60 2.10 2.30 9.50 7.50 10.20 4.50 6.50 0.40 0.80 0.90 0.60 0.80 2.50 2.30 1.40 300.00 3.20 3.00 15.60 43.50 29.30 3.50 1.50 1.10 8.20 3.90 6.20 3.70 2.80 2.60 1.80 500.00 3.80 3.50 17.50 47.50 31.20 4.20 1.90 1.40 9.10 4.50 7.10 4.50 Fast 1.50 1.80 1.70 10.00 1.90 2.50 2.90 2.00 3.30 3.50 4.00 5.40 1.80 5.40 3.20 1.80 2.40 2.50 10.30 8.30 12.00 6.00 7.50 0.29 1.00 1.20

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.8333 0.6667 0.7143 0.1887 1.1111 1.0000 0.8333 1.0000 0.5263 0.4348 0.3125 0.2632 1.0000 0.3125 0.8333 0.7692 0.5556 0.5000 0.1266 0.1449 0.1176 0.2857 0.1923 1.4286 1.2500 2.5000 1.4286 0.9091 0.4762 0.5263 0.3571 0.8333 1.1111 0.1316 0.3226 0.2222 0.3226 Average 0.7692 0.6250 0.6667 0.1408 0.5556 0.4545 0.4000 0.7143 0.4348 0.3571 0.2222 0.2083 0.6667 0.2439 0.3571 0.6250 0.4762 0.4348 0.1053 0.1333 0.0980 0.2222 0.1538 2.50 1.2500 1.1111 1.6667 1.2500 0.4000 0.4348 0.7143 0.0033 0.3125 0.3333 0.0641 0.0230 0.0341 0.2857 0.6667 0.9091 0.1220 0.2564 0.1613 0.2703 Fast 0.6667 0.5556 0.5882 0.1000 0.5263 0.4000 0.3448 0.5000 0.3030 0.2857 0.2500 0.1852 0.5556 0.1852 0.3125 0.5556 0.4167 0.4000 0.0971 0.1205 0.0833 0.1667 0.1333 3.50 1.0000 0.8333 0.3571 0.3846 0.5556 0.0020 0.2632 0.2857 0.0571 0.0211 0.0321 0.2381 0.5263 0.7143 0.1099 0.2222 0.1408 0.2222

Decking Simple Universal Beam Steel Bridge, concrete bridge deck, grano cover m days 7.10 0.1408 -

Cutting Switchboxes Cutting in Concrete, small box Cutting in Concrete, large box Cutting in Brickwork, small box Cutting in Brickwork, large box Cutting in Lightweight Blockwork, small box Cutting in Lightweight Blockwork, large box no no no no no no hours hours hours hours hours hours 64 7.10 3.60 6.60 4.20 20.00 10.00 9.50 4.50 9.50 5.30 23.00 12.50 12.50 5.60 12.50 6.30 25.00 14.30 0.1408 0.2778 0.1515 0.2381 0.0500 0.1000 0.1053 0.2222 0.1053 0.1887 0.0435 0.0800 0.0800 0.1786 0.0800 0.1587 0.0400 0.0699

PRODUCTION RATES
ITEM NO. DESCRIPTION
Cutting in Heavyweight Blockwork, small box Cutting in Heavyweight Blockwork, large box

UNIT FOR QUANTITY


no no

UNIT FOR TIME


hours hours

PRODUCTION RATES (Qty per Time) Slow 7.70 3.80 Average 10.00 4.80 Fast 12.50 5.90

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1299 0.2632 Average 0.1000 0.2083 Fast 0.0800 0.1695

Cutting Chases Concrete, cutting by hand, < 25mm wide Concrete, cutting by hand, 25-50mm wide Concrete, cutting by hand, 50-75mm wide Concrete, cutting by hand, 75-100mm wide Concrete, cutting by machine, < 25mm wide Concrete, cutting by machine, 25-50mm wide Concrete, cutting by machine, 50-75mm wide Concrete, cutting by machine, 75-100mm wide Brickwork, cutting by hand, < 25mm wide Brickwork, cutting by hand, 25-50mm wide Brickwork, cutting by hand, 50-75mm wide Brickwork, cutting by hand, 75-100mm wide Brickwork, cutting by machine, < 25mm wide Brickwork, cutting by machine, 25-50mm wide Brickwork, cutting by machine, 50-75mm wide Brickwork, cutting by machine, 75-100mm wide Light Blockwork, cutting by hand, < 25mm wide Light Blockwork, cutting by hand, 25-50mm wide Light Blockwork, cutting by hand, 50-75mm wide Light Blockwork, cutting by hand, 75-100mm wide Light Blockwork, cutting by machine, < 25mm wide Light Blockwork, cutting by machine, 25-50mm wide Light Blockwork, cutting by machine, 50-75mm wide Light Blockwork, cutting by machine, 75-100mm wide Heavy Blockwork, cutting by hand, < 25mm wide Heavy Blockwork, cutting by hand, 25-50mm wide Heavy Blockwork, cutting by hand, 50-75mm wide Heavy Blockwork, cutting by hand, 75-100mm wide Heavy Blockwork, cutting by machine, < 25mm wide Heavy Blockwork, cutting by machine, 25-50mm wide Heavy Blockwork, cutting by machine, 50-75mm wide Heavy Blockwork, cutting by machine, 75-100mm wide m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 1.50 1.20 1.00 0.90 3.10 2.50 2.10 1.80 2.10 1.60 1.40 1.20 4.20 3.30 3.30 2.50 3.80 3.20 2.60 2.30 7.70 5.90 5.20 4.70 1.90 1.60 1.30 1.20 3.80 3.20 2.70 2.30 2.10 1.60 1.40 1.20 4.00 3.30 2.90 2.40 2.70 2.30 1.90 1.60 5.50 4.50 4.50 3.30 5.00 4.20 3.40 3.10 10.00 7.70 7.20 6.30 2.60 2.10 1.80 1.50 5.00 4.20 3.60 3.10 3.10 2.50 2.10 1.80 5.80 5.00 4.20 3.70 4.10 3.50 2.80 2.50 11.10 6.70 6.70 5.00 7.70 6.30 5.30 4.50 14.20 11.10 10.00 9.10 3.80 3.20 2.70 2.30 7.70 6.20 5.20 4.50 0.6667 0.8333 1.0000 1.1111 0.3226 0.4000 0.4762 0.5556 0.4762 0.6250 0.7143 0.8333 0.2381 0.3030 0.3030 0.4000 0.2632 0.3125 0.3846 0.4348 0.1299 0.1695 0.1923 0.2128 0.5263 0.6250 0.7692 0.8333 0.2632 0.3125 0.3704 0.4348 0.4762 0.6250 0.7143 0.8333 0.2500 0.3030 0.3448 0.4167 0.3704 0.4348 0.5263 0.6250 0.1818 0.2222 0.2222 0.3030 0.2000 0.2381 0.2941 0.3226 0.1000 0.1299 0.1389 0.1587 0.3846 0.4762 0.5556 0.6667 0.2000 0.2381 0.2778 0.3226 0.3226 0.4000 0.4762 0.5556 0.1724 0.2000 0.2381 0.2703 0.2439 0.2857 0.3571 0.4000 0.0901 0.1493 0.1493 0.2000 0.1299 0.1587 0.1887 0.2222 0.0704 0.0901 0.1000 0.1099 0.2632 0.3125 0.3704 0.4348 0.1299 0.1613 0.1923 0.2222

Cutting Back Concrete Pile Caps, 50-300mm deep and 0.6m dia Concrete Pile Caps, 300-750mm deep and 0.6m dia Concrete Pile Caps, > 750mm deep and 0.6m dia Concrete Pile Caps, 50-300mm deep and 1.1m dia Concrete Pile Caps, 300-750mm deep and 1.1m dia Concrete Pile Caps, > 750mm deep and 1.1m dia Concrete Pile Caps, 50-300mm deep and 2.5m dia Concrete Pile Caps, 300-750mm deep and 2.5m dia Concrete Pile Caps, > 750mm deep and 2.5m dia Concrete, Cutting Slabs, 5-25m deep Concrete, Cutting Slabs, 25-50m deep Concrete, Cutting Slabs, 50-75m deep Concrete, Cutting Holes, coring machine Concrete, Cutting Back to expose couplers 0.7m slab no no no no no no no no no m m m m3 m hours hours hours hours hours hours hours hours hours hours hours hours hours days 1.6667 0.6667 0.5556 0.5263 0.4000 0.2381 0.1087 0.0990 0.0870 15.20 11.50 6.70 0.20 2.50 3.3333 2.5000 1.2500 1.2500 0.9091 0.4348 0.1220 0.1053 0.0980 0.60 1.50 1.80 1.90 2.50 4.20 9.20 10.10 11.50 0.0658 0.0870 0.1493 5.0000 0.4000 0.30 0.40 0.80 0.80 1.10 2.30 8.20 9.50 10.20 -

