Project Client Standard: Manufacturer: AS:3000 Check Sheet Location Fed From: Serial number:
DOCUMENT NUMBER
NOTE: Where automated relay test equipment is used, the test results obtained may take priority over or supplement the information recorded on this check sheet. In this case, a reference will be made to an attached result sheet.
VERIFY INSTALLATION
Tests Required (Minimum) Verify board installation method Verify board design and labelling as per schematic notes Verify clearances, terminal shrouding/pole blanks are installed and labelled Verify operation of all handles/locks Verify door seals Ensure all penetrations are filled/blanked N/A N/A N/A Schematics Greenlined/Updated Operation (Pass/Fail)
Accepted By (signature)
Accepted By (signature)
VERIFY EARTHING
Schematics Greenlined/Updated Operation (Pass/Fail)
Accepted By (signature)
Verify M.E.N. is installed with correct rating and clearly stamped Verify earthing to each cubicle section/gland plate/escutcheon plate/door Verify R.C.D. earthing (same numbered terminal as C/B pole) Verify cable screen earthing Verify spare cores are earthed Switchboard Earth bar to grid/stake MEN bar to grid connection MEN bar to switchboard connection
Acceptance 0.5
Acceptance 20
Acceptance 20
DOCUMENT NUMBER
Accepted By (signature)
Accepted By (signature)
Accepted By (signature)
RECORD VOLTAGES
Schematics Greenlined/Updated N/A A-E B-E C-E Operation (Pass/Fail)
Accepted By (signature)
TEST RCDs
Schematics Greenlined/Updated N/A N/A Operation (Pass/Fail)
Accepted By (signature)
Verify operation of RCDs with test trip button Test each RCD and fill out logbook
DOCUMENT NUMBER
Accepted By (signature)
Remarks:
The associated system has been tested and proved to operate successfully as per the design information provided. Please refer to the Defect Report list and Testing Equipment Details. Commissioning Officer: Signed: Date: The test results have been reviewed, are within tolerance and are consistent with the design information provided. Commissioning Engineer(RPEQ): Signed: Date:
Serial Number