65

PRODUCTION RATES
ITEM NO.
Concrete Placement Placing concrete, lorry based pump Hollorib Decking, concrete topping Hollorib Decking, concrete topping, incl PowerFloat Placing Concrete, By Wheelbarrow over 1-10m Placing Concrete, By Wheelbarrow over 10-20m Placing Concrete, By Wheelbarrow over 20-50m Placing Direct From Readymix Lorry, Mass Fill Placing Direct From Readymix Lorry, 50mm Blinding Placing Direct From Readymix Lorry, Ground Beams Placing Direct From Readymix Lorry, Pile Caps Placing Direct From Readymix Lorry, Duct Walls Placing Direct From Readymix Lorry, Stub Columns Placing Direct From Readymix Lorry, Ground Slab Placing Direct From Readymix Lorry,Drains Bed and Cover Placing From Tower Crane, Pile Caps Placing From Tower Crane, Mass Fill Placing From Tower Crane, Slabs under 150mm thick Placing From Tower Crane, Slabs over 150mm thick Placing From Tower Crane, Trough/Coffered Slabs Placing From Tower Crane, Stairs and Landings Placing From Tower Crane, Blinding Placing From Tower Crane, Beams under 150mm thick Placing From Tower Crane, Beams over 150mm thick Placing From Tower Crane, Walls Placing From Tower Crane, Columns m3 m2 m2 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 m3 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 1.20 4.00 0.90 1.20 0.90 0.60 0.80 0.50 0.60 0.60 0.40 2.10 1.50 1.00 30.00 85.00 40.00 2.10 1.50 0.80 2.80 40.00 100.00 50.00 2.30 1.80 1.10 3.10 1.30 1.50 0.80 0.40 2.30 0.90 1.40 4.50 1.30 1.50 1.10 0.70 1.00 0.60 0.80 1.10 0.50 50.00 120.00 70.00 2.50 2.10 1.50 3.30 1.60 1.70 2.30 1.10 0.60 2.60 1.00 1.60 5.50 1.70 1.80 1.20 0.90 1.10 0.80 1.00 1.50 0.60 0.0333 0.0118 0.0250 0.4762 0.6667 1.2500 0.3571 0.6667 1.0000 0.4762 0.8333 0.2500 1.1111 0.8333 1.1111 1.6667 1.2500 2.0000 1.6667 1.6667 2.5000 0.0250 0.0100 0.0200 0.4348 0.5556 0.9091 0.3226 0.7692 0.6667 1.2500 2.5000 0.4348 1.1111 0.7143 0.2222 0.7692 0.6667 0.9091 1.4286 1.0000 1.6667 1.2500 0.9091 2.0000 0.0200 0.0083 0.0143 0.4000 0.4762 0.6667 0.3030 0.6250 0.5882 0.4348 0.9091 1.6667 0.3846 1.0000 0.6250 0.1818 0.5882 0.5556 0.8333 1.1111 0.9091 1.2500 1.0000 0.6667 1.6667

DESCRIPTION

UNIT FOR QUANTITY

UNIT FOR TIME

PRODUCTION RATES (Qty per Time) Slow Average Fast

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Concrete Mixing Concrete Weight, 1m3 Readymix Lorry, Length Readymix Lorry, Width Readymix Lorry, Height Readymix Lorry, Length Readymix Lorry, Turning Circle Readymix Lorry, Allowable Access Ramp Gradient Mixing Concrete, By Hand Mixing Concrete, Single Drum Paddle Mixer Mixing Concrete, Double Drum Paddle Mixer Mixing Concrete, Single Drum Plant Pan Mixer Mixing Concrete, Dry Mix Plant Tonnes m m m Tonnes m degrees m3 m3 m3 m3 m3 hours hours hours hours hours 158.00 315.00 2.40 8.30 2.50 3.70 24.40 16.40 17.00 0.30 180.00 370.00 120.00 90.00 210.00 420.00 20.00 0.0063 0.0032 3.3333 0.0056 0.0027 0.0083 0.0111 0.0048 0.0024 -

Barrette Piles Rule of Thumb, overall rate by Mill Fabricate reinforcement cages Concreting barrette panels Trimming top of barrette panels Concrete Testing, Coring Test Concrete Testing, Sonic Logging Test no cage m3 no no no hours hours hours days days days 2.0000 40.00 0.2500 0.9091 0.2500 50.00 0.4167 0.2857 1.4286 0.8333 55.00 0.5000 4.00 0.0250 0.50 1.10 4.00 0.0200 2.40 3.50 0.70 2.00 0.0182 1.20

Bell Ground Anchors Uncased Anchors, 10m long Top Cased Anchors, 15m long Anchors stressing no no no days days days 66 2.00 1.00 2.20 0.5000 1.0000 0.4545 -

PRODUCTION RATES
ITEM NO. DESCRIPTION UNIT FOR QUANTITY UNIT FOR TIME
PRODUCTION RATES (Qty per Time) Slow Average Fast PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Bored Piling Cycle Time, 5-20m deep Cycle Time, 20-40m deep Cycle Time, 40-70m deep Cycle Time, 70-90m deep Cycle Time, 90-135m deep Move piling setup to next location Excave shaft by grab, general fill/uppr levels Excave shaft by grab, sand/minor rubble Excave shaft by grab, marinve/aluvium Excave shaft by grab/RCD, CDT Excave shaft by grab/RCD, CDG <150 Excave shaft by RCD, CDG 150-200 Excave shaft by RCD, CDG >200/gravel Excave shaft by RCD/Chisel, corestones Excave Rock Socket by RCD, grade IV/V rock Excave Rock Socket by RCD, grade II/III rock Excave Rock Socket by RCD, tendering rate Add/remove RCD plant Add/remove RCD drill string/drill bit Remove Obstruction, above water hand hammers Remove Obstruction, below water heavy chisel Concrete Plug, RCD off/tremmie/concrete/cure/RCD on Install air lift tremmie tube Fabricate reinforcement cages Install reinforcement cages Shaft cleaning, air lifting after excavation Shaft cleaning, air lifting after cage installed Shaft concreting/extract casing 5-70m deep Shaft concreting/extract casing 70-95m deep Shaft concreting/extract casing 95-135m deep Concrete curing prior to remove telescopic casing Concrete Testing, Coring Test Concrete Testing, Sonic Logging Test Concrete Testing, Vibration Test m no no cage no m m m m m m m m m m m m m no no no no no days days days days days hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 3.50 2.10 2.50 0.50 1.50 1.00 0.50 0.50 0.20 0.10 0.10 0.80 0.50 0.4000 0.5000 3.20 0.4000 0.1538 2.20 0.30 0.20 0.1250 0.1000 0.0400 0.0222 0.0167 0.2500 0.1250 0.1000 0.0400 0.0222 0.2500 60.00 8.00 10.00 25.00 45.00 60.00 4.00 8.00 10.00 25.00 45.00 2.00 0.2857 0.4762 0.4000 2.0000 0.6667 1.0000 2.0000 2.0000 5.0000 10.0000 10.0000 2.00 5.00 1.2500 2.0000 53.00 5.00 2.50 2.00 8.0 2.0 12.0 14.0 48.0 72.0 0.3125 2.50 6.50 0.4545 3.3333 5.0000 50.00 4.00

Timber Frames Roof Trusses Wall Plates Roof Rafters Ceiling Joists Roof Carcass, Common Rafters, under 3m Roof Carcass, Common Rafters, 3-6mm Roof Carcass, Common Rafters, over 6m Roof Carcass, Jack Rafters, under 3m Roof Carcass, Jack Rafters, 3-6mm Roof Carcass, Purlins, under 3m Roof Carcass, Purlins, 3-6mm Roof Carcass, Purlins, over 6m Roof Carcass, Binders, under 3m Roof Carcass, Binders, 3-6mm Roof Carcass, Binders, over 6m Roof Carcass, Hangers, under 3m no m m m no no no no no no no no no no no no hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 67 18.20 13.30 14.10 18.80 10.40 5.10 4.30 3.50 5.70 2.10 1.30 8.20 1.30 2.70 1.20 32.10 20.00 16.60 15.60 20.10 16.10 5.40 4.80 4.30 6.60 2.30 1.50 9.00 21.70 18.20 16.10 21.70 16.60 5.80 5.10 4.60 7.60 2.50 1.60 9.60 0.0549 0.0752 0.0709 0.0532 0.0962 0.1961 0.2326 0.2857 0.1754 0.4762 0.7692 0.1220 0.7692 0.3704 0.8333 0.0312 0.0500 0.0602 0.0641 0.0498 0.0621 0.1852 0.2083 0.2326 0.1515 0.4348 0.6667 0.1111 0.0461 0.0549 0.0621 0.0461 0.0602 0.1724 0.1961 0.2174 0.1316 0.4000 0.6250 0.1042

PRODUCTION RATES
ITEM NO. DESCRIPTION
Roof Carcass, Collars under 3m Roof Carcass, Collars 3-m Roof Carcass, Ridge Boards under 3m Roof Carcass, Cut Rafter Feet to line Roof Soffits, Softwood, nailed Roof Soffits, Softwood, screwed Roof Soffits Asbestos, under 300mm nailed Roof Soffits Asbestos, under 300mm screwed Roof Soffits, Asbestos, over 300mm nailed Roof Soffits, Asbestos, over 300mm screwed Roof Facia Panels, Softwood Roof Facia Panels, Asbestos Roof Facia Panel Studding, nailed Roof Facia Panel Studding, screwed Roof Facia Panel Studding, bolted to beams Roof Works, Fix Herringbone Strutting Roof Works, Fix Firing Strips Roof Works, Fix Drip/Tilt Filleting

UNIT FOR QUANTITY


no no no no m m m m m m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 7.60 6.50 12.00 142.00 5.10 1.30 7.30 4.60 5.40 Average 8.00 7.40 13.10 166.00 9.20 3.90 9.10 3.80 3.50 1.30 7.20 2.50 8.10 5.20 5.90 5.10 25.00 20.50 9.30 3.90 9.00 5.80 6.60 Fast 9.10 8.30 15.30 175.00

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1316 0.1538 0.0833 0.0070 0.1961 0.7692 0.1370 0.2174 0.1852 Average 0.1250 0.1351 0.0763 0.0060 0.1087 0.2564 0.1099 0.2632 0.2857 0.7692 0.1389 0.4000 0.1235 0.1923 0.1695 0.1961 0.0400 0.0488 Fast 0.1099 0.1205 0.0654 0.0057 0.1075 0.2564 0.1111 0.1724 0.1515 -

Steel Frames Steel Frame and Roof Members Wall Frame, Bow String Truss and Frame Roof Frame, Curved Truss and Frame Wall Frame, Glazed Frame and Atrium Tons Tons Tons Tons days days days days 3.40 1.60 5.20 0.30 4.60 0.2941 0.6250 0.1923 3.3333 0.2174 -

Slates and Tiling Slate Roofs, Welsh Slate 3-5mm Slate Roofs, Cumbrian Slate 8-11mm Slate Roofs, Asbestos Slates m2 m2 m2 days days days 18.00 8.50 36.00 0.0556 0.1176 0.0278 -

68

PRODUCTION RATES
ITEM NO. DESCRIPTION
Tiled Roofs, Concrete Tiles Tiled Roofs, Clay Pan Tiles

UNIT FOR QUANTITY


m2 m2

UNIT FOR TIME


days days

PRODUCTION RATES (Qty per Time) Slow Average 52.00 26.00 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.0192 0.0385 Fast -

Sheeted Roofs PVC Sheeted Roofs, large areas PVC Sheeted Roofs, small areas Plastic Profiled Sheet Systems m2 m2 m2 days days days 50.00 40.00 54.00 0.0200 0.0250 0.0185 -

Flat and Layered Roofs Asphalt Roof in layers Asbestos Sheets in layers Felt Roofs, large areas Felt Roofs, small or complicated Felt Roofs, Gravel roof chippings m2 m2 m2 m2 Tons days days days days days 45.00 39.00 52.00 35.00 1.40 0.0222 0.0256 0.0192 0.0286 0.7143 -

Wallpapering Strip Existing Wallpaper (3 layers) & Prepare Walls Fix Wallpaper and lining paper Fix Vinyl and Washable paper Fix Ceiling Lining Paper m2 m2 m2 m2 hours hours hours hours 5.00 5.00 4.20 4.00 0.2000 0.2000 0.2381 0.2500 -

Wall Finishes Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, Window Cills, setout and level Clay, quarry Tiles, Window Cills, fix, grout and clean Ceramic Tiles 150x150mm, Ledges/Upstands Ceramic Tiles 150x150mm, Areas under 1.5m2 per room Ceramic Tiles 150x150mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 150x150mm, Areas over 2.5m2 per room Ceramic Tiles 150x150mm, Extra Over for Cutting Ceramic Tiles 108x108mm, Ledges/Upstands Ceramic Tiles 108x108mm, Areas under 1.5m2 per room Ceramic Tiles 108x108mm, Areas of 1.5-2.5m2 per room Ceramic Tiles 108x108mm, Areas over 2.5m2 per room Ceramic Tiles 108x108mm, Extra Over for Cutting Ceramic Tiles, Grouting Works no m m2 no m2 m2 m2 no no m2 m2 m2 no m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours 1.00 1.60 1.70 2.20 20.40 0.90 1.40 1.50 1.10 55.50 1.50 27.10 1.00 1.60 1.70 41.60 62.50 1.30 1.80 1.90 125.00 2.50 1.50 2.10 2.20 2.60 32.00 1.20 1.90 2.10 1.50 0.0490 1.1111 0.7143 0.6667 1.0000 0.6250 0.5882 0.4545 0.9091 0.0180 0.6667 0.0369 1.0000 0.6250 0.5882 0.0240 0.0160 0.7692 0.5556 0.5263 0.0080 0.4000 0.6667 0.0313 0.8333 0.5263 0.4762 0.6667 0.4762 0.4545 0.3846

Stonework Fix 0.5m2 Stones to Metal Support Frame Fix 0.5-0.75m2 Stones to Metal Support Frame Fix 0.75-1.0m2 Stones to Metal Support Frame Fix Complex Stonework to Metal Support Frame Fix Curved Stone Cladding Fix Stone Edge Beams/Window Reveals Fix Stone Soffits Stone Floors Granite Wall Panels, First Fix m2 m2 m2 m2 m2 m2 m2 m2 m2 days days days days days days days days hours 69 6.90 6.90 5.60 7.20 6.90 7.00 9.00 8.70 1.80 8.00 2.30 4.00 10.40 1.30 12.20 9.20 3.20 7.80 10.10 9.70 0.1786 0.1389 0.1449 0.1449 0.1449 0.1429 0.1111 0.1149 0.5556 0.1250 0.4348 0.2500 0.0962 0.7692 0.1282 0.0990 0.1031 0.1087 0.3125 0.0820 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
Granite Wall Panels, Second Fix

UNIT FOR QUANTITY


m2

UNIT FOR TIME


hours

PRODUCTION RATES (Qty per Time) Slow Average 1.10 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.9091 Fast -

Screeding Sand/Cement Floor Screed, 15-20mm thick Sand/Cement Floor Screed, 20-30mm thick Sand/Cement Floor Screed, 30-40mm thick Sand/Cement Floor Screed, 40-50mm thick Sand/Cement Floor Screed, 50-65mm thick Sand/Cement Floor Screed, 65-100mm thick Fix/Setout Screed Battens m2 m2 m2 m2 m2 m2 m hours hours hours hours hours hours hours 3.20 2.00 4.80 4.60 4.20 3.80 3.30 3.00 10.00 5.70 5.50 5.30 5.20 3.90 3.60 0.3125 0.5000 0.2083 0.2174 0.2381 0.2632 0.3030 0.3333 0.1000 0.1754 0.1818 0.1887 0.1923 0.2564 0.2778 -

Restoration Works Faade Cleaning, Water Jetting Faade Cleaning, Acid Etching Faade Cleaning, Grit Blasting Cladding Restoration, Brickwork Cladding Restoration, Stonework courses m2 m2 m2 m2 m days days days days days 25.00 9.00 12.00 6.50 20.00 0.0400 0.1111 0.0833 0.1538 0.0500 -

Rendering Large Wall Areas, applied in 2 coats Small Wall Areas, applied in 2 coats Narrow Widths, applied in 2 coats Columns and Beams, applied in 2 coats Staircase and Soffits, applied in 2 coats m2 m2 m2 m2 m2 hours hours hours hours hours 2.20 1.50 1.20 1.50 1.40 2.70 1.70 1.40 1.70 0.4545 0.6667 0.8333 0.6667 0.7143 0.3704 0.5882 0.7143 0.5882 -

Plastering Browning (undercoat), Internal Walls under 2.5m high Browning (undercoat), Internal Walls over 2.5m high Browning (undercoat), Reveals and Columns less than 100mm wide Browning (undercoat), Reveals and Columns 100-200mm wide Browning (undercoat), Reveals and Columns 200-300mm wide Covings Skimming (topcoat), Internal Walls under 2.5m high Skimming (topcoat), Internal Walls over 2.5m high Skimming (topcoat), Reveals and Columns less than 100mm wide Skimming (topcoat), Reveals and Columns 100-200mm wide Skimming (topcoat), Reveals and Columns 200-300mm wide Plaster Board to Ceilings Plastering Ceilings, 1 Bonding, 1 Skimming Plastering Ceilings, Topcoat Skimming m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours 6.10 5.50 12.60 7.70 4.50 3.20 1.10 2.70 2.20 2.10 9.90 5.20 3.30 2.80 2.60 10.00 5.40 3.60 5.00 6.70 6.10 13.80 8.30 5.00 4.50 1.70 3.20 7.30 6.70 15.40 9.80 5.50 5.50 2.40 5.40 3.10 2.80 10.10 6.40 3.90 0.4545 0.4762 0.1010 0.1923 0.3030 0.1639 0.1818 0.0794 0.1299 0.2222 0.3125 0.9091 0.3704 0.3571 0.3846 0.1000 0.1852 0.2778 0.2000 0.1493 0.1639 0.0725 0.1205 0.2000 0.2222 0.5882 0.3125 0.3226 0.3571 0.0990 0.1563 0.2564 0.1370 0.1493 0.0649 0.1020 0.1818 0.1818 0.4167 0.1852

Plasterboard Boarding to Plaster dabs Boarding to Stud-work/Metal Lathes Boarding 12mm nailed to studding Boarding 19mm nailed to studding Tape, Jointing and Sanding m2 m2 m2 m2 m hours hours hours hours hours 3.60 4.00 4.00 5.00 12.50 16.50 10.00 5.50 6.70 0.2778 0.2500 0.2500 0.2000 0.0800 0.0606 0.10 0.1818 0.1493 -

Partitioning 70

PRODUCTION RATES
ITEM NO.
Timber Studding Metalwork System (MF) Studding Tape, Joint Sand and Top Coat Plasterboard Skimming to Plasterboards 5mm Hardboard Paneling, excluding studding time 100mm Pine Paneling, excluding studding time Quality Hardwood Paneling, excluding studding time Fix 50mm Rocksil Insulation to cavities Fix Timber Studding and Paramount Partitions Fix Timber Studding and Demountable Partitions Fix Timber Studding and Hills Duraboard Partitions Fix Timber Studding and Gyproc Laminated Partitions Stud Partitions, Butt Jointed, nailed Stud Partitions, Butt Jointed, screwed Stud Partitions, T&G Jointed, nailed Stud Partitions, T&G Jointed, screwed Stud Partitions, Fix Sole Plates Stud Partitions, Fix Noggins Stud Partitions, Drill 25-40mm Holes Fix Toilet Partition System, Separation panels Fix Toilet Partition System, Wall Front Panels Fix Toilet Partition System, Separation Front Panels Fix Toilet Partition System, End Front Panels Fix Toilet Partition System, Hang Door to Panel Fix Toilet Partition System, Hand Door plugged to wall Fix Toilet Partition System, Fix Head Rails

DESCRIPTION

UNIT FOR QUANTITY


m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m m m m no no no no no no no no

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 5.90 1.60 1.10 5.50 0.80 0.30 2.60 0.80 3.00 2.20 5.90 3.50 2.90 2.10 Average 6.20 2.00 1.50 6.10 3.20 1.10 0.50 17.80 3.00 1.10 3.50 2.60 7.30 4.60 3.60 2.80 11.10 16.60 28.50 1.25 1.43 1.67 1.67 2.50 1.67 10.00 Fast 6.80 2.50 2.10 6.70 3.60 1.40 0.60 20.20 3.40 1.60 3.90 2.90 9.10 5.80 4.80 3.70

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.1695 0.6250 0.9091 0.1818 1.2500 3.3333 0.3846 1.2500 0.3333 0.4545 0.1695 0.2857 0.3448 0.4762 Average 0.1613 0.5000 0.6667 0.1639 0.3125 0.9091 2.0000 0.0562 0.3333 0.9091 0.2857 0.3846 0.1370 0.2174 0.2778 0.3571 0.0901 0.0602 0.0351 0.80 0.70 0.60 0.60 0.40 0.60 0.10 Fast 0.1471 0.4000 0.4762 0.1493 0.2778 0.7143 1.6667 0.0495 0.2941 0.6250 0.2564 0.3448 0.1099 0.1724 0.2083 0.2703 -

Painting Prepare Walls Prepare Doors Prepare Door Frames Burn Off / Heat Strip Paintwork Internal Timber, 1 coat primer before fixing, generally Internal Timber, 1 coat primer before fixing, timber lengths Internal Timber, knot, 1 primer, stop, 1 undercoat, 1 gloss Internal Timber, touchup primer, 1 undercoat, 1 coat gloss Internal Timber, polyurethane varnish, 2 coats Internal Timber, polyurethane varnish, 3 coats Internal Timber, linseed oil to hardwood, 2 coats External Timber, windows and frames External Timber, knot, 1 primer, 2 undercoats, 1 coat gloss, External Timber, touchup primer, 2 undercoats, 1 coat gloss, External Timber, 2 coats wood preservative External Timber, 3 coats polyurethane varnish Internal Walls, 2 coats emulsion to plaster Internal Walls, 2 coats emulsion to brick/blockwork Internal Walls, 1 mist, 2 coats emulsion to plaster Internal Walls, 1 mist, 2 coats emulsion to brick/blockwork Internal Walls, 1 primer, 1 undercoat, 1 gloss to plaster Internal Walls, undercoat to door frame Internal Walls, gloss to door frame Internal Walls, undercoat to door Internal Walls, gloss to door External Walls, 2 coats sandtex to render/concrete External Walls, 2 coats sandtex to brick/blockwork External Walls, 1 sealer, 2 emulsion to render/concrete External Walls, 1 sealer, 2 emulsion to brick/blockwork Floors, epoxy paint Ceilings, emulsion paint, 2 coats Ceilings, emulsion paint, 3 coats Ceilings, textured paint m2 m2 m m2 m2 m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 71 14.20 12.50 25.00 1.10 6.70 20.00 1.70 3.10 3.30 2.20 3.60 2.40 1.50 2.00 4.00 2.00 8.00 6.00 6.00 4.50 2.30 20.00 16.50 7.10 6.20 2.50 2.00 2.00 1.70 2.90 6.10 5.00 4.20 2.10 3.80 0.0704 0.0800 0.0400 0.9091 0.1493 0.0500 0.5882 0.3226 0.3030 0.4545 0.2778 0.4167 0.6667 0.5000 0.2500 0.5000 0.1250 0.1667 0.1667 0.2222 0.4348 0.0500 0.0606 0.1408 0.1613 0.4000 0.5000 0.5000 0.5882 0.3448 0.1639 0.2000 0.2381 0.4762 0.2632 -

PRODUCTION RATES
ITEM NO.
Ceilings, artex finish Internal Steelwork, 1 primer, 1 undercoat, 1 gloss External Steelwork, 1 primer, 2 undercoats, 1 gloss Guttering Steelwork, 1 coat primer, 2 undercoats, 1 gloss

DESCRIPTION

UNIT FOR QUANTITY


m2 m2 m2 m

UNIT FOR TIME


hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 1.30 0.90 Average 4.10 2.40 1.70 2.50 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.7692 1.1111 Average 0.2439 0.4167 0.5882 0.4000 Fast -

Landscaping Top Soil, spread, level and prepare for turf or seeding Top Soil, rake in fertilizer for seeding Planting, Shrubs and Hedges, under 750mm high Planting, Shrubs and Hedges, over 750mm high Planting, Saplings, under 3.0m high Turfing, including for minor preparations m2 m2 no no no m2 hours hours hours hours hours hours 2.50 25.00 4.00 1.50 1.70 16.80 0.4000 0.0400 0.2500 0.6667 0.5882 0.0595 -

Kerbs & Paving Concrete Slabs, laid on bedding, to slight falls Concrete Slabs, laid on bedding, to steep falls Concrete Slabs, laid in mortar, to slight falls Concrete Slabs, laid in mortar, to steep falls Concrete Slabs, laid on sand, to slight falls Concrete Slabs, laid on sand, to steep falls Cobble Stones, laid in mortar, no patterns Cobble Stones, laid in mortar, with patterns Artificial Stone, laid on sand, with patterns Brick Paviors, in mortar, straight joints Brick Paviors, in mortar, herringbone pattern Gravel Paths, including preparation of sub-base Concrete Paths, 100mm thick, including preparation of sub-base Concrete Kerbs or Channels, laid straight Concrete Kerbs or Channels, laid to 5m radius Concrete Kerbs or Channels, laid to 10m radius Concrete Kerbs or Channels, laid to 20m radius Stone/Granite Kerbs or Channels, laid straight Concrete Edging, laid straight Concrete Edging, laid to 5m radius Concrete Edging, laid to 10m radius Concrete Edging, laid to 20m radius Cutting and Fitting Ends, Concrete Kerbs Cutting and Fitting Ends, Channels Cutting and Fitting Ends, Concrete Edging m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m m m m m m m m m no no no hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 0.90 2.70 2.30 1.50 1.10 1.70 1.60 0.30 0.20 2.50 1.30 1.00 10.50 2.50 6.20 4.50 5.00 5.50 3.50 7.70 5.80 6.20 7.10 6.60 5.80 8.30 1.90 1.20 4.20 2.70 2.30 1.50 2.80 1.90 0.3704 0.4348 0.6667 0.9091 0.5882 0.6250 1.1111 3.3333 5.0000 0.4000 0.7692 1.0000 0.0952 0.4000 0.1613 0.2222 0.2000 0.1818 0.2857 0.1299 0.1724 0.1613 0.1408 0.1515 0.1724 0.1205 0.2381 0.3704 0.4348 0.6667 0.3571 0.5263 0.5263 0.8333 -

Floor Finishes Granolithic Flooring Terrazzo Flooring, in-situ Terrazzo Flooring, pre-cast Mosaic Tiling, 0.045x0.045m Clay, quarry Tiles, small areas, much cutting Clay, quarry Tiles, large areas, little cutting Raised Floor System Linolium/Thermo-Plastic Flooring Thermo-Plastic Floor Tiles Wood Block Flooring, lay blocks Wood Block Flooring, sand and polish Carpeting, Underlay & Gripper Carpeting, Adhesive Fixing m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours 72 3.10 3.60 4.60 1.50 0.80 2.20 2.60 3.10 3.30 1.50 3.10 5.60 3.50 6.10 4.20 5.00 5.60 2.10 5.10 2.20 1.10 2.80 0.3226 0.2778 0.2174 0.6667 1.2500 0.4545 0.3846 0.3226 0.3030 0.6667 0.3226 0.1786 0.2857 0.1961 0.4545 0.9091 0.3571 0.2000 0.1786 0.4762 0.1639 0.2381

PRODUCTION RATES
ITEM NO. DESCRIPTION
Carpeting, Fully Fitted Hardboard Sheeting Coverings, small areas Hardboard Sheeting Coverings, large areas Floor Sheeting Coverings, Lay Lino

UNIT FOR QUANTITY


m2 m2 m2 m2

UNIT FOR TIME


hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 2.00 3.70 6.60 9.50 Fast 2.80 4.10 7.20 10.50

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.5000 0.2703 0.1515 0.1053 Fast 0.3571 0.2439 0.1389 0.0952

Doors and Windows Mastic Pointing to Frames Fix Metal and Timber Windows After Wall Complete Window Glazing Window Glazing, Single Glazed Units Window Glazing, Double Glazed Units m m2 m2 m2 m2 hours hours hours hours hours 9.50 2.00 1.30 2.00 1.30 0.1053 0.5000 0.7692 0.5000 0.7692 -

Blockwork Thermalite Blockwork, under 100mm thick Thermalite Blockwork, under 100-150mm thick Thermalite Blockwork, over 150mm thick Lightweight Concrete Blockwork, under 100mm thick Lightweight Concrete Blockwork, under 100-150mm thick Lightweight Concrete Blockwork, over 150mm thick Heavyweight Concrete Blockwork, under 100mm thick Heavyweight Concrete Blockwork, under 100-150mm thick Heavyweight Concrete Blockwork, over 150mm thick Face Finish, Raked Out Face Finish, Bag Rubbed Face Finish, Flush Pointing m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours 1.80 1.40 1.20 1.50 1.40 1.20 1.40 1.20 1.10 2.50 1.90 1.60 2.20 1.90 1.60 2.10 1.60 1.40 71.40 29.40 17.60 3.20 2.50 2.10 2.90 2.10 2.00 2.90 2.10 1.80 0.5556 0.7143 0.8333 0.6667 0.7143 0.8333 0.7143 0.8333 0.9091 0.4000 0.5263 0.6250 0.4545 0.5263 0.6250 0.4762 0.6250 0.7143 0.0140 0.0340 0.0568 0.3125 0.4000 0.4762 0.3448 0.4762 0.5000 0.3448 0.4762 0.5556 -

Curtain Walling Vertical Glazed Lights, 6m x 2.5m Vertical Glazed Walls, large scale Clerestory Frame/Glazing, 3m x 4m Oriel Window Frame/Glazing, 4m x 2m Glazed Curtain Wall, First Fix Glazed Curtain Wall, Second Fix High Quality Glazed Curtain Walling m2 m2 m2 m2 m2 m2 m2 days days days days hours hours days 14.50 70.00 28.00 35.00 1.20 1.10 25.00 0.0690 0.0143 0.0357 0.0286 0.8333 0.9091 0.0400 -

Concrete Finishing Surface Finishing, Steel Float By Hand Surface Finishing, Wood Float By Hand Surface Finishing, Power Float Surface Finishing, Light Brush on Trowel Surface Finishing, Brush on Trowel Margin Surface Finishing, Sprayed By Pump, expose aggregate Surface Finishing, Wire Brush, expose aggregate Making Good Walls, prepare, shutter, pour Making Good Columns, prepare, shutter, pour Making Good Sides of Beams, prepare, shutter, pour Making Good Slab Soffits, prepare, shutter, pour Making Good Bolt Holes, prepare, shutter, pour Making Good Rubdown Precast Concrete, prepare, shutter, pour Making Good Scabble 3 head brush hammer, prepare, shutter, pour m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 no/hr m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours 30.70 14.80 9.20 11.70 13.90 55.80 28.80 65.00 15.00 13.90 17.20 20.80 90.10 48.50 95.00 25.00 5.50 2.80 2.80 4.20 16.80 18.00 59.50 73.80 25.00 29.40 37.00 170.00 85.00 145.00 30.00 8.60 6.90 7.00 5.50 25.80 0.1087 0.0855 0.0719 0.0179 0.0347 0.0154 0.0667 0.0676 0.0326 0.0719 0.0581 0.0481 0.0111 0.0206 0.0105 0.0400 0.1818 0.3571 0.3571 0.2381 0.0595 0.0556 0.0168 0.0400 0.0340 0.0270 0.0059 0.0118 0.0069 0.0333 0.1163 0.1449 0.1429 0.1818 0.0388 0.0136

73

PRODUCTION RATES
ITEM NO. DESCRIPTION UNIT FOR QUANTITY UNIT FOR TIME
PRODUCTION RATES (Qty per Time) Slow Average Fast PRODUCTION RATES (Time per Quantity) REMARKS Slow Average Fast

Commercial Kitchen Overall Installation for 100 persons or 50m2 Overall Installation for 500 persons or 150m2 Overall Installation for 1000 persons or 250m2 Install Ovens, friers and large mixers etc Install Sinks, bain maries and washers etc wks wks wks mandays mandays 3.00 5.00 8.00 1.00 2.00 -

Ceiling Finishes Suspended Ceilings, office situations Suspended Ceilings, First Fix Suspended Ceilings, Second Fix m2 m2 m2 hours hours hours 2.60 0.70 1.20 3.50 0.3846 1.4286 0.8333 0.2857 -

Carpentry Final Fixing Windows, Softwood, 3.0-7.0m2 Windows, Softwood, 7.0-10.0m2 Windows, Hardwood, 1.0-3.0m2 Windows, Hardwood, 3.0-7.0m2 Windows, Hardwood, 7.0-10.0m2 Windows, Aluminum, 1.0-3.0m2 Windows, Aluminum, 3.0-7.0m2 Windows, Aluminum, 7.0-10.0m2 Windows, Steel, 1.0-3.0m2 Windows, Steel, 3.0-7.0m2 Windows, Steel, 7.0-10.0m2 Window Boards, nailed Window Boards, screwed Mouldings, Softwood, Nailed Mouldings, Softwood, Screwed Mouldings, Softwood, Gun Nailed Mouldings, Hardwood, Nailed Mouldings, Hardwood, Screwed Mouldings, Hardwood, Gun Nailed Skirting, Aluminum, Screwed 150-300mm centres Skirting, Aluminum, Screwed 300-450mm centres Skirting, Plastic, Adhesive Fixing Architrave Mouldings Architrave, Fix to Doors Door Stop Mouldings Glazed Bead Mouldings Hanging Doors, Softwood, Single Pair Butts Hanging Doors, Hardwood, Single Pair Butts Cut Mortice to Receive Lock, Softwood Cut Mortice to Receive Lock, Hardwood Cut & Fix Formica Bath Panel Kitchen Cupboards, Floor Units Kitchen Cupboards, Wall Units Kitchen Cupboards, Shelf Units Staircase, pre-made, simple, straight flight Staircase, pre-made, 2 straight flights, 1 landing Staircase, pre-made, 2 straight flights, 2 landings Staircase, Balustrades/Handrails, fix horizontal Staircase, Balustrades/Handrails, fix raking Staircase, Cut and Fix Newel to Walls no no no no no no no no no no no m m m m m m m m m m m m door m m no no no no no no no no no no no no no no hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 74 10.10 15.50 0.7692 0.5263 0.5263 0.2703 0.8333 1.1111 1.1111 9.50 1.6667 0.7692 2.5000 1.4286 0.6250 5.0000 2.0000 0.8333 2.5000 0.8333 0.7143 2.5000 1.1111 3.3333 2.0000 0.8333 3.3333 2.5000 1.2500 3.3333 1.6667 0.8333 3.3333 2.5000 6.30 4.60 8.20 3.30 2.40 8.50 7.60 4.50 8.60 12.20 0.8333 16.90 18.60 1.1111 0.8333 5.0000 1.6667 2.5000 1.2500 1.4286 0.6667 0.3448 0.1587 1.6667 2.0000 25.00 20.40 1.6667 1.1111 1.6667 2.0000 1.4286 0.9091 0.3846 10.0000 3.3333 5.0000 1.20 0.90 0.90 1.90 3.70 18.20 3.3333 1.6667 2.5000 1.4286 3.3333 2.0000 5.0000 2.0000 1.0000 5.0000 3.3333 8.50 5.60 11.10 5.50 3.70 11.30 0.1053 0.0990 0.0645 1.30 1.90 0.60 1.30 0.40 0.70 1.60 0.20 0.50 1.20 0.40 1.20 1.40 0.40 0.90 0.30 0.50 1.20 0.30 0.40 0.80 0.30 0.60 1.20 0.30 0.40 0.1587 0.2174 0.1220 0.3030 0.4167 0.1176 0.1316 0.2222 0.1163 0.0820 1.20 0.0592 0.0538 0.90 1.20 0.20 0.60 0.40 0.80 0.70 0.8 1.50 2.90 6.30 0.60 0.50 0.10 0.30 0.20 0.60 0.50 0.70 1.10 2.60 0.30 0.50 0.20 0.50 1.00 0.20 0.30 0.1176 0.1786 0.0901 0.1818 0.2703 0.0885 0.0549 0.0400 0.0490 0.60 0.90 0.40 0.70 0.30 0.60

PRODUCTION RATES
ITEM NO. DESCRIPTION
Windows, Softwood, 1.0-3.0m2 Raised Flooring, metal system

UNIT FOR QUANTITY


no m2

UNIT FOR TIME


hours hours

PRODUCTION RATES (Qty per Time) Slow 3.3333 Average 5.0000 0.50 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.30 Average 0.20 2.0000 Fast -

Carpentry Carcassing Windows, Timber Frames for Bricklaying Windows, Drill, Screw & Plug extra over Door Frames, Softwood, 1.0-3.0m2 Door Frames, Softwood, 3.0-7.0m2 Door Frames, Softwood, 7.0-10.0m2 Door Frames, Hardwood, 1.0-3.0m2 Door Frames, Hardwood, 3.0-7.0m2 Door Frames, Hardwood, 7.0-10.0m2 Erect Water Tank Platform Fix Studding For Bath Cut Access Hatch Floor Joists, under 3m Floor Joists, 3.0-4.5m Floor Joists, 4.5-6.0m Ceiling Joists, under 3m Ceiling Joists, 3.0-4.5m Ceiling Joists, 4.5-6.0m Ceiling Joists, Notch to Beams Ceiling Joists, Pack Joist Ends Ceiling Joists, Nailing Joists together Ceiling Joists, Bolting Joists Together Floor Boards, Butt Jointed Floor Boards, T&G Boards, under 75mm wide Floor Boards, T&G Boards, 75-100mm wide Floor Boards, T&G Boards, 100-125mm wide Floor Boards, T&G Boards, 125-150mm wide Plywood Sheeting, Butt Jointed, nailed Plywood Sheeting, Butt Jointed, screwed Plywood Sheeting, T&G Jointed, nailed Plywood Sheeting, T&G Jointed, screwed Chipboard Sheeting, Butt Jointed, nailed Chipboard Sheeting, Butt Jointed, screwed Chipboard Sheeting, T&G Jointed, nailed Chipboard Sheeting, T&G Jointed, screwed no no no no no no no no no m no no no no no no no no no m m m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 m2 hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 9.00 6.80 5.50 12.80 10.80 9.60 20.00 20.10 0.9091 3.3333 2.0000 0.8333 1.6667 0.7143 2.0000 10.0000 5.0000 2.5000 1.2500 3.3333 3.3333 1.0000 2.30 10.00 0.30 9.60 7.20 5.80 14.00 12.10 10.80 25.00 23.80 23.00 12.60 1.70 3.40 3.80 4.20 5.50 9.10 4.10 8.30 4.00 10.00 5.10 9.30 5.50 10.20 4.80 9.10 4.60 11.50 5.80 9.10 5.90 11.60 9.70 7.30 14.70 12.60 11.10 28.50 26.30 10.0000 0.1111 0.1471 0.1818 0.0781 0.0926 0.1042 0.0500 0.0498 0.60 1.40 0.50 1.20 1.10 0.30 0.50 0.10 0.20 0.40 0.80 0.30 0.30 1.00 0.4348 0.10 3.3333 0.1042 0.1389 0.1724 0.0714 0.0826 0.0926 0.0400 0.0420 0.0435 0.0794 0.5882 0.2941 0.2632 0.2381 0.1818 0.1099 0.2439 0.1205 0.2500 0.1000 0.1961 0.1075 0.1818 0.0862 0.1031 0.1370 0.0680 0.0794 0.0901 0.0351 0.0380 0.0980 0.2083 0.1099 0.2174 0.0870 0.1724 0.1099 0.1695 0.10

Carpentry & Joinery Formwork to Soffit of Manhole Formwork to Walls of Manhole Formwork to Road Edges, straight Formwork to Road Edges, curves m2 m2 m m hours hours hours hours 11.20 1.80 14.20 7.70 6.20 20.20 0.0893 0.5556 0.0704 0.1299 0.1613 0.0495 -

Power Supply AC Install 2 no Service transformers, 6 men AC Install 2 no Switchgear, 7 men AC Install Associated Trays and ladders, 3 men AC Cable Terminations in Tx and SWG Rooms, 3 men DC Install Insulated Flooring in DC Room, 1 men DC Install 1 set Rectifier Transformer and Rectifier, 7 men DC Install Switchgear, 7 men days days days days days days days 75 11.00 12.00 12.00 12.00 5.00 6.00 5.00 1.00 10.00 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
DC Primary Cable Terminations and Busduct, 18 men DC Secondary Cable Terminations and Connections, 9 men Trackside Cabling 33kV/Pilot Cables, 10 men Trackside Cabling Terminations, 6 men m run

UNIT FOR QUANTITY

UNIT FOR TIME


days days days days

PRODUCTION RATES (Qty per Time) Slow 2,100.00 Average Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow 12.0 12.0 0.0005 Average 9.00 6.00 1.0 Fast -

Electrical System Railway Station 1st Fix Railway Station 2nd Fix Railway Station T&C Cable Installation, 1 cable laid in trench and protect Cable Installation, 2 cable laid in trench and protect Cable Installation, 5 cable laid in trench and protect Cable Installation, 7 cable laid in trench and protect Cable Installation, 8 cable laid in trench and protect Cable Installation, 2 cable laid in trench and protect, 100mm dia Cable Installation, 2 cable laid in trench and protect, 135mm dia Cable Installation, 3 cable laid in trench and protect, 100mm dia Cable Installation, 6 cable laid in trench and protect, 100mm dia Cable Installation, 4 cable laid in trench and protect, 150mm dia Cable Installation, 36 cable laid in trench and protect, 100mm dia Cable Installation, 10 cable laid in trench and protect, 100mm dia Cable Installation, 1 cable laid in trench and protect, 300mm dia m m m m m m m m m m m m m wks wks wks hours hours hours hours hours hours hours hours hours hours hours hours hours 0.70 6.20 5.60 4.30 3.70 3.50 1.80 1.60 1.00 0.70 1.20 0.20 0.50 1.30 1.50 1.20 3.10 1.4286 38.0 16.0 8.0 0.1613 0.1786 0.2326 0.2703 0.2857 0.5556 0.6250 1.0000 1.4286 0.8333 5.0000 2.0000 0.7692 0.6667 0.8333 0.3226 -

Rainwater Works UPVC Downpipes, 75mm UPVC Guttering, 75mm UPVC RWP Fittings, 75mm Cast Iron Downpipes, 75mm Cast Iron Guttering, 75mm Cast Iron RWP Fittings, 75mm Aluminium Downpipes, 72mm Aluminium Guttering, 72mm Aluminium RWP Fittings, 72mm m m no m m no m m no hours hours hours hours hours hours hours hours hours 3.30 3.10 3.10 2.10 2.50 2.20 2.50 2.90 1.90 0.3030 0.3226 0.3226 0.4762 0.4000 0.4545 0.4000 0.3448 0.5263 -

Manholes and Gulleys Concrete Pre-Cast Manhole Units, 610 x 455 x 51 mm Concrete Pre-Cast Manhole Units, 990 x 610 x 64 mm Brickwork Manhole, 1.0 brick engineering Brickwork Manhole, 1.5 brick engineering Brickwork Manhole, 2.0 brick engineering Benching to Manhole, under 0.5m2 Benching to Manhole, 0.5-0.75m2 Benching to Manhole, 0.75-1.0m2 Brickwork Manhole, build in pipes, under 150mm dia Brickwork Manhole, build in pipes, 150-225mm dia Brickwork Manhole, build in pipes, over 225mm dia Brickwork Manhole, build in cast iron covers Yard Gulleys, 75-150mm dia pipes, bed and level Yard Gulleys, 150-225mm dia pipes, bed and level Yard Gulleys, 225-300mm dia pipes, bed and level Road Gulleys, 600mm deep, bed and level Road Gulleys, 750mm deep, bed and level Road Gulleys, 900mm deep, bed and level no no m2 m2 m2 no no no no no no no no no no no no no hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 76 3.33 0.8333 0.6250 0.30 0.20 0.20 1.1111 0.8333 0.5556 10.0000 5.0000 3.3333 1.6667 2.20 1.80 1.50 1.20 0.80 0.40 0.83 0.30 1.20 1.60 3.3333 5.0000 5.0000 0.90 1.20 1.80 0.10 0.20 0.30 0.60 0.4545 0.5556 0.6667 0.8333 1.2500 2.5000 1.20 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
Road Gulleys, 1,200mm deep, bed and level Road Gulleys, install gratings PVC Manhole

UNIT FOR QUANTITY


no no no

UNIT FOR TIME


hours hours minutes

PRODUCTION RATES (Qty per Time) Slow Average 0.30 5.00 0.0667 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 3.3333 0.2000 15.00 Fast -

Lift Installation Hydraulic Lift, Install 2 to 3 storeys Hydraulic Lift, Install 4 storeys and above Hydraulic Lift, Testing allow 2 wks plus Standard Lift, Manufacture, test and deliver Non-Standard Lift, Manufacture, test and deliver floor floor floor weeks weeks days weeks weeks 0.3333 0.5000 1.0000 75.00 3.00 2.00 1.00 12.00 65.00 52.00

Escalators Truss type, Overall Installation (excl arch finishes) Truss type, Manufacture, test and deliver Truss type, Phase A assemble truss , position/level Truss type, Stop-Work for surrounding finishes Truss type, Phase B decking and glazing etc Truss type, Phase C performance testing Truss type, Phase D full load testing Truss type, Phase E final test and inspection wks wks wks wks wks wks wks wks 8.00 14.00 12.00 60.00 1.00 6.00 5.00 2.00 2.00 2.00 4.00 11.00 48.00

Drainage PVC Drainage, 1m pipes, 100-150mm dia, 0-5m run PVC Drainage, 1m pipes, 100-150mm dia, 5-30m run PVC Drainage, 1m pipes, 100-150mm dia, over 30m run PVC Drainage, 3m pipes, 100-150mm dia, 0-5m run PVC Drainage, 3m pipes, 100-150mm dia, 5-30m run PVC Drainage, 3m pipes, 100-150mm dia, over 30m run PVC Drainage, 6m pipes, 100-150mm dia, 0-5m run PVC Drainage, 6m pipes, 100-150mm dia, 5-30m run PVC Drainage, 6m pipes, 100-150mm dia, over 30m run PVC Drainage, 3m pipes, 150-200mm dia, 5-30m run PVC Drainage, 3m pipes, 150-200mm dia, over 30m run PVC Drainage, 6m pipes, 150-200mm dia, 5-30m run PVC Drainage, 6m pipes, 150-200mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 75mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 75mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 75mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 100mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 100mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 100mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 150mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 150mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 150mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 225mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 225mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 225mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, 300mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, 300mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, 300mm dia, over 30m run Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 0-5m run Stoneware Drainage, Cement/Sand Joints, over 375mm dia, 5-30m run Stoneware Drainage, Cement/Sand Joints, over 375mm dia, over 30m run m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 77 5.70 8.10 9.50 12.20 15.20 18.20 22.20 27.70 33.30 10.60 12.80 21.20 25.60 4.70 5.50 6.60 4.40 5.00 6.20 3.20 3.80 4.50 2.10 2.60 3.10 1.40 1.70 2.40 1.10 1.30 1.60 0.1754 0.1235 0.1053 0.0820 0.0658 0.0549 0.0450 0.0361 0.0300 0.0943 0.0781 0.0472 0.0391 0.2128 0.1818 0.1515 0.2273 0.2000 0.1613 0.3125 0.2632 0.2222 0.4762 0.3846 0.3226 0.7143 0.5882 0.4167 0.9091 0.7692 0.6250 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
Stoneware Drainage, Flexible Joints, 75mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 75mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 75mm dia, over 30m run Stoneware Drainage, Flexible Joints, 100mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 100mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 100mm dia, over 30m run Stoneware Drainage, Flexible Joints, 150mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 150mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 150mm dia, over 30m run Stoneware Drainage, Flexible Joints, 225mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 225mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 225mm dia, over 30m run Stoneware Drainage, Flexible Joints, 300mm dia, 0-5m run Stoneware Drainage, Flexible Joints, 300mm dia, 5-30m run Stoneware Drainage, Flexible Joints, 300mm dia, over 30m run Stoneware Drainage, Flexible Joints, over 375mm dia, 0-5m run Stoneware Drainage, Flexible Joints, over 375mm dia, 5-30m run Stoneware Drainage, Flexible Joints, over 375mm dia, over 30m run PVC, Stoneware, Pitch Fibre & Concrete Joints Pitch Fibre Pipes, 75mm dia, 0-5m run Pitch Fibre Pipes, 75mm dia, 5-30m run Pitch Fibre Pipes, 75mm dia, over 30m run Pitch Fibre Pipes, 100mm dia, 0-5m run Pitch Fibre Pipes, 100mm dia, 5-30m run Pitch Fibre Pipes, 100mm dia, over 30m run Pitch Fibre Pipes, 150mm dia, 0-5m run Pitch Fibre Pipes, 150mm dia, 5-30m run Pitch Fibre Pipes, 150mm dia, over 30m run Pitch Fibre Pipes, 200mm dia, 0-5m run Pitch Fibre Pipes, 200mm dia, 5-30m run Pitch Fibre Pipes, 200mm dia, over 30m run Pitch Fibre Pipes, 225mm dia, 0-5m run Pitch Fibre Pipes, 225mm dia, 5-30m run Pitch Fibre Pipes, 225mm dia, over 30m run Hepsleve Rubber Joint System, 75mm dia, 0-5m run Hepsleve Rubber Joint System, 75mm dia, 5-30m run Hepsleve Rubber Joint System, 75mm dia, over 30m run Hepsleve Rubber Joint System, 100mm dia, 0-5m run Hepsleve Rubber Joint System, 100mm dia, 5-30m run Hepsleve Rubber Joint System, 100mm dia, over 30m run Hepsleve Rubber Joint System, 150mm dia, 0-5m run Hepsleve Rubber Joint System, 150mm dia, 5-30m run Hepsleve Rubber Joint System, 150mm dia, over 30m run Hepsleve Rubber Joint System, 225mm dia, 0-5m run Hepsleve Rubber Joint System, 225mm dia, 5-30m run Hepsleve Rubber Joint System, 225mm dia, over 30m run Hepsleve Rubber Joint System, 300mm dia, 0-5m run Hepsleve Rubber Joint System, 300mm dia, 5-30m run Hepsleve Rubber Joint System, 300mm dia, over 30m run Hepsleve Rubber Joint System, over 375mm dia, 0-5m run Hepsleve Rubber Joint System, over 375mm dia, 5-30m run Hepsleve Rubber Joint System, over 375mm dia, over 30m run Concrete Pipes, 1.5m pipes, 375mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 375mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 375mm dia, over 30m run Concrete Pipes, 1.5m pipes, 450mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 450mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 450mm dia, over 30m run Concrete Pipes, 1.5m pipes, 525mm dia, 0-5m run

UNIT FOR QUANTITY


m m m m m m m m m m m m m m m m m m no m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours minutes hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours 78

PRODUCTION RATES (Qty per Time) Slow 11.20 8.30 Average 8.30 10.00 12.50 7.70 9.10 10.00 5.20 6.20 7.70 2.70 3.30 4.00 1.70 2.10 2.50 1.40 1.60 2.10 0.4167 9.10 16.60 20.00 9.10 16.60 20.00 6.60 12.50 14.30 6.20 11.10 12.50 5.80 10.00 12.10 12.50 14.30 16.60 10.00 12.50 14.30 7.10 9.10 10.00 6.80 4.50 5.50 2.50 2.90 3.70 1.90 2.30 2.70 2.80 3.40 3.80 2.70 3.20 3.60 2.50 13.80 Fast 30.10

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.0893 0.1205 Average 0.1205 0.1000 0.0800 0.1299 0.1099 0.1000 0.1923 0.1613 0.1299 0.3704 0.3030 0.2500 0.5882 0.4762 0.4000 0.7143 0.6250 0.4762 2.40 0.1099 0.0602 0.0500 0.1099 0.0602 0.0500 0.1515 0.0800 0.0699 0.1613 0.0901 0.0800 0.1724 0.1000 0.0826 0.0800 0.0699 0.0602 0.1000 0.0800 0.0699 0.1408 0.1099 0.1000 0.1471 0.2222 0.1818 0.4000 0.3448 0.2703 0.5263 0.4348 0.3704 0.3571 0.2941 0.2632 0.3704 0.3125 0.2778 0.4000 Fast 0.0332 0.0725 -

PRODUCTION RATES
ITEM NO. DESCRIPTION
Concrete Pipes, 1.5m pipes, 525mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 525mm dia, over 30m run Concrete Pipes, 1.5m pipes, 600mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 600mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 600mm dia, over 30m run Concrete Pipes, 1.5m pipes, 675mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 675mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 675mm dia, over 30m run Concrete Pipes, 1.5m pipes, 750mm dia, 0-5m run Concrete Pipes, 1.5m pipes, 750mm dia, 5-30m run Concrete Pipes, 1.5m pipes, 750mm dia, over 30m run Concrete Pipes, 1.5m pipes, 1,050mm dia Concrete Pipes, 1.5m pipes, 1,500mm dia Concrete Pipes, 1.5m pipes, 1,800mm dia Concrete Pipes, 2.5m pipes, 375mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 375mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 375mm dia, over 30m run Concrete Pipes, 2.5m pipes, 450mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 450mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 450mm dia, over 30m run Concrete Pipes, 2.5m pipes, 525mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 525mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 525mm dia, over 30m run Concrete Pipes, 2.5m pipes, 600mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 600mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 600mm dia, over 30m run Concrete Pipes, 2.5m pipes, 675mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 675mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 675mm dia, over 30m run Concrete Pipes, 2.5m pipes, 750mm dia, 0-5m run Concrete Pipes, 2.5m pipes, 750mm dia, 5-30m run Concrete Pipes, 2.5m pipes, 750mm dia, over 30m run Lay Shingle Around Pipework, under 150mm dia Lay Shingle Around Pipework, over 150mm dia

UNIT FOR QUANTITY


m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m m

UNIT FOR TIME


hours hours hours hours hours hours hours hours hours hours hours days days days hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow 4.00 Average 2.90 3.40 2.40 2.70 3.30 2.20 2.60 2.90 1.10 2.40 2.50 2.90 2.50 2.10 3.60 4.30 5.00 3.40 4.10 4.50 3.30 3.80 4.10 3.00 3.50 4.00 2.80 3.30 3.70 2.60 3.10 3.60 7.00 5.50 9.00 9.00 8.00 Fast 4.20 3.80 2.60

PRODUCTION RATES (Time per Quantity) REMARKS Slow 0.2500 Average 0.3448 0.2941 0.4167 0.3704 0.3030 0.4545 0.3846 0.3448 0.9091 0.4167 0.4000 0.3448 0.4000 0.4762 0.2778 0.2326 0.2000 0.2941 0.2439 0.2222 0.3030 0.2632 0.2439 0.3333 0.2857 0.2500 0.3571 0.3030 0.2703 0.3846 0.3226 0.2778 0.1429 0.1818 Fast 0.2381 0.2632 0.3846 0.1250 0.1111 0.1111

Concrete Road surfacing Concrete Road surfacing, Kerbs or Side Haunches Concrete Road surfacing, 150mm thick Concrete Road surfacing, 200mm thick Concrete Road surfacing, 300mm thick m3 m2 m2 m2 hours hours hours hours 0.40 12.50 7.70 6.70 2.5000 0.0800 0.1299 0.1493 -

Basecourse Production Rates Urban environment: Spread & Compact Production = 30m3/hr Trimming Production = 250m2/hr Rural environment: Spread & Compact Production = 50m3/hr Trimming Production = 350m2/hr m3 m2 hours hours 50.00 350.00 0.0200 0.0029 m3 m2 hours hours 30.00 250.00 0.0333 0.0040 -

Ground Compaction Deep Vibroflot, 3m centres Vibro-Roller, Sand m3 m2 hours hours 79 330.00 28.50 380.00 31.20 465.00 45.20 0.0030 0.0351 0.0026 0.0321 0.0022 0.0221

PRODUCTION RATES
ITEM NO.
Vibro-Roller, Soil Vibro-Roller, Clay Vibro-Roller, Hardcore Vibro-Roller, Ash

DESCRIPTION

UNIT FOR QUANTITY


m2 m2 m2 m2

UNIT FOR TIME


hours hours hours hours

PRODUCTION RATES (Qty per Time) Slow Average 58.80 55.60 38.40 57.80 Fast -

PRODUCTION RATES (Time per Quantity) REMARKS Slow Average 0.0170 0.0180 0.0260 0.0173 Fast -

80

PRODUCTION RATES
ITEM NO. DESCRIPTION PAGE NO.

1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0 28.0 29.0 30.0 31.0 32.0 33.0 34.0 35.0 36.0 37.0 38.0 39.0 40.0 41.0 42.0 43.0 44.0

Excavate and Remove Trench Excavation Spread and Level Small or Deep Excavation Rock Tunnels Bulk Excavation Basement Excavation Working Platforms Underpinning Tower Cranes Soil Mix Walls Slurry Mix Walls Site Clearance Sheet Piling Secant Piling Rule of Thumb Removable Anchors NATM Tunnels Fencing Works Dewatering Demolition Breaking Out Site Investigation Waterproofing Trackwork Structural Steelwork Steel Strutting Reinforcement Ratios Reinforcement Post Tensioning Metal Decking Land Drains Formwork Decking Cutting Switchboxes Cutting Chases Cutting Back Concrete Placement Concrete Mixing Barrette Piles Bell Ground Anchors Bored Piling Timber Frames Steel Frames
81 of 84

1 1 1 2 2 2 3 3 3 3 4 4 4 4 4 4 5 5 5 6 6 6 7 7 7 7 8 8 8 9 9 9 9 10 10 11 11 12 12 12 12 13 13 14

PRODUCTION RATES
ITEM NO.
45.0 46.0 47.0 48.0 49.0 50.0 51.0 52.0 53.0 54.0 55.0 56.0 57.0 58.0 59.0 60.0 61.0 62.0 63.0 64.0 65.0 66.0 67.0 68.0 69.0 70.0 71.0 72.0 73.0 74.0 75.0 76.0 77.0 78.0 79.0

DESCRIPTION

PAGE NO.
14 15 15 15 15 15 16 16 16 16 16 16 17 18 18 18 19 19 19 19 20 20 20 21 21 21 22 22 22 23 23 23 25 25 25

Slates and Tiling Sheeted Roofs Flat and Layered Roofs Wallpapering Wall Finishes Stonework Screeding Restoration Works Rendering Plastering Plasterboard Partitioning Painting Landscaping Kerbs & Paving Floor Finishes Doors and Windows Blockwork Curtain Walling Concrete Finishing Commercial Kitchen Ceiling Finishes Carpentry Final Fixing Carpentry Carcassing Carpentry & Joinery Power Supply Electrical System Rainwater Works Manholes and Gulleys Lift Installation Escalators Drainage Concrete Road surfacing Basecourse Production Rates Ground Compaction

82 of 84

PRODUCTION RATES
Table of Contents ITEM NO. DESCRIPTION PAGE NO.

1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0 17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0 28.0 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 9.0 10.0 11.0 12.0 13.0 14.0 15.0 16.0

Barrette Piles Basecourse Production Rates Basement Excavation Bell Ground Anchors Blockwork Bored Piling Breaking Out Bulk Excavation Carpentry & Joinery Carpentry Carcassing Carpentry Final Fixing Ceiling Finishes Commercial Kitchen Concrete Finishing Concrete Mixing Concrete Placement Concrete Road surfacing Curtain Walling Cutting Back Cutting Chases Cutting Switchboxes Decking Demolition Dewatering Doors and Windows Drainage Electrical System Escalators Excavate and Remove Fencing Works Flat and Layered Roofs Floor Finishes Formwork Ground Compaction Kerbs & Paving Land Drains Landscaping Lift Installation Manholes and Gulleys Metal Decking NATM Tunnels Painting Partitioning Plasterboard
83 of 84

12 25 3 12 19 13 6 2 21 21 20 20 20 19 12 12 25 19 11 11 10 10 6 6 19 23 22 23 1 5 15 18 9 25 18 9 18 23 22 9 5 17 16 16

PRODUCTION RATES
Table of Contents ITEM NO.
17.0 18.0 19.0 20.0 21.0 22.0 23.0 24.0 25.0 26.0 27.0 28.0 29.0 30.0 31.0 32.0 33.0 34.0 35.0 36.0 37.0 38.0 39.0 40.0 41.0 42.0 43.0 44.0 45.0 46.0 47.0 48.0 49.0 50.0 51.0

DESCRIPTION

PAGE NO.
16 9 21 22 8 8 5 16 16 2 4 16 4 4 15 4 7 14 4 2 4 1 14 8 15 7 13 3 7 1 3 15 15 7 3

Plastering Post Tensioning Power Supply Rainwater Works Reinforcement Reinforcement Ratios Removable Anchors Rendering Restoration Works Rock Tunnels Rule of Thumb Screeding Secant Piling Sheet Piling Sheeted Roofs Site Clearance Site Investigation Slates and Tiling Slurry Mix Walls Small or Deep Excavation Soil Mix Walls Spread and Level Steel Frames Steel Strutting Stonework Structural Steelwork Timber Frames Tower Cranes Trackwork Trench Excavation Underpinning Wall Finishes Wallpapering Waterproofing Working Platforms

84 of 84